Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
1
CHAPTER 9: SANITARY SEWER PLAN
BACKGROUND
The Sanitary Sewer Plan evaluates the adequacy of the existing sanitary sewer system,
projects sanitary sewer flows from future development, and recommends future
improvements to accommodate future flows. This plan is used by both the City locally
and the Metropolitan Council regionally for long-term planning of sanitary sewer
infrastructure.
In 1984, the City of Savage prepared a Comprehensive Sanitary Sewer Plan describing
the expansion of the municipal sewer system to serve the ultimate development of the
City. In 2004, the City submitted an updated sewer plan that was found to meet the
Metropolitan Council’s Tier II requirements. Most recently, in 2009, the City submitted
another update to the sewer plan that was also found to meet the Metropolitan
Council’s requirements.
The initial sanitary sewer trunk for the City was constructed in the 1970s and was sized
to accommodate the urbanization of that portion of the City lying generally east of
CSAH 27 (Dakota Avenue). The trunk system has since expanded to serve most of the
City, with the exception of the far southwest corner. Figure 9-1 illustrates the existing
service area, and Figure 9-2 illustrates the locations of City sanitary sewers and lift
stations and Metropolitan Council Environmental Services (MCES) interceptor sewers.
Currently, the City has approximately 134 miles of sanitary sewer lines providing
services to households and businesses. Trunk sewers and lift stations collect the
wastewater and deliver it to the MCES interceptor sewers. The primary MCES
interceptor sewer serving the City of Savage is the Savage Interceptor. The smaller
Southeast Sanitary District flows into Burnsville and into the Southwest Interceptor.
These two MCES Interceptors flow north and eastward, where they connect with the
MSB 7030 Interceptor, which delivers the waste to the MCES Seneca Wastewater
Treatment Plant in Eagan. A small portion of the City, identified as the Southwest
Sanitary District, flows into the Prior Lake Interceptor and ultimately to the MCES Blue
Lake Wastewater Treatment Plant in Shakopee.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
2
EXISTING SANITARY SEWER SYSTEM
Sanitary Sewer Service Area
Except for the far southwestern portion of the city, all of Savage has access to public
sanitary sewer. The trunk sanitary sewer system is planned to be expanded to provide
service to the unserved areas. Because the entire City is located within the
Metropolitan Urban Service Area (MUSA), MCES will provide regional collection and
treatment for all future development within the city.
The City sanitary sewer system has been divided into four (4) main districts and thirty-
eight (38) sub-districts to assist with flow allocations and capacity analysis. The
existing districts and sub-districts are shown in Figure 9-1.
Intercommunity Flows
The City has several intercommunity sanitary sewer flows with neighboring
communities. These service areas are summarized in Table 9-1 below.
Table 9-1. Intercommunity Flows
Neighboring
Community Flow INTO Savage Flow OUT OF Savage
Burnsville 30 homes
(Rose Bluff) N/A
Prior Lake N/A 120 homes, 1 business
(Cates Lake, Country Court)
Gravity Sewers
The system’s gravity sewers include 8-inch through 36-inch diameter pipe. Much of
the system is polyvinyl chloride (PVC) pipe, although other pipe materials include
reinforced concrete (RCP), vitrified clay (VCP), ductile iron (DIP), and centrifugally cast
fiberglass-reinforced polymer mortar (CCFRPM). The trunk gravity sewers are shown
in Figure 9-2.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
3
Figure 9-1: Existing Sanitary Sewer Districts
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
4
Existing Wastewater Flows
The MCES measures wastewater flows within the City of Savage utilizing flow meters.
Meters M405 and M406 measure the majority of the flow generated in the City.
M405 measures the wastewater flow generated in the Southeast district, and M406
measures the wastewater flow generated in both the West and East districts.
Historical flow data from these meters is shown in Tables 9-2 and 9-3.
The total average daily flow generated in Savage from 2013-2017 was approximately
2.16 million gallons per day (MGD). This total is slightly greater than the sum of the
average daily flows below because the wastewater from sub-districts SW-1 and SW-2
flows unmetered into the City of Prior Lake.
