CHAPTER 3 INFORMATION ON APPLICATION FOR SUPPLY · 3.6 6. If there is no central metering cubicle...

107
CHAPTER 3 INFORMATION ON APPLICATION FOR SUPPLY

Transcript of CHAPTER 3 INFORMATION ON APPLICATION FOR SUPPLY · 3.6 6. If there is no central metering cubicle...

CHAPTER 3

INFORMATION ON

APPLICATION FOR SUPPLY

3.1

CHAPTER 3 INFORMATION ON APPLICATION FOR SUPPLY 3.1 Application for Supply to New Building 1. Supply would, as decided by HK Electric, either be provided by

establishing a customer substation at the building or by direct cables from existing low voltage network.

2. Supply arrangement, requirements of substation/cable entry ducts and

other facilities required for provision of supply would normally be agreed with the authorised architect/consultant responsible for the development at an early stage of the building construction.

3. For supply with establishment of a new substation, the substation should

be constructed and handed over to HK Electric in a complete condition and other facilities (as required) provided. Installation work will take about six weeks to complete after acceptance of all these facilities provided by the developers, payment of service charge (if any) and after receipt of all necessary permits issued by relevant government authority/private land owner. [Please see Clause 3.10 (1 & 2)]

4. For supply from existing low voltage network, the cable entry ducts and

other facilities as required should be provided. Installation work will take about four weeks to complete after acceptance of all these facilities, payment of service charge (if any) and after receipt of all necessary permits issued by relevant government authority/private land owner. [Please see Clause 3.10 (1 & 2)]

5. Under normal circumstances, the supply scheme will be prepared and

service charge (if any) determined in about two weeks after receipt of formal application for supply. For exceptional cases where special type of equipment or complicated supply arrangements are involved, an additional two weeks may be needed for determination of service charge. [Please see Clause 3.10 (1 & 2)]

3.2

3.2 Application for Supply to Village Houses on Hong Kong Island or 3-Storey Houses on Lamma Island

1. Supply would normally be provided by direct cables from existing low

voltage network. However, there would be some special cases where supply would be provided by low voltage overhead wires.

2. Formal application for supply should be submitted as early as possible.

The applicant will be advised of HK Electric's requirements of the cable entry ducts, weatherproof enclosure and/or other facilities in about four weeks upon receipt of the application.

3. Apart from preparation of the supply scheme, approval of excavation

permit from District Lands Office will require about another three months. Should there be any private lot involved along the excavation route, written approval from all private lot owners must be received before the applicant is asked to pay the service charge required for provision of supply.

4. The cable entry ducts, weatherproof enclosure and/or other facilities as

required should be provided. Installation work will take about four weeks to complete after acceptance of all these facilities, payment of service charge (if any) and receipt of all necessary permits issued by relevant government authority/private land owner. [Please see Clause 3.10 (1 & 2)]

3.3 Application for Supply (New or Additional) at Existing Building 1. It must not be assumed that such supply (even if it is a small supply or

application for transfer) at existing building can be obtained at short notice because the existing supply system may have already been loaded to its capacity and need reinforcement.

2. For application of a very large supply, a new substation or extension of the

existing substation at the building may be required. This will involve alteration of building plans and will have to be handled by authorised architect/consultant. The whole process of providing supply including negotiation of substation space, approval from relevant Government Authorities, construction/extension of substation, inspection and handing over of substation, commissioning of substation and connection of supply may take six months to a few years.

3.3

3. Application of smaller supply may also necessitate the installation of

additional service cable or replacement of existing service cable supplying the building. The applicant will be advised of the supply situation, HK Electric's requirements of the cable entry ducts and other facilities, and service charge required for provision of supply (if any) in about three weeks upon receipt of the application. The cable installation work will take about four weeks to complete after acceptance of all these facilities, payment of service charge (if any) and after receipt of all necessary permits issued by relevant government authority/private land owner. [Please see Clause 3.10 (1 & 2)]

4. The processing time will be much shorter if the application for supply does not require any reinforcement work by HK Electric.

5. It is always the customer's REC/REW responsibility to ensure that prior

consent has been obtained from the building management and/or the owners incorporation of the building regarding connection of customer's new or additional load to the distribution system of the building and that connection of customer's new or additional installation will not cause overload to the distribution system of the building.

6. To help speed up the processing of application for supply, the applicants or

their RECs/REWs are requested to complete Form DP1 to provide the information on Supply Number details from which the proposed electrical installation will be supplied.

7. The work flow and telephone contact list for application for additional

load is shown in Drg. No. GCS/3/01.

3.4 Application for Temporary Supply to Construction Sites 1. Supply would normally be provided either by establishing a transformer

pillar at the site or by direct cables from existing low voltage network up to the boundary of the site.

3.4

2. If the requested load cannot be supplied from existing low voltage network,

a transformer pillar at the site will be required. To accommodate the pillar, a space of not less than 4 m x 4 m on levelled and stable ground free from flooding and landslip hazard with 1.6-m all-round clearance should be provided. Access to pillar should be freely available at all times and at least one side of the pillar should be along the periphery of the construction site. A customer's main switch room adjacent to the transformer pillar should also be provided. The access to customer’s main switch room should be freely available at all times and should be at the periphery of the construction site. The low voltage connection will be by single-core cables.

3. For supply with establishment of a transformer pillar, the pillar foundation

should be constructed and handed over to HK Electric in a complete condition and other facilities (as required) provided, and service charge required for provision of supply paid at least eight weeks before supply is required.

4. If the requested load can be supplied from existing low voltage network, a

cable will be laid up to the boundary of the site. A weatherproof enclosure for housing service cutout and meter will be supplied by HK Electric but installed by the applicant. The applicant shall install the distribution facilities inside their own switch cubicle.

5. For supply from existing low voltage network, the installation of

weatherproof enclosure and provision of other facilities will be inspected by HK Electric after payment of the service charge. Cable installation will take about four weeks to complete after acceptance of all these facilities, and after receipt of all necessary permits issued by relevant government authority/private land owner. [Please see Clause 3.10 (1 & 2)]

6. Under normal circumstances, the scheme for supply from existing low

voltage network will be prepared and service charge determined in about two weeks after receipt of formal application for supply and location of weatherproof enclosure is agreed. For supply with establishment of a transformer pillar, the scheme will be prepared and service charge determined in about four weeks after receipt of formal application for supply and location of transformer pillar is agreed. [Please see Clause 3.10(1 & 2)]

7. The flow chart on application procedures for site supply by installation of

new L.V. cable is shown in Drg. No. GCS/3/02.

3.5

3.5 Application for Supply to Squatters

1. Supply to squatter hut would be either by central metering scheme or running overhead wires directly to customer’s hut depending on the site conditions.

2. For supply to squatter by central metering scheme, the applicant for supply will be required to install a MCB board or otherwise at the hut and run main wiring back to the pole with central metering cubicles and then fix a RCD complete with overcurrent protection as main switch at the metering cubicle to control the whole installation as per Drg. No. GCS/3/03.

3. For supply to squatter by direct overhead wires, the applicant for supply

will be required to provide and install a weatherproof enclosure for housing HK Electric’s service cutout and meter.

4. Formal application for supply with a sketch indicating the exact location

of hut where supply is required should be submitted as early as possible. Upon receipt of the application, HK Electric’s site engineer will conduct an inspection to see if there is any available central metering cubicle on site and advise the applicant accordingly.

5. If there is no central metering cubicle available and there is suitable space for erecting a central metering pole or adding new metering cubicle at existing pole, a scheme of providing a cubicle will be prepared in about four weeks after receipt of the application. If it involves erection of pole or cable laying in Government Land, District Lands Office will be approached for the issue of the permit, which will take about three months. After the necessary permit (if any) is received, the applicant will be advised of the supply arrangement, the location of the central metering pole and the service charge required for provision of supply. Installation work will take about four weeks to complete after payment of service charge (if any) and receipt of all necessary permits issued by relevant government authority/private land owner. [Please see Clause 3.10 (1 & 2)]

3.6

6. If there is no central metering cubicle available and there is no suitable space for adding a central metering cubicle, a scheme for providing supply by direct overhead wires will be prepared. The applicant will be advised of the supply arrangement, the location of the weatherproof enclosure to be provided and installed and the service charge (if required) for provision of supply. The installed weatherproof enclosure will be inspected by HK Electric after payment of the service charge/deposit. Installation work will take about four weeks to complete after payment of service charge (if any) and deposit and acceptance of the weatherproof enclosure. [Please see Clause 3.10 (1 & 2)]

3.6 Application for Supply to Pontoon/Vessel/Boat

1. Customer shall install a socket outlet of appropriate rating inside a weatherproof enclosure erected on shore for supplying electricity to pontoon/vessel/boat.

2. Supply would normally be provided by HK Electric LV service

cable/cutout or central metering scheme.

3. The customer main switch shall be of a RCD of 30-mA operating current. It should be equipped with overcurrent protection and adequate short circuit breaking capacity.

4. The supply arrangement is shown in Drg. No. GCS/3/04.

5. Formal application for supply with a sketch indicating the exact location of

the weatherproof enclosure and pontoon/vessel/boat where supply is required should be submitted as early as possible. Upon receipt of the application, HK Electric’s site engineer will conduct an inspection to see how to provide the supply and advise the applicant accordingly.

3.7 Application for Supply to Hawker Stalls

1. Applicant for supply to a stall should submit to HK Electric the following

documents: a. A copy of his licence issued by Food and Environmental Hygiene

Department (FEHD)

3.7

b. A no-objection letter from FEHD on the installation or connection of

any electrical wirings or electrical equipment for his hawking purpose.

c. A drawing showing his approved licensed area and location.

2. Supply would normally be provided by direct cables from existing LV network. The applicant is required to install a weatherproof enclosure within his licensed area to house HK Electric equipment with the door and window for meter reading facing footpath or public access.

3. The scheme for supply will be prepared and service charge determined in about three weeks after receipt of formal application for supply and the required documents. Cable installation will take about four weeks to complete after receipt of service charge from the applicant, acceptance of the required weatherproof enclosure and receipt of all necessary excavation permits issued by relevant government authority. [Please see Clause 3.10 (1 & 2)]

3.8 Temporary Supply for Filming/Decoration 1. Unmetered Temporary Supply for Filming Unmetered temporary supply for say, filming purpose, may be considered

if the supply required lasts not more than 3 days. However, customer must comply with the requirements of the Supply Rules and the Electricity (Wiring) Regulations and provide a copy of Work Completion Certificate prior to connection of supply. The installation shall be protected by a residual current device complete with overcurrent protection main switch at the connection of supply.

2. Metered Temporary Supply for Decoration/Renovation Unauthorised extension from communal installation for decoration/

renovation is extremely dangerous and therefore is strictly forbidden. Customer can apply for temporary supply for decoration/renovation. The installation shall be protected by a residual current device complete with overcurrent protection main switch at the connection of supply.

3.8

3.9 Application for Transfer 1. We require one working day advance notice to process transfer of account.

For most of the cases, we accept phone application/application by electronic form available from our website www.hkelectric.com for transfer and the process can be completed the next working day. A meter reading will be taken on the specified transfer date after which the customer will be responsible for the electricity consumption of the account. In case the customer has already occupied the address for a period of time, the date of the last monthly meter reading would be used in the transfer of account. The meter reading date is shown in the monthly electricity bill.

2. The completed Application Form For Supply/Transfer can also be returned

to our Customer Centre by post or in person or by fax to 2510 7667. HK Electric will inform the customer of the deposit amount by letter.

3. No service charge is required for an application for transfer of account. 4. For details of deposit amount for a transfer of account, please call our

Customer Services Representatives at 2887 3411 during office hours. 5. When the transfer of account has been completed, the account of the

former registered customer will be closed and the deposit will normally be ready for refund.

3.10 Additional Information 1. The time scales mentioned in the above sections are for indication only and

HK Electric is not committed to provide supply by any prescribed date although every effort will be made to provide supply as early as possible.

