CHAPTER 4 CASE STUDY –LEARNING FROM...
Transcript of CHAPTER 4 CASE STUDY –LEARNING FROM...
![Page 1: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/1.jpg)
74
CHAPTER 4
CASE STUDY –LEARNING FROM FAILURE
4.1 INTRODUCTION
In this chapter we report on two case studies conducted as part of
this research. These cases relate to two different ERP implementations in
ABC Corporation, a midsized, multi location process industry in India with
over 2000 employees, over a 100 customers and a supply chain extending
across the country as well as overseas. The cases were selected because the
first was considered a failure and the second a success. The lessons learnt
from the first failed implementation led to a change in implementation
strategy for the second which finally led to success. We believe there are
lessons to be learnt both from the failure and from the later success both for
research and practice. Being from the same organization with no major
changes in either the ERP or the management and user teams, a comparative
study gives an opportunity to zero in on those causal variables that seem to
make a difference.
This company had a good legacy system but had decided to
implement ERP for meeting the long term information needs of the business.
The first project which we call ERP 1, had large cost and time overruns, did
not deliver promised results and met with severe user resistance. After
managing with an unsatisfactory implementation and attempting to a correct
the gaps over a two year period the company decided to do re-
![Page 2: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/2.jpg)
75
implementation. This project we call ERP 2 was completed on time, largely
met targets and was considered successful.
We have used this context to scientifically study the processes that
caused failure in the first instance and success in the other. We look at the
interaction between the implementation process and organizational dynamics
to seek answers for the question of ERP failures. The case study addresses the
meta-question: “Why do ERP projects fail? We use insights gained to
identify key causal factors that lead to failure and steps that could be taken to
steer such projects to success.
In the following section we identify factors that have been found in
earlier research to have influenced IT project outcomes. Next the key
hypotheses that would be tested in the research through the case study are
enumerated. The section that follows explains the nature of qualitative
research and justifies its use in this research. The research methodology
followed is explained next. The cases are then described and the analysis of
the cases follows. The chapter ends with a detailed discussion on the case
similarities and differences with a final word on the key learning from the
case which are used in the empirical study that follows.
4.2 FACTORS INFLUENCING ERP OUTCOME
Chapter 2 presented a detailed literature study which included a
section on CSFs which could be causal factors in influencing ERP project
outcomes. We revisit these critical factors in this chapter as one of the
objectives of the case study is to understand the manner in which these causal
factors work in actual practice.
Most researchers starting from Davenport (1998) identify top
management support and such directional factors as crucial for ERP success.
![Page 3: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/3.jpg)
76
These include factors like use of a cross functional steering committee,
communication, cross functional implementation teams etc.
Hong and Kim (2002) stress on the organization preparedness
aspects of the implementation namely organizational fit, system adaptation
levels, resistance to change etc.
Wixom and Watson (2001), study implementation issues related to
data warehousing project success. They categorize the CSFs as belonging to
into three groups, viz., Organizational, Project and Technical. A data
warehousing project has many similarities with an ERP project- it is complex,
it has pan-organization linkages, and change management issues are involved
Chua et al (2009) analyze CSF literature and point out to the
contradictions and fragmented nature of the studies. The CSFs listed vary
across studies, the operational definitions are different, several important
causal factors like change management are missing from some lists etc., The
researchers believe because CSF research has “emphasized identifying CSFs
linked to project success at the expense of a more thorough exploration of the
causal mechanisms connecting organizational actions and processes to project
success. In other words, CSF research has focused on what CSFs look like,
but overlooked how and why they become critical” (pp 2).
Parr and Shanks (2000), studying ERP implementation propose a
project phase model (PPM) consisting of three distinct phases: planning,
project and enhancement. The PPM model synthesizes earlier ERP
implementation models of Bancroft et al (1998), Ross (1998) and Markus
and Tannis (1999) which focus on the pre and post implementation steps and
bundle the implementation project into one category. While recognizing the
importance of the planning phase and post project phases, PPM focuses on the
project phase which they subdivide into set up, reengineering, design,
![Page 4: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/4.jpg)
77
configuration/testing and installation. They then identify the relative
importance of different CSFs in the different phases and sub phases. They use
a two case methodology of a failed ERP implementation in one organization
and a successful one in another to establish their model. They emphasize the
need for “further studies of ERP systems to validate and extend the particular
CSFs that are important in each PPM phase” (pp302).
This then is the motivation for this case study. We attempt to
understand the CSFs in greater detail –beyond mere words and articulation to
how they are interpreted by the users whom they impact. We follow the Parr
and Shanks (2000) two case methodology with the difference that both the
failed and successful implementations are in the same organization. We also
focus on the first two phases of the PPM model, viz., planning and project.
4.3 HYPOTHESIS DEVELOPMENT
In this case study we address the following questions:
1. Why do ERP projects fail?
2. What are the factors that lead to a troubled ERP project
resulting in poor acceptance by users?
3. What changes in these factors would alter the course of the
ERP project in gaining greater user acceptance?