Table 9-2. M405 Historical Wastewater Flow
Year Average Daily Flow
(MGD)
Peak Flow
(MGD) Peak Factor
2013 0.246 0.612 2.48
2014 0.252 0.703 2.79
2015 0.248 0.613 2.47
2016 0.248 0.606 2.45
2017 0.246 0.623 2.53
5-Year Average 0.248 0.631 2.54
Table 9-3. M406 Historical Wastewater Flow
Year Average Daily Flow
(MGD)
Peak Flow
(MGD) Peak Factor
2013 1.815 5.599 3.09
2014 1.833 5.776 3.15
2015 1.785 5.723 3.21
2016 1.870 6.042 3.23
2017 1.905 4.701 2.47
5-Year Average 1.841 5.568 3.03
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
5
Existing Lift Stations
The City sanitary sewer system includes fourteen (14) lift stations. The installation
years, pumping capacities, peak hourly flows, and existing residual capacities of each
lift station are provided in Table 9-4. The firm pumping capacity, which should equal
or exceed the peak hourly sanitary flow, is the capacity of the station with its largest
pump out of service. The firm capacity for the lift stations equipped with more than
two pumps was calculated using SewerCAD V8i, a sewer modeling software. The
location of each lift station is indicated in Figure 9-2.
Table 9-4. Existing Lift Station Summary
Lift Station Year
Built
No. of
Pumps
Individual Pump
Design Capacity
(gpm)
Firm Pumping
Capacity
(gpm)
Peak Flow
(gpm)
Residual
Capacity
(%)
139th St 1971 2 110 110 4 96
Natchez 1979 2 50 50 17 67
Utica 1979 3 275 350 203 42
Ottawa 1979 2 50 50 10 80
Hwy 13 1984 2 600 600 374 38
Deer Run 1985 2 100 100 9 91
River Bend 1988 3 1,000 1,700 438 74
Steiner 1992 2 720 720 281 61
Bunge 1992 2 150 150 115 23
Cty Rd 42 1993 2 1,000 1,000 264 74
154th St 1996 2 380 380 179 53
Downtown 2000 3 560 850 451 47
Oak Hills 2003 2 400 400 32 92
Big Sky 2017 3 1,040 2,300* 53 98
* Dual forcemains
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
6
Existing Trunk Sewers
A trunk main is a sewer pipe having a diameter greater than eight (8) inches. It is
important to ensure that trunk mains are sized properly since they convey large
quantities of flow. Trunk mains throughout the City of Savage were identified, and
their capacities were analyzed with SewerCAD. The size, capacity, sub-district being
served by each trunk main, existing peak hourly flows, and existing residual capacities
are listed in Table 9-5. Residual capacities obtained from the SewerCAD model are
shown in Figure 9-3.
Table 9-5. Trunk Sewer Summary
Sub-District Diameter
(in)
Capacity
(gpm)
Peak
Flow
(gpm)*
Residual
Capacity
(%)
W-15 15 1,095 132 88
W-14 33 6,337 259 96
W-13 33 4,434 332 93
W-12 33 4,118 677 84
W-11 15 1,321 220 83
W-10 36 6,746 1,196 82
W-9 18 2,687 210 92
W-8 18 5,536 224 96
W-6 15 9,024 128 99
W-4 12 619 174 72
W-5 36 5,184 2,177 58
E-17 10 609 161 74
E-16 15 2,673 213 92
E-9 12 639 346 46
E-7 18 2,033 493 76
E-5 12 856 576 33
E-8 15 1,381 304 78
E-6 12 1,113 458 59
E-4 10 580 64 89
E-1 36 6,693 3,875 42
*Peak hourly flow in trunk mains includes all wastewater flows
collected in upstream sub-districts.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
7
Figure 9-2: Existing Sanitary Sewer System
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
8
Figure 9-3: Existing Residual Capacity
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
9
Individual Sewage Treatment Systems
Many homes in Savage are served by individual sewage treatment systems (ISTS), also
known as septic systems. As of October 2018, there were a total of 106 active ISTS
within the City. Two (2) of these systems have been identified as non-conforming and
are planned for repair or abandonment. Scott County administers the regulation and
oversight of these systems.
