Chapter 8 Costing PDF
-
Upload
nurul-aashikhin -
Category
Documents
-
view
371 -
download
0
Transcript of Chapter 8 Costing PDF
CHAPTER 8
PROFITABILITY ANALYSIS
8.1 INTRODUCTION
Chemical plants like glycerine plants are built to make a profit and an estimate of
investment required and the cost of production are needed before the profitability of a
project can be assessed. Cost estimation is a specialized subject and a profession in its
own right, but the design engineer must be able to make rough cost estimates to decide
between project alternatives and optimize the design (R. K. Sinnott, 2009).
The costing of equipment which has been estimated of glycerine production will
be evaluated by profitability analysis to make sure the project is economically attractive.
8.2 PURCHASED COST
8.2.1 Module Costing Technique
The equipment module cost technique is a common technique to estimate cost of a new
chemical plant. This technique relates all costs back to the purchased cost of
equipment evaluated for some base conditions. Deviation from these base conditions
are handled by using multiplying factors that depend on the following:
1. The specific equipment type
2. The specific system pressure
3. The specific materials of construction
The bare module cost as in Equation 8.1 is the sum of the direct and indirect costs as
presented in Appendix C.1 (R. Turton, 2009).
(8.1)
Where:
CBM = bare module equipment cost: direct and indirect costs for each unit
FBM = bare module cost factor: multiplication factor to account for the items in
Table 7.6 plus the specific materials of construction and operating pressure
Cop = purchased cost for base conditions: equipment made of the most common
material usually carbon steel and operating at near ambient pressure
8.2.2 Bare Module Cost for Equipment at Base Conditions
The bare module equipment cost represents the sum of direct and indirect costs as
shown in Appendix C.1. The conditions specified for the base case are (R. Turton,
2009)
1. Unit fabricated from most common material, usually carbon steel (CS)
2. Unit operated at near-ambient pressure
For Equation 8.1 is used to obtain the bare module cost for the base conditions. For
these base conditions, a superscript zero (0) is added to the bare module cost factor
and the bare module equipment cost. So, the CoBM and Fo
BM refer to the base
conditions.
8.2.3 Bare Module Cost for Nonbase Case Condition
For equipment made from others materials of construction and/or operating at non
ambient pressure, the values for FM and FP are greater than 1.0. In the equipment
module technique, these additional costs are incorporated into the bare module cost
factor, FBM. The bare module factor is used for the base case, FoBM in Equation 8.1. The
information needed to determine this actual bare module factor is provided in Appendix
C.1. The effect of pressure on the cost of equipment is considered first.
Pressure factors for process vessel is
For tvessel>0.0063 m (8.2)
If Fp, vessel is less than 1 (corresponding to tvessel>0.0063 m), then Fp, vessel =1. For
pressure less than -0.5 barg, Fp, vessel =1.25. Equation 8.2 is used when the thickness of
the vessel wall is less than ¼ D which is for vessel range D = 0.3 to 4.0 m, occurs at
pressure 320 barg.
Pressure factors for other process equipment is
(8.3)
The pressure, P is obtained from operating pressure in equipment and the values
constant, C1, C2 and C3 for different equipment are refer to the Appendix C.2 (A.2).
8.2.4 Purchased Equipment Cost
Data for the purchased cost equipment, at ambient operating pressure and using
carbon steel construction normally, Cop is
(8.4)
Where A is capacity or size parameter of equipment. The data K1, K2 and K3 along with
the maximum and minimum values used in the Appendix C.2.
8.2.5 Cost Escalation
(8.5)
The data of purchased equipment cost from survey of equipment manufactures during
period 2001 with an average CEPCI of 397. The purchased cost for the equipment is
obtained from period 2011 with an average CEPCI of 585.
8.2.6 Estimation Cost of Purchased Equipment
1. Heat exchanger
Heat transfer area: Area of one tube x number of tubes
The purchase cost of heat exchanger Cop can be found in Appendix C.5 (figure A.5) by
choosing the fixed tube sheet (shell and tube heat exchanger). So, the value of is
210. The purchase cost of heat exchanger is
The pressure factor, Fp for heat exchanger,
For heat exchanger with fixed tube sheet and floating head, the identification number
with material of construction of carbon steel-shell/stainless steel-tube is 4. From
Appendix C.3 , FM=2.8. From Appendix C.5, B1=1.63 and B2=1.66.
)
This is the bare module cost for 2001 (CEPCI = 397). The cost for 2011 can thus be
calculated as follows using the CEPCI of 585.