2. The actual time needed to plan and install any plant required for provision

of a supply depends on many factors such as the network situation, the working condition on site, availability of necessary permits issued by relevant government authority/private land owner (Excavation Permit, Government Lands Permit, Hong Kong Police Force Roadworks Advice, Construction Noise Permit and written approval from private land owners), etc.

3.9

Should there be any delay in provision of cable entry ducts and other facilities as required, HK Electric would not be able to complete the required excavation work within the period co-ordinated with other utility undertakers and approved by the relevant government authority and this could lead to a long delay in provision of supply due to the imposed restrictions on extension or re-application of excavation permit. Please refer to the leaflet, “Information on Application for Excavation Permit” as shown in Drg. No. GCS/3/24, prepared by HK Electric for more information.

3. If it is necessary to install any plant required for provision of supply, a

Planning Number will be assigned to the scheme. The applicant or REC/REW should quote the Planning Number or the Application Number when making any enquiries regarding the supply.

3.11 Schedule of Drawings - Information on Application for Supply Drawing No. Drawing Title GCS/3/01 Workflow and Telephone Contact List for Application

of Additional Load GCS/3/02 Application Procedures for Site Supply by Installation

of New L.V. Cable GCS/3/03 Squatter Hut Central Metering Scheme (P274/94/R-1) GCS/3/04 Typical Supply Arrangement for Pontoon / Vessel /

Boat GCS/3/05 Requirements for Service Cutout (LV RMU Type) in

New Building / Premises (P427/99/R-8) (Total 2 sheets) GCS/3/06 Details of Cable Entry Facilities in Existing Building for

Cutout Installation (P53/89/R-2) GCS/3/07 Space Requirements for 400-A Service Cutout in

Existing Building and Locations without Switch Room (Switch Type and with Disconnection Link)

(P213/92/R-4) GCS/3/08 Installation of Mild Steel Weatherproof Enclosure for

Site Services (up to 400 A) (P661/08) (Total 3 sheets)

3.10

GCS/3/09 Space Requirements for Stainless Steel Weather-proof Enclosure for Village House on Lamma Island (P72/89/R-8)

GCS/3/10 Transformer Pillar Foundation (For T.P. in Construction

Site with RTU) (P505/00/R-2) GCS/3/11 Typical Layout for 1 - Tx. Substation with HV Cable Pit

(P512/00/R-7) (Total 5 sheets) GCS/3/12 Typical Layout for Twin Transformer Substation with

HV Cable Pit (P584/03/R-2) (Total 4 sheets) GCS/3/13 Arrangement for Tariff Meter Communication (TMC)

Termination Box (P383/98/R-6) (Total 2 sheets) GCS/3/14 Details of LV Transit Block at Mid Level (P314/96/R-4) GCS/3/15 Arrangement for Single-Core Cables Connected to HK

Electric Substation (Customer’s Main Switch Not Exceeding 2250 A) (P31/88/R-6)

GCS/3/16 Typical Design of Working Platform at Cable Shaft /

Cable Compartment for First Level Substation (P605/04/R-4)

GCS/3/17 Earthing Bracket for New Substation (P574/02/R-2) GCS/3/18 Substation Main Supply & Schematic Diagram

(P561/01/R-8) GCS/3/19 Typical Arrangement of Cable Entry Ducts in

Substation (P627/05/R-1) (Total 2 Sheets)

GCS/3/20 Typical Arrangement of Cables and Cable Cleats in Riser Duct (Vertical Height 7 Metre) (P671/08/R-3) (Total 2 sheets)

GCS/3/21 Typical Arrangement of Cables and Cable Cleats in

Riser Duct for Upper Floor Substation or Basement Substation with Level Difference Exceeding 7 m (P666/08/R-4) (Total 2 sheets)

3.11

GCS/3/22 High Level Hazard Zone (P346/97)

GCS/3/23 Substation Louvres Details (P638/06/R-1) GCS/3/24 Information on Application for Excavation Permit

(Total 2 sheets) GCS/3/25 Mild Steel Weatherproof Enclosure for Site Services up

to 100 A 3-Phase (P630/06/R-2) (Total 4 sheets) GCS/3/26 Conditions on Acceptance of Attaching External

Decorative Louvres / Cladding to Substation Door or Additional Decorative Door in Front of Substation Door of Ground Floor Substation (P753/14)

GCS/3/27 Requirements on Fire Resisting Door for Substations

(P339/97/R-7) GCS/3/28 Requirements of Precast Reinforced Concrete Cover

(P722/12/R-1) GCS/3/29 Anchoring Eye and Facilities for First Level Substation

(P342/97/R-3) (Total 2 sheets) GCS/3/30 Typical Layout for Single Transformer First Level

Substation with HV & LV Compartments (P381/98/R-6) (Total 6 sheets)

GCS/3/31 Mild Steel Weather-proof Enclosure for Single Phase

Supply (655/07/R-1) GCS/3/32 Mild Steel Weather-proof Enclosure for Single Phase

Supply to Hawker Stall (P717/12/R-3) (Total 2 sheets)

Submission of ApplicationCustomer is required to submit application form and the following information as far as possible Load estimation Schematic wiring diagram Proposed service position (if installation of new supply point is required). Supply number details form

All requiredinformationsubmitted?

Preparation of Supply Scheme

Enquiry on service position service charge issue cable lead-in arrangement service cutout installation requirements latest status on application of excavation permit or private permissions situation arrange the site check of cabling facilities provided by customer

Distribution Planning Department Eastern Central Western

2843 31052843 31642843 3108General Enquiry on

enquiry on application form amount of service charge amount of deposit method of payment fix the first customer installation inspection date

Customer Centre / Application Unit

Creation of Account and Inspectionof Customer Installation

2887 3411

Enquiry on customer's installation comments on schematic wiring diagram metering equipment collection arrange the customer installation re-inspection date if required installation inspection result/report meter fixing date customer is required to submit a copy of Work Completion Certificate and C.I. 140 Form where appropriate enquiry on supply number details form technical enquiry on customer installation

Customer Installation & 2887 3455

Site checkpassed?

Enquiry on commencement date of the work service cutout and cable installation date duration of work progress of work date of completion

Construction & Maintenance DepartmentCustomer Services Representative

Installation of Cutout/Service Cable

2814 3997

Additional supply available

Remark: 1.Please contact the corresponding department or call our Electricity-By-Phone Service at telephone No. 2887 3838 if you have any queries regardingthe progress of application.

Customer Supplies Department

No

Yes

No

Yes

CUSTOMER

HK ELECTRIC

Training Department

*

Drg. No. GCS/3/01WORKFLOW AND TELEPHONE CONTACT LIST

FOR APPLICATION OF ADDITIONAL LOAD3.12

Notes: 1.The weather-proof enclosure shall be installed on site within 1 week from the date of taking over to avoid any delay in provision of supply. 2.For enquiry related to progress of application and inspection, please call the automated telephone system, Electricity-By-Phone Service (EPS), at 2887 3838 or the responsible party at the following numbers:

Customer Installation & Training Department to fix meter and connect supply

Distribution Planning Dept Eastern Central Western

Construction & Maintenance Dept Eastern Central Western

Customer Supplies Department General Enquiry 2887 3411 Customer Installation & Training Dept Customer Installation 2887 3455

NoSatisfactoryInstallationInspection

Yes

Construction & Maintenance Department to installservice cable when excavation permit obtained

Customer/REC/REW to inform DistributionPlanning Department for inspection when enclosure

installed

Customer/REC/REW to arrange inspection ofcustomer's installation as follows:

Customer/REC/REW to collect metering equipmentfrom Customer Installation & Training Department

if required

Distribution Planning Department to liaise withCustomer/REC/REW and deliver the enclosure to

site for installation by Customer/REC/REW

NoEnclosure properlyinstalled at agreedposition?

Yes

Customer/REC/REW to make site ready for installation ofweather-proof enclosure and pay service charge & deposit

Distribution Planning Department to advise supply arrangement, serviceposition and amount of service charge required

Distribution Planning Department to assess and agree service positionwith Customer/REC/REW

Customer/REC/REW to submit application with details of load estimate,main switch rating, site boundary and proposed service position

First Inspection: Customer Supplies DepartmentRe-inspection: Customer Installation & Training

Department

---

2843 3105

2843 3164

2843 3108

2814 3230

2814 3287

2814 3607

---

Drg. No. GCS/3/02APPLICATION ROCEDURES FOR SITE SUPPLY

BY INSTALLATION OF NEW L.V. CABLE3.13

Drg

. No.

GC

S/3/

03SQ

UA

TTER

HU

T C

ENTR

AL

MET

ERIN

G S

CH

EME

(P27

4/94

/R-1

)

3.14

Pont

oon/

Vess

el /

Boat

Sock

etO

utle

tLo

cal

Switc

hOn-

shor

eCu

stom

er P

illar

HK E

lect

ricTa

riff M

eter

HK E

lect

ricSe

rvic

e Cu

tout

orCe

ntra

lM

eter

ing

Sche

me

Cust

omer

Mai

n Sw

itch

(30-

mA

RCD)

LAN

DSE

A

Drg

. No.

GC

S/3/

04TY

PIC

AL

SUPP

LY A

RR

AN

GEM

ENT

FOR

PO

NTO

ON

/VES

SEL/

BO

AT

3.15

65

0

20

35

72

5

65

20

50

L1 L2 L3 N

FU

SE

WA

Y N

o. 1

FU

SE

WA

Y N

o. 2

FU

SE

WA

Y N

o. 3

CONNECTION FOR CUSTOMER'S WIRING

FLOOR

WEIGHT OF 160 kg

560

EARTHING

CONNECTION

Front View of Service Cutout ( LV RMU Type )

The cable ends terminated onto HK Electric service cutout

shall be fitted with proper, durable and legible phase

identification labels ( such as cable ties, sleeves, ferrules

etc. ) marked in L1, L2, L3 and N.

The minimum size of copper conductor to be terminated onto the

outgoing service terminals of HK Electric service cutout is 50 sq. mm.

Should the customer's main wiring be less than this size, a copper collar

of 50 sq. mm (by hydraulic crimping or by mechanical connection)

should be provided for termination onto HK Electric cutout.

A maximum of two (2) sets of customer's wiring to be connected directly

to HK Electric service cutout.

4 nos. mounting bracket ( 4 nos. M10 G.I. expansion anchor bolts with

nuts & washers with protruded length of 50 mm from wall surface , to be

supplied & installed by customer )

11

25

97

5

750

W

FIXING BOLT

HAND HOLE

CABLE TRENCH

OF WIDTH W

CENTRE LINE OF CUTOUT

WALL

75

560

37

0

EDGE OF CABLE TRENCH

75-mm-WIDE CONCRETE

FLOOR SPACE FOR LV

RMU TO SIT ON

29

5

295 x 560 OPENING FOR

HK Electric SERVICE CUTOUT

( LV RMU TYPE ) TO BE

TEMPORARILY COVERED

UP WITH TIMBER BOARD

Typical Layout of Chequer Plates

For HK Electric Service Cutout

U-SHAPE CHEQUER PLATE

IN ONE PIECE IF NOT

EXCEEDING 20 kg

Drg. No. GCS/3/05REQUIREMENTS FOR SERVICE CUTOUT (LV RMU TYPE) IN

NEW BUILDING / PREMISES (P427/99/R-8) SHEET 1 OF 2

NOTE:

ALL DIMENSIONS ARE IN mm

3.16

L1

L2

L3

NL1

L2

L3

NL1

L2

L3

N

2100

800

SW

IT

CH

RO

OM

CA

BLE

T

RE

NC

H

BU

IL

DIN

G

BO

UN

DA

RY

PA

VE

ME

NT

760

Section

750

750

750

370

W

CA

BL

E

TR

EN

CH

OF

D

EP

TH

80

0

SW

IT

CH

RO

OM

PA

VE

ME

NT

BU

IL

DIN

G

BO

UN

DA

RY

N N

os. O

F

15

0 D

IA

. C

AB

LE

EN

TR

Y D

UC

TS

(M

AX

. 2

L

AY

ER

S)

SE

RV

IC

E

CU

TO

UT

EA

CH

O

F

16

0 kg

WE

IG

HT

75

07

50

75

0

DO

OR

N

OT

LE

SS

T

HA

N

23

00

H

IG

H A

ND

75

0 W

ID

E

(IN

TE

RN

AL

ME

AS

UR

EM

EN

T)

Pa

rt o

f G

ro

un

d F

lo

or P

la

n o

f a

T

yp

ica

l B

uild

in

g

Cu

sto

me

r sh

all p

ro

vid

e ch

eq

ue

r p

la

te

s to

co

ve

r tre

nch

o

pe

nin

g.

