    Chapter 9

    FUNDAMENTALS OF SQAPLANNING

  • 8/11/2019 Chapter 9 SQA Planning

    2/44

    Objectives

    Upon completing this chapter, you will be ableto: Define the benefits of SQA for projects specified Modify SQAP checklists for organization-specific projects Incorporate quality assurance with an overall organization Set the standards and procedures for the specific project

    implement the SQAP to develop quality end product Develop an SQA plan that complies with the identified

    goals.

  • 8/11/2019 Chapter 9 SQA Planning

    3/44

    BUILDING BLOCKS OF SOFTWAREQUALITY ASSURANCE

    IEEE Guideline for Software Quality Assurance Planning[IEEE Std 730.1-1995] defines defines following building

    blocks to develop software quality: Purpose Reference Documents Management Documentations Standards, Practices, Conventions, and Metrics

    Review, and Audits Test Problem Reporting and Corrective Actions

  • 8/11/2019 Chapter 9 SQA Planning

    4/44

    BUILDING BLOCKS OF SOFTWAREQUALITY ASSURANCE (cont.)

    Tools, techniques, and Methodologies Code Control Media Control

    Supplier Control Records Collection, Maintenance, and Retention Training Risk Management

  • 8/11/2019 Chapter 9 SQA Planning

    5/44

    PURPOSE

    This section identifies the specific purposeand scope of SQAP by: developing the names of software items

    covered by SQAP and the use of software.

    It shall answer for the questions like how issoftware to be used? How critical is this

    software? Who does it apply to? Which portion of the software life cycle applies toeach of software items? Etc.

  • 8/11/2019 Chapter 9 SQA Planning

    6/44

    REFERENCE DOCUMENTS

    This section will provide the complete listof document referenced to develop SQAP,e.g. Military, industry specific or corporatequality assurance standards and guidelines.

  • 8/11/2019 Chapter 9 SQA Planning

    7/44

    MANAGEMENT

    This section with the major elements of theorganization that influences the quality ofsoftware, list of tasks covered by this planand specification of organizationresponsible for each task.

    Therefore, IEEE has described this conceptto be incorporated in SQA planning-Organization, Tasks and Responsibilities

  • 8/11/2019 Chapter 9 SQA Planning

    8/44

    Organization This section of SQA plan will depict the

    organizational structure by describing eachmajor elements of organization togetherwith the delegated responsibilities.

    Project Manager

    ManagementTeam

    ArchitectureTeam

    DevelopmentTeam

    AssessmentTeam

    Common Organisational Structure

  • 8/11/2019 Chapter 9 SQA Planning

    9/44

    Role and Responsibilities i) Project Manager:

    Project manager is responsible for providingrequirements and directions, reporting bugs and issuesfound by himself and the supervisory committee.Project manager hosts status meeting time to time tocheck the status of project. Project manager is alsoresponsible for grading presentation.

    ii) Management Team: Management team is responsible for planning the

    effort, conducting the plan and adapting the plan tochanges in understanding of the requirements or thedesign.

  • 8/11/2019 Chapter 9 SQA Planning

    10/44

    iii) Architecture Team: Architecture team is responsible for the use case

    modelers, and for achieving the system-wide qualities.

    iv) Development Team: Development team is the most popular team, which is

    responsible for quality of individual components,component development, testing and maintenance.

    v) Assessment Team: Assessment team is responsible for quality of end

    product with respect to the requirement and customerexpectation.

    Role and Responsibilities

  • 8/11/2019 Chapter 9 SQA Planning

    11/44

    Tasks

    This section of the plan should identify the planned major checkpoint to assure the

    quality, the tasks to be performed withspecial emphasis on software qualityassurance activities and the relationship

    between the tasks and the plannedcheckpoints.

  • 8/11/2019 Chapter 9 SQA Planning

    12/44

  • 8/11/2019 Chapter 9 SQA Planning

    13/44

    iii) Architecture Team: It is responsible to resolve the design issues. Architecture team focuses on architecture properties,

    architecture maintenance, multiple component issueresolution, performance tuning and qualityimprovements.

    iv) Development Team: This team decides how a design or implementation

    issues local to a single component is resolved. Itfocuses on critical design, implementation, test andmaintenance.

    Associated Tasks

  • 8/11/2019 Chapter 9 SQA Planning

    14/44

  • 8/11/2019 Chapter 9 SQA Planning

    15/44

    DOCUMENTATIONS

    This is an important section of quality assurance plan as it identifies the the team, documentationsgoverning the development, verification andvalidation, use and maintenance of software.

    The main emphasis of this section is on how thedocuments are to be checked for adequacy byidentifying the appropriate review or audits.

