Chapter 5,6,7 (group 1 project man)
-
Upload
arvin-dela-cruz -
Category
Education
-
view
76 -
download
7
Transcript of Chapter 5,6,7 (group 1 project man)
Chapter 5: Problem and Solution
Chapter 5:Problem & Solution
Presented by:MACABIO, ELLEINE C.
PROJECT MANAGEMENT
Presentation Outline:
What Is a Problem?
From Problem to Project
Conclusion: Making the Solution Work
5 Parts of a Problem:
A crisis A symptom
A consequence
A causeA root cause
What makes a
situation a problem
.
..
Cause and Root cause of a Problem:
Crisis requires urgent
attention
.
.
Cause and Root cause of a Problem:
.
Symptom tells us
about the problem.
.
Cause and Root cause of a Problem:
.
.
The consequence
of a problem is the unwanted
results if we do
nothing
Cause and Root cause of a Problem:
.
Root cause is the cause of
the cause.
Cause and Root cause of a Problem:
.
.
Permanent preventive
solution puts an end to a root cause.
Cause and Root cause of a Problem:
.
.
Cause and Root cause of a Problem:
What makes a
situation a problem
Crisis requires urgent
attention
Symptom tells us
about the problem.
The consequence
of a problem is the unwanted
results if we do
nothing
Root cause is the cause of
the cause
Permanent preventive
solution puts an end to a root cause.
Cause is the center of
the problem
What is Problem Definition tool:
Allow you to sort out the pieces of
a problem.
Example of Problem
definition
tool
3 categories to organize a problem:
problems from your own company, directly
under your control
problems you can influence
problems you can’t do anything about
Picture the solution.
Ask if you need
information
Ask if you need
expertise.
Maybe make a decision.
List your options
Here is a process for choosing the best solution to
a problem
Problem to project:
Conclusion: Making the Solution Work
What Are
We Making?
Chapter 6
Scope of What Are We Making?
• The Steps of Defining Scope
• Write a Basic Statement of What We Are Making
• Choose a General Approach to How We Will Make It
• Draw and Write a Detailed Description of What We Are Making
• Write a Detailed Work Breakdown Structure (WBS)
• Write a Detailed Action Plan
• Conclusion: A Leader with a Plan
What Are We Making?
• YOU’VE LEARNED HOW TO DEFINE DREAMS, OPPORTUNITIES, AND PROBLEMS, IT’S TIME TO PICK ONE PLAN AND PLAN OUT WHAT WE ARE DOING IN DETAIL TO MAKE THIS PROJECT HAPPEN.
Defining the scope of the project
DEFINING
RESULTS PROCESS TASK
The Steps of Defining Scope
• Features
• Benefits
• A system
• Value
• A set of steps of work
• Components
The Steps of Defining Scope
1.Write a basic statement of what we are making.
2.Choose a general approach to how we will make it.
3. Draw and write a detailed description of what we are making.
4. Write a detailed Work Breakdown Structure (WBS).
5. Write a detailed action plan.
Write a Basic Statement of What We Are Making
• Requirements Elicitation
Most common challenges
• Some customers simply don’t know what they want until they see it.
• Some customers aren’t available.
• Some customers know what they want, but can’t define it unless we guide them.
How to do requirements elicitation in six steps:
1. Figure out who the customers are.2. If you can, prepare a prototype, mock-up, or picture of the
product .3. Make a list of questions .4. Meet with the customers5. Write up a clear, detailed description of the product or service6. Show the results to the customers
Choose a General Approach to How We Will Make It
• DRIVER• CONTRAINTS
Draw and Write a Detailed Description of What We Are Making
Requirements Specification
• Complete
• Consistent
• Correct
• Feasible
• Modifiable
• Necessary
• Prioritized
• Testable
• Traceable
• Unambiguous
Write a Detailed Work Breakdown Structure (WBS)
Making a Really Good WBS• Let each person make the WBS for the work he
or she will do. People are more committed when they plan their own work. It also lets everyone contribute expertise to the project.
• Walk through the WBS as a team to clarify ideas and make improvements.
• Never copy a whole WBS because every project is unique. But copy and modify parts of WBSs that are similar from past projects.
Write a Detailed Action Plan • Is each step clear? A clear step is a verb followed by a noun. For example,
“draw blueprint,” “write user instructions,” and “assemble gearbox” are all good, clear steps.
• Is there a clear starting point? Are all the components listed? Does the worker know where he or she will get each one?
• Is everything checked or tested as the work is done?
• Is all the work necessary to complete the whole work package included?
• Are all appropriate tests included?
• Does a walk-through show that this will get everything done?