Cost in 2011 = Cost in year 2011 x Cost index in 2011
Cost index in 2001
2. Falling-film Evaporator
The purchase cost of falling film evaporator, at ambient operating pressure and using
stainless steel construction, Cop is
From Appendix C.7; K1 = 3.9119, K2 = 0.8627, K3 = -0.0088 and area of evaporator, A =
62.02 m2
Pressure factor, Fp, for the remaining process equipment are given by
where P is a unit of pressure are bar gauge = 1 bar
From Appendix C.8; P<10 for falling film evaporators with value of pressure rating is
C1=C2=C3=0
The bare module factors for the falling film evaporator is
where; Cop = purchased cost of equipment
FBM = bare module cost
From Appendix C.5, identification number of falling film evaporator is 26 and from
Appendix C.8, the value FBM is 3.90
This is the bare module cost for 2001 (CEPCI = 397). The cost for 2011 can thus be
calculated as follows using the CEPCI of 585.
Cost in 2011 = Cost in year 2011 x Cost index in 2011
Cost index in 2001
3. Separator
The purchase cost of vessel volume Cop can be found in Appendix C.9 which gives
1900 USD/m3. So, the value of is 1900. The purchase cost of separator is
Pressure factor, Fp, for the process vessel are given by
The bare module factors for the separator is
where; Cop = purchased cost of equipment
FBM = bare module cost
From Appendix C.4, identification number of process vessel is 20 and from Appendix
C.3, the value FBM is 3.20. From Appendix C.6, B1=2.25 and B2=1.82.
This is the bare module cost for 2001 (CEPCI = 397). The cost for 2011 can thus be
calculated as follows using the CEPCI of 585.
Cost in 2011 = Cost in year 2011 x Cost index in 2011
Cost index in 2001
4. Distillation column
Data needed in the estimation of the cost are:
Tray towers:
(8.5)
Thus,
From Table 21.2 in kNovel (pg 720)
Therefore cost of tray tower is estimated below:
Packed Towers:
(8.6)
From pg 720
Therefore cost of packed tower is estimated below:
Thus, the estimation cost of distillation column is defined as below:
5. Splitting Tower
From the Appendix C.2 of Analysis, Synthesis, and Design of Chemical Process book,
the values of K can be obtained as followed:
K1 = 3.4974
K2 = 0.4485
K3 = 0.704
While the value of A referred as a reactor volume. Thus A = 9.55
Therefore,
From the purchased cost calculated, the price of purchasing reactor in 2001 is
. Therefore, the price of purchasing reactor in 2011 can be determined by
using the following formula:
The bare module factors for the splitting tower is
Where,
Bare module cost is depending on the type of material besides the operating
condition of splitting tower itself. Therefore, the calculation of bare module cost should
involve with those factor.
The value of B1 and B2 can be determined through Appendix C.6 in Analysis,
Synthesis, and Design of Chemical Process book. By referring to the same book, the
material factor, FM can be got through Appendix C.3. Material factor relies on the type of
equipment thus different type of equipment should have different value of material
factor. Pressure factor, Fp is taken as 1 since the operating pressure is more than – 0.5
barg.
B1 = 2.25
B2 = 1.82
FM = 3.1
Therefore,
Thus,
The bare module cost of splitting tower is 479,194 USD approximately MYR
1,514,244.16. By referring to the Perry’s Chemical Handbook, Table 25-57 of Typical
Factors of Converting Carbon Steel Cost to Equivalent-Alloy Costs, the factor for
converting carbon steel material to the stainless steel type 316 is 2.86. The bare
module cost obtained before need to be multiplied with 2.86 factors since the
calculation performed before is based on carbon steel material. Thus, the new value of
bare module cost is:
Table 8.1: Purchase Cost of Equipment
Equipment Unit CBM2001
(MYR)
CBM2011
(MYR)
Cost (MYR)
Reactor 1 - 4,330,738 4,330,738
Separator 2 225,696 332, 575 665, 150
Falling film
Evaporator
2 3,293,020 4, 852, 435 9,704, 870
Distillation column 1 - 1,721,126 1,721,126
Storage tank 2 - 97,400 194, 800
Heat exchanger 6 438,742 646,509 3,879,054
Pump P-102 51,842 76,392 79,392
P-103 14,956 22,039 22,039
Compressor 1 220,098 324,326 324,326
Total purchase cost of equipment (PCE) 20,723,695
8.3 CAPITAL COST ESTIMATION
Total capital cost, CTC of a project consist of the fixed capital cost, CFC and the working
capital cost, CWC, plus the cost of land and any other non-depreciable assets, CL. The
Equation 8.7 is given by
(8.7)
Where,
CTC = Total capital cost
CFC = Fixed capital cost
CWC = Working capital cost
CS = Start up cost
FP = Pressure factor to account for high pressure
FM = Material factor to account for material of construction
CP = Purchase cost for base condition
FBM = Bare module cost factor
CBM = Bare module equipment cost for base condition
8.3.1 Grass Roots and Total Module Costs
Total module cost refers to the cost of making small-to-moderate expansions or
alterations to an existing facility. The total module cost can be evaluated from (R.