Dissatisfaction in ERP projects comes from a perceived gap
between expected and actual benefits. Expectations-Confirmation theory
posits that expectations, coupled with perceived performance, leads to post-
purchase satisfaction. If a product outperforms expectations (positive
disconfirmation) post-purchase satisfaction will result. If a product falls short
of expectations (negative disconfirmation) the consumer is likely to be
dissatisfied (Oliver 1977). If during the goal setting and scoping stage, high
![Page 5: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/5.jpg)
78
expectations are raised, likelihood of the product falling short of expectations
is high: If the gap is large, theory tells us that this would lead to “negative
disconfirmation” and therefore dissatisfaction. Our first hypothesis therefore
is:
H1 - High expectations negatively impact ERP success
An ERP project is “…perhaps the world’s largest experiment in
business change” (Davenport 1998). Lewin’s model of change posits that
change management in organizations moves through three stages
“Unfreezing”, “Change” and “Refreezing”. Internal resistance to the new way
of working happens during critical phases of Unfreezing and Change. During
this phase top management’s visible advocacy of the project , a shared vision
of change, role of internal change agents (champions) become important and
determines the future acceptance or otherwise of the proposed change.
ERP being a change project if the support and direction from top
management is weak, then theory tells us that the “Unfreezing” and “Change”
phases could face problems leading to the ERP not being accepted by users.
Top management support is evidenced by (a) senior management leading by
example (b) allocation of resources as needed on time (c) repeated
communications on the importance of project (d) inter-departmental/process
conflict resolution and (d) continual monitoring and redirecting through an
effective steering committee process. The users see these as evidence that top
management is strongly backing the ERP project. In line with this our next
hypothesis is:
H2: Top management support would be seen as real only if it is
manifest in specific actions and sustained throughout the project.
Structuration theory provides us with an overarching view of the
interaction of the technology (ERP artifact) with the existing social structure
![Page 6: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/6.jpg)
79
of an organization. Originally proposed by Giddens (1979) and developed as
adaptive structuration theory (Poole and De Sanctis 1990), these models
explore “how people (in organizations), interact with a technology in their
ongoing practices, (and) enact structures (rules, practices etc.) which shape
their emergent and situated use of that technology...” (Orlikowski 2000,
pp 404).
This theory relates to the existing social structures in the company-
“Structure here is understood as the set of rules and resources instantiated in
recurrent social practice” (Orlikowski 2000, pp 406). These would include the
roles, reporting relationships, the power and authority of the various role
holders in an organization. These are embodied in the legacy systems of the
company which “encapsulate the existing business processes, organization
structure, culture...” (Holland, Light and Gibson, 1999 pp 31). An ERP with
its revised work flows could alter the existing business processes and
therefore would encounter resistance as per Interaction theory. “…resistance
–generating conditions (are defined) as mismatch between patterns of
interaction prescribed by the system and the patterns that already exist”
(Markus 1983, pp 438)
So structuration theory seen along with interaction theory would
suggest that the existing structures embodied in the well entrenched legacy
system will offer greater resistance to work flows dictated by the ERP . We
therefore frame the hypothesis:
H3: A strong and well entrenched legacy system negatively
influences the adoption of an ERP system.
4.4 CASE STUDY METHODOLOGY
In this section we explore qualitative research as used in IS studies.
Both quantitative and qualitative research are based on some underlying
![Page 7: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/7.jpg)
80
assumptions regarding what is 'valid' research and which research methods
would be most appropriate. Let us look at these core assumptions.
Looking at the underlying epistemology which guides the research,
Guba and Lincoln (1994) suggest four underlying "paradigms" for qualitative
research: positivism, post-positivism, critical theory, and constructivism.
Orlikowski and Baroudi (1991), suggest three categories - positivist,
interpretive and critical. While these three categories are philosophically
distinct, often there is a need to accommodate various aspects of the three in
one study.
Qualitative research could be (a) positivist ( where there are formal
hypothesis, quantification of variables, testing, and the drawing of inferences
from the sample to a stated population) (b) Interpretive ( where inferences are
drawn based on an understanding of the social context of the phenomena
under study : how the IS artifact influences the organizational context and is
also influenced by the context ) and (c) Critical ( an approach that looks at the
interplay of forces of opposition, and conflicts with those that are
emancipatory – in the organizational context this would look at the
reinforcing cycles of change along with the balancing or countering forces
and seek meanings from them).
It follows from this that the choice of a specific qualitative research
method (such as the case study method) is independent of the underlying
philosophical position adopted. For example, case study research can be
positivist, interpretive, or critical, just as action research can be positivist,
interpretive or critical.
Case study research has been used in Information Systems research
for the last three decades (Benbasat et al 1987, Lee 1989, Yin 1993, Keil
1995, Markus 1983). It is an appropriate methodology because ERP is an
![Page 8: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/8.jpg)
81
example is an artifact that cannot be studied outside the context in which it is
deployed. Being dynamically reconfigurable an ERP system “emerges” as it
were in an organization through repeated use and interpretation by users.
Structuration theory posits that “…structures of technology use are
constituted recursively as humans regularly interact with certain properties of
a technology and thus shape the set of rules and resources that serve to shape
their interaction…” (Orlikowski 2000 pp 407). The context therefore, defines
the ERP. Hence a case study approach is appropriate to study issues related to
ERP implementations in organizations.
This paper follows the scientific methodology suggested for case
study research (Pare 2001, Yin 1993). The four important issues in a case
study research are (a) framing of the research question (b) a priori
specification of constructs /theory/hypothesis (c) definition of unit of analysis
and (d) selection of cases for study (Pare 2001). We discuss each of these:
4.4.1 Defining the Unit of Analysis
The units of analysis chosen for this study are the ERP projects 1 &
2 of ABC Corporation. ERP 1 refers to the first implementation project of
Oracle Applications 10.4 in a division of ABC Corporation. ERP 2 refers to a
fresh implementation of Oracle Applications 11i in the same division. To
understand the context of the implementation, a prequel, representing the two
years prior to the start of ERP 1 is also included. Although this prequel period
is outside the boundary of the unit of analysis, during this period a strong
legacy system was built and internalized at ABC Corporation’s division. We
have included this as our hypothesis states that this legacy system has an
influence in the success or otherwise of the ERP project to follow.