    Minimum documents required to ensure that theimplementation of software satisfy requirements,may be listed as follows:

  • 8/11/2019 Chapter 9 SQA Planning

    16/44

    Software Requirement Specification (SRS)

    ii) Software Design Description (SDD) iii) Software Verification and Validation Plan

    (SVVP) iv) Software Verification and Validation Report

    (SVVR) v) User Documentation (UD) vi) Software Configuration Management Plan

    (SCMP) Other documentation such as Sw Dev Plan,

    Standards and procedures, Sw ProjectManagement Plan and Sw Maintenance Manual

  • 8/11/2019 Chapter 9 SQA Planning

    17/44

    STANDARDS, PRACTICES,CONVENTIONS AND METRICS

    This section will describe the standards, practices, conventions and metrics to beemployed by all associated with the projectincluding management and vendors.

  • 8/11/2019 Chapter 9 SQA Planning

    18/44

    REVIEWS AND AUDITS

    To determine the extent of program of thesoftware developed during the software

    development life cycle and to evaluate thetechnical adequacy of the work and itsconformance to software requirements, it is

    necessary to review and audit the producton a planned basis.

  • 8/11/2019 Chapter 9 SQA Planning

    19/44

    i) Software Requirement Review: This review wil1 guarantee the technical feasibility,

    adequacy, and completeness of the requirements as

    outlined in SRS. It wil1 occur after the initialsubmission of the SRS. Software development team isresponsible to perform such type of review.

    ii) Preliminary Design Review:

    This is also known as top-level design review. Thisreview is to evaluate the technical adequacy of the preliminary design of the software as depicted in thesoftware architectural design description.

    iii) Critical Design Review: The critical design review (CDR) is held to determine

    the acceptability of the detailed software design asdepicted in the detailed software design description insatisfying the request in SRS.

  • 8/11/2019 Chapter 9 SQA Planning

    20/44

  • 8/11/2019 Chapter 9 SQA Planning

    21/44

    vi) Physical Audits:

    This audit is conducted to verify that the software andits documentation are internally consistent and areready for delivery.

    vii) In-Process Audits: In-process audit verifies the consistency of the design

    from the various aspects including code versus designdocumentation, interface specifications, designimplementation versus functional requirements andfunctional requirements versus test descriptions.

    viii) Managerial Review: Managerial reviews assess the execution of all actions

    with items identified in software quality assurance plans

  • 8/11/2019 Chapter 9 SQA Planning

    22/44

    ix) Software Configuration Management PlanReview: The adequacy and completeness of configuration

    management methods defined in software configurationmanagement plan will be evaluated through softwareconfiguration management plan review.

    x) Post-Mortem Review: On the successful completion of project, the

    development team will submit it to supervisingcommittee to be reviewed. Now the committee has todecide the approval of project. The project isconsidered as complete, when supervisory committeeapproves it.

  • 8/11/2019 Chapter 9 SQA Planning

    23/44

    TEST Software test plan will be developed by qualityassurance team to outline the test activities, schedule

    and resources required for testing and how the test will be implemented.

    The entire specific software tests and testing, which arenot addressed in SVVP, will be included in this section.

    The testing process described in SQAP may be used toaddress the preparation and review of documentation

    associated with the testing process, including test plans,test design and test case specification, etc.

  • 8/11/2019 Chapter 9 SQA Planning

    24/44

    PROBLEM REPORTING AND

    CORRECTIVE ACTION This section deals with the responsibility of

    SQA team to provide the continuous feedbackconcerning the problem status to managementand technical team, and describe the practicesand procedures to be followed for reporting,

    tracking, and resolving problems identified.

  • 8/11/2019 Chapter 9 SQA Planning

    25/44

    The tasks performed during the problem reportingand corrective action may be listed as follows: .Identification of all development discrepancies and

    submission to development team Validation check for the items submitted to team. Data base maintenance for all discrepancies found in

    report. Documentation of system and process related problems

    identified by SQA on report. Problem resolution by the end of working session.

    Conducting meeting to handle any dispute among teamand relevant parties with manager as a mediator. Documentation and maintenance database for any

    problem resolved by the team members.

  • 8/11/2019 Chapter 9 SQA Planning

    26/44

    TOOLS, TECHNIQUES AND

    METHODS This section will describe the specific

    software tolls, techniques and methodologies

    to be used to support software qualityassurance activity.

  • 8/11/2019 Chapter 9 SQA Planning

    27/44

    Tools Numerous tools have been proposed in literature for

    this purpose. Few of them may be listed as follows: Operating System Utilities - Simulators

    Performance Monitor - Test Drivers Structure Analyzer - Code Analyzer Execution Analyzer - Test case Generator

    Statistical Analysis Package - Rational Rose Enterprise

    Static or Dynamic Test Tools

  • 8/11/2019 Chapter 9 SQA Planning

    28/44

    Techniques One of the technical and managerial procedures

    used to evaluate and improve requirements isSQA technique, such as listed below:

    Review of the use of standards Software Inspection Requirements Tracing Requirements and Design Verification Reliability Measurement and Assessments

  • 8/11/2019 Chapter 9 SQA Planning

    29/44

    CODE CONTROL

    It is a way to protect or ensure the validityof completed code. Methods and facilities

    used to maintain, store, secure anddocument controlled version of theidentified software during all phases of

    software life cycle, will be discussed in thissection.

