Chapter 4 - 2_Time Value of Money Part II(1)
-
Upload
shogo-bernardo-okada -
Category
Documents
-
view
218 -
download
0
Transcript of Chapter 4 - 2_Time Value of Money Part II(1)
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
1/42
Chapter 4 Part II
The Time Value of Money - Part II
Instructor: Joonyup Eun
1 Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
2/42
Contents
2
A Uniform Series (Annuity) to Its Present and FutureEquivalent Values
Deferred Annuities (Uniform Series)
Equivalence Calculations Involving Multiple Interest
Formulas
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
3/42
3
A Uniform Series
(Annuity) to Its Presentand Future Equivalent
Values
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
4/42
Definition of Annuity
4
An annuity is a series of equal (uniform) cash flowsoccurring at fixed time intervals.
The first cash flow occurs at the end of the first period.
The last cash flow occurs at the end of the last period
0 1 2 3 N-1 N
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
5/42
PreliminaryGeometric Series
5
Lets define , , , , , =
Calculate
1 1 1
1
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
6/42
Finding F when Given A
6
0 1 2 3 N-1 N
1
1
1 1
Find the future equivalent at the end ofth period of anannuity, a series of.
1 1 1 1 1 1
1 1 1 1
=
1
1
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
7/42
Finding F when Given A
7
Let ,%, +
. Then
1 1
, %, Example:
Interest at 8% per year
Receiving $502 each year for the next 3 years.
0 1 2 3 8%
$502 $502 $502 ?
+ 502+.
. 1629.693 , %, 502 ,8%,3 502 3.2464 1629.693
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
8/42
Finding P when Given A
8
Find the present equivalent of an annuity, a series of.
0 1 2 3 N-1 N
1 1
1
1 ()
1
1 1 1 1 1 1 1 1
1 1
1 1
1
=
1
1
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
9/42
Finding P when Given A
9
Let ,%, +
+ . Then , %,
Example:
Interest at 8% per year Receiving $502 each year for the next 3 years.
0 1 2 3 8%
$502 $502 $502 ?
+ + 502+. . . 1293.703
, %, 502 , 8%, 3 502 2.5771 1293.704Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
10/42
Relationship between and
10
, %, 1293.703 1629.693 , 8%, 3 1629.693 0.7938 1293.703 , %, , %, , %, , %, , %, , %, , %, , %,
+ +
+
+
+ +
0 1 2 3
8%
$502 $502 $502 1293.703
1629.693
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
11/42
Finding A when Given F
11
+
+ Let , %, + , Then , %, Example: You need $1,000,000 ten years later. You will make 10
yearly deposits in a saving account at the end of each year. The
interest rate is 5% per year. How much money you need to pay
every year?
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
12/42
Finding A when Given F
12
Example: You need $1,000,000 ten years later. You will make 10yearly deposits in a saving account at the end of each year. The
interest rate is 5% per year. How much money you need to
pay every year?
0 1 2 3 9 10 5%
1,000,000
, %, 1,000,000 ,5%,10 1,000,000 0.0795 79,500
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
13/42
Finding A when Given P
13
+
+ +
+
Let , %, + + , then , %, Example: You plan to borrow a loan of $100,000 which you will
repay with equal annual payments for the next 5 years.
Suppose the interest rate you are charged is 8% per year and
you will make the first payment one year after receiving the
loan. How much is your annual payment?
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
14/42
Finding A when Given P
14
Example: You plan to borrow a loan of $100,000 which you will
repay with equal annual payments for the next 5 years.
Suppose the interest rate you are charged is 8% per year and
you will make the first payment one year after receiving the
loan. How much is your annual payment?
0 1 2 3 4 5
$100,000
8%
, %, 100,000 , 8%, 5 100,0000.2505 25,050
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
15/42
Other consideration
15
For the problems that Finding the number of cash flows in an Annuity Given A,P and I
Example
Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
0 1 2 3 N-1 N? 5%
1,000
1,000,000
1,000,000 1,000 , 5%, 1,000 +. . +. N?
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
16/42
16 Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
For the problems that Finding the interest rate I, Given A, F and N
Example
Other consideration
0 1 2 3 49 50 ?
1,000
1,000,000
1,000,000 1,000 ,%,50 1,000 + ?
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
17/42
17 Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
Other consideration
For the problems that Finding the interest rate I, Given A, F and N
Finding the number of cash flows in an Annuity Given A,P and I
No closed form (analytical) solution is known.
We can solve these problems numerically.
Please refer to Excel help session.
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
18/42
18
Example
Annual interest rate is
10%. You have 3 plans to pay the balance back.
Plan 1: Pay interest, $1,000, due at end of each year and principal, $10,000,at end of third year. PV= FV=
Plan 2: Pay principal and interest, $13,310, in one payment at the end ofthird year PV= FV=
Plan 3: Pay off the debt in 3 equal end-of-year payments of$4,021PV= FV=
0 1 2 3 10%
$10,000
$1,000 $1,000 $1,000
Plan 1 1000 , 10%, 3 10,000 , 10%, 3 10,000
?Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
19/42
19
Example
Annual interest rate is
10%. You have 3 plans to pay the balance back.