Cases for study need to be: (a) revelatory (“when an investigator
has an opportunity to observe and analyze phenomena previously inaccessible
![Page 9: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/9.jpg)
82
to scientific investigation”) (Pare, 2001 pp13) (b) Unique or (c) Critical to
testing the theory. Furthermore case study choices should provide
opportunities to replicate and generalize the study.
The cases chosen by us are “revelatory” as the researcher was
personally involved in ERP 1 as a project manager and in ERP 2 as an
observer. “…participant –observation makes the researcher into an active
participant in the events being studied”. This provides “some unusual
opportunities for collecting data” but could also be problematic … “as the
researcher could well alter the course of events…” Pare (2001, pp16). This
drawback is addressed as the researcher is looking at the events that unfolded
years back in retrospect and has the advantage of seeing the events in
perspective. Detailed notes of the events made by the researcher also helped
in this process.
In addition, we had access to a detailed post completion audit done
of ERP 1 before the start of ERP 2 by a separate team. This provides an
excellent third party perspective of the events prevailing, the problems
encountered, and the results achieved with a causal analysis. This proved
invaluable in revalidating the impressions recorded in the notes of the
researcher.
The choice of case studies also satisfies the condition of criticality -
meeting the necessary conditions for testing our hypothesis. The organization
remains the same, top management and management team is largely the same;
the ERP under implementation is an enhanced version of the same ERP; the
changes are related to the differences in top management support, change
management initiatives, expectations management –all of which are the
hypothesis under test. Hence the choice of cases affords an opportunity to test
replicability of findings.
![Page 10: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/10.jpg)
83
4.4.2 Data Collection and Analysis Methods
The data for the case was gathered over a six month period as
follows. :
1. Study of personal notes made by the researcher who was a
project manager during the implementation of ERP1.
2. Detailed discussions with the erstwhile project manager of the
ERP 2 project-specifically focusing on the differences in ERP1
and ERP2.( the concerned project manager was a team lead in
the ERP1 project and therefore could make the comparisons)
3. Face to face semi-structured interviews with users representing
different user groups: (1) President and Business Head (2)
CFO, Materials manager, Marketing Manager (3) Sales
Coordination executive (4) Production manager and production
executive representing manufacturing (5) IT implementation
staff.
4. 10 users representing three different user cohorts: Strategic
users (business head/senior management) Operational users
(materials, sales, finance staff) and Technical (IT staff,
database administrators) responded to a structured
questionnaire which captured impressions of the respondents
on the strength and presence of various factors during the
implementation on a 7 point Likert scale with end values:
7= Completely Agree and 1= Completely Disagree. It also
checked the overall satisfaction level with the ERP on a 7 point
Likert scale with similar end values.
![Page 11: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/11.jpg)
84
5. We studied a post completion audit report of ERP1 that was
prepared by a cross functional team. This audit report was
prepared prior to the start of ERP2. This report was exhaustive
and made a very good causal analysis of the issues resulting in
a failed implementation.
4.5 THE CASE STUDIES: ERP IMPLEMENTATION AT ABC
CORPORATION
The case studies relate to ABC Corporation, a technology driven
process industry based in India with over 2000 employees, over a 100
industrial customers, and a supplier base spread all over the country as well
as overseas. Computerized accounting systems were introduced at ABC
Corporation in early part of the eighties.
In the early nineties, a FOXPRO based accounting system was
developed by, a company IT team. Data was captured in a batch mode, from
the various departments of the company and updated daily into the standalone
accounting system. Modules for stores/inventory, sales, purchase and payroll
were added -each stand-alone, feeding into the accounting system through
batch updating. To overcome the problem disparate databases, the FOXPRO
system was replaced with an (Relational Data Base Management System)
RDBMS system using INGRES1. The various modules were linked, creating
the first semblance of a future enterprise wide system.
In the years 1993 to 1995 the legacy system grew in functionality
and was used for all transaction processing. The internal EDP department
maintained the same, often going out of the way to accommodate requests
1 INGRES was one of the earliest RDBMS systems available in the early nineties fromIngres Corporation
![Page 12: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/12.jpg)
85
from the users for newer and newer reports and functionality. The demands
from the users often exceeded the capacity of the internal EDP department to
meet.
With the opening of the Indian economy in the early nineties ABC
Corporation had the vision of becoming a world class player in its business
domain. The company appointed an international consultant to carry out a gap
analysis to study if the existing IT system was ready to meet information
needs of the future. They wanted the consultant to answer the following
questions:
1. What were the weaknesses of the current IT system of the
company?
2. What changes should be made to align the Information System
to the business vision of ABC to become a world class
company?
The consultant team after a detailed study recommended that the
company phase out legacy systems and go for an ERP. A detailed exercise
was carried out to select the ERP. The choices were between SAP, JD
Edwards, Oracle Applications and Ramco Marshal.2 Oracle Applications was
chosen as it had a local support office, met the required functionality, had
another reference site and was competitively priced. The implementation was
planned at the largest division of the company. It was decided that after
successful implementation at one location, the same could be rolled out to the
other locations easily. The chronology of the ERP projects at ABC
Corporation is given in Table 4.1.