Th

e ch

eq

ue

r p

la

te

s fo

r e

ach

se

rvice

cu

to

ut sh

all b

e o

f d

im

en

sio

ns

75

0 m

m x W

, w

he

re

W

is th

e w

id

th

o

f th

e ca

ble

tre

nch

. T

he

ch

eq

ue

r p

la

te

s sh

all b

e in

p

ie

ce

s fo

rm

in

g a

re

a 7

50

m

m x W

in

ord

er th

at e

ach

p

ie

ce

sh

all n

ot e

xce

ed

2

0 kg

. T

he

ch

eq

ue

r p

la

te

s

sh

all b

e p

ro

vid

ed

w

ith

h

an

d h

ole

s, fixe

d b

y b

olts a

nd

n

uts a

nd

fitte

d w

ith

stiffe

ne

rs if n

ece

ssa

ry.

Th

e flo

or a

re

a m

ea

su

re

d 9

00

m

m in

fro

nt o

f e

ach

se

rvice

cu

to

ut

an

d m

ea

su

re

d 6

00

m

m fro

m b

oth

le

ft h

an

d sid

e a

nd

rig

ht h

an

d

sid

e ( if n

ot o

bstru

cte

d b

y th

e w

all o

r d

oo

r ) o

f th

e ce

ntre

lin

e o

f

ea

ch

se

rvice

cu

to

ut sh

all b

e o

f co

ncre

te

flo

or o

r co

ve

re

d w

ith

ch

eq

ue

r p

la

te

s to

fa

cilita

te

th

e cu

to

ut in

sta

lla

tio

n w

ork b

y H

K

Ele

ctric.

Flo

or sp

ace

o

f 7

5 m

m w

id

e sh

all b

e p

ro

vid

ed

b

etw

ee

n w

all a

nd

ed

ge

o

f ca

ble

tre

nch

fo

r L

V R

MU

to

sit o

n.

In

ca

se

th

e w

id

th

o

f th

is flo

or sp

ace

e

xce

ed

s 7

5 m

m, cu

sto

me

r

sh

all co

nstru

ct a

ro

bu

st fra

me

wo

rk o

f h

ot d

ip

g

alva

nise

d ste

el to

be

m

ou

nte

d o

n w

all so

th

at th

e h

orizo

nta

l se

pa

ra

tio

n o

f

fra

me

wo

rk a

nd

e

dg

e o

f tre

nch

w

ill b

e 7

5 m

m.

Ho

le

s o

f 1

4 m

m d

ia

. to

ge

th

er w

ith

M

10

b

olts, n

uts a

nd

w

ash

ers

sh

all b

e p

ro

vid

ed

o

n th

e fra

me

wo

rk to

su

it th

e 4

n

os. m

ou

ntin

g

bra

cke

t a

t th

e se

rvice

cu

to

ut.

16

00

W

ID

E C

LE

AR

AN

CE

(W

IT

HO

UT

A

NY

U

ND

ER

GR

OU

ND

O

BS

TA

CL

E)

AT

C

AB

LE

E

NT

RY

S

HA

LL

B

E P

RO

VID

ED

.

SE

RV

IC

E

CU

TO

UT

EA

CH

O

F

16

0 kg

WE

IG

HT

15

0 D

IA

. C

AB

LE

EN

TR

Y D

UC

TS

(M

AX

. 2

L

AY

ER

S)

Drg

. No.

GC

S/3/

05R

EQU

IREM

ENTS

FO

R S

ERV

ICE

CU

TOU

T (L

V R

MU

TY

PE) I

NN

EW B

UIL

DIN

G /

PREM

ISES

(P42

7/99

/R-8

) SH

EET

2 O

F 2

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.17

3.18

Notes for Drawing No. GCS/3/05 1. This drawing shows the typical layout of cable entry facilities in buildings where

there is no underground obstacles. All dimensions shown in this drawing are in mm (millimetre).

2. Reinstatement of excavation surfaces required for provision of cable entry facilities

and cable laying work by The Hongkong Electric Co. Ltd. 香港電燈有限公司 within the building lot boundary shall be the responsibility of customers.

3. The cable entry facilities shall be sealed properly by customers against ingress of

water to the switchroom and other parts of the building during the excavation work by customers and after HK Electric's new cables are installed.

4. All excavation work by customers shall be carried out within the building lot

boundary. It is unlawful to excavate in public road and footway outside the building lot boundary without prior approval of the Government Highways Department.

5. A minimum clearance space of 900 mm for the full width and in front of HK

Electric's service cutouts and customer's switchgear shall be provided. 6. Where there is spare space on wall of switchroom for contingency service cutout

(please refer to the returned marked-up copy of Ground Floor Plan), the spare space shall be painted in red with an engraved label not less than 150 mm wide x 75 mm high stating

"SPACE RESERVED FOR HK ELECTRIC'S CONTINGENCY SERVICE CUTOUT" with Chinese translation,「應 急 熔 斷 器 之 預 留 空 間 」 being

securely fixed on the wall space. 7. Normally, HK Electric will install service cutouts at the positions furthest from the

cable entry ducts. Spare spaces for contingency service cutouts will be the closest from the cable entry ducts.

8. The number of cable entry ducts and width of cable trench shall be provided

according to the following table, unless otherwise specified.

No. of Service Cutout Spaces (including spare, if any)

No. of Cable Entry Ducts (N)

Width of Cable Trench (W)

1 4 500 mm 2 6 600 mm 3 8 750 mm

3.19

Notes for Drawing No. GCS/3/05 9. A minimum clearance of 1600 mm wide (without any underground obstacle)

immediately in front of the cable entries should be provided for cable installation. Where necessary the architect shall be responsible for clearing underground obstacles with other utility companies before hand-over of the switchroom to HK Electric for cable installation.

10. The door of switchroom shall not be less than 750 mm wide by 2300 mm high

measured clear of obstacles.

GENERAL NOTES:

obstacles. All dimensions shown in this drawing are in mm (millimetre).

excavate in public road and footway outside the building lot boundary without prior approval of theGovernment Highways Department.

shall be filled up temporarily with sand bags and be covered in proper condition in order to avoid hazardsendangering residents in the building.

The Hongkong Electric Co. Ltd. within the building lot boundary shall be the responsibility of customers.

1. This drawing shows the typical layout of cable entry facilities in buildings where there is no underground

2. Unless otherwise specified, 2 nos. of 150-mm-diameter ducts shall be provided for cable entry.

3. Reinstatment of excavation surfaces required for provision of cable entry facilities and cable laying work by

4. The temporary pit shall be backfilled by customers. All pits and trenches within the building lot boundary

5. The cable entry facilities shall be sealed properly by customers against ingress of water to other parts of

6. All excavation work by customers shall be carried out within the building lot boundary. It is unlawful to

the premises during the excavation work by customers and after HK Electric's new cables are installed.

Drg. No. GCS/3/06DETAILS OF CABLE ENTRY FACILITIES IN EXISTING BUILDING

FOR CUTOUT INSTALLATION (P53/89/R-2)

3.20

a

b b

a a

b b

c c

a

b

b

c

a

b

c

Drg. No. GCS/3/07SPACE REQUIREMENTS FOR 400-A SERVICE CUTOUT IN

EXISTING BUILDING AND LOCATIONS WITHOUT SWITCH ROOM(SWITCH TYPE AND WITH DISCONNECTION LINK) (P213/92/R-4)

3.21

1200

490

135

120

222

118

118

410

IN

TE

RN

AL

L

AY

OU

T O

F W

EA

TH

ER

PR

OO

F E

NC

LO

SU

RE

2

L1

L2

L3

N

2 N

os. M

8x3

2 L

ON

G

ST

UD

F

OR

E

AR

TH

IN

G

TH

IS

S

PA

CE

IS

F

OR

HK

E

LE

CT

RIC

S

ER

VIC

E C

UT

OU

T

EA

RT

HIN

G T

ER

MIN

AL

SU

IT

AB

LE

F

OR

M

AX

.

2x 9

5-m

m C

ON

DU

CT

OR

S

"a

" F

OR

M

10

x7

0-m

m-L

ON

G

ST

UD

W

EL

DE

D O

NT

O B

AC

K

OF

E

NC

LO

SU

RE

, W

IT

H N

UT

S

AN

D W

AS

HE

RS

( T

OT

AL

3

S

ET

S )

"b

"

TH

IS

S

PA

CE

IS

F

OR

H

K E

LE

CT

RIC

ME

TE

RIN

G E

QU

IP

ME

NT

. C

US

TO

ME

R

SH

AL

L IN

ST

AL

L T

HE

IR

M

AIN

S

WIT

CH

IN

SID

E T

HE

IR

O

WN

S

WIT

CH

C

UB

IC

LE

.

KK

"c":

65

0 W

x 1

20

0 H

x 2

0 T

HIC

K

WO

OD

EN

B

OA

RD

45

0 W

x 1

20

0 H

x 2

0 T

HIC

K

WO

OD

EN

B

OA

RD

LE

VE

L O

F

PA

VE

ME

NT

2

N

os. O

F S

CR

EW

F

OR

F

IX

IN

G C

AB

LE

C

OV

ER

O

N W

OO

DE

N

B

OA

RD

( T

O B

E P

RO

VID

ED

A

ND

IN

ST

AL

LE

D

B

Y H

K E

LE

CT

RIC

)

F

OR

1

2 D

IA

. H

OL

E W

IT

H

A N

UT

W

EL

DE

D A

T T

HE

RE

AR

E

XT

ER

NA

L S

UR

FA

CE

OF

E

NC

LO

SU

RE

( A

N M

10

x8

0-m

m-L

ON

G B

OL

T

A

ND

W

AS

HE

R )

( T

OT

AL

4

S

ET

S )

TH

E C

AB

LE

E

ND

S T

ER

MIN

AT

ED

ON

TO

H

K E

LE

CT

RIC

S

ER

VIC

E

CU

TO

UT

S

HA

LL

B

E F

IT

TE

D W

IT

H

PR

OP

ER

, D

UR

AB

LE

A

ND

L

EG

IB

LE

PH

AS

E ID

EN

TIF

IC

AT

IO

N

LA

BE

LS

( S

UC

H A

S C

AB

LE

T

IE

S,

SL

EE

VE

S, F

ER

RU

LE

S E

TC

. )

MA

RK

ED

IN

L

1, L

2, L

3 A

ND

N

.

SW

IT

CH

T

YP

E

SE

RV

IC

E C

UT

OU

T

TO

B

E S

UP

PL

IE

D &

IN

ST

AL

LE

D B

Y

HK

E

LE

CT

RIC

A

T T

HE

TIM

E O

F C

AB

LIN

G W

OR

K

120

222

444 503

725

1300

HO

AR

DIN

G

PA

VE

ME

NT

LO

CA

TIO

N P

LA

N

TH

IS

R

EC

ES

S A

RE

A

SH

AL

L B

E C

OV

ER

ED

CU

ST

OM

ER

S

WIT

CH

C

UB

IC

LE

FO

R H

OU

SIN

G T

HE

IR

M

AIN

S

WIT

CH

( S

IZ

E T

O B

E D

EC

ID

ED

B

Y C

US

TO

ME

R )

WE

AT

HE

RP

RO

OF

E

NC

LO

SU

RE

FO

R H

K E

LE

CT

RIC

'S

S

ER

VIC

E

CU

TO

UT

CO

NS

TR

UC

TIO

N S

IT

E

700

aa

a

cc

b

bb

b

Drg

. No.

