CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in...

111
CHAPTER 7 Transmission Network Development Plan

Transcript of CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in...

Page 1: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

CHAPTER 7 Transmission Network

Development Plan

Page 2: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-1

Chapter 7 Transmission network development plan

7-1 Outline of Transmission Network in Nigeria

7-1-1 Geographical Structure of the Transmission Company of Nigeria (TCN)

TCN has created eight Transmission Planning Regions for better planning.

The actual regions under the field and maintenance services sector are shown in Figure 7-1.1. Since new regions, Abuja Region (FCT (Abuja), Nasarawa and Kogi states) were settled in July, 2018, there are currently nine Transmission Planning Regions.

Source: TCN Figure 7-1.1 Geographical Structure of TCN

The electricity supply to Nigerian consumers is handled by 11 privatized distribution companies, each with its own area, as shown in Figure 7-1.2.

ABUJA REGION

Page 3: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-2

Source: JICA Study Team Figure 7-1.2 Areas of Distribution Companies in Nigeria

The electricity consumption of the southern DisCos far exceeds their northern equivalents because the former are far more densely populated and most industries are concentrated there.

7-1-2 Existing and Planned Power System and Network Configuration

The two latest maps with the existing, ongoing and planned Nigerian 330 and 132 kV transmission network are shown in Annexes 7.1a and 7.1b (respectively dated January and March, 2018).

The latest version of the single-line diagram of the existing network (dated July, 2016), is shown in Annex 7.1c. TCN has advised that there has not been further updated.

Technical data on transmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively.

The present status of reactors and capacitors installed in the TCN network is summarized in Table 7-1.1 and Table 7-1.2. Introducing additional capacitors, as necessary, takes the status of pre-existing units into consideration, as shown in Table 7-1.2, assuming all faulty and repairable capacitors will, if necessary, be repaired and the others will be commissioned as planned.

Table 7-1.1 Shunt Reactors

S/N Substation Voltage

(kV)

MX

(MVar) Switchable

1 KANO 330 -75.00 Y

2 GOMBE 330 -50.00 Y

3 GOMBE 330 -50.00 Y

4 YOLA 330 -75.00 Y

5 KADUNA 330 -75.00 Y

Benue

MakurdiNo. Disco Location

1 Abuja Electricity Distribution Company Abuja

2 Benin Electricity Distribution Company Benin

3 Eko Electricity Distribution Company Eko

4 Enugu Electricity Distribution Company Enugu

5 Ibadan Electricity Distribution Company Ibadan

6 Ikeja Electricity Distribution Company Ikeja

7 Jos Electricity Distribution Company Jos

8 Kaduna Electricity Distribution Company Kaduna

9 Kano Electricity Distribution Company kano

10 Port Harcourt Electricity Distribution Company Port Harcourt

11 Yola Electricity Distribution Company Yola

Page 4: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-3

S/N Substation Voltage

(kV)

MX

(MVar) Switchable

6 JOS 330 -75.00 Y

7 JEBBA T.S. 330 -75.00 Y

8 JEBBA T.S. 330 -75.00 Y

9 OSHOGBO 330 -75.00 N

10 BENIN 330 -75.00 Y

11 BENIN 330 -75.00 Y

12 ALAOJI 330 -75.00 Y

13 IKEJA WEST 330 -75.00 Y

14 IKEJA WEST 330 -75.00 Y

15 KATAMPE 330 -75.00 Y

16 MAKURDI 330 -75.00 Y

17 ONITSHA 330 -75.00 Y

18 OKEARO 330 -75.00 Y

19 GOMBE 33 -30.00 Y

20 GOMBE 33 -30.00 Y

21 YOLA 33 -30.00 Y

22 YOLA 33 -30.00 Y

Source: JICA Study Team

Table 7-1.2 Fixed capacitors

S/N Substation Voltage

(kV)

Capacitor

(MVar) Status Planned Action

1 Kumbotso 330 50 In operation

2 Kumbotso 330 50 In operation

3 Akangba A 132 72 Installed but not commissioned yet To be commissioned

4 Akangba B 33 24 Installed but not commissioned yet To be commissioned

5 Akoka 33 24 Installed but not commissioned yet To be commissioned

6 Alausa 33 24 Installed but not commissioned yet To be commissioned

7 Alimoso 33 24 Installed but not commissioned yet To be commissioned

8 Ejigbo 33 24 Installed but not commissioned yet To be commissioned

9 Ijoro 33 24 Installed but not commissioned yet To be commissioned

10 Isolo 33 24 Installed but not commissioned yet To be commissioned

11 Ogba 33 24 Installed but not commissioned yet To be commissioned

12 Otta 33 24 Installed but not commissioned yet To be commissioned

13 Yandev 33 20 Installed but not commissioned yet To be commissioned

14 Ikorodu 33 20 Faulty, mainly due to CB fault Can be repaired

15 Ikorodu 33 20 Faulty, mainly due to CB fault Can be repaired

16 Abeokuta 33 20 Faulty, mainly due to CB fault Can be repaired

17 Abeokuta 33 20 Faulty, mainly due to CB fault Can be repaired

18 Iseyin 33 20 Faulty, mainly due to CB fault Can be repaired

19 Aiyede 33 20 Faulty, mainly due to CB fault Can be repaired

20 Aiyede 33 20 Faulty, mainly due to CB fault Can be repaired

21 Agbara 33 20 Commissioned, can be switched on

22 Ijebuode 33 20 Commissioned, can be switched on

23 Sagamu 33 20 Commissioned, can be switched on

24 Irua 33 20 Faulty, mainly due to CB fault Can be repaired

25 Ilorin 33 20 Faulty, mainly due to CB fault Can be repaired

26 Akure 33 20 Faulty, mainly due to CB fault Can be repaired

27 Awka 33 20 Faulty, mainly due to CB fault Can be repaired

28 Uyo 33 20 Faulty, mainly due to CB fault Can be repaired

29 Effurum 33 20 Faulty, mainly due to CB fault Can be repaired

Page 5: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-4

S/N Substation Voltage

(kV)

Capacitor

(MVar) Status Planned Action

30 Amkpe 33 20 Faulty, mainly due to CB fault Can be repaired

31 Akwanga 33 20 Faulty, mainly due to CB fault Can be repaired

32 Akwanga 33 20 Faulty, mainly due to CB fault Can be repaired

33 Minna 33 20 Faulty, mainly due to CB fault Can be repaired

34 Minna 33 20 Faulty, mainly due to CB fault Can be repaired

35 Kontagora 33 20 Faulty, mainly due to CB fault Can be repaired

36 Kontagora 33 20 Faulty, mainly due to CB fault Can be repaired

37 Zaria 33 20 Faulty, mainly due to CB fault Can be repaired

38 Zaria 33 20 Faulty, mainly due to CB fault Can be repaired

39 Kaduna Town 33 20 Faulty, mainly due to CB fault Can be repaired

40 Kaduna Town 33 20 Faulty, mainly due to CB fault Can be repaired

41 Dakata 33 20 Faulty, mainly due to CB fault Can be repaired

42 Dakata 33 20 Faulty, mainly due to CB fault Can be repaired

43 Apir 33 20 Faulty, mainly due to CB fault Can be repaired

44 Kumbotso 33 20 Installed but not commissioned yet To be commissioned

45 Okene 33 20 Installed but not commissioned yet To be commissioned

46 Dan-Agundi 33 20 Installed but not commissioned yet To be commissioned

47 Katsina 33 20 Installed but not commissioned yet To be commissioned

48 Ife 33 20 Installed but not commissioned yet To be commissioned

49 Ayede 33 20 Installed but not commissioned yet To be commissioned

50 Ijebu-Ode 33 20 Installed but not commissioned yet To be commissioned

51 Shagamu 33 20 Installed but not commissioned yet To be commissioned

52 Iseyin 33 20 Installed but not commissioned yet To be commissioned

53 Ilorin 33 20 Installed but not commissioned yet To be commissioned

54 Akure 33 20 Installed but not commissioned yet To be commissioned

55 Apo 33 20 Installed but not commissioned yet To be commissioned

56 Apo 33 20 Installed but not commissioned yet To be commissioned

Source: JICA Study Team

7-1-3 Operating Frequency and Voltage Limits

In accordance with the Grid Code and to maintain the security and integrity of the transmission system, it is necessary that the System Operator operate and dispatch the transmission system in such a manner as to provide adequate frequency control and achieve operation within applicable frequency limits at all times.

The nominal system frequency shall be 50 Hz. The National Control Center endeavors to control this to within a narrow operating band of +/- 0.5% from 50 Hz (49.75 – 50.25 Hz), but under system stress the frequency on the power system may vary within the limits of 50 Hz +/- 2.5% (48.75 – 51.25 Hz).

The nominal voltage levels of the transmission and distribution system are 330, 132, 66, 33 and 11 kV respectively. Under normal operation, the limits of the 330 and 132 kV systems are 0.85-1.05 and 0.85-1.10 pu respectively. Under contingency conditions the emergency limits for the same are 0.80-1.10 and 0.80-1.15 pu.

Page 6: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-5

7-1-4 System Peak Demand and Generation

7-1-4-1 Development of Peak Output and Energy Generated

The installed capacity (less de-commissioned units) in the grid as of December, 2016 was 12,310 MW. In 2016, the plant average MW availability was 7,877 MW, which was 23.07% higher than the 6,401 MW obtained in 2015. The Thermal Station average MW availability contribution was 6,669 MW – exceeding the, 2015 figure of 5,312 MW by 25.53%. The Hydro Station average MW availability was 1208 MW, which exceeded the, 2015 figure of 1,088 MW by 120 MW (11.07%). The maximum daily energy of 109,372 MWh occurred on 2 February, 2016, exceeding the maximum daily energy of 106,825 MWh recorded on 24 November, 2015 by 2,546 MWh (2.38%). The peak generation of 5,074 MW. which was attained on 2 February, 2016 exceeds the peak generation of 4,883 MW recorded on 23 November, 2015 by 190 MW (3.91%).

Peak output of power stations depends on the availability of generation units, water inflow for hydro power plants and gas supply for thermal power plants and not on actual demand. Demand is always much higher than the available generation capacity.

NCC daily operational report on 08.12.2015 shows a Peak Demand Forecast (connected + suppressed load) of 14,630 MW.

The peak generation of 5,074 MW, which was attained on 2 February, 2016 exceeded the peak generation of 4,883 MW recorded on 23 November, 2015 by 190 MW (3.91%).”

In general, only approximately 40% of the estimated demand could be supplied.

NCC’s operational reports show that many generation units are not in operation due to the unavailability of gas. On December 8, 2015 for example, about 1,500 MW of generation capacity were was offline for this reason. The gas supply was interrupted due to sabotage of the pipeline system.

7-1-4-2 Transition of Energy Generation and Peak Demand

Records on annual energy generated and simultaneous national peak demand of electricity show permanent growth with two periods of stagnation/decline.

Figure 7-1.3 and Figure 7-1.4 indicate that periods of stagnation/decline of energy generation and peak demand were offset rapidly in the following years.

Between 1973 and 2016, peak generation increased from 385 to 5,074 MW, i.e. with an average growth rate of about 6.2%. During the same period the annual energy generated increased from 2,493 to 28,412 GWh, i.e. with an average growth rate of about 6%.

Page 7: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-6

Source: TCN Annual Report, 2016

Figure 7-1.3 Annual Energy Generated

Source: TCN Annual Report, 2016 Figure 7-1.4 National Peak

24

93

27

80

33

22

37

50

41

95

43

59

51

51

57

24

67

66

71

02 84

56

89

27 10

15

51

06

65

11

14

11

14

71

12

70

01

33

64

14

21

21

50

66

14

61

71

45

57

15

79

31

59

71

15

41

61

62

53

16

29

11

52

27 1

76

37

21

54

42

26

12

24

13

22

40

77

23

30

02

31

87

21

30

92

08

70

25

02

02

50

20

29

57

32

96

28

30

12

63

15

15

28

41

2

0

5000

10000

15000

20000

25000

30000

350001

97

31

97

41

97

51

97

61

97

71

97

81

97

91

98

01

98

11

98

21

98

31

98

41

98

51

98

61

98

71

98

81

98

91

99

01

99

11

99

21

99

31

99

41

99

51

99

61

99

71

99

81

99

92

00

02

00

12

00

22

00

32

00

42

00

52

00

62

00

72

00

82

00

92

01

02

01

12

01

22

01

32

01

42

01

52

01

6

GWH ANNUAL ENERGY GENERATED (GWH) 1973 -20163

85

45

7 57

9 70

87

67 88

7 10

95

11

81

13

23

14

48

14

34

15

32

17

20

17

30

18

55

19

52

20

08 22

19

22

46

23

82

23

30

24

46

24

52

24

70

24

57

24

48

24

58

24

99

29

34 32

23 34

79

34

27 3

77

43

68

23

60

03

59

63

71

03

80

43

80

44

51

84

45

84

39

04

88

45

07

4

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

5500

19

73

19

74

19

75

19

76

19

77

19

78

19

79

19

80

19

81

19

82

19

83

19

84

19

85

19

86

19

87

19

88

19

89

19

90

19

91

19

92

19

93

19

94

19

95

19

96

19

97

19

98

19

99

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

20

16

MW

YEAR

SIMULTANEOUS NATIONAL PEAK (MW ) 1973 -2016

Page 8: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-7

7-1-4-3 Transmission Losses

The overall transmission losses and substation consumptions amounted to 9.92% of the energy sent out in 2016, as shown in Table 7-1.3. The losses in 2016 were lower than the previous year, signifying a steady decline over the past three years.

Table 7-1.3 Energy balance summary (Dec-Jan, 2016)

Energy generated

(MWh)

Energy sent out

(MWh)

Energy available

for sales, incl distr

losses (MWh)

Transformer

losses and

substations

consumption

(MWh)

Transformer

losses and

substations

consumption (%

of energy sent

out)

Energy available

for sales and distr

losses (% of

energy)

28,532 28,033 25,251 27,821 9.92 90.08

Source: JICA Study Team

7-1-4-4 Existing Generation and Generation Expansion

Based on information provided, the already installed gross power generation capacity is about 13,300 MW, of which some 11,800 MW are noted as net available capacity.

Considering the latest information provided by generating companies, about 9,500 MW (80%) of this capacity should have been available at the end of the year, 2015. However, only 5,900 MW net capacity has been made available, as reflected in the statistics of the National Control Center (NCC).

The reasons for the unavailability include: planned outages for maintenance or forced outages due to technical deficiencies of assets, as well as unplanned unavailability due to fuel supply shortages or sabotage of gas pipelines.

A further analysis of information provided shows that about 20% of the installed generation capacity is based on plants which are 25 or more years old, some of which have efficiency of under 30%.

It is obvious that most of the old thermal power plants are - or will be – subject to more frequent forced outages or long- term planned maintenance outages in the near future. Accordingly, they should be replaced by new and more efficient facilities.

Together with TCN, it was agreed that all existing power plant units not being currently available should be made available by 2020 at the latest, even if currently unavailable for technical reasons.

The Master Plan shows a program for step-by-step modernization of these plants in parallel to implementing new units at existing sites, as well as completely new power plants.

It further shows technical data for all existing and new generation facilities and the respective implementation timetable. Newly proposed power plants are considering diversification of primary energy sources in the form of solar/wind/hydro technology, as well as modern gas- and coal-fired thermal plants.

Installation of new assets will follow the assumed increasing power demand, as well as the need for replacement of existing power generation assets.

Page 9: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-8

7-1-4-5 Daily Load Curve

Electrical power demand in Nigeria peaks in the evening, between 20:00 and 23:00 hours, while power demand is lowest in the early morning between 03:00 and 05:00 hours.

Figure 7-1.5 Daily Load Curve on 1 October, 2014

7-1-5 Difficulties and Challenges Faced by TCN

7-1-5-1 General

The electric power system of Nigeria has long suffered from a lack of generation capacity which requires permanent load shedding. Furthermore, frequent transmission and distribution system disturbances exacerbate the unreliability of the power system.

The main reasons for power shortages are outages of generation units and a lack of gas to generate power. The gas supply is frequently interrupted due to the pipeline network being sabotaged.

The main concern for the future expansion of generation, however, is the availability of gas for additional generation capacity and the expansion of the gas pipeline network. Currently, most power plants are installed in southern Nigeria close to oil and gas fields. To ensure a reliable and optimally expanded transmission system, there will be a need to install new power plants also elsewhere in Nigeria.

There are some plans for new hydro power plants, while photovoltaic and wind power plants are also under consideration.

However, to provide sufficient base load power in future, large coal-fired power plants may have to be

Page 10: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-9

included in the generation expansion program.

In terms of generation and load balance in the eight TCN planning regions, four or five have a significant generation deficit. With the exception of Benin and Port Harcourt regions, demand exceeds available generation power in all others. In the Shiroro region however, the situation will be reversed once new HPP plants (e.g. Zugeru) come into operation.

The reason for this imbalance is due to the generation being mainly concentrated in South (thermal stations in Port Harcourt, Enugu, Benin and Lagos) and Central West (hydro stations of Jebba, Kainji and Shiroro in Shiroro region). The Central, North and North-East in particular are characterized by the total absence of generating stations, while load demand is mainly in the South and South-West.

To supply power in areas with little or no generation such as the North-East, long 330 kV transmission lines are built (radial system), which means voltage regulation problems may occur and the reactive power flowing through them necessitates large reactive power compensation equipment (reactors) at the corresponding substations (Kano, Gombe, Maiduguri).

Additional 330 kV lines running in parallel are expected to exacerbate overvoltage issues, necessitating additional compensation equipment at Yola, Jalingo and other substations.

7-1-5-2 Frequency Control

The Grid Code frequency range is 50 Hz + 0.50%, i.e. 49.75 to 50.25 Hz (Grid Code chapter 4 Section 15.3.1), however due to the low availability of units on free governor control coupled with serious demand/generation imbalance, it was practically difficult to maintain and only Omotosho gas and NIPP and Olorunsogo gas units that were on free governor at one point or the other in recent years.

NCC was therefore constrained on numerous occasions to operate the grid outside the statutory frequency limits.

The frequency fluctuations which are mostly due to load rejection by DisCos and volatile loads from steel mills create harmonics and cause voltage flickering within the system. Most of the UFLS relay schemes installed in some substations to mitigate the impact of system collapses were not functional most of the time, which is why the characteristically strenuous manual frequency control technique, achieved through load shedding, defined year-round operations.

7-1-5-3 Voltage Control

In 2016, the voltage limits specified by the Grid Code were achieved largely on the upper voltage limit. The lower voltage limit meanwhile, formally experienced in the northern axis of the grid and plagued by voltage instability/decay, has been improved by installing capacity banks at Kano T.S. The AVRs of some GenCos are not functional.

7-1-5-4 Transmission Constraints

Transmission is plagued with incessant tripping of transmission lines, improper relay coordination, line

Page 11: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-10

limitation, ageing lines and inability to satisfy the N-1 contingency.

Transformers loaded to 100% and above of their rating require very urgent attention. Circumstances where some have to be loaded for hours above 100% reflects the urgent need to reinforce affected transformer banks.

7-1-5-5 Power Pool With Neighboring Countries

The sphere of operations of the Transmission Company of Nigeria transcends the geographical landscape of the country; the Republics of Niger and Benin are interconnected with the Nigerian transmission network.

The energy supplied to Benin Republic in 2016 was 1,275 GWH, signifying a decrease of 16.95% when compared with the 2015 figure of 1,535 GWH. The Republic of Niger was furnished with energy of 666 GWH in 2016, which is lower than the 2015 supply of 692 by 3.77% (ref. Table 7-1.4). These values represent only energy delivered through the 132kV transmission lines only. A fraction of the total supply to that country was through some 33kV distribution feeders.

Table 7-1.4 Cross-border electricity transactions (MWH)

Month BENIN REPUBLIC NIGER REPUBLIC

2016 2015 2016

JANUARY 139,232 131,851 JANUARY 139,232

FEBRUARY 137,028 128,821 FEBRUARY 137,028

MARCH 117,525 133,755 MARCH 117,525

APRIL 104,796 134,685 APRIL 104,796

MAY 86,139 111,132 MAY 86,139

JUNE 63,542 125,313 JUNE 63,542

JULY 88,775 114,134 JULY 88,775

AUGUST 97,162 133,044 AUGUST 97,162

SEPTEMBER 85,785 120,276 SEPTEMBER 85,785

OCTOBER 122,435 137,372 OCTOBER 122,435

NOVEMBER 116,345 137,028 NOVEMBER 116,345

DECEMBER 116,487 128,131 DECEMBER 116,487

TOTAL 1,275,251 1,535,542 TOTAL 1,275,251

AVERAGE 106,271 127,962 AVERAGE 106,271

Source: JICA Study Team

Page 12: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-11

7-2 Ongoing Projects

7-2-1 Contents of Projects

In July 2018, the JICA study team received two updated lists of recently completed and ongoing projects from TCN:

One list with TCN projects and

One list with NIPP projects.

These are included in Annexes 7.2a and 7.2b respectively.

While executing the Transmission Expansion Plan Study, it was agreed with TCN that as a basis for preparing the plan, we will assume that all ongoing projects will be completed by 2020.

Based on this network configuration, power system studies to identify further transmission system expansions between 2020 and 2040 were carried out.

The challenging nature of implementing transmission projects identified in the Transmission Expansion Plan by 2020 is acknowledged, given that it takes a minimum of three years from now to implement such projects (one year to prepare tender documents and select the implementation contractor and two years for project implementation). Accordingly, projects that may not be completed by 2020 should be prioritized for completion as soon as possible after 2020.

The TCN and NIPP projects that are expected to be implemented by 2020 have been included in the new PSS/E case for 2020. They are listed in Annexes 7.2a and 7.2b and the PSS/E case has also been modified to include the decisions made, following an exchange of dialog between TCN and the JICA study team.

7-2-2 Donors Assistance and Prospective Donors

7-2-2-1 Inclusion of TCN, NIPP, JICA and AFD projects

Annexes 7.2c and 7.2d show the 330 kV network configurations in the Lagos region including the projects that will be implemented under JICA financing. Furthermore, the following ongoing projects financed by AFD (Agence Française de Développement) for Abuja area have been considered:

New transmission lines:

142km of new 330 kV Double-Circuit line from Lafia 330 kV Substation (new) to New Apo 330/132/33 kV Substation.

7km of new 132 kV Double-Circuit line from New Apo 330/132/33 kV substation to Old Apo 132/33 kV substation

35km of new 132 kV Double-Circuit line from New Apo 330/132/33 kV substation to the new Kuje132/33 kV substation

29km of new 132 kV Double-Circuit line from the proposed Kuje 132/33 kV Substation to West Main (Lugbe) 330/132/33V substation.

Page 13: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-12

New substations:

330/132/33 kV substation at New Apo 132 kV line bay extension at Old Apo 132 kV SS 330/132/33 kV substation at WestMain (Lugbe) 132/33 kV substation at Kuje to be equipped with 3 × No. 60MVA 132/33 kV Substation at Wumba/Lokogomato 132/33 kV GIS substation at Gwarimpa

7-2-2-2 Additional Transmission System Expansions and Rehabilitation Measures Proposed by TCN

In the latest Transmission Expansion Plan submitted to TCN in December 2017, TCN has requested the inclusion of additional transmission system expansions and rehabilitation/reinforcement measures which have been identified by TCN. Six EXCEL lists have been provided with proposed projects, see Annexes 7.2e1 to 7.2e5.

The annexes also show the costs of the individual measures as estimated by TCN.

TCN plans to implement the measures and finance them via development banks as shown in Table 7-2.1.

Table 7-2.1 Prospective Development Banks Finance

Project Development Bank Total Cost

(million US$)

Annex 7.2e1 AFD (French Development Agency - Agence Française de Développement) 170

Annex 7.2e2 JICA (Japan International Cooperation Agency) To be determined

Annex 7.2e3 AfDB (African Development Bank) 410

Annex 7.2e4 World Bank 486

Annex 7.2e5 AFD (French Development Agency - Agence Française de Développement) 272

Total 1,538

Source: JICA Study Team

There are plans to implement all network expansions and rehabilitation/reinforcement measures as soon as possible, but considerable preparatory work (e.g. feasibility studies, tender documents etc.) is required in most cases. At this stage only implementation of system expansions according to Annex 7.2e1 (AFD-Project) is going-on and commissioning by 2020 may be achievable.

For projects financed by other banks (Annexes 7.2e2 to 7.2e5) implementation between 2020 and 2025 can be considered feasible. Usually about two to three years are required for feasibility studies, environmental impact studies, route survey, preparation of technical specifications and tender documents, bidding, tender evaluation and contracting and arrangement financing agreements. Two to three years can also be assumed for constructing and commissioning the projects.

Page 14: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-13

Table 7-2.2 Main TCN 330 and 132 kV transmission line projects

Area Region Location Description Voltage

(kV)

in

operation

by

PROPOSED ABUJA TRANSMISSION RING PROJECT (AFD1)

North-Central Abuja New Apo

Construction of about 172km of a new 330 kV

Double-Circuit line from Lafia 330 kV Substation

(new) to the proposed New Apo 330/132/33 kV

Substation.

330 2020

North-Central Abuja Old Apo

Construction of about 7km of a new 132 kV

Double-Circuit line from New Apo 330/132/33 kV

substation to Old Apo 132/33 kV substation:

132 2020

North-Central Abuja Old Kuje

Construction of 35km of a new 132 kV

Double-Circuit line from New Apo 330/132/33 kV

substation to the proposed Kuje 132/33 kV

substation.

132 2020

North-Central Abuja West Main Lugbe

Construction of 29 km of a new 132 kV

Double-Circuit line from the proposed Kuje 132/33

kV Substation to West Main (Lugbe) 330/132/33 V

substation.

132 2020

LAGOS/OGUN TRANSMISSION PROJECTS (JICA)

South-West Lagos New Abeokuta (Kobape) Ejio (Arigbajo) – New Abeokuta (Kobape) 132 kV

D/C Transmission Line (37.8km). 132 2022

South-West Lagos Ejio (Arigbajo) Olorunsogo – Ejio (Arigbajo) 330 kV D/C

Transmission Line (12.9km). 330 2022

South-West Lagos Ikeja West Ejio (Arigbajo) – Ikeja West/Osogbo 330 kV D/C

Turn-in-out (5.9km). 330 2022

South-West Lagos Ejio (Arigbajo) Likosi (Ogijo) - Aribajo D/C Transmission Line

(43.7km). 330 2022

South-West Lagos Shagamu

132 kV Quad Line (2.3km) from Likosi (Ogijo) –

Existing Ikorodu/Shagamu 132 kV 2x D/C

Transmission Line

132 2022

South-West Lagos Abule Oba (Redeem) 132 kV D/C Transmission Line (10.3km) from Likosi

(Ogijo) – Abule Oba (Redeem). 132 2022

South-West Lagos Ikeja West MAKOGI (MFM) – Existing Benin (Omotosho)/Ikeja

West 330 kV 2 x D/C Transmission Line (4.2km). 330 2022

South-West Lagos Ajegunle

(New Agbara)

Ejio (Arigbajo) – Ajegunle (New Agbara) 330 kV D/C

Transmission Line (30.6km). 330 2022

South-West Lagos Agbara Ajegunle (New Agbara) – Agbara 132 kV D/C

Transmission Line (20.8km). 132 2022

South-West Lagos Badagry Ajegunle (New Agbara) – Badagry 132 kV D/C

Transmission Line (34.2km). 132 2022

PROPOSAL FOR NORTH-EAST TRANSMISSION INFRASTRUCTURE PROJECT TO BE FINANCED BY AfDB

North-East Bauchi Maiduguri - Manguno - Marte -

Dikwa - Bama

Construction of a new 321km, 132 kV

Double-Circuit Line Between Maiduguri - Manguno -

Marte - Dikwa -Bama.

132 after

2020

North-East Bauchi Maiduguri - Bama - Goza - Gulak

Construction of a new 165km, 132 kV

Double-Circuit Line from Maiduguri - Bama - Goza -

Gulak.

132 after

2020

North-East Bauchi Mayo Belwa - Jada - Ganye Construction of a new 78km, 132 kV Double-Circuit

Line from Mayo Belwa - Jada - Ganye. 132

after

2020

North-East Bauchi Biu - BuniYadi - Damaturu Construction of a new 134km, 132 kV

Double-Circuit Line from Biu - BuniYadi - Damaturu. 132

after

2020

North-East Bauchi Dambua - Chibok - Uba - Mubi Construction of a new 130km, 132 kV

Double-Circuit Line from Dambua - Chibok - Uba - 132

after

2020

Page 15: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-14

Area Region Location Description Voltage

(kV)

in

operation

by

Mubi.

North-East Bauchi Mayo Belwa - Jada - Ganye Construction of a new 78km, 132 kV Double-Circuit

Line from Mayo Belwa - Jada - Ganye. 132

after

2020

North-East Bauchi Biu - BuniYadi - Damaturu Construction of a new 134km, 132 kV

Double-Circuit Line from Biu - BuniYadi - Damaturu. 132

after

2020

North-East Bauchi Dambua - Chibok - Uba - Mubi

Construction of a new 130km, 132 kV

Double-Circuit Line from Dambua - Chibok - Uba -

Mubi.

132 after

2020

North-West Kaduna

Construction of Quad 330 kV on

Kaduna-Kano 330 kV Single DC

Transmission Line

Construction of Double-Circuit 330 kV Quad

Conductor Kaduna-Kano Transmission line. 330

after

2020

North-West Kaduna Zaria

Turn-in Turn-out and Installation of 2x150 MVA

330/132/33 kV Transformer, 6x330 kV bay

extension, 2x60MVA 132/33 kV Transformer,

associated 132 kV line bays and 6 number 33 kV

feeder bays at Zaria.

330 after

2020

North-West Kaduna Millennium City Kaduna

Turn-in Turn-Out and Installation of 2x150 MVA

330/132/33 kV Transformer, 2 x330 kV bay

extension and 2x60MVA 132/33 kV Transformer

and 2x3number associated outgoing 33 kV feeders.

330 after

2020

North-West Kaduna Rigasa town, Kaduna

Turn-in Turn-out and Installation of 2x60 MVA

132/33 kV Transformer and 5 number outgoing 33

kV feeders.

132 after

2020

North-West Kaduna Jaji, Kaduna

Turn-in Turn-out and Installation of 2x60 MVA

132/33 kV Transformer and 6 number outgoing 33

kV feeders.

132 after

2020

South-South Benin Reconstruction of Delta to Benin

330 kV Transmission Line

Reconstruction of one of Delta-Benin 330 kV

Transmission Line Double-Circuit to Quad

Conductor 330 kV Double-Circuit Line.

330 after

2020

South-South Port

Harcourt

Reconstruction of Alaoji to Onitsha

330 kV Transmission Line

Double-Circuit Alaoji-Ihiala-Onitsha to Quad

conductor 330 kV transmission line. 330

after

2020

South-South

Ahoda,

Gilili and

Sapele

Environmental Impact Assessment

and Resettlement Action Plan and

Payment of Compensation

Double-Circuit (DC) 132 kV Ahoda-Gilli-Gilli DC

Transmission Line and 2x60MVA 132/33 kV

Transformer at Gilli plus associated 6 number

outgoing 33 kV feeders and DC 132 kV Sapele -

Odilli DC Transmission Line and 2x60MVA

132/33 kV Transformer at Gilli plus associated 6

number outgoing 33 kV feeders.

132 after

2020

North-East `Bauchi

Environmental Impact Assessment

and Resettlement Action Plan and

Payment of Compensation

132 kV line and associated substations:

Maiduguri-Manguno-Marte-Dikwa-Bama,

Maiduguri-Bama-Gwoza;

Hadeja-Nguru-Gashua-Damaturu; Biu-Miringa-Buni

Yadi-Damaturu; Dambua-Chibok-Askira-Uba-Mubi;

Mayo Belwa-Jada-Ganye

132 after

2020

PROPOSED NETAP PACKAGE AS OF 03 APRIL, 2017 - $486 MILLION

South-West Osogbo Osogbo- Offa -Ganmo - Ilorin Reconductoring of 150km, 132 kV Line Between

Osogbo-Offa/Omuaran to Ganmo and Ilorin T.S. 132 2020

South-West Osogbo Ayede - Shagamu

Reconstruction and Conversion of SC to

Double-Circuit of Ayede -Ajebo-Ishara-Shagamu 132

kV Line (54km) and Creation of Additional Bays 132

132 2020

Page 16: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-15

Area Region Location Description Voltage

(kV)

in

operation

by

kV Line Bays at Ayede, Ajebo, Ishara and Shagamu.

South-West Osogbo Osogbo- Ife/Ilesha

Reconstruction and Conversion to Double-Circuit of

Osogbo-Ife/Ilesha 132 kV Line (39.21 km) and

Osogbo-Ilesha 132 kV Line Tie-Off (22.1km) and

Creation of Additional 132 kV Line Bays at Osogbo

and Ilesha.

132 2020

South-East Port

Harcourt AFAM - PH Main

Reconstruction of Existing Double 132 kV Line

Circuit to 4 x 132 kV Line Circuit Using the Same

Right of Way from AFAM to Port Harcourt Main

(37.8km) and Creating Additional 3 x 132 kV Line

Bays.

132 2020

South-East Port

Harcourt PH Main - PH Town

Reconductoring of 132 kV Double-Circuit of Port

Harcourt Main to Port Harcourt Town 132 kV Line

(6km).

132 2020

North-West Kaduna Kumbotso - Hadelja Reconductoring of Kumbotsho- Hadeji 132 kV Line

(165 km). 132 2020

North-West Kaduna Kumbotso - Kankia Reconductoring of Kumbotsho- Kankia 132 kV Line

(100 km). 132 2020

South-East Enugu Onitsha - Oji River

Reconductoring of Onitsha- Orji 132 kV Line (87km)

with Turn-In- Turn-Out Tower at Nibo (Agu Awka) in

Awka 132 kV Substation.

132 2020

South-East Enugu Alaoji to Aba Town

Reconductoring of Alaoji - Aba Town Double-Circuit

132 kV line (8km) Including Rehabilitation of Two

Nos. Towers along the Line.

132 2020

South-South Benin Irrua - Benin Reconductoring of Irrua - Benin 132 kV line (81 km). 132 2020

South-South Benin Irrua - Okpila Reconductoring of Irrua- Okpilai 132 kV line (43

km). 132 2020

South-South Benin Okpila - Okene Reconductoring of Okpilai - Okene 132 kV line (65

km). 132 2020

South-South Benin Ajakuta-Okene Reconductoring of Ajakuta- Okene 132 kV line (60

km). 132 2020

North-East Bauchi Gombe-Biu-Damboa-Maiduguri

Reconductoring of the Entire Route Length from

Gombe -Dadin Kowa- Biu -Damboa - Maiduguri 132

kV line of 356 km Route Length.

132 2020

NORTHERN CORRIDOR TRANSMISSION PROJECT 2 (AFD2)

North-West Shiroro Kainji - Birnin-Kebbi 330 kV

Double-Circuit (DC) Line (310km)

330 kV DC Transmission Line Kainji-Birnin-Kebbi

(following the existing ROW of the SC 330 kV line)

and 4x 330 kV bay extension at B/ Kebbi and 2 x 330

kV bay extension at Kainji

330 after

2020

North-West Shiroro Birnin-Kebbi-Sokoto 330 kV

Double-Circuit (DC) Line (130km)

(1) Birnin-Kebbi-Sokoto 330 kV DC Transmission

Line on the existing 132 kV Birnin-Kebbi Sokoto

ROW and reconducting the existing 132 kV

Single-Circuit Birnin-Kebbi Line to double its

capacity

330 after

2020

North-West Kaduna Katsina-Daura-Gwiwa-Minjibir-Kura

(234KM)

Construction of length of 330 kV DC Twin line

between Katsina-Daura-Gwiwa-Jogana- Kura. 330

after

2020

North-Central Shiroro Lambata (Mina-Suleja Rd)

Turn-in Turn-out Mina - Suleja 132 kV DC and

Construction of 1 x 60 MVA 132/33 kV Complete

substation.

132 after

2020

North-West Shiroro Fakon Sarki-Argungu

Turn-in Turn-Out on Brinin Kebbi-Sokoto 132 kV

Line and Construction of 2 x 60MVA 132/33 kV

Complete substation.

132 after

2020

Page 17: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-16

Area Region Location Description Voltage

(kV)

in

operation

by

North-West Shiroro Yelwa- Yawuri

Construction of 1 x 60MVA 132/33 kV Complete

substation and High-Voltage Switchgears and

Associated Equipment.

132 after

2020

North-Central Shiroro Birnin Gwari

Construction of 1 x 60MVA 132/33 kV Complete

substation and High-Voltage Switchgears and

Associated Equipment.

132 after

2020

North-West Kaduna Daura-Katsina State

Installation of 2x150MVA 330/132/33 kV

Double-Circuit Substation and with associated 132

kV bay extension and Installation of 2x60MVA

132/33 kV transformers, 6number outgoing 33 kV

feeder bays.

330 after

2020

North-West Kaduna Jogana-Kano

Installation of 2x150MVA 330/132/33 kV

Double-Circuit Substation and with associated 132

kV bay extension and Installation of 2x60 MVA

132/33 kV transformers, 6number outgoing 33 kV

feeder bays.

330 after

2020

North-West Shiroro 330 kV Sokoto Transmission

Substation

Installation of 2x150 MVA 330/132/33 kV

Transformers at Sokoto New 330 Double-Circuit

Substation and with associated 132 kV bay

extension and Installation of 2 x 60 MVA 132/33 kV

transformers, 6 number outgoing 33 kV feeder

bays.

330 after

2020

North-Central Shiroro

Shiroro –Kaduna (Mando) 330 kV

Lines 1 & 2 SC Transmission Lines

(96km)

Reconstruction and upgrading of two Single-Circuit

330 kV Transmission Lines 1 & 2 from Shiroro PS to

Mando (Kaduna) to a two Double-Circuit, Quad

conductor Shiroro-Mando (Kaduna) Transmission

lines 1 and 2. The line bay extension at Mando and

Shiroro.

330 after

2020

North-East Bauchi Bauchi 330 kV Transmission

Substation (2km)

Turn-in-out of the existing 330 kV SC Jos-Gombe

line at Bauchi and installation of 2x150 MVA

330/132/33 kV Transformers with associated 132

kV bay extension and 2 x 60 MVA 132/33 kV

transformers, 6 number outgoing 33 kV feeder

bays.

330 after

2020

Source: JICA Study Team

Some of these projects are critical to operate the system in 2020 and if a load exceeding 9 GW is to be served adequately, these projects will have to be expedited, targeting completion by 2020 or as soon as possible after 2020.

7-2-2-3 Transmission System Expansions Financed by AFD

A financing agreement is in place to improve the transmission system in the Greater Abuja area.

The transmission system expansions included in the ADF-financed project will strengthen the 330/132 kV system supplying power to the capital Abuja. A new 132 kV Double-Circuit transmission line (172 km) between New Apo 330/132/33 kV Substation and the planned Lafia 330 kV Substation will establish a third infeed to the Abuja 132 kV ring allowing power supply from the power plants in the Delta Area and the planned Mambilla Hydro Power Plant.

Page 18: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-17

These network expansions are planned to be commissioned in 2020, see Table 7-2.2.

A detailed list of the transmission system expansions with their cost as estimated by TCN is shown in Annex 7.2e1. The planned transmission lines and substations are shown in Annex 7.1 on a map of Nigeria.

7-2-2-4 Transmission System Expansions to Be Financed by JICA

To improve the transmission system operation and reliability of the transmission network in the Lagos region, there are plans to install new transmission lines and substations financed by JICA, which is currently preparing a feasibility study.

The planned 330 kV substations Likosi (Ogijo) and Ejio (Arigbajo) will reconfigure the transmission system from single- to Double-Circuit configuration improving rehabilitation during line maintenance and outages. The 330-kV Double-Circuit line to Ejio (Arigbajo) - Ajegunle (New Agbara) and Ajegunle (New Agbara) substation will allow power export to Benin bypassing the heavily loaded Ikeja Substation. The new 132/33 kV substations Abule Oba (Redeem), MAKOGI (MFM) and Badagry will provide additional infeed capacity into the distribution system.

Commissioning of these network expansions is scheduled for 2020, see Table 7-2.2.

Annex 7.2d shows the present network configuration in the Lagos area and the future configuration after commissioning new lines and substations.

A detailed list of the transmission system expansions with their cost as estimated by TCN is shown in Annex 7.2e2.

7-2-2-5 Transmission System Expansions to Be Financed by AfDB

The transmission system in the North-East of Nigeria is not well developed. Many north-eastern cities are not yet connected to the transmission system and rely on local generation only.

To improve the electricity supply from the national grid, TCN is planning to install various 132 kV transmission lines and new 132/33 kV substations as follows:

New Transmission Lines 321 km, 132 kV Double-Circuit Line Between Maiduguri - Manguno - Marte - Dikwa -Bama 165 km, 132 kV Double-Circuit Line from Maiduguri - Bama - Goza - Gulak 78 km, 132 kV Double-Circuit Line from Mayo Belwa - Jada - Ganye 134 km, 132 kV Double-Circuit Line from Biu - BuniYadi - Damaturu 130 km, 132 kV Double-Circuit Line from Dambua - Chibok - Uba - Mubi

132/33 kV Substations New 132/33 kV Manguno Substation, 2 x 60 MVA, Extension of Old Maiduguri 132 kV switchgear by 2 bays, New 132/33 kV Marte Substation, 2 x 60 MVA,

Page 19: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-18

New 132/33 kV Dikwa Substation, 1 x 60 MVA, New 132/33 kV Bama Substation, 2 x 60 MVA, Extension of New Maiduguri 132 kV switchgear by 2 bays, New 132/33 kV Gwoza Substation, 1 x 60 MVA, Extension of Gulak 132 kV switchgear by 2 bays, New 132/33 kV Jada Substation, 2 x 60 MVA, New 132/33 kV Ganye Substation, 2 x 60 MVA, New 132/33 kV Uba Substation, 2 x 60 MVA, New 132/33 kV Chibok Substation, 1 x 60 MVA, New 132/33 kV Biu Substation, 1 x 60 MVA, New 132/33 kV Bunyadi Substation, 1 x 60 MVA, Extension of Damaturu 132 kV switchgear by four bays, New 132/33 kV Kwaya Kusar Substation, 1 x 60 MVA, Extension of Gulak 132 kV switchgear by 2 bays,

In addition to the above, the following lines are planned:

In the North-West planning region of Nigeria there are plans to build a 330-kV Double-Circuit line between Kaduna and Kano, two 330/132 kV substations and two 132/33 kV substations.

In the South planning region, the reconstruction of two 330 kV transmission lines is planned. The 330 kV lines Delta-Benin and Alaoji-Ihiala-Onitsha shall be replaced by Double-Circuit lines with Quad conductors.

Furthermore, environmental impact assessments for various transmission lines are included in the scope.

A detailed list of transmission system expansion measures included in the scope of financing is shown in Annex 7.2e3 with their cost as estimated by TCN.

The planned transmission lines and substations are shown in Annex 7.1 on a map of Nigeria.

7-2-2-6 Transmission System Rehabilitations and Reinforcements/Upgrading to Be Financed by the World Bank

Under the Nigeria - Electricity Transmission Project (NETAP) it is proposed to carry out numerous rehabilitations/reinforcements of existing substations and transmission lines, financed by the World Bank.

The reinforcement and upgrading of substations includes the installation of additional 330/132 kV and 132/33 kV transformers, replacement of existing transformers by units with a higher rated capacity and installation of associated switchgear equipment and control and protection equipment. The rehabilitation measures include replacing high-voltage switchgear and associated equipment as well as control and protection equipment.

The rehabilitation/reinforcement of transmission lines includes mostly reconductoring of lines.

Page 20: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-19

A detailed list of system rehabilitations and reinforcements/upgrading with their cost as estimated by TCN is shown in Annex 7.2e4. The annex shows that the substations and transmission lines are located throughout all the TCN planning regions of Nigeria.

7-2-2-7 Transmission System Expansions to Be Financed by AFD

Under a second financing agreement with AFD, there are plans to build new transmission lines and substations and rehabilitate transmission lines and substations in various northern planning areas of TCN, to improve power transmission in the northern transmission corridor. The scope includes also various rehabilitation measures for substations and transmission lines.

A detailed list of transmission system expansion measures included in the scope of financing is shown in Annex 7.4e5 with their cost as estimated by TCN.

Page 21: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-20

7-3 Criteria to Formulate a Transmission Network Development Plan

7-3-1 Appraisal Criteria for TCN Network Expansions

Each of the main 330 and 132 kV projects has been appraised using ENTSO-E methodology. As such, the benefit of each project is assessed against a number of indicators, ranging from technical and socio-economic issues to their environmental impact.

The analysis has been performed for projects with implementation in the transmission network scheduled for 2025. Applying the ENTSO-E methodology, expected benefits were weighted and individually applied for each project. For this study, the projects were appraised against the following criteria:

Increase of Network Transfer Capacity, estimating the incremental power transfer capacity between two points of the transmission system (MW);

Social and Environmental Impacts, reflecting the level of certainty with respect to the planned commissioning time of the project and its impacts on the environment;

Security of Power Supply, evaluating the project impact on the reliability status of connected parts of the network;

Integration of Renewable Energy Sources (RES), Support for RES integration is defined as the ability of the system to allow the connection of new RES plants and unlock existing and future “green” generation;

Effect on Transmission Losses (Energy Efficiency), comparing losses (in MWs) relevant to scenarios with and without projects (or their specific components);

Technical resilience/system safety margin, evaluating the project influence on overall system reliability;

The radar format graph of Figure 7-3.1 shows, for example, the points scored by certain projects and hence their priority ranking. When comparing for the five projects, the 132 kV Ayade – Ibadan North project has the highest score and thus the highest priority. Other projects are also calculated and prioritized accordingly.