2 An Indian ERP that was gaining in popularity
![Page 13: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/13.jpg)
86
Table 4.1 ERP Project chronology
1993 -1995 (Background Phase) 1996 -1998 (ERP 1)
Even
ts
FOXPRO based accounting system developed by internalteam - replaced with INGRESS based integrated system.
Legacy system gets well entrenched through repeated use –
allows “maverick” practices.
ERP 1 -project commenced ; Top management not fully aware of thecomplexity of ERP project;No dedicated user teamsSteering committee formed – but meets infrequently; Top management
visible support wanesHigh expectations from ERP as projected by consultant oversells ERPbenefits
ERP Implementation continues- legacy system still in use inpocketsNo reduction in staff- in fact increase in some areas due toincreased data entry load
Only very limited drill down available due to different systems –legacy and ERP
Co
nse
q-
uen
ces
Information needs grow; delays in financial closure ofbooks;
ABC has the vision of becoming world class – - not sure ifthe information system is geared up for future needs.
At the end of 8 months :ERP project delays-project cost escalates
Many system difficulties encounteredSevere resistance to ERP best practices –reluctance to changeentrenched practices
Additional work load as ERP as well as legacy system workconcurrently.
Reconciliation problems continueVery low level of user acceptance
acti
on
/
decis
ion
s International consultant asked to study ABC’s IT strategy.Consultant recommends migration to an ERP system fromthe legacy system.
Decision to continue with implementation effortsDecision to revert back to the legacy system for Manufacturing
Conclusion: ERP Project is a failure: Decision: take stock andre-look at total project. A third party project audit was carried out.Findings: re-implement ERP ( newer version 11i) with a new
methodology/new implementation partner
2000 2001 and beyond
Even
ts
ERP 2 –Migration to Oracle 11i; The project charter simple
: goal of re-implementing Oracle 11iPresident takes ERP as personal KRA. Steering committeemeets at least once a month; Multi functional team with-
dedicated team- project led by CFO. Core users identified ;Project champion designated and empowered;Training – “ just in time” ;
Very limited customization – no new reports allowed unlesssanctioned by senior management. A system of notionaldebit of customization costs to the department budget
introduced as a disincentive.
Oracle 11i takes root
Very limited expectations from ERP ( due to earlier bad experience)
Users start to see value in an integrated system
Due to user teams having being full time –much greater understanding
of ERP screen navigation/work around etc.
ERP –Oracle 11i extended to other divisions of the company
The team that implemented the ERP system seen as experts and
extend services to other implementations in the company
Co
nse
qu
en
ces
Visible signs of change in attitudesGreater acceptance levels
Oracle goes live in 6 months
Complete shift from Legacy system; Much greater acceptance byusers;
MIS quality improves ;Greater usage of systems for decision making
Users acceptance of the new ways of working almost completeVisible benefits of ERP- reduction in staff (15 to 20% of
transaction processing staff reduced)Quicker turn round of inventory due to faster order to deliverycycles
Acti
on
/
Decis
ion
s Conclusion: ERP 2 Project is a Success: Decision : Management plans for the next level ofsystems extension to the extended supply chain. Also decides toroll out the ERP to all divisions of the company.
![Page 14: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/14.jpg)
87
4.5.1 Case 1: ERP 1 – Roll out of Oracle Apps 10.4
The same international consultant was engaged for implementation.
A project team headed by the IT head was constituted for the ERP project.
The in house team consisted of 3 full time IT resources, 5 user members (part
time- as departments could not spare resources full time). The consultant team
consisted of a project manager and 5 full time resources (2 technical
consultants and 3 functional consultants). A senior manager was appointed as
project champion.
The project was initiated with a formal “kick off” with the CEO
and top management team emphasizing the importance of the project. The
project followed the standard ERP implementation methodology involving:
(1) Definition (requirement analysis, scoping, creating work plan)
(2) Operational Analysis (Gap analysis, ‘As is’ and “To be” process design)
(3) Solutioning (detailed design, work-around plans) (3) Building
(parameterizing, coding, data migration, testing) (4) Transitioning and (5) Go
live. A steering committee consisting of the IT head as chair and departmental
heads as members was constituted. This committee was mandated to meet
once a month to review the project. Being themselves new to ERP and
perhaps as a means of securing the contract the consultant had raised the
expectations on what the ERP would do for the business. The scope of the
project, therefore, was ambitious (Table 4.2).
From the start ERP1 had problems. Top management showed great
interest at the start of the project but soon this interest started to wane with
competing pressures on everybody’s time. After the “kick off” meeting there
was no formal review of the project. The steering committee met for the first
two months – from the third meeting onwards the attendance for the meetings
started dwindling and altogether stopped after the fourth meeting.
![Page 15: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/15.jpg)
88
Table 4.2 Differences in project goals ERP1 and ERP 2
Goal/Scope ERP 1 ERP 2
Cost US $ X3 US $ Y
Time 9 months from start 6 months
Functionality Seamless integration of
Marketing, sales,
manufacturing, procurement,
inventory and financial
To move from Oracle
10.4 to Oracle 11i
Compliance with ABC ‘s
accounting policy
Use ERPs standard
reports as far as possible;
< 10 % custom reports.
Accuracy 100 % accuracy and timeliness
of business MIS
Nothing specified
Drill down
capability
Drill down capabilities up to
transaction level- “what if”
analysis capabilities
Nothing specified
Information quality Real-time information on
inventories, product
availability, pending orders,
sales, costs etc.
