61 CHAPTER VI IMPLEMENTATION PLAN Implementation Plan In this chapter, the implementation plan describes how the information system will be deployed, installed and transitioned into an operational system. This developed system or website was implemented once approved. Deliverable Items The group decided to remake some revisions on how the user will take quizzes. The users can be viewed under maintenance by admin To make other resources such as video tutorials to be able the user to cope with each lesson. Milestone Description The following milestones or checkpoints marked the completion of some phase of project implementation. This includes but, unlimited to;

Transcript of CHAPTER-VI.docx

61

CHAPTER VIIMPLEMENTATION PLANImplementation PlanIn this chapter, the implementation plan describes how the information system will be deployed, installed and transitioned into an operational system. This developed system or website was implemented once approved.Deliverable Items The group decided to remake some revisions on how the user will take quizzes. The users can be viewed under maintenance by admin To make other resources such as video tutorials to be able the user to cope with each lesson.

Milestone DescriptionThe following milestones or checkpoints marked the completion of some phase of project implementation. This includes but, unlimited to;

Outline requirements: In this point, the proponents studied existing technology and analyzed in detailed the system requirements.

Develop prototype: From the system or website requirements specified on the above points, the overall project flow as well as the content has been conceptualized.

Evaluate prototype: On the develop prototype, the overall system flow and content/design has been evaluated.

Develop Software: Right after the planning and after evaluation of prototype has passed; it was designed and developed according to the scope and functions stated. Integrating and normalizing of database as well as optimization is being developed. As well as the structure of programs inside the website to improve the websites loading time.

Validate System: Right after the website was developed it was tested first by conducting alpha testing. The bugs and errors surrounding the software, as well as to determine the functionality of the system. Errors and some bugs were corrected during this point. On the second phase of testing (white box testing), the researchers allowed gamers to use ad play with game to come up with some suggestions from the gamers and players. The suggestion and reaction was then carried over and noted, and finally, the software was evaluated with the number of respondents (users and IT experts) using the PhilWeb Awards software quality criteria to determine the level of content, design, usability, functionality of the system.

Delivered Software: Since the software was already evaluated, it was already done through series of intensive testing. The website can now be used and is already set for implementation and deployment.

Milestone Completion Criteria

Milestone/CheckpointsCriteria/Determinants

a.) Outline RequirementsDetailed website/system requirements must be delivered.

b.) Develop PrototypeConceptualized program, structure, design, and contents of the website

c.) Evaluate PrototypeEvaluate the developed prototype

d.) Develop SoftwareDevelop the evaluated prototype

e.) Validate SystemTest and evaluate if the evaluated prototype is a match to the developed software

f.) Delivered SystemImplement the system or website

Table 15.0: Milestone Completion Criteria/DeterminantsIn this table, shows the milestone completion criteria and/or determinants:

Schedule of Milestone Completion

Milestone/checkpointNovember 2014December2014January2014February2014

Outline Requirements345123451234512345

a.) Study existing systems

b.) Identify website/system requirements

Develop Prototype

a.) Conceptualize l project flow and design

Evaluate Prototype

a.) Assessment of overall project flow, content and design

Develop Software

a.) Coding and designing of website and database

b.) Review and debugging

Validate a System

a.) Operation and Testing

b.) System evaluation

c.) Implementation plan

Delivered Software

a.) Deployment

Table 16.0: Gantt ChartIn this figure, shows a Gantt chart that specifies the schedule of each milestone/checkpoints.