Connection to City utilities is governed by City Code Title 5, Chapter 53, excerpted
below. Generally, if a dwelling is located within 200 feet of a new sanitary sewer or
water main, the property owner must connect after receiving notification from the City
Clerk. If an ISTS was installed or replaced prior to the availability of public sewer
service then it may be allowed to continue in operation if the property owner obtains
a waiver from the City in accordance with Section 53.02.
§ 53.01 SEWER SERVICE CONNECTIONS.
(A) Connection required, notice. When property abuts or has access to any public street
or alley and a dwelling on the property is within 200 feet of the proposed construction
along which sewer mains have been constructed, the owner of any dwelling or
commercial establishment on the property shall connect with the sanitary sewer in
accordance with the provisions of this chapter within 90 days after the date of mailing
or delivering official notice to do so. The notice shall be given to the owner or occupant
in writing by the City Clerk on order of the Council.
Community Treatment Systems
There are no public or private community treatment system within the City of Savage.
All properties within the City are served by the public collection system or by ISTS.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
10
Figure 9-4: Individual Sewage Treatment Systems
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
11
SEWAGE GENERATION RATES
The City of Savage’s zoning policy encourages development in “planned
developments.” These developments result in housing densities on the order of 2.5 to
11 units per acre. Table 9-6 displays the sanitary sewer generation rates used in this
Sanitary Sewer Plan. These generation rates are based on the existing land use
densities of the City of Savage.
Table 9-6. Assumed Sanitary Sewer Flows by Land Use Type
Land Use Average Flow
(gallons/acre/day)
Single Family Residential (SFR) 650
Med-Density Residential (MDR) 950
High-Density Residential (HDR) 1,250
Mixed Use 1,500
Commercial 800
Industrial & Office 800
Business Park 800
Institutional 800
Park 50
Historical flow meter data was used in conjunction with the assumed sewer generation
rates listed in Table 9-6 to allocate existing wastewater flows to each district and sub-
district. These flows were entered into the SewerCAD model to evaluate existing trunk
sewer capacity. The residual capacities obtained from modeling are displayed in
Figure 9-3. The assumed sewer generation rates shown in Table 9-6 were also
applied to future land use designations to project future wastewater flows.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
12
FLOW VARIATION FACTORS
To ensure that the sanitary sewer system is capable of handling flow fluctuations
throughout the day and during rainfall events, peak flow factors are applied based on
average flows. Pipes that serve smaller areas are more likely to experience larger
fluctuations in flow. Therefore, the peak factor decreases as average flow increases.
The MCES flow variation factors for sewer design are listed in Table 9-7 below. These
factors were used to calculate future peak hourly flows. Existing peak hourly flows
were calculated using the peak factors obtained from MCES meter data.
Table 9-7. MCES Flow Variation Factors for Sewer Design
Average Flow
(MGD)
Peak Hourly
Flow Factor
Average Flow
(MGD)
Peak Hourly
Flow Factor
0.00 to 0.11 4.0 1.90 to 2.29 2.8
0.12 to 0.18 3.9 2.30 to 2.89 2.7
0.19 to 0.23 3.8 2.90 to 3.49 2.6
0.24 to 0.29 3.7 3.50 to 4.19 2.5
0.30 to 0.39 3.6 4.20 to 5.09 2.4
0.40 to 0.49 3.5 5.10 to 6.39 2.3
0.50 to 0.64 3.4 6.40 to 7.99 2.2
0.65 to 0.79 3.3 8.00 to 10.39 2.1
0.80 to 0.99 3.2 10.40 to 13.49 2.0
1.00 to 1.19 3.1 13.50 to 17.99 1.9
1.20 to 1.49 3.0 18.00 to 29.99 1.8
1.50 to 1.89 2.9 Over 30.00 1.7
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
13
PROJECTED POPULATION AND SANITARY SEWER FLOW
Projected Population
The Metropolitan Council projects populations and sanitary sewer flows for each
community in the Metropolitan Area. The Metropolitan Council’s population
projections for the City of Savage are listed in Table 9-8 below.