Turton, 2009)
(8.8)
Grass roots refer to a completely new facility in which start the construction on
essentially undeveloped land, a grass field. The grass roots cab be evaluated from (R.
Turton, 2009)
(8.9)
Where n represents the total number of pieces of equipment.
Total Bare Modul Cost, TBM = MYR 20,097,704
Total Grass Roots Cost:
Contingency and Fee Costs MYR
Total bare module cost CTBM 20,723,695
Contingency, CC CC = 0.15CTBM 3,108,554.25
Fee, CF CF =0.03 CTBM 621,710.85
Total module cost CC+ CF+ CTBM=CBM 24,453,960
Auxiliary Facilities MYR
Site development, CSD CSD =0.05CTBM 1,036,184.75
Auxiliary building, CAB CAB = 0.04CTBM 828,947.80
Offsite facilities, COF COS =0.20C TBM 4,144,739
Total 6,009,871.55
Total Gross Roots Cost, GRC = Total Module Cost + Total Auxiliary Facilities
= MYR 30,463,832
8.3.2 Fixed Capital Cost
Fixed capital is the total cost of the plant ready for start-up. It is the cost paid to the
contractors. It includes the direct cost items that are incurred in the construction of a
plant, in addition to the cost of equipments are
1. Equipment erection, including foundations and minor structural work.
2. Piping, including insulation and painting.
3. Electrical, power and lighting.
4. Instruments, local and control room.
5. Ancillary buildings, offices, laboratory buildings, workshops.
6. Storages, raw materials and finished product.
7. Utilities (service), provision of plant for steam, water, air, firefighting services (if not
costed separately).
8. Site and site preparation.
9. Process buildings and structures.
In addition to the direct cost of the purchase and installation of equipment, the
capital cost of a project will include the indirect costs as listed below. These can be
estimated as a function of the direct costs.
a) Indirect costs
1. Design and engineering costs, which cover the cost of design and the cost of
engineering the plant: purchasing, procurement and construction supervision.
Typically 20% to 30% of the direct capital costs.
2. Contractor’s fees, if contractor is employed his fees (profit) would be added to the
total capital cost and would range from 5% to 10% of the direct costs.
3. Contingency allowance, this is an allowance built into the capital cost estimate to
cover for unforeseen circumstances (labour disputes, design errors, adverse
weather). Typically 5% to 10% of direct costs.
Table 8.2: Direct and Indirect Cost Specification
Specification Range MYR
Direct Cost (DC) / Physical Plant Cost (PPC)
Equipment erection 0.4GRC 12,185,532.66
Piping 0.7GRC 21,324,682.16
Instrumentation 0.2GRC 6,092,766.33
Electrical 0.1GRC 3,046,383.17
Land 3,000,000 3,000,000
Total Direct Cost (MYR) 45,649,364
Indirect Cost (IC)
Engineering and supervision 0.3DC 13,694,809.30
Construction expenses 0.1DC 4,564,936.43
Legal expenses 0.1DC 4,564,936.43
Contractor fees 0.05DC 2,282,468.22
Contingency 0.1DC 4,564,936.43
Total Indirect Cost (MYR) 29,672,086.43
TOTAL COST/FIXED CAPITAL
COST
Direct+ Indirect cost 75,321,450.43
8.3.3 Working Capital
Working capital is the additional investment needed, over and above the fixed capital to
start the plant up and operate it to the point when income is earned. It includes the cost
of (R. K. Sinnott, 1999):
1. Start-up.
2. Initial catalyst charges.
3. Raw materials and intermediates in the process.
4. Finished product inventories.
5. Funds to cover outstanding accounts from customers.
Most of the working capital is recovered at the end of the project. The total
investment needed for a project is the sum of the fixed and working capital. Working
capital can vary from as low as 5% of the fixed capital for a simple, single product,
process with little or no finished product storage; to as high as 30% for a process
producing a diverse range of product grades for a sophisticated market, such as
synthetic fibers.