GC

S/3/

08IN

STA

LLA

TIO

N O

F M

ILD

STE

EL W

EATH

ERPR

OO

F EN

CLO

SUR

E FO

R S

ITE

SER

VIC

ES(U

P TO

400

A)

(P66

1/08

) SH

EET

1 O

F 3

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.22

1200

72

0

20

02

00

26

0

41

0

300

12

00

32

0

700

FR

ON

T V

IE

W

SID

E V

IE

W

GE

NE

RA

L C

ON

ST

RU

CT

IO

N

FR

ON

TR

EA

R

LE

VE

L O

F

PA

VE

ME

NT

LE

VE

L O

F

PA

VE

ME

NT

OW

NE

RS

HIP

O

F T

HIS

E

NC

LO

SU

RE

BE

LO

NG

S T

O T

HE

U

SE

R,

CO

MP

AN

Y N

AM

E:

:

,

20

0x2

00

P

ER

SP

EX

FO

R M

ET

ER

R

EA

DIN

G

KK

!D

AN

GE

R!

2 P

IE

CE

S O

F

20

-m

m-T

HIC

K

WO

OD

EN

B

OA

RD

IN

SID

E E

NC

LO

SU

RE

2 N

os. C

AB

LE

CL

AM

P W

IT

H M

10

FIX

IN

G B

OL

T &

NU

T

UP

PE

R C

OM

PA

RT

ME

NT

&

LO

WE

R F

RA

ME

WO

RK

T

O B

E

TR

AN

SP

OR

TE

D S

EP

AR

AT

EL

Y

AN

D A

SS

EM

BL

ED

B

Y C

US

TO

ME

R

ON

S

IT

E U

SIN

G 8

S

ET

S O

F

M1

2 B

OL

TS

&

N

UT

S

2 N

os. C

AB

LE

C

LA

MP

F

OR

H

K E

LE

CT

RIC

CA

BL

E W

IT

H M

10

F

IX

IN

G B

OL

T &

N

UT

DE

MO

UN

TA

BL

E

60

x6

0x6

M

.S

. A

NG

LE

60

x6

0x6

E

ND

P

LA

TE

S

OF

M

.S

. A

NG

LE

12

D

IA

. H

OL

ES

WIT

H M

10

B

OL

TS

&

N

UT

S

DE

TA

IL

'A

'

UP

PE

R C

OM

PA

RT

ME

NT

2 P

IE

CE

S O

F D

EM

OU

NT

AB

LE

6

0x6

0x6

M

.S

. A

NG

LE

W

IT

H

EN

D P

LA

TE

( U

PP

ER

&

L

OW

ER

) ( S

EE

D

ET

AIL

'A

' )

TO

P

RO

VID

E A

3

00

W

ID

E O

PE

NIN

G T

O A

LL

OW

S

LO

T-IN

OF

H

K E

LE

CT

RIC

C

AB

LE

S ( F

RO

NT

O

NL

Y )

30

0

1300

60

x6

0x6

M

.S

. A

NG

LE

LO

WE

R F

RA

ME

WO

RK

HO

LE

F

OR

H

K E

LE

CT

RIC

P

AD

L

OC

K

HO

LE

F

OR

C

US

TO

ME

R P

AD

L

OC

K

LO

CK

B

AR

LA

BE

L O

F O

WN

ER

SH

IP

60

650 Drg

. No.

GC

S/3/

08IN

STA

LLA

TIO

N O

F M

ILD

STE

EL W

EATH

ERPR

OO

F EN

CLO

SUR

E FO

R S

ITE

SER

VIC

ES (U

P TO

400

A)

(P66

1/08

) SH

EET

2 O

F 3

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.23

40

0

35

0

225

770

12

00

485

14

00

10

01

00

25

0

720

48

5

77

0

250

42

0

60

x6

0x6

M

.S

. A

NG

LE

FA

CIN

G D

OW

NW

AR

DS

60

W

ID

E x 6

T

HIC

K

M.S

. P

LA

TE

'X' 'X'

SP

AC

E F

OR

CA

BL

E E

NT

RY

14

00

x7

70

x4

00

D

EE

P

RE

IN

FO

RC

ED

C

ON

CR

ET

E

PL

IN

TH

CO

NC

RE

TE

P

LIN

TH

( B

Y C

US

TO

ME

R )

BO

TT

OM

O

F

EN

CL

OS

UR

E

MO

UN

TIN

G T

EM

PL

AT

E IN

ST

AL

LA

TIO

N

SE

CT

IO

N 'X

' - 'X

'

LE

VE

L O

F

PA

VE

ME

NT

RE

AR

FR

ON

T

75

-m

m B

IN

DIN

G L

AY

ER

EX

CE

PT

F

OR

CA

BL

E E

NT

RY

A

RE

A

12

N

os. M

OU

NT

IN

G S

TU

D

( 1

2 S

ET

S O

F N

UT

&

W

AS

HE

R IN

CL

UD

ED

)

( T

O B

E S

UP

PL

IE

D A

ND

IN

ST

AL

LE

D B

Y C

US

TO

ME

R )

A2

52

W

IR

E M

ES

H O

R

EQ

UIV

AL

EN

T. T

HE

W

IR

E M

ES

H

TO

B

E C

UT

&

B

EN

T T

O S

UIT

TH

E S

IT

E C

ON

DIT

IO

N.

MO

UN

TIN

G T

EM

PLA

TE

( S

UP

PLIE

D B

Y H

K E

LE

CT

RIC

A

ND

T

O B

E C

AS

T IN

C

ON

CR

ET

E P

LIN

TH

B

Y C

US

TO

ME

R )

RE

AR

FR

ON

T

25

0 W

ID

E x 4

85

D

EE

P

SP

AC

E F

OR

C

AB

LE

EN

TR

Y

320 225

37

5

MO

UN

TIN

G T

EM

PL

AT

E

12

N

os. M

OU

NT

IN

G S

TU

D

BA

CK

FIL

LIN

G

MINIMUM 400

12

N

os. M

OU

NT

IN

G S

TU

D

50

Drg

. No.

GC

S/3/

08IN

STA

LLA

TIO

N O

F M

ILD

STE

EL W

EATH

ERPR

OO

F EN

CLO

SUR

E FO

R S

ITE

SER

VIC

ES(U

P TO

400

A) (

P661

/08)

SH

EET

3 O

F 3

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.24

3.25

Notes for Drawing No. GCS/3/08

1. A weatherproof enclosure comprising upper compartment, lower framework and

mounting template provided by HK Electric shall be installed by customer on site.

2. The ownership of the weatherproof enclosure belongs to the customer after

collection of the enclosure. Customer is required to write down the company name on enclosure at the space provided on the “LABEL OF OWNERSHIP”.

3. Customer shall provide and install a switch cubicle adjacent to the weatherproof

enclosure for housing customer’s main switch and associated installation.

4. The weatherproof enclosure and switch cubicle shall be installed inside the

boundary of construction site and be facing the pavement as shown on the location plan. A minimum clearance space of 900 mm for the full width in front of enclosure shall be provided. A clear access to the enclosure shall be provided without any obstruction from covered walkway.

5. The mounting template shall be cast in a reinforced concrete plinth by customer.

6. The concrete shall be designed mix of grade 20/20D with compressive stress

20 N/mm2 at 28 days.

7. The concrete cover to mesh reinforcement shall be 50 mm minimum.

8. Proper earthing of the weatherproof enclosure shall be by customer.

9. Customer is required to inform HK Electric for an inspection after completion of

the weatherproof enclosure installation and their pad lock fitted.

120 120 120 120

1000

ABO

VE G

RO

UN

D

110 110

1600

550

700

BYHK ELECTRIC

TOTAL WEIGHT OF ENCLOSUREAND CUTOUT IS 250 kgCUSTOMER HAS TO PROVIDE SEPARATEEARTHING FOR HIS INSTALLATIONSIN ACCORDANCE WITH ELECTRICITY( WIRING ) REGULATIONS

1)

2)

NOTES:

L1 L2 L3 N

2

250

15

N

N

A

350

SPACEFORCUSTOMER'SMAINSWITCH

N

N A

4 nos. M10 S.S.EXPANSION ANCHORBOLTS WITH NUTS &WASHERS WITHPROTRUDED LENGTHOF 50 mm FROM WALLSURFACE TO BESUPPLIED & INSTALLEDBY CUSTOMER

20 THICKWOODEN BOARD( SAM CHEUNG )

400-A CUTOUT BYHK ELECTRIC( SWITCH TYPE WITH DISCONNECTION LINK )

CL

L

L

L

L

L:

100

475

25

50

260

100

SIDE VIEW

N

FRONT VIEW

WALL

50100

50

50

N

50

605

450

605

100( INTERNAL DIAMETER)S.S. PIPE FORCUSTOMER'SOUTGOINGWIRINGS

N:

EARTHING TERMINALFOR CUSTOMER( MAXIMUM 2 nos. 95-mm CONDUCTOR )

4 nos. M10 S.S.EXPANSION ANCHORWITH 50-mm BOLTS &WASHERS TO BE FLUSHWITH WALL SURFACE ,TO BE SUPPLIED &INSTALLED BY CUSTOMER

450

340

EARTHING STUDFOR HK ELECTRIC USE

300

LEGEND :

S.S. = STAINLESS STEEL

THE CABLE ENDS TERMINATEDONTO HK ELECTRIC SERVICE CUTOUTSHALL BE FITTED WITH PROPER,DURABLE AND LEGIBLE PHASEIDENTIFICATION LABELS( SUCH AS CABLE TIES, SLEEVES, FERRULES ETC. ) MARKED INL1, L2, L3 AND N.

75 75

L50

L50

50

60

80

120

80

340

ALL DIMENSIONS ARE IN mm3)

Drg. No. GCS/3/09SPACE REQUIREMENTS FOR STAINLESS STEEL WEATHER-PROOF

ENCLOSURE FOR VILLAGE HOUSE ON LAMMA ISLAND (P72/89/R-8)3.26

PLA

N

2840

150x200

R.C

. T

IE

150x200

R.C

. T

IE

BLIN

DIN

G LA

YE

R

CA

BLE

T

RE

NC

H T

O B

E B

AC

KF

ILLE

D

WIT

H S

IF

TE

D S

OIL B

Y H

K E

LE

CT

RIC

GR

OU

ND

LE

VE

L

200

1000 50

150

SE

CT

IO

N 'X

' - 'X

'

DIM

EN

SIO

NS

IN

m

m

1 )

NO

TE

S :

2 )

NOT LESS

THAN 300

SID

E 'C

'

SID

E 'A

'

SIDE 'B'

SIDE 'D'

150x200 R

.C

. T

IE

150x200 R

.C

. T

IE

150x200 R

.C

. T

IE

150x200 R

.C

. T

IE

R.C

.C

.

'X'

'X'

150

15

0

510

4700

4004001130400

1850x2300(H) DOOR D5

1730x2300(H

) D

OO

R D

4

2370x2300(H

) D

OO

R D

61500x2300(H

) D

OO

R D

7

D1

850x2300(H) DOOR

2100x2300(H

) D

OO

R D

2

150 D

IA

. U

PV

C C

AB

LE

D

UC

T

15

0 D

IA

.