Table 9-8. Population Projections
Year Total Sewered
Population Households Employment Population Households Employment
2010 26,911 9,116 6,753 24,577 8,305 6,135
2020 33,400 11,600 8,100 31,070 10,790 7,480
2030 37,400 13,000 8,800 35,070 12,190 8,180
2040 41,100 14,300 9,400 38,770 13,490 8,780
The sewered population projections have been allocated to the MCES Meter Service
Areas within the City of Savage as listed in Table 9-9 below. The vast majority of
growth is expected to occur within Metershed M406.
Table 9-9. Projections by Meter Service Area & Interceptor
Meter M404 (Prior Lake)* M405 (Burnsville) M406 (MCES Lift Station in Savage)
Interceptor 7120 3-BV-39 8560
Year Popn. Hhds. Empl. Popn. Hhds. Empl. Popn. Hhds. Empl.
2010 324 120 5 3,524 1,305 10 20,729 6,880 6,120
2020 338 125 5 3,532 1,308 10 27,200 9,357 7,465
2030 351 130 5 3,542 1,312 10 31,177 10,748 8,165
2040 0 0 0 3,553 1,316 10 35,217 12,174 8,770
*The flows generated in SW-1 and SW-2, which contribute to the flow metered in M404, will be
rerouted to flow towards the Big Sky Lift Station. When this happens, the flows generated within
SW-1 and SW-2 will be metered by MCES Meter M406, instead of MCES Meter M404. This is
expected to occur between 2030 and 2040.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
14
Projected Wastewater Flows
Table 9-10 lists the projected total average wastewater flow for the City of Savage
from the MCES Water Resources Policy Plan (WRPP) and this Sanitary Sewer Plan.
The projections in this report are greater than the MCES projections since they rely on
flow estimates for each parcel of developable land rather than population growth.
Additionally, it is anticipated that flow generated in the Credit River West Sewer
District (CRWSD), located immediately south of Savage, will discharge to the Big Sky
lift station as indicated in the Big Sky Station Feasibility Study completed in 2016.
Thus, this flow was included in the future flow projections for the Western district. The
flow generated by the CRWSD is expected to be 0.7 MGD on average in 2040, based
on the capacity of an 18-inch trunk sewer.
Table 9-10. Total Average Wastewater Projections
Projection Source 2020 Projected
Flow (MGD)
2030 Projected
Flow (MGD)
2040 Projected
Flow (MGD)
MCES WRPP 2.35 2.54 2.71
Sanitary Sewer Plan 2.30 3.01 3.72
Future flow projections were divided by sewer district and are shown in Table 9-11.
Note that although there will be a minor increase in the wastewater generated in the
Southeast and Southwest districts given the projections shown in Table 9-9, this flow
increase is not perceptible in Table 9-11 since the average wastewater flows are
expressed in million gallons per day.
Table 9-11. Average Wastewater Projections by Sewer District
Sewer District 2020 Projected
Flow (MGD)
2030 Projected
Flow (MGD)
2040 Projected
Flow (MGD)
East 0.82 0.91 1.00
Southeast 0.25 0.25 0.25
Southwest 0.07 0.07 0.07
West 1.16 1.78 2.40
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
15
PROPOSED SANITARY SEWER SYSTEM
The sanitary sewer system will require expansion to serve future development. The
proposed future sanitary sewer districts are shown in Figure 9-5 and the proposed
future sanitary sewer system is shown in Figure 9-6. The new trunk sewers were sized
and located based on the areas that the City expects to develop. The exact alignment
of the proposed trunk sewers and lift stations may change during the design phase of
each project. The purpose of these recommendations is to provide the City with an
overall plan for large infrastructure additions and replacements. Future wastewater
flows generated throughout the City of Savage were calculated using the assumed
sewer generation listed under Table 9-6 and future land use data provided by the
City. Recommended peak factors displayed in Table 9-7 were used to estimate future
peak hourly flows.