Working capital cost, CWC = 5% CFC
Fixed Capital Cost, CFC = Grass Roots Cost + Total Cost
= MYR 30,463,832+MYR 75,321,450.43
= MYR105, 785,282.40
Working capital cost, CWC = 5% CFC
= 0.05 x MYR 105,785,282.40
= MYR 5,289,264.12
Start-up cost, CS = 3% CFC
= 0.03 x MYR 105,785,282.40
= MYR 3,173,558.50
8.3.4 Cost of Land
The land needed for the construction of glycerine plant have been estimated about 5
acres which is approximately to 20234.28 m2.This value of land is including the future
expansion of the plant. Kampung Acheh in Perak has been chosen to construct this
plant. According to ministry of industrial development authority (MIDA), the land value in
Kampung Acheh is MYR 17.00 per square feet.
Total Capital Cost, CTC = CFC +CWC + CL
= MYR105, 785,282.40+ MYR 5,289,264.12+ MYR 3,702,600
= MYR 114,777,146.50
8.4 COST OF MANUFACTURING
In order to estimate the manufacturing cost, should be provided the process information
provided on the PFD (process flow diagram), an estimate of the fixed capital investment
and an estimate of the number of operators required to operate the plant. The fixed
capital investment is the same as either the total module cost or the grass roots cost (R.
Turton, 2009).
The Equation 8.10 is used to evaluate the cost of manufacture becomes:
Cost of manufacture (COM) = Direct Manufacturing Cost (DMC) + Fixed Manufacturing
Cost (FMC) + General Expenses (GE) (8.10)
The cost of manufacturing, COM, can be determined when the following costs
are known or can be estimated:
1. Fixed Capital Investment (FCI): (CTM or CGR)
2. Cost of operating labor (COL)
3. Cost of utilities (CUT)
4. Cost of waste treatment (CWT)
5. Cost of raw materials (CRM)
8.4.1 Estimation Cost of Raw Material
Table 8.3: Raw Material Cost
Raw material Price (MYR/yr)
Crude palm oil MYR3.00/kg x 105,684,214 kg/yr = MYR317,052,642
Water MYR1.44/m3 x 6.302 m3/kg x 24h/day x 365/yr =MYR79,496
Total 317,211,634
8.4.2 Estimation Cost of Operating Labor
The operating labor requirement for chemical processing plants is given by Equation
8.11:
(8.11)
Where NOL is the number of operators per shift, P is the number of processing steps
involving the handling of particulate solids such as transportation and distribution,
particulate size control and particulate removal. Nnp is the number of non particulate
processing steps and includes compression, heating, and cooling, mixing and reaction
(R. Turton, 2009).
In general for the processes considered the value of P is zero and the value of
Nnp is given by
(8.12)
Table 8.4: Cost of Operating Labor
Equipment Type Quantity Nnp
Reactor 1 1
Separator 2 2
Distillation Column 1 1
Heat exchanger 6 6
Storage Tank 2 -
Evaporator 2 -
Pump 2 -
Compressor 1 -
Total 17 10
Since P =0 and Nnp = 10
For one equipment
A chemical plant normally operates 24 hours/day (R. Turton, 2009).
A single operator works on the average 49 weeks a year which is 3 weeks’ time off for
vacation and sick leave, five 8-hour shifts a week.
Four and one-half operators are hired for each operator needed in the plant at any time.
For all equipment:
Cost of Operating Labor per Year:
For 1 month wages of mechanical engineers is MYR 30024/Year
8.4.3 Estimation Cost of Utilities
The costs of utilities are directly influenced by the cost of fuel. Specific difficulties
emerge when estimating the cost of fuel, which directly impact the price of utilities such
as electricity, steam, thermal fluids, compressed air, cooling and process water. The
quantities required can be obtained from the energy balances and the flow-sheets. The
prices can be taken from the electrical company such as Tenaga Nasional Berhad and
it will depend on the primary energy sources and the plant location (R. K. Sinnott,
1999).
Cost of Utilities required:
Yearly cost = flow rate x costs x period x stream factor (8.13)
Since, assuming the plants operating days per year is 350 days. The plant is most
reliable and well-managed is typically shut down the plant for two week a year for
scheduled maintenance. So, stream factor is
Total heat load after heat integration consists of
1. Hot utilities
Power = 404.920 kW
Efficiency of drives, ξdr = 80.96%
2. Cold Utilities
Power =10.365 kW
Efficiency of drives, ξdr = 99.59%
Pump in the plant consist of
1. Pump (P-103)
Power =2.242x104 kW
Efficiency of drives, ξdr = 96.50%
2. Pump (P-102)
Power =142.3 kW
Efficiency of drives, ξdr = 91.30%
Evaporator in plant consist of
1. Evaporator (V-102)
Flow rate = 6089 kg/h
2. Evaporator (V-103)
Flow rate = 4915 kg/h
Total utilities cost = MYR (10,083+5036+11,241,151+75,411+982,034+792,691)/yr
= MYR 13,106,406/yr
8.4.4 Fixed Capital Investments (FCI)
Fixed capital investment is the total cost of designing, constructing and installing a plant
and the associated modification needed to prepare the plant site. The fixed capital
investment is made up of (R. K. Sinnott, 2009):
1. The inside battery limits (ISBL) investment – the cost of the plant itself
2. The modifications and improvements that must be made to the site infrastructure,
known as off-site or OSBL investment
3. Engineering and construction costs
4. Contingency charges
The value of fixed capital investments (FCI) is equal to the cost of grass roots which is
MYR 30,463,832.