UP

VC

C

AB

LE

D

UC

T

CO

VE

RE

D

PU

BL

IC

PA

VE

ME

NT

TH

E T

RA

NS

FO

RM

ER

P

ILLA

R F

OU

ND

AT

IO

N

SH

ALL B

E D

ES

IG

NE

D A

ND

C

ON

ST

RU

CT

ED

BY

C

US

TO

ME

R T

O W

IT

HS

TA

ND

T

HE

T

OT

AL

WE

IG

HT

O

F T

HE

P

ILLA

R A

ND

E

QU

IP

ME

NT

IN

SID

E T

HE

P

ILLA

R W

HIC

H S

HO

ULD

B

E

TA

KE

N A

S 10000 kg ( 10 T

ON

NE

S )

5)

3 )

4 )

CO

NS

TR

UC

TIO

N

SIT

E H

OA

RD

IN

G

CO

NS

TR

UC

TIO

N

SIT

E H

OA

RD

IN

G

CA

SIN

G O

F

TR

AN

SF

OR

ME

R P

ILLA

R

( H

EIG

HT

O

F 3000 )

( B

Y H

K E

LE

CT

RIC

)

CO

VE

RE

D

PU

BLIC

PA

VE

ME

NT

LO

CA

TIO

N P

LA

N

CO

NS

TR

UC

TIO

N

SIT

E H

OA

RD

IN

G

PE

RS

ON

NE

L A

CC

ES

S

PE

RS

ON

NE

L

AC

CE

SS

HK

E

LE

CT

RIC

'S

TR

AN

SF

OR

ME

R

PILLA

R

1.6 m

TH

E A

CC

ES

S T

O C

US

TO

ME

R'S

M

AIN

S

WIT

CH

RO

OM

SH

ALL B

E F

RE

ELY

A

VA

ILA

BLE

A

T A

LL T

IM

ES

AN

D S

HA

LL B

E A

T T

HE

P

ER

IP

HE

RY

O

F T

HE

CO

NS

TR

UC

TIO

N S

IT

E

TH

E A

CC

ES

S T

O T

HE

T

RA

NS

FO

RM

ER

P

ILLA

R

SH

ALL B

E F

RE

ELY

A

VA

ILA

BLE

A

T A

LL T

IM

ES

AN

D A

T LE

AS

T O

NE

S

ID

E O

F T

HE

P

ILLA

R

SH

ALL B

E A

T T

HE

P

ER

IP

HE

RY

O

F T

HE

CO

NS

TR

UC

TIO

N S

IT

E

2500

TH

E S

PA

CE

F

OR

T

RA

NS

FO

RM

ER

P

ILLA

R

SH

ALL B

E O

N LE

VE

LLE

D A

ND

S

TA

BLE

G

RO

UN

D

FR

EE

F

RO

M F

LO

OD

IN

G A

ND

LA

ND

SLID

E H

AZ

AR

D

WIT

H M

IN

IM

UM

1600-m

m A

LL R

OU

ND

C

LE

AR

AN

CE

MIN

IM

UM

CU

ST

OM

ER

'S

S

WIT

CH

RO

OM

( P

RE

FE

RA

BL

Y A

DJA

CE

NT

T

O

SID

E 'B

') F

OR

H

OU

SIN

G T

HE

ME

TE

RIN

G E

QU

IP

ME

NT

&

T

HE

IR

MA

IN

S

WIT

CH

( S

IZ

E T

O B

E

DE

CID

ED

B

Y C

US

TO

ME

R )

SIDE 'B'

Drg

. No.

GC

S/3/

10TR

AN

SFO

RM

ER P

ILLA

R F

OU

ND

ATI

ON

(FO

R T

.P. I

N C

ON

STR

UC

TIO

N S

ITE

WIT

H R

TU) (

P505

/00/

R-2

)

3.27

R.C.

C. C

ANOP

YR.

C.C.

CAN

OPY

1000kg1000kg1000kg1000kg

VFC

TELRTU OPT

BATT

CAP. BANK200kVAr

LVT

TT

TMC

TXTMCBB

DOW

N-ST

REAM

SILE

NCER

EART

HING

POI

NT F

OR C

HEQU

ER P

LATE

100x

100 S

LOT

OPEN

ING

AT C

HEQU

ER P

LATE

4500

CMH

AXI

AL F

LOW

FAN

150 W

IDE

U-CH

ANNE

LTO

BE

INST

ALLE

D FL

USH

WIT

H SU

BSTA

TION

FLO

OR

150 H

IGH

DOOR

SILL

THIS

FLU

ORES

CENT

LAMP

ON

WAL

L AT

2200

HIG

H ,

OTHE

R FL

UORE

SCEN

T LA

MPS

ON W

ALL A

T 28

00 H

IGH

CBMB

TMC

CBMB

PAVE

MENT

'A''A'

'B'

'B'

'C' 'C'50

400 50

500

75

50

500

900

50

800

150

2400800

75

50

757575

4600

300x

300x

300 S

UMP

PIT

WIT

H G.

I. GR

ATIN

G CO

VER

WB

55 D

IA. O

PENI

NG O

N W

ALL F

OR H

EC E

ARTH

TAP

E ( S

EE D

ETAI

L 'A'

)

TRAN

SIT

BLOC

K W

ITH

CENT

RE LI

NE A

T 15

70 H

IGH

( DET

AILS

REF

ER T

O DR

AWIN

G No

. P31

4/96/R

-3 )

400 W

IDE

300 R

ISE

STAI

NLES

S ST

EEL C

AT LA

DDER

WIT

H HA

NDRA

IL AN

D AN

TI-S

KID

STEP

S

HIGH

LEVE

L HAZ

ARD

ZONE

(DE

TAILS

REF

ER T

O DR

AWIN

G No

. P34

6/97 )

1800

LONG

STA

INLE

SS S

TEEL

CHA

IN( I

N W

EIGH

T OF

3 kg

/ MET

RE IN

LINE

AR M

EASU

REME

NT )

FIX

ED O

N BO

TH S

IDES

OF

THE

VERT

ICAL

HAN

DLE

AND

LOOS

ELY

SAGG

ED O

N SU

BSTA

TION

FLO

OR F

OR S

UPPO

RTIN

G US

E

100

150

200SW

ING

TYPE

800x

800 H

EAVY

DUT

Y G.

I. GR

ATIN

G TO

BE

FITT

ED F

LUSH

WIT

H SU

BSTA

TION

FLO

OR

SWIN

G TY

PE 80

0x80

0 HEA

VY D

UTY

G.I.

GRAT

ING

IN 2

PIEC

ESTO

BE

FITT

ED F

LUSH

WIT

H SU

BSTA

TION

FLO

OR

50 D

IA. 1

000 H

IGH

STAI

NLES

S ST

EEL P

OST

FAST

ENED

ON

FLOO

R (

SEE

DETA

IL 'B

' )

425

EART

HING

POI

NT F

OR C

HEQU

ER P

LATE

50x5

0 SLO

T OP

ENIN

G AT

CHE

QUER

PLA

TE

150 W

IDE

U-CH

ANNE

LTO

BE

INST

ALLE

D FL

USH

WIT

H SU

BSTA

TION

FLO

OR

1 PI

ECE

OF 20

0x50

0 CHE

QUER

PLA

TE

350

R950

( CAB

LE E

NTRY

DUC

T EX

TEND

ED T

O SI

TE B

OUND

ARY

)

AREA

OF

1350

x500

COV

ERED

WIT

H3 P

IECE

S OF

CHE

QUER

PLA

TE50 150

PLAN

OF

TRAN

SFOR

MER

COMP

ARTM

ENT

& HV

SW

ITCH

GEAR

COM

PART

MENT

5001550

1350

115 W

IDE

OPEN

ING

AT T

OP &

BOT

TOM

ON W

ALL &

55 D

IA.

OPEN

ING

ON W

ALL F

OR H

EC E

ARTH

TAP

E ( S

EE D

ETAI

L 'A'

)

100X

100

SLOT

OPE

NING

AT

CHEQ

UER

PLAT

E

400

50

450

300

3700

4300

6x 15

0 DIA

. AND

6x 75

DIA

. UPV

C CA

BLE

ENTR

Y DU

CT( M

IN. 5

00 LO

NG )

AS

PER

DRAW

ING

No. P

627/0

5/R-1

HING

E OF

GRA

TING

FLU

SH W

ITH

SUBS

TATI

ON F

LOOR

HING

E OF

GRA

TING

FLU

SH W

ITH

SUBS

TATI

ON F

LOOR

HIGH

LEVE

L HAZ

ARD

ZONE

( DET

AILS

REF

ER T

O DR

AWIN

G No

. P34

6/97 )

EART

HING

BRA

CKET

WIT

H EA

RTHI

NG P

ITBO

NDED

TO

THE

BUILD

ING

MAIN

EAR

THIN

GAT

TRE

NCH

OPEN

ING

( DET

AILS

REF

ER T

O DR

AWIN

G No

. P57

4/02/R

-1 )

H.V.

L.V.

N L3 L2 L1

L1 L

2 L3 N

E

4 PIE

CES

OF 50

0x12

5 CHE

QUER

PLA

TE

500

500

1280

1530

400

10001000

178018

0015

0

150

BATT LV

CBMB CBMB

75

TRANSFORMER

500

150

500 D

EEP

CABL

E TR

ENCH

2x 15

0 DIA

. CAB

LE D

UCT

IN 2

LAYE

RS A

T BO

TTOM

OF

TREN

CHTO

BE

SEAL

ED O

FF W

ITH

FIRE

RES

ISTA

NT M

ATER

IAL

BY D

EVEL

OPER

AFT

ER T

MC C

ABLE

INST

ALLE

D

500

500

8 PIE

CES

OF 70

0x30

0 CHE

QUER

PLA

TE80

070

0

400

REMO

VABL

E ST

AINL

ESS

STEE

L GUA

RD C

HAIN

WIT

H HO

OK

REMO

VABL

E ST

AINL

ESS

STEE

L GUA

RD C

HAIN

WIT

H HO

OK

900

EART

HING

POI

NT F

OR G

RATI

NG

EART

HING

POI

NT F

OR G

RATI

NG

400 W

IDE

300 R

ISE

AND

300 W

IDE

300 R

ISE

STAI

NLES

S ST

EEL C

AT LA

DDER

WIT

H HA

NDRA

IL AN

D AN

TI-S

KID

STEP

S

MIN

. 50

STAI

NLES

S ST

EEL L

OUVR

E AT

HIG

H LE

VEL F

OR E

XHAU

ST A

IR D

UCT

COMBINEDL.V. ISOLATOR PANEL& L.V. PANEL

ENCL.B/B

MIN

. 50

MIN

. 50

TRAN

SFOR

MER

COMP

ARTM

ENT

NOTE

:WID

TH O

F TR

ENCH

SHA

LL B

E TH

E ME

ASUR

ED S

PACE

BETW

EEN

EDGE

S OF

CHE

QUER

PLA

TE A

ND S

UPPO

RTIN

GAN

GLES

115 W

IDE

OPEN

ING

AT B

OTTO

M ON

WAL

L &55

DIA

. OPE

NING

ON

WAL

L FOR

HEC

EAR

TH T

APE

( SEE

DET

AIL '

A' )

RAMPUP

EART

HING

POI

NT F

OR C

HEQU

ER P

LATE

50x5

0 SLO

T OP

ENIN

G AT

CHE

QUER

PLA

TE

150 W

IDE

U-CH

ANNE

LTO

BE

INST

ALLE

D FL

USH

WIT

H SU

BSTA

TION

FLO

OR

2000

x260

0(H)

STAI

NLES

S ST

EEL D

OUBL

E LE

AF D

OOR

WIT

HOUT

LOUV

RE( D

RG. N

o. P

592/0

3/R-5

)

920x

2300

(H)

STAI

NLES

S ST

EEL P

ARTI

TION

DOO

R W

ITHO

UT LO

UVRE

AS P

ER D

RAW

ING

No. P

479/0

0/R-6

2000

x260

0(H)

STAI

NLES

S ST

EEL D

OUBL

E LE

AF D

OOR

WIT

H LO

UVRE

S( D

RG. N

o. P

591/0

3/R-5

)

RAMP

UP

750 L

ONG

STAI

NLES

S ST

EEL 5

0 DIA

. VER

TICA

LHA

NDLE

FIX

ED O

N W

ALL

( SEE

DET

AIL '

C' )

600x

600(

H) S

TAIN

LESS

STE

ELLO

UVRE

AT

HIGH

LEVE

L

75 D

IA. D

RAIN

HOL

E TO

BUI

LDIN

G MA

IN D

RAIN

AGE

SYST

EM( W

ITH

COVE

R AN

D NO

N-RE

TURN

VAL

VE A

S FL

OOD

GATE

TO P

REVE

NT B

ACKW

ARD

FLOW

OF

DRAI

N W

ATER

. DET

AILS

TO B

E SU

BMIT

TED

BY D

EVEL

OPER

TO

HEC

FOR

APPR

OVAL

)

FLOO

R OP

ENIN

G TO

BE

COVE

RED

WIT

H CH

EQUE

R PL

ATES

1800

LONG

STA

INLE

SS S

TEEL

CHA

IN (

IN W

EIGH

T OF

3 kg

/ MET

RE IN

LINE

ARME

ASUR

EMEN

T )

FIXE

D ON

BOT

H SI

DES

OF T

HE V

ERTI

CAL H

ANDL

E AN

DLO

OSEL

Y SA

GGED

ON

SUBS

TATI

ON F

LOOR

FOR

SUP

PORT

ING

USE

R.C.

