Chapter 8 Linear Programming: Sensitivity Analysis and Interpretation of Solution
description
Transcript of Chapter 8 Linear Programming: Sensitivity Analysis and Interpretation of Solution
Chapter 8 Linear Programming: Sensitivity Analysis
and Interpretation of Solution Introduction to Sensitivity Analysis Objective Function Coefficients Right-Hand Sides Limitations of Classical Sensitivity Analysis
In the previous chapter we discussed:• objective function value• values of the decision variables• reduced costs• slack/surplus
In this chapter we will discuss:• changes in the coefficients of the objective
function• changes in the right-hand side value of a
constraint
Introduction to Sensitivity Analysis
Introduction to Sensitivity Analysis Sensitivity analysis (or post-optimality
analysis) is used to determine how the optimal solution is affected by changes, within specified ranges, in:• the objective function coefficients• the right-hand side (RHS) values
Sensitivity analysis is important to a manager who must operate in a dynamic environment with imprecise estimates of the coefficients.
Sensitivity analysis allows a manager to ask certain what-if questions about the problem.
Example 1 LP Formulation
Max 5x1 + 7x2
s.t. x1 < 6
2x1 + 3x2 < 19
x1 + x2 < 8
x1, x2 > 0
Example 1 Graphical Solution
2x1 + 3x2 < 19
x2
x1
x1 + x2 < 8Max 5x1 + 7x2
x1 < 6Optimal Solution: x1 = 5, x2 = 3
87654321
1 2 3 4 5 6 7 8 9 10
Objective Function Coefficients Let us consider how changes in the objective
function coefficients might affect the optimal solution.
The range of optimality for each coefficient provides the range of values over which the current solution will remain optimal.
Managers should focus on those objective coefficients that have a narrow range of optimality and coefficients near the endpoints of the range.
Example 1 Changing Slope of Objective
Function
x1
FeasibleRegion
1 2
3
4
5
x2 Coincides withx1 + x2 < 8
constraint line87654321
1 2 3 4 5 6 7 8 9 10
Coincides with2x1 + 3x2 < 19constraint line
Objective functionline for 5x1 + 7x2
Range of Optimality Graphically, the limits of a range of optimality
are found by changing the slope of the objective function line within the limits of the slopes of the binding constraint lines.
Slope of an objective function line, Max c1x1 + c2x2, is -c1/c2, and the slope of a constraint, a1x1 + a2x2 = b, is -a1/a2.
Example 1 Range of Optimality for c1
The slope of the objective function line is -c1/c2. The slope of the first binding constraint, x1 + x2 = 8, is -1 and the slope of the second binding constraint, x1 + 3x2 = 19, is -2/3.
Find the range of values for c1 (with c2 staying 7) such that the objective function line slope lies between that of the two binding constraints:
-1 < -c1/7 < -2/3 Multiplying through by -7 (and
reversing the inequalities): 14/3 < c1 < 7
Example 1 Range of Optimality for c2
Find the range of values for c2 ( with c1 staying 5) such that the objective function line slope lies between that of the two binding constraints:
-1 < -5/c2 < -2/3
Multiplying by -1: 1 > 5/c2 > 2/3Inverting, 1 < c2/5 < 3/2
Multiplying by 5: 5 < c2 < 15/2
Software packages such as LINGO and Microsoft Excel
provide the following LP information: Information about the objective function:
• its optimal value• coefficient ranges (ranges of optimality)
Information about the decision variables:• their optimal values• their reduced costs
Information about the constraints:• the amount of slack or surplus• the dual prices• right-hand side ranges (ranges of feasibility)
Sensitivity Analysis: Computer Solution
Example 1 Range of Optimality for c1 and
c2 Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 5.000 0.000 5.000 2.000 0.333 X2 3.000 0.000 7.000 0.500 2.000
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.000 0.000 6.000 1E+30 1.000 2 19.000 2.000 19.000 5.000 1.000 3 8.000 1.000 8.000 0.333 1.667
VariableModel
X1 X2
1 2 3
NumberConstraint
Right-Hand Sides Let us consider how a change in the right-hand
side for a constraint might affect the feasible region and perhaps cause a change in the optimal solution.