  • 8/11/2019 Chapter 9 SQA Planning

    30/44

    MEDIA CONTROL

    In this section, methods and facilities will be usedto identify the media for each product anddocumentation required to store the media and to

    protect these media from unauthorized access ordamage during the development life cycle.

    This activity will assure the software storage andretrieval process, accessibility of software to thosewith the need of access, and controls environmentso that the physical media on which the softwareis stored do not degrade.

  • 8/11/2019 Chapter 9 SQA Planning

    31/44

    SUPPLIER CONTROL

    This section will assure that the developedsoftware meets the established requirements

    by assuring that the developer receives theadequate and complete requirements.

  • 8/11/2019 Chapter 9 SQA Planning

    32/44

    RECORDS COLLECTION,MAINTENANCE AND

    RETENTION

    All the projects artifacts will be stored inconfiguration management system.

    A copy of each deliverable will be given to the project manager upon completion of the project.

    This section deals with retaining, assembling,safeguarding, and maintaining the documentation.

  • 8/11/2019 Chapter 9 SQA Planning

    33/44

    TRAINING

    This section deals with team trainingsession carried out whenever necessary to

    familiarize the team members to new toolsor techniques. The technical manager may prepare this

    training. Clients may also be trained after delivering

    the software upon the client's request.

  • 8/11/2019 Chapter 9 SQA Planning

    34/44

    RISK MANAGEMENT

    This section will deal with ensuring that any potentialrisks are identified and discussed fully in team meeting.

    Risk Notification Procedure will record the risk thatarises throughout the duration of the project.

    Risk management is responsible for identifying thelevel of risk associated with the possible failure of eachrequired task or the unavailability of each resource andwill quantify the magnitude of each identified risk.

  • 8/11/2019 Chapter 9 SQA Planning

    35/44

  • 8/11/2019 Chapter 9 SQA Planning

    36/44

    Meta-checklist Examples

    Purpose Intended use of the software covered by SQAP has been defined:

    Scope of SQAP has been identified: Basic Objective of writing SQAP has been specified:

    Software items covered by SQAP has been abbreviated:

    Software life cycle development model used has been described:

    The reasons for choosing supporting documents that form basisof SQAP has been presented:

  • 8/11/2019 Chapter 9 SQA Planning

    37/44

    Reference Documents All the documents that form the basis of SQAP has been

    listed: These documents has been originated outside the project: The use of most current official version of document has

    been ensured : All the standards, procedures and guidelines has been listed: Deviations from identified standards, procedures and

    guidelines as been listed: Software deliverables requiring additional or rigorous

    practices, procedures or guidelines has been identified:

  • 8/11/2019 Chapter 9 SQA Planning

    38/44

    Management

    i) Organization An appropriate organizational structure has been presented: Each major elements of organization together with the

    delegated responsibilities has described: The relationship among SQA organizational elements and

    software development elements has been delineated andexplained:

    A process to resolve all the conflicts has been followed:

  • 8/11/2019 Chapter 9 SQA Planning

    39/44

    ii) Tasks Major checkpoints to assure the quality has been identified: Tasks to be performed with special emphasis on software

    quality assurance activities has been listed: The relationship between the tasks and planned checkpoints

    has been established and shown: A workflow diagram has been designed for SQA activities:

  • 8/11/2019 Chapter 9 SQA Planning

    40/44

    iii) Responsibilities All the specific organizational elements responsible

    for each tasks has been listed: Responsibilities of individuals have been identified

    if two organizational elements are sharing theresponsibilities for task.

  • 8/11/2019 Chapter 9 SQA Planning

    41/44

    Documentation All the documents governing the development, verification and

    validation, use and maintenance of software has been identified: An appropriate way to check for adequacy of documents has been

    emphasized: Minimum documents required to ensure the implementation has

    been identified: All required test documentation has been noted:

  • 8/11/2019 Chapter 9 SQA Planning

    42/44

  • 8/11/2019 Chapter 9 SQA Planning

    43/44

    SUMMARY Software quality assurance is more about the

    customer. Creating a product that has gone through proper

    software testing is crucial to guaranteeingcustomer satisfaction.

    Quality planning involves deciding on a suitabledevelopment process and setting target values forinternal attributes.

    Quantitative targets are set for the internal qualityattributes identified in the quality model.

  • 8/11/2019 Chapter 9 SQA Planning

    44/44

    Below is the meta-checklist prepared toverify and ensure the quality of SQAP.