8.4.6 Operating Costs
An estimate of the operating or manufacturing costs, the cost of producing the product,
is needed to judge the viability of a project, and to make choices between possible
alternative processing schemes. These costs can be estimated from the flow-sheet
which gives the raw material and service requirement and the capital cost estimate (R.
K. Sinnott, 1999).
The cost producing a chemical product including the items below this is divided
into two groups.
1. Fixed manufacturing costs: costs that do not vary with production rate. These are the
bills that have to be paid whatever the quantity produced.
2. Variable manufacturing costs: costs that are dependent on the amount of product
produced.
Table 8.5: Summary of manufacturing costs (R. K. Sinnott, 1999)
Description Specification Cost (MYR/yr)
Fixed Capital Investments
(FCI)
- 30,463,832
Fixed manufacturing costs
1. Operating labor, OL
2. Maintenance
3. Laboratory costs
4. Supervision
5. Plant overheads
6. Capital charges
7. Insurance
8. Local taxes
9. Royalties
-
10%FCI
20%OL
20%OL
50%OL
15%FCI
1%FCI
2%FCI
1%FCI
390,312
3,046,383.20
78,062
78,062
195,156
4,569,574.80
304,638.32
609,276.64
304,638.32
Total 9,576,103.28
Variable costs
1. Raw materials
2. Utilities
3. Miscellaneous materials
(waste treatment)
10% Maintenance
317,211,634
13,106,406
304,638.32
Total 330,622,678.30
Total manufacturing
expenses, AME
Fixed manufacturing
cost + Variable cost
340,198,781.60
General expenses
1. Administration
2. Distribution and selling
expenses
3. Research and
development
10% from supervision,
operating labor and
maintenance
10%FCI
7%FCI
351,475.72
3,046,383.20
2,132,468.24
Total annual general expenses, AGE 5,530,327.16
Cost of Manufacture, COM AME + AGE 345,729,108.80
8.5 PROFITABILITY ANALYSIS
There are three bases used for the evaluation of profitability which are:
a) Time
b) Cash
c) Interest rate
8.5.1 Depreciation Value
Assumption:
i. Use 5 years MACRS
ii. Project life of years is 10 years
iii. Taxation rate, t = 45%
iv. Using two methods which are double declining balance depreciation method, DDB
and straight line depreciation value method, SL
The MACRS method requires depreciation of the total FCIL, without regard for the
salvage value. Calculations are given below by using a basis MYR 29, 543,625:
For DDB, (8.14)
For SL, (8.15)
k dk DDB dk SL
1 6092766.33
2 9748426.128 5415792.293
3 5849055.677 4177896.912
4 3509433.406 3509433.406
5 2105660.044 3509433.406
6 1754716.703
A MACRS method over a short period of time is used which is 5 years for the class life.
In general, it is better to depreciation an investment as soon as possible. This is
because the more depreciation is in given year, the less taxes paid (R. Turton, 2009).
The MARCS method uses a double declining balance method and switches to
a straight line method when straight-line method yields a greater depreciation allowance
for that year. The straight –line method is applied to the remaining depreciable capital
over the remaining time allowed for depreciation. The half-year convention assumes
that the equipment is bought midway through the first year for which depreciation is
allowed. In the first year, the depreciation is only half of that for a full year. For sixth
year, the depreciation is for half-year (R. Turton, 2009). The depreciation schedule for
equipment with a 9.5 years class life and 5 year recovery period, using MARCS method
is shown in Table 8.7.
Table 8.6: Depreciation Schedule for MARCS Method for Equipment with a 9.5 Year
Class Life and a 5-Year Recovery Period
Year Depreciation Allowance (% of Capital
Investment)
1 6092766.33
2 9748426.128
3 5849055.677
4 3509433.406
5 3509433.406
6 1754716.703
8.5.2 Taxation, Cash Flow and Profit
Taxation has direct impact on the profits realized from building and operating a plant.
Tax regulations are complex, and companies have tax accounts and attorneys to
ensure compliance and to maximize the benefit from these laws.