Page 22: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-21

Source: JICA Study Team

Figure 7-3.1 Project Appraisal Criteria and Scores

7-3-2 Methodology Overview

The methodology of the power system analysis is summarized as follows:

7-3-2-1 Definition of the Security Reference Level

The goal of the study is to propose the necessary updates and reinforcements to the TCN power system to achieve secure operation for the system for the period 2020 to 2040. First, the present system model is analyzed, taking into account the recently completed and ongoing TCN and NIPP projects scheduled for completion by 2020. It has also been assumed that certain projects in the Lagos area undertaken by JICA will be completed for the period 2020-2025.

(1) Voltage criteria

The Grid Code of, 2014, v2, states that the System Operator shall endeavor to control the different busbar voltages to be within the voltage control ranges specified in Table 7-3.1:

Table 7-3.1 Voltage criteria

Voltage Level

(kV)

Normal Operation Contingency Operation

Minimum Voltage

(kV) (pu)

Maximum Voltage

(kV) (pu)

Minimum Voltage

(pu)

Maximum Voltage

(pu)

330 kV 280.5 (0.85) 346.5 (1.05) 0.80 1.10

132 kV 112.2 (0.85) 145.2 (1.10) 0.80 1.15

66 kV 62.04 (0.94) 69.96 (1.06) 0.89 1.11

33 kV 31.02 (0.94) 34.98 (1.06) 0.89 1.11

11 kV 10.45 (0.95) 11.55 (1.05) 0.90 1.10

Source: JICA Study Team

0

0.5

1

1.5

2

2.5

3

Increase ofnetwork transfer

capacity

RES integration

Improved securityof supply

Reduction intransmission

losses

Technicalresilience/system

safety margin

Social andEnvironmental

Impacts

330 and 132 kV projects

330 Akangba-Alagbon

330 Ukwaji-Abakaliki

132 Ayede-Ibadan North

132 NewAgbara-Agbara

132 Ibom IPP-Ikot Abasi

Points:

9

10.3

10.8

9.9

10

Page 23: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-22

Under system stress or following system faults, voltages can be expected to deviate outside the above limits by a further +/-5% (excluding transient and sub-transient disturbances).

7-3-2-2 Thermal Criteria

The maximum permissible thermal overloading for all branches at 330 and 132 kV level is 100% of the nominal rating (Rate A) under normal (N) system conditions and 110% of the nominal rating under contingency (N-1) system conditions.

7-3-2-3 Policy of the Power System Analysis

(1) Execution of analyses on the 2020 model

The initial analysis relates to the static security assessment. Using the outcome of this analysis, an initial reinforcement list and recommendations for new lines and transformers are provided.

(2) Execution of the analysis on the 2025, 2030, 2035 and 2040 models

Considering the recommendations and reinforcements provided in b) already implemented in the 2020 network model, the same analysis is carried out on the 2025, 2030, 2035 and 2040 scenarios. The reinforcements and recommendations for these years constitute the outcome of this analysis.

The proposed transmission expansion projects from 2020 to 40 are detailed in the following sections.

Five milestone study years have been selected to cover the planning horizon of the Master Plan: 2020, 2025, 2030, 2035 and 2040.

7-3-3 Load Demand

The load demand in each of the DisCos areas in Nigeria is summarized in Table 7-3.2

In the 2020 network configuration, the assumed total demand is 9,023 MW, to closely match the validated DisCos load demand, as presented by the 11 DisCos in the workshop of January 2017 in Abuja. Thereafter, the load demand to be served depends on two factors: (a) the rate of increase in forecast demand as presented in Section 5 and, more importantly, (b) the limits of the generation expansion plan.

The maximum load demand that can be realistically supplied will, accordingly, have to follow the development of the generation planning schedule and will be limited by associated financial and time constraints.

The total demand that can be served includes the export requirements to neighboring countries.

Table 7-3.2 Load demand per DisCo

DisCo 2020 incr 2025 incr 2030 incr 2035 incr 2040

1-Ikeja 1,166 76% 2,058 42% 2,921 21% 3,536 22% 4,300

2-Ibadan 1,104 107% 2,285 43% 3,267 24% 4,054 25% 5,055

3-Abuja 865 169% 2,329 50% 3,500 26% 4,398 21% 5,336

4-Benin 954 94% 1,852 34% 2,489 17% 2,901 17% 3,391

5-Kaduna 495 136% 1,169 81% 2,117 20% 2,533 20% 3,045

Page 24: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-23

DisCo 2020 incr 2025 incr 2030 incr 2035 incr 2040

6-Jos 309 109% 646 60% 1,035 4% 1,079 5% 1,131

7-Enugu 924 81% 1,668 19% 1,979 3% 2,037 4% 2,112

8-Port Harcourt 794 122% 1,762 35% 2,385 17% 2,802 18% 3,305

9-ΕΚΟ 1,087 69% 1,837 22% 2,240 6% 2,382 5% 2,512

10-Kano 708 121% 1,565 64% 2,570 38% 3,549 13% 4,023

11-Yola 230 131% 532 77% 942 54% 1,448 16% 1,680

Country (MW) 8,636 105% 17,703 44% 25,447 21% 30,719 17% 35,890

Export (MW) 387 1,540 1,830 2,000 2,000

Total Load (MW) 9,023 113% 19,243 42% 27,277 20% 32,719 16% 37,890

Source: JICA Study Team

The increase in load that can be supplied by the planned generation for the period 2020-2040 is shown in Figure 7-3.2. The development of the generation system and associated demand can thus be referred to as the 9 GW in 2020, 18 GW in 2025, 26 GW in 2030, 31 GW in 2035 and 36 GW in 2040 respectively.

Source: JICA Study Team

Figure 7-3.2 Increase in Served Nigerian Load 2020-2040

Based on the installed generation, the maximum generation that can be made available to supply the peak demand is calculated as shown in the following Table 7-3.3 and Figure 7-3.3.

The generation expansion assumed for this study, for an average exceeding 2 GW per year for the period 2020-2034, is considered rather optimistic.

Table 7-3.3 Installed and available generation for 2020, 2025, 2030, 2035 and 2040

2020 2025 2030 2035 2040

Installed generation (GW) 14.1 29.2 41.2 51.3 54.9

Proposed candidates (GW) 0.7 9.1 18.5 28.6 32.4

Less PV (not available during peak load) in GW -1.08 -1.31 -2.11 -2.11 -2.11

Less a% of proposed candidates (in% and GW)

0% 20% 20% 20% 20%

0.0 -1.8 -3.7 -5.7 -6.5

Less a min% on planned and unplanned outages (in% and GW)

20% 20% 20% 20% 20%

-2.6 -5.2 -7.1 -8.7 -9.3

Available generation (max./rated) in GW 10.4 20.9 28.3 34.8 37.1

Available generation (running) during peak demand (GW)

9.9 19.8 26.9 33.4 35.6

Available generation (max), as% of the total (installed+planned+proposed).

74% 71% 69% 68% 67%

Source: JICA Study Team

8636

17703

25447

30719

35890

0

5000

10000

15000

20000

25000

30000

35000

40000

2015 2020 2025 2030 2035 2040 2045

Supplied Nigerian Load MW

Page 25: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-24

Source: JICA Study Team

Figure 7-3.3 Installed and Available Generation for 2020, 2025, 2030, 2035 and 2040

7-4 Expansion Plan for 2020

7-4-1 Static Security Analysis, Year 2020

7-4-1-1 Network Configuration

The network configuration for 2020 is shown in the single-line diagrams of Annexes 7.4.2 and 7.4.1. The SLDs include all the ongoing and committed TCN, NIPP and JICA new projects, assuming completion in all cases by 2020.

The new transmission expansion projects identified on the basis of the load-flow studies carried out are shown on the map of Annexes 7.4.3 and 7.4.4.

The input data used and the assumptions made with regard to the load demand, generation capacities and expansion, transmission lines and reactive power compensation equipment are detailed in the following sections.

Figure 7-4.1 below shows the 330-kV transmission system in 2020 (red lines), assuming all the ongoing

Page 26: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-25

and committed TCN, NIPP and certain JICA new projects will be completed by 2020.

The diagram shows the running generation and load in each DisCo area and the power flows between DisCos.

Dotted lines and lines in magenta denote future projects beyond 2020, which were analyzed in the study of the corresponding year and reported accordingly in this report.

Source: JICA Study Team

Figure 7-4.1 330 kV Transmission System 2020

7-4-1-2 Load Demand

In the 2020 network configuration the assumed total demand is 9,023 MW, closely matching the validated DisCos load demand, as presented by the 11 DisCos in the workshop of January 2017 in Abuja.

The load in each of the DisCo areas in Nigeria is shown in Figure 7-4.2 and summarized in Table 7-4.1.

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1194 MW

8 TO 4 563 MW

3 TO 2 223 MW

7 TO 4 792 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 179 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 633 MW

G

G

G

DISCOS

2 TO 1 1242 MW

4 TO 3 0 MW

G

G

Diagram created using'D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\2020\DP 2020 model Yash.sav'

'D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\Diagrams-SLDs-Use Power Exch only\Power Exchanges 330kV model Discos Yash.sld'

GG

TCN 2020 MODEL

DISCO DEMANDWED, JUL 18 2018 15:15

3 TO 5 1009 MW

1 TO 9 284 MW

GG

5 TO 6 -64 MW

10 TO 6 0 MW

5 TO 10 0 MW

6 TO 11 218 MW

G

4 TO 9 506 MW

4 TO 1 761 MW

G

G

83004IKOT-EKPENE_

73006UGWUAJI_3

73001ONITSHA 3

73005ASABA_3

73003MAKURDI_3

1

1

33007GWAGW BB1

23005AKURE 3

23001OSOGBO 3

1

2

3

23003GANMO 3

23002OMOTOSHO3

33002BKEBBI 3

1

2

13003IKEJA W 3

13005OLORUNSOGO3

13029OGIJO 3

13030MFM 3

1

0 50

2

0 50

SW

0

63007DAMATURU 3

63005MAIDUGURI 3

2

0

69

13002EGBIN 3

13025EPE 3

13000AJA 3

13031OKO_OBA_313034

LEKKI 330

13027ALAGBON_3

13001AKANGBA 3

1

33001KATAMPE 3

83007ONNIE_3

1

83002ALAOJI 3

83010IKOT ABASI_3

83000AFAM IV 3

83005OWERRI_3

73004ALIADE_3

63001JOS 3

73010ABAKALIKI_3

0 72

63002YOLA 3

53001KANO 3

2

3

SW

0

53005KANO_NEW330

53003ZARIA_330

53000KADUNA 3

53002KATSINA 3

13032NEW_AGBARA_3

1260

1

23000AYEDE 3

43000AJAOKUTA 3

43008LOKOJA _3

43002BENIN 3

43001ALADJA 3

43003DELTA IV 3

43004SAPELE 3

43011B_NORTH_3

43005GEREGU

43009OBAJANA_3

83006EGBEMA_3

83009OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000GOMBE 3

2

1 2

33020SHIRORO 3

33008WESTMAIN_3

73000NHAVEN 3

53004FUNTUA 3

53007TMAFARA3

53008GUSAU 3

33021KAINJI 3

33005KAINJI G .S.3

33003JEBBA T.S.3

33009ZUNGERU

33004JEBBA G .S.3

33022APO_NEW 3

33023LAFIA 3

63003BAUCHI 3

63008MAMBILA 3

43006EFFURUN 3

73002OKPAI 3

73030IHIALA 3

23006IBADAN

13026OKE_ARO_3

53012DUTSE 3

53011KAZAURE 3

1

2

0 72

63009WUKARI

33006SOKOTO 3

83001ALAOJI NIPP3

73007NNEWI 3

0

32 9

30

338

1

2

1

13004SAKETE 3

13028ARIGBAJO

63006JALINGO_3

33010ZABORI

SW 0

13012PARAS

63015MAYOBELWA

43007AZURA

43010ETHIOPE

13035IJORA 3

187

1

32021NIAMEY 1

1

40

1

52010GAZOUA 1

SW

34

Export 387 MW

Total Generation 9417 MWNigeria Load 8637 MW

Genera tion from H PP 1322 MW

Generation per DISCO Loads per DISCO

3-Abuja 866 MW

7-Enugu 924 MW

2-Ibadan 1104 MW

1-Ikeja 1166 MW

6-Jos 309 MW

5-Kaduna 495 MW

10-Kano 708 MW

11-Yola 230 MW

3-Abuja 1750 MW

4-Benin 1775 MW

9-Eko 0 MW

7-Enugu 796 MW

2-Ibadan 476 MW

1-Ikeja 1110 MW

6-Jos 105 MW

5-Kaduna 194 MW

10-Kano 9 MW

8-Pt Harco 3202 MW

11-Yola 0 MW

Genera tion from PV 0 MW

Total Load 9024 MW

9-Eko 1087 MW

8-Pt Harco 794 MW

4-Benin 954 MW

1

1

1

1

1

1

Page 27: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-26

The total demand includes the export requirements to neighboring countries as follows:

To Benin (Sakete, 330 kV): To Niger (Niamey, 132 kV): To Niger (Gazoua, 132 kV):

The export requirements modeled for 2020, 2025, 2030 and 2035 were based on information provided by TCN and the results of earlier WAPP studies and reports.

In the 2020 load model representation in PSS/E, a pessimistic power factor of around 0.85 has been assumed, despite the new Grid Code requirements calling for a pf of 0.95, as it is believed that most users at distribution level are not in full compliance yet with this requirement. It is noted that the Grid Code requirements (ref. article 15.6 on Demand power factor corrections and 16.7 on provision of voltage control) states that The Off-takers shall maintain a power factor of at least 0.95 at the Connection Point.

Accordingly, the loads in the 2020 models are based on a pf of 0.85, those in the 2025 model on a still-conservative pf of 0.92 and only the 2030 loads have a pf of 0.95.

Table 7-4.1 Load demand per DisCo

SCO Load (MW)

1-Ikeja 1,166

2-Ibadan 1,104

3-Abuja 866

4-Benin 954

5-Kaduna 495

6-Jos 309

7-Enugu 924

8-Port Harcourt 794

9-Eko 1,087

10-Kano 708

11-Yola 230

Total for Nigeria 8,637

Export 387

Total load 9,024

Source: JICA Study Team

The modeled loads of individual substations within each DisCo are detailed in Annex 7.4.5.

The total generation required to meet the load in Nigeria is 9,421 MW and total losses are 397 MW.

7-4-1-3 Generation Capacity

The ratings of the conventional generating units in Nigeria for 2020 are shown in Table 7-4.2.

Page 28: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-27

Table 7-4.2 Ratings of power generating units (Pmax)

Station Name Company Name Primary Energy

Resource

Commercial Operation

Date

No of Units

Gross Unit

Capacity (MW)

Gross Plant

Capacity (MW)

Total 2020

Existing generation capacity

AFAM IV - GT13-18 AFAM POWER PLC. GAS 1982 6 75 450 150

AFAM V - GT19-20 AFAM POWER PLC. GAS 2002 2 138 276 276

AFAM VI - GT11-13 SHELL ROT GAS 2009 3 166 498 450

AFAM VI - ST1 SHELL ROT STEAM 2010 1 230 230 200

ALAOJI – NIPP NIPP GAS 2013 4 120 480 480

CALABAR / ODUKPANI NIPP NIPP GAS 2015 5 113 565 338

DELTA II - GT3-8 TRANSCORP POWER LTD GAS 2002 6 24 143 123

DELTA III - GT9-14 TRANSCORP POWER LTD GAS 2005 6 24 143 128

DELTA IV - GT15-20 TRANSCORP POWER LTD GAS 1990 6 99 594 630

EBUTE BARGE (CYREX) AES AES / CYREX ENERGY LTD GAS 2002 9 31 279 0

EGBIN EGBIN POWER PLC STEAM 1985 6 220 1,320 1,320

GBARAIN - GT2 NIPP NIPP GAS 2016 1 113 113 113

GEREGU FGN 1 GEREGU GENERATION

COMPANY LTD GAS 2007 3 138 414 414

GEREGU NIPP 1 NIPP GAS 2013 3 148 444 220

IBOM 1 IBOM POWER GAS 2009 1 42 42 0

IBOM 1 IBOM POWER GAS 2010 1 114 114 114

IBOM 1 IBOM POWER GAS 2016 1 40 40 0

IHOVBOR (EYAEN) NIPP NIPP GAS 2013 4 113 452 339

JEBBA POWER HOLDING CO OF

NIGERIA HYDRO 1983 6 101.15 606.9 607

KAINJI - G11-12 POWER HOLDING CO OF

NIGERIA HYDRO 1976 2 100 200 200

KAINJI - G5-6 POWER HOLDING CO OF

NIGERIA HYDRO 1968 2 120 240 240

KAINJI - G7-10 POWER HOLDING CO OF

NIGERIA HYDRO 1978 4 80 320 160

OKPAI IPP NIGERIAN AGIP OIL CO GAS 2005 2 165 330 300

OKPAI IPP NIGERIAN AGIP OIL CO STEAM 2005 1 140 140 140

OLORUNSOGO I PACIFIC ENERGY GAS 2007 8 42 335 335

OLORUNSOGO II NIPP NIPP GAS 2011 4 120 480 240

OLORUNSOGO II NIPP NIPP STEAM 2012 2 120 240 120

OMOKU IPP FIRST INDEPENDENT

POWER GAS 2006 6 25 150 150

OMOTOSHO I OMOTOSHO ELECTRIC

ENERGY COMPANY GAS 2007 8 42 335 304

OMOTOSHO II NIPP NIPP GAS 2012 4 120 480 240

PARAS ENERGY PARAS ENERGY &

NATURALS RES. DEV. LTD GAS 2016 9 9 79 170

RIVERS IPP FIRST INDEPENDENT

POWER GAS 2012 1 191 191 191

SAPELE SAPELE POWER PLC STEAM 1978 6 88 528 400

SAPELE OGORODE 1 NIPP NIPP GAS 2011 4 113 454 454

SHIRORO SHIRORO HYDRO ELECTRIC HYDRO 1990 4 150 600 600

TRANS-AMADI IPP FIRST INDEPENDENT

POWER GAS 2010 4 25 100 100

Subtotal 1-Existing generation capacity 10,098

Additional generation capacity by 2020

AFAM III

GAS 2018 8 30 240 240

Page 29: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-28

Station Name Company Name Primary Energy

Resource

Commercial Operation

Date

No of Units

Gross Unit

Capacity (MW)

Gross Plant

Capacity (MW)

Total 2020

AFRINERGIA SOLAR AFRINIGER SOLAR PV 2020 50 50

ANJEED KAFACHAN SOLAR

IPP

ANJEED KAFACHAN SOLAR

IPP PV 2020 100 100

AZURA

GAS 2018 3 150 450 450

CT COSMOS CT COSMOS PV 2020 70 70

EGBEMA I - NIPP NIPP GAS 2018 1 113 113 113

EGBEMA I - NIPP NIPP GAS 2019 1 113 113 113

EGBEMA I - NIPP NIPP GAS 2019 1 113 113 113

EN Consulting & Projects -

Kaduna PV 2020 100 50

GBARAIN / UBIE I NIPP GAS 2017 1 113 113 113

GURARA SALINI NIGERIA LTD HYDRO 2017 2 15 30 30

IBOM II

GAS 2020 4 138 552 276

KADUNA IPP KADUNA IPP GAS 2019 1 215 215 215

KASHIMBILLA

HYDRO 2019 40 40 40

KVK POWER NIGERIA LTD KVK POWER NIGERIA LTD PV 2020 55 55

LR AARON SOLAR POWER

PLANT LR AARON SOLAR PV 2019 100 100

MABON - DADIN KOWA MABIN LTD. HYDRO 2018 1 39 39 39

MIDDLE BAND SOLAR MIDDLE BAND SOLAR PV 2020 100 100

MOTIR DUSABLE MOTIR DUSABLE LTD PV 2020 100 100

NIGERIA SOLAR CAPITAL

PARTNERS

NIGERIA SOLAR CAPITAL

PARTNERS PV 2020 100 100

NOVA SCOTIA POWER Nova Scotia Power

Development Ltd PV 2018 80 80

NOVA SOLAR NOVA SOLAR POWER LTD PV 2018 100 100

OKPAI IPP II - AGIP (NNPC

POWER BUSINESS PLAN) NIGERIAN AGIP OIL CO GAS 2020 2 150 300 300

OKPAI IPP II - AGIP (NNPC

POWER BUSINESS PLAN) NIGERIAN AGIP OIL CO STEAM 2020 1 150 150 150

OMOKU - NIPP NIPP GAS 2018 1 113 113 113

OMOKU - NIPP NIPP GAS 2019 1 113 113 113

ORIENTAL

PV 2020 50 50

PAN AFRICA SOLAR PAN AFRICA SOLAR LTD PV 2019 75 75

QUAINT ENERGY SOLUTIONS QUAINT ENERGY

SOLUTIONS PV 2019 50 50

ZUNGERU

HYDRO 2019 4 700 700 700

Subtotal 2-Additional generation capacity by 2020 4,198

Total by 2020 14,296

Source: JICA Study Team

The PV plants shown in Table 7-4.3, are planned to be installed mainly in northern Nigeria and are most likely to go into operation by 2020.

Table 7-4.3 PV plants in operation by 2020

PN Plant Location Installed Capacity (MW)

Pan Africa Solar Kankia 75

Nova Solar Katsina 100

LR Aaron Power Abuja/Gwangwalada 100

Nova Scotia Dutse/Jigawa 80

Page 30: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-29

PN Plant Location Installed Capacity (MW)

KVK Power Sokoto 55

Quaint Power/Energy Kaduna 50

Anjeed Kafanchan Kafanchan 100

Nigeria Solar Capital Partners Gombe/Bauchi 100

Motir Dusable Oji 100

Afrinergia Solar Karu-Keffi 50

CT Cosmos Jos/Makeri/Pankshin 70

Oriental Dutse 50

EN Consulting-Kaduna Kaduna-Zaria 50

Middle Band Solar Lokoja 100

Source: JICA Study Team

7-4-1-4 Study Cases 2020

Four scenarios, as shown in Table 7-4.4 have been studied for 2020. The focus was on the two cases, (Dry Season Peak and Dry Season Off-Peak), which capture the extreme combinations of generation and load. Other scenarios, such as Wet Season Peak and Wet Season Off-Peak, are less onerous, as it has emerged that their requirements are covered by the extreme case studied:

Table 7-4.4 2020 study cases

Case Description Generation Load (MW)

Dry Season Peak

DP

Dry

Night

Peak Load

Dry-Reduced HPP generation (1,322 MW)

No PV generation

Increased requirement from GTs

Peak load

(night)

8637 +

export (387)

Wet Season

Peak

WP

Wet

Night

Peak Load

Wet-Normal HPP generation (2,100 MW)

No PV generation

Increased requirement from GTs

Peak load

(night)

8637 +

export

Dry Season

Off-Peak

DOP

Dry

Day

Off-Peak Load

Dry-Reduced HPP generation (1,100 MW)

PV generation (400 MW)

Off-Peak

load (day)

7340+

export (387)

Wet Season

Off-Peak

WOP

Wet

Day

Off-Peak Load

Wet-Normal HPP generation (2,100 MW)

PV generation (400 MW)

Off-Peak

load (day)

7340 +

export (387)

Source: JICA Study Team

7-4-2 2020 Base Case Load-flow Results

The load-flow results are shown in Annexes 7.4.2 and 7.4.6 to 7.4.9

In the base case (N-0) load-flow calculations the following observations are made:

7-4-2-1 Power Flows Between DisCos and Regions

The diagram of Figure 7-4.1 and the SLD in Annex 7.4.1 indicate the power flows between the 11 DisCos areas in Nigeria using green arrows, for general peak load and generation case. The DisCos are:

1-Ikeja 5-Kaduna 9-Eko 2-Ibadan 6-Jos 10-Kano 3-Abuja 7-Enugu 11-Yola 4-Benin 8-Port Harcourt

Page 31: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-30

The Nigeria planning regions are:

1-Lagos 5-Kaduna 9-Abuja (July 2018~) 2-Osogbo 6-Bauchi 3-Shiroro 7-Enugu 4-Benin 8-Port Harcourt

The generation (installed and running) and the load in each DisCo are summarized in Table 7-4.5 and Figure 7-4.2. The running generation is approximately 74% of the total installed capacity.

Table 7-4.5 Running generation and load in different areas (DisCos)

Region

Running Generation

(MW)

Load

(MW)

Generation deficit/surplus

(MW) Remarks

1-Ikeja 735 1,166 -431 Generation deficit

2-Ibadan 476 1,104 -628 Generation deficit

3-Abuja 1,979 866 1,113 Generation surplus

4-Benin 1,775 954 821 Generation surplus

5-Kaduna 344 495 -151 Generation deficit

6-Jos 105 309 -204 Generation deficit

7-Enugu 796 924 -128 Generation deficit

8-Port Harcourt 3,202 794 2,408 Generation surplus

9-Eko 0 1,087 -1,087 Generation deficit

10-Kano 9 708 -699 Generation deficit

11-Yola 0 230 -230 Generation deficit

Total for Nigeria - 8,637 -

Export - 387 -

Totals 9,421 9,024 397 (losses)

Source: JICA Study Team

Source: JICA Study Team

Figure 7-4.2 Generation and Load per DisCo

Ikeja Ibadan Abuja Benin Kaduna Jos Enugu P Harc Eko Kano YolaTotalfor

NigeriaExport

Totals,incl

export

Run Genaration 735 476 1979 1775 344 105 796 3202 0 9 0 9421

Load 1166 1104 866 954 495 309 924 794 1087 708 230 8637 387 9024

Gen deficit/surplus -431 -628 1113 821 -151 -204 -128 2408 -1087 -699 -230 397

-1500

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

MW

Page 32: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-31

The general voltage profile is shown in Figure 7-4.3, with blue and red indicating relatively low and high voltages respectively. Lagos, Osogbo and Kaduna are clearly areas with low voltages encountered due to high demand, insufficient local generation, voltage drop in radial feeders and overloaded 132 kV lines and 132/33 kV transformers, even in some areas with high generation.

Source: JICA Study Team

Figure 7-4.3 Voltage Profile of 330, 132 and 33 kV Systems

It can be seen that:

The generation is mainly concentrated in the South (thermal stations in Port Harcourt, Enugu, Benin and Lagos) and Central West (hydro stations of Jebba, Kainji and Shiroro in the Shiroro region). The Central, North and North-East regions in particular are characterized by the total absence of generating stations.

Load demand centers in the South and South-West. Table 7-4.5 shows that with the exception of Benin, Abuja and Port Harcourt areas, where there is a significant generation surplus, demand exceeds available supply in all other regions of Nigeria.

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1153 MW

8 TO 4 593 MW

3 TO 2 403 MW

7 TO 4 856 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 170 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 626 MW

G

G

G

DISCOS

2 TO 1 1505 MW

4 TO 3 0 MW

G

G

Diagram created using'D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\2020\Master 2020 model Yash.sav''D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\Diagrams-SLDs-Use Power Exch only\Power Exchanges 330kV model Discos Yash.sld'

GG

TCN 2020 MODELDISCO DEMANDSAT, JUL 14 2018 21:56

3 TO 5 935 MW

1 TO 9 331 MW

GG

5 TO 6 -85 MW

10 TO 6 0 MW

5 TO 10 0 MW

6 TO 11 219 MW

G

4 TO 9 602 MW

4 TO 1 875 MW

G

G

1.016

1.008

286

6

1.013

1.035

1.040

278 5

278 5

278 5

278 5

83004IK OT -E K P E NE _

73006

UGWUA JI_3

73001ONIT S HA 3

73005

A S A B A _3

1.041

1.023

352

5

1.038

296

21296

21

1. 04973003

MA K URDI_3

1.050

1

1.037

28 20

28 20

1

1.038

35 8

39

35 8

39

1.03570 47

1. 042

179 23

179 23

33007GWA GW B B 1

0.992

585

67

585

67

601

19

0.980

23005

A K URE 3

0.995

1.014

319 16

84

87

23001

OS OGB O 3

0.999

231

19

231

19

153

15

1

1.007

54

55

1.033

80

90

80

90

244

146

2

3

23003GA NMO 3

23002

OMOT OS HO3

33002

B K E B B I 3 1.051

1.0331.045

134

12

135

12

93

56 93

56

108 41

0. 957

297

85

0.987

0.968

1

2

0.976

216

29 216

29

216

29

216

29

13003

IK E JA W 3

13005OLORUNS OGO3

13029

OGIJO 3

0.971

195

29 195

29

22 8

38

22 8

38

13030

MF M 3

0.964

123

65 123

65

0.972

21 8

10 6

21 8

10 6

105

68

105

68

1.018

172 61

174

23

1

0 52

2

0 52SW

0

63007

DA MA T URU 3 1.020

123

48

63005

MA IDUGURI 3 0.983

42

88

2

0

72

0. 981

192

49

192

49

218

158 218

158

0

14 7

19 4

15

13002E GB IN 3

0.966

0.970

249

90

0.974

84

130

84

130

28 2

10 8

28 2

10 8

0.977

114

25

114

25

0.978

115

1

115

1

183

27 183

27

298

19

298

19

13025

E P E 3

13000

A JA 3

13031

OK O_OB A _313034

LE K K I 330

13027

A LA GB ON_3

13001A K A NGB A 3

1.028

158

30

6

64

1

33001K A T A MP E 3

1.033

61 861 8

1.047

201 20

201 20

83007

ONNIE _3

1.038

217

49

217

49

190

4 190

4

1

83002

A LA OJI 3

1.040121

12 121

12 184

36

222

9222

9 184

36

1. 038

103

34 103

34

1. 030

48 67 48 67

1.037

504

504

83010

IK OT A B A S I_3

1.048

50

11 50

11

83000A F A M IV 3

83005

OWE RRI_3

1.033

25 37

114

61

114

61

1. 045

356

80

356

80

323 63

323 63

73004

A LIA DE _3

63001JOS 3

1.030

63 763 7

73010

A B A K A LIK I_3

1.003

96 34

0 75

63002Y OLA 3

1.000

53001K A NO 3

1.010

2

3

S W

0

1.010

221

36

53005

K A NO_NE W330

1.025

276

25

53003Z A RIA _330

53000

K A DUNA 3

53002K A T S INA 3

1.010

74

25

75

42

74

25 75

42

0.973

85 65

85

6513032

NE W_A GB A RA _3

0.962

26 2

8

1260

1

23000

A Y E DE 3

1.039

43000A JA OK UT A 3

43008

LOK OJA _3

43002

B E NIN 3

1.020 304

6

43001A LA DJA 3

43003

DE LT A IV 3

1.014

30 4

6

202

22

202

22

202

22

43004

S A P E LE 3

43011B _NORT H_3

1.039 224 3

224 3

43005GE RE GU

1.043

8

208

20

43009

OB A JA NA _3

1.024

388 1

388 1

83006E GB E MA _3

83009OMOK U_3

83008CA LA B A R_P S _3

83003A DIA GB O_3

63000

GOMB E 3

313

14

2

1 2

33020

S HIRORO 3

33008WE S T MA IN_3

73000NHA V E N 3

1.000

53004F UNT UA 3

1.000

53007

T MA F A RA 3

1.000

53008

GUS A U 3

33021K A INJI 3

1.04524

13

33005

K A INJI G.S .3

33003JE B B A T .S .3

274

10

276

24

249

90

108 41

28

601.037

12

52

247

45

33009

Z UNGE RU

33004

JE B B A G.S .3

33022

A P O_NE W 3

1.050

33023LA F IA 3

1.057

229 15

23 2

46

311

61

311

61

54

43 54

43

63003

B A UCHI 3 1.044

173 62

176

23

63008

MA MB ILA 3

1.000

1.038

161 4

161 4

1. 000

43006E F F URUN 3

286

6

73002OK P A I 3

1.018

1.018

265 15

73030

IHIA LA 3

23006IB A DA N

1.000

13026OK E _A RO_3

388

23

53012

DUT S E 3

1.000

53011

K A Z A URE 3

1.000

1

2

0 75

1.000

63009WUK A RI

33006

S OK OT O 3

1.000

22

11

22

11

83001A LA OJI NIP P 3

73007NNE WI 3

0

32 9

30

338

1

2

1

13004

S A K E T E 3

1.014

1.000

13028A RIGB A JO

63006

JA LINGO_3

33010ZABORI

1.000

SW 0

13012PARAS

0.978

67

23 6723

67

32

67

32

63015M AYOBELWA 1.004 2

6

4

117

121

117

114

246

7

244

65

247

24

243

48

71

26

72

105

21

1

62

21

1

46

21

1

62

21

1

46

171

36

173

15

43007

A Z URA

66

24

66

96

200

11

200

11

202

11

202

11

43010E T HIOP E

0.964

69

1010

141

44 141

44

69

13035

IJORA 3

1.000

187

1

32021NIA ME Y 1

0.954

1

40 1

52010GA Z OUA 1

SW

32

Export 387 MW

Total Generation 9421 MWNigeria Load 8637 MW

Genera tion from H PP 1501 MW

Generation per DISCO Loads per DISCO

3-Abuja 866 MW

7-Enugu 924 MW

2-Ibadan 1104 MW

1-Ikeja 1166 MW

6-Jos 309 MW

5-Kaduna 495 MW

10-Kano 708 MW

11-Yola 230 MW

3-Abuja 1979 MW

4-Benin 1775 MW

9-Eko 0 MW

7-Enugu 796 MW

2-Ibadan 476 MW

1-Ikeja 735 MW

6-Jos 105 MW

5-Kaduna 344 MW

10-Kano 9 MW

8-Pt Harco 3202 MW

11-Yola 0 MW

Genera tion from PV 200 MW

Total Load 9024 MW

9-Eko 1087 MW

8-Pt Harco 794 MW

4-Benin 954 MW

1

1

1

1

1

1

1.037

0.975

0.912

1.1

0.85

Vo

lta

ge

(p

u)

Page 33: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-32

To supply load to areas with little or no generation such as the North-East, long 330 kV transmission lines are built (radial system), which are then prone to voltage regulation problems. Moreover, the excessive reactive power flowing through these lines necessitates large reactive power compensation equipment (reactors) at the corresponding substations (Kano, Gombe, Maiduguri).

Any addition of more 330 kV lines running in parallel, as planned, may require additional compensation equipment, as of Yola and Jalingo and possibly elsewhere to limit the overvoltages due to line charging currents.

The general profile of power flows in the TCN system is shown graphically in Figure 7-4.4

Source: JICA Study Team

Figure 7-4.4 Power flows in the TCN system

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1153 MW

8 TO 4 593 MW

3 TO 2 403 MW

7 TO 4 856 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 170 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 626 MW

G

G

G

DISCOS

2 TO 1 1505 MW

4 TO 3 0 MW

G

G

Diagram created using'D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\2020\Master 2020 model Yash.sav''D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\Diagrams-SLDs-Use Power Exch only\Power Exchanges 330kV model Discos Yash.sld'

GG

TCN 2020 MODELDISCO DEMANDSAT, JUL 14 2018 21:56

3 TO 5 935 MW

1 TO 9 331 MW

GG

5 TO 6 -85 MW

10 TO 6 0 MW

5 TO 10 0 MW

6 TO 11 219 MW

G

4 TO 9 602 MW

4 TO 1 875 MW

G

G

1.016

1.008

286

6

1.013

1.035

1.040

278 5

278 5

278 5

278 5

83004IK OT -E K P E NE _

73006

UGWUA JI_3

73001ONIT S HA 3

73005

A S A B A _3

1.041

1.023

352

5

1.038

296

21296

21

1. 04973003

MA K URDI_3

1.050

1

1.037

28 20

28 20

1

1.038

35 8

39

35 8

39

1.03570 47

1. 042

179 23

179 23

33007GWA GW B B 1

0.992

585

67

585

67

601

19

0.980

23005

A K URE 3

0.995

1.014

319 16

84

87

23001

OS OGB O 3

0.999

231

19

231

19

153

15

1

1.007

54

55

1.033

80

90

80

90

244

146

2

3

23003GA NMO 3

23002

OMOT OS HO3

33002

B K E B B I 3 1.051

1.0331.045

134

12

135

12

93

56 93

56

108 41

0. 957

297

85

0.987

0.968

1

2

0.976

216

29 216

29

216

29

216

29

13003

IK E JA W 3

13005OLORUNS OGO3

13029

OGIJO 3

0.971

195

29 195

29

22 8

38

22 8

38

13030

MF M 3

0.964

123

65 123

65

0.972

21 8

10 6

21 8

10 6

105

68

105

68

1.018

172 61

174

23

1

0 52

2

0 52SW

0

63007

DA MA T URU 3 1.020

123

48

63005

MA IDUGURI 3 0.983

42

88

2

0

72

0. 981

192

49

192

49

218

158 218

158

0

14 7

19 4

15

13002E GB IN 3

0.966

0.970

249

90

0.974

84

130

84

130

28 2

10 8

28 2

10 8

0.977

114

25

114

25

0.978

115

1

115

1

183

27 183

27

298

19

298

19

13025

E P E 3

13000

A JA 3

13031

OK O_OB A _313034

LE K K I 330

13027

A LA GB ON_3

13001A K A NGB A 3

1.028

158

30

6

64

1

33001K A T A MP E 3

1.033

61 861 8

1.047

201 20

201 20

83007

ONNIE _3

1.038

217

49

217

49

190

4 190

4

1

83002

A LA OJI 3

1.040121

12 121

12 184

36

222

9222

9 184

36

1. 038

103

34 103

34

1. 030

48 67 48 67

1.037

504

504

83010

IK OT A B A S I_3

1.048

50

11 50

11

83000A F A M IV 3

83005

OWE RRI_3

1.033

25 37

114

61

114

61

1. 045

356

80

356

80

323 63

323 63

73004

A LIA DE _3

63001JOS 3

1.030

63 763 7

73010

A B A K A LIK I_3

1.003

96 34

0 75

63002Y OLA 3

1.000

53001K A NO 3

1.010

2

3

S W

0

1.010

221

36

53005

K A NO_NE W330

1.025

276

25

53003Z A RIA _330

53000

K A DUNA 3

53002K A T S INA 3

1.010

74

25

75

42

74

25 75

42

0.973

85 65

85

6513032

NE W_A GB A RA _3

0.962

26 2

8

1260

1

23000

A Y E DE 3

1.039

43000A JA OK UT A 3

43008

LOK OJA _3

43002

B E NIN 3

1.020 304

6

43001A LA DJA 3

43003

DE LT A IV 3

1.014

30 4

6

202

22

202

22

202

22

43004

S A P E LE 3

43011B _NORT H_3

1.039 224 3

224 3

43005GE RE GU

1.043

8

208

20

43009

OB A JA NA _3

1.024

388 1

388 1

83006E GB E MA _3

83009OMOK U_3

83008CA LA B A R_P S _3

83003A DIA GB O_3

63000

GOMB E 3

313

14

2

1 2

33020

S HIRORO 3

33008WE S T MA IN_3

73000NHA V E N 3

1.000

53004F UNT UA 3

1.000

53007

T MA F A RA 3

1.000

53008

GUS A U 3

33021K A INJI 3

1.04524

13

33005

K A INJI G.S .3

33003JE B B A T .S .3

274

10

276

24

249

90

108 41

28

601.037

12

52

247

45

33009

Z UNGE RU

33004

JE B B A G.S .3

33022

A P O_NE W 3

1.050

33023LA F IA 3

1.057

229 15

23 2

46

311

61

311

61

54

43 54

43

63003

B A UCHI 3 1.044

173 62

176

23

63008

MA MB ILA 3

1.000

1.038

161 4

161 4

1. 000

43006E F F URUN 3

286

6

73002OK P A I 3

1.018

1.018

265 15

73030

IHIA LA 3

23006IB A DA N

1.000

13026OK E _A RO_3

388

23

53012

DUT S E 3

1.000

53011

K A Z A URE 3

1.000

1

2

0 75

1.000

63009WUK A RI

33006

S OK OT O 3

1.000

22

11

22

11

83001A LA OJI NIP P 3

73007NNE WI 3

0

32 9

30

338

1

2

1

13004

S A K E T E 3

1.014

1.000

13028A RIGB A JO

63006

JA LINGO_3

33010ZABORI

1.000

SW 0

13012PARAS

0.978

67

23 6723

67

32

67

32

63015M AYOBELWA 1.004 2

6

4

117

121

117

114

246

7

244

65

247

24

243

48

71

26

72

105

21

1

62

21

1

46

21

1

62

21

1

46

171

36

173

15

43007

A Z URA

66

24

66

96

200

11

200

11

202

11

202

11

43010E T HIOP E

0.964

69

1010

141

44 141

44

69

13035

IJORA 3

1.000

187

1

32021NIA ME Y 1

0.954

1

40 1

52010GA Z OUA 1

SW

32

Export 387 MW

Total Generation 9421 MWNigeria Load 8637 MW

Genera tion from H PP 1501 MW

Generation per DISCO Loads per DISCO

3-Abuja 866 MW

7-Enugu 924 MW

2-Ibadan 1104 MW

1-Ikeja 1166 MW

6-Jos 309 MW

5-Kaduna 495 MW

10-Kano 708 MW

11-Yola 230 MW

3-Abuja 1979 MW

4-Benin 1775 MW

9-Eko 0 MW

7-Enugu 796 MW

2-Ibadan 476 MW

1-Ikeja 735 MW

6-Jos 105 MW

5-Kaduna 344 MW

10-Kano 9 MW

8-Pt Harco 3202 MW

11-Yola 0 MW

Genera tion from PV 200 MW

Total Load 9024 MW

9-Eko 1087 MW

8-Pt Harco 794 MW

4-Benin 954 MW

1

1

1

1

1

1

300

200

100

400

0

MW

Flo

w

TCN330kV TRANSMISSINO NETWORK

TCN2020MODEL

Total Generation: 9421 MW

Nigeria Load: 8637 MW

Export: 387 MW

Total Load: 9024 MW

Generation from PV: 200 MW

Generarion from HPP: 1501 MW

Page 34: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-33

7-4-2-2 Dry Season Peak Case

(1) Prerequisites for analysis

(a) Generation from PVs = 0 MW and (b) Reduced generation from HPP plants of 1,322 MW)

The running generation and load for each DisCo are shown in Figure 7-4.5 and Table 7-4.6. The total running generation to meet the load and losses is 9,417 MW.