The improvement in the value of the optimal solution per unit increase in the right-hand side is called the shadow price.
The range of feasibility is the range over which the shadow price is applicable.
As the RHS increases, other constraints will become binding and limit the change in the value of the objective function.
Shadow Price Graphically, a shadow price is determined by
adding +1 to the right hand side value in question and then resolving for the optimal solution in terms of the same two binding constraints.
The shadow price for a nonbinding constraint is 0.
A negative shadow price indicates that the objective function will not improve if the RHS is increased.
Relevant Cost and Sunk Cost A resource cost is a relevant cost if the amount
paid for it is dependent upon the amount of the resource used by the decision variables.
Relevant costs are reflected in the objective function coefficients.
A resource cost is a sunk cost if it must be paid regardless of the amount of the resource actually used by the decision variables.
Sunk resource costs are not reflected in the objective function coefficients.
Cautionary Note on theInterpretation of Shadow Prices
Resource Cost is SunkThe shadow price is the maximum amount you should be willing to pay for one additional unit of the resource.
Resource Cost is RelevantThe shadow price is the maximum premium over the normal cost that you should be willing to pay for one unit of the resource.
Example 1 Shadow Prices Constraint 1: Since x1 < 6 is not a binding
constraint, its shadow price is 0. Constraint 2: Change the RHS value of the
second constraint to 20 and resolve for the optimal point determined by the last two constraints: 2x1 + 3x2 = 20 and x1 + x2 = 8.
The solution is x1 = 4, x2 = 4, z = 48. Hence,
the shadow price = znew - zold = 48 - 46 = 2.
Example 1 Shadow Prices
Constraint 3: Change the RHS value of the third constraint to 9 and resolve for the optimal point determined by the last two constraints: 2x1 + 3x2 = 19 and x1 + x2 = 9.
The solution is: x1 = 8, x2 = 1, z = 47. The shadow price is znew - zold = 47 - 46 =
1.
Example 1 Shadow Prices
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 5.000 0.000 5.000 2.000 0.333 X2 3.000 0.000 7.000 0.500 2.000
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.000 0.000 6.000 1E+30 1.000 2 19.000 2.000 19.000 5.000 1.000 3 8.000 1.000 8.000 0.333 1.667
VariableModel
X1 X2
1 2 3
NumberConstraint
Range of Feasibility The range of feasibility for a change in the
right hand side value is the range of values for this coefficient in which the original dual price remains constant.
Graphically, the range of feasibility is determined by finding the values of a right hand side coefficient such that the same two lines that determined the original optimal solution continue to determine the optimal solution for the problem.
Example 1 Range of Feasibility
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 5.000 0.000 5.000 2.000 0.333 X2 3.000 0.000 7.000 0.500 2.000
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.000 0.000 6.000 1E+30 1.000 2 19.000 2.000 19.000 5.000 1.000 3 8.000 1.000 8.000 0.333 1.667
VariableModel
X1 X2
1 2 3
NumberConstraint
Olympic Bike is introducing two new lightweightbicycle frames, the Deluxe and the Professional, to bemade from special aluminum and steel alloys. Theanticipated unit profits are $10 for the Deluxe and $15 forthe Professional. The number of pounds of each alloyneeded per frame is summarized on the next slide.
Example 2: Olympic Bike Co.
A supplier delivers 100 pounds of thealuminum alloy and 80 pounds of the steelalloy weekly.
Aluminum Alloy Steel Alloy
Deluxe 2 3 Professional 4 2
How many Deluxe and Professional frames should Olympic produce each week?
Example 2: Olympic Bike Co.
Example 2: Olympic Bike Co. Model Formulation
• Verbal Statement of the Objective Function Maximize total weekly profit.• Verbal Statement of the Constraints
Total weekly usage of aluminum alloy < 100 pounds. Total weekly usage of steel alloy < 80 pounds.• Definition of the Decision Variables x1 = number of Deluxe frames produced
weekly. x2 = number of Professional frames produced weekly.