For most large corporation, the basic federal taxation rate is 35%. In addition,
corporations must also pay state, city, and other local taxes. The overall taxation rate is
often in range of 40% to 50% (R. Turton, 2009). Table 8.8 provides the terms and
equation used to evaluate the cash flow and the profits produced from a project.
Table 8.8: The terms and equation used to evaluate the cash flow and the profits
produced from a project
Description Formula Equation
Expenses= Manufacturing costs +
Depreciation
= COMd + d (8.16)
Income tax= (Revenue – Expenses)(Tax rate) = (R - COMd – d)(t) (8.17)
After tax(net profit)= Revenue – Expenses –
Income tax
= (R - COMd – d)(1- t) (8.18)
After tax Cash Flow = Net Profit +
Depreciation
= (R - COMd – d)(1- t)+d (8.19)
Variables:
t = Tax rate
COMd = Cost of Manufacturing Excluding
Depreciation
d = Depreciation: depends upon method use
R = Revenue from sales
8.5.3 Nondiscounted Profitability Criteria
There are four nondiscounted profitability criteria as follow (R. Turton, 2009):
1. Time criterion
The term used for this criterion is the payback period (PBP), also known by a variety of
other names, such as payout period, payoff period, and cash recovery period. The
payback period can be defined as follow:
PBP = Time required after start-up to recover the Fixed Capital Investment, FCIL, for the
project
2. Cash criterion
The criterion used here is the cumulative cash position (CCP), which is simply the worth
of the project at the end of its life. For criteria using cash or monetary value, it is difficult
to compare projects with dissimilar fixed capital investment, and sometimes it is more
useful to use the cumulative cash ratio (CCR), which is defined as:
(8.20)
The definition effectively gives the cumulative cash position normalized by the initial
investment. From Table 8.10, the value of CCR was calculated which gives 4.25.
Projects with cumulative cash ratios greater than 1 are potentially profitable, whereas
those with ratios less than unity cannot be profitable.
3. Interest rate criterion
The criterion used here is called the rate of return on investment (ROROI) and
represents the non discounted rate at which money is made from our fixed capital
investment. ROROI also represented the percentage increase or decrease of an
investment over a period of time. It gives ideas of how much an investment is growing
or declining. The rate of return is given by
ROROI = Average Annual Net Profit (8.21)
Fixed Capital Investment (FCIL)
Sum of All Positive Cash Flows
CCR =
Sum of All Negative Cash Flows
Table 8.9: Rate of Return calculations (R. Turton, 2009)
Description Typical value Cost (MYR)
Revenue from sales
(IOI Oleochemical
Company and Network
Timur Sdn. Bhd,
September 2011)
RM2.10/kg of Glycerine
RM4.00/kg of Fatty Acid
Total
21,000,000
328,424,734
370,424,734.10
Annual net profit, ANP Revenues from sales – COM
= 370,424,734.10– 345,287,211
25,137,523.08
Income taxes 30% from ANP 7,541,256.92
Net annual profit, ANNP ANP – Income taxes
= 25,137,523.08– 7,541,256.92
17,596,266.16
The rate of return is often calculated for the anticipated best year of the project
which is the year in the net cash flow is greatest. It can also be based on the book value
of the investment, the investment after allowing for depreciation (R. K. Sinnott, 1999).
So, the return rate on investment is 40% over the period of a year by referring to the
Figure 8.1. A higher ROR indicates better returns and a negative ROROI indicates
losses.
