Chapter 9:
Benefit/Cost Analysis and
Public Sector Economics
Session 25
Dr Abdelaziz Berrado
![Page 2: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/2.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
2
Topics to Be Covered in Today’s Lecture
Section 9.1: Public Sector Analysis
Section 9.2: Benefit Cost Analysis
Section 9.3: Alternative Selection
Section 9.4: Multiple AlternativesUsing the
B/CRatio
Approach
![Page 3: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/3.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
3
Section 9. 1: Public Sector Projects
•Public Sector:
•Ownership – by citizens- the public
•Public Sector Projects:
•Provide needed services to the public at “no profit”
![Page 4: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/4.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
4
9.1 Types of Projects
•Hospitals
•Parks and recreation facilities
•Highways, Dams, Bridges
•Courts, schools, prisons
•Public Housing
•Many other types
![Page 5: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/5.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
5
9.1 Characteristics - compared
Revenues – profit
cost estimates
No Profit: costs and
benefits and disbenefits
are estimated
Annual Cash Flow
estimates
Shorter:
2-25 years
Quite Long 30 – 50
years
Life Estimates
Some Large; medium
to small
LargerSize of Investment
Private SectorPublic SectorCharacteristic
![Page 6: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/6.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
6
9. 1 Attributes
• Public Sector Projects do not have “profits”
•Projects can have certain undesirable consequences associated—Should be estimated in monetary terms.
•Thus, can be controversial in nature
•Draw media attention – debated on pros and cons
![Page 7: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/7.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
7
9. 1 Estimating for Public
Projects COSTS
•Basic elements for public projects:
•Costs
•Construction, operations, maintenance less any expected salvage values
•Initial costs fairly well know
•Future O&M are less known and must be estimated
![Page 8: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/8.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
8
9.1 Estimating: Benefits
•BENEFITS to the public (users) must be estimated in terms of periodic dollar values
•Very difficult to do
•Benefits = the advantage's to the public stated in $$
•Owners – generally the public
![Page 9: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/9.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
9
9.1 Estimating DISBENEFITS
•Disbenefits
•Expected undesirable (negative) consequences to the owners (public)
•Assuming the project is undertaken
•May be indirect economic disadvantages to the public
•Very hard to estimate and convert to $ amounts
![Page 10: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/10.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
10
9. 1 General Principle
•For public projects we find:
It is very difficult to estimate and reach agreement on the economic impacts of
benefits and disbenefits for public sector projects
![Page 11: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/11.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
11
9. 1 Funding Sources - compared
Higher: At market costTends to be lowerInterest Rate
Sale of new stock,
bonds, loans, Returns
earnings
Taxes, fees, bonds,
Private funds
Funding
Private SectorPublic SectorCharacteristic
![Page 12: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/12.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
12
9. 1 Funding Public Projects
• Generally low interest charges
•Public entities do not pay taxes
•Project investments basically backed by public agencies
•Cost sharing arrangements often exist
•Less perceived risk with public projects
![Page 13: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/13.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
13
9. 1 Determination of an Interest
Rate
• Determined differently than in the private sector
•Called the social discount rate
• Discount rate often in range of 4% to 8% per year
•For Federal Projects a current working rate (2001) is 10% per year
![Page 14: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/14.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
14
9. 1 Additional Comparisons
Primarily economicPolitical Arena
(debated, pressure
groups)
Environment of the
evaluation
Rate of Return or
Present Value
Multiple criteriaSelection Criteria
Private SectorPublic SectorCharacteristic
![Page 15: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/15.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
15
9.1 Selection Process
•Not as “clean” as in the private sector
•Involves interest and pressure groups
•Often draw media attention
•Involve many different viewpoints
![Page 16: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/16.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
16
9. 1 Evaluation Process
•The viewpoint finally adopted will:
•Determine the estimates of..
•Costs
•Benefits
•Disbenefits
•Thus, the viewpoint must be established before the economic evaluation
![Page 17: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/17.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
17
9.1 See Example 9.1
• This is a common problem
•Define the viewpoints
•A given viewpoint will drive the analysis
•Multiple views = multiple results!
•Read Example 9.1
![Page 18: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/18.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
18
Section 9. 2: B/C Analysis – Single
Project
• Historical Point
•B/C analysis philosophy was instituted and promoted in 1936 in the US.
•Relied upon as a fundamental analysis method for public sector projects
• Introduced to promote a sense of objectivity in an analysis
![Page 19: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/19.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
19
9.2 B/C Formulations
•Assignable life, N - years
•Estimate costs ($)
•Estimate benefits in ($)
•Estimate disbenefits in ($)
•Assign an interest rate – i (%/year)
![Page 20: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/20.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
20
9.2 B/C formulations
•Then convert all amounts to either a
•Present Worth - PW(i%)
•Annual Worth – AW(i%)
•Then calculate a B/C ratio in one of three ways…..
![Page 21: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/21.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
21
9. 2 B/C Ratios: 3 formats
( )/
(cos )
PW benefitsB C
PW ts=
( )
(cos )
AW benefits
AW ts=
•Three acceptable formats are:
( )
(cos )
FW benefits
FW ts=
![Page 22: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/22.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
22
9. 2 Notes regarding signs
•By convention:
•Revenues are assigned (+) signs
•Costs are assigned (+) signs
•Salvage values are subtracted from costs
•Disbenefits are treated in more than one way
![Page 23: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/23.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
23
9. 2 Handling Disbenefits
1. Disbenefit values are subtracted from benefits
2. Disbenefit values are added to costs
3. Either approach will result in a consistent analysis – but be consistent through out an analysis
![Page 24: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/24.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
24
9. 2 Decision Rule
•IF B/C ratio (=>) 1.00
•Accept the alternative
•IF B/C ratio (<) 1.00, reject the alternative
•IF B/C ratio “close” to 1.00 then intangible factors may sway the decision to accept or reject
![Page 25: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/25.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
25
9.2 Conventional B/C Ratio
•The conventional B/C Ratio is:
- disbenefits/
Benefits B DB C
Costs C
−= =
![Page 26: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/26.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
26
9. 2 Modified B/C Ratio
• Modified B/C subtracts the Maintenance and operations costs in the numerator
modified
Benefits - disbenefits-M&O costs/
CostsB C =
![Page 27: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/27.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
27
9. 2 Convention vs. Modified?
