Transcript of Chapter 3 : Managing the Information Systems Project
![Page 1: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/1.jpg)
Chapter 3 : Managing the Information Systems Project
![Page 2: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/2.jpg)
Objectives:
Explain the process of managing an information systems project.
Describe the skills required to be an effective project manager.
List project management activities during project initiation, planning, execution, and closedown.
Explain critical path scheduling, Gantt charts, and Network diagrams.
Explain the utility of commercial project management software tools.
![Page 3: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/3.jpg)
Importance of Project Management
Project management may be the most important aspect of systems development.
Effective Project Management helps ensure
•Meeting customer expectations
•Satisfying budget and time constraints Project Management skills are difficult and
important to learn.
![Page 4: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/4.jpg)
Pine Valley Application Project
![Page 5: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/5.jpg)
Deciding on Systems Projects
System Service Request (SSR) A standard form for requesting or proposing
systems development work within an organization
Feasibility study A study that determines whether a requested
system makes economic and operational sense for an organization
![Page 6: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/6.jpg)
System Service Request (SSR)
System Service Request (SSR) is a form requesting development or maintenance of an information system. It includes the contact person, a problem statement, a service request statement, and liaison contact information
![Page 7: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/7.jpg)
Managing the Information Systems Project
Project A planned undertaking of related activities to
reach an objective that has a beginning and an end
Project management A controlled process of initiating, planning,
executing, and closing down a projectProject manager Systems analyst with management and
leadership skills responsible for leading project initiation, planning, execution, and closedown
Deliverable The end product of an SDLC phase
![Page 8: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/8.jpg)
![Page 9: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/9.jpg)
Phases of Project Management Process
Phase 1: InitiationPhase 2: PlanningPhase 3: ExecutionPhase 4: Closedown
![Page 10: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/10.jpg)
Project Initiation
Assess size, scope and complexity, and establish procedures.
Establish:
• Initiation team
•Relationship with customer
•Project initiation plan
•Management procedures
•Project management environment
•Project workbook
![Page 11: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/11.jpg)
Project Planning
Define clear, discrete activities and the work needed to complete each activity
Tasks• Define project scope, alternatives, feasibility• Divide project into tasks• Estimate resource requirements• Develop preliminary schedule• Develop communication plan• Determine standards and procedures• Risk identification and assessment• Create preliminary budget• Develop a statement of work• Set baseline project plan
![Page 12: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/12.jpg)
Planning Detail
![Page 13: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/13.jpg)
Some Components of Project Planning
Statement of Work (SOW) “Contract” between the IS staff and the
customer regarding deliverables and time estimates for a system development project
The Baseline Project Plan (BPP) Contains estimates of scope, benefits,
schedules, costs, risks, and resource requirements
Preliminary Budget Cost-benefit analysis outlining planned
expenses and revenues
![Page 14: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/14.jpg)
Some Components of Project Planning
Work Breakdown Structure (WBS) Division of project into manageable and
logically ordered tasks and subtasks
Scheduling Diagrams Gantt chart: horizontal bars represent task
durations Network diagram: boxes and links represent
task dependencies
![Page 15: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/15.jpg)
Scheduling Diagrams Gantt Chart
Special-purpose project management software is available for this.
![Page 16: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/16.jpg)
Scheduling Diagrams Network Diagram
![Page 17: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/17.jpg)
Preliminary Budget
![Page 18: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/18.jpg)
Project Execution
Plans created in prior phases are put into action.
Actions
•Execute baseline project plan
•Monitor progress against baseline plan
•Manage changes in baseline plan
•Maintain project workbook
•Communicate project status
![Page 19: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/19.jpg)
Monitoring Progress with a Gantt Chart
![Page 20: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/20.jpg)
Communication Methods
Project workbook Meetings Seminars and workshops Newsletters Status reports Specification documents Minutes of meetings Bulletin boards Memos Brown bag lunches Hallway discussions
![Page 21: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/21.jpg)
Project Closedown
Bring the project to an end. Actions
•Close down the project.
•Conduct post-project reviews.
•Close the customer contract.
![Page 22: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/22.jpg)
Representing and Scheduling Project Plans
Gantt Charts Network Diagrams PERT Calculations Critical Path Scheduling Project Management Software
![Page 23: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/23.jpg)
Gantt Charts vs. Network Diagrams
Gantt charts
•Show task durations.
•Show time overlap.
Network diagrams
•Show task dependencies.
•Do not show time overlap, but show parallelism.
![Page 24: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/24.jpg)
Estimating Task Duration
PERT: Program Evaluation Review Technique
Technique that uses optimistic (o), pessimistic (p), and realistic (r) time estimates to determine expected task duration
Formula for Estimated Time:
•ET = (o + 4r + p)/6
![Page 25: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/25.jpg)
Example PERT Analysis
![Page 26: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/26.jpg)
Critical Path Analysis
Critical path method (CPM)—also called critical path analysis—is a network diagramming technique used to predict total project duration.
A critical path for a project is the series of activities that determine the earliest time by which the project can be completed. It is the longest path through the network diagram and has the least amount of slack or float.
• Slack or float is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date.
The longest path or the path containing the critical tasks is what is driving the completion date for the project.
![Page 27: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/27.jpg)
Critical Path Analysis
![Page 28: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/28.jpg)
What Does the Critical Path Really Mean?
The critical path shows the shortest time in which a project can be completed.
If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action.
For example: Apple Computer team members put a stuffed gorilla on top of the cubicle of whoever was in charge of a critical task, so they would not distract him or her.
![Page 29: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/29.jpg)
Using Project Management Software
Many powerful software tools exist for assisting with project management.
Example: Microsoft Project can help with
•Entering project start date.
•Establishing tasks and task dependencies.
•Viewing project information as Gantt or Network diagrams.
![Page 30: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/30.jpg)
Project Start Date
![Page 31: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/31.jpg)
Entering Tasks
![Page 32: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/32.jpg)
Viewing Network Diagram
•Hexagon shape indicates a milestone.
•Red boxes and arrows indicate critical path (no slack).
![Page 33: Chapter 3 : Managing the Information Systems Project](https://reader036.fdocuments.us/reader036/viewer/2022081421/5681322c550346895d988cb3/html5/thumbnails/33.jpg)
Viewing Gantt Chart
Black line at top indicates a summary activity (composed of subtasks).Diamond shape indicates a milestone.