Table 8.10: Nondiscounted After-Tax Cash Flows
End of
Year
(k)
Investment dk FCI - ∑dk R COMd (R - COMD -dk)(1-t) + dk Cash Flow Cumulative
Cash Flow
0 3,702,600 30,463,832 -3,702,600 -3,702,600
1 21324682.16 30,463,832 -21324682.16 -25,027,282
2 14428413.62 30,463,832 -14428413.62 -39,455,696
3 6092766.33 24,371,065 370,424,734 345,729,109 16324338.76 16324338.76 -23,131,357
4 9748426.128 14,622,639 370,424,734 345,729,109 17969385.67 17969385.67 -5,161,971
5 5849055.677 8,773,584 370,424,734 345,729,109 16214668.97 16214668.97 11,052,698
6 3509433.406 5,264,150 370,424,734 345,729,109 15161838.95 15161838.95 26,214,537
7 3509433.406 1,754,717 370,424,734 345,729,109 15161838.95 15161838.95 41,376,376
8 1754716.703 0 370,424,734 345,729,109 14372216.43 14372216.43 55,748,592
9 0 370,424,734 345,729,109 13582593.92 13582593.92 69,331,186
10 0 370,424,734 345,729,109 13582593.92 13582593.92 82,913,780
11 0 370,424,734 345,729,109 13582593.92 13582593.92 96,496,374
12 9,795,366 0 374,127,334 345,729,109 15619023.92 25,414,390 121,910,764
Figure 8.1: Cumulative Cash Flow Diagram for Nondiscounted After-Tax Cash Flows
-60,000,000
-40,000,000
-20,000,000
0
20,000,000
40,000,000
60,000,000
80,000,000
100,000,000
120,000,000
140,000,000
0 2 4 6 8 10 12 14
No
nd
isc
ou
nte
d C
ash
Flo
w (
MY
R)
Time after Project Start (Years)
Nondiscounted After-Tax Cash Flow
PBP = 4.82 years
FCIL =MYR 30,463,832
CCP= MYR 121,910,764
CCR = 4.09
ROROI = 40%
8.5.4 Discounted Profitability Criteria
The difference between the nondiscounted and discounted criteria is that for the latter it
discounts each of the yearly cash flows back to time zero. The discounted cumulative
cash flow diagram will be used to evaluate profitability. There have three different types
of criteria (R. Turton, 2009):
1. Time criterion
The discounted payback period (DPBP) is similar to the nondiscounted which is
DPBP = Time required, after start-up, to recover the fixed capital investment, FCIL,
required for the project, with all cash flows discounted back to time zero.
The project with the shortest discounted payback period is the most desirable.
2. Cash criterion
The discounted cumulative cash position, is known as the net present value (NPV) or
net present worth (NPW) of the project, is defined as
NPV = Cumulative discounted cash position at the end of the project
The NPV of a project is influenced by the level of fixed capital investment, and a
better criterion for comparison of projects with different investment levels is present
value ratio (PVR):
PVR = Present Value of All Positive Cash Flows
Present Value of All Positive Cash Flows
A value of unity for a project represents a break-even situation. Values greater
than 1 is profitable processes, whereas less than 1 represent unprofitable projects.
Table 8.11: Discounted Cash Flows
End of Year (k) Non discounted Cash flow Discounted Cash Flow Cumulative Discounted Cash Flow
0 -3,702,600 -3,702,600 -3,702,600
1 -21324682.16 -19386074.69 -23,088,675
2 -14428413.62 -11924308.77 -35,012,983
3 16324338.76 12264717.33 -22,748,266
4 17969385.67 12273332.2 -10,474,934
5 16214668.97 10068033.71 -406,900
6 15161838.95 8558462.818 8,151,563
7 15161838.95 7780420.743 15,931,983
8 14372216.43 6704745.035 22,636,728
9 13582593.92 5760345.731 28,397,074
10 13582593.92 5236677.937 33,633,752
11 13582593.92 4760616.306 38,394,368
12 25,414,390 8097807.945 46,492,176
Figure 8.2: Cumulative Cash Flow Diagram for Discounted After- Tax Cash Flows
-40,000,000
-30,000,000
-20,000,000
-10,000,000
0
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
0 2 4 6 8 10 12
Dis
co
un
ted
Ca
sh
Flo
w (
MY
R)
Time After Project Start (years)
Discounted After-Tax Cash Flows
PVR = 2.32
DPBP = 5 years
NPV = MYR 46,492,176
Discounted land + WC = MYR 8,425,157
Based on the nondiscounted cash flow and discounted cash flow, there are significant
effects of discounting the cash flows to account for time value of money. From these
results, the following observations can be made.
1. In term of the time basis, the payback period increases as the discount rate
increases. From the calculation, it increases from 4.82 to 5 years.
2. In term of cash basis, replacing the cash flow with the discounted cash flow
decreases at the end of the project which is dropped from MYR 121,910,764 to
46,492,176.
3. In terms of cash ratios, discounting the cash flows gives a lower ratio which is
dropped from 4.09 to 2.32.
As the discount rate increases, all of the discounted profitability criteria will be reduced.
3. Interest Rate Criterion
The discounted cash flow rate of return (DCFROR) is defined to be the interest rate at
which all the cash flows must be discounted to get the net present value of the project
to be equal to zero (R. Turton, 2009).
DCFROR = Interest or discount rate for which the net present value of the project is
equal to zero
If the DCFROR is greater than the internal discount rate, the project is
considered to be profitable. Table 8.12 showed the NPVs for several different discount
rates were calculated and the results.
