Chapter 5 Present Worth Analysis EGN 3615 ENGINEERING ECONOMICS WITH SOCIAL AND GLOBAL IMPLICATIONS.
-
Upload
melina-stokes -
Category
Documents
-
view
249 -
download
4
Transcript of Chapter 5 Present Worth Analysis EGN 3615 ENGINEERING ECONOMICS WITH SOCIAL AND GLOBAL IMPLICATIONS.
Three Economic Analysis MethodsThere are three major economic analysis
techniques:
Present Worth AnalysisAnnual Cash Flow AnalysisRate of Return Analysis
This chapter discusses the first techniques
2
Chapter ContentsEconomic CriteriaConsidering Project LifeNet Present WorthApplying Present Worth Techniques
Useful Lives Equal the Analysis PeriodUseful Lives Different from the Analysis
PeriodInfinite Analysis Period: Capitalized CostMultiple Alternatives
Spreadsheet Solution3
Economic CriteriaDepending on situation, the economic
criterion should be chosen from one of the following 3:
Situation CriterionNeither input nor output fixed
Maximize (Output – Input)
Fixed input Maximize outputFixed output Minimize input
4Engineering Economics
Analysis PeriodSpecific time period, same for each
alternative, called the analysis period, planning horizon, or project life
Three different analysis-period situations may be considered:1. All alternatives have the same useful life: Set
it as the analysis period.2. Alternatives have different useful lives: Let
the analysis period equal the least common multiple, or some realistic time (based on needs).
3. Infinite analysis period, n=∞ 5Engineering Economics
Net Present Worth (NPW or PW)Here is the basic NPW formula:
PW = PW of benefits – PW of cost
Costs
of
rth Present wo
-
Benefits
of
rth Present wo
PWor NPW
WORTH
PRESENT NET
6Engineering Economics
Present Worth TechniquesMutually exclusive alternatives: Resolve their consequences to the present
time. Situation Criterion
Neither input nor output fixed
Maximize net present worth
Amount of money or other input resources are fixed
Maximize present worth of benefits or other outputs
Fixed task, benefit, or other outputs
Minimize present worth of costs or other inputs
7Engineering Economics
Present Worth—Equal Useful LivesExample: Consider two mechanical devices to
install to reduce cost. Expected costs and benefits of machines are shown in the following table for each device. If interest rate is 6%, which device should be purchased?DEVICE COS
TCOST SAVING USEFUL
LIFEDEVICE A
$1000
$300 Annually5 year
DEVICE B
$1350
$300 The first year and increase $50 annually
5 year8Engineering Economics
Example Continues
263.6
(4.212) 300 1000
(P/A,6%,5) 3001000PW A
0
1
2 3
4 5
A=$300
P= $1000
i=6%
9Engineering Economics
Example Continues
310.3
(7.934) 50 (4.212) 300 1350
(P/G,6%,5) 50 (P/A,6%,5) 300 1350 PW B
0
1
2 3
4
$300
P= $1350
i=6%
$350
$400
$450
$500
5
10Engineering Economics
Example Continues
310.3 PW
263.6 PW
B
A
0
1
2 3
4 5
A=$300
P= $1000
i=6%
DEVICE B has the larger present worth & is the preferred alternative
0
1
2 3
4
$300
P= $1350
i=6%
$350
$400
$450
$500
5
11Engineering Economics
Work 5-4
Example: Consider two investments with expected costs and benefits shown below for each investment. If investments have lives equal to the 5-year analysis period, which one should be selected at 10% interest rate?
Investment
Cost Benefit Useful
Life
Salvage Value (End of Useful
Life) Investment 1
$2000
$450 Annually
5 year $100
Investment 2
$3000
$600 Annually
5 year $700
Present Worth—Equal Useful Lives
12Engineering Economics
Example Continues
96.231
] (0.6209) 100200[(3.791) 450
10%,5)] (P/F, 100200[5) 10%, (P/A, 450
Costs ofPW Benefits ofPW
:1 Investment
13Engineering Economics
Example Continues
290.77
] (0.6209) 7003000[(3.791) 600
] 10%,5) (P/F, 7003000[5) 10%, 600(P/A,
Costs ofPW Benefits ofPW
:2 Investment
14Engineering Economics
Example Continues
290.77
(0.6209)] 7003000[(3.791) 600
10%,5)] (P/F, 7003000[5) 10%, 600(P/A,Costs ofPW - Benefits ofPW
:2 Investment
96.231
] (0.6209) 100200[(3.791) 450
] 10%,5) (P/F, 100200[5) 10%, (P/A, 450Costs ofPW - Benefits ofPW
:1 Investment
Salvage value is considered as another positive cash flow. Since criterion is to maximize PW (= present worth of benefits – present worth of costs), the preferred alterative is INVESTMENT1
15Engineering Economics
EQUIPMENT
COSTSALVAGE
VALUEUSEFUL
LIFEEQUIPMENT
A$1500 $200 5 year
EQUIPMENT B
$1600 $350 10 year
Example: Consider two new equipments to perform desired level of (fixed) output. expected costs and benefits of machines are shown in the below table for each equipment. If interest rate is 6%, which equipment should be purchased?