Example 2: Olympic Bike Co. Model Formulation (continued)
Max 10x1 + 15x2 (Total Weekly Profit)
s.t. 2x1 + 4x2 < 100 (Aluminum Available)
3x1 + 2x2 < 80 (Steel Available)
x1, x2 > 0
Example 2: Olympic Bike Co. Partial Spreadsheet Showing
SolutionA B C D
67 Deluxe Professional8 Bikes Made 15 17.5009
10 412.5001112 Constraints Amount Used Amount Avail.13 Aluminum 100 <= 10014 Steel 80 <= 80
Decision Variables
Maximized Total Profit
A B C D67 Deluxe Professional8 Bikes Made 15 17.5009
10 412.5001112 Constraints Amount Used Amount Avail.13 Aluminum 100 <= 10014 Steel 80 <= 80
Decision Variables
Maximized Total Profit
Example 2: Olympic Bike Co. Optimal Solution
According to the output:
x1 (Deluxe frames) = 15 x2 (Professional frames) =
17.5 Objective function value =
$412.50
Example 2: Olympic Bike Co. Range of Optimality
Question:Suppose the profit on deluxe frames is
increased to $20. Is the above solution still optimal? What is the value of the objective function when this unit profit is increased to $20?
Example 2: Olympic Bike Co. Sensitivity Report
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease Deluxe 15.000 0.000 10.000 12.500 2.500 Profes. 17.500 0.000 15.000 5.000 8.333
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease Alum. 100.000 3.125 100.000 60.000 46.667 Steel 80.000 1.250 80.000 70.000 30.000
VariableModel
X1 X2
1 2
NumberConstraint
Example 2: Olympic Bike Co. Range of Optimality
Answer:The output states that the solution
remains optimal as long as the objective function coefficient of x1 is between 7.5 and 22.5. Because 20 is within this range, the optimal solution will not change. The optimal profit will change: 20x1 + 15x2 = 20(15) + 15(17.5) = $562.50.
Example 2: Olympic Bike Co. Range of Optimality
Question:If the unit profit on deluxe frames were
$6 instead of $10, would the optimal solution change?
Example 2: Olympic Bike Co. Range of Optimality
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease Deluxe 15.000 0.000 10.000 12.500 2.500 Profes. 17.500 0.000 15.000 5.000 8.333
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease Alum. 100.000 3.125 100.000 60.000 46.667 Steel 80.000 1.250 80.000 70.000 30.000
VariableModel
X1 X2
1 2
NumberConstraint
Range of OptimalityAnswer:
The output states that the solution remains optimal as long as the objective function coefficient of x1 is between 7.5 and 22.5. Because 6 is outside this range, the optimal solution would change.
Example 2: Olympic Bike Co.
Simultaneous Changes Range of Optimality and 100% Rule
The 100% rule states that simultaneous changes in objective function coefficients will not change the optimal solution as long as the sum of the percentages of the change divided by the corresponding maximum allowable change in the range of optimality for each coefficient does not exceed 100%.
Example 2: Olympic Bike Co. Range of Optimality and 100% Rule
Question:If simultaneously the profit on Deluxe
frames was raised to $16 and the profit on Professional frames was raised to $17, would the current solution be optimal?
Example 2: Olympic Bike Co. Range of Optimality and 100% Rule
Answer:If c1 = 16, the amount c1 changed is 16 -
10 = 6 . The maximum allowable increase is 22.5 - 10 = 12.5, so this is a 6/12.5 = 48% change. If c2 = 17, the amount that c2 changed is 17 - 15 = 2. The maximum allowable increase is 20 - 15 = 5 so this is a 2/5 = 40% change. The sum of the change percentages is 88%. Since this does not exceed 100%, the optimal solution would not change.
Simultaneous Changes Range of Feasibility and 100%
RuleThe 100% rule states that simultaneous changes in right-hand sides will not change the dual prices as long as the sum of the percentages of the changes divided by the corresponding maximum allowable change in the range of feasibility for each right-hand side does not exceed 100%.
Example 2: Olympic Bike Co. Range of Feasibility and Sunk Costs
Question:Given that aluminum is a sunk cost,
what is the maximum amount the company should pay for 50 extra pounds of aluminum?