Nothing specified
Ease of use Simple screen navigation;
quick screen refresh (< 3
seconds.);
user-friendly reports .All
approvals of vouchers,
purchase orders online- work
flow to be created to match the
delegation of authority within
the company
Simple screen navigation
– as close to that of
current legacy system as
possible
Enable workflow as per
revised business
processes
Manpower
reduction
As a result of ERP – reduction
in staff of at least 15%
No manpower reduction
goal
3 Amount disguised to ensure confidentiality of commercially sensitive information
![Page 16: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/16.jpg)
89
User team members, not being full time, got busy with their day to
day work and saw the ERP project as an “additional burden”. In key areas, the
participation of user members was poor –the most dispensable junior was
often the choice for serving on the ERP team. This person neither had the
knowledge nor the authority to make process change decisions that were
required in configuring the ERP. There was a lot of resistance from users who
constantly compared the ERP with the existing system. A comment often
heard was:
“why are we spending so much for this (say an accounts
payable report) – our old system already gives it at the click of
a button- in the ERP we need to go through three screens to get
the report – and that too without all the details…”
Problems also started with “localization”- this refers to the ability
of the ERP to handle the country/region specific requirements of taxes/ levies
etc. The legacy system handled all of this perfectly but ERP always seemed a
step behind in addressing these. This necessitated work rounds which were
cumbersome. Another source of resistance to the ERP came from (a)
prevention of maverick behaviour and (b) perceived loss of power. We
explain these in the ensuing paragraphs.
(a) Maverick behaviour: in many operational areas, there were
informal (not officially authorized) practices. For example: purchasing often
asked suppliers to send material without formal purchase orders. These were
then “regularized” at the time of payment; similarly “sales” had a practice of
extending dispatches beyond the close of a period (say quarter or month) –
with predated invoices- to meet month end targets. These practices were
tacitly allowed by the departmental managers . As the ERP did not allow
![Page 17: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/17.jpg)
90
these, users who had been doing this for years resisted the change terming the
ERP as not being “user friendly” .
(b) Perceived Loss of power: ERP work flow changes resulted in
power shift between departments. In the legacy system bill passing was done
by the accounts department. As a best practice it was decided that the
complete accounts payable process would have the procurement department
as the “process owner”. as the ERP provided a robust “three way match”
(between invoice, goods receipt and purchase order) and also provided good
audit trails. This change was resisted by the accounts department who felt that
they had lost the power they had earlier exercised over vendors and the
procurement team by controlling the payment process. The procurement
department happily accepted the changed workflow as they saw the power
shift to them. This caused conflict between departments that manifested in
other areas also.
At the end of 9 months the ERP project costs had exceeded original
estimates of $X Million as hardware had to be upgraded, additional licenses
procured to take care of the revised workflows; non-standard reports/
customizations (to match legacy system functionalities) required additional 12
man months of work. New estimates of cost were twice the original estimate.
The “go –live” happened after 14 months of start. During the first
two weeks there was total chaos. The legacy system had been switched off but
ERP processes still had glitches. Dispatches were delayed as inventory data
was inaccurate. Manufacturing systems were difficult to use. Improperly
trained users could not handle the screens on their own. IT staff and
consultants were running from one user to the other to trouble shoot/train/
help. Customers started complaining of wrong /delayed deliveries.
![Page 18: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/18.jpg)
91
With no other alternative it was decided to switch back the legacy
at least for key “show stopper” processes .The consultant was asked to extend
their contract by another six months. After 24 months the conclusion was that
the ERP project was a failure. ERP was running but in many of the business
processes the legacy system was still continuing in parallel. There was
dissatisfaction at all levels in the company. Commenting on the state of
affairs, a senior manager from accounts put it best. To quote him:
“We had a good reasonably good legacy system... we were told
that the ERP would solve all problems and take us take to the
next level … now after more than a year and a half we find the
ERP is way below our legacy system, and we are putting
efforts to bring it up to our legacy level .. If only we had spent
half the amount of time and money and upgraded the legacy
system we would have been much better…....”
Table 4.3 gives the planned versus actual benefits derived from
ERP 1. The conclusion was that even at this late stage, ABC should consider
abandoning the ERP project and focus on improving the legacy system to
bridge the gaps. This feeling was shared by quite a few other managers. The
company continued with this hybrid solution for another year or so before
deciding to take a complete relook at the whole ERP implementation. By now
Oracle had come out with an upgraded version 11i and this was a good
opportunity to do a reimplementation.
![Page 19: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/19.jpg)
92
Table 4.3 Planned versus Actual benefits of ERP1
Expectations of benefit Practical difficulty Actual benefit
Top Management will be
able to “drill down” to
transaction level
Facility would work only
if all modules
implemented and
perfectly integrated
Very limited drill down
possible. Reports had to
be generated out of the
ERP with Excel –Users
felt that there was no
additional benefit from
ERP
Manpower reduction
(hence cost) would be
reduced to 20% extent
Additional data entry
load and unfamiliar
screen navigation
required additional staff
(ERP forms had many
more fields to be
entered)
No reduction – in fact in
some cases additional
staff was needed to take
care of increased data
entry load.
Users will get reports as
needed
ERP reports looked
different from those they
were familiar with –
standard ERP reports had
a different “look and
feel”
Users found reports to be
cumbersome to use
3 sec screen refresh Due to wrong sizing and
network overload –
system slowed down
considerably.
Screen refresh took a long
time ( 5 -10 seconds)
Additional investments in
upgrading server/memory
were seen as additional
unbudgeted costs
Best practices would be
introduced
Best practices not
acceptable to users as
they were different from
prevailing practices
Users were not familiar
with online approval of
documents and needed
hard copies.