Source: JICA Study Team

Figure 7-4.5 Dry Season Peak Generation and Load Per DisCo

Table 7-4.6 2020 Dry Season Peak - Running Generation

Bus Name PGen

(MW) Bus Name

PGen

(MW) Bus Name

PGen

(MW)

AARON PV 15.000 0 EGBIN ST 2 16.000 171.4 NOVA SOLA PV33.000 0

AES BERG202 11.000 0 EGBIN ST 3 16.000 171.4 NSCP PV 15.000 0

AES BERG203 11.000 0 EGBIN ST 4 16.000 171.4 O REN SOL PV15.000 0

AES BERG204 11.000 0 EGBIN ST 5 16.000 171.4 OBAJANA 15.000 0

AES BERG205 11.000 0 EGBIN ST 6 16.000 171.4 OKPAI GT11 11.500 135

AES BERG207 11.000 0 ELEME 15.000 0 OKPAI GT12 11.500 135

AES BERG208 11.000 0 EN ARFICA PV15.000 0 OKPAI ST18 11.500 126

AES BERG209 11.000 0 ETHIOPE 15.000 0 OKPAI_IPPII 11.500 400

AES BERG210 11.000 0 GBARAIN_GTB115.000 102 OLOR NIPPST110.500 108

AES BERG211 11.000 0 GBARAIN_GTB215.000 102 OLOR NIPPST210.500 0

AFAM VI GT1111.500 150 GEN DANGOTE 15.000 0 OLORNIPPGT1110.500 0

AFAM VI GT1211.500 150 GEN_AMADI 15.000 90 OLORNIPPGT1210.500 0

AFAM VI GT1311.500 105 GEN_KADUNA 15.000 194 OLORNIPPGT2110.500 108

AFAM VI ST1011.500 180 GEOMETRIC_AB15.000 0 OLORNIPPGT2210.500 108

AFAM1GT1-2 11.500 0 GER NIPPGT2110.500 100 OLORUNSO GT110.500 22

AFAM1GT3-4 11.500 0 GER NIPPGT2210.500 0 OLORUNSO GT210.500 22

Ikeja Ibadan Abuja Benin Kaduna Jos Enugu P Harc Eko Kano YolaTotalfor

NigeriaExport Totals

Run Genaration 1110 476 1750 1775 194 105 796 3202 0 9 0 9417

Load 1166 1104 866 954 495 309 924 794 1087 708 230 8637 387 9024

Gen deficit/surplus -56 -628 884 821 -301 -204 -128 2408 -1087 -699 -230 393

-1500

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

MW

Dry season Peak

Page 35: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-34

Bus Name PGen

(MW) Bus Name

PGen

(MW) Bus Name

PGen

(MW)

AFAM2 GT5-6 11.500 54 GER NIPPGT2310.500 100 OLORUNSO GT310.500 20

AFAM2GT 7-8 11.500 54 GEREGU GT11 10.500 83 OLORUNSO GT410.500 0

AFAM3 GT9-1011.500 54 GEREGU GT12 10.500 83 OLORUNSO GT510.500 22

AFAM3GT11-1211.500 54 GEREGU GT13 10.500 83 OLORUNSO GT610.500 22

AFAM4GT13-1411.500 67 GR COWRI PV 33.000 0 OLORUNSO GT710.500 22

AFAM4GT15-1611.500 0 GURARA GBUS 11.500 0 OLORUNSO GT810.500 22

AFAM4GT17-1811.500 0 IBOM GT1 11.500 34 OMOKU1 GT1 15.000 68

AFAMV GT 19 11.500 125 IBOM GT2 11.500 34 OMOKU1 GT2 15.000 50

AFAMV GT 20 11.500 125 IBOM GT3 11.500 34 OMOKU2 GT1 15.000 102

AFRINEGIA PV15.000 0 IBOM II 11.500 260 OMOKU2 GT2 15.000 102

ALAOJI_GTB1 15.000 81 IHOVBOR_GTB115.000 110 OMOTNIPP GT110.500 108

ALAOJI_GTB2 15.000 81 IHOVBOR_GTB215.000 110 OMOTNIPP GT210.500 108

ALAOJI_GTB3 15.000 81 IHOVBOR_GTB315.000 110 OMOTNIPP GT310.500 0

ALAOJI_GTB4 15.000 81 IHOVBOR_GTB415.000 0 OMOTNIPP GT410.500 0

ALAOJI_STB1 17.000 0 IJORA GT 4-611.000 0 OMOTOSO GT1 10.500 70

ALAOJI_STB1 17.000 0 JBS WIND 15.000 70 OMOTOSO GT3 10.500 66

ALSCON GT1 11.500 0 JEBBA 2G1 16.000 90 OMOTOSO GT5 10.500 0

ALSCON GT2 11.500 0 JEBBA 2G2 16.000 90 OMOTOSO GT7 10.500 0

ANJEED PV 15.000 0 JEBBA 2G3 16.000 0 PAN AFRIC PV15.000 0

ASCO G1 11.000 0 JEBBA 2G4 16.000 0 PARAS 11.500 0

ASCO G2 11.000 0 JEBBA 2G5 16.000 0 PARASGT1-9 11.000 81

AZURA GT 15.000 280 JEBBA 2G6 16.000 90 QUAINT PV 15.000 0

AZURA ST 15.000 125 KAINJ 1G11 16.000 90 RIVERS _GT1 10.500 172

BRESSON GTS 11.000 0 KAINJ 1G12 16.000 90 RIVERS_GT2 10.500 0

CALABAR_GTB115.000 100 KAINJ 1G5 16.000 45 SAP_NIPP_GT115.800 77

CALABAR_GTB215.000 102 KAINJ 1G6 16.000 45 SAP_NIPP_GT215.800 77

CALABAR_GTB315.000 102 KAINJ 1G7-8 16.000 160 SAP_NIPP_GT315.800 76

CALABAR_GTB415.000 0 KAINJ 1G9-1016.000 0 SAP_NIPP_GT415.800 76

CALABAR_GTB515.000 0 KASHIMB HP2 15.000 0 SAPELE GT1-215.800 0

CT COSMO PV 15.000 0 KASHIMB HP3 15.000 0 SAPELE GT3-415.800 0

DELT3 GT9-1111.500 38 KASHIMB HP4 15.000 0 SAPELE ROT 15.800 0

DELT3GT12-1411.500 0 KASHIMB HPP 15.000 21 SAPELE ST1 15.800 0

DELTA GT 15 11.500 96 KAZAURE PV1 11.000 0 SAPELE ST2 15.800 0

DELTA GT16 11.500 96 KAZAURE PV1011.000 0 SAPELE ST3 15.800 0

DELTA GT17 11.500 97 KAZAURE PV2 11.000 0 SAPELE ST4 15.800 0

DELTA GT18 11.500 0 KAZAURE PV3 11.000 0 SAPELE ST5 15.800 0

DELTA GT19 11.500 0 KAZAURE PV4 11.000 0 SAPELE ST6 15.800 0

DELTA GT20 11.500 0 KAZAURE PV5 11.000 0 SHIROR 411G116.000 140

DELTA1 GT1 11.500 0 KAZAURE PV6 11.000 0 SHIROR 411G216.000 140

DELTA1 GT2 11.500 0 KAZAURE PV7 11.000 0 SHIROR 411G316.000 0

DELTA2 GT3-511.500 45 KAZAURE PV8 11.000 0 SHIROR 411G416.000 0

DELTA2 GT6-811.500 10 KAZAURE PV9 11.000 0 SINOSUN PV 15.000 0

DKOWA G1 11.000 14 KT WF 33 33.000 9 SYNER GEN PV15.000 0

DUSABLE PV 15.000 0 KVKPOWER PV 15.000 0 ZUNGE_G1 16.000 107

EGBEMA_GTB1 15.000 102 LAFARAGE 1 11.000 0 ZUNGE_G2 16.000 107

EGBEMA_GTB2 15.000 102 MIDBAND PV 15.000 0 ZUNGE_G3 16.000 0

EGBEMA_GTB3 15.000 102 NOVA SCOT PV132.00 0 ZUNGE_G4 16.000 107

EGBIN ST 1 16.000 171.4 NOVA SOLA PV15.000 0

Source: JICA Study Team

Page 36: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-35

The power flows are shown in Figure 7-4.6.

Source: JICA Study Team

Figure 7-4.6 2020 Dry Season Peak Power Flows in 330 kV System

(2) Overloads of lines and transformers

The base case (N-0) overloaded 132 kV lines as well as the 330/132 kV and 132/33 kV transformers are listed in Table 7-4.7, Table 7-4.8 and Table 7-4.9.

It should be noted that introducing the 330kV substation at Ijora eliminates the overloads of the 132kV line Alagbon - Ijora and the need to have this line reinforced. It will become even more crucial in subsequent years, so it should be integrated into the system as soon as possible.

Table 7-4.7 2020 Dry Season Peak - Overloaded Lines (base case)

Bus

Number

Bus name Bus

Number

Bus name CKT Contingency

label

Rating

(MVA)

Flow

(MVA)

Loading

(%)

82024 IBOM IPP 1 132.00 82031 IKOT_ABASI 132.00 1 BASE CASE 125.7 182.1 144.8

Source: JICA Study Team

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1194 MW

8 TO 4 563 MW

3 TO 2 223 MW

7 TO 4 792 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETW ORK

G

G

G

G

G

G

6 TO 3 179 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 633 MW

G

G

G

DISCOS

2 TO 1 1242 MW

4 TO 3 0 MW

G

Diagram created using

'D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\2020\DP 2020 model Yash.sav''D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\Diagrams-SLDs-Use Power Exch only\Power Exchanges 330kV model Discos Yash.sld'

GG

TCN 2020 MODEL

DISCO DEMANDSAT, JUL 14 2018 23:19

3 TO 5 1009 MW

1 TO 9 284 MW

GG

5 TO 6 -64 MW

10 TO 6 0 MW

6 TO 11 218 MW

G

4 TO 9 506 MW

4 TO 1 761 MW

G

G

1.016

1.012

265

8

1.014

1.028

1.037

28

8 2

28

8 2

28

8 2

28

8 2

83004

IKOT-EKPENE_

73006

UGWUAJI_3

73001

ONITSHA 3

73005

ASABA_3

1.040

1.025

339

4

1.03728

1

26

28

1

26

1.03173003

MAKURDI_3

1.034

1

1.025

22

26

21

26

1

1.030

384

26

384

26

1.02696

53

1.037

23

8

18

23

8

18

33007GWAGW BB1

0.999

481

44 481

44

491

3

0.985

23005AKURE 3

0.999

1.017

321 12

112

81

23001

OSOGBO 3

1.004

233

16

233

16

155

17

1

1.010

27

58

1.033

31

88

31

88

16

0

14

7

2

3

23003GANMO 3

23002

OMOTOSHO3

33002

BKEBBI 3 1.046

1.0331.045

134

12

135

12

82

55 82

55

11

9

43

0.964

213

96

0.994

0.974

1

2

0.983

189

37 189

37

189

37

189

37

13003

IKEJA W 3

13005OLORUNSOGO3

13029

OGIJO 3

0.978

186

34 186

34

218

41

218

41

13030

MFM 3

0.970

103

68 103

68

0.978

278

91

278

91

160

52

160

52

0.999

17

2

63

17

5

17

1

0 50

2

0 50

SW

0

63007

DAMATURU 3 0.997

12

2

41

2

0.988

127

62

127

62

218

155 218

155

73

137

118

17

13002EGBIN 3

0.972

0.977

273

83

0.980

155

107

155

107

307

101

307

101

0.984

96

31

96

31

0.985

96

6

96

6

154

37 154

37

251

33

251

33

13025

EPE 3

13000

AJA 3

13031

OKO_OBA_313034LEKKI 330

13027

ALAGBON_3

13001

AKANGBA 3

1.018

168

32

8

68

1

33001

KATAMPE 3

1.023

62

1062

10

1.047

20

2

21

20

2

21

83007

ONNIE_3

1.037

22

8

40

22

8

40

19

1

5 19

1

5

1

83002ALAOJI 3

1.03912

6

16

12

6

16

19

3

29

20

8

14

20

8

14

19

3

29

1.036

10

3

30

10

3

30

1.028

48 6

7 4

8 67

1.034

50

4

50

4

83010

IKOT ABASI_3

1.047

50

11

50

11

83000

AFAM IV 3

83005

OWERRI_3

1.026

18

18

93

51

93

51

1.030

40

0

57

40

0

57

36

5

59

36

5

59

73004ALIADE_3

63001

JOS 3

1.023

63

663

6

73010

ABAKALIKI_3

0.980

96

29

0 72

63002

YOLA 3

1.000

53001

KANO 3

0.997

2

3

SW

0

0.998

221

38

53005

KANO_NEW330

1.013

277

29

53003

ZARIA_330

53000KADUNA 3

0.999

74

22

75

43

22 75

43

0.981

77

66 7

7

66

13032

NEW_AGBARA_3

0.968

262

9

1260

1

23000AYEDE 3

1.036

43000

AJAOKUTA 3

43008LOKOJA _3

43002BENIN 3

1.023 29

1

7

43001ALADJA 3

43003

DELTA IV 3

1.017

291

7

197

19

197

19

197

19

43004

SAPELE 3

43011B_NORTH_3

1.036

22

4

12

22

4

12

43005

GEREGU

1.038

8

208

20

43009OBAJANA_3

1.024

38

8 1 3

88 1

83006

EGBEMA_3

83009

OMOKU_3

83008

CALABAR_PS_3

83003

ADIAGBO_3

63000GOMBE 3

29

2

22

2

1 2

33020

SHIRORO 3

33008

WESTMAIN_3

73000

NHAVEN 3

1.000

53004FUNTUA 3

1.000

1.000

53008GUSAU 3

33021KAINJI 3

1.04524

13

33005

KAINJI G .S.3

33003

JEBBA T.S.3

253

13

255

30

273

83

11

9

43

21

531.030

93

47

25

2

35

33009

ZUNGERU

33004

JEBBA G .S.3

33022APO_NEW 3

1.033

33023

LAFIA 3

1.039

26

9 1

273

49

35467

354

67

56

38 56

38

63003BAUCHI 3 1.027

17

4

63

17

7

17

63008

MAMBILA 3

1.000

1.037

16

1 61

61 6

1.000

43006EFFURUN 3

265

8

73002

OKPAI 3

1.018

1.018

25

1

16

73030

IHIALA 3

23006IBADAN

1.000

13026

OKE_ARO_3

37

7

21

1.000

1

2

0 72

1.000

63009

WUKARI

1.000

23

11

23

11

83001ALAOJI NIPP3

73007

NNEWI 3

0

329

30

338

1

2

1

13004

SAKETE 3

1.017

1.000

13028ARIGBAJO

63006JALINGO_3

33010ZABORI

1.000

SW

0

13012PARAS

0.984

16

8 16

8

16

17

16

17

63015MAYOBELWA 0.982

25

3

156

112

15

6

10

6

24 7

4

24 5

64

24 8

22

24 3

47

128 24

129

98

272

50

271

38

272

50

271

38

171

34

173

15

43007

AZURA

12

5

22

12

6

90

200

6

20

0

7

202

6

20

2

6

43010

ETHIOPE

0.971

92

44

165

37 165

37

92

13035

IJORA 3

Export 387 MW

Total Generation 9417 MWNigeria Load 8637 MW

Generation from HPP 1322 MW

Generation per DISCO Loads per DISCO

3-Abuja 866 MW

7-Enugu 924 MW

2-Ibadan 1104 MW

1-Ikeja 1166 MW

6-Jos 309 MW

5-Kaduna 495 MW

10-Kano 708 MW

11-Yola 230 MW

3-Abuja 1750 MW

4-Benin 1775 MW

9-Eko 0 MW

7-Enugu 796 MW

2-Ibadan 476 MW

1-Ikeja 1110 MW

6-Jos 105 MW

5-Kaduna 194 MW

10-Kano 9 MW

8-Pt Harco 3202 MW

11-Yola 0 MW

Generation from PV 0 MW

Total Load 9024 MW

9-Eko 1087 MW

8-Pt Harco 794 MW

4-Benin 954 MW

1

1

1

1

1

1

300

200

100

400

0

MW

Flo

w

TCN330kV TRANSMISSINO NETWORK

TCN2020MODEL

Total Generation: 9421 MW

Nigeria Load: 8637 MW

Export: 387 MW

Total Load: 9024 MW

Generation from PV: 200 MW

Generarion from HPP: 1501 MW

Page 37: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-36

Table 7-4.8 2020 Dry Season Peak - Overloaded 330/132 kV transformers (base case)

Bus

Number Bus Name

Voltage

(kV) Area

Bus

Number Bus Name

Wind

Number CKT

Loading

(MVA)

Rating

(MVA)

Loading

(%)

330/132 kV 3-W and A/T

23003 GANMO 3 330 2 3WNDTR GANMO TR2A 1 1 157.4 150 104.9

33002 BKEBBI 3 330 3 3WNDTR B_KEBBI T1 1 1 176.9 150 118

43002 BENIN 3 330 4 3WNDTR BENIN TR1 1 1 156 150 104

43002 BENIN 3 330 4 3WNDTR BENIN TR2 1 1 156 150 104

43002 BENIN 3 330 4 3WNDTR BENIN TR3 1 1 156 150 145.6

43011 B.NORTH_3 330 4 3WNDTR BENIN 9T1 2 1 88 67.5 131.6

Source: JICA Study Team

Table 7-4.9 2020 Dry Season Peak - Overloaded 2-winding transformers (base case)

Bus

Number Bus Name

Voltage

(kV) Area

Bus

Number Bus Name

Voltage

(kV) cct

Loading

(MVA)

Rating

(MVA)

Loading

(%)

132/33 and 132/11 kV 2-W transformers

32017 SULEJA 1 132 3 36016 SULEJA 11 11 1 18.6 7.5 247.6

42004 BENIN 1 132 4 45029 BENIN T22 33 33 1 85.9 60 143.1

52001 KANO 1 132 5 55058 KUMB T3

MOB 33 3 41.9 30 139.6

42004 BENIN 1 132 4 45031 BENIN T24 33 33 1 82.9 60 138.1

42004 BENIN 1 132 4 45030 BENIN T23 33 33 1 80.9 60 134.8

52016 FUNTUA 1 132 5 56000 FUNTUA 11 11 1 9.6 7.5 127.6

42005 B_N0RTH 1 132 4 45015 B_NORTH_33 33 1 73.9 60 123.2

22015 OMUARAN

1 132 2 25016 OMUARAN 33 33 1 33.4 30 111.4

52016 FUNTUA 1 132 5 55003 FUNTUA 33 33 1 33 30 109.9

52016 FUNTUA 1 132 5 56005 FUNTUA T2 11 2 7.9 7.5 105.9

22013 OFFA 1 132 2 25015 OFFA 33 33 1 31.8 30 105.8

12029 OJO 1 132 1 15030 OJO 33 33 1 30.4 30 101.4

Source: JICA Study Team

7-4-2-3 Wet Season Peak Case

(1) Prerequisites for analysis

(a) Generation from PVs = 0 MW and (b) Normal generation from HPP plants of 2,100 MW,

The running generation and load for each DisCo are shown in Figure 7-4.7.

Page 38: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-37

Source: JICA Study Team

Figure 7-4.7 Wet Season Peak Generation and Load Per DisCo

(2) Overloads of lines and transformers

The base case (N-0) overloaded 132 kV lines are listed in Table 7-4.10.

Table 7-4.10 2020 Wet Season Peak - Overloaded Lines (base case)

Bus

Number

Bus name Bus

Number

Bus name CKT Contingency

label

Rating

(MVA)

Flow

(MVA)

Loading

(%)

82024 IBOM IPP 1 132.00 82031 IKOT_ABASI 132.00 1 BASE CASE 125.7 182.6 145.2

Source: JICA Study Team

No new overloaded lines are reported, in addition to those overloaded in the Dry Season Peak case. The same applies for the overloaded transformer.

7-4-2-4 Dry Season Off- Peak Case

(1) Prerequisites for analysis

(a) Generation from PVs = 400 MW and (b) Reduced generation from HPP plants of 1,100 MW,

The running generation and load for each DisCo are shown in Figure 7-4.8.

Ikeja Ibadan Abuja Benin Kaduna Jos Enugu P Harc Eko Kano YolaTotalfor

NigeriaExport Totals

Run Genaration 692 476 2120 1775 224 134 796 3202 0 9 0 9428

Load 1166 1104 866 954 495 309 924 794 1087 708 230 8637 387 9024

Gen deficit/surplus -474 -628 1254 821 -271 -175 -128 2408 -1087 -699 -230 404

-1500

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

MW

Wet season Peak

Page 39: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-38

Source: JICA Study Team

Figure 7-4.8 Dry Season Off-Peak Generation and Load per DisCo

(2) Overloads of lines and transformers

The base case (N-0) overloaded 132 kV lines are listed in Table 7-4.11.

Table 7-4.11 2020 Dry Season Off-Peak - Overloaded Lines (base case)

Bus Number

Bus name Bus

Number Bus name CKT

Contingency label

Rating (MVA)

Flow (MVA)

Loading (%)

82024 IBOM IPP 1 132.00 82031 IKOT_ABASI 132.00 1 BASE CASE 125.7 189.6 150.9

Source: JICA Study Team

The overloaded line(s) are the same as in the Dry Season Peak case.

The overloaded transformers are fewer than the Dry Season Peak case, as shown in the following tables, Table 7-4.12 and Table 7-4.13.

Table 7-4.12 2020 Dry Season Off-Peak - Overloaded 330/132 kV transformers (base case)

Bus Number

Bus Name

Voltage (kV)

Area Bus

Number Bus

Name Wind CKT

Loading (MVA)

Rating (MVA)

Loading (%)

43011 B.NORTH_3 330 4 3WNDTR BENIN 9T1 2 1 74.3 67.5 110

Source: JICA Study Team

Table 7-4.13 2020 Dry Season Off-Peak - Overloaded 2-winding transformers (base case)

Bus Number

Bus Name

Voltage (kV)

Area Bus

Number Bus

Name Voltage

(kV) cct

Loading (MVA)

Rating (MVA)

Loading (%)

132/33 and 132/11 kV 2-W transformers

32017 SULEJA 1 132 3 36016 SULEJA 11 11 1 15.5 7.5 206

42004 BENIN 1 132 4 45029 BENIN T22 33 33 1 72.4 60 120.6

52001 KANO 1 132 5 55058 KUMB T3 33 3 34.9 30 116.3

Ikeja Ibadan Abuja Benin Kaduna Jos Enugu P Harc Eko Kano YolaTotal for NigeriaExport Totals

Run Genaration 97 476 1170 1775 364 105 795 3202 0 149 0 8133

Load 991 938 736 811 421 263 785 675 924 602 195 7341 387 7728

Gen deficit/surplus -894 -462 434 964 -57 -158 10 2527 -924 -453 -195 405

-1500

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

MW

Dry season Off-Peak

Page 40: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-39

Bus Number

Bus Name

Voltage (kV)

Area Bus

Number Bus

Name Voltage

(kV) cct

Loading (MVA)

Rating (MVA)

Loading (%)

MOB

42004 BENIN 1 132 4 45031 BENIN T24 33 33 1 69.9 60 116.4

42004 BENIN 1 132 4 45030 BENIN T23 33 33 1 68.2 60 113.7

52016 FUNTUA 1 132 5 56000 FUNTUA 11 11 1 9.6 7.5 127.6

42005 B_N0RTH 1 132 4 45015 B_NORTH_33 33 1 62.4 60 104

Source: JICA Study Team

7-4-2-5 Wet Season Off-Peak Case

(1) Prerequisites for analysis

(a) Generation from PVs = 400 MW and

(b) Normal generation from HPP plants of 2,100 MW,

The running generation and load for each DisCo are shown in Figure 7-4.9.

Source: JICA Study Team

Figure 7-4.9 Wet Season Off-Peak Generation and Load Per DisCo

(2) Overloads of lines and transformers

The base case (N-0) overloaded 132 kV lines are listed in Table 7-4.14.

Ikeja Ibadan Abuja Benin Kaduna Jos Enugu P Harc Eko Kano YolaTotalfor

NigeriaExport Totals

Run Genaration 129 476 2135 1469 364 139 796 2382 0 149 0 8039

Load 991 938 736 811 421 263 785 675 924 602 195 7341 387 7728

Gen deficit/surplus -862 -462 1399 658 -57 -124 11 1707 -924 -453 -195 311

-1500

-1000

-500

0

500

1000

1500

2000

2500

3000

3500

MW

Wet season Off- Peak

Page 41: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-40

Table 7-4.14 2020 Wet Season Off-peak - Overloaded Lines (base case)

Bus Number

Bus name Bus

Number Bus name CKT

Contingency label

Rating (MVA)

Flow (MVA)

Loading (%)

82024 IBOM IPP 1 132.00 82031 IKOT_ABASI 132.00 1 BASE CASE 125.7 189.4 150.7

Source: JICA Study Team

No new overloaded lines are reported, in addition to those overloaded in the Dry Season Peak case.

The same applies for the overloaded transformer.

7-4-3 2020 Contingency Analysis Load-flow Results

An N-1 contingency analysis using ACCC in PSS/E has been carried out for the 330 and 132 kV transmission lines, using their RATE B as short-term overload ratings.

The N-1 criterion is not applicable for transformer circuits. The results are summarized in tables fromTable 7-4.15 to Table 7-4.19.

Table 7-4.15 Non-converged cases

Contingency LINE Bus

Number Bus Name

Voltage (kV)

Bus Number

Bus name CKT

SINGLE 53001-53005(2) OPEN LINE 53001 KANO 3 330 53005 KANO_NEW330 2

SINGLE 63000-63002(1) OPEN LINE 63000 GOMBE 3 330 63002 YOLA 3 1

SINGLE 63000-63007(1) OPEN LINE 63000 GOMBE 3 330 63007 DAMATURU 3 1

SINGLE 32003-32041(3) OPEN LINE 32003 BKEBBI 1 132 32041 KVKPOWER PV 3

SINGLE 32016-32041(3) OPEN LINE 32016 SOKOTO 1 132 32041 KVKPOWER PV 3

SINGLE 52015-52016(1) OPEN LINE 52015 ZARIA 1 132 52016 FUNTUA 1 1

Source: JICA Study Team

In the above contingency cases of the loss of 330 kV lines from Gombe to Yola and Damaturu, the load-flow case did not converge as expected, due to the absence of a second parallel circuit and insufficient support from alternative routes.

Converting to a Double-Circuit will resolve these issues.

The overloads reported for the 132 kV circuits will have to be resolved by either reinforcing these lines or providing new alternative routes for the power flow.

In all N-1 contingencies, a number of 132 kV voltages are lower than the minimum permissible level of 0.8p.u. However, this is due to overloads of the associated 132 kV lines and transformers and the remedial actions for the U/V are linked to the solutions initially required for overloads of these circuits.

7-4-3-1 2020 Dry Season Peak Case-ACCC

The base case and N-1 contingency analysis results are shown in Table 7-4.16.

It can be seen that the loadings of all the 330 kV lines are within their thermal rating limits with the exception of the Double-Circuit 330 kV lines from Benin to Omotosho and from Shiroro to Kaduna.

Table 7-4.16 shows the overloaded 132 kV lines.

Page 42: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-41

Table 7-4.16 2020 Dry Season Peak - Overloaded Lines (base case and under N-1)

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

330 kV System

None

132 kV System

82024 IBOM IPP 1 82031 IKOT_ABASI 1 BASE CASE 125.7 182.1 144.8

82019 OMOKU 1 82036 RUMUSOI 1 2 SINGLE 82019-82036(1) 138.3 219 158.3

82019 OMOKU 1 82036 RUMUSOI 1 1 SINGLE 82019-82036(2) 138.3 219 158.3

42000 AJAOKUTA 1 42009 OKENE 1 1 SINGLE 42004-42008(1) 138.3 211.5 152.9

42004 BENIN 1 42008 IRRUA 1 1 SINGLE 42000-42009(1) 138.3 203.5 147.1

22002 OSOGBO 4T2 22008 IWO 1 1 SINGLE 22000-22006(1) 138.3 201.9 146

82017 YENAGOA 1 82022 GBARAIN UBIE 2 SINGLE 82017-82022(1) 138.3 191.2 138.2

82017 YENAGOA 1 82022 GBARAIN UBIE 1 SINGLE 82017-82022(2) 138.3 191.2 138.2

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 2 SINGLE 12003-12019(1) 138.3 176.8 127.9

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 1 SINGLE 12003-12019(2) 138.3 176.8 127.9

52033 MANDO T4A BB 52035 KUDENDA 1 2 SINGLE 52033-52035(1) 138.3 172.5 124.8

52033 MANDO T4A BB 52035 KUDENDA 1 1 SINGLE 52033-52035(2) 138.3 172.5 124.8

22000 AYEDE 1 22006 IBADAN NORTH 1 SINGLE 22002-22008(1) 138.3 172 124.4

82017 YENAGOA 1 82018 AHOADA 1 2 SINGLE 82017-82018(1) 138.3 171.4 123.9

82017 YENAGOA 1 82018 AHOADA 1 1 SINGLE 82017-82018(2) 138.3 171.4 123.9

62009 BIU 1 62026 DADINKOWA 1 1 SINGLE 63005-63007(1) 76.7 94.7 123.5

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82024-82031(1) 150.4 184.2 122.4

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82024-82031(1) 150.4 184.2 122.4

82007 PHCT MAIN1 82036 RUMUSOI 1 2 SINGLE 82007-82036(1) 138.3 166 120

82007 PHCT MAIN1 82036 RUMUSOI 1 1 SINGLE 82007-82036(2) 138.3 166 120

82000 AFAM 1-2-3 82002 AFAM IV 2 SINGLE 82000-82002(1) 138.3 160.2 115.8

82000 AFAM 1-2-3 82002 AFAM IV 1 SINGLE 82000-82002(2) 138.3 160.2 115.8

52015 ZARIA 1 52016 FUNTUA 1 1 SINGLE 32016-52004(1) 99.3 110.4 111.2

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82005-82024(1) 150.4 166.5 110.7

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82005-82024(2) 150.4 166.5 110.7

Source: JICA Study Team

7-4-3-2 2020 Wet Season Peak case-ACCC

The base case and N-1 contingency analysis results are shown in Table 7-4.17.

Table 7-4.17 2020 Wet Season Peak - Overloaded Lines (base case and under N-1)

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

330 kV System

None

132 kV System

82024 IBOM IPP 1 82031 IKOT_ABASI 1 BASE CASE 125.7 182.6 145.2

82019 OMOKU 1 82036 RUMUSOI 1 1 SINGLE 82019-82036(2) 138.3 220 159.1

42000 AJAOKUTA 1 42009 OKENE 1 1 SINGLE 42004-42008(1) 138.3 208.8 151

42004 BENIN 1 42008 IRRUA 1 1 SINGLE 42000-42009(1) 138.3 201.9 146

22002 OSOGBO 4T2 22008 IWO 1 1 SINGLE 22000-22006(1) 138.3 200.8 145.2

52033 MANDO T4A BB 52035 KUDENDA 1 2 SINGLE 52033-52035(1) 138.3 200.2 144.8

52033 MANDO T4A BB 52035 KUDENDA 1 1 SINGLE 52033-52035(2) 138.3 200.2 144.8

82017 YENAGOA 1 82022 GBARAIN UBIE 2 SINGLE 82017-82022(1) 138.3 191.2 138.3

82017 YENAGOA 1 82022 GBARAIN UBIE 1 SINGLE 82017-82022(2) 138.3 191.2 138.3

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 2 SINGLE 12003-12019(1) 138.3 180 130.1

Page 43: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-42

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 1 SINGLE 12003-12019(2) 138.3 180 130.1

62009 BIU 1 62026 DADINKOWA 1 1 SINGLE 63005-63007(1) 76.7 98.1 128

22000 AYEDE 1 22006 IBADAN NORTH 1 SINGLE 22002-22008(1) 138.3 172.9 125

82017 YENAGOA 1 82018 AHOADA 1 2 SINGLE 82017-82018(1) 138.3 171.5 124

82017 YENAGOA 1 82018 AHOADA 1 1 SINGLE 82017-82018(2) 138.3 171.5 124

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82024-82031(1) 150.4 184.5 122.7

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82024-82031(1) 150.4 184.5 122.7

82007 PHCT MAIN1 82036 RUMUSOI 1 2 SINGLE 82007-82036(1) 138.3 167.1 120.8

82007 PHCT MAIN1 82036 RUMUSOI 1 1 SINGLE 82007-82036(2) 138.3 167.1 120.8

82000 AFAM 1-2-3 82002 AFAM IV 2 SINGLE 82000-82002(1) 138.3 160.2 115.8

82000 AFAM 1-2-3 82002 AFAM IV 1 SINGLE 82000-82002(2) 138.3 160.2 115.8

23002 OMOTOSHO3 43002 BENIN 3 2 SINGLE 23002-43002(1) 855.1 948.8 111

23002 OMOTOSHO3 43002 BENIN 3 1 SINGLE 23002-43002(2) 855.1 948.8 111

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82005-82024(1) 150.4 166.4 110.6

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82005-82024(2) 150.4 166.4 110.6

52015 ZARIA 1 52016 FUNTUA 1 1 SINGLE 32016-52004(1) 99.3 106.3 107

82013 ONNE 1 82040 TRAMADI 2 SINGLE 82013-82040(1) 138.3 139.6 100.9

82013 ONNE 1 82040 TRAMADI 1 SINGLE 82013-82040(2) 138.3 139.6 100.9

Source: JICA Study Team

7-4-3-3 2020 Dry Season Off-Peak Case-ACCC

The base case and N-1 contingency analysis results are shown in Table 7-4.18. The 330 kV lines overloaded under N-1 are shown in red fonts.

Table 7-4.18 2020 Dry Season Off-Peak - Overloaded Lines (base case and under N-1)

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

330 kV

23002 OMOTOSHO3 43002 BENIN 3 2 SINGLE 23002-43002(1) 855.1 1,081.6 126.5

23002 OMOTOSHO3 43002 BENIN 3 1 SINGLE 23002-43002(2) 855.1 1,081.6 126.5

132 kV

82024 IBOM IPP 1 82031 IKOT_ABASI 1 BASE CASE 125.7 189.6 150.9

62000 GOMBE 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 151.3 197.2

82019 OMOKU 1 82036 RUMUSOI 1 2 SINGLE 82019-82036(1) 138.3 213.6 154.5

82019 OMOKU 1 82036 RUMUSOI 1 1 SINGLE 82019-82036(2) 138.3 213.6 154.5

62003 YOLA 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 114.4 149.2

52033 MANDO T4A BB 52035 KUDENDA 1 2 SINGLE 52033-52035(1) 138.3 202.6 146.5

52033 MANDO T4A BB 52035 KUDENDA 1 1 SINGLE 52033-52035(2) 138.3 202.6 146.5

82017 YENAGOA 1 82022 GBARAIN UBIE 2 SINGLE 82017-82022(1) 138.3 191.5 138.5

82017 YENAGOA 1 82022 GBARAIN UBIE 1 SINGLE 82017-82022(2) 138.3 191.5 138.5

82000 AFAM 1-2-3 82002 AFAM IV 2 SINGLE 82000-82002(1) 138.3 181.4 131.1

82000 AFAM 1-2-3 82002 AFAM IV 1 SINGLE 82000-82002(2) 138.3 181.4 131.1

22002 OSOGBO 4T2 22008 IWO 1 1 SINGLE 22000-22006(1) 138.3 175.5 126.9

62009 BIU 1 62026 DADINKOWA 1 1 SINGLE 63005-63007(1) 76.7 97.0 126.5

82017 YENAGOA 1 82018 AHOADA 1 2 SINGLE 82017-82018(1) 138.3 174.5 126.2

82017 YENAGOA 1 82018 AHOADA 1 1 SINGLE 82017-82018(2) 138.3 174.5 126.2

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82024-82031(1) 150.4 185.3 123.2

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82024-82031(1) 150.4 185.3 123.2

42000 AJAOKUTA 1 42009 OKENE 1 1 SINGLE 42004-42008(1) 138.3 169.9 122.9

82007 PHCT MAIN1 82036 RUMUSOI 1 2 SINGLE 82007-82036(1) 138.3 169.5 122.5

Page 44: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-43

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

82007 PHCT MAIN1 82036 RUMUSOI 1 1 SINGLE 82007-82036(2) 138.3 169.5 122.5

42004 BENIN 1 42008 IRRUA 1 1 SINGLE 42000-42009(1) 138.3 169.1 122.3

82013 ONNE 1 82040 TRAMADI 2 SINGLE 82013-82040(1) 138.3 157.5 113.9

82013 ONNE 1 82040 TRAMADI 1 SINGLE 82013-82040(2) 138.3 157.5 113.9

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 2 SINGLE 12003-12019(1) 138.3 153.1 110.7

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 1 SINGLE 12003-12019(2) 138.3 153.1 110.7

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82005-82024(1) 150.4 155 103.1

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82005-82024(2) 150.4 155 103.1

22000 AYEDE 1 22006 IBADAN NORTH 1 SINGLE 22002-22008(1) 138.3 142.4 103

Source: JICA Study Team

7-4-3-4 2020 Wet Season Off-Peak case-ACCC

The base case and N-1 contingency analysis results are shown in Table 7-4.19. The 330 kV lines overloaded under N-1 are shown in red fonts.

Table 7-4.19 2020 Wet Season Off- peak - Overloaded Lines (base case and under N-1)

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

330 kV System

23002 OMOTOSHO3 43002 BENIN 3 2 SINGLE 23002-43002(1) 855.1 944.4 110.4

23002 OMOTOSHO3 43002 BENIN 3 1 SINGLE 23002-43002(2) 855.1 944.4 110.4

132 kV System

82024 IBOM IPP 1 82031 IKOT_ABASI 1 BASE CASE 125.7 189.4 150.7

62000 GOMBE 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 153.2 199.7

62003 YOLA 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 116.3 151.6

52033 MANDO T4A BB 52035 KUDENDA 1 2 SINGLE 52033-52035(1) 138.3 202.5 146.4

52033 MANDO T4A BB 52035 KUDENDA 1 1 SINGLE 52033-52035(2) 138.3 202.5 146.4

62009 BIU 1 62026 DADINKOWA 1 1 SINGLE 63005-63007(1) 76.7 98.2 128.1

22002 OSOGBO 4T2 22008 IWO 1 1 SINGLE 22000-22006(1) 138.3 175.5 126.9

42004 BENIN 1 42008 IRRUA 1 1 SINGLE 42000-42009(1) 138.3 171.2 123.8

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82024-82031(1) 150.4 184.6 122.7

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82024-82031(1) 150.4 184.6 122.7

42000 AJAOKUTA 1 42009 OKENE 1 1 SINGLE 42004-42008(1) 138.3 169.4 122.5

82007 PHCT MAIN1 82014 RIVERS_IPP 2 SINGLE 82007-82014(1) 138.3 155.2 112.2

82007 PHCT MAIN1 82014 RIVERS_IPP 1 SINGLE 82007-82014(2) 138.3 155.2 112.2

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 2 SINGLE 12003-12019(1) 138.3 153.8 111.2

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 1 SINGLE 12003-12019(2) 138.3 153.8 111.2

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82005-82024(1) 150.4 156.7 104.2

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82005-82024(2) 150.4 156.7 104.2

22000 AYEDE 1 22006 IBADAN NORTH 1 SINGLE 22002-22008(1) 138.3 142.4 103.0

Source: JICA Study Team

7-4-4 Summary of Results of Load-flow Analysis for 2020

The results of the static security analysis for 2020 are summarized as follows:

7-4-4-1 Overloaded 330 and 132 kV Transmission Lines

There are no overloads in 330 kV lines under normal operation. However, when tripping the 330 kV lines from Gombe to Yola and Damaturu, the load-flow case did not converge, as expected, due to the absence of

Page 45: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-44

a second parallel circuit and insufficient support from alternative routes. Converting to a Double-Circuit will resolve these issues.

Under N-1, if any of the following 132 kV lines are tripped, the case will also not converge:

From BKebbi to KVK Power PV From Zaria to Funtua

These 132 kV N-1 cases will have to be resolved by providing new alternative routes for the power flow.

Priority is to resolve the overloads occurring under normal (N-0) operation of the 132 kV lines shown in Table 7-4.20.

Table 7-4.20 Reinforcements of 132 kV lines overloaded under N-0

Bus Name Bus Name Proposed Solution

Ibom IPP Ikot Abasi convert to DC

Source: JICA Study Team

As a next priority, the overloaded 330 and 132 kV lines under N-1 contingencies must be reinforced. This entails either reconductoring to higher rating conductors or, in the case of SC, converting to DC by installing a second parallel circuit.

The lines in Table 7-4.21 are ranked according to their percentage overload. The table lists the worst scenarios in terms of overloads, out of the four study cases (DP, DoP, WP, WoP). The shaded lines are DC lines for which reconductoring is recommended. The 330 kV lines overloaded under N-1 are shown in red fonts.

Table 7-4.21 Reinforcements of 330 and 132 kV lines overloaded under N-1

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

330 kV

23002 OMOTOSHO3 43002 BENIN 3 cct1 SINGLE 23002-43002(1) 855.1 1,081.6 126.5

23002 OMOTOSHO3 43002 BENIN 3 cct2 SINGLE 23002-43002(2) 855.1 1,081.6 126.5

132 kV

82024 IBOM IPP 1 82031 IKOT_ABASI 1 BASE CASE 125.7 189.6 150.9

62000 GOMBE 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 151.3 197.2

82019 OMOKU 1 82036 RUMUSOI 1 1 SINGLE 82019-82036(2) 138.3 220 159.1

82019 OMOKU 1 82036 RUMUSOI 1 2 SINGLE 82019-82036(1) 138.3 213.6 154.5

42000 AJAOKUTA 1 42009 OKENE 1 1 SINGLE 42004-42008(1) 138.3 211.5 152.9

62003 YOLA 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 116.3 151.6

42004 BENIN 1 42008 IRRUA 1 1 SINGLE 42000-42009(1) 138.3 203.5 147.1

52033 MANDO T4A BB 52035 KUDENDA 1 2 SINGLE 52033-52035(1) 138.3 202.6 146.5

52033 MANDO T4A BB 52035 KUDENDA 1 1 SINGLE 52033-52035(2) 138.3 202.6 146.5

22002 OSOGBO 4T2 22008 IWO 1 1 SINGLE 22000-22006(1) 138.3 201.9 146

82017 YENAGOA 1 82022 GBARAIN UBIE 2 SINGLE 82017-82022(1) 138.3 191.5 138.5

82017 YENAGOA 1 82022 GBARAIN UBIE 1 SINGLE 82017-82022(2) 138.3 191.5 138.5

82000 AFAM 1-2-3 82002 AFAM IV 2 SINGLE 82000-82002(1) 138.3 181.4 131.1

82000 AFAM 1-2-3 82002 AFAM IV 1 SINGLE 82000-82002(2) 138.3 181.4 131.1

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 2 SINGLE 12003-12019(1) 138.3 180 130.1

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 1 SINGLE 12003-12019(2) 138.3 180 130.1

Page 46: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-45

Bus Number

Bus Name Bus

Number Bus Name cct Contingency Label

Rating (MVA)

Flow (MVA)

Loading (%)

62009 BIU 1 62026 DADINKOWA 1 1 SINGLE 63005-63007(1) 76.7 98.2 128.1

82017 YENAGOA 1 82018 AHOADA 1 2 SINGLE 82017-82018(1) 138.3 174.5 126.2

82017 YENAGOA 1 82018 AHOADA 1 1 SINGLE 82017-82018(2) 138.3 174.5 126.2

22000 AYEDE 1 22006 IBADAN NORTH 1 SINGLE 22002-22008(1) 138.3 172.9 125

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82024-82031(1) 150.4 184.5 122.7

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82024-82031(1) 150.4 184.5 122.7

82007 PHCT MAIN1 82036 RUMUSOI 1 2 SINGLE 82007-82036(1) 138.3 169.5 122.5

82007 PHCT MAIN1 82036 RUMUSOI 1 1 SINGLE 82007-82036(2) 138.3 169.5 122.5

82013 ONNE 1 82040 TRAMADI 2 SINGLE 82013-82040(1) 138.3 157.5 113.9

82013 ONNE 1 82040 TRAMADI 1 SINGLE 82013-82040(2) 138.3 157.5 113.9

82007 PHCT MAIN1 82014 RIVERS_IPP 2 SINGLE 82007-82014(1) 138.3 155.2 112.2

82007 PHCT MAIN1 82014 RIVERS_IPP 1 SINGLE 82007-82014(2) 138.3 155.2 112.2

52015 ZARIA 1 52016 FUNTUA 1 1 SINGLE 32016-52004(1) 99.3 110.4 111.2

Source: JICA Study Team Note: It should be noted that with regard to the overloaded 330 kV lines in 2020 (Benin-Omotosho), remedial actions are already

planned and these lines will not be overloaded in 2025, as shown in Section 7.5.

7-4-4-2 Overloaded Transformers

(1) Overloads above 100% of transformer ratings

The 330/132 kV 3-W and A/T transformers overloaded above their 100% rating MVA under normal (base case) operation, listed in Table 7-4.22, must be upgraded:

Table 7-4.22 Upgrading requirements of 330/132 kV 3-winding transformers overloaded under N-0

Bus Number

Bus Name Voltage

(kV) Bus Name

Loading (MVA)

Rating (MVA)

Loading (%)

330/132 kV 3-W transformers

43002 BENIN 3 330 BENIN TR3 156 150 145.6

43011 B.NORTH_3 330 BENIN 9T1 88 67.5 131.6

33002 BKEBBI 3 330 B_KEBBI T1 176.9 150 118

23003 GANMO 3 330 GANMO TR2A 157.4 150 104.9

43002 BENIN 3 330 BENIN TR1 156 150 104

43002 BENIN 3 330 BENIN TR2 156 150 104

Source: JICA Study Team

The 132/33 kV and 132/11 kV transformers overloaded above their 100% rating MVA under normal (base case) operation, listed in Table 7-4.23, must be upgraded:

Table 7-4.23 Upgrading requirements of 132/33 kV and 132/11 kV 2W transformers

overloaded under N-0

Bus Number

Bus Name

Voltage (kV)

Bus Number

Bus Name

Voltage (kV)

Loading (MVA)

Rating (MVA)

Loading (%)

132/33 and 132/11 kV 2-W transformers

32017 SULEJA 1 132 36016 SULEJA 11 11 18.6 7.5 247.6

42004 BENIN 1 132 45029 BENIN T22 33 33 85.9 60 143.1

52001 KANO 1 132 55058 KUMB T3 MOB 33 41.9 30 139.6

42004 BENIN 1 132 45031 BENIN T24 33 33 82.9 60 138.1

42004 BENIN 1 132 45030 BENIN T23 33 33 80.9 60 134.8

52016 FUNTUA 1 132 56000 FUNTUA 11 11 9.6 7.5 127.6

42005 B_N0RTH 1 132 45015 B_NORTH_33 33 73.9 60 123.2

Page 47: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-46

Bus Number

Bus Name

Voltage (kV)

Bus Number

Bus Name

Voltage (kV)

Loading (MVA)

Rating (MVA)

Loading (%)

22015 OMUARAN 1 132 25016 OMUARAN 33 33 33.4 30 111.4

52016 FUNTUA 1 132 55003 FUNTUA 33 33 33 30 109.9

52016 FUNTUA 1 132 56005 FUNTUA T2 11 7.9 7.5 105.9

22013 OFFA 1 132 25015 OFFA 33 33 31.8 30 105.8

12029 OJO 1 132 15030 OJO 33 33 30.4 30 101.4

Source: JICA Study Team

(2) Overloads above 85% of transformer ratings

Table 7-4.24 shows 330/132 kV, 132/33 kV and 132/11 kV transformers which are overloaded above their 85% rating MVA under normal (base case) operation and shall be considered for upgrading.

Table 7-4.24 Upgrading requirements of 330/132 kV, 132/33 kV and

132/11 kV transformers overloaded over 85% under N-0

Bus Number

Bus Name

Voltage (kV)

Bus Number

Bus Name

Voltage (kV)

cct Load

(MVA) Rating (MVA)

Loading (%)

330/132 kV Transformers 3-W

52001 KANO 1 132 3WNDTR KANO T3A WND 2 1 112.3 120 93.6

42005 B_N0RTH 1 132 3WNDTR BENIN 9T1 WND 1 1 82.8 90 92

132/33 kV and 132/11 kV Transformers

82005 EKET 1 132 85002 EKET T1B 33 1 43.7 45 97.2

12055 ODOGUNYAN 1 132 15063 ODOGUNYA 33 33 1 57.9 60 96.5

12055 ODOGUNYAN 1 132 15063 ODOGUNYA 33 33 2 57.9 60 96.5

22022 GANM0 T1 BB 132 25032 GANMO T1 33 1 57.1 60 95.2

12023 EJIGBO 1 132 15128 EJIGBO 33 33 1 28.4 30 94.5

12023 EJIGBO 1 132 15128 EJIGBO 33 33 2 28.4 30 94.5

12029 OJO 1 132 15047 OJO T3_T4 33 5 55.8 60 92.9

12019 ALIMOSHO 1 132 15072 ALIMOSHO T1 33 3 27.5 30 91.8

42002 UGHELLI 1 132 45001 UGHELLI 33 33 1 53.6 60 89.3

12037 PARAS_1 132 15116 AFR FOUNDRY 33 1 35.6 40 89

22027 SHAGAMU 1 132 25035 SHAGAMU 33 33 1 26.5 30 88.3

82000 AFAM 1-2-3 132 86000 AFAM 11 11 1 55.1 64 86.1

22008 IWO 1 132 25002 IWO 33 33 1 12.9 15 85.9

22008 IWO 1 132 25002 IWO 33 33 2 34.3 40 85.9

82005 EKET 1 132 85002 EKET T1B 33 1 43.7 45 97.2

Source: JICA Study Team

7-4-4-3 Undervoltages Under N-1 Conditions

In all N-1 contingencies, a number of 132 kV voltages are lower than the minimum permissible level of 0.8p.u. However, this is due to overloads of the associated 132 kV lines and transformers and the remedial actions for the undervoltages (U/V) is linked with the solutions required first for overloads of these circuits, as well as with the implementation of reactive power compensation equipment.