STR

UCTU

RE T

O SU

PPOR

T SW

ITCH

GEAR

IN A

ROW

IN T

OTAL

WEI

GHT

NOT

LESS

THA

N 40

00 kg

f50

DIA

. 100

0 HIG

H ST

AINL

ESS

STEE

L POS

TFA

STEN

ED O

N FL

OOR

( SE

E DE

TAIL

'B' )

750 L

ONG

STAI

NLES

S ST

EEL 5

0 DIA

. VER

TICA

L HAN

DLE

FIXE

D ON

WAL

L ( S

EE D

ETAI

L 'C'

)

75150150 150

75

* *

50-m

m-IN

TERN

AL-D

IAME

TER

PAD

EYE

WEL

DED

ONTO

A 10

0x10

0 6-m

m-TH

ICK

STAI

NLES

SST

EEL B

RACK

ET (

SEE

DETA

IL 'D

' )

2x 50

-mm-

INTE

RNAL

-DIA

METE

R PA

D EY

E W

ELDE

D ON

TO A

100x

100 6

-mm

-THI

CK S

TAIN

LESS

STE

EL B

RACK

ET A

T 20

0 mm

AND

900 m

m AB

OVE

TREN

CH B

OTTO

M RE

SPEC

TIVE

LY (S

EE D

ETAI

L 'D'

)

1x 50

-mm-

INTE

RNAL

-DIA

METE

R PA

D EY

E W

ELDE

D ON

TOA

100x

100 6

-mm-

THIC

K ST

AINL

ESS

STEE

L BRA

CKET

AT

900 m

mAB

OVE

TREN

CH B

OTTO

M (S

EE D

ETAI

L 'D'

)

RAMPUP

600

MIN

. 50

( CAB

LE E

NTRY

DUC

T EX

TEND

ED T

O SI

TE B

OUND

ARY

)

130x

130

WAL

L OPE

NING

FOR

EME

RGEN

CY W

IRIN

G( D

ETAI

LS R

EFER

TO

DRAW

ING

No. P

638/0

6 )

4x 15

0 DIA

. AND

6x75

DIA

. UPV

C CA

BLE

ENTR

Y DU

CT( M

IN. 5

00 LO

NG )

AS

PER

DRAW

ING

No. P

627/0

5/R-1

MIN

. 50

MIN

. 500

1000450

RAMPUP

200

EART

HING

POI

NT F

OR G

RATI

NG

1050

DEE

P CA

BLE

TREN

CHTO

BE

COVE

RED

WIT

H CH

EQUE

R PL

ATES

500

500

UPST

REAM

SILE

NCER

900

300 H

IGH

SLOT

AT

TREN

CH B

OTTO

M

2500

CABL

E TR

ENCH

UND

ERNE

ATH

6x 15

0 DIA

. & 6x

75 D

IA. P

VC C

ABLE

ENT

RY D

UCT

( MIN

. 500

LONG

) AS

PER

DRA

WIN

G No

. P62

7/05/R

-1( C

ABLE

ENT

RY D

UCT

EXTE

NDED

TO

SITE

BOU

NDAR

Y )

HV SWIT

CHGE

ARCO

MPAR

TMEN

T

'D'

'D'

6x75

DIA

. UPV

C DU

CTS

IN 3

LAYE

RS

500 W

IDE

SLOT

UND

ER F

LOOR

SLA

B

1000

x100

0(H)

STA

INLE

SS S

TEEL

LOUV

RES

AT T

OP &

BOT

TOM

( LOW

ER O

NE T

O BE

300 A

BOVE

FLO

OR A

ND S

CREE

NED

WIT

H 10

-mm

S.S.

WIR

E ME

SH IN

SIDE

)

400

700

400 D

rg. N

o. G

CS/

3/11

TYPI

CA

L LA

YO

UT

FOR

1 -

TX. S

UB

STA

TIO

N W

ITH

HV

CA

BLE

PIT

(P51

2/00

/R-7

) SH

EET

1 O

F 5

3.28

150

MIN. 3400 HEADROOM CLEAR UNDER BEAM

FALL

1 : 5

0

150

1800

1200

900200

200900

50 D

IA.

1000

HIG

H ST

AINL

ESS

STEE

LPO

ST F

ASTE

NED

ON

FLO

OR

( SE

E DE

TAIL

'B' )

REM

OVA

BLE

STAI

NLES

S ST

EEL

GUA

RD C

HAIN

WIT

H HO

OK

750

LONG

STA

INLE

SS S

TEEL

50

DIA.

VER

TICA

L HA

NDLE

FIXE

D O

N W

ALL

( SE

E DE

TAIL

'C' )

SWIN

G T

YPE

800x

800

HEAV

Y DU

TY G

.I. G

RATI

NGIN

2 P

IECE

S TO

BE

FITT

ED F

LUSH

WIT

HSU

BSTA

TIO

N FL

OO

R

HV SWIT

CHGE

ARCO

MPA

RTM

ENT

R.C.

C. C

ANO

PY

600x

600(

H) S

TAIN

LESS

STE

EL L

OUV

RE A

T HI

GH

LEVE

L

PAVE

MEN

T

1800

LO

NG S

TAIN

LESS

STE

EL C

HAIN

FIX

ED O

N BO

THSI

DES

OF

THE

VERT

ICAL

HAN

DLE

AND

LOO

SELY

SAG

GED

ON

SUBS

TATI

ON

FLO

OR

FOR

SUPP

ORT

ING

USE

750

LONG

STA

INLE

SS S

TEEL

50

DIA.

VER

TICA

L HA

NDLE

FIXE

D O

N W

ALL

( SE

E DE

TAIL

'C' )

38 D

IA.

DRAI

N HO

LE W

ITH

PRO

PER

CONN

ECTI

ON

TO B

UILD

ING

MAI

N DR

AIN

SYST

EM

HV C

ABLE

PIT

1600

WID

E CL

EARA

NCE

( WIT

HOUT

ANY

UND

ERG

ROUN

D O

BSTA

CLE

)AT

CAB

LE E

NTRY 6x 15

0 DIA

. AND

6x 75

DIA

. UPV

C CA

BLE

ENTR

Y DU

CT( M

IN. 5

00 LO

NG )

AS

PER

DRAW

ING

No. P

627/0

5/R-1

( CAB

LE E

NTRY

DUC

T EX

TEND

ED T

O SI

TE B

OUND

ARY

)

SWIN

G TY

PE 80

0x80

0 HEA

VY D

UTY

G.I.

GRAT

ING

IN 2

PIEC

ES T

O BE

FIT

TED

FLUS

H W

ITH

SUBS

TATI

ON F

LOOR

REM

OVA

BLE

STAI

NLES

S ST

EEL

GUA

RD C

HAIN

WIT

H HO

OK

50 D

IA.

1000

HIG

H ST

AINL

ESS

STEE

LPO

ST F

ASTE

NED

ON

FLO

OR

( SE

E DE

TAIL

'B' )

400 W

IDE

300 R

ISE

AND

300 W

IDE

300 R

ISE

STAI

NLES

SST

EEL C

AT LA

DDER

WIT

H HA

NDRA

IL AN

D AN

TI-S

KID

STEP

S

REF.

LEV

EL

SECT

ION

'A' -

'A'

R.C.

STR

UCTU

RE T

O S

UPPO

RT S

WIT

CHG

EAR

IN A

RO

W IN

TO

TAL

WEI

GHT

NO

T LE

SSTH

AN 4

000

kgf

400

WID

E 30

0 RI

SE S

TAIN

LESS

STE

EL C

AT L

ADDE

RW

ITH

HAND

RAIL

AND

ANT

I-SKI

D ST

EPS

1800

LO

NG S

TAIN

LESS

STE

EL C

HAIN

FIX

ED O

N BO

THSI

DES

OF

THE

VERT

ICAL

HAN

DLE

AND

LOO

SELY

SAG

GED

ON

SUBS

TATI

ON

FLO

OR

FOR

SUPP

ORT

ING

USE

50-m

m-IN

TERN

AL-D

IAM

ETER

PAD

EYE

WEL

DED

ONT

OA

100x

100

6-m

m-T

HICK

STA

INLE

SS S

TEEL

BRA

CKET

( SEE

DET

AIL

'D' )

50-m

m-IN

TERN

AL-D

IAM

ETER

PAD

EYE

WEL

DED

ONT

OA

100x

100

6-m

m-T

HICK

STA

INLE

SS S

TEEL

BRA

CKET

( SEE

DET

AIL

'D' )

300x

300x

300 S

UMP

PIT

WIT

H G.

I. GR

ATIN

G CO

VER

FALL

1 : 5

0

2000

x260

0(H)

STA

INLE

SS S

TEEL

DO

UBLE

LEA

F DO

OR

WIT

HOUT

LO

UVRE

( RE

FER

TO D

RAW

ING

No.

P59

2/03

/R-5

)

DOUB

LE-S

LAB

CEIL

ING

CO

NSTR

UCTI

ON

ASPE

R IT

EM 1

.13

OF

DRAW

ING

NO

. P58

5/03

/R-5

Drg

. No.

GC

S/3/

11TY

PIC

AL

LAY

OU

T FO

R 1

- TX

. SU

BST

ATI

ON

WIT

H H

V C

AB

LE P

IT(P

512/

00/R

-7) S

HEE

T 2

OF

5

NO

TE:

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.29

MIN. 3400 HEADROOM CLEAR UNDER BEAM

1050

1050

150

300150

MIN. 2700

300

400

1200

I R

200

2000

x260

0(H)

STA

INLE

SS S

TEEL

DO

UBLE

LEA

F DO

OR

WIT

H LO

UVRE

S ( R

EFER

TO

DRA

WIN

G N

o. P

591/

03/R

-5 )

600x

600(

H) S

TAIN

LESS

STE

EL L

OUV

RE A

T HI

GH

LEVE

L

400

WID

E 30

0 RI

SE A

ND 3

00 W

IDE

300

RISE

STA

INLE

SSST

EEL

CAT

LADD

ER W

ITH

HAND

RAIL

AND

ANT

I-SKI

D ST

EPS

6x 1

50 D

IA.

AND

6x 7

5 DI

A. U

PVC

CABL

E EN

TRY

DUCT

( MIN

. 50

0 LO

NG )

AS P

ER D

RAW

ING

No.

P62

7/05

/R-1

R.C.