Users felt system was not
“user friendly”
Many easy work practices
in the legacy were
replaced with seemingly
complex steps in the ERP.
Go –live in 9 months Actual go-live after 14
months – stabilization
after 24 months
Huge time and cost
overrun
![Page 20: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/20.jpg)
93
4.5.2 Case 2: ERP 2 - Re-implementation of Oracle Apps 11 i
ERP2, the reimplementation project, was handled very differently.
A post completion audit was conducted to analyze the causes of ERP1 failure.
A causal analysis identified the key causal factors that led to the problem:
Lack of visible management advocacy, inadequate process monitoring and
control and resistance to change from the current way of working came out as
the key reasons. In addition it was felt that the goals of the ERP were
unrealistic and that the implementation consultants had unnecessarily raised
expectations among the users.
Following this analysis the management took up ERP2 with the
following differences in approach:
1. The project goal was simple and realistic (Table 4.2). The key
goal was moving from Oracle 10.4 to Oracle 11i smoothly.
2. Top management decided to demonstrate commitment through
visible actions: (1) The President took the ERP implementation
as his personal Key Result Area (KRA). (2) The CFO was
made as the ERP project manager with the IT department
playing a supportive role. (3) The steering committee, with the
CFO as the chair met every month without fail. During the
initial and final phases the meeting frequency was increased to
once a fortnight.
3. A full time user team, relieved of all other duties, was created
(unlike in ERP1 where the user team worked on the project
part-time). A set of core users per module were identified and
given intensive training. Other users were trained “just in time”
- just before they were expected to use a module. (Note: In ERP
1, training was given well ahead of use. When the module was
![Page 21: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/21.jpg)
94
ready (about 4 to 6 months down the line) to be used most
users had forgotten all that they had learnt).
4. A systematic BPR exercise, led by an expert consultant
involving all, preceded the new implementation. Special care
was taken to address the change management issues. In each
department opinion leaders were identified and tasked with
championing the revised work methods and flows. The issues
of power loss that were felt earlier in ERP 1 were much less as
new work flows had been in place for a year and users had got
used to the new power structures. Moreover through change
management interventions, these issues were tackled as and
when they arose.
5. Wherever possible, attempts were made to integrate legacy data
entry screens into the ERP using Application Program
Interfaces (APIs). This gave the users the comfort of familiar
legacy interfaces while at the same time not diluting the
integrity of the ERP.
Results: Within 6 months the ERP2 went on stream. The “go-live”
was relatively smooth and trouble free. As the users were trained just in time,
they were fresh and very little hand holding was needed. The “core users”
team became a very valuable resource and was able to solve most of the
operational issues. The quality of the MIS improved. With all systems under
ERP, drill down became possible to a large extent. As the expectations were
quite low to begin with, the results exceeded expectations.
The ERP stabilized soon and within the next 12 months the same
was well entrenched in the company. ERP2 was a success. Following this
success the company decided to roll out the ERP to other divisions of the
company.
![Page 22: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/22.jpg)
95
4.6 DISCUSSION, ANALYSIS AND RESULTS
The cases were chosen primarily to illustrate how a change in
operationalizing certain critical success factors brought about a change in
outcome of the ERP project from failure to success. As the organization
remains the same, the ERP is the same and user groups largely remain the
same, it is the different operationalization of the CSFs that has made the
difference. We now discuss the similarities and differences in the two cases
and draw inferences for research and practice.
4.6.1 Case Study Findings – Similarities
Both projects followed the same standard methodology used by
implementation consultants
The ERP package- Oracle Applications, in both cases is the same –
the only difference being the versions -10.4 in the first case and 11i in the
second case. Both cases followed the standard ERP implementation
methodology which involves (1) Definition (scoping, creating work plan) (2)
Operational Analysis (Gap analysis, ‘As is’ and “To be” process design) (3)
Solutioning (detailed design, work-around plans) (3) Build (parameterizing,
coding, data migration, testing) (4) Transitioning and Go live. (see Appendix
5 for the standard AIM methodology used by Oracle)
There is no significant change in top management, users, technical
team between the two projects
Top management in the two cases remains largely the same. The
user community also is largely the same. The technical team for the
implementation from the company’s side was the same. The implementation
partner was different-but both being internationally known firms with
![Page 23: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/23.jpg)
96
established systems, templates and practices we do not see this as a major
differentiating factor.
Top management support, project champion, a priori BPR
(considered as important CSFs) were present in both the projects (at least on
paper at the surface level)
Top management support was understood to be important in both
cases. Both projects started out with a letter from the CEO on the importance
of the project. Steering committees were constituted in both cases. A project
champion was appointed; user teams were constituted and trained. A BPR
exercise was carried out and revised work flows mapped. It must be noted that
at the surface level all the key CSFs appear to have been complied with. We
show in the next section that it is the differences in the manner in which these
are operationalized that seemed to have made the difference in the outcome.
4.6.2 Case Study Findings – Differences
ERP 2 had a much smaller scope and realistic goal when compared
to ERP 1
A key difference is in the scope of the project. While ERP 1 had
very ambitious goals ERP 2 had a much smaller scope, the key goal being the
smooth transition from version 10.4 to 11i (see Table 4.2 for the differences
in scope between the two projects). This goal was understood by all and
accepted as the only benefit to be expected from the ERP.
Top Management support was visible, overt and continued
throughout the course of the project
Although in both cases top management support was available,
there was also a critical difference. In ERP 1 after the initial letter from CEO
![Page 24: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/24.jpg)
97
and the kick-off meeting top management’s attention appeared to have waned.