Lift Station Analysis
The SewerCAD model was used to evaluate the residual capacity of each lift station.
The peak flows and residual capacities of City lift stations are listed in Table 9-12
below. The majority of the lift stations are projected to have adequate capacity
through full build out development.
Table 9-12. Future Lift Station Capacity Analysis
Lift Station
Firm Pumping
Capacity
(gpm)
Future Peak
Hourly Flow
(gpm)
Residual
Capacity (%)
139th St 110 6 95
Natchez 50 22 56
Utica 350 280 20
Ottawa 50 13 73
Hwy 13 600 619 -3
Deer Run 100 12 88
River Bend 1,700 647 62
Steiner 720 410 43
Bunge 150 152 -2
Cty Rd 42 1,000 340 66
Downtown 850 632 26
Oak Hills 400 52 87
Big Sky 2,300* 2,141** 7
* Dual forcemains
** The Big Sky Lift Station has capacity for rerouted flows from SW-1 and SW-2, as
well as wastewater collected in the CRWSD. The future peak hourly flow reflects
these additions.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
16
As seen in Table 9-12, the future peak hourly flows at two lift stations (Hwy 13 and
Bunge) may exceed their firm pumping capacities. It is recommended that the City
review runtime records and monitor flows at these lift stations as development
progresses within their service areas.
The Hwy 13 Lift Station has a small wet well (6-foot diameter) relative to its capacity,
which causes the pumps to have short pumping cycles. Due to the short pumping
cycles, the pumps require frequent maintenance and replacement. Given the future
flows forecasted for this lift station’s service area, consideration should be given to
upsizing the lift station’s wet well in the future.
Trunk Sewer Analysis
The SewerCAD model was used to evaluate the estimated future peak hourly sanitary
flow for each trunk sanitary sewer (larger than 8-inch) in the system. These peak flows
and the subsequent residual capacities in each trunk are listed in Table 9-12 below.
All trunk sewers exhibit adequate capacity through full build out development. The
projected residual capacity of the future sanitary sewer system is shown in Figure 9-7.
Table 9-12. Trunk Sewer Capacity Analysis
Trunk Main
Location
Diameter
(in)
Capacity
(gpm)
Future Peak
Hourly Flow
(gpm)
Residual
Capacity (%)
W-15 15 1,095 331 70
W-14 33 6,337 514 92
W-13* 33 4,434 2,524 43
W-12* 33 4,118 2,803 32
W-11 15 1,321 317 76
W-10* 36 6,746 3,284 51
W-9 18 2,687 316 88
W-8 18 5,536 325 94
W-6 15 9,024 211 98
W-4 12 619 279 55
W-5* 36 5,184 4,630 11
E-17 10 609 213 65
E-16 15 2,673 282 89
E-9 12 639 454 29
E-7 18 2,033 610 70
E-5 12 856 712 17
E-8 15 1,381 403 71
E-6 12 1,113 614 45
E-4 10 580 162 72
E-1* 36 6,693 6,266 6
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
17
* These trunks will convey the flow generated in SW-1, SW-2, and the CRWSD in
the future since those sub-districts will likely be rerouted to flow by gravity to the
Big Sky Lift Station. Note that these trunks are not currently conveying the flow
generated in those sub-districts.
It is recommended that the City reviews flows and capacities in three parts of
the trunk sanitary sewer system as development progresses: (1) the 36-inch
trunks immediately upstream of the MCES Lift Station, (2) the 21-inch trunks
immediately downstream of the Big Sky Lift Station, and (3) the 15-inch trunk
located downstream of the CR42 Lift Station.
MCES Interceptor Facility Forecasts
The projected sanitary flows to the MCES Meters and Interceptors that serve the City
of Savage are listed in Table 9-13 below. Note that these flow projections include only
the flow contributed from the City of Savage. Future flows to the Blue Lake WWTP
from the City of Savage may be eliminated if the City decides the reroute the flows
from SW-1 and SW-2 to the Big Sky Lift Station. If this were to occur, those flows
would then be conveyed to the Seneca WWTP in Eagan. Future flows in Table 9-13
reflect this scenario.