The reactive power requirements, i.e. the need to have existing reactors and capacitors in operation and/or install new ones by 2020, including the need for new SVCs, are summarized in the following sections:

Page 48: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-47

(1) SVC requirements

No SVC at Gombe is necessary by 2020.

(2) Reactors

The status of reactors required in the Dry Season Peak case is shown in Table 7-4.25. It can be seen that only reactors at Gombe, Yola and Maiduguri are required. The new equipment required is shown in bold:

Table 7-4.25 Reactor requirements for 2020 Dry Season Peak

Bus Number

Bus Name Voltage

(kV) Id In Service

B-Shunt (MVar)

63005 MAIDUGURI 3 330.00 330 2 1 -75.00

63002 YOLA 3 330.00 330 1 1 -75.00

63002 YOLA 3 330.00 330 2 1 -75.00

63000 GOMBE 3 330.00 330 1 1 -50.00

63000 GOMBE 3 330.00 330 2 1 -50.00

65001 YOLA T1 33 33.000 33 1 1 -30.00

65014 GOMBE T4A 33.000 33 1 1 -30.00

Source: JICA Study Team

The status of reactors required in Dry Season Off-Peak and in Wet Season Off-Peak cases is shown in Table 7-4.26. The new equipment required is shown in bold:

Table 7-4.26 Reactor requirements for 2020 dry and wet season off-peak

Bus Number

Bus Name Voltage

(kV) Id

In Service

B-Shunt (MVar)

53001 KANO 3 330 1 1 -75

63001 JOS 3 330 1 1 -75

63002 YOLA 3 330 1 1 -75

63002 YOLA 3 330 2 1 -75

63005 MAIDUGURI 3 330 2 1 -75

63000 GOMBE 3 330 1 1 -50

63000 GOMBE 3 330 2 1 -50

65001 YOLA T1 33 33 1 1 -30

65014 GOMBE T4A 33 1 1 -30

Source: JICA Study Team

(3) Capacitors

The status of capacitors required in the Dry Season Peak case is shown in Table 7-4.27. The new equipment required is shown in bold:

Table 7-4.27 Capacitor requirements for 2020 Dry Season Peak

Bus Number

Bus Name Voltage

(kV) Id

In Service

Capacity (MVar)

62021 MAIDUGURI 1 132 1 1 10.8

52022 HADEJIA 1 132 1 1 20

22017 ONDO2 1 132 1 1 24

42008 IRRUA 1 132 1 1 24

52011 GUSAU 1 132 1 1 50

12004 AKANGBA BBII 132 1 1 72

Page 49: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-48

Bus Number

Bus Name Voltage

(kV) Id

In Service

Capacity (MVar)

15002 AGBARA 33 33 1 1 20

15022 IKORODU 33 33 2 1 20

15027 ILUPEJU 33 33 1 1 20

25018 AKURE T3A 33 33 1 1 20

45003 OKENE 33 33 1 1 20

55001 DAN AGUNDI 3 33 2 1 20

55010 KATSINA 33 33 1 1 20

15037 NEW ABEOK 33 33 1 1 20

25004 AYEDE 33 33 1 1 20

25012 ISEYIN 33 33 1 1 20

25035 SHAGAMU 33 33 1 1 20

25038 IJEBU-ODE 33 33 1 1 20

15006 AKANGBA 33 33 1 1 24

15007 AKOKA T1 33 33 1 1 24

15009 ALAUSA 33 33 1 1 24

15010 ALIMOSHO 33 33 1 1 24

15014 EJIGBO 33 33 1 1 24

15015 IJORA 33 33 1 1 24

15018 OGBA 33 33 1 1 24

15028 ISOLO 33 33 1 1 24

15128 EJIGBO 33 33 1 1 24

15079 OTTA T2 33 1 1 24

15080 OLD ABEOK T2 33 3 1 24

25011 ILORIN 33 33 1 1 24

Source: JICA Study Team

The status of capacitors required in Dry Season Off-Peak case is shown in Table 7-4.28.

Table 7-4.28 Capacitor requirements for 2020 Dry Season Off-Peak

Bus Number

Bus Name Voltage

(kV) Id

In Service

Capacity (MVar)

62021 MAIDUGURI 1 132 1 1 10.8

52022 HADEJIA 1 132 1 1 20

22017 ONDO2 1 132 1 1 24

42008 IRRUA 1 132 1 1 24

52011 GUSAU 1 132 1 1 50

12004 AKANGBA BBII 132 1 1 72

15002 AGBARA 33 33 1 1 20

15022 IKORODU 33 33 2 1 20

15027 ILUPEJU 33 33 1 1 20

15037 NEW ABEOK 33 33 1 1 20

25004 AYEDE 33 33 1 1 20

25012 ISEYIN 33 33 1 1 20

25018 AKURE T3A 33 33 1 1 20

25035 SHAGAMU 33 33 1 1 20

25038 IJEBU-ODE 33 33 1 1 20

45003 OKENE 33 33 1 1 20

55001 DAN AGUNDI 3 33 2 1 20

55010 KATSINA 33 33 1 1 20

15006 AKANGBA 33 33 1 1 24

Page 50: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-49

Bus Number

Bus Name Voltage

(kV) Id

In Service

Capacity (MVar)

15007 AKOKA T1 33 33 1 1 24

15009 ALAUSA 33 33 1 1 24

15010 ALIMOSHO 33 33 1 1 24

15014 EJIGBO 33 33 1 1 24

15015 IJORA 33 33 1 1 24

15018 OGBA 33 33 1 1 24

15028 ISOLO 33 33 1 1 24

15079 OTTA T2 33 1 1 24

15080 OLD ABEOK T2 33 3 1 24

15128 EJIGBO 33 33 1 1 24

25011 ILORIN 33 33 1 1 24

Source: JICA Study Team

7-4-4-4 Power Factor Correction at DisCo’s Level

With reference to the Grid Code requirements (ref. article 15.6 on Demand power factor corrections and 16.7 on the provision of voltage control stating that The Off-takers shall maintain a power factor not less than 0.95 at the Connection Point), since the resulting power factor of loads connected at 33 kV level and below is less than the 0.95 required, all DisCos shall be required to undertake a program of having capacitors installed at distribution level to ensure the power factor at all 33 kV S/S is not less than 0.9 by 2020 and 0.95 by 2025, in line with the Grid Code requirements. (Note: the loads in the 2025 model however have been based on a conservative power factor of 0.92 and only the 2030 loads have a pf of 0.95)

7-4-5 Expansion Plan for 2020

7-4-5-1 Transmission Lines

As shown in the SLDs of Annexes 7.4.1 and 7.4.2, the transmission lines shown in Table 7-4.29 must be implemented by 2020 or as soon as possible thereafter. Line Nos. 1 to 5 in Table 7-4.29 require reconductoring only. A priority ranking from 1 to 3 has been included in this table, with 1 denoting the highest priority.

Page 51: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-50

Table 7-4.29 New transmission lines required by 2020

No From To

kV km Remarks Priority/Ranking

1

Part of

North-East

Ring

Damaturu Maiduguri DC 330 260 An SC already exists. 1

2 Gombe Damaturu DC 330 180 An SC already exists. 1

3 Gombe Yola DC 330 240 An SC already exists. 1

4 Yola Jalingo DC 330 160 Can be delayed beyond 2020 but ASAP

thereafter. One circuit via Mayo Belwa. 3

5 Jos Gombe DC 330 270

Via Bauchi.

Should be completed by 2020 or ASAP

thereafter.

A SC already exists.

1

6

Part of

North-West

ring

Kainji Birnin-Kebbi DC 330 310

An SC already exists. Needs to be

expedited by 2020 if possible or ASAP

thereafter.

3

7 Kaduna Kano DC 330 230

Undertaken by TCN as part of the NTEP

to be financed by IDB. Needs to be

expedited by 2020 if possible or ASAP

thereafter.

2

8 Akangba Ijora DC 330 14 A 330kV substation at Ijora and

associated 330kV lines are necessary

after 2020, but since they remove in

2020 the overloads at 132kV

Ijora-Alagbon line and improve voltage

profile in the area, it is recommended to

implement as soon as possible after

2020.

2

9 Ijora Alagbon DC 330 8 2

10 Arigbajo New Agbara DC 330 40

If not undertaken by JICA.

Not considered necessary for 2020, as it

is lightly loaded. However, it is necessary

for meeting the N-1 criterion for the

export lines to Sakete.

2

11 Ugwaji Abakaliki DC 330 85 1

12 Osogbo Arigbajo DC 330 183 If not undertaken by JICA. 1

13 Ayede Ibadan North DC 132 15 An SC exists. A second circuit in parallel is

needed. 1

14 New Agbara Agbara DC 132 18 2

15 Ogijo Redeem DC 132 14 If not undertaken by JICA. 2

16 Birmin Kebbi Dosso DC 132 128 An SC already exists. 2

Source: JICA Study Team Notes: The lines recommended for the North-East ring above must comply with the N-1 static security criterion, as well as

improving the voltage stability of the area. It is recognized however that in implementation terms it will be challenging to complete it all by 2020. However, if it is not possible to implement by 2020, they should be implemented as soon as possible thereafter within the period 2020-2025, based on which the investment plan detailed in Section 9 has been drawn up.

The JICA project of new 330 kV lines (DC) from Ogijo to Arigbajo is not considered necessary in 2020, as it is lightly loaded under all scenarios (it will be required, though, in 2025).

The JICA project of new 330 kV lines (DC) from Arigbajo to New Agbara is not considered necessary for 2020, as it is lightly loaded. It is necessary only for meeting the N-1 criterion for the export lines to Sakete.

As shown in Section 8, the first priority is to resolve the overloads occurring under normal (N-0) operation of the following 132 kV lines shown in Table 7-4.30:

Page 52: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-51

Table 7-4.30 Reinforcements of 132 kV lines overloaded under N-0

From To Proposed solution

Ibom IPP Ikot Abasi Convert to DC

Source: JICA Study Team

As a next priority, the overloaded 330 and 132 kV lines under N-1 contingencies must be reinforced. This entails either reconductoring to higher rating conductors or, in case of SC, conversion to DC by installing a second parallel circuit.

The lines in Table 7-4.31 are ranked according to their percentage overload. The shaded lines are DC lines for which reconductoring is recommended.

Table 7-4.31 Reinforcements of 132 kV lines overloaded under N-1

FROM Bus No.

Bus name TO Bus No.

Bus name cct Contingency label Rating (MVA)

Flow (MVA)

Loading (%)

330 kV

23002 OMOTOSHO3 43002 BENIN 3 cct1 SINGLE 23002-43002(1) 855.1 1081.6 126.5

23002 OMOTOSHO3 43002 BENIN 3 cct2 SINGLE 23002-43002(2) 855.1 1081.6 126.5

132 kV

82024 IBOM IPP 1 82031 IKOT_ABASI 1 BASE CASE 125.7 189.6 150.9

62000 GOMBE 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 151.3 197.2

82019 OMOKU 1 82036 RUMUSOI 1 1 SINGLE 82019-82036(2) 138.3 220 159.1

82019 OMOKU 1 82036 RUMUSOI 1 2 SINGLE 82019-82036(1) 138.3 213.6 154.5

42000 AJAOKUTA 1 42009 OKENE 1 1 SINGLE 42004-42008(1) 138.3 211.5 152.9

62003 YOLA 1 62013 T_JUNCTION 1 1 SINGLE 63000-63002(1) 76.7 116.3 151.6

42004 BENIN 1 42008 IRRUA 1 1 SINGLE 42000-42009(1) 138.3 203.5 147.1

52033 MANDO T4A BB 52035 KUDENDA 1 2 SINGLE 52033-52035(1) 138.3 202.6 146.5

52033 MANDO T4A BB 52035 KUDENDA 1 1 SINGLE 52033-52035(2) 138.3 202.6 146.5

22002 OSOGBO 4T2 22008 IWO 1 1 SINGLE 22000-22006(1) 138.3 201.9 146

82017 YENAGOA 1 82022 GBARAIN UBIE 2 SINGLE 82017-82022(1) 138.3 191.5 138.5

82017 YENAGOA 1 82022 GBARAIN UBIE 1 SINGLE 82017-82022(2) 138.3 191.5 138.5

82000 AFAM 1-2-3 82002 AFAM IV 2 SINGLE 82000-82002(1) 138.3 181.4 131.1

82000 AFAM 1-2-3 82002 AFAM IV 1 SINGLE 82000-82002(2) 138.3 181.4 131.1

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 2 SINGLE 12003-12019(1) 138.3 180 130.1

12003 IKEJA W 1BB1 12019 ALIMOSHO 1 1 SINGLE 12003-12019(2) 138.3 180 130.1

62009 BIU 1 62026 DADINKOWA 1 1 SINGLE 63005-63007(1) 76.7 98.2 128.1

82017 YENAGOA 1 82018 AHOADA 1 2 SINGLE 82017-82018(1) 138.3 174.5 126.2

82017 YENAGOA 1 82018 AHOADA 1 1 SINGLE 82017-82018(2) 138.3 174.5 126.2

22000 AYEDE 1 22006 IBADAN NORTH 1 SINGLE 22002-22008(1) 138.3 172.9 125

82005 EKET 1 82024 IBOM IPP 1 1 SINGLE 82024-82031(1) 150.4 184.5 122.7

82005 EKET 1 82024 IBOM IPP 1 2 SINGLE 82024-82031(1) 150.4 184.5 122.7

82007 PHCT MAIN1 82036 RUMUSOI 1 2 SINGLE 82007-82036(1) 138.3 169.5 122.5

82007 PHCT MAIN1 82036 RUMUSOI 1 1 SINGLE 82007-82036(2) 138.3 169.5 122.5

82013 ONNE 1 82040 TRAMADI 2 SINGLE 82013-82040(1) 138.3 157.5 113.9

82013 ONNE 1 82040 TRAMADI 1 SINGLE 82013-82040(2) 138.3 157.5 113.9

82007 PHCT MAIN1 82014 RIVERS_IPP 2 SINGLE 82007-82014(1) 138.3 155.2 112.2

82007 PHCT MAIN1 82014 RIVERS_IPP 1 SINGLE 82007-82014(2) 138.3 155.2 112.2

52015 ZARIA 1 52016 FUNTUA 1 1 SINGLE 32016-52004(1) 99.3 110.4 111.2

Source: JICA Study Team Note: It should be noted that with regard to the overloaded 330 kV lines in 2020 (Benin-Omotosho), remedial actions are already

planned and these lines will not be overloaded in 2025.

7-4-5-2 Transformers

Page 53: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-52

The upgrading of 6 x 330/132 kV 3-W and A/T transformers which are overloaded above their 100% rating MVA under normal (base case) operation, is required, as listed in Table 7-4.22.

The upgrading of 12 x 132/33 kV and 132/11 kV transformers which are overloaded above their 100% rating MVA under normal (base case) operation, is required, as listed in Table 7-4.23.

The upgrading of the following types of transformers overloaded above their 85% rating MVA under normal (base case) operation shall be upgraded, as listed in Table 7-4.24: a) 2 x 330/132 kV 3-w and A/T, b) 15 x 132/33 kV and 132/11 kV transformers

7-4-5-3 Reactive Power Compensation

(1) SVC requirements

No SVC at Gombe is necessary by 2020.

(2) Reactors

The new reactors required in the Dry Season Peak and Dry Season Off-Peak cases are shown in Table 7-4.32. Only reactors at Gombe, Yola and Maiduguri must be in operation. The new reactor at Maiduguri is shown in bold:

Table 7-4.32 Reactor requirements for 2020

Bus Number

Bus Name Voltage

(kV) Id

In Service

B-Shunt (MVar)

63005 MAIDUGURI 3 330.00 330 2 1 -75.00

Source: JICA Study Team

(3) Capacitors

The new capacitors required in the Dry Season Peak, Dry Season Off-Peak and Wet Season Off-Peak cases are shown in Table 7-4.33:

Table 7-4.33 Capacitor requirements for 2020

Bus Number

Bus Name Voltage

(kV) Id

In Service

B-Shunt (MVar)

22017 ONDO2 1 132 1 1 24

42008 IRRUA 1 132 1 1 24

52011 GUSAU 1 132 1 1 50

Source: JICA Study Team

7-4-6 Fault Analysis

Short-circuit calculations were carried out for three-phase faults under all load scenarios. As a result of the calculations, design parameters for new substations and lines, short-circuit levels on existing substations and the impact of the expansion measures are shown. It is important to calculate the short-circuit currents since they are a measure to indicate the strength of both systems which will be interconnected.

The short-circuit calculations were performed according to the IEC 60909 standard and the following

Page 54: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-53

values were determined at all 330 and 132 kV substations in the TCN network:

3-phase symmetrical short-circuit power Sk3 (MVA) Ik3” total symmetrical short-circuit current for three-phase solid faults

The calculations are based on the operational condition available in the corresponding load-flow scenarios.

The results of the preliminary fault analysis are summarized in Annex 7.4.10 (Table 1) for all 330 and 132 kV substations. The generators sub-transient reactance are used.

The most critical 330 and 132 kV substations are shown in Table 7-4.34.

Table 7-4.34 Fault analysis results 2020

Bus Number

Bus Name Voltage

(kV) I

(A) Bus

Number Bus Name

Voltage (kV)

I (A)

43002 BENIN 3 330 30,340 82000 AFAM 1-2-3 132 29,882

83000 AFAM IV 3 330 29,491 82002 AFAM IV 132 29,767

83002 ALAOJI 3 330 28,225 12003 IKEJA W 1BB1 132 28,156

83001 ALAOJI NIPP3 330 27,810 82019 OMOKU 1 132 26,663

43011 B_NORTH_3 330 27,132 12042 OKE_ARO_1 132 25,624

Source: JICA Study Team

The most critical 330 kV substations are BENIN, AFAM IV, ALAOJI and BENIN NORTH, with fault levels ranging from 30.3 kA to 27.1 kA for a 3ph busbar fault.

The most relatively critical 132 kV substation is AFAM and IKEJA WEST, with fault levels of 29.8 and 28.1 kA. It is clear from this analysis that the TCN standard switchgear ratings of 31.5 kA will be inadequate in future when new power plants are commissioned in later years.

a) Install switchgear with higher capacity breakers (63 kA).

b) Study different topological configurations of the elements connected to the different bus sections.

c) Install Current Limiting Reactors (CLR) aiming to reduce the short-circuit current contributions from adjacent bus sections.

Page 55: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-54

7-5 Expansion Plan for 2025

7-5-1 Static Security Analysis, Year 2025

7-5-1-1 Transmission lines

The network configuration for 2025 is shown in the PSS/E SLD of Annex 7.5.1

7-5-1-2 Evacuation from Mambilla HPP

(1) New transmission lines

A major development for 2025 is the operation of the first units of the Mambilla HPP. The new transmission lines required to evacuate the power from Mambilla will have to be designed to evacuate full power, assuming power of 2,400 MW is to be evacuated from the Mambilla Hydro Power Plant:

1. If the N-1 criterion is to be maintained, as per the current Grid Code, the following is proposed:

a) 330/132/33 kV substation at Wukari

b) Double-Circuit with Quad Bison conductors from Mambilla to Wukari

c) Double-Circuit with Quad Bison conductors from Wukari to Makurdi

d) Double-Circuit with Quad Bison conductors from Mambilla to Jailingo (to close the 330-kV loop)

2. Due to the importance of the power station and in line with international practice by other utilities, it is proposed to apply the N-2 criteria only for the transmission lines leaving the power plant. If this is adopted, it would be necessary to have:

a) Two Double Circuits with Quad Bison conductors from Mambila to Wukari

b) Two Double Circuits with Quad Bison conductors from Mambila to Jailingo

Each Quad Bison circuit will be rated 1,550MVA approx. The scheme is shown on the Single-Line Diagram of Figure 7-5.1.

In both cases, two evacuation routes must be maintained (one towards Makurdi and another towards Jalingo) at all times, since 2,400MW will not be able to be evacuated through one route only, given that bottlenecks will occur downstream, beyond Makurdi and Jalingo respectively.

Page 56: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-55

Source: JICA Study Team

Figure 7-5.1 Evacuation from Mambilla HPP

(2) PV analysis

A PV analysis was carried out to determine the maximum power that can be evacuated from Mambilla HPP (MHPP).

The starting scenario was set up with an initial generation of 1,000 MW at MHPP and both base case and contingency (N-1) conditions were analyzed. It was determined that:

Under base case (normal) conditions, an additional 2,000 MW can be evacuated, i.e. a total of 3,000 MW, before a 330-kV line in the TCN system reaches its limit.

Under contingency conditions, an additional 1,700 MW can be evacuated, i.e. total 2,700 MW, before a line in the TCN system reaches its thermal limit (777 MVA), in this case the Gombe-Yola 330 kV line (cct1) when the other Gombe-Yola line (cct 2) is tripped. This is shown in the graphs of Figure 7-5.2.

QUAD QUAD

QUAD

1

63006JALINGO_3

1

63002YOLA 3

483

67

504

194

1

2

63000GOMBE 3

340

66

357

19

340

66

357

19

1

2

SW

0

138

112

134

74

1

33023LAFIA 3

395

25

381

79

395

25

381

79

619

52

636

60

619

52

636

60

175

8

24

175

8

177

24

571

230

295

571

230

578

295

63009WUKARI 3

531

63

521

14

179

609

71

531

63

521

14

609

71

622

179 141

97

141

97

73003MAKURDI_3

73004ALIADE_3

177

33022APO_NEW 3

63001JOS 3

166

102

96

84

63003BAUCHI 3

622

493

62

101

505

199

491

108

63008MAMBILA 3

63015MAYOBELWA

578

499

240

95

240

95

240

95

240

95

240

95

240

95

240

95

240

95

240

95

240

95

1240

114R

1240

114R

1240

114R

1240

114R

1240

114R

1240

114R

1240

114R

1240

114R

1240

114R

1240

114R

Page 57: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-56

Source: JICA Study Team

Figure 7-5.2 PV Analysis for Mambilla Evacuation

Considering that the Mambilla plant is rated 3,000 MW and is highly unlikely to reach production exceeding 2,400 MW, it is concluded that all power can be evacuated without any additional reinforcements in the transmission system required.

(3) Specifications of transmission lines

The following data is used: the 330-kV conductor is 4-bundle ACSR350 per phase, spaced at 400 mm. The conductor types (aluminum conductor steel reinforced):

Page 58: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-57

ACSR 350 ‘Bison’ (381-AL1/49-ST1A; 54 Al wires diameter 3.0 mm; seven Fe wires diameter 3.0 mm, i.e. 54/7), Outside diameter 27 mm. The Basic Conductor Characteristics are in Table 7-5.1

Table 7-5.1 Basic Conductor Characteristics for 330 kV OHL

Description Value

Cross-section

Aluminum (mm2) 381.6

Steel (mm2) 49.4

Total (mm2) 431

Stranding and wire diameter

Aluminum (mm) 54 / 3.0

Steel (mm) 7 / 3.0

Overall diameter (mm) 27

(4) 330 kV Transmission Line R, X and B

The tower design is shown in Figure 7-5.3 and the conductors’ arrangements in Figure 7-5.4.

Source: JICA Study Team Figure 7-5.3 Tower Design

Page 59: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-58

Based on the above, with d=400mm (1.32 ft):

d=400mm=1.32ft

D12= 10.5m= 34.44ft D23=10.5m=34.44ft

D13=21m=68.88ft

Source: JICA Study Team

Figure 7-5.4 Conductors Spacing 330 kV Line

In general:

2-strand bundle 3-strand bundle 4-strand bundle

d d d

The Geometric Mean Radius (GMR) of bundled conductors:

𝐷𝑠𝑏 = √𝐷𝑠. 𝑑 𝐷𝑠

𝑏 = √𝐷𝑠. 𝑑23 𝐷𝑠𝑏 = 1.09 √𝐷𝑠. 𝑑34

where Ds is the GMR of one stranded conductor.

For Bison conductors, the GMR (=Ds) of one conductor, as taken from tables, is:

GMR=Ds=0.0363 ft

For bundled conductors the equivalent GMR is

𝐷𝑠𝑏 = √𝐷𝑠. 𝑑 for 2-bundle conductors (1)

𝐷𝑠

𝑏 = √𝐷𝑠. 𝑑23 for 3-bundle conductors (2) 𝐷𝑠

𝑏 = 1.09 √𝐷𝑠. 𝑑34 for 4-bundle conductors (3)

In this case, for 4-b (Quad):

GMR(=Ds) of one conductor from tables

Page 60: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-59

𝐷𝑠𝑏 = 1.09√𝐷𝑠. 𝑑34

= 1.09√0.0363 × 1.3234 = 0.586 𝑓𝑡

The equivalent spacing between phases is:

𝐷𝑒𝑞 = 𝐷𝑚 = √𝐷12. 𝐷23. 𝐷313 = √34.44 × 34.44 × 68.88

3= 43.4 𝑓𝑡

Inductive Reactance:

𝑋𝐿 = 4.657 . 10−3 . 𝑓. logDm

Dsb = 0.4353 ohms/mile = 0.27 ohms/km (for SC)

= 0.25 ohms/km (for DC)

Capacitance:

𝐶𝑛 =0.0388

log𝐷𝑒𝑞

𝐷𝑠 𝑐𝑏

μF/mile

where 𝐷𝑠 𝑐𝑏 is the equivalent GMR for capacitance calculations and derived from eqs. (1), (2) and (3)

used for inductance calculations, except that the Ds is replaced by the radius r of the conductor in ft, i.e.

𝑟 =𝐷𝑜𝑢𝑡

2 ×12 ft, where Dout is the conductor outside diameter in inches

Accordingly, for capacitance:

𝐷𝑠 𝑐𝑏 = √𝑟. 𝑑 for 2-bundle conductors (4)

𝐷𝑠 𝑐

𝑏 = √𝑟. 𝑑23 for 3-bundle conductors (5) 𝐷𝑠 𝑐

𝑏 = 1.09 √𝑟. 𝑑34 for 4-bundle conductors (6)

For Bison conductors: 𝑟 =𝐷𝑜𝑢𝑡

2 ×12=

1.062

2 ×12= 0.04425 ft

𝐷𝑠 𝑐𝑏 = 1.09√𝑟. 𝑑34

= 1.09√0.04425 ×. 1.3234= 0.6156 𝑓𝑡

𝐶𝑛 =0.0388

log𝐷𝑒𝑞

𝐷𝑠 𝑐𝑏

= 0.0388

log43.4

0.6156

= 0.021 𝜇𝐹/𝑚𝑖𝑙𝑒 = 0.013 𝜇𝐹/𝑘𝑚 (for SC)

= 0.014 𝜇𝐹/𝑘𝑚 (for DC)

Susceptance B=ωC=314 x 0.013 = 4.08 μmho/km = 4.08 μS/km), for SC = 4.39 μS/km), for DC

Resistance: R=0.0762 ohms/km (R=0.019 ohms/km for four bundle conductors)

The electrical parameters in PSS/E of the DC 330 kV line Mambila-Wukari and Mambilla-Jalingo are summarized in Table 7-5.2.

Page 61: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-60

Table 7-5.2 Double-Circuit 330 kV line characteristics

PSS/E input data

Substation

Name

Substation

Name

L

(km)

R

(Ω/km)

L

(mH/km) X (Ω/km) C (μF/km)

R

(ohms)

X

(ohms)

C

(μF)

Mabila Wukari 159 0.019 0.7962 0.25 0.014 3.021 39.750 2.2260

Mabila Jalinko 95 0.019 0.7962 0.25 0.014 1.805 23.750 1.3300

Source: JICA Study Team

(5) Line surge impedance and thermal rating

1) Surge Impedance Loading Limits - Natural Line Rating

As power flows along a transmission line, there is an electrical phase shift, which increases with distance and power flow. As this phase shift increases, the system in which the line is embedded can become increasingly unstable during electrical disturbances.

Typically, for very long lines, the power flow must be limited to what is commonly called the Surge Impedance Loading (SIL) of the line.

Surge Impedance Loading is equal to the product of the end bus voltages divided by the surge (characteristic) impedance of the line. Since the characteristic impedance of various HV and EHV lines is relatively similar, the SIL depends approximately on the square of the system voltage:

𝑆𝐼𝐿 =𝑘𝑉2

𝑍𝑠

where Zs is the surge impedance of the line: 𝑍𝑠 = √𝐿

𝐶 =√

0.7962𝑥1000

0.014 = 238.5 ohms

𝑺𝑰𝑳 = 𝟑𝟑𝟎𝟐

𝟐𝟑𝟖. 𝟓= 𝟒𝟓𝟔 𝐌𝐖

Typically, stability limits may determine the maximum allowable power flow on lines that are more than approx. up to 250 km in length.

2) Thermal Limits

Thermal power flow limits on overhead lines are intended to limit the temperature attained by the energized conductors and the resulting sag and loss of tensile strength. In most cases, the maximum conductor temperature applied to modern transmission lines reflect ground clearance concerns rather than annealing of aluminum.

Thermal limits are not a function of line length. Thus for a given line design, lines of 1 km and 500 km long typically have the same thermal limit.

The thermal transmission capacities of the 330 kV OHL have been calculated as follows:

Voltage 330 kV

Page 62: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-61

Conductor Type 3 x AC 381/49 Wind Speed 0.6 m/s Air temperature 40 °C Maximum conductor temperature 75 °C

Thermal Ratings: Capacity 1,555 MVA Capacity 1,400 MW

7-5-1-3 2025 Load demand

Table 7-5.3 shows that the increase in load demand follows an approximately equivalent increase (in percentage terms) in the load forecast.

Table 7-5.3 Load demand per DisCo

DisCo Load demand 2020

(MVA) Increase 2020-2025

Load demand 2025

(MVA)

1-Ikeja 1,166 76% 2,058

2-Ibadan 1,104 107% 2,285

3-Abuja 865 169% 2,329

4-Benin 954 94% 1,852

5-Kaduna 495 136% 1,169

6-Jos 309 109% 646

7-Enugu 924 81% 1,668

8-Port Harcourt 794 122% 1,762

9-ΕΚΟ 1,087 69% 1,837

10-Kano 708 121% 1,565

11-Yola 230 131% 532

Country MW 8,636 105% 17,703

Export* MW 387 - 1,540

Tota Load MW 9,023 113% 19,243

Source: JICA Study Team Ref: 330 kV export lines: To Sakete 360MW, To Faraku 400MW, To Zabori 631MW

7-5-1-4 Study cases 2025

Table 7-5.4 shows the two scenarios studied for 2025, to capture the extreme combinations of generation and load.

Table 7-5.4 2025 study cases

Case Description Generation Load (MW)

Dry Season

Peak

DP

Dry

Night

Peak Load

Reduced HPP generation (2228 MW)

No PV generation

Increased requirement from GTs

Peak load

(night)

17703 + export

(1540)

Dry Season

Off-Peak

DOP

Dry

Day

Off-Peak Load

Reduced HPP generation

PV generation

Increased requirement from GTs

Off-Peak load

(day)

15000 + export

(1540)

Source: JICA Study Team

Page 63: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-62

7-5-2 2025 Base Case Load-flow Results

7-5-2-1 Dry Season Peak-2025

(1) Prerequisites for analysis

(a) Generation from PVs = 0 and (b) Reduced generation from HPP plants of 2,228 MW,

The running generation and load for each DisCo is as shown in Figure 7-5.5.

Source: JICA Study Team

Figure 7-5.5 Dry Season Peak Generation and Load per DisCo

Ikeja Ibadan Abuja Benin Kaduna Jos Enugu P Harc Eko Kano YolaTotalfor

NigeriaExport Totals

Run Genaration 2699 1168 3426 4430 218 84 1301 5415 900 9 500 20150

Load 2058 2268 2330 1827 1165 648 1666 1753 1837 1555 532 17639 1540 19179

Gen deficit/surplus 641 -1100 1096 2603 -947 -564 -365 3662 -937 -1546 -32 971

-2500

-1500

-500

500

1500

2500

3500

4500

5500

MW

Dry Season Peak

Page 64: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-63

Table 7-5.5 Dry Season Peak Generation and Load per DisCo

Bus Number

Bus Name PGen

(MW) Bus

Number Bus Name

PGen (MW)

Bus Number

Bus Name PGen

(MW)

16040 AES BERG202 31 16004 EGBIN ST 5 274.8 76022 OKPAI STPH2 135

16041 AES BERG203 31 16005 EGBIN ST 6 274.8 16064 OLOR NIPPST1 108

16042 AES BERG204 31 16006 EGBIN ST_123 600 16065 OLOR NIPPST2 108

16043 AES BERG205 31 86050 ELEME 68 16060 OLORNIPPGT11 132

16045 AES BERG207 31 96012 ETHIOPE 450 16061 OLORNIPPGT12 100

16046 AES BERG208 31 46037 ETHIOPE GTS 344 16062 OLORNIPPGT21 100

16047 AES BERG209 31 46038 ETHIOPE ST 156 16063 OLORNIPPGT22 100

16048 AES BERG210 31 86068 GBARAIN_GTB1 112.5 16050 OLORUNSO GT1 30

16049 AES BERG211 31 86069 GBARAIN_GTB2 112.5 16051 OLORUNSO GT2 30

86012 AFAM VI GT11 150 86055 GEN_AMADI 100 16054 OLORUNSO GT5 30

86013 AFAM VI GT12 150 56010 GEN_KADUNA 200 16055 OLORUNSO GT6 30

86014 AFAM VI GT13 150 46023 GER NIPPGT21 140 16056 OLORUNSO GT7 30

86015 AFAM VI ST10 180 46024 GER NIPPGT22 140 86047 OMA_GT 225

86003 AFAM2 GT5-6 48 46025 GER NIPPGT23 140 86023 OMOKU1 GT1 75

86004 AFAM2GT 7-8 48 46020 GEREGU GT11 124 86024 OMOKU1 GT2 75

86005 AFAM3 GT9-10 50 56003 GURARA GBUS 18 86021 OMOKU2 GT1 113

86006 AFAM3GT11-12 50 86025 IBOM GT1 32 86022 OMOKU2 GT2 113

86080 AKWA-IBOM NU 600 86026 IBOM GT2 32 26026 OMOTNIPP GT1 110

86039 ALAOJI_GTB1 112.5 86027 IBOM GT3 32 26027 OMOTNIPP GT2 110

86040 ALAOJI_GTB2 112.5 86028 IBOM II 260 26028 OMOTNIPP GT3 110

86041 ALAOJI_GTB3 112.5 46031 IHOVBOR_GTB1 110 26029 OMOTNIPP GT4 110

86042 ALAOJI_GTB4 112.5 46032 IHOVBOR_GTB2 110 26020 OMOTOSO GT1 70

86043 ALAOJI2_STB1 257 46033 IHOVBOR_GTB3 110 26022 OMOTOSO GT3 70

86031 ALSCON GT1 90 46034 IHOVBOR_GTB4 110 26024 OMOTOSO GT5 62

46027 ASCO G1 55 66033 JBS WIND 70 26025 OMOTOSO GT7 62

46028 ASCO G2 55 36006 JEBBA 2G1 90 96008 ONDO IPP 405

46035 AZURA GT 280 36007 JEBBA 2G2 90 16012 PARAS 270

46036 AZURA ST 140 36008 JEBBA 2G3 90 16011 PARASGT1-9 93

16008 BRESSON GTS 80 36009 JEBBA 2G4 40 46070 PROTON 135

96009 CABLE INLAND 900 36011 JEBBA 2G6 90 86070 QUA IBOE PP 480

86062 CALABAR_GTB1 100 36004 KAINJ 1G11 80 86035 RIVERS _GT1 190

86061 CALABAR_GTB2 100 36005 KAINJ 1G12 80 46050 SAP_NIPP_GT1 100

86060 CALABAR_GTB3 100 36000 KAINJ 1G5 80 46051 SAP_NIPP_GT2 100

86063 CALABAR_GTB4 100 36001 KAINJ 1G6 80 46052 SAP_NIPP_GT3 100

76011 CENTURY IPP 480 36002 KAINJ 1G7-8 160 46012 SAPELE GT1-2 175

86030 CUMMINS 135 36003 KAINJ 1G9-10 160 46013 SAPELE GT3-4 95

46010 DELTAIV GT19 133 46080 KOJI NUCLEAR 600 36012 SHIROR 411G1 140

46011 DELTAIV GT20 133 55075 KT WF 33 9 36013 SHIROR 411G2 140

66005 DKOWA G1 14 16010 LAFARAGE 2 100 36014 SHIROR 411G3 80

86065 EGBEMA_GTB1 100 66007 MAMBILA GT1 250 96016 TURBINE DR 300

86066 EGBEMA_GTB2 100 66008 MAMBILA GT2 250 96017 YELLOW STONE 162

86067 EGBEMA_GTB3 100 76000 OKPAI GT11 145 46029 ZUMA 540

16000 EGBIN GT 1 274.8 76001 OKPAI GT12 145 86071 ZUMA (GAS) 337

16001 EGBIN GT 2 274.8 76020 OKPAI GT4PH2 135 36024 ZUNGE_G1 150

16002 EGBIN GT 3 274.8 76021 OKPAI GT5PH2 135 36025 ZUNGE_G2 150

16003 EGBIN GT 4 274.8 76002 OKPAI ST18 126 36027 ZUNGE_G4 10

Source: JICA Study Team

Page 65: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-64

The power flows are shown in Figure 7-5.6.

Source: JICA Study Team

Figure 7-5.6 2025 Dry Season Peak Power Flows in 330 kV System

7-5-2-2 Dry Season Off-Peak-2025

(1) Prerequisites for analysis

(a) Generation from PVs = 750MW and (b) Reduced generation from HPP plants of 1,390 MW,

The running generation and load for each DisCo are shown in Figure 7-5.7.

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1163 MW

8 TO 4 297 MW

3 TO 2 -568 MW

7 TO 4 486 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 449 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

6 JOS EDC

1 IKEJA EDC

4 TO 2 1083 MW

G

G

DISCOS

2 TO 1 1365 MW

4 TO 3 544 MW

Diagram created using'D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\2025\DP 2025 model Yash with SGRD July 8 reinf.sav''D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\Diagrams-SLDs-Use Power Exch only\Power Exchanges 330kV model Discos Yach SGRD.sld'

GG

1 TO 9 231 MW

GG

5 TO 6 -88 MW

6 TO 11 144 MW

G

4 TO 9 336 MW

4 TO 1 1086 MW

G

G

TCN 2025 MODELDISCO DEMANDTHU, JUL 19 2018 11:39

1.002

0.997

12 6

18

0.999

0.990

1.016

306 28

306 28

306 28

306 28

83004

IKOT-EKPENE_

73006UGWUAJI_3

73001

ONITSHA 3

73005ASABA_3

1.019

1.005

286

25

1.018149

20

149

20

1.00473003

MAKURDI_3

1.021

1

1.001

44 10

1

1.012

32 9

10

32 9

10

32 9

10

32 9

10

0.996325

89

325

89

1.005

40

4 40

40

4 40

33007GWAGW BB1

1.011

14 5

37 145

37

146

73

0.993

23005AKURE 3

0.926

1.003

56 1 71

251

124

23001

OSOGBO 3

0.952

40 4

10

40 4

10

24 0

98

10

68

0.955

48 6

65

0.994

21 0

12 2

21 0

12 214

9

337

2

3

23003GANMO 3

23002OMOTOSHO3

0.9961.009

199

82

199

82

342

102342

102

0.945

21 5

57

0.979

0.974

1

2

0.981

26 8

55 26 8

55

26 8

55

26 8

55

13003IKEJA W 3

13029

OGIJO 3

0.977

16 0

28 16 0

28

21 0

3921 0

39

13030MFM 3

0.967

42 128

42 128

0.982

62 5

12 7

62 5

12 7

42 6

94

42 6

94

1.045

88

10

89 90

SW

0 154

42

0.975

50

26

50

26

180

107

18 0

10 7 18 0

10 7 18 0

10 7

44 8

15 1

284

15 284

15

13002

EGBIN 3

0.971

0.980

59 0

15 7

0.986

21

3 1

19

21

3 1

19

64 6

20 0

64 6

20 0

0.996

19 7

60

19 7

60

1.000

252

64

252

64

33 8

94 33 8

94

167

35

167

35

13025EPE 3

13000AJA 3

13031OKO_OBA_313034

LEKKI 33013027

ALAGBON_3

13001

AKANGBA 3

45 0

24

61 10 5

1

33001KATAMPE 3

0.989

160 32

160 32

1.030

312 27

312 27

83007ONNIE_3

1.015

340

48

340

48

356

21 356

21

1

83002ALAOJI 3

1.01918 51 18 51 235

24

77 977 9 235

24

1.013

55

38 55

38

0.996

144

121

144 12

11.019

234

2 23

4

2

83010IKOT ABASI_3

1.030

2

132

13

83000AFAM IV 3

83005OWERRI_3

0.989

297 14

16

61

16

61

0.998

429

65

429

65

374 94

374 94

73004

ALIADE_3

63001JOS 3

0.978

104

21104

21

73010

ABAKALIKI_3

1.048

164 2

5

1

63002YOLA 3

1.046

27

5

20

49

0.968

146

54 14

6

54

13032

NEW_AGBARA_3

0.952

24 3

64

1360

141

23000

AYEDE 3

1.01743000

AJAOKUTA 3

43002BENIN 3

1.007 115

34

43001ALADJA 3

43003DELTA IV 3

1.009

11 5

34

271

56

271

56

271

56

43004SAPELE 3

43011B_NORTH_3

1.017 272 49

272 49

0.997

90 4190 41

43009

OBAJANA_3

1.015

24

5

57

24

5

57

83006

EGBEMA_3

83009

OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000

GOMBE 3

169

11

2

1 2

33020

SHIRORO 3

33008WESTMAIN_3

73000NHAVEN 3

33021KAINJI 3

1.00996

59

33005

KAINJI G.S.3

33003

JEBBA T.S.3

104

11

104

20

59 0

15 7

44

65

164 2

5

154

42

1.015

111

81

123

27

33009

ZUNGERU

33004

JEBBA G.S.3

33022APO_NEW 3

0.965

33023LAFIA 3

0.998

293 63

30 0

92

50 957

50 957

135

76 135

76

63003BAUCHI 3 1.034

57 1

129

73

63008MAMBILA 3

1.041

1.016

351 35351 351.000

43006EFFURUN 3

126

18

73002

OKPAI 3

1.006

1.006

366 5

366 5

73030IHIALA 3

23006

IBADAN

1.000

13026OKE_ARO_3

229

8

47 11 4

47 6

330 37

330

1

2

1.032

63009WUKARI 3

197

19

197

19

83001

ALAOJI NIPP3

73007

NNEWI 3

0

338

1

2

1

13004SAKETE 3

1.003

1.003

13028ARIGBAJO

11 4 82 82

63006

JALINGO_3

37

6

11 9

67

119

47

26

7

44

13012

PARAS

0.991

15 2

115 2

1

287

91

287

91

33011

FARAKU

0.985

201

57

200

78201

57

200

78

400

157

43012ZUMA 1.013

335

10335

10

59

9

41

59

9

41

53020MILLENIUM

1.004

34

61

34

56

45

60

45 9

63015MAYOBELWA 1.04726

9

43

14 4

17 14 4

17

18

46

18 31

18

46

18 31

123

27 12

3

36

123

27

123

36

12 6

18

127

27

15

4 5

9

154

43

15

4 5

9

154

43

47 3

56

6242 7

62

228

42

43007AZURA

284

46

281

25

43010ETHIOPE

90001

1.01511 11

13

9000290003

1.000

90004

0.953 25 9

90005

1.004

57 7

33

5566

55 66

90006

0.996 92 2 39

91

12991

129

25 1

42

25 1

42

90007

1.017

1147 56

562

24 56

2

24

440

29

440

29

43008

LOKOJA _3

0.978

1.000

90009

1.000

18 2

314 15

3

313

150

13035

IJORA 3

0.968

291

14

291

14409

75

409

75

43005GEREGU

47 3

56

13005OLORUNSOGO3

44 8

15 1

23010

SHAGAMU

0.977

122

70122

70

21 5

57

Export 1540 MW

Total Generation 20152 MWNigeria Load 17634 MW

Generation from HPP 2228 MW

Generation per DISCO Loads per DISCO

3-Abuja 3426 MW

4-Benin 4430 MW

9-Eko 900 MW

7-Enugu 1301 MW

2-Ibadan 1168 MW

1-Ikeja 2701 MW

6-Jos 84 MW

5-Kaduna 218 MW

10-Kano 9 MW

8-Pt Harco 5415 MW

11-Yola 500 MW

Generation from PV 0 MW

Total Load 19174 MW

9-Eko 1837 MW

7-Enugu 1666 MW

2-Ibadan 2266 MW

6-Jos 648 MW

5-Kaduna 1165 MW

10-Kano 1453 MW

8-Pt Harco 1753 MW

11-Yola 532 MW

1-Ikeja 2058 MW

3-Abuja 2329 MW

4-Benin 1827 MW

25 0

66

250

66

1250

48R

1

1

1

1

1250

48R

36033

ABUJA TPP

375

250

125

500

0

MV

A F

low

TCN330kV TRANSMISSINO NETWORK

TCN2025MODEL

Total Generation: 20152 MW

Nigeria Load: 17634 MW

Export: 1540 MW

Total Load: 19174 MW

Generation from PV: 0 MW

Generarion from HPP: 2228 MW

Page 66: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-65

Source: JICA Study Team

Figure 7-5.7 Dry Season Off-Peak Generation and Load per DisCo

The power flows are shown in Figure 7-5.8.