In ERP 2 however, the president himself took ERP implementation as his
personal KRA. At every occasion the senior management would reemphasize
the importance of ERP. In business review meetings the status of ERP
implementation was the first agenda point. Resources in terms of personnel
(releasing best people from each functional area as full time team members),
additional computer hardware (new terminals, additional RAM memory etc.),
additional training, and visits to other successful sites were sanctioned by top
management.
Unlike in ERP 1 where the IT head was the ERP project manager,
in ERP 2 a senior line manager (the CFO) was made the ERP project head.
This person was very senior in the company, had the authority to sanction
business process changes and had a personal stake in a successful
implementation as his functional area would be the biggest user of the ERP
system.
Importance of the change management and BPR activities
In ERP 2 great care was taken to ensure that the reengineering
efforts had the “buy in” of large sections of the users. This was done through
several rounds of discussions involving all levels of employees, addressing
genuine concerns, allaying fears of loss of power, and above all constant
reinforcing communication. The opinion leaders played a crucial role
throughout the process. A process based structure (as against a function based
structure) with appropriate changes in goals (process goals against department
goals), appropriate changes in compensation structures (rewards on
achievement of group goals) etc. were incorporated.
The ERP with the revised work flows was rolled out only after a
reasonable comfort level on the new ways of working was achieved. In
![Page 25: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/25.jpg)
98
several instances legacy screens were integrated into the ERP to give the users
the comfort of familiar screens.
Project monitoring and control
In ERP 2 the steering actively monitored the project without let up
till the completion of two months after go-live. As the CFO was the project
head (and also the steering committee chair) he was able to ensure full
participation of all the other steering committee members unlike in ERP 1
where the steering committee chair was the IT head who was not as senior in
the organization as the CFO.
A fully functioning steering committee was able to take crucial
decisions on funds allocation, changing work flows as needed and could limit
the extent of customizations in ERP 2 unlike in ERP 1 where there was very
little control on customizations. A disincentive for customization was
introduced by creating a notional debit (to a department’s budget) based on
customization man-days.
Creative use of legacy system
In ERP 1 on “go-live” the legacy system was switched off. This
created havoc and affected dispatches to customers forcing the company to
run the legacy in parallel. In ERP 2 a different strategy was adopted. A hybrid
strategy of introducing the ERP while retaining some crucial legacy screens
was adopted. The APIs available in the ERP were used to ensure that legacy
system data was sent to the appropriate ERP tables. As users got familiar with
the ERP slowly these legacy systems were phased out. The resistance from
users was thus creatively addressed.
![Page 26: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/26.jpg)
99
4.7 HYPOTHESIS TESTING
We had hypothesized: H 1 - High expectations negatively impact
ERP success
Analysis of the cases shows that there were clearly different
expectations from ERP 1 and ERP 2 among the users. In the first
implementation, being new to ERP practice, the consultant inadvertently
raised expectations to a very high degree. For example, detailed “drill down”
capability, reduction in manpower of 20%, 3 second screen response, best
practices introduction were promised (Table 4.3). The actual results for ERP
fell far short.
Result: A large gap between expectations and actual delivery
leading to expectations-disconfirmation and thereby dissatisfaction.
In contrast in ERP 2 everybody including the consultant was wiser.
Coming after a disastrous implementation, the organization went into ERP2
project with little or no expectations. The ERP 2 scope was simple- the key
goal being migration to the latest version Oracle 11i. Furthermore, the users
had “zero” expectations from ERP due to their bad experiences in the past. As
one user succinctly put it
“… anyway the new ERP can’t be worse than the earlier one,
nothing can be worse … as long as it makes my work a little
easier I am satisfied”.
Result: ERP 2 was perceived as a successful implementation by
most users – compared to the failed implementation of ERP1.
We conducted a small empirical study, using a Likert scale with
anchor values of 7= completely agree and 1= completely disagree among a
sample of ten users drawn from diverse areas: Strategic users, operational
![Page 27: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/27.jpg)
100
users and technical users. The results show a marked improvement
(Table 4.4) in satisfaction levels with ERP 2 compared to ERP 1 confirming
our hypothesis that high expectations negatively impact user satisfaction and
conversely low expectations positively impacts user satisfaction.
The next hypothesis H2: Top management support would be seen
as real only if it is manifest in specific actions and sustained throughout the
project.
We next analyze the differences in the nature of top management
support in the two projects. The key difference between the two
implementations with reference to top management support is in actual
actions of management. Although both the projects appear to have the
support of top management in ERP 1 the support was in form only while in
ERP such support was actually manifest in affirmative action (see discussions
on the differences between implementations). This fact is sensed by the users
and the nature of resistance to the ERP therefore varies in the two projects.
The empirical study also shows that the user’s perceptions of top management
involvement in ERP2 is substantially higher (Table 4.4).
Conclusion: Top Management Support is perceived to be real only
if accompanied by actions. Some typical actions that seem to make the
difference are: The president declaring the ERP project as his personal KRA,
visible use of systems by top management, ensuring that the steering
committee functions, allocation of full time resources, empowering the
project champion etc. The evidence of the cases supports the hypothesis.
The next hypothesis: H3: A strong and well entrenched legacy
system negatively influences the adoption of an ERP system
The company had a well entrenched legacy system. The legacy
system incorporated the current practices in the company – and conversely the
![Page 28: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/28.jpg)
101
legacy system practices became the company preferred practices – the ERP
best practices therefore encountered resistance. The legacy system allowed
some amount of “bending” of system – for example the predating of invoices
– which the ERP did not allow. By the time ERP 2 was in place, the legacy
system influence was reduced as in many areas ERP 1 practices had taken
root (Table 4.4). Moreover the change management exercise addressed many
of the issues of power balancing and revised roles and responsibilities.