Table 8.12: NPV for Glycerine Project as a Function of Discount Rate
Interest/Discount rate NPV (MYR)
0% 46,492,176
10% 13329987.94
15% 4,796,091
20% -967840.5494
The value of the DCFROR is found at NPV equals 0. Interpolating from Table
8.12 gives:
Figure 8.3 provides the cumulative discounted cash flow diagram for several
discount factors. It shows the effect of changing discount factors on the profitability and
shape of the curves. It also includes curves for the DCFROR with 19.20%. It can be
seen that the NPV for the project is zero. If the acceptable rate of return were set at
20%, then the project would not be considered an acceptable investment because it is
indicated by negative NPV for I =20%. For project having a short life and small discount
factors, the effect of discounting is small, and nondiscounted criteria may be used to
give an accurate measure of profitability. Normally, large projects that involved many
millions of ringgit of capital investment discounting techniques is always used (R.
Turton, 2009).
Table 8.13: Discounted Cumulative Cash Flow with Different Discount Rates
Discount rate, I = 10% Discount rate, I = 20%
End of
Year
(k)
Discounted cash
flow (DCF)
fd = 1/(1+i)n
Discounted
cash flow
DCC =DCFx fd
Cumulative
discounted
cash flow fd = 1/(1+i)n
Discounted
cash flow
DCC=DCFx fd
Cumulative
discounted
cash flow
0 -3,702,600 1 -3702600 -3702600 1 -3702600 -3702600
1 -19386074.69 0.909090909 -17623704.26 -21326304 0.83333333 -16155062.24 -19857662.24
2 -11924308.77 0.826446281 -9854800.639 -31181105 0.69444444 -8280769.981 -28138432.22
3 12264717.33 0.751314801 9214663.657 -21966441 0.5787037 7097637.343 -21040794.88
4 12273332.2 0.683013455 8382851.034 -13583590 0.48225309 5918852.334 -15121942.54
5 10068033.71 0.620921323 6251456.812 -7332133.4 0.40187757 4046116.942 -11075825.6
6 8558462.818 0.56447393 4831029.142 -2501104.3 0.33489798 2866211.881 -8209613.72
7 7780420.743 0.513158118 3992586.068 1491481.81 0.27908165 2171372.637 -6038241.083
8 6704745.035 0.46650738 3127813.041 4619294.86 0.23256804 1559309.407 -4478931.676
9 5760345.731 0.424097618 2442948.905 7062243.76 0.1938067 1116393.594 -3362538.082
10 5236677.937 0.385543289 2018966.038 9081209.8 0.16150558 845752.7226 -2516785.359
11 4760616.306 0.350493899 1668566.973 10749776.8 0.13458799 640721.7596 -1876063.6
12 8097807.945 0.318630818 2580211.167 13329987.9 0.11215665 908223.0502 -967840.5494
Discount rate, I = 19.20%
fd = 1/(1+i)n
Discounted cash flow
DCC =DCFx fd
Cumulative discounted cash
flow
1 -3702600 -3702600
0.838926174 -16263485.48 -19966085.48
0.703797126 -8392294.247 -28358379.72
0.590433831 7241504.035 -21116875.69
0.495330395 6079354.485 -15037521.2
0.415545633 4183727.444 -10853793.76
0.348612108 2983583.768 -7870209.989
0.292459823 2275460.47 -5594749.519
0.2453522 1645023.946 -3949725.573
0.205832383 1185665.687 -2764059.887
0.172678173 904259.9807 -1859799.906
0.144864239 689643.0603 -1170156.846
0.121530402 183940.9069 -986215.9387
Figure 8.3: Discounted Cumulative Cash Flow Diagrams Using Different Discount Rate
-40,000,000
-30,000,000
-20,000,000
-10,000,000
0
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
0 2 4 6 8 10 12 14
Dis
co
un
ted
Ca
sh
Flo
w (
MY
R)
Time after project start (Years)
Discounted After- Tax Cash Flows
Discount rate = 10%
Discount rate = 19.20% at NPV=0 (DCFROR)
Discount rate = 20%
Discount rate = 0%
REFFERENCES
Aspen Hysis Simulation Basis Guideline AspenTech
http://www.tnb.com.my (March 2009)
IOI Oleochemical Company and Network Timur Sdn. Bhd, September 2011
Malaysian Industrial Development Authority (MIDA), August 2010
R. Sinnott and G. Towler (1999), Chemical Engineering Design, 3rd Edition, Elsevier
Ltd
R. Sinnott and G. Towler (2009), Chemical Engineering Design, 5th Edition, Elsevier
Ltd
R. Turton, R. Ballies, W. B. Whiting and J. A. Shaeiwitz (2009), Analysis, Synthesis and
Design of Chemical Processes, 3rd Edition, Pearson Education International
Robert H. Perry, Don W. Green and James O. Maloney (1997), 7th Edition, McGraw-Hill
Higher Education