Table 9-13. Projected MCES Facility Flows
MCES Meter MCES
Interceptor MCES WWTP
Future Average
Flow
(MGD)
Future Peak
Hourly Flow
(MGD)
M404
(Prior Lake) 7120 Blue Lake WWTP 0 0
M405
(Burnsville) 3-BV-39 Seneca WWTP 0.252 0.932
M406 (MCES Lift
Station in Savage) L66, 8560 Seneca WWTP 3.470 9.022
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
18
Figure 9-5: Future Sanitary Sewer Districts
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
19
Figure 9-6: Future Sanitary Sewer System
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
20
Figure 9-7: Future Residual Capacity
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
21
INFLOW/INFILTRATION (I/I)
I/I Background
Inflow is clear water, typically stormwater, which enters the sewer system through
broken manhole covers, sewer cleanouts, sump pumps, foundation drains, and rain
leaders. Infiltration is water, typically groundwater, which leaks into the sewer system
through cracks in the sewer mains, laterals, joints, and manholes.
I/I consumes available capacity in the wastewater collection system and increases the
flow into treatment facilities. In extreme cases, the added flow can cause bypasses or
overflows of raw wastewater. This extra flow also requires a larger capacity in the
City’s collection and treatment components, which results in increased capital,
operation and maintenance, and replacement costs. As a sewer system ages and
deteriorates, I/I can become an increasing burden on a City’s system. Therefore, it is
imperative that I/I be reduced whenever it is cost effective to do so.
In 1993, the City of Savage commissioned an I/I Study. The study was completed and
adopted by the City Council in 1995. A complete study was forwarded to MCES
shortly after City Council adoption. The I/I Study found two main sources of I/I. One
source is the old sewer pipes in the Downtown District. The other source was
determined to be illegal sump pump connections. The report recommended
addressing the deficient sewer pipes in the Downtown District through an
Infrastructure Replacement Program and the illegal sump pump program through the
adoption of a “tough” sump pump ordinance and an aggressive inspection program.
A complete accounting of the I/I reduction activities completed by the City over the
last twenty years is provided in the I/I Reduction section that follows.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
22
The City of Savage prohibits the discharge of stormwater to the sanitary sewer system
and requires the disconnection of existing I/I sources per the City Code excerpted
below. The majority of sump pump connections have been eliminated through the
adoption of ordinance, extensive public relations campaigns, and comprehensive
inspection programs. The City requires sump pumps to be installed prior to final
occupancy, thereby assuring that the installation will be inspected by City staff.
§ 53.05 PROHIBITION OF CLEAN WATER DISCHARGES INTO THE SANITARY SEWER
SYSTEM.
…
(B) Definition and method. No water from any roof, surface, groundwater sump pump,
footing tile, swimming pool or other natural precipitation water shall be discharged into
the sanitary sewer system. Dwellings and other buildings and structures which require,
because of infiltration of water into basements, crawl spaces and the like, a sump pump
discharge system, shall have a permanently installed discharge line which shall not at
any time discharge water into the sanitary sewer system, except as provided herein. A
permanent installation shall be one which provides for year-round surface discharge
capability to the outside of the dwelling, building or structure, or is connected to the city
storm sewer. Permanently installed discharge lines discharging water to the surface
shall be terminated on private property prior to any curb, gutter, or street. A
permanent installation shall consist of a rigid discharge line without valving or quick
connections for altering the path of discharge, and if connections for altering the path
of discharge, and if connected to the city storm sewer line, include a check valve and an
air gap located in a small diameter structure as shown in the city’s standards plates.
The Utility Services Superintendent or his or her designated agent shall determine the
appropriate method for providing a permanent installation to avoid flooding of
adjacent properties, sidewalks, streets and the like. A permanent sump pump discharge
system may not create a public nuisance under §95.01(B) of the city code.