Conclusion: The facts of the case support the hypothesis that a well
entrenched legacy system negatively influences ERP adoption – only when
legacy system influences are reduced do the ERP best practices gain
acceptance.
Table 4.4 Results of empirical study
(10 respondents diverse stakeholder group)
User cohort (Nos.) ERP 1 ERP 2 Remarks
Q1 :Overall I am satisfied with the ERP that has been implemented
in our organization
Strategic Users (2) 4, 4(*) 6,5
Operational Users (4) 3,2,3,3 5,6,6,5
Technical Users (4) 2,1,2,2 6,7,6,6
Marked shift in
satisfaction levels –
especially among
operational users
Q2: The top management was actively involved and supported the
ERP project from start to finish
Strategic Users(2) 5,5 6,6
Operational Users (4) 2,1,1,1 7,6,6,7
Technical Users (4) 2,2,2,2 6,7,7,7
Major change in
perception about
Top management in
ERP 2
Q3: A steering committee was formed which met at least once a month,
monitored progress and initiated corrective actions in case of any
Strategic Users(2) 3,2 6,6
Operational Users (4) 1,1,1,1 7,7,7,7
Technical Users (4) 2,2,2,2 6,7,6,7
Steering committee
was seen to be
functioning very
well in ERP 2.
![Page 29: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/29.jpg)
102
Table 4.4 (Continued)
User cohort (Nos.) ERP 1 ERP 2 Remarks
Q4: There was a project champion who led the project throughout by
providing guidance / building consensus /solving issues
Strategic Users(2) 5,5 6,6
Operational Users (4) 2,1,1,1 7,6,6,7
Technical Users (4) 2,2,2,2 6,7,7,7
Project champion
was appointed but
not empowered in
ERP 1
Q5: The ERP helps me do my job better when compared to the old (legacy)
system.
Strategic Users(2) 2,3 6,6
Operational Users (4) 1,1,1,1 6,6,6,7
Technical Users (4) 3,232,2 6,5,4,6
Legacy system
influence reduced by
the time of ERP 2
(*) responses measured on a Likert Scale: completely agree=7 to completely disagree =1
4.8 IMPLICATIONS
4.8.1 Implications for Practice
In the practice area, management is advised to take care in the
scoping and goal setting process of an ERP implementation. Simple
achievable goals facilitates acceptance. The overall feel-good factor that
follows from achievement of expected goals will allow the management to
push its larger agenda for more fundamental process changes. It is better to
undersell ERP than oversell it. It gets accepted better.
Top Management has a pivotal role in ERP success. This role is
both symbolic as well as substantive. Symbolically top management should
be seen to own the project- as in the case of ERP 2 where the president of the
company takes ERP implementation as his personal Key Result Area (KRA).
Substantively top management has to ensure that best resources are made
available to the project - this means dedicated user teams for the duration of
![Page 30: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/30.jpg)
103
the project, quality time for reviews, funds as needed for up gradation of
computer infrastructure etc.
The role of good project management cannot be reemphasized. A
senior line manager as ERP project head is most desirable. A functioning
steering committee that “steers” the project throughout its course is vital for
success. The steering committee has a key role in addressing issues that are
bound to come up quickly and decisively. An important decision involves
customization a major cause of cost and time delays. Users must be
encouraged to use ERP standard practices and reports. At ABC Corporation a
disincentive for customization was created. A notional cost debit (based on
estimated man days) was made to a department’s budget for every
customization request. This worked in curbing customizations.
4.8.2 Implications for Research
Our study extends the work of Parr and Shanks (2000). It follows a
similar two case methodology of an unsuccessful implementation followed by
a successful one in a new and important ERP market-India. It establishes the
value of scientific case studies in drawing important lessons for research and
practice. It differs from the work of Parr and Shanks in that the two
implementations are in the same organization separated in time. Thus it is
closer to a controlled experiment when compared to the earlier work. Further
it explores the effect of one of the key CSFs at the planning stage, the scoping
process. This was not covered in depth in the earlier research which primarily
focused on the implementation stage.
Our research has identified some key constructs that seem to impact
ERP implementation outcomes. For example, we have shown that top
management support is actually a composite of several other CSFs like full
time user teams allocation, personal example, empowering a champion etc.
![Page 31: CHAPTER 4 CASE STUDY –LEARNING FROM FAILUREshodhganga.inflibnet.ac.in/bitstream/10603/9902/9/09_chapter 4.pdfa two case methodology of a failed ERP implementation in one organization](https://reader034.fdocuments.us/reader034/viewer/2022042211/5eb1c39da84f433961342493/html5/thumbnails/31.jpg)
104
All these together constitute a latent construct which could be called
Leadership the dimensions of which exceed what is generally understood as
top management support. Similarly all the other issues of managing the
implementation process like scope management, change management etc.,
would map to another latent construct –Process. These constructs represent
better ways of classifying the CSFs and future research could develop
measurement scales for these which could be used as predictive ex ante
indicators for ERP outcomes.
Our research had some limitations. The events of the case happened
at a time when ERP and computerization were in their infancy in India.
Perhaps with time and greater familiarity some of the issues that impacted the
project may not be as relevant today as it was then. But we believe the
learning is still relevant.