Source: JICA Study Team

Figure 7-5.8 2025 Dry Season Off- Peak Power Flows in 330 kV System

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 977 MW

8 TO 4 309 MW

3 TO 2 -658 MW

7 TO 4 555 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 399 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 975 MW

G

G

G

DISCOS

2 TO 1 1036 MW

4 TO 3 917 MW

G

G

Diagram created using

'D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\2025\DoP 2025 model Yash with SGRD July 19 reinf.sav''D:\NIGERIA JICA-YACHIYO\PSSE Yachiyo MP\Diagrams-SLDs-Use Power Exch only\Power Exchanges 330kV model Discos Yach SGRD.sld'

GG

3 TO 5 1596 MW

1 TO 9 161 MW

G G

5 TO 6 -183 MW

10 TO 6 0 MW

5 TO 10 -488 MW

6 TO 11 199 MW

G

4 TO 9 136 MW

4 TO 1 788 MW

G

G

TCN 2025 MODELDISCO DEMANDTHU, JUL 19 2018 22:25

1.016

1.010

143

19

1.014

1.013

1.023

269 7

269 7

269 7

269 7

83004IK OT -E K P E NE _

73006

UGWUA JI_3

73001ONIT S HA 3

73005A S A B A _3

1.026

1.018

298

23

1.027

155

29155

29

1. 03073003

MA K URDI_3

1.033

1

0 80

1.019

92 24

1

1.022

21 9

20

21 9

20

21 9

20

21 9

20

1.025243

45

243

45

1. 021

234 14

234 14

33007

GWA GW B B 1

1.023

30

16

30

16

30

62

1.005

23005

A K URE 3

0.964

1.015

501 38

209

93

23001OS OGB O 3

0.980

361

5

361

5

225

65

10

72

0.979

49 9

37

0.999

22 3

80

22 3

80

212

223

2

3

23003

GA NMO 3

23002

OMOT OS HO3

33002B K E B B I 3 0.950

1.0000.999

134

28

135

28

350

43350

43

234 47

0. 973

28 9

60

1.000

0.992

1

2

1.000

195

54 195

54

195

54

195

54

13003

IK E JA W 3

13029

OGIJO 3

0.996

111

44 111

44

15 3

48

15 3

48

13030MF M 3

0.988

17 95 17 95

0.997

56 2

83

56 2

83

398

49

398

49

1.034

78

41

79 62

1

0 53

2

0 53SW

0

63007

DA MA T URU 3 1.043

97 64

63005MA IDUGURI 3 1.028

52

66

2

0 79

0. 996

71

41

71

41

183

93

183

93

183

93 183

93

49 1

10 7

262

4 262

4

13002E GB IN 3

0.990

0.997

521

103

1.001

205

73 205

73

56 8

13 4

56 8

13 4

1.009

165

47

165

47

1.012

211

42

211

42

284

70 284

70

68

53

68

53

13025

E P E 3

13000A JA 3

13031

OK O_OB A _313034LE K K I 33013027

A LA GB ON_3

13001

A K A NGB A 3

346

40

45

73

1

33001K A T A MP E 3

1.020

124 20124 20

1. 036

328 19

328 19

83007

ONNIE _3

1.024

411

48

411

48

388

34 388

34

1

83002A LA OJI 3

1.02713 41 13 41 281

27

64 17

64 17

281

27

1. 022

84

21 84

21

1. 010

114 88 114 88

1.025

25614 25614

83010

IK OT A B A S I_3

1.037

14

17 14

17

83000

A F A M IV 3

83005

OWE RRI_3

1.012

282 12

2 57

2 57

1. 024

401

78 401

78

353 84

353 84

73004

A LIA DE _3

63001JOS 3

1.005

88 488 4

73010A B A K A LIK I_3

1.019

98

12

1

0 78

63002Y OLA 3

1.028

182 2

3

53001K A NO 3

0.968

0

70

0.966

152

14

0

70

53005

K A NO_NE W330

1.009

318

10

53003

Z A RIA _330

53000

K A DUNA 3

53002

K A T S INA 3

0.985

1

1

1

65

1

11

65

0.989

127 54

127

5413032

NE W_A GB A RA _3

0.973

24 7

55

1360

141

23000A Y E DE 3

1.02043000

A JA OK UT A 3

43002

B E NIN 3

1.017 200

15

43001

A LA DJA 3

43003

DE LT A IV 3

1.014

20 0

15

111

21

111

21

111

21

43004

S A P E LE 3

43011

B _NORT H_3

1.020

0 10 1

1. 016

65 1965 19

43009

OB A JA NA _3

1.025

233 34

233 34

83006

E GB E MA _3

83009OMOK U_3

83008CA LA B A R_P S _3

83003

A DIA GB O_3

63000GOMB E 3

179 14

2

1 2

33020S HIRORO 3

33008

WE S T MA IN_3

73000NHA V E N 3

0.985

89

93

89

93

53004

F UNT UA 3

1.017

38

44

38

44

53007T MA F A RA 3

1.006

53008

GUS A U 3

124

27 124

27

109

64 109

64

263

17263

17

33021

K A INJI 3

0.99965

31

33005

K A INJI G.S .3

33003

JE B B A T .S .3

124

13

125

17

521

103

234 47

234 47

91

50

98

12

97 64

52

66

1. 022

88

85

67 6

33009

Z UNGE RU

33004

JE B B A G.S .3

33022A P O_NE W 3

0.999

33023

LA F IA 3

1.028

218 6

22 1

65

41246

41246

132

72 132

72

63003

B A UCHI 3 1.037

57

30

107

46

63008

MA MB ILA 3

1.027

1.024

351 15

351 151. 000

43006

E F F URUN 3

143

19

73002OK P A I 3

1.017

1.018

369 13

369 13

73030

IHIA LA 3

23006

IB A DA N

1.000

13026

OK E _A RO_3

220

6

53012DUT S E 3

1.000

53011

K A Z A URE 3

0.980

1 125

1 58

225

8

225

1

0 11

2

0 78

1. 039

63009

WUK A RI 3

1.013

202

33

202

33

83001

A LA OJI NIP P 3

73007

NNE WI 3

0

329

30

338

1

2

1

13004

S A K E T E 3

112

62

113

23

1.015

1.015

13028A RIGB A JO

125 101 101

63006JA LINGO_3

8

58

33010

Z A B ORI

0.902

320

132

315

124 320

132

315

124631

247

115

75

115

53

445 83

SW 0

13012

P A RA S

1.006

16 7

36

16 7

36

302

41

302

41

33011

F A RA K U

0.974

201

58

200

78201

58

200

78

400

157

43012Z UMA 1.023

234

71

234

71

332 13

332 13

53013DA URA

0.980

19

1519

15

9

289

28

53016JOGA NA

0.978 48 107

4898

21 6

15

213

53

65

0

65

0

53020MILLE NIUM

1.021

83

46

83

41

92

45

93 23

63015

MA Y OB E LWA 1.022

172

1

4

54

5

49

70

49 5

49

70

49 5 67 6

67

3

67 6

67

3

143

19

144

26

168

38

168

22

168

38

168

22

47 3

5

32 4

42

320

93

32 4

42

320

93

219

30

43007A Z URA

189 21

188

12

112

62

113

23

43010

E T HIOP E

90001

1.02310 12

75

9000290003

1.000

90004

0.981 274

90005

1.030

429

10

50 6 38

50 6 38

90006

1.025

773

65

131

137

131

137

27 8

51

27 8

51

90007

1.020

667

121

330

9

330

9

90008

1.017

687

33

348

42

348

42

43008LOK OJA _3

1.009

1.000

90009

1.000

26 2

33006

S OK OT O 3

26 1 113

261

108

13035

IJORA 3

0.988

268

4

268

4368

45

368

45

43005

GE RE GU

47 3

5

13005

OLORUNS OGO3

49 1

10 7

23010

S HA GA MU

0.997

106

49106

49

28 9

60

1.000

190

35

32021

NIA ME Y 1

0.85660 18

52010GA Z OUA 1

S W

72

Export 1541 MW

Total Generation 17232 MWNigeria Load 14950 MW

Genera tion from H PP 1390 MW

Generation per DISCO Loads per DISCO

3-Abuja 1932 MW

4-Benin 3520 MW

9-Eko 900 MW

7-Enugu 1301 MW

2-Ibadan 1168 MW

1-Ikeja 2523 MW

6-Jos 214 MW

5-Kaduna 340 MW

10-Kano 189 MW

8-Pt Harco 4815 MW

11-Yola 330 MW

Genera tion from PV 750 MW

Total Load 16491 MW

9-Eko 1551 MW

7-Enugu 1409 MW

2-Ibadan 1930 MW

6-Jos 547 MW

5-Kaduna 984 MW

10-Kano 1321 MW

8-Pt Harco 1488 MW

11-Yola 450 MW

1-Ikeja 1738 MW

3-Abuja 1968 MW

4-Benin 1564 MW

250

10 4

0

96

1250

84R

1

1

1

1

10

93R

36033

A B UJA T P P

375

250

125

500

0

MV

A F

low

TCN330kV TRANSMISSINO NETWORK

TCN2025MODEL Total Generation: 17232 MW Nigeria Load: 14950 MW Export: 1541 MW Total Load: 16491 MW Generation from PV: 750 MW

Generarion from HPP: 1390 MW

Page 67: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-66

7-5-3 Contingency (N-1) Analysis for 330 kV Circuits

The contingency N-1 analysis carried out for the 330 kV lines has shown that the following 330 kV DC lines are overloaded and require reinforcement by converting to Quad conductors.

Table 7-5.6 Overloaded 330 kV lines under N-1

Substation Name Substation Name Rating (MVA)

Flow (MVA)

Loading (%)

Length (km)

AJA LEKKI 856 1,372 160.4 7

ALAGBON LEKKI 856 1,184 138.5 14

LOKOJA ZUMA 856 1,117 130.7 24

Source: JICA Study Team

Reconductoring to Quad-bundle conductors has already been implemented by TCN. This is also assumed to be possible for these lines, but must be verified to ensure the structures are suitable. If not, the DC lines will need to be replaced.

7-5-4 2025 Base Case Load-flow Results

7-5-4-1 Overloads of 330 kV or 132 kV Lines

There are no overloaded 330 kV or 132 kV lines which are overloaded under normal operation (base case).

7-5-4-2 Overloads of Transformers

The 330/132 kV 3-W and A/T transformers overloaded above their 100% rating MVA under normal (base case) operation, in addition to those reported for the 2020 case, are listed in Table 7-5.7 and must be upgraded.

Table 7-5.7 Overloaded 330/132 kV transformers

Bus Number

Bus Name Voltage

(kV) Bus

Number Bus Name

Voltage (kV)

cct Load

(MVA) Rating (MVA)

Loading (%)

83003 ADIAGBO_3 330 3WNDTR ADIAGB T1A WND 1 1 188.2 150 125.5

83003 ADIAGBO_3 330 3WNDTR ADIAGB T1B WND 1 2 188.2 150 125.5

12000 AJA 132 132 3WNDTR AJA T4 WND 1 1 68.9 45 153.2

13000 AJA 3 330 3WNDTR AJA T2A WND 1 3 194.6 150 129.8

42000 AJAOKUTA 1 132 3WNDTR AJAOK T1A WND 2 1 86 80 107.5

42000 AJAOKUTA 1 132 3WNDTR AJAOK T2A WND 2 1 86 80 107.5

42000 AJAOKUTA 1 132 3WNDTR AJAOK T3A WND 2 1 86 80 107.5

13001 AKANGBA 3 330 3WNDTR AKANGBA5T4A WND 1 1 152.4 150 101.6

13001 AKANGBA 3 330 3WNDTR AKANGBA5T4B WND 1 1 152.4 150 101.6

12016 AKOKA 1 132 3WNDTR AKOKA T1 WND 1 1 53.8 45 119.6

23005 AKURE 3 330 3WNDTR AKURE T1A WND 1 1 182.2 150 121.5

23005 AKURE 3 330 3WNDTR AKURE T1B WND 1 2 182.2 150 121.5

12022 APAPA RD 1 132 3WNDTR APAPA RD T1 WND 1 1 46.4 45 103.2

23000 AYEDE 3 330 3WNDTR AYEDE TR1 WND 1 1 198.9 150 132.6

23000 AYEDE 3 330 3WNDTR AYEDE TR2 WND 1 1 197.1 150 131.4

23000 AYEDE 3 330 3WNDTR AYEDE TR3 WND 1 1 197.1 150 131.4

42003 DELTA 1 132 43003 DELTA IV 3 330 1 270.1 150 180.1

42003 DELTA 1 132 43003 DELTA IV 3 330 2 270.1 150 180.1

23003 GANMO 3 330 3WNDTR GANMO TR1A WND 1 1 212.4 150 141.6

72036 IHIALA 1 132 3WNDTR IHIALA TR WND 2 1 124.2 120 103.5

Page 68: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-67

Bus Number

Bus Name Voltage

(kV) Bus

Number Bus Name

Voltage (kV)

cct Load

(MVA) Rating (MVA)

Loading (%)

13003 IKEJA W 3 330 3WNDTR IKW T2B WND 1 3 163.1 150 108.7

12027 ISOLO 1 132 3WNDTR ISOLO TR3 WND 1 1 53.3 45 118.3

22012 JERICHO 1 132 3WNDTR JERICO TR1 WND 1 1 73.7 45 163.8

53001 KANO 3 330 3WNDTR KANO OLD T5A WND 1 2 169.6 150 113

53001 KANO 3 330 3WNDTR KANO T3A WND 1 1 169.6 150 113

52030 KUMB T1A BB 132 3WNDTR KANO T1A WND 2 1 242.5 225 107.8

73007 NNEWI 3 330 3WNDTR NNEWI T2A WND 2 1 91.8 67.5 136

22014 OMOTOSHO 1 132 3WNDTR OMOTOSHO TR1 WND 2 1 134.3 120 111.9

22024 OMOTOSHO 2 132 3WNDTR OMOTOSHO TR2 WND 2 1 137.7 120 114.8

73001 ONITSHA 3 330 3WNDTR ONITSH T3A WND 1 1 152.4 150 101.6

73001 ONITSHA 3 330 3WNDTR ONITSHA T4 WND 1 1 157.6 150 105.1

22001 OSOGBO 1 132 3WNDTR OSOGBO 4T1 WND 2 1 134.9 120 112.5

22001 OSOGBO 1 132 3WNDTR OSOGBO 4T6 WND 2 1 134.9 120 112.5

22001 OSOGBO 1 132 3WNDTR OSOGBO N T5 WND 2 5 134.9 120 112.5

82028 OWERRI 1 132 3WNDTR OWERRI TR1 WND 1 1 70.1 60 116.8

83005 OWERRI_3 330 3WNDTR OWERRI T1A WND 1 1 160.6 150 107.1

32027 WESTMAIN_1 132 3WNDTR EASTMAIN TR1 WND 2 1 135.3 120 112.7

32027 WESTMAIN_1 132 3WNDTR EASTMAIN2 WND 2 2 135.3 120 112.7

Source: JICA Study Team

The 132/33 kV and 132/11 kV transformers overloaded above their 100% MVA rating under normal (base case) operation, listed in Table 7-5.8, are in addition to those overloaded in 2020 and must be upgraded. Some of these transformers, shown in bold, have already been reported in the 2020 case as being overloaded above their 85% rating:

Table 7-5.8 Overloaded 132/33 kV transformers

Bus Number

Bus Name Voltage

(kV) Bus

Number Bus Name

Voltage (kV)

cct Load

(MVA) Rating

(MVA) Loading

(%)

82026 ABA 1 132 86020 ABA T1A 6.6 6.6 1 8.6 7.5 114

82026 ABA 1 132 85023 ABA T4A(MOB) 33 1 17.5 15 116.4

72016 ABAKALIKI 1 132 75001 ABAKALIKI 33 33 1 72.1 60 120.2

82000 AFAM 1-2-3 132 86000 AFAM 11 11 1 119.3 64 186.4

82018 AHOADA 1 132 85038 AHOADA T2 33 2 42.9 40 107.4

12000 AJA 132 132 15003 AJA 33 33 1 107.2 60 178.6

42000 AJAOKUTA 1 132 45033 AJAOKUTA T2 33 1 64.8 60 107.9

12004 AKANGBA BBII 132 15053 AKANGBA 33 33 1 67.8 60 113

12016 AKOKA 1 132 15067 AKOKA T2 33 1 47.6 40 119

22005 AKURE 1 132 25003 AKURE 33 33 1 40.9 30 136.4

22005 AKURE 1 132 25028 AKURE T2A 33 2 46.7 30 155.6

22005 AKURE 1 132 25018 AKURE T3A 33 33 1 82.6 60 137.7

12017 ALAGBON 1 132 15008 ALAGBON 33 33 1 70.9 66 107.4

12017 ALAGBON 1 132 15008 ALAGBON 33 33 2 70.9 66 107.4

12019 ALIMOSHO 1 132 15010 ALIMOSHO 33 33 1 37.8 30 125.9

12019 ALIMOSHO 1 132 15072 ALIMOSHO T1 33 3 48.5 30 161.6

42015 AMUKPE 1 132 45026 AMUKPE BB 33 33 1 68.3 60 113.9

12054 ARIGBAJO 1 132 15062 ARIGBAJO 33 33 1 61.1 60 101.9

12054 ARIGBAJO 1 132 15062 ARIGBAJO 33 33 2 61.1 60 101.9

22000 AYEDE 1 132 25004 AYEDE 33 33 1 107.1 100 107.1

22000 AYEDE 1 132 25045 AYEDE 33 33 3 81.3 60 135.5

42004 BENIN 1 132 45000 BENIN 33 33 1 67.8 60 112.9

42004 BENIN 1 132 45000 BENIN 33 33 9 67.8 60 112.9

Page 69: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-68

Bus Number

Bus Name Voltage

(kV) Bus

Number Bus Name

Voltage (kV)

cct Load

(MVA) Rating

(MVA) Loading

(%)

52007 DAN AGUNDI 1 132 55001 DAN AGUNDI 3 33 1 73.2 60 122

12002 EGBIN 1 132 15033 EGBIN 33 33 1 46.9 40 117.2

12023 EJIGBO 1 132 15014 EJIGBO 33 33 1 46.2 30 153.9

12023 EJIGBO 1 132 15014 EJIGBO 33 33 2 46.2 30 153.9

12023 EJIGBO 1 132 15128 EJIGBO 33 33 1 46.2 30 153.9

12023 EJIGBO 1 132 15128 EJIGBO 33 33 2 46.2 30 153.9

12023 EJIGBO 1 132 15016 EJIGBO BBI 3 33 1 104.6 100 104.6

82005 EKET 1 132 85003 EKET 33 33 2 80.2 60 133.6

82005 EKET 1 132 85002 EKET T1B 33 1 96.3 45 213.9

82035 ELELENWO 1 132 85036 ELENLEWO 33 33 1 42.1 40 105.3

82035 ELELENWO 1 132 85036 ELENLEWO 33 33 2 42.1 40 105.3

22022 GANM0 T1 BB 132 25032 GANMO T1 33 1 118.5 60 197.5

62029 GASHUWA 1 132 65062 GASHUWA T2A 33 2 54.9 45 122

62029 GASHUWA 1 132 65061 GASHUWAT1A 33 1 54.9 45 122

52011 GUSAU 1 132 55004 GUSAU 33 33 1 40.6 30 135.4

52011 GUSAU 1 132 55046 GUSAU T1 33 2 35.6 30 118.5

22006 IBADAN NORTH 132 25007 IBADAN NORTH 33 1 88.3 60 147.2

22006 IBADAN NORTH 132 25042 IBADAN T2 BB 33 2 79.3 60 132.2

22028 IJEBU-ODE 1 132 25041 IJEBU T1 BB 33 1 60.6 60 101

12024 IJORA 1 132 15045 IJORA T1A&B 33 2 33.2 30 110.8

12024 IJORA 1 132 15046 IJORA T2B 33 2 36.1 30 120.4

12025 IKORODU 132 15050 IKORODU T3 33 3 102.5 100 102.5

82031 IKOT_ABASI 132 85092 IKOT ABAS 33 33 1 52.3 40 130.9

82031 IKOT_ABASI 132 85092 IKOT ABAS 33 33 2 52.3 40 130.9

22009 ILESHA 1 132 25010 ILESHA 33 33 1 40.1 40 100.3

22009 ILESHA 1 132 25031 ILESHA T1 33 2 40.1 40 100.3

12026 ILLUPEJU 1 132 16033 ILLUPEJU T2 11 3 31 30 103.2

12026 ILLUPEJU 1 132 16025 ILUPEJU 11 11 2 15.1 15 100.8

12026 ILLUPEJU 1 132 15027 ILUPEJU 33 33 1 32 30 106.7

42008 IRRUA 1 132 45002 IRRUA 33 33 1 79.1 60 131.9

22011 ISEYIN 1 132 25012 ISEYIN 33 33 1 46.8 45 104

22011 ISEYIN 1 132 25049 ISEYIN T2 33 33 1 40.8 30 136.1

12027 ISOLO 1 132 15028 ISOLO 33 33 1 77.6 60 129.4

12020 ITIRE 1 132 16034 ITERE T3 11 2 44.9 40 112.1

12020 ITIRE 1 132 16032 ITIRE 11 11 1 33.4 30 111.2

22008 IWO 1 132 25002 IWO 33 33 1 45.8 40 114.5

22008 IWO 1 132 25002 IWO 33 33 2 45.8 40 114.5

62020 JALINGO 1 132 65015 JALINGO 33B 33 1 32.4 30 108

22012 JERICHO 1 132 25013 JERICHO2 33 33 1 66.4 40 166.1

62001 JOS 1 132 65005 JOS T4 60MVA 33 2 99.7 60 166.2

52003 KADUNA TOWN 132 55006 KADUNA TOWN 33 1 33.6 30 111.9

52003 KADUNA TOWN 132 55061 KD TWN T1 33 2 33.6 30 111.9

62025 KAFANCHAN 1 132 65037 KAFANC M TR1 33 3 55.2 40 138.1

52001 KANO 1 132 55057 KUMB T2 33 1 53 40 132.5

52001 KANO 1 132 55059 KUMB T4 33 4 68.8 60 114.7

52029 KANO_NEW132 132 55070 KANOII 33 33 1 72.7 60 121.2

52029 KANO_NEW132 132 55070 KANOII 33 33 2 72.7 60 121.2

52012 KATSINA 1 132 55056 KATSINA T3 33 3 41.7 30 139.1

52042 KAZAURE 1 132 55092 KAZAURE 33 33 1 32.4 30 108

52042 KAZAURE 1 132 55092 KAZAURE 33 33 2 32.4 30 108

62024 MAKERI 1 132 65033 MAKERI 33 33 1 30.3 30 101.1

Page 70: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-69

Bus Number

Bus Name Voltage

(kV) Bus

Number Bus Name

Voltage (kV)

cct Load

(MVA) Rating

(MVA) Loading

(%)

72002 NHAVEN 1 132 75039 NHAV TR2 33 2 32 30 106.6

72002 NHAVEN 1 132 75041 NHAV TR4 33 4 68 60 113.4

72011 NKALAGU 1 132 75044 NKALGU T1A 33 2 31.9 30 106.3

12055 ODOGUNYAN 1 132 15063 ODOGUNYA 33 33 1 84.4 60 140.6

12055 ODOGUNYAN 1 132 15063 ODOGUNYA 33 33 2 84.4 60 140.6

12032 OGBA 1 132 16027 OGBA 11 11 1 20.4 20 102

12029 OJO 1 132 15030 OJO 33 33 2 33.5 30 111.6

12029 OJO 1 132 15047 OJO T3_T4 33 5 85.2 60 142

22017 ONDO2 1 132 25017 ONDO1 33 33 1 63.7 60 106.2

72001 ONITSHA 1 132 75037 ONITSH TR14 33 5 42.9 40 107.2

72001 ONITSHA 1 132 75038 ONITSHA TR11 33 4 65.1 60 108.4

22001 OSOGBO 1 132 25026 OSOGBO 33 33 3 64.8 60 108

22001 OSOGBO 1 132 25029 OSOGBO T1 33 1 41.3 30 137.7

22001 OSOGBO 1 132 25030 OSOGBO T2 33 2 34.9 30 116.3

12033 OTTA 1 132 15079 OTTA T2 33 2 76.8 60 127.9

82028 OWERRI 1 132 85020 OWERR T1MOB 33 1 40.2 40 100.6

12034 OWOROSOKI 1 132 15020 OWOROSOKI 33 33 1 64.7 60 107.8

12037 PARAS_1 132 15116 AFR FOUNDRY 33 1 62.9 40 157.2

12037 PARAS_1 132 15115 PARAS IPP 33 1 43.8 40 109.6

12037 PARAS_1 132 15115 PARAS IPP 33 2 65.8 60 109.6

82008 PHCT TOWN1 1 132 85027 PHCT T1A 33 2 63.4 60 105.6

82009 PHCT TOWN2 1 132 86018 PHCT TOWN 11 11 1 65.6 60 109.3

82036 RUMUSOI 1 132 85060 RUMUSOI T133 33 1 70 60 116.7

82036 RUMUSOI 1 132 85061 RUMUSOI T233 33 1 70 60 116.7

62012 SAVANNAH 1 132 65010 SAVANNAH 33 33 1 18.4 15 122.5

22027 SHAGAMU 1 132 25040 SHAGAM T2 BB 33 2 38 30 126.6

22027 SHAGAMU 1 132 25035 SHAGAMU 33 33 1 59.1 30 197.1

12036 SHAGAMU

CEME 132 16007 SHAG CEM 11 11 1 16.1 15 107.4

12036 SHAGAMU

CEME 132 16038 SHAG CEM 11 11 2 16.1 15 107.4

32001 SHIRORO 1 132 35013 SHIRORO 33 33 1 51.3 30 171

32016 SOKOTO 1 132 35050 SOKOTO T3 33 3 41.8 30 139.5

32017 SULEJA 1 132 35047 SULEJA T3 33 2 41.4 30 138.1

32014 TEGINA 1 132 35015 TEGINA 33 33 1 42.6 30 142.1

42002 UGHELLI 1 132 45001 UGHELLI 33 33 1 92.6 60 154.3

82027 UMUAHIA 1 132 85024 UMUAHIA 33 33 1 44.5 40 111.2

82027 UMUAHIA 1 132 85024 UMUAHIA 33 33 2 44.5 40 111.2

82010 UYO 1 132 85007 UYO 33 33 3 95.2 60 158.7

82010 UYO 1 132 85030 UYO T2B 33 1 51 40 127.4

82010 UYO 1 132 85030 UYO T2B 33 2 51 40 127.4

7-5-4-3 Reactive Power Compensation Requirements

(1) SVC requirements

No SVC is needed in 2025, but more detailed and dedicated studies will subsequently be necessary stage to determine any need for such equipment in the post-2025 period.

In 2025, in addition to the reactors and capacitors listed in Table 7-5.9, Table 7-5.10, Table 7-5.11 and

Page 71: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-70

Table 7-5.12, reactive power compensation (150 MVar capacitors) will be required at Bernin Kebbi due to export requirements to WAPP. It should be noted however that in 2030, the proposed supergrid will be extended with a Kainji-Bernin Kebbi line. Once this is implemented, there will be no further need for reactive power compensation at Bernin Kebbi.

With regards to Gombe, should additional reactive power compensation be required at lightly loaded conditions, instead of SVC, a more cost-effective option would be relocating from other S/S to Gombe approximately 100-150 MVar of reactors that, as this analysis has shown, are no longer needed there.

As was shown in the static security analysis for 2025, a more appropriate candidate for an SVC (or in fact only capacitors, given the lack of MVars) could be the Lagos/Ikeja/Eko region, where there is a reactive power deficit of approximately 400-500 MVar. It should be noted however that this deficit is expected to ease when the DisCos implement the reactive power control program at distribution level, as proposed and in line with the Grid Code requirements, as well as when transmission lines and transformers are upgraded, as has been shown in previous chapters of this report.

(2) Reactors

The status of reactors required in the Dry Season Peak case is shown in Table 7-5.9.

Table 7-5.9 Reactor requirements for the 2025 Dry Season Peak

Bus Number

Bus Name Voltage

(kV) Id In Service

B-Shunt (MVar)

63005 MAIDUGURI 3 330 2 1 -75

65001 YOLA T1 33 33 1 1 -30

65014 GOMBE T4A 33 1 1 -30

Source: JICA Study Team

The status of reactors required in the Dry Season Off-Peak case is shown in Table 7-5.10.

Table 7-5.10 Reactor requirements for the 2025 Dry Season Off-Peak

Bus Number

Bus Name Voltage

(kV) Id In Service

B-Shunt (MVar)

53001 KANO 3 330 1 1 -75

53005 KANO_NEW330 330 1 1 -75

63001 JOS 3 330 1 1 -75

63002 YOLA 3 330 1 1 -75

63002 YOLA 3 330 2 1 -75

63005 MAIDUGURI 3 330 2 1 -75

63000 GOMBE 3 330 1 1 -50

63000 GOMBE 3 330 2 1 -50

65001 YOLA T1 33 33 1 1 -30

65014 GOMBE T4A 33 1 1 -30

63006 JALINGO_3 330 1 1 -10

Source: JICA Study Team

Page 72: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-71

(3) Capacitors

The status of capacitors required in the Dry Season Peak case is shown in Table 7-5.11.

Table 7-5.11 Capacitor requirements for the 2025 Dry Season Peak

Bus Number

Bus Name Voltage

(kV) Id

In Service

Capacity (MVar)

75004 AWKA 33 33 1 1 10

75012 OJI RIVER 33 33 1 1 10

15002 AGBARA 33 33 1 1 20

15011 ABEOKUTA OLD 33 2 1 20

15022 IKORODU 33 33 2 1 20

15027 ILUPEJU 33 33 1 1 20

15030 OJO 33 33 1 1 20

25004 AYEDE 33 33 1 1 20

25012 ISEYIN 33 33 1 1 20

25018 AKURE T3A 33 33 1 1 20

25035 SHAGAMU 33 33 1 1 20

25038 IJEBU-ODE 33 33 1 1 20

35000 AKWANGA 33 33 1 1 20

35001 APO 33 33 2 1 20

35009 KONTAGORA 33 33 1 1 20

35012 MINNA 33 33 1 1 20

35048 MINNA T2 33 2 1 20

42014 EFFURUN 1 132 2 1 20

42015 AMUKPE 1 132 1 1 20

45003 OKENE 33 33 1 1 20

52022 HADEJIA 1 132 1 1 20

55001 DAN AGUNDI 3 33 2 1 20

55010 KATSINA 33 33 1 1 20

55011 ZARIA 33 33 1 1 20

55032 MALUMFASHI_3 33 1 1 20

55051 DAKATA T2 33 1 1 20

55057 KUMB T2 33 1 1 20

55069 KD TWN T2 33 1 1 20

55072 KD TWN T3 33 1 1 20

72009 AWKA 1 132 1 1 20

75002 APIR 33 33 1 1 20

75017 YANDEV 33 33 1 1 20

75048 APIR_33B 33 1 1 20

15006 AKANGBA 33 33 1 1 24

15007 AKOKA T1 33 33 1 1 24

15009 ALAUSA 33 33 1 1 24

15010 ALIMOSHO 33 33 1 1 24

15014 EJIGBO 33 33 1 1 24

15015 IJORA 33 33 1 1 24

15018 OGBA 33 33 1 1 24

15028 ISOLO 33 33 1 1 24

15079 OTTA T2 33 1 1 24

15080 OLD ABEOK T2 33 3 1 24

15128 EJIGBO 33 33 1 1 24

22017 ONDO2 1 132 1 1 24

25011 ILORIN 33 33 1 1 24

Page 73: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-72

Bus Number

Bus Name Voltage

(kV) Id

In Service

Capacity (MVar)

25012 ISEYIN 33 33 2 1 24

42008 IRRUA 1 132 1 1 24

45027 IRRUA BBII33 33 1 1 24

32012 KEFFI 1 132 1 1 25

82006 ITU 1 132 1 1 40

22015 OMUARAN 1 132 1 1 50

35036 GWAGWALAD 33 33 1 1 50

52022 HADEJIA 1 132 2 1 50

53001 KANO 3 330 2 1 50

53001 KANO 3 330 3 1 50

32006 APO 1 132 1 1 60

32017 SULEJA 1 132 1 1 60

12004 AKANGBA BBII 132 1 1 72

12032 OGBA 1 132 1 1 72

82010 UYO 1 132 1 1 100

Source: JICA Study Team

The status of capacitors required in the Dry Season Off-Peak case is shown in Table 7-5.12.

Table 7-5.12 Capacitor requirements for the 2025 Dry Season Off-Peak

Bus Number

Bus Name Voltage

(kV) Id In Service

Capacity (MVar)

15002 AGBARA 33 33 1 1 20

15011 ABEOKUTA OLD 33 2 1 20

15022 IKORODU 33 33 2 1 20

15027 ILUPEJU 33 33 1 1 20

25004 AYEDE 33 33 1 1 20

25012 ISEYIN 33 33 1 1 20

25018 AKURE T3A 33 33 1 1 20

25035 SHAGAMU 33 33 1 1 20

25038 IJEBU-ODE 33 33 1 1 20

35001 APO 33 33 2 1 20

35012 MINNA 33 33 1 1 20

42014 EFFURUN 1 132 2 1 20

42015 AMUKPE 1 132 1 1 20

45003 OKENE 33 33 1 1 20

52022 HADEJIA 1 132 1 1 20

55001 DAN AGUNDI 3 33 2 1 20

55010 KATSINA 33 33 1 1 20

15006 AKANGBA 33 33 1 1 24

15007 AKOKA T1 33 33 1 1 24

15009 ALAUSA 33 33 1 1 24

15010 ALIMOSHO 33 33 1 1 24

15014 EJIGBO 33 33 1 1 24

15015 IJORA 33 33 1 1 24

15028 ISOLO 33 33 1 1 24

15079 OTTA T2 33 1 1 24

15128 EJIGBO 33 33 1 1 24

22017 ONDO2 1 132 1 1 24

25011 ILORIN 33 33 1 1 24

25012 ISEYIN 33 33 2 1 24

42008 IRRUA 1 132 1 1 24

Page 74: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-73

Bus Number

Bus Name Voltage

(kV) Id In Service

Capacity (MVar)

45027 IRRUA BBII33 33 1 1 24

52022 HADEJIA 1 132 2 1 24

32012 KEFFI 1 132 1 1 25

82006 ITU 1 132 1 1 40

32021 NIAMEY 1 132 2 1 45

22015 OMUARAN 1 132 1 1 50

32006 APO 1 132 1 1 60

12004 AKANGBA BBII 132 1 1 72

82010 UYO 1 132 1 1 100

Source: JICA Study Team

7-5-5 Expansion Plan for 2025

In addition to the projects undertaken by TCN and NIPP, the following 330 and 132 kV lines, shown in Table 7-5.13, are included in the 2025 model. These are also in addition to those included in the 2020 model. A priority ranking from 1 to 3 has been included in the table, with 1 denoting the highest priority.

Table 7-5.13 Additional lines required by 2025 (1)

No Area From To

Voltage (kV)

Length (km)

Remarks Priority/ Ranking

1 Ejio (Arigbajo) Ayede SC 330 50

Turn-in/out Ejio (Arigbajo)-Osogbo line at Ayede, or have one direct line Ikeja West-Ayede, instead of two lines: Ikeja West Ejio (Arigbajo) and Ejio (Arigbajo)-Osogbo

1

2

Part of North-Wes

t Ring

Birnin-Kebbi Sokoto DC 330 130 in parallel of existing 132 kV 3

3 Sokoto Talata Mafara DC 330 100

3

4 Talata Mafara Gusau DC 330 125

3

5 Gusau Funtua DC 330 70

2

6 Funtua Zaria DC 330 70 2

7 Olorusongo Ejio (Arigbajo) DC 330 20

JICA. Already a DC. 4 circuits are required, or conversion of the two circuits from twin to Quad-bundle conductors.

2

8 Katsina Daura DC 330 40 Undertaken by TCN as part of the Northern Corridor Transmission projects 2, to be financed by AFD

2

9 Daura Kazaure DC 330 25 Undertaken by TCN as part of the Northern Corridor Transmission projects 2, to be financed by AFD

2

10

Part of North-East

Ring

Damaturu Maiduguri DC 330 260 If not by 2020, implement as soon as possible thereafter (An SC already exists.)

3

11 Gombe Daimaturu DC 330 160 If not by 2020, implement as soon as possible thereafter (An SC already exists.)

3

12 Gombe Yola DC 330 240 If not by 2020, implement as soon as possible thereafter (An SC already exists.)

3

13 Yola Jalingo DC 330 160 If not by 2020, implement as soon as possible thereafter (1 SC via Mayo Belwa)

3

14 Mambila

evacuation Mambila Jalingo 2xDC 330 95

2xDC only if N-2 is adopted, otherwise 1xDC

1

Page 75: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-74

No Area From To

Voltage (kV)

Length (km)

Remarks Priority/ Ranking

15 Mambila Wukari 2xDC 330 159 2xDC only if N-2 is adopted, otherwise 1xDC

1

16 Wukari Makurdi DC 330 159

1

16 Wukari Lafia DC 330 95 after 2025 3

18 Shiroro Kaduna DC 330 96

or upgrade to 4-b (Quad). Two DC project with Quad conductors is undertaken by TCN as part of the Northern Corridor Transmission projects 2, to be financed by AFD

3

19 Ejio (Arigbajo) Ajegunle (New

Agbara) DC 330 40 JICA. 2

20 Ejio (Arigbajo) Likosi (Ogijo) DC 330 48 JICA. 2

21 Ajegunle (New

Agbara) Badagry DC 132 32 JICA. 2

22 Ejio (Arigbajo) New Ajeokuta DC 132 37 JICA. 2

23 Gwangwalada Shiroro DC 330 a SC exists 1

24 Benin North Omotosho DC 330 110 Quad conductors. May be required before 2025 and as early as 2022 for the evacuation of new Ethiope PP

1

25 Zungeru Kainji DC 330 200 2

26 Zungeru Shiroro DC 330 25 2

27

Part of the future

Supergrid

Ikot-Ekpene Makurdi DC 330 320 1

28 Makurdi Gwangwalada DC 330 180 1

29 Ajaokouta Gwangwalada DC 330 150 1

30 Osogbo Gwangwalada DC 330 250 1

31 Gwangwalada Funtua DC 330 250 1

Source: JICA Study Team

Furthermore, since a number of undervoltages were encountered in the Dry Season Peak case and also to meet the N-1 security criterion, the following additions, shown in Table 7-5.14, were made at 132 kV level:

Table 7-5.14 Additional 132 kV lines required by 2025 (2)

No From To

Voltage (kV)

Length (km)

Remarks Priority/ Ranking

1 Shiroro Tegina SC 132 65 SC only exists. Add a second SC 1

2 Tegina Kontagora SC 132 90 SC only exists. Add a second SC 1

3 Kontagora Yelwa-Yauri SC 132 88 SC only exists. Add a second SC 1

5 Ganmo Ilorin SC 132 10.5 SC only exists. Add a second SC 3

6 Obajana Egbe DC 132 97 new DC 1

7 Omotosho Ondo DC 132 98 new DC 1

8 Benin Irrua SC 132 88 SC only exists. Add a second SC 2

9 Irrua Ukpilla SC 132 43 SC only exists. Add a second SC 2

10 Ukpilla Okene SC 132 33 SC only exists. Add a second SC 3

11 Shagamu Ijebu-Ode SC 132 41 SC only exists. Add a second SC 3

12 Dakata Gagarawa SC 132 89 SC only exists. Add a second SC 3

13 Gagarawa Hadejia SC 132 60 SC only exists. Add a second SC 3

14 Dakata Kumboso SC 132 30 SC only exists. Add a second SC 3

15 Obajana Okene DC 132 97 New DC 2

16 Kainji Iseyin DC 132 200 New DC 1

Source: JICA Study Team

Due to the thermal overloads encountered under normal (N-0) operation, it is necessary for a number of 132kV lines rated 125 MVA to be reconductored with ZTACIR conductors or ACCC Oriole CTC Global conductors, already used by TCN.

Page 76: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-75

The following lines shall be reconductored, as per Table 7-5.15.

The table shows the new ratings after reconductoring:

Table 7-5.15 132 kV lines to be reconductored

From Bus Bus name To bus Bus name Id Rating

(MVA)

Length

(km)

12002 EGBIN 1 12025 IKORODU 1 225 20

12002 EGBIN 1 12025 IKORODU 2 225 20

12046 OGIJO 1 22027 SHAGAMU 1 1 188 16

12046 OGIJO 1 22027 SHAGAMU 1 2 188 16

22000 AYEDE 1 22006 IBADAN NORTH 1 188 12

22000 AYEDE 1 22006 IBADAN NORTH 2 188 12

22000 AYEDE 1 22012 JERICHO 1 2 188 6

82001 ALAOJI 1 82026 ABA 1 1 188 10

82001 ALAOJI 1 82026 ABA 1 2 188 10

82005 EKET 1 82024 IBOM IPP 1 1 188 45

82005 EKET 1 82024 IBOM IPP 1 2 188 45

82007 PHCT MAIN1 82009 PHCT TOWN2 1 1 188 6

82007 PHCT MAIN1 82036 RUMUSOI 1 1 188 10

82007 PHCT MAIN1 82036 RUMUSOI 1 2 188 10

82019 OMOKU 1 82036 RUMUSOI 1 1 225 20

82019 OMOKU 1 82036 RUMUSOI 1 2 225 20

Source: JICA Study Team

7-6 Examination of the Need for a Supergrid

7-6-1 Requirement for Supergrid (330, 500 or 750 kV)

The load-flow simulations with generation and load, as detailed in the previous Section, showed that without a major upgrade of the transmission system, widespread undervoltages and overloads will proliferate throughout the system and at all voltage levels, leading to high system losses. It is therefore considered necessary and appropriate at this stage to roll out the new “supergrid” in full, i.e. a backbone for bulk transmission at 330, 500 or 750 kV. In addition to the supergrid transmission lines, other 330 kV transmission lines have also been considered and assessed, as per TCN’s request, such as:

Yola-Little Gombi-Biu-Damaturu Damaturu-Potiskum-Azare-Dutse-Jogana Osogbo-Okene-Ajeokuta-Ayangba-Makurdi Mambila-Kashimbila-Ogoja-Ibom-Calabar Ugheli (Delta)-Onne (PH) Ugheli-Okpai

The following lines, requested to be assessed by TCN, were already introduced in 2025:

Zunkeru-Kainji Zunkeru-Shiroro

With regards to the conductor necessary for each supergrid option, the following arrangements are

Page 77: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-76

recommended:

At 330 kV a Double-Circuit is proposed with 4-bundle (Quad) Bison conductors for each circuit. At 500 kV a Single-Circuit is proposed with 4-bundle (Quad) Bison conductors. At 750 kV a Single-Circuit is proposed with 5-bundle Bison conductors, which is typical at this

voltage level due to corona phenomenon.

The main electrical characteristics are summarized in Table 7-6.1.

Table 7-6.1 Conductor parameters for the proposed supergrid

Voltage Level

No of

Conductors of bundle

R (omhs/km)

L (mH/km)

X (Ω/km)

C (μF/km)

C (nF/km)

Thermal Rating (MVA)

Zs (ohms)

SIL (MW)

330 kV DC 4 0.019 0.7962 0.25 0.014 14 2x1,550 238.5 456

500 kV SC 4 0.019 0.8908 0.2797 0.0127 12.7 2,350 264.8 944

750 kV SC 5 0.015 0.9201 0.2889 0.0123 12.3 4,400 273.5 2,057

Source: JICA Study Team

The proposed tower configurations for a typical SC 500 and/or 750 kV EHV grid are shown in Figure 7-6.1.

Source: JICA Study Team

Figure 7-6.1 Towers for 500 and 750 kV EHV Grids

Page 78: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-77

7-6-1-1 Comparison of Load-flow Results Between the Two EHV Options

The comparison of load-flow results for 2030 between the two EHV options is summarized in Table 7-6.2. The system loading is taken between the peak and off-peak values.

Table 7-6.2 Load-flow results for 2030

Voltage

Level

(kV)

O/V and U/V of

330 kV and above

(outside 0.9-1.05)

O/L of 330 kV

above 80%

Losses

(MW) Remarks

330 None 7 circuits* 1,124 (4.69%) Lower losses than 500 kV (line losses are higher

but no transformer losses are involved)

500 None 12 circuits * 1,264 (5.25%) 206 MW (0.85%) higher losses compared to

the 750-kV option

750 None 6 circuits** 1,058 (4.42%) Slighter lower losses than the 330-kV option

Source: JICA Study Team

(1) 330 kV System

BUS# X-- NAME --X BASKV AREA BUS# X-- NAME --X BASKV AREA CKT LOADING RATING PERCENT

23001 OSOGBO 3 330.00* 2 23003 GANMO 3 330.00 2 1 626.5 777.3 80.6

23005 AKURE 3 330.00 2 43011 EYEAN_3 330.00* 4 3 641.0 777.3 82.5

43000 AJAOKUTA 3 330.00 4 43005 GEREGU 330.00* 4 1 647.7 777.3 83.3

43000 AJAOKUTA 3 330.00 4 43005 GEREGU 330.00* 4 2 647.7 777.3 83.3

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 1 648.7 777.3 83.5

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 2 648.7 777.3 83.5

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 3 648.7 777.3 83.5

(2) 500 kV System

BUS# X-- NAME --X BASKV AREA BUS# X-- NAME --X BASKV AREA CKT LOADING RATING PERCENT

13000 AJA 3 330.00* 1 13034 LEKKI 330 330.00 1 1 637.0 777.0 82.0

13000 AJA 3 330.00* 1 13034 LEKKI 330 330.00 1 2 637.0 777.0 82.0

13028 ARIGBAJO 330.00* 1 23000 AYEDE 3 330.00 2 1 689.7 777.3 88.7

23001 OSOGBO 3 330.00* 2 23003 GANMO 3 330.00 2 1 651.0 777.3 83.7

23005 AKURE 3 330.00 2 43011 EYEAN_3 330.00* 4 3 760.6 777.3 97.9

43000 AJAOKUTA 3 330.00 4 43005 GEREGU 330.00* 4 1 648.6 777.3 83.4

43000 AJAOKUTA 3 330.00 4 43005 GEREGU 330.00* 4 2 648.6 777.3 83.4

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 1 651.2 777.3 83.8

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 2 651.2 777.3 83.8

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 3 651.2 777.3 83.8

43008 LOKOJA _3 330.00 4 43012 ZUMA 330.00* 4 1 662.9 777.3 85.3

43008 LOKOJA _3 330.00 4 43012 ZUMA 330.00* 4 2 662.9 777.3 85.3

(3) 750 kV System

BUS# X-- NAME --X BASKV AREA BUS# X-- NAME --X BASKV AREA CKT LOADING RATING PERCENT

23005 AKURE 3 330.00 2 43011 EYEAN_3 330.00* 4 3 648.8 777.3 83.5

43000 AJAOKUTA 3 330.00* 4 43005 GEREGU 330.00 4 1 662.1 777.3 85.2

43000 AJAOKUTA 3 330.00* 4 43005 GEREGU 330.00 4 2 662.1 777.3 85.2

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 1 631.4 777.3 81.2

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 2 631.4 777.3 81.2

43002 BENIN 3 330.00 4 43004 SAPELE 3 330.00* 4 3 631.4 777.3 81.2

Page 79: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-78

7-6-1-2 Conclusion on Supergrid/EHV Options

The load-flow simulations have shown that without a major upgrade of the transmission system, widespread undervoltages and overloads will proliferate system-wide and at all voltage levels, meaning high system losses.