(C) Disconnection. Beginning April 1, 1996, any person, firm or corporation having a
roof surface, groundwater sump pump, footing tile or swimming pool, or unpolluted
industrial waste now connected and/or discharging into the sanitary sewer system shall
disconnect and/or remove same. Any disconnects or openings in the sanitary sewer
shall be closed or repaired in an effective, approved manner, as approved by the Utility
Services Superintendent or his or her designated agent.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
23
I/I Analysis
The sanitary sewer system currently consists of 129 miles of gravity main, fourteen (14)
lift stations, and 6.1 miles of forcemain. Approximately five percent of the residential
housing in the City was constructed before 1970. All homes in the City were inspected
in the late 1990s to eliminate illicit sump pump connections. I/I reduction activities are
discussed in greater detail in the following section.
The amount of clearwater flow within the City was estimated by calculating the
average annual and peak month I/I rates, equal to the average wastewater flow minus
the base wastewater flow, using data from 2013-2017. The average flow, both annual
and monthly, was calculated from MCES meter data. The peak month flow was
determined for each year from 2013-2017, and then those peak month flows were
averaged to give the value listed in Table 9-14. The base flow was approximated as
the lowest monthly average flow within each year.
Table 9-14. Estimated I/I Rate
Metershed M405 M406
Average Flow (MGD) 0.248 1.841
Peak Month Flow (MGD) 0.278 2.097
Base Flow (MGD) 0.232 1.713
Average Annual I/I Rate (MGD (%)) 0.016 (7%) 0.128 (7%)
Peak Month I/I Rate (MGD (%)) 0.046 (17%) 0.384 (17%)
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
24
I/I Reduction
From 1995-2005, the City of Savage took the following corrective steps to address I/I
in the sewer system:
• In 1996, the City adopted a sump pump ordinance, as excerpted previously.
• In 1996, the City hired a consultant to inspect every home in Savage for sump
pump connections to the sanitary sewer system. The final report was
completed in 1997. The inspections identified several areas where the City
must install storm sewers or drain tiles to provide an outlet for sump pump
discharges prior to homeowner disconnections. Two projects were completed
in 1997/98 in which sump pump discharge lines were connected to the City’s
storm sewer system.
• In 1998, a feasibility report and planning study was completed for the
Downtown area (the Hamilton District). The City Council embarked on a
multi-year, phased project to replace all the infrastructure downtown and
provide development/redevelopment opportunities of the commercial
downtown area that started in 2000. All aging sanitary sewer pipes will be
replaced as part of this program and an extensive storm system installed, with
water quality ponding elements, to capture all surface runoff.
• An extensive public relations campaign was completed regarding sump
pumps, including newspaper articles, direct mailings, two public informational
meetings and an educational video that ran weekly on the City’s local cable
access channel.
• As part of the sump pump program, the City of Savage applied for and
received an MCES grant for I/I reduction and subsequently entered into an
agreement with MCES for follow-up inspections and monitoring of the
program results for five years.
• In October of 2005 the City had a study prepared evaluating I/I near Xenwood
Avenue/TH 13. In conjunction with the TH 13 Frontage Road project the City
abandoned a significant portion of the sewer main that was contributing to I/I
in this area.
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
25
More recently, the City’s I/I reduction efforts have shifted to rehabilitation of the
collection system, both public and private. The I/I reduction projects completed in the
last ten years are listed in Table 9-15 below.
Table 9-15. I/I Projects Completed
Year Approximate Location(s) Description Cost
2009 Alabama Ave, Zarthan Ave Adjust SSMH Casting
Reconstruct SSMH $13,230.00
2010 Inglewood Ave, Lynn Ave,
Glenhurst Ave
Adjust SSMH Casting
Reconstruct SSMH $44,946.50
2011 Alabama Ave, Brunswick Ave,
Huntington Ave, 141st St Adjust SSMH Casting $39,655.00
2012
132nd St, 134th St, 135th St,
Natchez Ave, Ottawa Ave,
Monterrey Ave.