Plan 1: Pay interest, $1,000, due at end of each year and principal, $10,000,at end of third year. PV=10,000 FV=
Plan 2: Pay principal and interest, $13,310, in one payment at the end ofthird year PV= FV=
Plan 3: Pay off the debt in 3 equal end-of-year payments of$4,021PV= FV=
0 1 2 3 10%
$10,000
$1,000 $1,000 $1,000
Plan 1 1000 ,10%,3 10,000 13,310
?Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
20/42
20
Example
Annual interest rate is
10%. You have 3 plans to pay the balance back.
Plan 1: Pay interest, $1,000, due at end of each year and principal, $10,000,at end of third year. PV=10,000 FV=13,310
Plan 2: Pay principal and interest, $13,310, in one payment at the end ofthird year PV= FV=
Plan 3: Pay off the debt in 3 equal end-of-year payments of$4,021PV= FV=Plan 2 13,310 ,10%,3 10,000
0 1 2 3 10%
$13,310 ?Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
21/42
21
Example
Annual interest rate is
10%. You have 3 plans to pay the balance back.
Plan 1: Pay interest, $1,000, due at end of each year and principal, $10,000,at end of third year. PV=10,000 FV=13,310
Plan 2: Pay principal and interest, $13,310, in one payment at the end ofthird year PV=10,000 FV=
Plan 3: Pay off the debt in 3 equal end-of-year payments of$4,021PV= FV=Plan 2 13,310
0 1 2 3 10%
$13,310 ?Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
22/42
22
Example
Annual interest rate is
10%. You have 3 plans to pay the balance back.
Plan 1: Pay interest, $1,000, due at end of each year and principal, $10,000,at end of third year. PV=10,000 FV=13,310
Plan 2: Pay principal and interest, $13,310, in one payment at the end ofthird year PV=10,000 FV=13,310
Plan 3: Pay off the debt in 3 equal end-of-year payments of$4,021PV= FV=Plan 3
0 1 2 3 10%
$4,021 $4,021 $4,021
4,021 ,10%,3 10,000
?Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
23/42
23
Example
Annual interest rate is
10%. You have 3 plans to pay the balance back.
Plan 1: Pay interest, $1,000, due at end of each year and principal, $10,000,at end of third year. PV=10,000 FV=13,310
Plan 2: Pay principal and interest, $13,310, in one payment at the end ofthird year PV=10,000 FV=13,310
Plan 3: Pay off the debt in 3 equal end-of-year payments of$4,021PV=10,000 FV=Plan 3
0 1 2 3 10%
$4,021 $4,021 $4,021
4,021 ,10%,3 13,310
?Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
24/42
24
Example
Annual interest rate is
10%. You have 3 plans to pay the balance back.
Plan 1: Pay interest, $1,000, due at end of each year and principal, $10,000,at end of third year. PV=10,000 FV=13,310
Plan 2: Pay principal and interest, $13,310, in one payment at the end ofthird year PV=10,000 FV=13,310
Plan 3: Pay off the debt in 3 equal end-of-year payments of$4,021PV=10,000 FV=13,310
All three plans are economically equivalent.
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
25/42
25
Example
You are analyzing a project with 5-year life. The project requires a
capital investment of $50,000 now, and it will generate uniform
annual revenue of $6,000 at the end of each year. Further, the
project will have a salvage value of $4,500 at the end of the fifth year
and it will require $3,000 each year for the operation. Appropriate
interest rate is 10%. What is the PV?
0 1 2 3 4 5
50,0006,000 , 10%, 5 3,000 ,10%,5 4,500 ,10%,5 35,833.49
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
26/42
26
Example
You are analyzing a project with 5-year life. The project requires a
capital investment of $50,000 now, and it will generate uniform
annual revenue of $6,000 at the end of each year. Further, the
project will have a salvage value of $4,500 at the end of the fifth year
and it will require $3,000 each year for the operation. Appropriate
interest rate is 10%. What is the FV?
0 1 2 3 4 5
$50,000
$6,000 $6,000 $6,000 $6,000 $6,000
$3,000 $3,000 $3,000 $3,000 $3,000
$4500
50,000 , 10%, 5 6,000 ,10%,5 3,000 ,10%,5 4,500 57,710.20
10% ?Purdue School of Industrial Engineering -
Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
27/42
27
Example
You are analyzing a project with 5-year life. The project requires a
capital investment of $50,000 now, and it will generate uniform
annual revenue of $6,000 at the end of each year. Further, the
project will have a salvage value of $4,500 at the end of the fifth year
and it will require $3,000 each year for the operation. Appropriate
interest rate is 10%. What is the PV?