It is therefore considered necessary and appropriate at this stage to introduce the full new “supergrid”, i.e. a backbone for bulk transmission at either 330, 500 or 750 kV. It was found necessary to introduce part of this supergrid.

A number of configurations have been examined and compared in terms of efficacy in voltage support, system losses and easing the line loadings of the existing and planned 330 kV systems.

The optimum configuration of a 330, 500 or 750 kV EHV grid is shown in Figure 7-6.2.

Table 7-6.3 Evaluation of 330, 500 or 750 kV supergrid

Voltage level Voltage support

System loss Stability Cost Comprehensive

evaluation

330 kV A A A B 1

500 kV B A B A 2

750 kV B A B C 3

Source: JICA Study Team

Figure 7-6.2 Supergrid Configuration

8 PT HARCO EDC

7 ENUGU EDC

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETW ORK

G

G

G

G

G

G

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

G

G

G

DISCOS

4 TO 3 -42 MW

G

G

Diagram created using'D:\NIGERIA - YEC\PSSE Yachiyo MP\2030\Master 2030-330kV SG Yach reinf.sav'

'D:\NIGERIA - YEC\PSSE Yachiyo MP\Dwgs SLDs- Power Exch\Power Exchanges 330kV model Yach SGRD only 2020-2040.sld'

GG

GG

5 TO 10 -567 MW

G

G

G

TCN 2030 MODELDISCO DEMANDSUN, AUG 12 2018 14:04

FUNTUA

GWANGWALADA

KAINJI

B.KEBBI

MAKURDI

AJAOKUTA

BENIN

EGBIN

OSOGBO

IKOT EGBENEExport 1828 MW

Total Generation 28580 MWNigeria Load 25350 MW

Generation from HPP 3240 MW

Generation per DISCO Loads per DISCO

3-Abuja 5399 MW

4-Benin 5834 MW

9-Eko 1350 MW

7-Enugu 1051 MW

2-Ibadan 1415 MW

1-Ikeja 3035 MW

6-Jos 105 MW

5-Kaduna 212 MW

10-Kano 649 MW

8-Pt Harco 8029 MW

11-Yola 1501 MW

Generation from PV 640 MW

Total Load 27178 MW

9-Eko 2240 MW

7-Enugu 1981 MW

2-Ibadan 3246 MW

6-Jos 1035 MW

5-Kaduna 2114 MW

10-Kano 2544 MW

8-Pt Harco 2375 MW

11-Yola 942 MW

1-Ikeja 2920 MW

3-Abuja 3493 MW

4-Benin 2460 MW

Page 80: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-79

The supergrid will encompass the following substations: Ikot-Ekpene, Benin, Egbin, Ajegunle (New Agbara), Osogbo, Gwangwalada, Makurdi, Ajeokuta, Funtua, Kainji, Bernin Kebbi.

From technical perspectives, both the 330 and 500 kV options are adequate. Furthermore, taking into consideration that:

Capacity of 330 kV supergrid lines: 3,100 MVA Capacity of 500 kV supergrid lines: 2,350 MVA Difference in losses between 330 and 500 kV supergrids: Marginal Impact on O/U voltages and overloads: 330 kV advantageous Higher static N-1 security of the 330 kV supergrid due to the Double-Circuit lines involved

It appears that the 330 kV supergrid system is technically the preferred option.

There is no justification to adopt and/or consider further any higher (750 kV) option for the EHV grid, particularly when the implications in cost differences are taken into account.

The higher transmission capacity (4,400 MVA) is not required at this stage and the marginal differences in losses cannot offset the high investment cost required in the planning horizon of this Master Plan.

7-6-1-3 Supergrid Transmission Lines

The following table summarizes the Double-Circuit 330kV transmission lines required to complete the supergrid for the 2030 system requirements. Part of this supergrid transmission system is required by 2025, as mentioned in the previous sections:

Table 7-6.4 Supergrid lines for 2030

From To Thermal rating (MVA) Length (km) Remarks

Ikot-Ekpene Benin 2 x 1,550 300

Ikot-Ekpene Makurdi 2 x 1,550 320 Required in 2025

Benin Egbin 2 x 1,550 230

Egbin Ajegunle (New Agbara) 2 x 1,550 50

Benin Osogbo 2 x 1,550 200

Ajegunle (New Agbara) Osogbo 2 x 1,550 150

Osogbo Kainji 2 x 1,550 200

Benin Ajeokuta 2 x 1,550 150

Ajeokuta Gwangwalada 2 x 1,550 150 Required in 2025

Gwangwalada Makurdi 2 x 1,550 180 Required in 2025

Gwangwalada Kainji 2 x 1,550 250

Gwangwalada Funtua 2 x 1,550 260 Required in 2025

Gwangwalada Osogbo 2 x 1,550 250 Required in 2025

Kainji Bernin Kebbi 2 x 1,550 300

Source: JICA Study Team (*) Note on the introduction of the “supergrid” in 2025:

The supergrid is to be fully rolled out in 2030 and its necessity is demonstrated in Section 7-6. However, due to the forecast high increase in load demand in the Abuja region and elsewhere by 2025 plus resulting overloads and undervoltages, the most cost-effective approach will involve introducing part of the supergrid in 2025, to avoid other temporary and potentially costly measures which will not be needed after the full roll-out of the supergrid in 2030. A full analysis of the supergrid and justifications for the selection of the appropriate voltage level and conductor type option is given in Section 7-6.

Page 81: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-80

In addition to the supergrid transmission lines, other 330 kV transmission lines have also been considered and assessed, as per TCN’s request, such as:

Yola-Little Gombi-Biu-Damaturu Damaturu-Potiskum-Azare-Dutse-Jogana Osogbo-Okene-Ajeokuta-Ayangba-Makurdi Mambila-Kashimbila-Ogoja-Ibom-Calabar Ugheli (Delta)-Onne (PH) Ugheli-Okpai

However, with the introduction of the supergrid, these lines will be lightly loaded. Furthermore, during off-peak loading periods their charging MVar will necessitate the operation of reactors, particularly in the north-eastern area of Nigeria. Accordingly, before a final decision is made, it is recommended that their benefits be reassessed at a later stage, once more updated information is available on load demand in the corresponding regions.

Page 82: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-81

7-7 Expansion Plan for 2030

7-7-1 2030 Base Cases Load-flow Analysis

7-7-1-1 Load demand

The demand load in 2030 in each DisCo area is shown in Table 7-7.1.

Table 7-7.1 Load demand per DisCo

DisCo Load Demand 2025

(MW) Increase

(2025-2030) Load Demand 2030

(MW)

IKEDC 1-Ikeja 2,058 42% 2,921

IBEDC 2-Ibadan 2,285 43% 3,267

AEDC 3-Abuja 2,329 50% 3,500

BEDC 4-Benin 1,852 34% 2,489

KAEDCO 5-Kaduna 1,169 81% 2,117

JEDC 6-Jos 646 60% 1,035

EEDC 7-Enugu 1,668 19% 1,979

PHEDC 8-Port Harcourt 1,762 35% 2,385

EKEDC 9-Eko 1,837 22% 2,240

KEDCO 10-Kano 1,565 64% 2,570

YOLA 11-Yola 532 77% 942

Total - 17,703 43.75% 25,447

Export* - 1,541 - 1,831

Total load - 19,244 - 27,278

Source: JICA Study Team Ref: 330 kV export lines: To Sakete 550 MW, To Faraku 500 MW, To Zabori 631 MW

The total generation assumed to be running in each DisCo area is shown in Table 7-7.2 and Figure 7-7.1. It includes 640 MW from PV and 3,240 MW from HPP.

Table 7-7.2 Generation per DisCo running in 2030

DisCo Generation (MW)

IKEDC 1-Ikeja 3,041

IBEDC 2-Ibadan 1,415

AEDC 3-Abuja 5,399

BEDC 4-Benin 5,834

KAEDCO 5-Kaduna 212

JEDC 6-Jos 105

EEDC 7-Enugu 1,051

PHEDC 8-Port Harcourt 8,029

EKEDC 9-Eko 1,350

KEDCO 10-Kano 649

YOLA 11-Yola 1,501

Source: JICA Study Team

The load and total running generation for each DisCo is shown graphically in Figure 7-7.1.

Page 83: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-82

Source: JICA Study Team

Figure 7-7.1 2030 Generation and Loads Per DisCo

Analytically, the generation assumed running is listed in Table 7-7.3. The new generation added, or increase in power plant output, in comparison to the 2025 case, is shown in bold.

Table 7-7.3 Generation running in 2030

Bus Number

Bus Name PGen

(MW) Bus

Number Bus Name

PGen (MW)

Bus Number

Bus Name PGen

(MW)

86012 AFAM VI GT11 150 86069 GBARAIN_GTB2 102 46026 NIPP2 ST 257

86013 AFAM VI GT12 150 86055 GEN_AMADI 45 96007 OATS 270

86014 AFAM VI GT13 105 56010 GEN_KADUNA 194 96021 ODUGPANI NIP 508

86015 AFAM VI ST10 180 46023 GER NIPPGT21 140 96020 ODUGPANI NIP 229

86003 AFAM2 GT5-6 48 46024 GER NIPPGT22 140 76000 OKPAI GT11 149

86004 AFAM2GT 7-8 48 96015 GEREGU 2 266 76001 OKPAI GT12 148

86005 AFAM3 GT9-10 54 96014 GEREGU 2 248 76020 OKPAI GT4PH2 135

86006 AFAM3GT11-12 54 46020 GEREGU GT11 124 76021 OKPAI GT5PH2 135

86080 AKWA-IBOM NU 1800 56003 GURARA GBUS 18 76002 OKPAI ST18 126

86039 ALAOJI_GTB1 112.5 96002 HUDSON 135 76022 OKPAI STPH2 135

86040 ALAOJI_GTB2 112.5 86025 IBOM GT1 32 16064 OLOR NIPPST1 100

86041 ALAOJI_GTB3 112.5 86026 IBOM GT2 32 16065 OLOR NIPPST2 100

86042 ALAOJI_GTB4 112.5 86027 IBOM GT3 32 16060 OLORNIPPGT11 100

86043 ALAOJI2_STB1 257 86028 IBOM II 497 16061 OLORNIPPGT12 100

86031 ALSCON GT1 90 96013 IHOVBOR 2 229 16062 OLORNIPPGT21 100

86032 ALSCON GT2 117 46031 IHOVBOR_GTB1 110 16063 OLORNIPPGT22 100

46027 ASCO G1 50 46032 IHOVBOR_GTB2 110 16050 OLORUNSO GT1 30

46028 ASCO G2 50 46033 IHOVBOR_GTB3 110 16055 OLORUNSO GT6 15

96011 AZIKEL 440 46034 IHOVBOR_GTB4 110 16057 OLORUNSO GT8 30

46035 AZURA GT 280 66033 JBS WIND 70 86047 OMA_GT 450

96001 BRESSON 135 36006 JEBBA 2G1 80 86022 OMOKU2 GT2 102

16008 BRESSON GTS 80 36007 JEBBA 2G2 80 26026 OMOTNIPP GT1 115

96009 CABLE INLAND 1350 36008 JEBBA 2G3 80 26027 OMOTNIPP GT2 115

Page 84: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-83

Bus Number

Bus Name PGen

(MW) Bus

Number Bus Name

PGen (MW)

Bus Number

Bus Name PGen

(MW)

86061 CALABAR_GTB2 100 36009 JEBBA 2G4 80 26030 OMOTOSHO 2+ 230

86060 CALABAR_GTB3 100 36011 JEBBA 2G6 80 26020 OMOTOSO GT1 74

76011 CENTURY IPP 223 36004 KAINJ 1G11 80 96008 ONDO IPP 400

96006 CHEVRON TEX 702 36005 KAINJ 1G12 80 16012 PARAS 270

86030 CUMMINS 135 36000 KAINJ 1G5 80 16011 PARASGT1-9 54

46006 DELTA IV 2-1 140 36001 KAINJ 1G6 80 46070 PROTON 135

46007 DELTA IV 2-2 140 36002 KAINJ 1G7-8 160 86070 QUA IBOE PP 468

46008 DELTA IV 2-3 140 36003 KAINJ 1G9-10 160 86035 RIVERS _GT1 172

46010 DELTAIV GT19 133 76013 KASHIMB HPP 21 46050 SAP_NIPP_GT1 100

46011 DELTAIV GT20 133 56011 KAZAURE PV1 80 46051 SAP_NIPP_GT2 100

66005 DKOWA G1 14 56012 KAZAURE PV2 80 46052 SAP_NIPP_GT3 100

96018 EGBEMA II 114 56013 KAZAURE PV3 80 46012 SAPELE GT1-2 180

86067 EGBEMA_GTB3 100 56014 KAZAURE PV4 80 46013 SAPELE GT3-4 90

16000 EGBIN GT 1 254.1 56015 KAZAURE PV5 80 46060 SAPELE ROT 140

16001 EGBIN GT 2 254.1 56016 KAZAURE PV6 80 46061 SAPELE ROT 2 140

16002 EGBIN GT 3 254.1 56017 KAZAURE PV7 80 46062 SAPELE ROT 2 130

16003 EGBIN GT 4 254.1 56018 KAZAURE PV8 80 36012 SHIROR 411G1 120

16004 EGBIN ST 5 254.1 46080 KOJI NUCLEAR 1800 36013 SHIROR 411G2 120

16005 EGBIN ST 6 254.1 55075 KT WF 33 9 36014 SHIROR 411G3 120

86050 ELEME 68 16010 LAFARAGE 2 200 96016 TURBINE DR 300

86056 ESSAR GTS 150 66008 MAMBILA GT2 250 96004 WESCOM 225

86057 ESSAR ST 140 66009 MAMBILA GT3 250 96017 YELLOW STONE 324

96012 ETHIOPE 450 66010 MAMBILA GT4 250 46029 ZUMA 810

46037 ETHIOPE GTS 310 66011 MAMBILA GT5 250 86071 ZUMA (GAS) 337

46038 ETHIOPE ST 140 66014 MAMBILA GT8 250 36024 ZUNGE_G1 150

86048 GBARAIN 2 GT 511 66015 MAMBILA GT9 250 36025 ZUNGE_G2 150

86068 GBARAIN_GTB1 102 96005 MBH 270

Source: JICA Study Team

Page 85: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-84

Source: JICA Study Team

Figure 7-7.2 Configuration of the 330-kV grid in 2030

7-7-2 Summary of the Load-flow Calculations for 2030

The ratings of the 330kV DC option are found adequate for meeting the Grid Code requirements. Using this option, the transmission system loading is shown in Figure 7-7.3.

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1433 MW

8 TO 4 380 MW

3 TO 2 -514 MW

7 TO 4 1001 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETW ORK

G

G

G

G

G

G

6 TO 3 650 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 891 MW

G

G

G

DISCOS

2 TO 1 1502 MW

4 TO 3 -37 MW

G

G

Diagram created using'D:\NIGERIA - YEC\PSSE Yachiyo MP\2030\Master 2030-330kV SG Yach reinf.sav''D:\NIGERIA - YEC\PSSE Yachiyo MP\Dwgs SLDs- Power Exch\Power Exchanges 330kV model Yach SGRD 2020-2030.sld'

GG

3 TO 5 2610 MW

1 TO 9 -1 MW

GG

5 TO 6 -70 MW

10 TO 6 0 MW

5 TO 10 -569 MW

6 TO 11 -402 MW

G

4 TO 9 485 MW

4 TO 1 1331 MW

G

G

TCN 2030 MODELDISCO DEMANDSUN, JUL 22 2018 15:57

0.990

0.988

253

15

0.988

0.968

1.003

38

8

21

38

8

21

38

8

21

38

8

21

83004

IKOT-EKPENE_

73006UGWUAJI_3

73001ONITSHA 3

73005ASABA_3

0.999

0.999

632

30

0.99919

0

46

19

0

46

0.96173003MAKURDI_3

0.957

1

0.956

35

36

1

0.983

456

85

456

85

456

85

456

85

1.00041

6

6 41

6

6

0.994

59

3

14

8

59

3

14

833007

GWAGW BB1

1.004

189

51 189

51

191

81

0.989

23005AKURE 3

0.910

0.997

609 69

65

155

23001

OSOGBO 3

0.959

379

14

379

14

104

139

0.947

677

31

0.988

238

99

238

99

39

32

5

2

3

23003GANMO 3

23002OMOTOSHO3

33002

BKEBBI 3 0.971

0.9911.001

199

97

199

97

256

88256

88

25

4

24

0.944

37

65

0.981

0.973

1

2

0.982

328

21 328

21

328

21

328

21

13003IKEJA W 3

13029OGIJO 3

0.976

233

9 233

9

362

50

362

50

13030MFM 3

0.967

50

133

0.979

393

4141

248

79

248

79

0.960

10

4

25

10

5

57

1 2

SW

13

5

63007

DAMATURU 3 0.947

23

0

20

63005

MAIDUGURI 3 0.918

10

3

59

2

0.978

34

28

34

28

150

100

150

100

150

100 150

100

433

174

263

8 263

8

13002EGBIN 3

0.969

0.977

628

107

0.983

104

139

104

139

722

162

722

162

0.991

275

37

275

37

0.996

370

58

370

58

480

62 480

62

241

14

241

14

13025

EPE 3

13000

AJA 3

13031

OKO_OBA_3

13034

LEKKI 330

13027

ALAGBON_3

13001

AKANGBA 3

586

94

74

85

1

33001KATAMPE 3

0.987

24

4

74

24

4

74

1.011

41

8

10

41

8

10

83007

ONNIE_3

0.997

16

2

69

16

2

69

50

1

58

50

1

58

1

83002

ALAOJI 3

1.002 0 66

0 66

10

9

34

20

2

820

2

8 10

9

34

1.006 3

92

8 39

2

8

0.995

74 84 7

4 84

1.006

26

612

26

612

83010IKOT ABASI_3

1.016 14

8

17

14

8

17

83000

AFAM IV 3

83005

OWERRI_3

0.967

12

7

77

16

6

30

16

6

30

0.959

46

6

22

46

6

22

41

4

72

41

4

72

73004ALIADE_3

63001JOS 3

0.957

10

5

14

10

5

14

73010ABAKALIKI_3

0.942

28

0

48

1

63002YOLA 3

0.978

53001

KANO 3

0.907

0

410

410.901

382

59

53005KANO_NEW330

0.938

383

53

53003ZARIA_330

53000KADUNA 3

53002

KATSINA 3

0.925

36

8

36

63

36

8 36

63

0.982

10

1

14 1

01

14

13032NEW_AGBARA_3

0.972

127

21

1550

50

23000AYEDE 3

1.01243000

AJAOKUTA 3

43002BENIN 3

0.995 46

0

16

43001

ALADJA 3

43003

DELTA IV 3

1.004

257

83

452

50

452

50

452

50

43004

SAPELE 3

43011B_NORTH_3

1.013

58

7

59

58

7

59

0.978

22

5

81

22

5

81

43009OBAJANA_3

1.009

34

5

71

34

5

71

83006

EGBEMA_3

83009

OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000GOMBE 3

29

8

23

2

1 2

33020SHIRORO 3

33008WESTMAIN_3

73000NHAVEN 3

0.952

17

2

10

17

2

10

53004

FUNTUA 3

0.941

68

19

68

19

53007

TMAFARA3

0.947

53008

GUSAU 3

48

14 48

14

183

24 183

24

312

37312

37

33021

KAINJI 3

1.001102

48

33005KAINJI G .S.3

33003JEBBA T.S.3

231

20

232

38

628

107

25

4

24

25

4

24

35

31

28

0

48

23

0

20

22

10

3

59

0.989

170

522

01

57

33009ZUNGERU

33004JEBBA G.S.3

33022

APO_NEW 3

0.910

33023

LAFIA 3

0.935

36

2

90

373

72

670

48

670

48

166

47 166

47

63003

BAUCHI 3 0.956

42

12

18

5

33

63008

MAMBILA 3

1.013

0.997

35

1

22

35

1

22

1.000

43006

EFFURUN 3

253

15

73002OKPAI 3

0.991

0.990

42

3

36

42

3

36

73030IHIALA 3

23006IBADAN

1.000

13026

OKE_ARO_3

49

3

0

53012

DUTSE 3

1.000

53011

KAZAURE 3

0.935

1.000

4575

454

59

1

79

59

1

1

2

0.994

63009

WUKARI

53010

EN ARFICA PV

0.941

67

27

67

27

83001

ALAOJI NIPP3

73007

NNEWI 3

0

329

30

338

1

2

1

13004

SAKETE 3

2

10

2

30

0.997

0.997

13028ARIGBAJO

75 153153

63006JALINGO_3

47

6

79

4

33010

ZABORI

0.961

31

9 2

315

0

31

9 2

315

0631

0

212

25

21

3

9

19

8

212

25

213

9

13012PARAS

0.989

50

750

7

185

58

185

58

33011

FARAKU

0.995

252

16

250

0252

16

250

0

500

0

43012

ZUMA 1.006

62

5

28

62

5

28

10

19

98

10

19

98

53013

DAURA

0.935

83

52 83

52

231

76231

76

53016

JOGANA

0.916 105

81

10674

334

5

326

5

12

54

12

54

53020

MILLENIUM

0.955

98

14

98

18

45

294

5

33

63015

MAYOBELWA 0.94849

2

10

245

29 245

29

86

25

85

45

86

25 8

5

45

20

1

57 2

01

632

01

57

201

63

253

15

25

6

38

55

67

56

49

55

67

56

49

448

88

474

70

463

28

474

70

463

28

48

9

13

43007AZURA

49

1

51

481

2

2

10

2

30

43010ETHIOPE

SW

12

08

90001

1.0022008

109

90002

1563

119

370

32370

32

90003

0.982

85

5

10

7

90004

0.960 466

811

105811105

248

15

248

15

90005

0.962

520

85

63485

63485

90006

1.000

1158

580

131

126131

126

352 112

352 112

90007

1.012

17

65

24

2

11

10

2 11

10

2

84

5

16

5 8

45

16

5

90008

0.941

1087

25

558

93

558

93

43008LOKOJA _3

0.960

0.988

90009

1.001

419

130

39

1

12

23

91

12

2

184

67

184

67

1031

33006

SOKOTO 3

81 191

8118

4

0.967

306

15

306

15441

45441

45

23007ADO EKITI 3

0.836

43013OKENE 3

0.915

384

126

53021

AZARE 3

0.913

63016

GOMBI 3

0.862

63017

BIU 3

0.889

63018

POTISKUM 3

0.880

73031KASHIMBILLA3

1.006

73032AYANGBA 3 0.924

83011OGOJA 3

0.895

0

0

83012IKOM 3 0.9100 0

43005GEREGU

448

88

90010

_1

0.989

676

184

339

6

339

6 675

69 675

69

13005OLORUNSOGO3

433

174

23010SHAGAMU

0.978

131

58131

58

37

65

393

50

13

3

13035

IJORA 3

90011

0.971

70177

35

7

11

35

7

11

1.000

190

20

32021

NIAMEY 1

0.805

1

58

16

52010

GAZOUA 1

SW

49

1.000

SW

568

12003IKEJA W 1BB1

Export 1829 MW

Total Generation 28601 MWNigeria Load 25390 MW

Generation from HPP 3240 MW

Generation per DISCO Loads per DISCO

3-Abuja 5399 MW

4-Benin 5834 MW

9-Eko 1350 MW

7-Enugu 1051 MW

2-Ibadan 1415 MW

1-Ikeja 3056 MW

6-Jos 105 MW

5-Kaduna 212 MW

10-Kano 649 MW

8-Pt Harco 8029 MW

11-Yola 1501 MW

Generation from PV 640 MW

Total Load 27219 MW

9-Eko 2240 MW

7-Enugu 1984 MW

2-Ibadan 3256 MW

6-Jos 1035 MW

5-Kaduna 2116 MW

10-Kano 2547 MW

8-Pt Harco 2379 MW

11-Yola 940 MW

1-Ikeja 2921 MW

3-Abuja 3499 MW

4-Benin 2471 MW

250

35

250

35

250

35

250

35

0

0

0

0

250

35

250

35

0

0

1

44

1250

53R

1250

53R

250

53R

1250

53R

1250

53R

1250

53R

11

44R

36033

ABUJA TPP

Page 86: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-85

Source: JICA Study Team

Figure 7-7.3 Transmission Line Loadings in 2030

No overloads or voltage violation encountered in the 330 and 132 kV systems.

One or two minor voltage violations at 132 kV (0.84 pu) will be corrected when the 132-kV network is reinforced to meet the N-1 criterion, as proposed earlier.

7-7-3 Reactive Power Compensation

In addition to the requirements described for the 2025 case, the following reactive power compensation would be required by 2030:

At 330 kV Gombe substation, 100 MVar Capacitors or SVC.

With regards to Bernin Kebbi, for the 2025 case, power compensation (150 MVar capacitors) will be required at Bernin Kebbi due to export requirements to WAPP. It should be noted however that in 2030 the proposed supergrid will be extended with a Kainji-Bernin Kebbi line. Once this implemented, there will be no further need for reactive power compensation at Bernin Kebbi.

Due to the sharp increase in forecast load in Abuja, the largest reactive power compensation is required at the Abuja area (Gwangwalada 330kV substation) of approx. 700 MVar. It is recommended that this,

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1433 MW

8 TO 4 380 MW

3 TO 2 -514 MW

7 TO 4 1001 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETW ORK

G

G

G

G

G

G

6 TO 3 650 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 891 MW

G

G

G

DISCOS

2 TO 1 1502 MW

4 TO 3 -37 MW

G

G

Diagram created using'D:\NIGERIA - YEC\PSSE Yachiyo MP\2030\Master 2030-330kV SG Yach reinf.sav''D:\NIGERIA - YEC\PSSE Yachiyo MP\Dwgs SLDs- Power Exch\Power Exchanges 330kV model Yach SGRD 2020-2030.sld'

GG

3 TO 5 2610 MW

1 TO 9 -1 MW

GG

5 TO 6 -70 MW

10 TO 6 0 MW

5 TO 10 -569 MW

6 TO 11 -402 MW

G

4 TO 9 485 MW

4 TO 1 1331 MW

G

G

TCN 2030 MODELDISCO DEMANDSUN, JUL 22 2018 15:57

0.990

0.988

253

15

0.988

0.968

1.003

38

8

21

38

8

21

38

8

21

38

8

21

83004

IKOT-EKPENE_

73006UGWUAJI_3

73001ONITSHA 3

73005ASABA_3

0.999

0.999

632

30

0.99919

0

46

19

0

46

0.96173003MAKURDI_3

0.957

1

0.956

35

36

1

0.983

456

85

456

85

456

85

456

85

1.00041

6

6 41

6

6

0.994

59

3

14

8

59

3

14

8

33007GWAGW BB1

1.004

189

51 189

51

191

81

0.989

23005AKURE 3

0.910

0.997

609 69

65

155

23001

OSOGBO 3

0.959

379

14

379

14

104

139

0.947

677

31

0.988

238

99

238

99

39

32

5

2

3

23003GANMO 3

23002OMOTOSHO3

33002

BKEBBI 3 0.971

0.9911.001

199

97

199

97

256

88256

88

25

4

24

0.944

37

65

0.981

0.973

1

2

0.982

328

21 328

21

328

21

328

21

13003IKEJA W 3

13029OGIJO 3

0.976

233

9 233

9

362

50

362

50

13030MFM 3

0.967

50

133

0.979

393

4141

248

79

248

79

0.960

10

4

25

10

5

57

1 2

SW

13

5

63007

DAMATURU 3 0.947

23

0

20

63005

MAIDUGURI 3 0.918

10

3

59

2

0.978

34

28

34

28

150

100

150

100

150

100 150

100

433

174

263

8 263

8

13002EGBIN 3

0.969

0.977

628

107

0.983

104

139

104

139

722

162

722

162

0.991

275

37

275

37

0.996

370

58

370

58

480

62 480

62

241

14

241

14

13025

EPE 3

13000

AJA 3

13031

OKO_OBA_3

13034

LEKKI 330

13027

ALAGBON_3

13001

AKANGBA 3

586

94

74

85

1

33001KATAMPE 3

0.987

24

4

74

24

4

74

1.011

41

8

10

41

8

10

83007

ONNIE_3

0.997

16

2

69

16

2

69

50

1

58

50

1

58

1

83002

ALAOJI 3

1.002 0 66

0 66

10

9

34

20

2

820

2

8 10

9

34

1.006

39

2

8 39

2

8

0.995

74 84 7

4 84

1.006

26

612

26

612

83010IKOT ABASI_3

1.016 14

8

17

14

8

17

83000

AFAM IV 3

83005

OWERRI_3

0.967

12

7

77

16

6

30

16

6

30

0.959

46

6

22

46

6

22

41

4

72

41

4

72

73004ALIADE_3

63001JOS 3

0.957

10

5

14

10

5

14

73010ABAKALIKI_3

0.942

28

0

48

1

63002YOLA 3

0.978

53001

KANO 3

0.907

0

410

410.901

382

59

53005KANO_NEW330

0.938

383

53

53003ZARIA_330

53000KADUNA 3

53002

KATSINA 3

0.925

36

8

36

63

36

8 36

63

0.982

10

1

14 1

01

14

13032NEW_AGBARA_3

0.972

127

21

1550

50

23000AYEDE 3

1.01243000

AJAOKUTA 3

43002BENIN 3

0.995 46

0

16

43001

ALADJA 3

43003

DELTA IV 3

1.004

257

83

452

50

452

50

452

50

43004

SAPELE 3

43011B_NORTH_3

1.013

58

7

59

58

7

59

0.978

22

5

81

22

5

81

43009OBAJANA_3

1.009

34

5

71

34

5

71

83006

EGBEMA_3

83009

OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000GOMBE 3

29

8

23

2

1 2

33020SHIRORO 3

33008WESTMAIN_3

73000NHAVEN 3

0.952

17

2

10

17

2

10

53004

FUNTUA 3

0.941

68

19

68

19

53007

TMAFARA3

0.947

53008

GUSAU 3

48

14 48

14

183

24 183

24

312

37312

37

33021

KAINJI 3

1.001102

48

33005KAINJI G .S.3

33003JEBBA T.S.3

231

20

232

38

628

107

25

4

24

25

4

24

35

31

28

0

48

23

0

20

22

10

3

59

0.989

170

52

20

1

57

33009ZUNGERU

33004JEBBA G .S.3

33022

APO_NEW 3

0.910

33023

LAFIA 3

0.935

36

2

90

373

72

67048

670

48

166

47 166

47

63003

BAUCHI 3 0.956

42

12

18

5

33

63008

MAMBILA 3

1.013

0.997

35

1

22

35

1

22

1.000

43006

EFFURUN 3

253

15

73002OKPAI 3

0.991

0.990

42

3

36

42

3

36

73030IHIALA 3

23006IBADAN

1.000

13026

OKE_ARO_3

49

3

0

53012

DUTSE 3

1.000

53011

KAZAURE 3

0.935

1.000

4575

454

59

1

79

59

1

1

2

0.994

63009

WUKARI

53010

EN ARFICA PV

0.941

67

27

67

27

83001

ALAOJI NIPP3

73007

NNEWI 3

0

329

30

338

1

2

1

13004

SAKETE 3

2

10

2

30

0.997

0.997

13028ARIGBAJO

75 153153

63006JALINGO_3

47

6

79

4

33010

ZABORI

0.961

31

9 2

315

0

31

9 2

315

0631

0

212

25

21

3

9

19

8

212

25

213

9

13012PARAS

0.989

50

750

7

185

58

185

58

33011

FARAKU

0.995

252

16

250

0252

16

250

0

500

0

43012

ZUMA 1.006

62

5

28

62

5

28

10

19

98

10

19

98

53013

DAURA

0.935

83

52 83

52

231

76231

76

53016

JOGANA

0.916

105

8110674

334

5

326

5

12

54

12

54

53020

MILLENIUM

0.955

98

14

98

18

45

29

45

33

63015

MAYOBELWA 0.94849

2

10

245

29 245

29

86

25

85

45

86

25

85

45

20

1

57 2

01

63

20

1

57

201

63

253

15

25

6

38

55

67

56

49

55

67

56

49

448

88

474

70

463

28

474

70

463

28

48

9

13

43007AZURA

49

1

51

481

2

2

10

2

30

43010ETHIOPE

SW

12

08

90001

1.0022008

109

90002

1563

119

370

32370

32

90003

0.982

85

5

10

7

90004

0.960 466

811

105811105

248

15

248

15

90005

0.962

520

85

63485

63485

90006

1.000

1158

580

131

126131

126

352 112

352 112

90007

1.012

17

65

24

2

11

10

2 11

10

2

84

5

16

5 8

45

16

5

90008

0.941

1087

25

558

93

558

93

43008LOKOJA _3

0.960

0.988

90009

1.001

419

130

39

1

12

23

91

12

2

184

67

184

67

1031

33006

SOKOTO 3

81 191

8118

4

0.967

306

15

306

15441

45441

45

23007ADO EKITI 3

0.836

43013OKENE 3

0.915

384

126

53021

AZARE 3

0.913

63016

GOMBI 3

0.862

63017

BIU 3

0.889

63018

POTISKUM 3

0.880

73031KASHIMBILLA3

1.006

73032AYANGBA 3 0.924

83011OGOJA 3

0.895

0

0

83012IKOM 3 0.9100 0

43005GEREGU

448

88

90010

_1

0.989

676

184

339

6

339

6 675

69 675

69

13005OLORUNSOGO3

433

174

23010SHAGAMU

0.978

131

58131

58

37

65

393

50

13

3

13035

IJORA 3

90011

0.971

70177

35

7

11

35

7

11

1.000

190

20

32021

NIAMEY 1

0.805

1

58

16

52010

GAZOUA 1

SW

49

1.000

SW

568

12003IKEJA W 1BB1

Export 1829 MW

Total Generation 28601 MWNigeria Load 25390 MW

Generation from HPP 3240 MW

Generation per DISCO Loads per DISCO

3-Abuja 5399 MW

4-Benin 5834 MW

9-Eko 1350 MW

7-Enugu 1051 MW

2-Ibadan 1415 MW

1-Ikeja 3056 MW

6-Jos 105 MW

5-Kaduna 212 MW

10-Kano 649 MW

8-Pt Harco 8029 MW

11-Yola 1501 MW

Generation from PV 640 MW

Total Load 27219 MW

9-Eko 2240 MW

7-Enugu 1984 MW

2-Ibadan 3256 MW

6-Jos 1035 MW

5-Kaduna 2116 MW

10-Kano 2547 MW

8-Pt Harco 2379 MW

11-Yola 940 MW

1-Ikeja 2921 MW

3-Abuja 3499 MW

4-Benin 2471 MW

250

35

250

35

250

35

250

35

0

0

0

0

250

35

250

35

0

0

1

44

1250

53R

1250

53R

250

53R

1250

53R

1250

53R

1250

53R

11

44R

36033

ABUJA TPP

375

250

125

500

0

MV

A F

low

TCN330kV TRANSMISSINO NETWORK

TCN2030MODEL

Total Generation: 28601 MW

Nigeria Load: 25390 MW

Export: 1829 MW

Total Load: 27219 MW

Generation from PV: 640 MW

Generarion from HPP: 3240 MW

Page 87: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-86

too, be the subject of a separated and dedicated reactive power compensation study, to determine the optimum locations and sizes required. Such a study shall be conducted at a later stage, when the current information on generation expansion plans and load forecast is updated.

However, if the Gwangwalada Power Plant of 1,000MW is in operation in 2030, instead of later, there will be no need for reactive power compensation in that area.

20 MVar capacitor at Gashuwa 132 kV

60 MVar capacitor at Apo 132 kV

25 MVar capacitor at Keffi 132 kV

40 MVar capacitor at Uba 132kV

Page 88: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-87

7-8 Expansion Plan for 2035

7-8-1 2035 Base Cases Load-flow Analysis

7-8-1-1 Transmission system

Figure 7-8.1 below shows the 330kV transmission system in 2035.

Source: JICA Study Team

Figure 7-8.1 Configuration of 330 kV grid in 2035

Table 7-8.1 shows that the increase in load demand in 2035.

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1405 M W

8 TO 4 585 M W

3 TO 2 -159 M W

7 TO 4 1710 M W

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 1042 M W

7 TO 6 1626 M W

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 911 M W

G

G

G

DISCOS

2 TO 1 1914 M W

4 TO 3 -207 M W

G

G

Diagram c reated us ing' D:\NIGERIA - YEC\PSSE Yac hiy o M P\2035\M as ter 2035-330k V SG Yac h re in f1.s av '' D:\NIGERIA - YEC\PSSE Yac hiy o M P\Dwgs SLDs - Power Ex c h\Power Ex c hanges 330k V m odel Yac h SGRD 2020-2030.s ld '

GG

3 TO 5 2446 M W

1 TO 9 -136 M W

GG

5 TO 6 -440 M W

10 TO 6 0 M W

5 TO 10 -555 M W

6 TO 11 -717 M W

G

4 TO 9 708 M W

4 TO 1 1712 M W

G

G

TCN 2035 MODELDISCO DEMANDSAT, JUL 28 2018 18:59

0.998

0.975

424

12

0.986

0.991

1.013

38

7

2

38

7

2

38

7

2

38

7

2

83004IKOT- EKPENE_

73006

UGW UAJI_3

73001ONITSHA 3

73005ASABA_3

0.999

0.992

778

43

0.995

29

2

39

29

2

39

1.01073003

MAKURDI_3

1.008

1

0.971

22

3

12

1

0.987

385

34

385

34

385

34

385

34

0.98044

7

60

44

7

60

0.985

48

3 82

48

3 82

33007GW AGW BB1

0.993

349

93 349

93

355

86

0.973

23005

AKURE 3

0.869

0.985

682 88

168

189

23001OSOGBO 3

0.930

406

13

406

13

62

164

0.910

676

86

0.969

176

112

176

112

19

3

36

3

2

3

23003

GANMO 3

23002

OMOTOSHO3

33002

BKEBBI 3 1.000

0.9720.983

199

102

199

102

208

88208

88

29

2

39

0.913

111

48

0.958

0.955

1

2

0.964

419

12 419

12

419

12

419

12

13003

IKEJA W 3

13029OGIJO 3

0.956

240

7 240

7

423

57

423

57

13030MFM 3

0.949

13

126

0.962

464

5050

241

104

241

104

0.990

22

0

25

22

4

35

1 2

SW

38

0

63007

DAMATURU 3 0.951

34

2

30

63005

MAIDUGURI 3 0.903

15

9

65

2

0.955

51

5

51

5

150

99

150

99

150

99 150

99

402

219

269

40 269

40

13002EGBIN 3

0.952

0.961

684

121

0.967

103

137 10

3

137

792

187

792

187

0.978

304

48

304

48

0.984

413

79

413

79

532

82 532

82

350

6

350

6

13025

EPE 3

13000

AJA 3

13031OKO_OBA_3

13034LEKKI 330

13027ALAGBON_3

13001

AKANGBA 3

604

75

83

117

1

33001

KATAMPE 3

0.965

27

1

83

27

1

83

1.012

53

2 12

53

2 12

83007ONNIE_3

1.000

13

0

11

61

30

11

6

62

8

10

3 6

28

10

3

1

83002

ALAOJI 3

1.003

56

51

56

51

70

70

31

7

27

31

7

27

70

70

1.013

35

2

46

35

2

46

0.999

115 1

01

11

5 10

1

1.010

22

933

22

933

83010

IKOT ABASI_3

1.018 16

3

20

16

3

20

83000

AFAM IV 3

83005

OW ERRI_3

0.989

30

50

25

6

46

25

6

46

1.005

36

6

82

36

6

82

31

7 75

31

7 75

73004ALIADE_3

63001

JOS 3

0.981

10

6

11

10

6

11

73010

ABAKALIKI_3

0.932

29

6

10

8

1

63002YOLA 3

0.976

53001KANO 3

0.905

0

410

410.896

628

72

53005

KANO_NEW 330

0.926

682

187

53003ZARIA_330

53000

KADUNA 3

53002

KATSINA 3

0.948

43

54

43

107

43

54 43

107

0.962

16

3

31 1

63

31

13032

NEW _AGBARA_3

0.943

96

33

1550

181

23000

AYEDE 3

1.010

43000AJAOKUTA 3

43002

BENIN 3

0.983

70

7

6

43001

ALADJA 3

43003

DELTA IV 3

0.998

372

116

393

108

393

108

393

108

43004

SAPELE 3

43011B_NORTH_3

1.011

51

3

70

51

3

70

0.963

30

0

11

5

30

0

11

5

43009OBAJANA_3

1.010

23

9

53

23

9

53

83006EGBEMA_3

83009OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000GOMBE 3

47

6

33

2

1 2

33020

SHIRORO 3

33008W ESTMAIN_3

73000

NHAVEN 3

0.958

17

8

66

17

8

66

53004

FUNTUA 3

0.920

15

13

15

13

53007TMAFARA3

0.942

53008

GUSAU 3 105

44 105

44

182

19 182

19

390

83390

83

33021KAINJI 3

0.983115

48

33005

KAINJI G.S.3

33003JEBBA T.S.3

403

16

408

2

684

121

29

2

39

29

2

39

220

54

29

6

10

8

34

2

30

51

15

9

65

0.992

41

77

11

2

55

33009ZUNGERU

33004JEBBA G.S.3

33022APO_NEW 3

0.920

33023

LAFIA 3

0.981

48

1

13

9

499

73

558

7

558 7

290

88 290

88

63003BAUCHI 3 0.995

15

4

14

31

0

4

63008

MAMBILA 3

1.033

1.000

35

1

15

35

1

15

1.000

43006EFFURUN 3

424

12

73002OKPAI 3

1.006

1.002

60

0

28

60

0

28

73030

IHIALA 3

23006

IBADAN

1.000

13026OKE_ARO_3

56

5

37

53012

DUTSE 3

1.000

53011

KAZAURE 3

0.947

1.000

30 99

3030

75

5

13

4

75

5

1

2

1.008

63009W UKARI

53010

EN ARFICA PV

0.930

18

5

11

51

85

11

5

83001

ALAOJI NIPP3

73007

NNEW I 3

0

329

30

338

1

2

1

426

36 426

36

433

49

13004

SAKETE 3

42

26

42

65

0.985

0.986

13028ARIGBAJO

99 410410

63006JALINGO_3

57

7

13

4

30

33010ZABORI

0.952

38

0

13

6

375

123

38

0

13

6

375

123750

247

227

63

22

9

52

10

4 3

227

63

229

52

SW

78

1

13012PARAS

0.973

68

268

2

203

88

203

88

33011FARAKU

0.950

278

83

275

90278

83

275

90

550

181

43012ZUMA 1.000

51

6

875

16

87

10

44

15

8

10

44

15

8

53013DAURA

0.947

66

3 66

3

282

39282

39

53016JOGANA

0.91324

95

2487

396

4

385

43

4

110

4

110

53020

MILLENIUM

0.971

41

4

41

9

233

55

23

7

19

63015

MAYOBELW A 0.937

60

6

19

441

65 441

65

41

46

41 2

6

41

46

41 2

6

11

2

55 1

12

63

11

2

55

112

63

424

12

43

4

17

16

3 1

05

16

4

92

16

3

10

5

16

4

92

448

139

623

139

605

2

623

139

605

2

55

9

66

43007AZURA

59

7 88

582

7

42

26

42

65

43010

ETHIOPE

SW

23

90001

1.0132186

80

90002

1545

102

535

42535

42

90003

0.962

10

22

21

4

90004

0.931 574

884

169884

169

102

39

102

39

90005

1.010

45

226

558

4

558

4

90006

0.980

375

365

83

121 83

121

564

43

564

43

90007

1.010

17

01

29

6

11

2

12

2 11

2

12

2

71

9

72

71

9

72

90008

0.920

1264

77

65

3

13

0

65

31

30

43008

LOKOJA _3

0.942

0.975

90009

0.983

446

113

30

2

14

53

02

14

5

345

53

345

53

1487

33006SOKOTO 3

210 234

20

9

23

1

0.949

353

6

353

6494

58494

58

23007ADO EKITI 3

0.789

43013OKENE 3

0.901

668

200

53021AZARE 3

0.917

63016

GOMBI 3

0.866

63017

BIU 3

0.909

63018POTISKUM 3

0.904

73031

KASHIMBILLA3

1.016

73032

AYANGBA 3 0.949

83011OGOJA 3

0.923

0

0

83012IKOM 3 0.9360 0

43005

GEREGU

448

139

90010

_1

0.973

214

440

508

59

508

59 613

147 613

147

13005

OLORUNSOGO3

402

219

23010SHAGAMU

0.960

128

59128

59

111

48

464

13

12

6

13035

IJORA 3

90011

1.000

811

91

41

5 64

41

5

64

1.000

193

31

32021NIAMEY 1

0.840

1

59

19

52010GAZOUA 1

SW

56

1.000

SW

793

12003IKEJA W 1BB1

E xport 2002 MW

Total Generation 34313 MW

Nigeria Load 30597 MW

Ge n e ra tio n fro m HPP 4 2 3 9 M W

Generation per DISCO Loads per DISCO

3-Abuja 6789 MW

4-Benin 6465 MW

9-Eko 1350 MW

7-Enugu 1667 MW

2-Ibadan 1314 MW

1-Ikeja 2640 MW

6-Jos 1605 MW

5-Kaduna 712 MW

10-Kano 1029 MW

8-Pt Harco 9022 MW

11-Yola 2350 MW

Ge n e ra tio n fro m PV 8 4 0 M W

Total Load 32599 MW

9-Eko 2381 MW

7-Enugu 2042 MW

2-Ibadan 4019 MW

6-Jos 1079 MW

5-Kaduna 2531 MW

10-Kano 3528 MW

8-Pt Harco 2792 MW

11-Yola 1446 MW

1-Ikeja 3534 MW

3-Abuja 4393 MW

4-Benin 2853 MW

250

52

250

52

250

52

250

52

250

52

100

59

250

52

250

52

250

52

250

52

1250

70R

1250

70R

250

70R

1250

70R

250

70R

100

63R

1250

70R

1250

70R

250

70R

1250

70R

12

00

90

0H 96029

GW AGW ALAD

Page 89: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-88

Table 7-8.1 Load demand per DisCo

DisCo Load Demand 2030

(MW) Increase

(2030-2035) Load Demand 2035

(MW)

IKEDC 1-Ikeja 2,921 21.06% 3,536

IBEDC 2-Ibadan 3,267 24.08% 4,054

AEDC 3-Abuja 3,500 25.66% 4,398

BEDC 4-Benin 2,489 16.54% 2,901

KAEDCO 5-Kaduna 2,117 19.61% 2,533

JEDC 6-Jos 1,035 4.24% 1,079

EEDC 7-Enugu 1,979 2.93% 2,037

PHEDC 8-Port Harcourt 2,385 17.49% 2,802

EKEDC 9-Eko 2,240 6.33% 2,382

KEDCO 10-Kano 2,570 38.06% 3,549

YOLA 11-Yola 942 53.72% 1,448

Total - 25,447 20.72% 30,719

Export* - 1,830 - 2,000

Total load - 27,277 - 32,719

Source: JICA Study Team Ref: 330 kV export lines: To Sakete 550 MW, To Faraku 550 MW, To Zabori 750 MW

7-8-1-2 Generation

The total generation assumed to be running in each DisCo area is shown in Table 7-8.2, as well as in Figure 7-8.1. It includes 840 MW from PV and 4,239 MW from HPP.