Example 2: Olympic Bike Co. Range of Feasibility and Sunk
Costs Variable Cells
Final Reduced Objective Allowable AllowableName Value Cost Coefficient Increase Decrease
Deluxe 15.000 0.000 10.000 12.500 2.500 Profes. 17.500 0.000 15.000 5.000 8.333
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease Alum. 100.000 3.125 100.000 60.000 46.667 Steel 80.000 1.250 80.000 70.000 30.000
VariableModel
X1 X2
1 2
NumberConstraint
Example 2: Olympic Bike Co. Range of Feasibility and Sunk Costs
Answer:Because the cost for aluminum is a sunk
cost, the shadow price provides the value of extra aluminum. The shadow price for aluminum is $3.125 per pound and the maximum allowable increase is 60 pounds. Because 50 is in this range, the $3.125 is valid. Thus, the value of 50 additional pounds is = 50($3.125) = $156.25.
Example 2: Olympic Bike Co. Range of Feasibility and Relevant Costs
Question:If aluminum were a relevant cost, what is
the maximum amount the company should pay for 50 extra pounds of aluminum?
Example 2: Olympic Bike Co. Range of Feasibility and Relevant Costs
Answer:If aluminum were a relevant cost, the
shadow price would be the amount above the normal price of aluminum the company would be willing to pay. Thus if initially aluminum cost $4 per pound, then additional units in the range of feasibility would be worth $4 + $3.125 = $7.125 per pound.
Example 3 Consider the following linear
program:Min 6x1 + 9x2 ($
cost)s.t. x1 + 2x2 <
8 10x1 + 7.5x2 >
30 x2 >
2 x1, x2 > 0
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 1.500 0.000 6.000 6.000 6.000 X2 2.000 0.000 9.000 1E+30 4.500
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.500 2.500 8.000 1E+30 2.500 2 30.000 -0.600 30.000 25.000 15.000 3 2.000 -4.500 2.000 2.000 2.000
VariableModel
X1 X2
1 2 3
NumberConstraint
Example 3 Sensitivity Report
Example 3 Optimal Solution
According to the output:
x1 = 1.5 x2 = 2.0Objective function value = 27.00
Example 3 Range of Optimality
Question:Suppose the unit cost of x1 is decreased
to $4. Is the current solution still optimal? What is the value of the objective function when this unit cost is decreased to $4?
Example 3
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 1.500 0.000 6.000 6.000 6.000 X2 2.000 0.000 9.000 1E+30 4.500
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.500 2.500 8.000 1E+30 2.500 2 30.000 -0.600 30.000 25.000 15.000 3 2.000 -4.500 2.000 2.000 2.000
VariableModel
X1 X2
1 2 3
NumberConstraint
Sensitivity Report
Example 3 Range of Optimality
Answer:The output states that the solution
remains optimal as long as the objective function coefficient of x1 is between 0 and 12. Because 4 is within this range, the optimal solution will not change. However, the optimal total cost will change: 6x1 + 9x2 = 4(1.5) + 9(2.0) = $24.00.
Example 3 Range of Optimality
Question:How much can the unit cost of x2 be
decreased without concern for the optimal solution changing?
Example 3
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 1.500 0.000 6.000 6.000 6.000 X2 2.000 0.000 9.000 1E+30 4.500
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.500 2.500 8.000 1E+30 2.500 2 30.000 -0.600 30.000 25.000 15.000 3 2.000 -4.500 2.000 2.000 2.000
VariableModel
X1 X2
1 2 3
NumberConstraint
Sensitivity Report
Example 3 Range of Optimality
Answer:The output states that the solution
remains optimal as long as the objective function coefficient of x2 does not fall below 4.5.
Example 3 Range of Optimality and 100% Rule
Question:If simultaneously the cost of x1 was raised
to $7.5 and the cost of x2 was reduced to $6, would the current solution remain optimal?