0 1 2 3 4 5
50,0003,000 , 10%, 4 7,500 ,10%,5 35,833.49
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
28/42
28
Example
You are analyzing a project with 5-year life. The project requires a
capital investment of $50,000 now, and it will generate uniform
annual revenue of $6,000 at the end of each year. Further, the
project will have a salvage value of $4,500 at the end of the fifth year
and it will require $3,000 each year for the operation. Appropriate
interest rate is 10%. What is the FV?
0 1 2 3 4 5
$50,000
$3,000 $3,000$3,000 $3,000$7,500
10%
50,000 , 10%, 5 3,000 ,10%,4 7,500
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
29/42
29
Example
You are analyzing a project with 5-year life. The project requires a
capital investment of $50,000 now, and it will generate uniform
annual revenue of $6,000 at the end of each year. Further, the
project will have a salvage value of $4,500 at the end of the fifth year
and it will require $3,000 each year for the operation. Appropriate
interest rate is 10%. What is the FV?
0 1 2 3 4 5
$50,000
$3,000 $3,000$3,000 $3,000$7,500
10%
50,000 , 10%, 5 3,000 ,10%,4 7,500 ,10%,1 57,710.20
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
30/42
30
Example
You are analyzing a project with 5-year life. The project requires a
capital investment of $50,000 now, and it will generate uniform
annual revenue of $6,000 at the end of each year. Further, the
project will have a salvage value of $4,500 at the end of the fifth year
and it will require $3,000 each year for the operation. Appropriate
interest rate is 10%. What is the FV?
0 1 2 3 4 5
$50,000
$3,000 $3,000$3,000 $3,000
10%
$4500$3,000
50,000 , 10%, 5 3,000 ,10%,5 4,500 57,710.20
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
31/42
31
Deferred Annuities(Uniform Series)
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
32/42
Deferred Annuities
32
Annuity series where the first of the uniform cash flows
occurs at the end of period J+1 instead of at the end of
period 1 and there are N-J such cash flows.
Ordinary Annuities
Deferred Annuities
0 2 4 6
1 3 5
N-4 N-2 N
N-5 N-3 N-1
0 2 4 61 3 5 J+1 N
J J+2 N-1
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
33/42
Present Value of Deferred Annuities
33
, %, , %,
, %, , %,
0 2 4 61 3 5 J+1 N
J J+2 N-1
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
34/42
Example
34
A father, on the day his son is born, wishes to determine what
lump amount would have to be paid into an account bearing
interest of 12% per year to provide withdrawals of $2,000 on
each of the sons 18th, 19th, 20th, and 21st birthdays.
0 2 4 61 3 5 18 2117 19 20
2,000 2,000
12%
2000 , 12%, 4 6,074.60 ,12%,17 6,074.600.1456 884.46
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
35/42
Future Value of Deferred Annuities
35
, %,
0 2 4 61 3 5 J+1 N
J J+2 N-1
?
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
36/42
Deferred Future Value of Annuities
36
, %, , %,
, %, , %,
0 2 J-1 J+11 J N
N-1
?
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
37/42
Example
37
When you take your first job, you decide to start saving right away for
your retirement. You put $5,000 per year into the companys 401(k)plan, which averages 8% interest per year. Five years later, you move to
another job and start a new 401(k) plan. You never get around to
merging the funds in the two plans. If the first plan continued to earn
interest at the rate of 8% per year for 35 years after you stopped
making contributions, how much is the account worth?
0 2 4 61 3 5 18 4017 19 39
5,000 5,000 8%
? ? 5,000 ,8%,5 5,0005.8666 $29,333.3 , 8%, 35 29,333.3 14.7853 $433,697
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
$433,697 in the account
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
38/42
38
Equivalence Calculations
Involving Multiple InterestFormulas
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
39/42
Example
39
The present equivalent expenditure The future equivalent expenditure
The annual equivalent expenditure
0 2 4 61 3 5 87 20%$100
$200$500
$400 $400 $400 $400 $400
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
40/42
Example (Present equivalent expenditure )
40
0 2 4 61 3 5 87 20%$100
$200$500
$400 $400 $400 $400 $400
100 , 20%, 1 200 , 20%, 2 500 , 20%, 3 400 ,20%,5
83.33
138.88
289.35
692.26
1,203.82 ,20%,3
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
41/42
41
Example (Future equivalent expenditure )0 2 4 61 3 5 87 20%
$100$200
$500$400 $400 $400 $400 $400
100 , 20%, 7 200 ,20%,6 500 , 20%, 5 400 , 20%, 5 , 20%, 8 5,176.19
1,203.82
1,203.82 4.2998
Purdue School of Industrial Engineering -Fall 2013, IE343 Engineering Economics
-
7/29/2019 Chapter 4 - 2_Time Value of Money Part II(1)
42/42
Example (Annual equivalent expenditure )0 2 4 61 3 5 87 20%
$100 $200
$500$400 $400 $400 $400 $400
1,203.82
, 20%, 8 1,203.82 0.2606 313.73
5,176.19
, 20%, 8 5,176.19 0.0606 313.73
?