Table 7-8.2 Generation per DisCo running in 2035

DisCo Generation (MW)

IKEDC 1-Ikeja 2,640

IBEDC 2-Ibadan 1,314

AEDC 3-Abuja 6,789

BEDC 4-Benin 6,465

KAEDCO 5-Kaduna 712

JEDC 6-Jos 1,605

EEDC 7-Enugu 1,667

PHEDC 8-Port Harcourt 9,022

EKEDC 9-Eko 1,350

KEDCO 10-Kano 1,029

YOLA 11-Yola 2,350

Source: JICA Study Team

7-8-2 Summary of the Load-flow Calculations for 2035

The loading of the transmission system is shown in Figure 7-8.2.

Page 90: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-89

Source: JICA Study Team

Figure 7-8.2 Transmission Line Loadings in 2035

7-8-2-1 Transmission Line Overloads and Voltage Violations

No overloads or voltage violations encountered in the 330 and 132 kV systems.

Two or three minor voltage violations at 132 kV (0.84 pu) will be corrected when the 132-kV network is reinforced to meet the N-1 criterion, as proposed earlier.

7-8-3 New Transmission Lines and Reactive Power Requirements

7-8-3-1 New transmission lines

The 330 kV DC line Zuma-Lokoja (25 km) is overloaded due to the Zuma power plant output. Reconductoring is recommended to Quad conductors.

The 330 kV DC line Makurdi-Lafia is overloaded due to the new Ramos 900 MW coal-fired power plant.

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1405 M W

8 TO 4 585 M W

3 TO 2 -159 M W

7 TO 4 1710 M W

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 1042 M W

7 TO 6 1626 M W

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 911 M W

G

G

G

DISCOS

2 TO 1 1914 M W

4 TO 3 -207 M W

G

G

Diagram c reated us ing' D:\NIGERIA - YEC\PSSE Yac hiy o M P\2035\M as ter 2035-330k V SG Yac h re in f1.s av '' D:\NIGERIA - YEC\PSSE Yac hiy o M P\Dwgs SLDs - Power Ex c h\Power Ex c hanges 330k V m odel Yac h SGRD 2020-2030.s ld '

GG

3 TO 5 2446 M W

1 TO 9 -136 M W

GG

5 TO 6 -440 M W

10 TO 6 0 M W

5 TO 10 -555 M W

6 TO 11 -717 M W

G

4 TO 9 708 M W

4 TO 1 1712 M W

G

G

TCN 2035 MODELDISCO DEMANDSAT, JUL 28 2018 18:59

0.998

0.975

424

12

0.986

0.991

1.013

38

7

2

38

7

2

38

7

2

38

7

2

83004IKOT- EKPENE_

73006

UGW UAJI_3

73001ONITSHA 3

73005ASABA_3

0.999

0.992

778

43

0.995

29

2

39

29

2

39

1.01073003

MAKURDI_3

1.008

1

0.971

22

3

12

1

0.987

385

34

385

34

385

34

385

34

0.98044

7

60

44

7

60

0.985

48

3 82

48

3 82

33007GW AGW BB1

0.993

349

93 349

93

355

86

0.973

23005

AKURE 3

0.869

0.985

682 88

168

189

23001OSOGBO 3

0.930

406

13

406

13

62

164

0.910

676

86

0.969

176

112

176

112

19

3

36

3

2

3

23003

GANMO 3

23002

OMOTOSHO3

33002

BKEBBI 3 1.000

0.9720.983

199

102

199

102

208

88208

88

29

2

39

0.913

111

48

0.958

0.955

1

2

0.964

419

12 419

12

419

12

419

12

13003

IKEJA W 3

13029OGIJO 3

0.956

240

7 240

7

423

57

423

57

13030MFM 3

0.949

13

126

0.962

464

5050

241

104

241

104

0.990

22

0

25

22

4

35

1 2

SW

38

0

63007

DAMATURU 3 0.951

34

2

30

63005

MAIDUGURI 3 0.903

15

9

65

2

0.955

51

5

51

5

150

99

150

99

150

99 150

99

402

219

269

40 269

40

13002EGBIN 3

0.952

0.961

684

121

0.967

103

137 10

3

137

792

187

792

187

0.978

304

48

304

48

0.984

413

79

413

79

532

82 532

82

350

6

350

6

13025

EPE 3

13000

AJA 3

13031OKO_OBA_3

13034LEKKI 330

13027ALAGBON_3

13001

AKANGBA 3

604

75

83

117

1

33001

KATAMPE 3

0.965

27

1

83

27

1

83

1.012

53

2 12

53

2 12

83007ONNIE_3

1.000

13

0

11

61

30

11

6

62

8

10

3 6

28

10

3

1

83002

ALAOJI 3

1.003

56

51

56

51

70

70

31

7

27

31

7

27

70

70

1.013

35

2

46

35

2

46

0.999

115 101 1

15 1

01

1.010

22

933

22

933

83010

IKOT ABASI_3

1.018 16

3

20

16

3

20

83000

AFAM IV 3

83005

OW ERRI_3

0.989

30

50

25

6

46

25

6

46

1.005

36

6

82

36

6

82

31

7 75

31

7 75

73004ALIADE_3

63001

JOS 3

0.981

10

6

11

10

6

11

73010

ABAKALIKI_3

0.932

29

6

10

8

1

63002YOLA 3

0.976

53001KANO 3

0.905

0

410

410.896

628

72

53005

KANO_NEW 330

0.926

682

187

53003ZARIA_330

53000

KADUNA 3

53002

KATSINA 3

0.948

43

54

43

107

43

54 43

107

0.962

16

3

31 1

63

31

13032

NEW _AGBARA_3

0.943

96

33

1550

181

23000

AYEDE 3

1.010

43000AJAOKUTA 3

43002

BENIN 3

0.983

70

7

6

43001

ALADJA 3

43003

DELTA IV 3

0.998

372

116

393

108

393

108

393

108

43004

SAPELE 3

43011B_NORTH_3

1.011

51

3

70

51

3

70

0.963

30

0

11

5

30

0

11

5

43009OBAJANA_3

1.010

23

9

53

23

9

53

83006EGBEMA_3

83009OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000GOMBE 3

47

6

33

2

1 2

33020

SHIRORO 3

33008W ESTMAIN_3

73000

NHAVEN 3

0.958

17

8

66

17

8

66

53004

FUNTUA 3

0.920

15

13

15

13

53007TMAFARA3

0.942

53008

GUSAU 3 105

44 105

44

182

19 182

19

390

83390

83

33021KAINJI 3

0.983115

48

33005

KAINJI G.S.3

33003JEBBA T.S.3

403

16

408

2

684

121

29

2

39

29

2

39

220

54

29

6

10

8

34

2

30

51

15

9

65

0.992

41

77

11

2

55

33009ZUNGERU

33004JEBBA G.S.3

33022APO_NEW 3

0.920

33023

LAFIA 3

0.981

48

1

13

9

499

73

558

7

558 7

290

88 290

88

63003BAUCHI 3 0.995

15

4

14

31

0

4

63008

MAMBILA 3

1.033

1.000

35

1

15

35

1

15

1.000

43006EFFURUN 3

424

12

73002OKPAI 3

1.006

1.002

60

0

28

60

0

28

73030

IHIALA 3

23006

IBADAN

1.000

13026OKE_ARO_3

56

5

37

53012

DUTSE 3

1.000

53011

KAZAURE 3

0.947

1.000

30 99

3030

75

5

13

4

75

5

1

2

1.008

63009W UKARI

53010

EN ARFICA PV

0.930

18

5

11

51

85

11

5

83001

ALAOJI NIPP3

73007

NNEW I 3

0

329

30

338

1

2

1

426

36 426

36

433

49

13004

SAKETE 3

42

26

42

65

0.985

0.986

13028ARIGBAJO

99 410410

63006JALINGO_3

57

7

13

4

30

33010ZABORI

0.952

38

0

13

6

375

123

38

0

13

6

375

123750

247

227

63

22

9

52

10

4 3

227

63

229

52

SW

78

1

13012PARAS

0.973

68

268

2

203

88

203

88

33011FARAKU

0.950

278

83

275

90278

83

275

90

550

181

43012ZUMA 1.000

51

6

875

16

87

10

44

15

8

10

44

15

8

53013DAURA

0.947

66

3 66

3

282

39282

39

53016JOGANA

0.91324

95

2487

396

4

385

43

4

110

4

110

53020

MILLENIUM

0.971

41

4

41

9

233

55

23

7

19

63015

MAYOBELW A 0.937

60

6

19

441

65 441

65

41

46

41 2

6

41

46

41 2

6

11

2

55 1

12

631

12

55

112

63

424

12

43

4

17

16

3 1

05

16

4

92

16

3

10

5

16

4

92

448

139

623

139

605

2

623

139

605

2

55

9

66

43007AZURA

59

7 88

582

7

42

26

42

65

43010

ETHIOPE

SW

23

90001

1.0132186

80

90002

1545

102

535

42535

42

90003

0.962

10

22

21

4

90004

0.931 574

884

169884

169

102

39

102

39

90005

1.010

45

226

558

4

558

4

90006

0.980

375

365

83

121 83

121

564

43

564

43

90007

1.010

17

01

29

6

11

2

12

2 11

2

12

2

71

9

72

71

9

72

90008

0.920

1264

77

65

3

13

0

65

31

30

43008

LOKOJA _3

0.942

0.975

90009

0.983

446

113

30

2

14

53

02

14

5

345

53

345

53

1487

33006SOKOTO 3

210 234

20

9

23

1

0.949

353

6

353

6494

58494

58

23007ADO EKITI 3

0.789

43013OKENE 3

0.901

668

200

53021AZARE 3

0.917

63016

GOMBI 3

0.866

63017

BIU 3

0.909

63018POTISKUM 3

0.904

73031

KASHIMBILLA3

1.016

73032

AYANGBA 3 0.949

83011OGOJA 3

0.923

0

0

83012IKOM 3 0.9360 0

43005

GEREGU

448

139

90010

_1

0.973

214

440

508

59

508

59 613

147 613

147

13005

OLORUNSOGO3

402

219

23010SHAGAMU

0.960

128

59128

59

111

48

464

13 1

26

13035

IJORA 3

90011

1.000

811

91

41

5 64

41

5

64

1.000

193

31

32021NIAMEY 1

0.840

1

59

19

52010GAZOUA 1

SW

56

1.000

SW

793

12003IKEJA W 1BB1

E xport 2002 MW

Total Generation 34313 MW

Nigeria Load 30597 MW

Ge n e ra tio n fro m HPP 4 2 3 9 M W

Generation per DISCO Loads per DISCO

3-Abuja 6789 MW

4-Benin 6465 MW

9-Eko 1350 MW

7-Enugu 1667 MW

2-Ibadan 1314 MW

1-Ikeja 2640 MW

6-Jos 1605 MW

5-Kaduna 712 MW

10-Kano 1029 MW

8-Pt Harco 9022 MW

11-Yola 2350 MW

Ge n e ra tio n fro m PV 8 4 0 M W

Total Load 32599 MW

9-Eko 2381 MW

7-Enugu 2042 MW

2-Ibadan 4019 MW

6-Jos 1079 MW

5-Kaduna 2531 MW

10-Kano 3528 MW

8-Pt Harco 2792 MW

11-Yola 1446 MW

1-Ikeja 3534 MW

3-Abuja 4393 MW

4-Benin 2853 MW

250

52

250

52

250

52

250

52

250

52

100

59

250

52

250

52

250

52

250

52

1250

70R

1250

70R

250

70R

1250

70R

250

70R

100

63R

1250

70R

1250

70R

250

70R

1250

70R

12

00

90

0H 96029

GW AGW ALAD

375

250

125

500

0

MV

A F

lo

w

TCN330kV TRANSMISSINO NETWORK

TCN2035MODEL

Total Generation: 34313 MW

Nigeria Load: 30587 MW

Export: 2002 MW

Total Load: 32599 MW

Generation from PV: 840 MW

Generarion from HPP: 4239 MW

Page 91: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-90

A new Wukari-Lafia 330 kV DC line (95 km) is proposed, which will remove these overloads and improve voltage profiles.

The following 330 kV lines are overloaded between 101 and 107% under normal (N-0) operation and need to be converted to Quad conductors

Aja - Lekki

Benin North - Akure

To meet the N-1 criterion and also remove undervoltages, a conversion to a DC circuit is recommended for the following SC 132 kV lines:

Kwaya Kusar - Biu

Biu - Damboa

Damboa - Maiduguri

To meet the N-1 criterion and also eliminate overload, new transmission lines are required, as listed in Table 7-8.3.

Table 7-8.3 New transmission lines and reinforcements required for 2035

Substation Name

Substation Name

Voltage (kV)

Length (km)

Type Proposed Solution

Wukari Lafia 330 95 DC New DC transmission line

Zuma Lokoja 330 25 DC Reconductoring of DC to Quad conductor

Aja Lekki 330 7 DC Reconductoring of DC to Quad conductor

Benin North Akure 330 130 SC Reconductoring to Quad conductor or

conversion to DC

Kwaya Kusar Biu 132 42 SC Convert from SC to DC

Biu Damboa 132 140 SC Convert from SC to DC

Damboa Maiduguri 132 64 SC Convert from SC to DC

Source: JICA Study Team

7-8-3-2 Reactive Power Compensation

In addition to the requirements described for the 2030 case, the following reactive power compensation would be required by 2035:

Due to the sharp increase in forecast load in Abuja, reactive power compensation is required at the Abuja area (Gwangwalada 330 kV substation).

However, if the Gwangwalada Power Plant of 1,200 MW is in operation in 2035, instead of later, there will be no need for reactive power compensation in that area.

250 MVar capacitors at Gombe 330 kV

700 MVar capacitors at Bernin Kebbi 330 kV

300 MVar capacitors at Ikeja West 132 kV

Page 92: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-91

7-8-3-3 Comparison of Load-flow Results Between the EHV Options

The comparison of load-flow results for 2035 between the two EHV options is summarized in Table 7-8.4.

Table 7-8.4 LF results for 2035

Voltage Level (kV)

Generation (MW)

O/V and U/V of 330 kV and above (outside 0.9-1.05)

O/L of 330 kV above 80%

Losses (MW)

Remarks

330 28763 5 buses 16 circuits* 1,471 (5.11%) Slightly lower losses compared to the

500-kV option

500 28974 10 buses 20 circuits * 1,737 (5.99%) 266 MW (0.91%) higher losses

compared to the 330-kV option

750 28688 1 bus 12 circuits** 1,359 (4.73%) Slightly lower losses compared to the

330-kV option

Source: JICA Study Team

7-8-3-4 Conclusion on EHV Options for 2035

The conclusions are the same as for 2030 cases. Based on technical considerations both the 330 and 500 kV options are adequate. Furthermore, taking into consideration that:

Capacity of 330 kV supergrid lines: 3,100 MVA

Capacity of 500 kV supergrid lines: 2,350 MVA

Difference in losses between 330 and 500 kV supergrids: Marginal

Impact on O/U voltages and overloads: 330 kV advantageous

Higher static N-1 security of the 330 kV supergrid due to Double-Circuit lines involved

It appears that the 330 kV supergrid system is technically the preferred option.

There is no justification for adopting and/or further considering any higher (750 kV) option for the EHV grid, particularly when the implications in cost differences are taken into account. The higher transmission capacity (4,400 MVA) is not required at this stage and the marginal differences in losses cannot offset the high investment cost required in the planning horizon of this Master Plan.

Page 93: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-92

7-9 Expansion Plan for 2040

7-9-1 2040 Base Cases Load-flow Analysis

7-9-1-1 Transmission system

Figure 7-9.1 below shows the 330kV transmission system in 2040.

Source: JICA Study Team

Figure 7-9.1 Configuration of 330 kV grid in 2040

7-9-1-2 Load demand

Table 7-9.1 shows that the increase in load demand follows approximately the same increase (in percentage) as in the load forecast detailed in Section 5.4.2.

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1267 MW

8 TO 4 700 MW

3 TO 2 -195 MW

7 TO 4 1985 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 1215 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 1045 MW

G

G

G

DISCOS

2 TO 1 1894 MW

4 TO 3 -213 MW

G

G

Diagram created using'D:\NIGERIA - YEC\PSSE Yachiyo MP\2040\Master 2040-330kV SG Yach reinf1.sav'

'D:\NIGERIA - YEC\PSSE Yachiyo MP\Dwgs SLDs- Power Exch\Power Exchanges 330kV model Yach SGRD 2020-2040.sld'

GG

3 TO 5 2804 MW

1 TO 9 -328 MW

G G

5 TO 6 -481 MW

10 TO 6 0 MW

5 TO 10 -652 MW

6 TO 11 -240 MW

G

4 TO 9 806 MW

4 TO 1 1881 MW

G

G

TCN 2035 MODELDISCO DEMANDSUN, JUL 29 2018 12:57

0.979

0.948

490

19

0.963

0.965

1.000

42

3

7

42

3

7

42

3

7

42

3

7

83004IKOT-EKPENE_

73006UGWUAJI_3

73001ONITSHA 3

73005ASABA_3

0.999

0.976

839

28

0.98035

0

33

35

0

33

0.96373003MAKURDI_3

0.982

1

0.9652

45

18

1

0.971

448

2

448

2

448

2

448

2

0.98054

6

15

54

6

15

0.962

60

4

18

7

60

4

18

7

33007GWAGW BB1

0.979

341

126 341

126

347

115

0.967

23005AKURE 3

0.792

0.963

783 106

257

253

23001OSOGBO 3

0.871

469

23

469

23

51

202

0.834

873

188

0.915

229

112

229

112

26

3

43

9

2

3

23003GANMO 3

23002OMOTOSHO3

33002BKEBBI 3 0.980

0.9180.940

199

99

199

99

210

122210

122

32

3

85

0.864

60

28

0.931

0.938

1

2

0.944

460

10 460

10

460

10

460

10

13003IKEJA W 3

13029OGIJO 3

0.937

240

46 240

46

490

46490

4613030MFM 3

0.934

35

92

0.948

528

115115

336

133

336

133

0.980

28

0

18

28

8

45

1 2

SW

34

0

63007DAMATURU 3 0.960

28

5

8

63005MAIDUGURI 3 0.931

12

7

55

2

0.927

10

40

10

40

150

97

150

97 150

97 150

97

597

336

403

77 403

77

13002EGBIN 3

0.939

0.950

754

163

0.958

174

195 1

74

195

875

243

875

243

0.969

311

48

311

48

0.975

433

86

433

86

549

84 549

85

398

39

398

39

13025EPE 3

13000AJA 3

13031OKO_OBA_3

13034LEKKI 330

13027ALAGBON_3

13001AKANGBA 3

714

130

106 122

1

33001KATAMPE 3

0.960

33

4

12

63

34

12

6

1.012

55

6

22

55

6

22

83007ONNIE_3

0.988

13

7

10

01

37

10

0

79

9

83

79

9

83

1

83002ALAOJI 3

0.991 12

4

54

12

4

54

54

59

41

2

53

41

2

53

54

59

1.005

23

4

66

23

4

66

0.991

14 1

13

14 1

130.999

22

422

22

422

83010IKOT ABASI_3

1.016 18

8

13

18

8

13

83000AFAM IV 3

83005OWERRI_3

0.964

72

76

26

6

31

26

6

31

0.958

51

6

18

51

6

18

45

8

10

3 4

58

10

3

73004ALIADE_3

63001JOS 3

0.965

20

19

20

19

73010ABAKALIKI_3

0.897

14

7

96

1

63002YOLA 3

0.933

53001KANO 3

0.980

0

480

48

SW

605

0.966

734

167

53005KANO_NEW330

0.923

732

171

53003ZARIA_330

53000KADUNA 3

53002KATSINA 3

0.985

4

0

4

64

4

0 4

64

0.944

25

8

10

52

58

10

5

13032NEW_AGBARA_3

0.925

101

37

1550

181

23000AYEDE 3

0.99743000

AJAOKUTA 3

43002BENIN 3

0.960 83

2

29

43001ALADJA 3

43003DELTA IV 3

0.979

337

134

469

146

469

146

469

146

43004SAPELE 3

43011B_NORTH_3

0.998 64

6

14

3

64

6

14

3

0.933

36

5

15

7

36

5

15

7

43009OBAJANA_3

0.998

19

6

91

19

6

91

83006EGBEMA_3

83009OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000GOMBE 3

54

5

62

2

1 2

33020SHIRORO 3

33008WESTMAIN_3

73000NHAVEN 3

0.932

21

8

80

21

8

80

53004FUNTUA 3

0.906

27

58

27

58

53007TMAFARA3

0.923

53008GUSAU 3

144

21 144

21

178

83 178

83

451

91451

91

33021KAINJI 3

0.939106

57

33005KAINJI G .S.3

33003JEBBA T.S.3

468

22

476

13

754

163

32

3

85

32

3

85

241

15

14

7

96

28

5

81

74

12

7

55

0.974

51

121

12

1

19

33009ZUNGERU

33004JEBBA G .S.3

33022APO_NEW 3

0.863

33023LAFIA 3

0.928

52

1

21

5

545

93

66318

66318

322

71 322

71

63003BAUCHI 3 0.972

22

0

29

36

6

13

63008MAMBILA 3

1.020

0.989

35

1

42

35

1

42

1.000

43006EFFURUN 3

490

19

73002OKPAI 3

0.994

0.988

75

0

29

75

0

29

73030IHIALA 3

23006IBADAN

1.000

13026OKE_ARO_3

61

8

21

53012DUTSE 3

0.974

53011KAZAURE 3

0.992

1.000

5 174

597

94

6

18

4

94

6

1

2

0.966

63009WUKARI

53010EN ARFICA PV

0.919

30

0

15

73

00

15

7

83001ALAOJI NIPP3

73007NNEWI 3

0

329

30

338

1

2

1

440

61

440

61

447

89

13004SAKETE 3

63

12

64

48

0.963

0.963

13028ARIGBAJO

174 260260

63006JALINGO_3

73

9

18

4

97

33010ZABORI

0.931

38

1

14

0

375

123

38

1

14

0

375

123750

247

225

62

22

65

2

10

8

22

225

62

226

52

SW

11

05

13012PARAS

0.960

115

69

115

69

249

176

249

176

33011FARAKU

0.904

278

89

275

90278

89

275

90

550

181

43012ZUMA 0.982

79

3

12

9

79

3

12

9

13

13

19

9

13

13

19

9

53013DAURA

0.992

64

40 64

40

329

98329

98

53016JOGANA

0.972101

74

100 83

414

112

401

162

70

70

70

7039

8

53020MILLENIUM

0.962

4

63

4

67

258

16

26

2

9

63015MAYOBELWA 0.8897

88

99

415

92 415

92

33

83

33

16

33

83

33

16 12

1

19 1

21

27

12

1

19

121

27

490

19

50

3

45

20

5 1

20

20

6

11

1

20

5 1

20

20

6

11

1

448

234

679

1

659

158

679

1

659

158

61

1

67

43007AZURA

77

4

13

2

745

79

63

12

64

48

43010ETHIOPE

SW

15

80

90001

0.9992622

407

90002

1749

339

614

94614

94

90003

0.944

12

04

35

0

90004

0.873 817

10323181032318

256

143

256

143

90005

0.963

39

209

696106

696106

90006

0.979

696

1374

60

197

60

197

650

8

650 8

90007

0.996

21

12

47

7

97

15

6 97

15

6

92

4

20

8 92

4

20

8

90008

0.906

1448

155

75

31

95

75

31

95

43008LOKOJA _3

0.923

0.948

90009

0.939

554

99

36

2

15

23

62

15

2

393

27

393

27

1892

33006SOKOTO 3

322 315

32

1

31

7

0.935

414

30

414

30562

98562

98

23007ADO EKITI 3

0.698

43013OKENE 3

0.869

1027

307

53021AZARE 3

0.972

79

1

79

1

63016GOMBI 3

0.909

381

73

381

73

63017BIU 3

0.928

17084

17084

281 111281 111

63018POTISKUM 3

0.967

146

22 146

22

18

6

57

18

6

57

73031KASHIMBILLA3

1.026

73032AYANGBA 3 0.925

83011OGOJA 3

1.027

0

0

83012IKOM 3 1.0160 0

43005GEREGU

448

234

90010_1

0.967

317

139

521

108

521

108 859

319

859

319

13005OLORUNSOGO3

597

336

23010SHAGAMU

0.939

134

67134

67

60

28

528

35

92

13035IJORA 3

90011

0.980

902 212

46

4

71

46

4 71

130

100

1.000

191

31

32021NIAMEY 1

0.868

1

59

2052010

GAZOUA 1

SW

58

1.000

SW

998

12003IKEJA W 1BB1

Export 2000 MW

Total Generation 39916 MWNigeria Load 35598 MW

Genera tion from H PP 4369 MW

Generation per DISCO Loads per DISCO

3-Abuja 7949 MW

4-Benin 7635 MW

9-Eko 1350 MW

7-Enugu 1904 MW

2-Ibadan 1575 MW

1-Ikeja 4125 MW

6-Jos 1745 MW

5-Kaduna 832 MW

10-Kano 1019 MW

8-Pt Harco 10842 MW

11-Yola 2470 MW

Genera tion from PV 990 MW

Total Load 37598 MW

9-Eko 2509 MW

7-Enugu 2114 MW

2-Ibadan 4923 MW

6-Jos 1131 MW

5-Kaduna 3043 MW

10-Kano 4021 MW

8-Pt Harco 3292 MW

11-Yola 1678 MW

1-Ikeja 4295 MW

3-Abuja 5316 MW

4-Benin 3275 MW

250

98

200

101

250

98

250

98

250

98

250

98

250

98

250

98

250

98

250

98

1250

117R

1200

114R

250

117R

1250

117R

250

117R

250

117R

1250

117R

1250

117R

250

117R

1250

117R

12

00

90

0H

96029GWAGWALAD

Page 94: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-93

Table 7-9.1 Load demand per DisCo

DisCo Load Demand 2035

(MW) Increase

(2035-2040) Load Demand 2040

(MW)

IKEDC 1-Ikeja 3,536 21.61% 4,300

IBEDC 2-Ibadan 4,054 24.70% 5,055

AEDC 3-Abuja 4,398 21.31% 5,336

BEDC 4-Benin 2,901 16.90% 3,391

KAEDCO 5-Kaduna 2,533 20.23% 3,045

JEDC 6-Jos 1,079 4.83% 1,131

EEDC 7-Enugu 2,037 3.67% 2,112

PHEDC 8-Port Harcourt 2,802 17.94% 3,305

EKEDC 9-Eko 2,382 5.44% 2,512

KEDCO 10-Kano 3,549 13.38% 4,023

YOLA 11-Yola 1,448 16.05% 1,680

Total - 30,719 16.83% 35,890

Export - 2,000 - 2,000

Total load - 32,719 - 37,890

Source: JICA Study Team Ref: 330 kV export lines: To Sakete 550 MW, To Faraku 550 MW, To Zabori 750 MW

7-9-1-3 Generation

The total generation assumed to be running in each DisCo area is shown in Table 7-9.2 as well as in Figure 7-9.1 and includes 990 MW from PV and 4,369 MW from HPP.

Table 7-9.2 Generation per DisCo running in 2040

DisCo Generation (MW)

IKEDC 1-Ikeja 4,125

IBEDC 2-Ibadan 1,575

AEDC 3-Abuja 7,949

BEDC 4-Benin 7,635

KAEDCO 5-Kaduna 832

JEDC 6-Jos 1,745

EEDC 7-Enugu 1,904

PHEDC 8-Port Harcourt 10,842

EKEDC 9-Eko 1,350

KEDCO 10-Kano 1,019

YOLA 11-Yola 2,470

Source: JICA Study Team

It should be noted that to meet the high load forecast for 2040, an additional power plant is necessary with a minimum capacity of 1,000 MW (such as Ethiope ph 2) to be located near Egbin S/S.

7-9-2 Summary of Load-flow Calculations for 2040

The loading of the transmission system is shown in Figure 7-9.2.

Page 95: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-94

Source: JICA Study Team

Figure 7-9.2 Transmission Line Loadings in 2040

7-9-2-1 Transmission Line Overloads and Voltage Violations

No voltage violation encountered in the 330 and 132 kV systems.

A few minor voltage violations at 132 kV will be corrected when the 132-kV network is reinforced to meet the N-1 criterion, as proposed earlier.

With regards to thermal overloads of the 330-kV system, the following lines are overloaded and need to be reinforced:

Aladja - Delta IV

Osogbo – Ganmo

7-9-3 New Transmission Lines and Reactive Power Requirements

7-9-3-1 New transmission lines

The following new 330 kV transmission lines are recommended at this stage in the North and North-East of the country:

8 PT HARCO EDC

7 ENUGU EDC

8 TO 7 1267 MW

8 TO 4 700 MW

3 TO 2 -195 MW

7 TO 4 1985 MW

G

G

G

G

G

G

TCN 330kV TRANSMISSION NETWORK

G

G

G

G

G

G

6 TO 3 1215 MW

7 TO 6 1626 MW

G

G

4 BENIN EDC

3 ABUJA EDC

9 EKO EDC

2 IBADAN EDC

5 KADUNA EDC

10 KANO EDC

6 JOS EDC

11 YOLA EDC

1 IKEJA EDC

4 TO 2 1045 MW

G

G

G

DISCOS

2 TO 1 1894 MW

4 TO 3 -213 MW

G

G

Diagram created using'D:\NIGERIA - YEC\PSSE Yachiyo MP\2040\Master 2040-330kV SG Yach reinf1.sav'

'D:\NIGERIA - YEC\PSSE Yachiyo MP\Dwgs SLDs- Power Exch\Power Exchanges 330kV model Yach SGRD 2020-2040.sld'

GG

3 TO 5 2804 MW

1 TO 9 -328 MW

G G

5 TO 6 -481 MW

10 TO 6 0 MW

5 TO 10 -652 MW

6 TO 11 -240 MW

G

4 TO 9 806 MW

4 TO 1 1881 MW

G

G

TCN 2035 MODELDISCO DEMANDSUN, JUL 29 2018 12:57

0.979

0.948

490

19

0.963

0.965

1.000

42

3

7

42

3

7

42

3

7

42

3

7

83004IKOT-EKPENE_

73006UGWUAJI_3

73001ONITSHA 3

73005ASABA_3

0.999

0.976

839

28

0.98035

0

33

35

0

33

0.96373003MAKURDI_3

0.982

1

0.965

24

5

18

1

0.971

448

2

448

2

448

2

448

2

0.98054

6

15

54

6

15

0.962

60

4

18

7

60

4

18

7

33007GWAGW BB1

0.979

341

126 341

126

347

115

0.967

23005AKURE 3

0.792

0.963

783 106

257

253

23001OSOGBO 3

0.871

469

23

469

23

51

202

0.834

873

188

0.915

229

112

229

112

26

3

43

9

2

3

23003GANMO 3

23002OMOTOSHO3

33002BKEBBI 3 0.980

0.9180.940

199

99

199

99

210

122210

122

32

3

85

0.864

60

28

0.931

0.938

1

2

0.944

460

10 460

10

460

10

460

10

13003IKEJA W 3

13029OGIJO 3

0.937

240

46 240

46

490

46490

4613030MFM 3

0.934

35

92

0.948

528

115115

336

133

336

133

0.980

28

0

18

28

8

45

1 2

SW

34

0

63007DAMATURU 3 0.960

28

5

8

63005MAIDUGURI 3 0.931

12

7

55

2

0.927

10

40

10

40

150

97

150

97 150

97 150

97

597

336

403

77 403

77

13002EGBIN 3

0.939

0.950

754

163

0.958

174

195 174

195

875

243

875

243

0.969

311

48

311

48

0.975

433

86

433

86

549

84 549

85

398

39

398

39

13025EPE 3

13000AJA 3

13031OKO_OBA_3

13034LEKKI 330

13027ALAGBON_3

13001AKANGBA 3

714

130

106 122

1

33001KATAMPE 3

0.960

33

4

12

63

34

12

6

1.012

55

6

22

55

6

22

83007ONNIE_3

0.988

13

7

10

01

37

10

0

79

9

83

79

9

83

1

83002ALAOJI 3

0.991 12

4

54

12

4

54

54

59

41

2

53

41

2

53

54

59

1.005

23

4

66

23

4

66

0.991

14 1

13

14 1130.999

22

422

22

422

83010IKOT ABASI_3

1.016 18

8

13

18

8

13

83000AFAM IV 3

83005OWERRI_3

0.964

72

76

26

6

31

26

6

31

0.958

51

6

18

51

6

18

45

8

10

3 4

58

10

3

73004ALIADE_3

63001JOS 3

0.965

20

19

20

19

73010ABAKALIKI_3

0.897

14

7

96

1

63002YOLA 3

0.933

53001KANO 3

0.980

0

480

48

SW

605

0.966

734

167

53005KANO_NEW330

0.923

732

171

53003ZARIA_330

53000KADUNA 3

53002KATSINA 3

0.985

4

0

4

64

4

0 4

64

0.944

25

8

10

52

58

10

5

13032NEW_AGBARA_3

0.925

101

37

1550

181

23000AYEDE 3

0.99743000

AJAOKUTA 3

43002BENIN 3

0.960 83

2

29

43001ALADJA 3

43003DELTA IV 3

0.979

337

134

469

146

469

146

469

146

43004SAPELE 3

43011B_NORTH_3

0.998 64

6

14

3

64

6

14

3

0.933

36

5

15

7

36

5

15

7

43009OBAJANA_3

0.998

19

6

91

19

6

91

83006EGBEMA_3

83009OMOKU_3

83008CALABAR_PS_3

83003ADIAGBO_3

63000GOMBE 3

54

5

62

2

1 2

33020SHIRORO 3

33008WESTMAIN_3

73000NHAVEN 3

0.932

21

8

80

21

8

80

53004FUNTUA 3

0.906

27

58

27

58

53007TMAFARA3

0.923

53008GUSAU 3

144

21 144

21

178

83 178

83

451

91451

91

33021KAINJI 3

0.939106

57

33005KAINJI G .S.3

33003JEBBA T.S.3

468

22

476

13

754

163

32

3

85

32

3

85

241

15

14

7

96

28

5

81

74

12

7

55

0.974

51

121

12

1

19

33009ZUNGERU

33004JEBBA G .S.3

33022APO_NEW 3

0.863

33023LAFIA 3

0.928

52

1

21

5

545

93

66318

66318

322

71 322

71

63003BAUCHI 3 0.972

22

0

29

36

6

13

63008MAMBILA 3

1.020

0.989

35

1

42

35

1

42

1.000

43006EFFURUN 3

490

19

73002OKPAI 3

0.994

0.988

75

0

29

75

0

29

73030IHIALA 3

23006IBADAN

1.000

13026OKE_ARO_3

61

8

21

53012DUTSE 3

0.974

53011KAZAURE 3

0.992

1.000

5 174

597

94

6

18

4

94

6

1

2

0.966

63009WUKARI

53010EN ARFICA PV

0.919

30

0

15

73

00

15

7

83001ALAOJI NIPP3

73007NNEWI 3

0

329

30

338

1

2

1

440

61

440

61

447

89

13004SAKETE 3

63

12

64

48

0.963

0.963

13028ARIGBAJO

174 260260

63006JALINGO_3

73

9

18

4

97

33010ZABORI

0.931

38

1

14

0

375

123

38

1

14

0

375

123750

247

225

62

22

6

52

10

8

22

225

62

226

52

SW

11

05

13012PARAS

0.960

115

69

115

69

249

176

249

176

33011FARAKU

0.904

278

89

275

90278

89

275

90

550

181

43012ZUMA 0.982

79

3

12

9

79

3

12

9

13

13

19

9

13

13

19

9

53013DAURA

0.992

64

40 64

40

329

98329

98

53016JOGANA

0.972

101

74 100 83

414

112

401

162

70

70

70

7039

8

53020MILLENIUM

0.962

4

63

4

67

258

16

26

2

9

63015MAYOBELWA 0.8897

88

99

415

92 415

92

33

83

33

16

33

83

33

16 12

1

19 1

21

27

12

1

19

121

27

490

19

50

3

45

205

120

20

6

11

1

205

120

20

6

11

1

448

234

679

1

659

158

679

1

659

158

61

1

67

43007AZURA

77

4

13

2

745

79

63

12

64

48

43010ETHIOPE

SW

15

80

90001

0.9992622

407

90002

1749

339

614

94614

94

90003

0.944

12

04

35

0

90004

0.873 817

10323181032318

256143

256

143

90005

0.963

39

209

696106696106

90006

0.979

696

1374

60

197 6

0

197

650

8

650 8

90007

0.996

21

12

47

7

97

15

6 97

15

6

92

4

20

8 92

4

20

8

90008

0.906

1448

155

753

195

753

195

43008LOKOJA _3

0.923

0.948

90009

0.939

554

99

36

2

15

23

62

15

2

393

27

393

27

1892

33006SOKOTO 3

322 315

32

1

31

7

0.935

414

30

414

30562

98562

98

23007ADO EKITI 3

0.698

43013OKENE 3

0.869

1027

307

53021AZARE 3

0.972

79

1

79

1

63016GOMBI 3

0.909

381 7

3

381

73

63017BIU 3

0.928

17084

17084

281 111281 111

63018POTISKUM 3

0.967

146

22 146

22

18

6

57

18

6

57

73031KASHIMBILLA3

1.026

73032AYANGBA 3 0.925

83011OGOJA 3

1.027

0

0

83012IKOM 3 1.0160 0

43005GEREGU

448

234

90010_1

0.967

317

139

521

108

521

108 859

319

859

319

13005OLORUNSOGO3

597

336

23010SHAGAMU

0.939

134

67134

67

60

28

528

35

92

13035IJORA 3

90011

0.980

902 212

46

4

71

46

4 71

130

100

1.000

191

31

32021NIAMEY 1

0.868

1

59

2052010

GAZOUA 1

SW

58

1.000

SW

998

12003IKEJA W 1BB1

Export 2000 MW

Total Generation 39916 MWNigeria Load 35598 MW

Genera tion from H PP 4369 MW

Generation per DISCO Loads per DISCO

3-Abuja 7949 MW

4-Benin 7635 MW

9-Eko 1350 MW

7-Enugu 1904 MW

2-Ibadan 1575 MW

1-Ikeja 4125 MW

6-Jos 1745 MW

5-Kaduna 832 MW

10-Kano 1019 MW

8-Pt Harco 10842 MW

11-Yola 2470 MW

Genera tion from PV 990 MW

Total Load 37598 MW

9-Eko 2509 MW

7-Enugu 2114 MW

2-Ibadan 4923 MW

6-Jos 1131 MW

5-Kaduna 3043 MW

10-Kano 4021 MW

8-Pt Harco 3292 MW

11-Yola 1678 MW

1-Ikeja 4295 MW

3-Abuja 5316 MW

4-Benin 3275 MW

250

98

200

101

250

98

250

98

250

98

250

98

250

98

250

98

250

98

250

98

1250

117R

1200

114R

250

117R

1250

117R

250

117R

250

117R

1250

117R

1250

117R

250

117R

1250

117R

12

00

90

0H

96029GWAGWALAD

375

250

125

500

0

MV

A F

low

TCN330kV TRANSMISSINO NETWORK

TCN2040MODEL

Total Generation: 39916 MW

Nigeria Load: 35598 MW

Export: 2000 MW

Total Load: 37598 MW

Generation from PV: 990 MW

Generarion from HPP: 4369 MW

Page 96: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-95

Yola-Little Gombi-Biu-Damaturu

Damaturu-Potiskum-Azare-Dutse-Jogana

The required new transmission lines for 2040 are shown in Table 7-9.3.

Table 7-9.3 New transmission lines and reinforcements required for 2040

Substation Name

Substation Name

Voltage (kV)

Length (km)

Type Proposed Solution

Aladja Delta IV 330 32 SC Convert to DC

Osogbo Ganmo 330 50 SC Convert to DC

Yola Little Gombi 330 100 DC New DC transmission line

Little Gombi Biu 330 80 DC New DC transmission line

Biu Daimaturu 330 130 DC New DC transmission line

Daimaturu Potiscum 330 100 DC New DC transmission line

Potiscum Azare 330 100 DC New DC transmission line

Azare Dutse 330 90 DC New DC transmission line

Dutse Jogana 330 76 DC New DC transmission line

Source: JICA Study Team

7-9-3-2 Reactive Power Compensation

In addition to the requirements described for the 2035 case, reactive power compensation would be required by 2040, considering the following:

Due to the sharp increase in the forecast load in Abuja, there is an additional reactive power deficit in the Abuja area of approx. 1,500 MVar.

Additional reactive power deficit at Kano of approx. 600 MVar

Additional reactive power deficit at Bernin Kebbi of approx. 400 MVar

Additional reactive power deficit at Ikeja West of approx. 200 MVar

It is recommended that more detailed reactive power compensation studies be conducted at a later stage to determine the optimal sizes and locations of the reactive power equipment for 2040.

Page 97: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-96

7-10 Cost Estimation of Transmission Network Development Plan

7-10-1 Basis for Cost Estimation

For calculation of cost of new transmission lines and substations of the proposed transmission system expansions, a simplified cost model has been prepared. For transmission lines it is based on cost per km of transmission line for each voltage level. For substations, the costs for high-voltage feeders have been estimated and comprise two components: one for high-voltage equipment and another for all other substation components (civil works, steel protection & control equipment, auxiliary power supply, etc.). Furthermore, the costs for main power transformers, reactors and capacitors have also been estimated.

For new 132/33 kV substations, the costs for new 33 kV switchgear have been taken into account. If increasing the transformer capacity in existing 132/33 kV substations, it has been assumed that additional 33 kV switchgear will also be installed. Based on this approach, cost estimation accuracy of ±25% can usually be assumed. Table 7-10.1 below shows the cost components considered in the cost estimation, based on experience with similar projects. The cost estimation is compared with TCN’s cost estimations and both agreed that they generally correlate effectively.

Table 7-10.1 Cost components

Unit Costs

Transmission Lines (million US$/km)

132 kV SC Line 0.17

330 kV SC Line 0.22

500 kV SC Line 0.28

750 kV SC Line 0.35

132 kV DC Line 0.26

330 kV DC Line 0.45

132 kV SC Line Reconductoring 0.04

330 kV SC Line Reconductoring 0.08

132 kV DC Line Reconductoring 0.08

330 kV DC Line Reconductoring 0.15

Substations (million US$)

132 kV HV equipment 0.70

330 kV HV equipment 1.00

500 kV HV equipment 1.30

750 kV HV equipment 2.20

132 kV feeder (= 132 kV HV equipment + Other components) 1.60

330 kV feeder (= 330 kV HV equipment + Other components) 1.90

30 MVA Transformer 132/11 kV 0.60

60 MVA Transformer 132/33 kV 0.80

150 MVA Transformer 330/132 kV 1.50

1000 MVA Transformer 750/330 kV 10.00

11 kV Switchgear 0.50

33 kV Switchgear 0.70

30 MVar Shunt Reactor – 33 kV (including 33 kV switchgear) 0.50

75 MVar Shunt Reactor – 330 kV 0.80

25 MVar Shunt Capacitor – 33 kV (including 33 kV switchgear) 0.25

25 MVar Shunt Capacitor – 132 kV 0.30

100 MVar Shunt Capacitor – 330kV 1.00

Other components (Civil Works, Steel, Protection, Station Control, Auxiliary Power Supply, Installation etc.)