STR

UCTU

RE T

O S

UPPO

RT S

WIT

CHG

EAR

IN A

RO

W IN

TO

TAL

WEI

GHT

NO

T LE

SS T

HAN

4000

kgf

1 N

o. O

F TW

IN 1

3-A

SOCK

ET T

O IP

65

SWIN

G T

YPE

800x

800

HEAV

Y DU

TY G

.I. G

RATI

NG IN

2 P

IECE

STO

BE

FITT

ED F

LUSH

WIT

H SU

BSTA

TIO

N FL

OO

R

1800

LO

NG S

TAIN

LESS

STE

EL C

HAIN

FIX

ED O

N BO

TH S

IDES

OF

THE

VERT

ICAL

HAN

DLE

AND

LOO

SELY

SAG

GED

ON

SUBS

TATI

ON

FLO

OR

FOR

SUPP

ORT

ING

USE

REM

OVA

BLE

STAI

NLES

S ST

EEL

GUA

RD C

HAIN

WIT

H HO

OK

50 D

IA.

1000

HIG

H ST

AINL

ESS

STEE

L PO

ST F

ASTE

NED

ON

FLO

OR

( SEE

DET

AIL

'B' )

HV SWIT

CHGE

ARCO

MPA

RTM

ENT

38 D

IA.

DRAI

N HO

LE W

ITH

PRO

PER

CONN

ECTI

ON

TO B

UILD

ING

MAI

N DR

AIN

SYST

EM

2000

x260

0(H)

STA

INLE

SS S

TEEL

DO

UBLE

LEA

F DO

OR

WIT

HOUT

LO

UVRE

( REF

ER T

O D

RAW

ING

No.

P59

2/03

/R-5

)

750

LONG

STA

INLE

SS S

TEEL

50

DIA.

VER

TICA

L HA

NDLE

FIXE

D O

N W

ALL

( SE

E DE

TAIL

'C' )

SIDE

INSP

ECTI

ON

PANE

L O

F M

INIM

UN S

IZE

150(

W)x

100(

H)

STAI

NLES

S ST

EEL

LOUV

RE A

T HI

GH

LEVE

L FO

R EX

HAUS

T AI

R DU

CTDO

UBLE

-SLA

B CE

ILIN

G C

ONS

TRUC

TIO

N AS

PER

ITEM

1.1

3 O

F DR

AWIN

G N

O. P

585/

03/R

-3

38 D

IA.

DRAI

N HO

LE W

ITH

PRO

PER

CONN

ECTI

ON

TO B

UILD

ING

MAI

N DR

AIN

SYST

EM

1000

x100

0(H)

STA

INLE

SS S

TEEL

LO

UVRE

S AT

TO

P &

BOTT

OM

( LO

WER

ONE

TO

BE

300

ABO

VE F

LOO

R AN

D SC

REEN

ED W

ITH

WIR

E M

ESH

INSI

DE )

130x

130

WAL

L O

PENI

NG F

OR

EMER

GEN

CY W

IRIN

G( D

ETAI

LS R

EFER

TO

DRA

WIN

G N

o. P

638/

06 )

150

HIG

H DO

OR

SILL

4x 1

50 D

IA.

UPVC

CAB

LE E

NTRY

DUC

T ( M

IN.

500

LONG

)AS

PER

DRA

WIN

G N

o. P

627/

05/R

-1

150

WID

E U-

CHAN

NEL

TO B

E IN

STAL

LED

FLUS

H W

ITH

SUBS

TATI

ON

FLO

OR

STAI

NLES

S ST

EEL

HAND

LE O

N SI

DEW

ALL

OF

RAM

P

6x 1

50 D

IA.

AND

6x 7

5 DI

A. U

PVC

CABL

E EN

TRY

DUCT

( MIN

. 50

0 LO

NG )

AS

PER

DRAW

ING

No.

P62

7/05

/R-1

SECT

ION

'B' -

'B'

920x

2300

(H)

STAI

NLES

S ST

EEL

PART

ITIO

N DO

OR

WIT

HOUT

LO

UVRE

AS P

ER D

RAW

ING

No.

P47

9/00

/R-6

TRAN

SFOR

MER

COM

PART

MEN

T

2500

900

300x

300x

300

SUM

P PI

T W

ITH

G.I.

GRA

TING

CO

VER

RAM

PUP

50-m

m-IN

TERN

AL-D

IAM

ETER

PAD

EYE

WEL

DED

ONT

O A

100

x100

6-m

m-T

HICK

STA

INLE

SS S

TEEL

BRA

CKET

(SEE

DET

AIL

'D')

I R1.

2-m

-LO

NG IM

PACT

RES

ISTA

NT T

YPE

FLUO

RESC

ENT

LAM

P AT

2-m

SEP

ARAT

ION

IMM

EDIA

TE B

ELO

W R

.C.

STRU

CTUR

E / S

LAB

HV CABL

EPI

T

1050

DEE

P CA

BLE

TREN

CH T

O B

ECO

VERE

D W

ITH

CHEQ

UER

PLAT

ES

500

WID

E SL

OT

UNDE

R FL

OO

R SL

AB

Drg

. No.

GC

S/3/

11TY

PIC

AL

LAY

OU

T FO

R 1

- TX

. SU

BST

ATI

ON

WIT

H H

V C

AB

LE P

IT(P

512/

00/R

-7) S

HEE

T 3

OF

5

NO

TE:

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.30

3.31

Drg

. No.

GC

S/3/

11TY

PIC

AL

LAY

OU

T FO

R 1

- TX

. SU

BST

ATI

ON

WIT

H H

V C

AB

LE P

IT(P

512/

00/R

-7) S

HEE

T 5

OF

5

NO

TE :

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.32

N B

Y R

H.V.

N B Y R

H.V.

TMC

T

TT

TT

TXT LVT

1050

DEE

P CA

BLE

TREN

CH

FOR

FAN

No.2

130x

130 W

ALL O

PENI

NG F

OR E

MERG

ENCY

MCBB

EART

HING

POI

NT F

OR C

HEQU

ER P

LATE

FOR

FAN

No.1

R.C.

C.

CANO

PY

FOR

TRAN

SFOR

MER

No.1

3 PIE

CES

OF 45

0x10

0 CHE

QUER

PLA

TE

4500

CMH

AXI

AL F

LOW

FAN

No.1

4500

CMH

AXI

AL F

LOW

FAN

No.2

STEE

L ADA

PTOR

TRU

NKIN

G

1050

DEE

P CA

BLE

TREN

CH

FOR

TRAN

SFOR

MER

No.2

SWIT

CH R

OOM

500

500

*

PLAN

1780

500

SIDE

OPE

RATE

D L.V

. ISO

LATO

R PA

NEL

50

500

50

STEE

L ADA

PTOR

TRU

NKIN

G

50

825

NOT LESS

710

1000

STAI

NLES

S ST

EEL L

OUVR

E AT

HIG

H LE

VEL F

OR E

XHAU

ST A

IR D

UCT

TXT

4450

3700

RTUOPT

BATT

CBMB

150 H

IGH

DOOR

SILL

600x

500(

H) S

TAIN

LESS

STE

EL LO

UVRE

AT

HIGH

LEVE

L

HING

E OF

GRA

TING

CBMB

CBMB

TMC

CBMB

PAVE

MENT

R.C.

C.

CANO

PY

300

50

300

50

800 150800150

900

700

300

300

T

50

55 D

IA. O

PENI

NG O

N W

ALL F

OR H

EC E

ARTH

TAP

E (

SEE

DETA

IL 'A

' )

CBMB CBMB CBMB CBMB

WB

400 W

IDE

300 R

ISE

STAI

NLES

S ST

EEL C

AT LA

DDER

WIT

H HA

NDRA

IL AN

D AN

TI-S

KID

STEP

S

7600

400 W

IDE

300 R

ISE

STAI

NLES

S ST

EEL C

AT LA

DDER

WIT

H HA

NDRA

IL AN

D AN

TI-S

KID

STEP

S

300x

300x

300 S

UMP

PIT

WIT

H G.

I. GR

ATIN

G CO

VER

55 D

IA. O

PENI

NG O

N W

ALL F

OR H

EC E

ARTH

TAP

E

HIGH

LEVE

L HAZ

ARD

ZONE

( D

ETAI

LS R

EFER

TO

DRAW

ING

No. P

346/9

7 )

1100

50x5

0 SLO

T OP

ENIN

G AT

CHE

QUER

PLA

TE

100x

100 S

LOT

OPEN

ING

AT C

HEQU

ER P

LATE

THAN 1000

450

440

200k

VAr

CAP.

BAN

K

750 L

ONG

STAI

NLES

S ST

EEL 5

0 DIA

. VER

TICA

L HAN

DLE

FIXE

D ON

WAL

L ( S

EE D

ETAI

L 'C'

)

50 D

IA. 1

000 H

IGH

STAI

NLES

S ST

EEL P

OST

FAST

ENED

ON

FLOO

R (

SEE

DETA

IL 'B

' )

STAI

NLES

S ST

EEL G

UARD

CHA

IN

50 D

IA. 1

000 H

IGH

STAI

NLES

S ST

EEL P

OST

FAST

ENED

ON

FLOO

R (

SEE

DETA

IL 'B

' )

STAI

NLES

S ST

EEL G

UARD

CHA

IN

750 L

ONG

STAI

NLES

S ST

EEL 5

0 DIA

. VER

TICA

L HAN

DLE

FIXE

D ON

WAL

L ( S

EE D

ETAI

L 'C'

)

SWIN

G TY

PE 80

0x80

0 HEA

VY D

UTY

G.I.

GRAT

ING

IN 2

PIEC

ES T

O BE

FIT

TED

FLUS

H W

ITH

SUBS

TATI

ON F

LOOR

HING

E OF

GRA

TING

300

450

300

1200

3 PIE

CES

OF 45

0x10

0 CHE

QUER

PLA

TE

700

50

2000

( CAB

LE E

NTRY

DUC

T EX

TEND

ED T

O SI

TE B

OUND

ARY

)

2500

500 1500500

HV SWIT

CHGE

ARCO

MPAR

TMEN

T

8x 15

0 DIA

. UPV

C CA

BLE

ENTR

Y DU

CT (

MIN.

500 L

ONG

) IN

2 LA

YERS

& 6x

75 D

IA U

PVC

DUCT

S IN

3 LA

YERS

AS P

ER D

RAW

ING

No. P

627/0

5/R-1

( CA

BLE

ENTR

Y DU

CT E

XTEN

DED

TO S

ITE

BOUN

DARY

)

4x 15

0 DIA

. UPV

C CA

BLE

ENTR

Y DU

CT (

MIN.

500 L

ONG

) IN

2 LA

YERS

AS

PER

DRAW

ING

No. P

627/0

5/R-1

TELBATTLV

'B'

'B'

'A''A'

115 W

IDE

OPEN

INGS

AT

TOP

AND

BOTT

OM O

N W

ALL &

( SEE

DET

AIL '

A' )

EART

HING

BRA

CKET

WIT

H EA

RTHI

NG P

ITBO

NDED

TO

THE

BUILD

ING

MAIN

EAR

THIN

GAT

TRE

NCH

BOTT

OM( D

ETAI

LS R

EFER

TO

DRAW

ING

No. P

574/0

2/R-1

)

( DRG

. No.

P59

1/03/R

-5 )

( DRG

. No.