•It makes no difference which approach is used
•However, the ratio values will differ (magnitude)
•But, the same absolute (accept/reject) decision will be the same
![Page 28: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/28.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
28
9. 2 Benefit-Cost Difference
•B-C Cost difference is not a ratio
•B-C cost difference is:
•(Benefits – Costs) (as a PW or AW)
•The “B” represents the Net Benefit
•Benefits - Disbenefits
![Page 29: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/29.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
29
9. 2 See Example 9-2
•Applies all three approaches to the same problem situation
•B/C = 0.51 (reject)
•Mod B/C = 0.39 (reject)
•(B-C) = $-1.24 million (< 0…reject)
•Result: Same decision with varying magnitudes of the ratio
![Page 30: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/30.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
30
9.2 Example 9.3
•Given two alternatives
•Bypass construction
•Upgrade construction
•Note: Unequal lives ..use AW
•i is set to 8%
•Read at home
![Page 31: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/31.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
31
9.2 Example 9.3, continued
•Conventional B/C – Bypass = 1.17
•Conventional B/C – Upgrade = 1.13
•Both B/C ratios are > 1
•Both proposal are economically justified at 8%
•Which one would you select?
![Page 32: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/32.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
32
9. 2 Uncertain Discount Rate (??)
•What if the value of “i” is uncertain?
•Apply a spreadsheet analysis and play “what-if)
•What if federal funds are available for the upgrade and a 4% rate is applied to that option?
•Changing discount rates can impact on the ratio for that alternative!
![Page 33: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/33.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
33
Section 9. 3: Alternative Selection using
Incremental Analysis: 2 Alternatives
• This approach is similar to the material in chapter 8
•Requires a proper ordering of the alternatives
•Order alternatives on the basis of Total Costs
![Page 34: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/34.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
34
9. 3 Rank on Total Costs - Rules
1. Determine total equivalent costs for both alternatives;
2. Order by total costs: Smaller first then larger
Calculate the incremental cost for the larger alternative = (∆∆∆∆C) – be the denominator in the B/C ratio
![Page 35: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/35.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
35
9. 3 ∆(B/C) Approach
3. For both alternatives determine:
•Total equivalent benefits and disbenefits.
•Calculate the (∆∆∆∆B) for the larger cost alternative or ∆∆∆∆(B-D) if disbenefits are involved
4. Calculate the ∆∆∆∆{ (B-D)/C } ratio
![Page 36: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/36.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
36
9. 3 ∆(B/C) Approach
5. If ∆∆∆∆(B/C) (=>) 1.00 go with the higher cost alternative
else,
Go with lower cost alternative!
![Page 37: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/37.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
37
9. 3 Important Point
• If one is using a PW to determine equivalency, then you must have an equal life model or lowest common multiple of lives.
•Or, apply the annual worth on a typical cycle for the alternatives and the repeatability assumption applies.
![Page 38: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/38.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
38
Section 9. 4: Incremental B/C for
Multiple Projects
•Select from three or more mutually exclusive alternatives
•Same approach as that in Chapter 8, Section 8.6
•Remember, the Do Nothing alternative always exists and should be evaluated as an alternative.
![Page 39: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/39.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
39
9. 4 Steps for Multiple Incremental
Analysis
1. Using either PW or AW determine the total equivalent cost for all options. If unequal lives, apply AW
2. Create the rankings based upon lowest to highest total cost of the alternatives
3. Determine the total equivalent net benefits for each alternative
![Page 40: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/40.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
40
9. 4 Steps - continued
4. The lowest cost option is the first Defender and the next higher cost alternative is the first challenger
Compute the B/C ratio on the increment
If B/C < 1, eliminate the Challenger else eliminate the Defender.
Current winner becomes new Defender
![Page 41: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/41.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
41
9. 4 Multiple Alternatives….
5. Compare the new defender to the next higher cost challenger and repeat the analysis.
6. Continue through the alternative until there are no more challengers.
7. The last “champion” is the winner
![Page 42: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/42.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
42
9.4 Example 9.5
• 4 Alternatives { 1,2,3, and 4}
•Ranked on total cost as shown
•Analysis Summary:
•(2 -1) B/C = 2.24 …Go with {2}
•(3-2) B/C =0.62…Reject 3, stay with {2}
•(4-2) B/C = 1.83 Go with 4, final winner
![Page 43: Chapter 9: Benefit/Cost Analysis and Public Sector …A.Berrado/EGR2302/EGR2302_Ch09.pdfEGR2302-Engineering Economics Al Akhawayn University 2 Topics to Be Covered in Today’s Lecture](https://reader034.fdocuments.us/reader034/viewer/2022052215/5b5022467f8b9a346e8dd189/html5/thumbnails/43.jpg)
EGR2302-Engineering Economics
Al Akhawayn University
43
Assignments and Announcements
� Assignments for Chapter 9
� Online Quizzes for chapter 9
� Homework for chapter 9: pbs 9.1, 9.2, 9.6, 9.7