0.90

Source: JICA Study Team

Page 98: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-97

The following are needed to enhance the power transmission line:

SC : Installation of Single-Circuit transmission line/Installing a second parallel circuit

DC : Installation of Double-Circuit transmission line

RE(SC) : Reconductoring of Single-Circuit transmission line

RE(DC) : Reconductoring of Double-Circuit transmission line

7-10-2 Transmission Reinforcements Required by 2020

Power system studies have shown that most of the transmission system expansion required by 2025 is needed in northern Nigeria, particularly for the 330-kV system. Under the current transmission system expansion program of TCN and NIPP (see Annexes 7.2a and 7.2b) most of the transmission system expansions have been commissioned in the southern and central parts of Nigeria. Some of the transmission system expansions have already been completed and it is expected that the remainder will be commissioned by 2020 or very soon afterwards.

Based on the results of Chapter 8: Power System Analysis, the costs of additional 330 and 132 kV transmission lines, additional 330/132 kV, 132/33 kV and 132/11 kV transformers as well as additional shunt reactors and shunt capacitors have been estimated.

Although it will be challenging to implement all measures by 2020 as required for over 9 GW power supply of the Nigerian transmission network, a major part of the network expansions is related to the 132-kV network and to additional 330/132 kV and 132/33 kV transformers.

7-10-2-1 Cost estimation of each project

Table 7-10.2 to Table 7-10.8 show the cost estimations for the individual groups of system expansion measures, i.e. transmission lines, transformers and reactive power compensation.

Table 7-10.9 summarizes all additional investments in transmission lines and substations by 2020.

Table 7-10.2 Reinforcements of 132 kV lines overloaded under N-0

Source: JICA Study Team

Rated

VoltageLength

Cost of Alternative 1

(Length × Unit Cost)

Cost of Alternative 2

(Length × Unit Cost)Cost

(kV) (km)Reinforce

ment

Unit Cost

(Million US$/km)

Reinforce

ment

Unit Cost

(Million US$/km)(Million US$) (Million US$) (Million US$)

1 Ibom IPP - Ikot Abasi 132 30 SC 0.17 DC 0.26 5.1 7.8

5.1 7.8

1 Ibom IPP 0 1 0 0 0 1.6

2 Ikot Abasi 0 1 0 0 0 1.6

3.2

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Subtotal II

Alternative 1 Alternative 2

Subtotal I

Grand Total (Alternative 1)

Grand Total (Alternative 2)

330 kV

Feeder

132 kV

Feeder

Cost Estimation of Reinforcement of 132 kV Transmission Lines overloaded under N-0 by 2020

8.3

14.2

Transmission Line Substation

Substations

Overhead Lines

No. Project

Page 99: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-98

Table 7-10.3 Reinforcements of 132 kV transmission lines overloaded under N-1

Source: JICA Study Team

Table 7-10.4 Upgrading requirements of 330/132 kV 3-winding transformers overloaded under N-0

Source: JICA Study Team

Table 7-10.5 Upgrading requirements of 132/33 kV and 132/11 kV transformers under N-0 by 2020

Source: JICA Study Team

Rated

VoltageLength

Cost of Alternative 1

(Length × Unit Cost)

Cost of Alternative 2

(Length × Unit Cost)Cost

(kV) (km)Reinforce

ment

Unit Cost

(Million US$/km)

Reinforce

ment

Unit Cost

(Million US$/km)(Million US$) (Million US$) (Million US$)

1 Gombe - T-Junction 132 40 SC 0.17 DC 0.26 6.8 10.4

2 Yola - T-Junction 132 56 SC 0.17 DC 0.26 9.5 14.6

3 Omoku - Rumusoi 132 20 RE 0.08 DC 0.26 1.6 5.2

4 PHCT Main - Rumusoi 132 10 RE 0.08 DC 0.26 0.8 2.6

5 Ajaokuta - Okene 132 60 SC 0.17 DC 0.26 10.2 15.6

6 Benin - Irrua 132 88 SC 0.17 DC 0.26 15.0 22.9

7 Mando - Kudenda 132 20 RE 0.08 DC 0.26 1.6 5.2

8 Osogbo - Iwo 132 80 SC 0.17 DC 0.26 13.6 20.8

9 Yenagoa - Gbarain 132 5 RE 0.08 DC 0.26 0.4 1.3

10 Afam 1-2-3 - Afam IV 132 1 RE 0.08 DC 0.26 0.1 0.3

11 Ikeja West - Alimoso 132 4 RE 0.08 DC 0.26 0.3 0.9

12 Biu - Dadinkowa 132 82 SC 0.17 DC 0.26 13.9 21.3

13 Yenagoa - Ahoada 132 46 RE 0.08 DC 0.26 3.7 12.0

14 Ayede - Idaban North 132 12 SC 0.17 DC 0.26 2.0 3.1

15 Eket - Ibom IPP 132 45 RE 0.08 DC 0.26 3.6 11.7

16 Onne - Tramadi 132 10 RE 0.08 DC 0.26 0.8 2.6

17 PHCT Main - Rivers IPP 132 12 RE 0.08 DC 0.26 1.0 3.1

18 Zaria - Funtua 132 7 SC 0.17 DC 0.26 1.2 1.8

86.1 155.4

1 Ajaokuta 0 1 0 0 0 1.6

2 Okene 0 1 0 0 0 1.6

3 Yenagoa 0 0 0 0 0 0.0

4 Gbarain 0 0 0 0 0 0.0

5 Osogbo 0 1 0 0 0 1.6

6 Iwo 0 1 0 0 0 1.6

7 Biu 0 1 0 0 0 1.6

8 Dadinkowa 0 1 0 0 0 1.6

9 Benin 0 1 0 0 0 1.6

10 Irrua 0 1 0 0 0 1.6

11 Ikeja West 0 0 0 0 0 0.0

12 Alimosho 0 0 0 0 0 0.0

13 Mando 0 0 0 0 0 0.0

14 Kudenda 0 0 0 0 0 0.0

15 PHCT Main 0 0 0 0 0 0.0

16 Rumusoi 0 0 0 0 0 0.0

17 Eket 0 0 0 0 0 0.0

18 Zaria 0 1 0 0 0 1.6

19 Funtua 0 1 0 0 0 1.6

20 Onne 0 1 0 0 0 1.6

21 Tramadi 0 0 0 0 0 0.0

17.6

Cost Estimation of Reinforcement of 132 kVTransmission Lines overloaded under N-1 by 2020

Alternative 1 Alternative 2 330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Subtotal I

103.7

Transmission Line Substation

Overhead Lines

Substations

Subtotal II

Grand Total - Alternative 1

No. Project

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Benin 2 2 0 2 0 10.0

2 Benin North 1 1 0 1 0 5.0

3 Birnin Kebbi 1 1 0 1 0 5.0

4 Ganmo 1 1 0 1 0 5.0

25.0

Cost Estimation of Upgrading of 330/132 kV 3-winding Transformers overloaded under N-1 by 2020

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Subtotal I

Subtotal II

25.0

Transmission Line Substation

Overhead Lines

Substations

Grand Total

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Suleja 0 1 0 1 0 0 1 2.7

2 Benin 0 3 3 0 0 3 0 9.3

3 Benin North 0 1 1 0 0 1 0 3.1

4 Kano 0 1 1 0 0 1 0 3.1

5 Funtua 0 1 1 0 0 1 0 3.1

6 Funtua 0 1 0 1 0 0 1 2.7

7 Ojo 0 1 1 0 0 1 0 3.1

8 Omuaran 0 1 1 0 0 1 0 3.1

30.2

Cost Estimation of Upgrading of Transformers overloaded under N-0 by 2020

330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

11kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

30 MVA、

132/11 kV

Transformer

Subtotal I

30.2

Transmission Line Substation

Overhead Lines

Substations

No. Project

Subtotal II

Grand Total

Page 100: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-99

Table 7-10.6 Upgrading requirements of 330/132 kV, 132/33 kV and 132/11 kV transformers loaded

above 85% under N-0 by 2020

Source: JICA Study Team

Table 7-10.7 New reactors and capacitors

Source: JICA Study Team

Table 7-10.8 New transmission lines required by 2020

Source: JICA Study Team Note: The 330 kV lines which are part of the North-East Ring and North-West Ring, are considered in the cost estimation for 2025

because implementation by 2020 is not possible.

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Kano 1 1 0 0 1 0 0 5.0

2 Benin North 1 1 0 0 1 0 0 5.0

3 Odogunyan 0 1 1 0 0 1 0 3.1

4 Ganmo 0 1 1 0 0 1 0 3.1

5 Ejigbo 0 1 1 0 0 1 0 3.1

6 Ojo 0 1 1 0 0 1 0 3.1

7 Alimosho 0 1 1 0 0 1 0 3.1

8 Ughelli 0 1 1 0 0 1 0 3.1

9 Paras 0 1 1 0 0 1 0 3.1

10 Shagamu 0 1 1 0 0 1 0 3.1

11 Afam 1-2-3 0 1 0 1 0 0 1 2.7

12 Iwo 0 1 1 0 0 1 0 3.1

13 Shiroro 0 1 1 0 0 1 0 3.1

43.7Subtotal II

Grand Total

Cost Estimation of Upgrading of Transformers loded about 85% under N-0 by 2020

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

11kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

30 MVA、

132/11 kV

Transformer

43.7

Transmission Line Substation

Overhead Lines

Substations

Subtotal I

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Maiduguri 1 0 0 0 0 1 0 2.7

2 Ondo2 0 1 0 0 1 0 0 1.9

3 Irrua 0 1 0 0 1 0 0 1.9

4 Gusau 0 1 0 0 1 0 0 1.9

8.4

33 kV

Switchgear

11kV

Switchgear

8.4

Substations

Cost Estimation of New Reactors and Capacitors required by 2020

Subtotal I

Subtotal II

Grand Total

132 kV

Capacitor

330 kV

Reactor

32 kV

Reactor

Overhead Lines

Transmission Line Substation

No. Project330 kV

Feeder

132 kV

Feeder

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Kaduna - Kano 330 230 0.45 103.5

2 Akangba - Ijora 330 14 0.45 6.3

3 Ijora - Alagbon 330 8 0.45 3.6

4 Arigbso - New Agbara 330 40 0.45 18.0

5 Ugwaji - Abakaliki 330 85 0.45 38.3

6 Osogbo - Arigbajo 330 183 0.45 82.4

7 Ayede - Idaban North 132 15 0.26 3.9

8 New Agbara - Agbara 132 18 0.26 4.7

9 Ogijo - Redeem 132 14 0.26 3.6

10 Birmin Kebbi - Dosso 132 128 0.26 33.3

Subtotal I 297.5

1 Kaduna 4 2 1 2 2 16.1

2 Kano 2 1 1 1 1 8.4

3 Akangba 4 2 1 2 2 16.1

4 Ijora 4 2 1 2 2 16.1

5 Arigbajo 12 2 1 2 2 31.3

6 Agbara 0 2 1 0 1 4.7

7 New Agbara 4 2 1 2 2 16.1

8 Ugwaji 2 0 0 0 0 3.8

9 Abakaliki 2 0 0 0 0 3.8

10 Osogbo 0 2 0 0 0 3.2

11 Ayede 0 2 0 0 0 3.2

12 Ibadan North 0 2 0 0 0 3.2

13 Ogijo 0 2 0 0 0 3.2

14 Redeem 0 4 1 0 2 8.7

15 Dosso 0 2 0 0 0 3.2

16 Ibom IPP 0 2 0 0 0 3.2

17 Ikot Abasi 0 2 0 0 0 3.2

Subtotal II 147.5

Grand Total

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Cost Estimation of New 132 kV Transmission Lines required by 2020

445.0

Transmission Line Substation

New Substations / Extension of Substations

Overhead Lines

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

Page 101: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-100

7-10-2-2 Summary of Additional Investments by 2020

Table 7-10.9 shows a summary of all additional investments in transmission lines and substations by 2020. The 330 kV North-East Ring and the 330-kV line Kainji - Birnin-Kebbi are also necessary to supply the forecast load of over 9 GW. However, considering the necessary implementation time, these lines are more likely to be available between 2020 and 2025. Accordingly, these costs are included in the 2025 investment costs.

Table 7-10.9 Summary of additional investments by 2020

Source: JICA Study Team

7-10-3 Transmission Reinforcements Required by 2025

To allow power transmission of approximately 20 GW by 2025, it will be necessary to build numerous new 330 and 132 kV transmission lines, to increase the transmission capacity of existing 132 kV transmission lines by reconductoring existing lines and installing additional 330/132 kV and 132/33(11) kV transformers.

7-10-3-1 Cost Estimation of Each Project

The cost estimate for additional 132 kV lines, 330/132 kV transformers and 132/33 (11) kV transformers is shown in Table 7-10.10 to Table 7-10.19.

Table 7-10.10 Additional Lines by 2025 - North-West Ring

Source: JICA Study Team

Reinforcements of 132 kV lines overloaded under N-0 5.1 3.2 8.3

Reinforcements of 132 kV lines overloaded under N-1 86.1 17.6 103.7

Upgrading requirements of 330/132 kV 3-winding transformers overloaded under N-0 0.0 25.0 25.0

Upgrading requirements of 132/33 kV and 132/11 kV transformers overloaded under N-0 0.0 30.2 30.2

Upgrading requirements of 330/132 kV, 132/33 kV and 132/11 kV transformers overloaded

loaded over 85% under N-00 43.7 43.7

New Reactor and Capacitors 0 8.4 8.4

New Transmission Lines by 2020 297.5 147.5 445.0

Total Additional Investment Cost by 2020 664.3

Total Cost required by 2020

Transmission System ExpansionsTransmission

Line

Substation

(Million US$)

Total Cost

(Million US$)

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Kainji - Birnin Kebbi 330 kV DC Line 330 310 0.45 139.5

2 Birnin Kebbi - Sokoto 330 kV DC Line 330 130 0.45 58.5

3 Sokoto - Talata Mafara 330 kV DC Line 330 125 0.45 56.3

4 Talata Mafara - Gusau 330 kV DC Line 330 85 0.45 38.3

5 Gusau - Funtua 330 kV DC Line 330 70 0.45 31.5

6 Funtua - Zaria 330 kV DC Line 330 70 0.45 31.5

355.5

1 Kainji 2 0 0 0 0 3.8

2 Birnin Kebbi 7 1 1 1 1 17.9

3 Sokoto 7 9 1 2 1 32.2

4 Talata Mafara 7 9 1 2 1 32.2

5 Gusau 7 9 1 2 1 32.2

6 Funtua 7 9 1 2 1 32.2

7 Zaria 4 2 1 2 1 15.3

165.8

Cost Estimation of Additional Transmission Lines required by 2025 (330 kV North West Ring)

Subtotal I

Subtotal II

Transmission Line Substation

Overhead Lines

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

521.3

Substations

Grand Total

Page 102: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-101

Table 7-10.11 Additional Lines by 2025 - North-East Ring

Source: JICA Study Team

Table 7-10.12 Additional Lines by 2025 - Mambilla Network Connection

Source: JICA Study Team

Table 7-10.13 Other Additional Lines by 2025 (1)

Source: JICA Study Team

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Jos - Gombe 330 kV DC Line 330 270 0.45 121.5

2 Gombe - Damaturu 330 kV DC Line 330 180 0.45 81.0

3 Damaturu - Maiduguri 330 kV DC Line 330 260 0.45 117.0

4 Gombe - Yola 330 kV DC Line 330 240 0.45 108.0

5 Yola - Jalingo 330 kV DC Line 330 160 0.45 72.0

499.5

1 Jos 2 0 0 0 0 3.8

2 Gombe 9 7 1 2 2 33.6

3 Damaturu 7 7 1 2 2 29.8

4 Maiduguri 5 5 1 2 2 22.8

5 Yola 7 7 1 2 2 29.8

6 Jailingo 7 9 1 2 1 32.2

152.0

Cost Estimation of Additional Transmission Lines required by 2025 (330 kV North East Ring)

60 MVA、

132/33 kV

Transformer

150 MVA、

330/132kV

Transformer

33 kV

Switchgear

132 kV

Feeder

330 kV

Feeder

Transmission Line Substation

Overhead Lines

Substations

No. Project

Subtotal I

Subtotal II

Grand Total 651.5

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Mambilla - Wukari 330 kV DC Line 330 159 0.45 71.6

2 Mambilla - Jailingo 330 95 0.45 42.8

3 Wukari - Makurdi 330 159 0.45 71.6

4 Wukari - Lafia 330 95 0.45 42.8

228.6

1 Mambilla 2 0 0 0 0 3.8

2 Wukari 5 5 0 2 2 22.1

3 Makurdi 2 0 0 0 0 3.8

4 Lafia 2 0 0 0 0 3.8

5 Jalingo 2 0 0 0 0 3.8

37.3

Cost Estimation of Additional Transmission Lines required by 2025 (330 kV Mambilla Network Con-nections)Transmission Line Substation

Overhead Lines

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Subtotal I

Substations

265.9

Subtotal II

Grand Total

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Arigbajo - Ayede Loop-in at Ayede 330 1 0.22 0.2

2 Katsina - Daura 330 40 0.45 18.0

3 Daura - Kazaure 330 25 0.45 11.3

4 Shiroro - Kaduna 330 96 0.45 43.2

5 Gwangwalada - Shiroro 132 145 0.26 37.7

6 Benin North - Omotosho 330 110 0.45 49.5

7 Zungeru - Kainji 330 200 0.45 90.0

8 Zungeru - Shiroro 330 25 0.45 11.3

261.1

1 Ayede 2 0 0 0 0 3.8

2 Katsina 2 0 0 0 0 3.8

3 Daura 4 0 0 0 0 7.6

4 Kazaure 2 0 0 0 0 3.8

5 Shiroro 6 0 0 0 0 11.4

6 Kaduna 2 0 0 0 0 3.8

7 Gwangwalada 2 0 0 0 0 3.8

8 Benin North 2 0 0 0 0 3.8

9 Omotosho 2 0 0 0 0 3.8

10 Zungeru 4 0 0 0 0 7.6

11 Kainji 2 0 0 0 0 3.8

57.0

Cost Estimation of Transmission Lines required by 2025 (Others 1)

Subtotal I

Subtotal II

318.1

Substations

Transmission Line Substation

Overhead Lines

Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

No.

Grand Total

Page 103: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-102

Table 7-10.14 Other Additional Lines by 2025 (2)

Source: JICA Study Team

Table 7-10.15 First transmission lines of the Supergrid by 2025

Source: JICA Study Team

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Shiroro - Tegina 132 65 0.26 16.9

2 Tegina - Kontagora 132 90 0.26 23.4

3 Kontagora - Yelwa-Yauri 132 88 0.26 22.9

4 Ganmo - Ilorin 132 10.5 0.26 2.7

5 Obajana - Egbe 132 97 0.26 25.2

6 Omotosho - Ondo 132 98 0.26 25.5

7 Benin - Irrua 132 88 0.26 22.9

8 Irrua - Ukpilla 132 43 0.26 11.2

9 Ukpilla - Okene 132 33 0.26 8.6

10 Shamagu - Ijebu Ode 132 41 0.26 10.7

11 Dakata - Gagarawa 132 89 0.26 23.1

12 Gagarawa - Hadejia 132 60 0.26 15.6

13 Dakata - Kumbotso 132 30 0.26 7.8

14 Obajana - Okene 132 97 0.26 25.2

15 Kainji - Iseyin 132 200 0.26 52.0

293.7

1 Shiroro 0 2 0 0 0 3.2

2 Tegina 0 2 0 0 0 3.2

3 Kontagora 0 2 0 0 0 3.2

4 Yelwa-Yauri 0 2 0 0 0 3.2

5 Ganmo 0 2 0 0 0 3.2

6 Ilorin 0 2 0 0 0 3.2

7 Obajana 0 2 0 0 0 3.2

8 Egbe 0 2 0 0 0 3.2

9 Omotosho 0 2 0 0 0 3.2

10 Ondo 0 2 0 0 0 3.2

11 Benin 0 2 0 0 0 3.2

12 Ukpilla 0 2 0 0 0 3.2

13 Shamagu 0 2 0 0 0 3.2

14 Ijebu Ode 0 2 0 0 0 3.2

15 Dakata 0 2 0 0 0 3.2

16 Gagarawa 0 2 0 0 0 3.2

17 Hadejia 0 2 0 0 0 3.2

18 Dakata 0 2 0 0 0 3.2

19 Kumbotso 0 2 0 0 0 3.2

20 Birmin Kebbi 0 2 0 0 0 3.2

21 Dosso 0 2 0 0 0 3.2

67.2

Cost Estimation of Transmission Lines required by 2025 (Others 2)

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Transmission Line Substation

No. Project330 kV

Feeder

Subtotal II

Grand Total 360.9

Subtotal I

Overhead Lines

Substations

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Ikot-Ekpene - Makurdi 330 320 0.45 144.0

2 Makurdi - Gwangwalada 330 180 0.45 81.0

3 Ajaokuta - Gwangwalada 330 150 0.45 67.5

4 Osogbo - Gwangwalada 330 250 0.45 112.5

5 Gwangwalada - Funtua 330 250 0.45 112.5

517.5

1 Ikot-Ekpene 2 2 0 2 0 10.0

2 Markurdi 2 2 0 2 0 10.0

3 Ajaokuta 2 2 0 2 0 10.0

4 Gwangwalada 8 2 0 2 0 21.4

5 Osogbo 2 2 0 2 0 10.0

6 Funtua 2 2 0 2 0 10.0

71.4

Cost Estimation of Transmission Lines for Supergrid required by 2025

Subtotal I

Subtotal II

Grand Total

Transmission Line Substation

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

588.9

Substations

Overhead Lines

Page 104: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-103

Table 7-10.16 Reconductoring of 132 kV lines by 2025

Source: JICA Study Team

Table 7-10.17 Upgrading requirements of 330/132kV transformers

Source: JICA Study Team

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Egbin - Ikorodu 132 20 0.08 1.6

2 Ogijo - Shagamu 132 16 0.08 1.3

3 Ayede - Idaban North 132 12 0.04 0.5

4 Ayede - Jericho 132 6 0.08 0.5

5 Alaoji - Aba 132 10 0.08 0.8

6 Eket - Ibom IPP 132 45 0.08 3.6

7 PHCT Main - PHCT Town 132 6 0.04 0.2

8.5

0.0

Cost Estimation of Reconductoring of 132 kV Transmission Lines required by 2025

Subtotal I

Subtotal II

Grand Total 8.5

Substations

Transmission Line Substation

Overhead Lines

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Adiagbo 2 2 0 2 0 10.0

2 Aja 2 2 0 2 0 10.0

3 Ajaokuta 2 2 0 2 0 10.0

4 Akangba 2 2 0 2 0 10.0

5 Akoka 2 2 0 2 0 10.0

6 Akure 2 2 0 2 0 10.0

7 Apapa 2 2 0 2 0 10.0

8 Ayede 2 2 0 2 0 10.0

9 Delta 2 2 0 2 0 10.0

10 Ganmo 2 2 0 2 0 10.0

11 Ihala 2 2 0 2 0 10.0

12 Ikeja West 2 2 0 2 0 10.0

13 Isolo 2 2 0 2 0 10.0

14 Jericho 2 2 0 2 0 10.0

15 Kano 2 2 0 2 0 10.0

16 Kumbotoso 2 2 0 2 0 10.0

17 Nnewi 2 2 0 2 0 10.0

18 Omotosho 2 2 0 2 0 10.0

19 Onitsha 2 2 0 2 0 10.0

20 Osogbo 2 2 0 2 0 10.0

21 Oweri 2 2 0 2 0 10.0

22 West Main 2 2 0 2 0 10.0

210.0

Cost Estimation of Upgrading of 330/132 kV 3-winding Transformers required by 2025

Subtotal I

Subtotal II

Transmission Line Substation

Overhead Lines

Substations

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

210.0Grand Total

Page 105: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-104

Table 7-10.18 Upgrading requirements of 132/33(11) kV transformers

Source: JICA Study Team

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Aba 0 2 2 0 0 2 0 6.2

2 Abakaliki 0 2 2 0 0 2 0 6.2

3 Afam 1-2-3 0 2 0 2 0 0 2 5.4

4 Ahoada 0 2 2 0 0 2 0 6.2

5 Ajaokuta 0 2 2 0 0 2 0 6.2

6 Akangba 0 2 2 0 0 2 0 6.2

7 Akoka 0 2 2 0 0 2 0 6.2

8 Akure 0 2 2 0 0 2 0 6.2

9 Alagbon 0 2 2 0 0 2 0 6.2

10 Alimosho 0 2 2 0 0 2 0 6.2

11 Amukpe 0 2 2 0 0 2 0 6.2

12 Arigbajo 0 2 2 0 0 2 0 6.2

13 Ayede 0 2 2 0 0 2 0 6.2

14 Benin 0 2 2 0 0 2 0 6.2

15 Dan Agundi 0 2 2 0 0 2 0 6.2

16 Egbin 0 2 2 0 0 2 0 6.2

17 Ejigbo 0 2 2 0 0 2 0 6.2

18 Eket 0 2 2 0 0 2 0 6.2

19 Elelenwo 0 2 2 0 0 2 0 6.2

20 Ganmo 0 2 2 0 0 2 0 6.2

21 Gashuwa 0 2 2 0 0 2 0 6.2

22 Gusau 0 2 2 0 0 2 0 6.2

23 Idaban North 0 2 2 0 0 2 0 6.2

24 Ijebu Ode 0 2 2 0 0 2 0 6.2

25 Ijora 0 2 2 0 0 2 0 6.2

26 Ikordu 0 2 2 0 0 2 0 6.2

27 Ikot Abasi 0 2 2 0 0 2 0 6.2

28 Ilesha 0 2 2 0 0 2 0 6.2

29 Illupeju 0 2 0 2 0 0 2 5.4

30 Irrua 0 2 2 0 0 2 0 6.2

31 Iseyin 0 2 2 0 0 2 0 6.2

32 Isolo 0 2 2 0 0 2 0 6.2

33 Itire 0 2 0 2 0 0 2 5.4

34 Iwo 0 2 2 0 0 2 0 6.2

35 Jalingo 0 2 2 0 0 2 0 6.2

36 Jos 0 2 2 0 0 2 0 6.2

37 Kaduna Town 0 2 2 0 0 2 0 6.2

38 Kafanchan 0 2 2 0 0 2 0 6.2

39 Kano 0 2 2 0 0 2 0 6.2

40 Katsina 0 2 2 0 0 2 0 6.2

41 Kazaure 0 2 2 0 0 2 0 6.2

42 Makeri 0 2 2 0 0 2 0 6.2

43 New Haven 0 2 2 0 0 2 0 6.2

44 Nkalagu 0 2 2 0 0 2 0 6.2

45 Odogunyan 0 2 2 0 0 2 0 6.2

46 Ogba 0 2 0 2 0 0 2 5.4

47 Ojo 0 2 2 0 0 2 0 6.2

48 Ondo2 0 2 2 0 0 2 0 6.2

49 Onitsha 0 2 2 0 0 2 0 6.2

50 Osogbo 0 2 2 0 0 2 0 6.2

51 Otta 0 2 2 0 0 2 0 6.2

52 Oweri 0 2 2 0 0 2 0 6.2

53 Oworosoki 0 2 2 0 0 2 0 6.2

54 Paras 0 2 2 0 0 2 0 6.2

55 PHCT Town 0 2 0 2 0 0 2 5.4

56 Rumusoi 0 2 2 0 0 2 0 6.2

57 Savannah 0 2 2 0 0 2 0 6.2

58 Shagamu 0 2 2 0 0 2 0 6.2

59 Shagamu Cement 0 2 0 2 0 0 2 5.4

60 Shiroro 0 2 2 0 0 2 0 6.2

61 Suleja 0 2 2 0 0 2 0 6.2

62 Tegina 0 2 2 0 0 2 0 6.2

63 Ughelli 0 2 2 0 0 2 0 6.2

64 Umuahia 0 2 2 0 0 2 0 6.2

65 Uyo 0 2 2 0 0 2 0 6.2

398.2

Grand Total

30 MVA、

132/11 kV

Transformer

Cost Estimation of Upgrading of 132/33, 132/11 kV Transformers required by 2025

Subtotal I

Subtotal II

132 kV

Feeder

33 kV

Switchgear

11kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

398.2

Transmission Line Substation

Substations

Overhead Lines

No. Project330 kV

Feeder

Page 106: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-105

Table 7-10.19 New reactors and capacitors by 2025

Source: JICA Study Team

7-10-3-2 Summary of Additional Investments between 2021 and 2025

Table 7-10.20 shows a summary of all additional investments in transmission lines and substations between 2021 and 2025.

Table 7-10.20 Summary of additional investments in transmission lines and

substations between 2021 and 2025

Source: JICA Study Team

7-10-4 Transmission Reinforcements Required by 2030

A further extension of the 330 kV Supergrid will be required by 2030. Furthermore, there will be a need to install capacitor banks at various substations to maintain voltages within permissible limits.

7-10-4-1 Cost Estimation of Each Project

The cost estimate for the additional transmission lines, transformers and capacitor banks is shown in Table 7-10.21 and 7-10.22.

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Iseyin 0 0 0 0 0 0 2 0 0.50

2 Irrua 0 0 0 0 0 0 1 0 0.25

3 Keffi 0 1 0 0 1 0 0 0 1.90

4 Omuaran 0 2 0 0 2 0 0 0 3.80

5 Hadejia 0 2 0 0 2 0 0 0 3.80

6 Apo 0 2 0 0 2 0 0 0 3.80

7 Sulejia 0 2 0 0 2 0 0 0 3.80

8 Uyo 0 4 0 0 4 0 0 0 7.60

9 Ondo 0 1 0 0 1 0 0 0 1.90

27.35

Cost Estimation of New Reactors and Capacitors required by 2025

Subtotal I

Subtotal II

11 kV

Switchgear132 kV

Capacitor

132 kV

Reactor

33 kV

Capacitor

33 kV

Reactor

Transmission Line Substation

Substations

Overhead Lines

27.35Grand Total

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

Project 1: 330 kV North West Ring by 2025 355.5 165.8 521.3

Project 2: 330 kV North East Ring by 2025 499.5 152.0 651.5

Project 3: 330 kV Mambilla Network Connections by 2025 228.6 37.3 265.9

Additional Transmission Lines by 2025 - Part 1 261.1 57.0 318.1

Additional Transmission Lines by 2025 - Part 2 293.7 67.2 360.9

First Transmission Lines of the Supergrid by 2025 517.5 71.4 588.9

Reconductoring of 132 kV Lines 8.5 0.0 8.5

Additional 330/132 kV Transformers by 2025 0.0 210.0 210.0

Additional 132/33 and 132/11 kV Transformers 0.0 398.2 398.2

New Reactive Power Compensation 0.0 27.4 27.4

Costs for converting 330 kV DC lines to quad conductors 10.0 0.0 10.0

Total Additional Investment Cost by 2025 3,360.7

Total Cost required from 2021 to 2025

Transmission System ExpansionsTransmission Line

(Million US$)

Substation

(Million US$)

Total Cost

(Million US$)

Page 107: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-106

Table 7-10.21 Additional investments in 330 kV Supergrid transmission lines and substations by 2030

Source: JICA Study Team

Table 7-10.22 Additional Capacitor Banks to be installed by 2030

Source: JICA Study Team

7-10-5 Transmission Reinforcements Required by 2035

Table 7-10.23 Additional investments in transmission lines and substations by 2035

Source: JICA Study Team

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Ikot Ekpene - Benin 330 300 0.45 135.0

2 Benin - Egbin 330 230 0.45 103.5

3 Egbin - New Agbara 330 50 0.45 22.5

4 Benin - Osogbo 330 200 0.45 90.0

5 Osogbo - Kainji 330 200 0.45 90.0

6 Benin - Ajeokuta 330 150 0.45 67.5

7 Gangwalada - Kainji 330 250 0.45 112.5

8 Kainji - Bernin Kebbi 330 300 0.45 135.0

9 New Agbara - Osogbo 330 150 0.45 67.5

823.5

1 Ikot Ekpene 2 0 0 0 0 3.8

2 Benin 6 5 0 0 0 19.4

3 Egbin 4 0 0 0 0 7.6

4 New Agbara 4 0 0 0 0 7.6

5 Osogbo 6 0 0 0 0 11.4

6 Ajaokuta 2 0 0 0 0 3.8

7 Gangwalada 2 0 0 0 0 3.8

8 Kainji 4 0 0 0 0 7.6

9 Bernin Kebbi 2 0 0 0 0 3.8

68.8

Subtotal I

Subtotal II

Grand Total

Cost Estimation of Additional 330 kV Supergrid Transmission Lines and Substations required by 2030

892.3

Transmission Line Substation

Overhead Lines

Substations

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Gombe 0 4 0 0 4 0 0 0 7.6

2 Bernin Kebbi 0 3 0 0 6 0 0 0 6.6

3 Gashuwa 0 1 0 0 1 0 0 0 1.9

4 Apo 0 2 0 0 2 0 0 0 3.8

5 Keffi 0 1 0 0 1 0 0 0 1.9

6 Uba 0 2 0 0 2 0 0 0 3.8

25.6

Cost Estimation of New Reactors and Capacitors required by 2030

Subtotal I

Transmission Line Substation

Overhead Lines

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

11 kV

Switchgear132 kV

Capacitor

132 kV

Reactor

33 kV

Capacitor

33 kV

Reactor

25.6

Subtotal II

Grand Total

Substations

Rated

VoltageLength Cost of Alternative 1 Cost of Alternative 2 Cost

(kV) (km)Reinforce

ment

Unit Cost

(Million US$/km)

Reinforce

ment

Unit Cost

(Million US$/km)(Million US$) (Million US$) (Million US$)

1 Wukari - Lafia 330 95 DC 0.45 DC 0.45 42.8 42.8

2 Zuma - Lokoja 330 25 RE 0.15 DC 0.45 3.8 11.3

3 Aja - Lekki 330 7 RE 0.15 DC 0.45 1.1 3.2

4 Benin North - Akure 330 130 RE 0.08 DC 0.45 10.4 58.5

5 Kwaya Kusar - Biu 132 42 SC 0.17 DC 0.26 7.1 10.9

6 Biu - Damboa 132 140 SC 0.17 DC 0.26 23.8 36.4

7 Damboa - Maiduguri 132 64 SC 0.17 DC 0.26 10.9 16.6

99.8 179.6

1 Wukari 2 0 0 0 0 3.8

2 Lafia 2 0 0 0 0 3.8

3 Zuma 0 0 0 0 0 0.0

4 Lokoja 0 0 0 0 0 0.0

5 Aja 0 0 0 0 0 0.0

6 Lekki 0 0 0 0 0 0.0

7 Benin North 0 0 0 0 0 0.0

8 Akure 0 0 0 0 0 0.0

9 Kwaya Kusar 0 1 0 0 0 1.6

10 Biu 0 2 0 0 0 3.2

11 Damboa 0 2 0 0 0 3.2

12 Maiduguri 0 1 0 0 0 1.6

17.2

117.0

60 MVA、

132/33 kV

Transformer

Cost Estimation of New Transmission Line required by 2035

Subtotal I

Subtotal II

Transmission Line Substation

Overhead Lines

Substations

Alternative 1 Alternative 2No. Project

330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

150 MVA、

330/132kV

Transformer

Grand Total - Alternative 1

Page 108: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-107

Table 7-10.24 Additional Capacitor Banks to be installed by 2035

Source: JICA Study Team

7-10-6 Transmission Reinforcements Required by 2040

Table 7-10.25 Additional investments in transmission lines and substations by 2035

Source: JICA Study Team

Table 7-10.26 Additional Capacitor Banks to be installed by 2040

Source: JICA Study Team

7-10-7 Summary of Cost Comparison for Three Voltage Levels

This Section compares the cost of a super grid based on 330 kV (presently the highest voltage) with the costs of a super grid based on 500 and 750 kV nominal voltages (respectively 550- and 800 kV-rated voltages).

In the case of a 330-kV super grid, it is assumed that the transmission line will be Double-Circuit lines with Quad Bison conductors.

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Gombe 3 0 0 0 1 3 0 0 0 7.6

2 Bernin Kebbi 7 0 0 0 1 7 0 0 0 16.4

3 Ikeja West 0 12 0 0 1 12 0 0 0 23.8

47.8

Cost Estimation of New Reactors and Capacitors required by 2035

Subtotal I

Subtotal II

Grand Total

132 kV

Capacitor

132 kV

Reactor

33 kV

Capacitor

33 kV

Reactor

Transmission Line Substation

Overhead Lines

Substations

No. Project330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

11 kV

Switchgear

330 kV

Capacitor

47.8

Rated

VoltageLength

Cost of

Alternative 1

Cost of

Alternative 2Cost

(kV) (km) ReinforcementUnit Cost

(Million US$/km)

Reinforce

ment

Unit Cost

(Million US$/km)(Million US$) (Million US$) (Million US$)

1 Aladja - Delta IV 330 32 SC 0.22 DC 0.45 7.0 14.4

2 Osogbo - Ganmo 330 50 SC 0.22 DC 0.45 11.0 22.5

3 Yola - Little Gombe 330 100 DC 0.45 DC 0.45 45.0 45.0

4 Little Gombi - Biu 330 80 DC 0.45 DC 0.45 36.0 36.0

5 Biu - Daimaturu 330 130 DC 0.45 DC 0.45 58.5 58.5

6 Daimaturu - Potiscum 330 100 DC 0.45 DC 0.45 45.0 45.0

7 Potiscum - Azare 330 100 DC 0.45 DC 0.45 45.0 45.0

8 Azare - Dutse 330 90 DC 0.45 DC 0.45 40.5 40.5

9 Dutse - Jogana 330 76 DC 0.45 DC 0.45 34.2 34.2

322.2 341.1

1 Aladja 2 0 0 0 0 3.8

2 Osogbo 2 0 0 0 0 3.8

3 Ganmo 2 0 0 0 0 3.8

4 Little Gombi 4 0 0 0 0 7.6

5 Biu 4 0 0 0 0 7.6

6 Daimaturu 4 0 0 0 0 7.6

7 Potiscum 4 0 0 0 0 7.6

8 Azare 4 0 0 0 0 7.6

9 Dutse 4 1 0 0 0 9.2

10 Jogana 2 2 0 0 0 7.0

65.6

Grand Total - Alternative 1

Cost Estimation of New Transmission Lines required by 2040

150 MVA、

330/132kV

Transformer

60 MVA、

132/33 kV

Transformer

Subtotal I

Subtotal II

387.8

Transmission Line Substation

Overhead Lines

Substations

Alternative 1 Alternative 2No. Project

330 kV

Feeder

132 kV

Feeder

33 kV

Switchgear

Rated

VoltageLength Unit Cost Cost Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

0.0

1 Abuja 15 0 0 0 15 0 0 0 0 43.5

2 Kano 6 0 0 0 6 0 0 0 0 17.4

3 Bernin Kebbi 4 0 0 0 4 0 0 0 0 11.6

4 Ikeja West 2 0 0 0 2 0 0 0 0 5.8

78.3

Cost Estimation of New Reactors and Capacitors required by 2040

Subtotal I

Subtotal II

Grand Total

132 kV

Capacitor

330 kV

Capacitor

11 kV

Switchgear

33 kV

Switchgear

132 kV

Feeder

78.3

Transmission Line Substation

Overhead Lines

Substations

No. Project33 kV

Reactor

33 kV

Capacitor

132 kV

Reactor

330 kV

Feeder

Page 109: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-108

In the case of a 500-kV super grid, it is assumed that the transmission lines will be Single-Circuit lines with Quad Bison conductors.

In the case of a 750-kV super grid, it is assumed that the transmission lines will be Single-Circuit lines with five-bundle Bison conductors.

Regarding substations, it is assumed that for a 330-kV double busbar system with an auxiliary busbar, a bus coupler will be installed whereas for 500 and 750 kV units, one-and-half circuit-breaker schemes will be installed.

Table 7-10.27, Table 7-10.28 and Table 7-10.29 show the cost estimation for the three voltage levels.

Table 7-10.27 Cost estimation for the 330-kV super grid

Source: JICA Study Team

RatedVoltage

Length Cost per km Total Cost Total Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Ikot Ekpene - Benin 330 300 0.45 135

2 Ikot Ekpene - Makurdi 330 300 0.45 135

3 Benin - New Agbara 330 250 0.45 113

4 Benin - Osogbo 330 160 0.45 72

5 Benin - Ajaokuta 330 300 0.45 135

6 New Agbara - Osogbo 330 160 0.45 72

7 Osogbo - Gwagwalad 330 260 0.45 117

8 Makurdi - Gwagwalad 330 200 0.45 90

9 Makurdi - Ajaokuta 330 200 0.45 90

10 Ajaokuta - Gwagwalad 330 200 0.45 90

11 Gwagwalad - Funtua 330 250 0.45 113

Subtotal I 1,161

1 Ikot Ekpene 9 2 2 25

2 Benin 11 2 2 29

3 Makurdi 11 2 2 29

4 Osogbo 11 2 2 29

5 New Agbara 9 2 2 25

6 Ajaokuta 11 2 2 29

7 Gwagwalad 13 2 2 33

8 Funtua 7 2 2 21

Subtotal II 220

Grand Total

No. Project330 kV

Line

Feeder

330 kV

Transformer

Feeder

330 kV Shunt Reactor

1,381

Cost Estimation of 330 kV Super GridTransmission Lines 変電所

Overhead Lines

Substations

Page 110: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-109

Table 7-10.28 Cost estimation for the 500-kV super grid

Source: JICA Study Team

Table 7-10.29 Cost estimation for the 750-kV super grid

Source: JICA Study Team

The cost comparison is summarized in Table 7-10.30.

RatedVoltage

Length Cost per km Total Cost Total Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Ikot Ekpene - Benin 500 300 0.28 84

2 Ikot Ekpene - Makurdi 500 300 0.28 84

3 Benin - New Agbara 500 250 0.28 70

4 Benin - Osogbo 500 160 0.28 45

5 Benin - Ajaokuta 500 300 0.28 84

6 New Agbara - Osogbo 500 160 0.28 45

7 Osogbo - Gwagwalad 500 260 0.28 73

8 Makurdi - Gwagwalad 500 200 0.28 56

9 Makurdi - Ajaokuta 500 200 0.28 56

10 Ajaokuta - Gwagwalad 500 200 0.28 56

11 Gwagwalad - Funtua 500 250 0.28 70

Subtotal I 722

1 Ikot Ekpene 6 2 2 2 64

2 Benin 8 2 2 2 72

3 Makurdi 7 2 2 2 68

4 Osogbo 7 2 2 2 68

5 New Agbara 6 2 2 2 64

6 Ajaokuta 7 2 2 2 68

7 Gwagwalad 8 2 2 2 72

8 Funtua 5 2 2 2 60

Subtotal II 533

Grand Total

Cost Estimation of 500 kV Super Grid

Overhead Lines

Substations

No. Project

1,256

Transmission Lines Substations

500kV feeder 330kV feeder

500MVA

500/330 kV

Transformer

500kV

Shunt Reactor

RatedVoltage

Length Cost per km Total Cost Total Cost

(kV) (km) (Million US$/km) (Million US$) (Million US$)

1 Ikot Ekpene - Benin 750 300 0.35 105

2 Ikot Ekpene - Makurdi 750 300 0.35 105

3 Benin - New Agbara 750 250 0.35 88

4 Benin - Osogbo 750 160 0.35 56

5 Benin - Ajaokuta 750 300 0.35 105

6 New Agbara - Osogbo 750 160 0.35 56

7 Osogbo - Gwagwalad 750 260 0.35 91

8 Makurdi - Gwagwalad 750 200 0.35 70

9 Makurdi - Ajaokuta 750 200 0.35 70

10 Ajaokuta - Gwagwalad 750 200 0.35 70

11 Gwagwalad - Funtua 750 250 0.35 88

Subtotal I 903

1 Ikot Ekpene 6 2 2 2 82

2 Benin 8 2 2 2 92

3 Makurdi 7 2 2 2 87

4 Osogbo 7 2 2 2 87

5 New Agbara 6 2 2 2 82

6 Ajaokuta 7 2 2 2 87

7 Gwagwalad 8 2 2 2 92

8 Funtua 5 2 2 2 77

Subtotal II 686

Grand Total

Cost Estimation of 750 kV Super Grid

No. Project

1,589

Transmission Lines Substations

750kV

feeder

330kV

feeder

500MVA

750/330 kV

Transformer

750kV

Shunt Reactor

Overhead Lines

Substations

Page 111: CHAPTER 7 Transmission Network Development Plantransmission lines and transformers is shown in Annexes 7.1d and 7.1e respectively. The present status of r eactors and capacitors installed

7-110

Table 7-10.30 Summary of cost comparison

Voltage Level Transmission Lines

(Million US$) Substations

(Million US$) Total

(Million US$)

330 kV 1,161 220 1,381

500 kV 722 533 1,256

750 kV 903 686 1,589

Source: JICA Study Team

A rough cost comparison indicates that the 500-kV super grid will require less investment. However, the cost difference to 330 kV is relatively small. Considering that in terms of technical performance (MVA transmission capacity, losses, impact on under/overvoltages and overloads as well as static security issues) the 330-kV system appears more advantageous, its 10% higher investment cost could be justified.

In view of the above, it is apparent that more detailed studies must confirm the conclusions of this study. It is therefore recommended to have these detailed studies carried out in due course and as soon as possible, before a final decision can be made on the selection of the voltage level (330 or 500 kV) for a future super grid.

The cost for 750 kV is far higher compared to 330 and 500 kV. The transmission capacity of a 330-kV Double-Circuit line and a 500-kV Single-Circuit line are 3,100 and 2,350 MVA respectively, compared to 4,400 MW for a 750-kV Single-Circuit line. The network calculations (Chapter 8), however, have indicated that the transmission capacity of the 330 and 500 kV supergrid systems suffices.

There is no justification for adopting and/or further considering any higher (750 kV) option for the EHV grid, particularly when the implications in cost differences are taken into account, as detailed in Section 8. The higher transmission capacity (4,400 MVA) is not required at this stage and the marginal differences in losses cannot offset the high investment cost required in the planning horizon of this Master Plan.