• Is this the best way to do the job?
Chapter 7:Planning Timeand Money
Presented by:DELA CRZ, ARVIN DOMINIC B.Group leader – Group 1
Project Management
Presentation Outline:
Allocating, Estimating, Scheduling,
and Budgeting
Detailed Scheduling
Detailed Budgeting
Conclusion: Ready to Stay on Track
EstimatingBudgeting
Scheduling Allocating
Allocating, Estimating, Scheduling, and Budgeting
` What is Estimation?
A
thoughtful
guess
about the
future.
More
detailed than estimation
Scheduling
gives us a
plan:
what job will be
done each day,
each week, until
all the work is
done.
What is Scheduling?
Gives us a
statement of
the total
amount of work
It is
completely
separate from
estimation
which is a
measure of
what it will
take to do
the project.
What is Allocation?
It is based on
what our
business can
give to the
project.
What is Budgeting?
A plan for spending money
from the beginning
of the project to the end.
Key Concepts:
1. Keep
allocation and
estimation
separate
2. In
estimating,
avoid bias.
Bias means
leaning
one way or
the other
3. In
estimating,
be as
accurate as
possible
Key Concepts (cont’n):
4. In time
estimation,
separate
effort and
duration:
Effort is the
amount of
work,
measured in
person-hours.
Duration is the
total schedule,
from beginning
to end, in days
5. We actually
plan work, not
time and
money.
Early Estimation
The first two questions that a business owner usually asks about a project are:
“How much will it cost?”
“How long will it take?”
Here are some steps for preparing a good early time estimate:
1. Complete as much of the plan as you can.
2. Write down any decisions you haven’t made.
3. Make a rough list of the steps that you are going to take.
4. Put two columns next to the list—low estimate and high estimate.
5. Add up the totals of each column to get your low and high estimates.
Here are some steps for preparing a good early cost estimate:
1. Complete as much of the plan as you can.
2. Write down any decisions you haven’t made.
4. Make a rough list of the steps that you are going to take.
5. Put two columns next to the list—low estimate and high estimate.
6. Add up the totals of each column to get your low and high estimates
3. Make a shopping list.
The Lesson: It is a mistake to think that your time or the time of your staff doesn’t count as money. Often, we are better off hiring an expert to do a project and spending our time making money some other way.
Time is Money:
How do we decide how long each item on our list will take or how much money it will cost? Here are some approaches:
Do some research
Estimate based on the steps of a past project
When in doubt, guess.
Detailed Scheduling
1. Make sure your action plan is
complete and correct.
2. Resolve any open decisions or unanswered questions.
3. Assign each work package or task to a
specific person.
4. Decide if each person will work on the project full time or what hours
each will be available.
5. Have each person come up with a single, final estimate of how long
each task will take
6. Put the tasks in order.
Detailed Scheduling
7. Include time for testing each output.
8. Allow time for things like paint drying or ovens warming up, where no work is being done, but time has to pass anyway. This is
called lag time.
9. Check people’s calendars for holidays, vacation, and other work
Detailed Scheduling
10. Pick a start date and work forward, or pick an end date and work backwards,
from the last task to the first.
11. Assign each task to a date. Include time for status meetings, tests, gate
reviews, and rework.
12. Review the schedule with each team member, making any changes or
corrections.
• Assign a dollar value to each person’s time
• Add up each person’s total time and then multiply it by his or her hourly rate.
• Review your shopping list against the completed WBS and action plan
• Do some research and get actual prices for your shopping list.
• Check for incidental expenses such as gas, travel expenses, or lunch for the team, and include those
• Add it all up.
Detailed Budgeting:
Conclusion: Ready to Stay on Track
/arvindelacruz39982
Follow me on:
1. __________ tells us about the problem2. __________ requires urgent attention.3. ___________ is the center of the problem.4. ___________ cause of the cause5. ___________ allows you to sort out the pieces of a problem.6. ____________ list of the ways that the product/service is good for the customer.7. ________ short explanation of why we are doing the project8. _______ list of all the pieces of the product/ service. 9. _______ description of what the product or service does. 10 . _______ thoughtful guess about the future. 11. _______ This shows how all the components work together.12. ________ - plan for spending money from the beginning to the end.13. _____ gives us a statement of the total amount of work14. _____ is Money15. ______ means leaning one way or the other
a. Root cause b. Causec. Problem Definition toold. Value: e. Benefitsf. Features:
g. Components:h. system
i. Estimation j. Allocation k. Budgeting l. Biasm. Time
n. Crisiso. Symptom
5 parts of a Problem?
Enumeration
Thanks for Listening