Adjust SSMH Casting
Repair SSMH
Replace Sewers and Services
Televise Sewers
$329,343.69
2013
Quentin Ave, Monterrey Ave,
Joppa Ave, Glenhurst Ave,
Dakota Ave
Adjust SSMH Casting
Repair SSMH
Replace Sewers and Services
Televise Sewers
$335,426.62
2014 Connelly Pkwy Adjust SSMH Casting
Repair SSMH $10,560.00
2015 Quentin Ave, 139th St, 140th St
Adjust SSMH Casting
Repair SSMH
Replace Sewers and Services
$68,051.00
2016 Connelly Pkwy, Boone Ave Adjust SSMH Casting
Repair SSMH $29,325.00
2017 136th St, 145th St, South Park Dr,
Zinran Ave
Adjust SSMH Casting
Repair SSMH
Seal SSMH Joints
$226,655.00
2018 Dufferin Dr, Ottawa Ave, River
Crossing, Vernon Ave
Adjust SSMH Casting
Seal SSMH Joints $164,508.32
Total $1,261,701.13
SSMH = sanitary sewer manhole
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
26
I/I Implementation
The City has invested approximately $126,000 annually in I/I reduction over the last
ten years and plans comparable investment going forward. Over the next ten (10)
years, the City plans to implement the sanitary sewer rehabilitation projects listed in
Table 9-16 below. The rehabilitation and replacement work that has been completed
over the last ten years has resulted in a reduction of I/I, and the City of Savage is
committed to further eliminating sources of I/I in its sanitary sewer system.
Table 9-16. I/I Implementation
Year Approximate Location(s) Description
2019 Glendale Rd, Bridgewater Dr, 150th
St, Hampshire Ave
Televise Sewers
Adjust SSMH Casting
Repair SSMH
Seal SSMH Joints
Replace Sewers and Services
2020 Yosemite Ave, W Hidden Valley Dr,
Dufferin Dr
2021 137th St, 154th St, Aquila Ave
2022 South Park Dr, O’Connell Rd,
Kipling Ave, Joppa Ave
2023 Flag Ave, Eagle Creek Pkwy, Credit
View Dr, River Oak Dr, Allen Dr
2024 125th St, 126th St
2025 Carriage Hill Rd, Foxberry Rd,
Heatherton Ridge Dr
2026 Wyoming Ave, Preserve Tr,
Yosemite Ave, Woodhill Dr
2027 Hwy 101 Frontage Rd, Boone Ave,
126th St, Quentin Ave, 143rd St
2028 Taylor Dr, Quebec Ave, Nevada
Ave, Sumter Ave, Virginia Ave
SSMH = sanitary sewer manhole
Savage 2040 Comprehensive Plan Chapter 9: Sanitary Sewer Plan
27
PROPOSED IMPROVEMENTS
The sanitary sewer system will require trunk extensions to serve the remaining
unserved portions of the City. The estimated costs of these improvements, as well as
planned maintenance and rehabilitation work, are listed in Table 9-17 below. The
estimated costs are in 2018 dollars, include only trunk oversizing (the incremental cost
above 8-inch pipe), and include a construction contingency and indirect costs.
Table 9-17. Proposed Improvements
Year Description Estimated Cost
Annual I/I Reduction Approx. $126,000
TBD W-16 Trunk Main Extension $320,000
TBD W-5 Trunk Main Extension $150,000
TBD W-14 Trunk Main Extension $110,000
TBD Hwy 13 LS Wet Well Expansion $280,000
TBD 154th St Lift Station Abandonment $25,000
OUTCOMES
The analysis provided in this Comprehensive Sanitary Sewer Plan is intended to
provide the City of Savage and the Metropolitan Council assistance in planning for
wastewater collection and treatment. It is anticipated that the design criteria and flow
projections will be referenced for utility planning as development continues. Tables
and figures can be utilized to create budget-level estimates and schematic
representations of infrastructure improvements, while specific sizing and routing will
need to be determined during the design phase of individual projects.