Alternatives with different Useful Lives
16Engineering Economics
Example ContinuesOne method to select an analysis period is
the least common multiple of useful lives.
0
1
2 3
4 5
$200
$1500
6 7 8 9 10
$1500
$200Replacement
Equipment A Investment
Original Equipment A Investment
EQUIPMENT A
81. 359,2$
) 5584.0( 200 ) 7473.0( 1300 1500
10) 6%, (P/F, 2005) 6%, (P/F, 200) (1500 1500
cost ofPW
17Engineering Economics
Question Continues$350
0
1
2 3
4 5
$1600
6 7 8 9 10
Original Equipment B Investment
EQUIPMENT B
1,404.56$
(0.5584) 350 1600
10) 6%, (P/F, 350 1600
cost ofPW
18Engineering Economics
Question Continues
$1,404.56
(0.5584) 325 1600
10) 6%, (P/F, 325 1600cost ofPW
81. 359,2$
) 5584.0( 200 ) 7473.0( 1300 1500
10) 6%, (P/F, 200
5) 6%, (P/F, 200)- (1500 1500cost ofPW
For fixed output of 10 years of service of equipments, Equipment B is preferred because it has a smaller cost.
EQUIPMENT A
EQUIPMENT B
19Engineering Economics
Example: Consider two alternative production machines with expected initial costs & salvage values shown below. If interest rate is 10%, compare these alternatives over a (suitable) 10-year analysis period (by using the present worth method)?
MACHINEINITIAL
COST
Salvage Value at the End
Of Useful Life
Terminal Value at the end of 10-
year analysis period
USEFUL LIFE
MACHINE A
$40,000
$8,000 $15,000 7 year
MACHINE B
$65,000
$10,000 $10,000 13 year
Present Worth-Useful Lives are Different from the Analysis Period
20Engineering Economics
Example Continues
$40,000
0
1
2 3
4 5
$8,000
6 7 8 9 10
$15,000
7-year life
MACHINE A
11 12 13 14
$40,0007-year life
50,639.90$
) 0.3855( 15,000) 5132.0( 000,3240,000
10) 10%, (P/F, 15,000
7) 10%, F,8,000)(P/ (40,00040,000
cost ofPW
21Engineering Economics
Example Continues
0
1
2 3
4 5 6 7 8 9 10
$10,000
$65,000
MACHINE B
11 12 13 14
13-year life
61,145.0$
0.3855) ( 10,000 000,56
10) 10%, (P/F, 10,000 000,56
cost ofPW
22Engineering Economics
Example Continues
$61,145.00
0.3855) ( 10,000 000,56
10) 10%, (P/F, 10,000 000,56cost ofPW
$50,639.90
) 0.3855( 15,000 ) 5132.0( 000,32 40,000
10) 10%, (P/F, 15,000
7) 10%, (P/F, 8,000)- (40,000 40,000cost ofPW
For fixed output of 10 years of service of equipments, Machine A is preferred because it has a smaller cost.
MACHINE B
MACHINE A
23Engineering Economics
Infinite Analysis Period (Capitalized Cost)
Capitalized cost is the present sum of money that is set aside now at a given interest rate to yield the funds (future interest earned) required to provide the service indefinitely.
(5-2)
i
A PCost dCapitalize
24Engineering Economics
Infinite Analysis Period (Capitalized Cost)
Example: How much should one set aside to pay $1000 per year for maintenance on an equipment if interest rate is 2.5% per year and the equipment is kept in service indefinitely (perpetual maintenance)?