Example 3
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 1.500 0.000 6.000 6.000 6.000 X2 2.000 0.000 9.000 1E+30 4.500
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.500 2.500 8.000 1E+30 2.500 2 30.000 -0.600 30.000 25.000 15.000 3 2.000 -4.500 2.000 2.000 2.000
VariableModel
X1 X2
1 2 3
NumberConstraint
Sensitivity Report
Example 3 Range of Optimality and 100% Rule
Answer:If c1 = 7.5, the amount c1 changed is 7.5
- 6 = 1.5. The maximum allowable increase is 12 - 6 = 6, so this is a 1.5/6 = 25% change. If c2 = 6, the amount that c2 changed is 9 - 6 = 3. The maximum allowable decrease is 9 - 4.5 = 4.5, so this is a 3/4.5 = 66.7% change. The sum of the change percentages is 25% + 66.7% = 91.7%. Because this does not exceed 100%, the optimal solution would not change.
Example 3 Range of Feasibility
Question:If the right-hand side of constraint 3 is
increased by 1, what will be the effect on the optimal solution?
Example 3
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease X1 1.500 0.000 6.000 6.000 6.000 X2 2.000 0.000 9.000 1E+30 4.500
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease 1 5.500 2.500 8.000 1E+30 2.500 2 30.000 -0.600 30.000 25.000 15.000 3 2.000 -4.500 2.000 2.000 2.000
VariableModel
X1 X2
1 2 3
NumberConstraint
Sensitivity Report
Example 3 Range of Feasibility
Answer:A shadow price represents the
improvement in the objective function value per unit increase in the right-hand side. A negative shadow price indicates a deterioration (negative improvement) in the objective, which in this problem means an increase in total cost because we're minimizing. Since the right-hand side remains within the range of feasibility, there is no change in the optimal solution. However, the objective function value increases by $4.50.
Changes in Constraint Coefficients Classical sensitivity analysis provides no
information about changes resulting from a change in the coefficient of a variable in a constraint.
We must change the coefficient and rerun the model to learn the impact the change will have on the solution.
Non-intuitive Shadow Prices Constraints with variables naturally on both
the left-hand and right-hand sides often lead to shadow prices that have a non-intuitive explanation.
Example 2: Olympic Bike Co. (Revised)Recall that Olympic Bike is introducing two
newlightweight bicycle frames, the Deluxe and theProfessional, to be made from special aluminum andsteel alloys. The objective is to maximize total profit, subject to limits on the availability of aluminum and steel.
Let us now introduce an additional constraint. Thenumber of Deluxe frames produced (x1) must be greater than or equal to the number of Professional frames produced (x2) .
x1 > x2
Example 2: Olympic Bike Co. (Revised) Model Formulation (continued)
Max 10x1 + 15x2 (Total Weekly Profit)
s.t. 2x1 + 4x2 < 100 (Aluminum Available)
3x1 + 2x2 < 80 (Steel Available) x1 - x2 > 0 (Product Ratio)
x1, x2 > 0
Variable CellsFinal Reduced Objective Allowable Allowable
Name Value Cost Coefficient Increase Decrease Deluxe 16.000 0.000 10.000 12.500 10.000 Profes. 16.000 0.000 15.000 1E+30 8.333
ConstraintsFinal Shadow Constraint Allowable Allowable
Name Value Price R.H. Side Increase Decrease Alum. 96.000 0.000 100.000 1E+30 4.000 Steel 80.000 5.000 80.000 3.333 80.000
VariableModel
X1 X2
1 2
NumberConstraint
Example 2: Olympic Bike Co. (Revised) Sensitivity Report (Revised)
Ratio 0.000 -5.000 0.000 26.667 2.500 3
Example 2: Olympic Bike Co. (Revised) Shadow Price for Constraint #3
The interpretation of the shadow price -5.00 is correctly stated as follows: “If we are forced to produce 1 more Deluxe frame over and above the number of Professional frames produced, total profits will decrease by $5.00.”
Example 2: Olympic Bike Co. (Revised Again)
We might instead be interested in what happens if we change the coefficient on x2.
For instance, what if management required Olympic to produce a number of Deluxe frames that is at least 110% of the number of Professional frames produced?
In other words, the constraint would change to
x1 > 1.1x2
The shadow price does not tell us what will happen in this case. We need to resolve the problem with this new constraint.
End of Chapter 8