000,40$0.025
1000P
(i) rateInterest
(A)nt disburseme AnnualP Cost, dCapitalize
25Engineering Economics
Multiple (3+) AlternativesQuestion: Cash flows (costs and incomes) for
three pieces of construction equipments are shown below. For 10% interest rate, which alternative should be selected?Year Equipment
1Equipment
2Equipment
3
0 -$2000 -$1500 -$3000
1 +1000 +700 +500
2 +850 +300 +500
3 +700 +300 +550
4 +550 +300 +600
5 +400 +300 +650
6 +400 +400 +700
7 +400 +500 +500
8 +400 +600 +50026Engineering Economics
Question Continues
$2000
0
1
2 3
4 5
$400
6 7 8
$400
EQUIPMENT 1
$1000
$850
$700
$550
$400
$400
17.379,1$200017.3379rthPresent WoNet
2000 Cost ofPW
3379.17150(4.378)
)170.3(600)335.5(400
4) 10%, 150(P/G,
4) 10%, 600(P/A,8) 10%, 400(P/A,Benefits ofPW
27Engineering Economics
Question Continues
0
1
2 3
4 5
$300
$1500
6 7 8
$600
EQUIPMENT 2
$700
$300
$300
$300
$400
$500
15.763$150015.2263rthPresent WoNet
1500 Cost ofPW
15.2263(0.6830) 100(4.378)
)9091.0(400)335.5(300
4) 10%, 4)(P/F, 10%, 100(P/G,
1) 10%, 300)(P/F,-007(
8) 10%, 300(P/A,Benefits ofPW
28Engineering Economics
Question Continues
0
1
2 3
4 5
$650
$3000
6 7 8
$500
EQUIPMENT 3
$500
$500
$550
$600
$700
$500
64.20$300036.2979rthPresent WoNet
3000 Cost ofPW
36.2979(0.9091)100(6.862)
)335.5(500
1) 10%, 5)(P/F, 10%, 50(P/G,
8) 10%, 500(P/A,Benefits ofPW
To maximize NPW, choose EQUIPMENT 1 29Engineering Economics
Question Continues (MS EXCEL)
30Engineering Economics
Use function: npv(rate, value range) - Return the net present value of a series of future cash flows “value range” at interest “rate”/period.
rate = interest rate per period
value range = the cash flow values
Question Continues (MS EXCEL)Year Equipment 1 Equipment2 Equipment3
0 ($2,000) ($1,500) ($3,000)
1 1000 700 500
2 850 300 500
3 700 300 550
4 550 300 600
5 400 300 650
6 400 400 700
7 400 500 500
8 400 600 500
Interest For Equip 1: NPW=NPV(A12,B3:B10)+B2
10% $1,379.17 $763.15 ($20.64)
31Engineering Economics
Problem 5-15
32Engineering Economics
Solution i = 12%P = $980,000 purchase costF = $20,000 salvage value after
13 yearsA = $200,000 annual benefit for 13
years
PW = –P + A(P/A, 0.12, 13) + F(P/F, 0.12, 13) = –980000 + 200000(6.424) + 20000(0.2292) = $309,384As PW > 0, purchase the machine.
Or using MS EXCELPW = -P + pv(0.12, 13, -200000, -20000) = $309,293.17Terms A(P/A, 0.12, 13) and F(P/F, 0.12, 13) are combined!
Problem 5-23
33Engineering Economics
Solution i = 18%/12 = 1.5% per monthA = $500 payment/monthn = 36 paymentsP = ? price of a car she can
afford
P = A(P/A, 0.015, 36) = 500(27.661) = $13,831
What is P, if r = 6%? i = 6%/12 = 0.5%P = pv(0.005, 36, -500) = $16,435.51
Do Problems 5-24, 5-25, 5-26!
Problem 5-41
34Engineering Economics
Outputs: 2000 lines for years 1~104000 lines for years 21~30
i = 10% per year, cables last for at least 30 yrsOption 1: 1 cable with capacity of 4000 lines
Cost: $200k with $15k annual maintenance costOption 2: 1 cable with capacity of 2000 lines now
1 cable with capacity of 2000 lines in 10 years
Cost: $150k with $10k maintenance cost/year/cable
(a) Which option to choose?(b) Will answer to (a) change if 2000 additional lines are
needed in 5 years, instead of 10 years?
Problem 5-41
35Engineering Economics
Solution(a)Present worth of cost for option 1PW 0f cost = $200k + $15k(P/A, 10%, 30)
= $341,400
Present worth of cost for option 2:PW of cost = $150k + $10k(P/A, 10%, 30)
+ $150k(P/F, 0.1, 10) + $10k(P/A, 0.1, 20)(P/F, 0.1, 10)
= $334,900
Select option 2, as it has a smaller PW of cost.
Problem 5-41
36Engineering Economics
Solution(b)Cost for option 1 will not change.PW 0f cost = $341,400
Present worth of cost for option 2:PW of cost = $150k + $10k(P/A, 10%, 30)
+ $150k(P/F, 0.1, 5) + $10k(P/A, 0.1, 25)(P/F, 0.1, 5)
= $394,300
Therefore, the answer will change to option 1.