P59

2/03/R

-5 )

100x

100

SLOT

OPE

NING

AT

CHEQ

UER

PLAT

E

EART

HING

POI

NT

EART

HING

POI

NT

EART

HING

POI

NT

1800

LONG

STA

INLE

SS S

TEEL

CHA

IN( I

N W

EIGH

T OF

3 kg

/ MET

RE IN

LINE

AR M

EASU

REME

NT )

FIX

ED O

N BO

TH S

IDES

OF

THE

VERT

ICAL

HAN

DLE

AND

LOOS

ELY

SAGG

ED O

N SU

BSTA

TION

FLO

OR F

OR S

UPPO

RTIN

G US

E

50-m

m-IN

TERN

AL-D

IAME

TER

PAD

EYE

WEL

DED

ONTO

A 10

0x10

0 6-m

m-T

HICK

STA

INLE

SS S

TEEL

BRA

CKET

(SEE

DET

AIL '

D')

THES

E 3 F

LUOR

ESCE

NT LA

MPS

ON W

ALL A

T 22

00 H

IGH

,OT

HER

FLUO

RESC

ENT

LAMP

S ON

WAL

L AT

2800

HIG

H

1800

LONG

STA

INLE

SS S

TEEL

CHA

IN( I

N W

EIGH

T OF

3 kg

/ MET

RE IN

LINE

AR M

EASU

REME

NT )

FIX

ED O

N BO

TH S

IDES

OF

THE

VERT

ICAL

HAN

DLE

AND

LOOS

ELY

SAGG

ED O

N SU

BSTA

TION

FLO

OR F

OR S

UPPO

RTIN

G US

E50

mm IN

TERN

AL D

IAME

TER

PAD

EYE

WEL

DED

ONTO

A 10

0x10

0 6-m

m-T

HICK

STA

INLE

SS S

TEEL

BRA

CKET

(SEE

DET

AIL '

D')

RAMP UP

( SUB

STAT

ION

FLO

OR IS

AT

150

HIG

HER

THA

N O

UTSI

DE LE

VEL )

'C'

'C'

TRANSFORMER No.2

TRAN

SFOR

MER

No.1

700

RAMP UP

DOW

N-ST

REAM

SILE

NCER

COMB

INED

L.V.

ISOL

ATOR

PAN

EL&

L.V. P

ANEL

ENCL

.B/

B

RAMP UP

8x 15

0 DIA

. UPV

C CA

BLE

ENTR

Y DU

CT (

MIN.

500 L

ONG

) IN

2 LA

YERS

AS P

ER D

RAW

ING

No. P

627/0

5/R-1

( CAB

LE E

NTRY

DUC

T EX

TEND

ED T

O SI

TE B

OUND

ARY

)

920x

2300

(H)

STAI

NLES

S ST

EEL P

ARTI

TION

DOO

R W

ITHO

UT LO

UVRE

AS P

ER D

RAW

ING

No. P

479/0

0/R-6

2000

x260

0(H)

STAI

NLES

S ST

EEL

DOUB

LE LE

AF D

OOR

WIT

H LO

UVRE

S

2000

x260

0(H)

STAI

NLES

S ST

EEL

DOUB

LE LE

AFDO

ORW

ITHO

UT LO

UVRE

6x75

DIA

UPV

C DU

CTS

IN 3

LAYE

RS A

S PE

R DR

AWIN

G No

. P62

7/05/R

-1( C

ABLE

ENT

RY D

UCT

EXTE

NDED

TO

SITE

BOU

NDAR

Y )

4 Nos

. 100

0x10

00 S

TAIN

LESS

STE

EL LO

UVRE

AT

TOP

AND

BOTT

OM( L

OWER

ONE

TO

BE S

CREE

NED

WIT

H 10

-mm

WIR

E ME

SH IN

SIDE

)

RAMP UP

CABL

E PA

SSAG

E UN

DER

WAL

L

6x 75

DIA

. CAB

LE E

NTRY

DUC

TS IN

3 LA

YERS

1650 1500

CABL

E PA

SSAG

E UN

DER

WAL

L

ENCL

.B/

B

TRAN

SIT

BLOC

K No

.2W

ITH

CENT

RE LI

NE A

T 15

70 A

FFL

1300

800

600 1350

VFC VFC

E N L3 L2 L1 E N L3 L2 L1

RAMPUP

SWIN

G TY

PE 80

0x80

0 HEA

VY D

UTY

G.I.

GRAT

ING

IN 2

PIEC

ESTO

BE

FITT

ED F

LUSH

WIT

H SU

BSTA

TION

FLO

OR

150 W

IDE

U-CH

ANNE

L TO

BE IN

STAL

LED

FLUS

H W

ITH

SUBS

TATI

ON F

LOOR

UPST

REAM

SILE

NCER

TRAN

SIT

BLOC

K No

.1W

ITH

CENT

RE LI

NE A

T 15

70 A

FFL

AREA

OF

1300

x500

COV

ERED

WIT

H3 P

IECE

S OF

CHE

QUER

PLA

TE

100

DOW

N-ST

REAM

SILE

NCER

UPST

REAM

SILE

NCER

2x 15

0 DIA

. CAB

LE D

UCT

FOR

TMC

CABL

E AT

200 m

mAB

OVE

BOTT

OM O

F TR

ENCH

TO

BE S

EALE

D OF

FW

ITH

FIRE

RES

ISTA

NT A

ND W

ATER

-PRO

OFIN

G MA

TERI

ALBY

DEV

ELOP

ER A

FTER

TMC

CAB

LE IN

STAL

LED

75 D

IA. D

RAIN

HOL

E TO

BUI

LDIN

G MA

IN D

RAIN

AGE

SYST

EM( W

ITH

COVE

R AN

D NO

N-RE

TURN

VAL

VE A

S FL

OOD

GATE

TO

PREV

ENT

BACK

WAR

D FL

OWOF

DRA

IN W

ATER

. DET

AILS

TO

BE S

UBMI

TTED

BY

DEVE

LOPE

R TO

HEC

FOR

APP

ROVA

L )

1000kg1000kg1000kg1000kg1000kg1000kg1000kg1000kg1000kg

R.C.

STR

UCTU

RE T

O SU

PPOR

T SW

ITCH

GEAR

IN A

ROW

IN T

OTAL

WEI

GHT

NOT

LESS

THA

N 90

00 kg

f

1710

( SUB

STAT

ION

FLOO

R IS

AT

150

HIGH

ER T

HAN

OUTS

IDE

LEVE

L )

TRAN

SFOR

MER

COMP

ARTM

ENT

EART

HING

POI

NT F

OR C

HEQU

ER P

LATE

500

800

Drg

. No.

GC

S/3/

12TY

PIC

AL

LAY

OU

T FO

R T

WIN

TR

AN

SFO

RM

ER S

UB

STA

TIO

N W

ITH

HV

CA

BLE

PIT

(P58

4/03

/R-2

) SH

EET

1 O

F 4

NO

TE:

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.33

Drg

. No.

GC

S/3/

12TY

PIC

AL

LAY

OU

T FO

R T

WIN

TR

AN

SFO

RM

ER S

UB

STA

TIO

N W

ITH

HV

CA

BLE

PIT

(P58

4/03

/R-2

) SH

EET

2 O

F 4

NO

TE :

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.34

Drg

. No.

GC

S/3/

12TY

PIC

AL

LAY

OU

T FO

R T

WIN

TR

AN

SFO

RM

ER S

UB

STA

TIO

N W

ITH

HV

CA

BLE

PIT

(P58

4/03

/R-2

) SH

EET

3 O

F 4

NO

TE :

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.35

Drg

. No.

GC

S/3/

12TY

PIC

AL

LAY

OU

T FO

R T

WIN

TR

AN

SFO

RM

ER S

UB

STA

TIO

N W

ITH

HV

CA

BLE

PIT

(P58

4/03

/R-2

) SH

EET

4 O

F 4

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.36

3.37

3.38

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

DETAILED REQUIREMENTS OF SUBSTATION

1. BUILDER'S WORK 1.1 No construction joint nor expansion joint shall be constructed within a

substation and at the substation enclosure. 1.2 Unless otherwise specified in the substation layout drawing, the substation shall

have a clear headroom of 3400 mm. The substation floor shall be designed and constructed to withstand the weight of transformer, its associated HV switchgear and control equipment, each set of which is 10,000 kgf. The substation structure shall be designed to an average floor loading of not less than 20 kPa. Also all the floor area within the substation must be capable of withstanding a concentrated load of 100 kN over two Nos. of 40-mm x 600-mm rectangular strips which are the bottom channels of the above equipment. For those substations to be installed with HV switchgear only or those substations with a separate compartment solely for housing HV switchgear only, the substation floor designed to an average floor loading of not less than 10 kPa to withstand the weight of HV switchgear in such substations can be accepted. Before handing over the substation, the architect must submit detailed structural drawings, structure calculation and a certificate duly signed by a registered structural engineer, indicating that the substation structure has been designed and constructed to such requirements for HK Electric record.

1.3 The wall and ceiling of substation must be of construction including material and

thickness, etc., complying with regulations of Fire Services Department (FSD) and Building Department. The substation wall shall preferably be of reinforced concrete construction, but brick of clay to BS.3921, concrete brick to BS.6073 can also be accepted. Hollow blockwork in the substation will not be accepted.

1.4 The substation wall and ceiling shall be cemented, sand plastered and finished

with one coat of liquid prepolymer sealer and two finishing coats of acrylic resin based coating in gloss white finish. Substation floor shall be cemented, sand rendered in trowelled smooth finish. For anti-skid reasons, no coating nor painting shall be applied on the substation floor.

1.5 Non-slip strip inserts shall be installed at the edges of steps as specified in the

latest edition of “General Specification for Building” by Architectural Services Department (ASD) of Hong Kong SAR Government, at: i. staircase within the area to be locked up by HK Electric; and ii. staircase outside the area to be locked up by HK Electric, but forming part

of the route of escape for the substation.

3.39

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30 1.6 Substation wall and ceiling shall be finished to a true plane and to correct line

and level. Maximum deviation permitted in surfaces shall be 3 mm from a 1800-mm straight edge. Substation floor shall be finished to a true plane and to extremely correct line and level. Maximum deviation permitted in surfaces of substation floor shall be 2 mm from a 1800-mm straight edge. For steelwork, maximum deviation shall be 2 mm from a 1800-mm straight edge.

1.7 Unless otherwise specified by HK Electric, all the building work, structural work

and steelwork for the substation shall comply with the latest edition of "General Specification for Building" by ASD.

1.8 Unless otherwise specified by HK Electric, all exposed steelwork for substation

shall be hot dip galvanized to BS EN ISO 1461. 1.9 Unless otherwise specified, all trenches shall be covered with 7-mm-thick hot

dip galvanised steel chequer plates according to drawing No. P76/89/R-5. 1.10 Where removable precast concrete slabs are provided to cover preformed trench

after cable installation, each piece of concrete slab shall be provided with lifting eyes and shall not weigh above 80 kgf. The precast concrete slabs shall be numbered in a sequential order by painting numbers of 50 mm high in white colour on both surfaces of each precast concrete slab so as to facilitate reinstatement of precast concrete slabs after cables installed. A sketch in permanent manner showing the layout and numbering of precast concrete slabs shall be posted on the substation wall for reference. Where the slabs are along the route of transportation of substation equipment, the slabs shall be capable of withstanding an average loading of 20 kPa. Otherwise the slabs shall withstand 10 kPa. Certificate by a registered structural engineer shall be submitted.

1.11 Where G.I. gratings of heavy duty type are specified to cover cable trench or

cable pit, the G.I. gratings shall be fabricated with load bars of not less than 25 mm x 3 mm in cross-section, in grid size of approximately 30 mm x 100 mm and in weight of not less than 20 kgf/m2. The gratings shall withstand a uniformly distributed load of 4 kPa without any permanent deformation. It shall be ensured that the deflection across the span shall not exceed 4 mm when a test load of 16 kPa is uniformly applied. Details of load table and catalogue of the gratings shall be submitted by customer to HK Electric for record.

3.40

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30 1.12 The drain hole at substation floor or at cable chamber floor shall be connected to

the building main drainage system for discharging lodged water at substation trench and the position is shown in substation layout drawing. The drain shall be equipped with a non-return valve as a flood gate to prevent the backward flow of drain water into the substation. Such non-return valve should be operated by gravity flow only but not for pressurized application. Details of non-return valve and layout plan of drainage system connecting to the drain hole at substation floor shall be submitted by customer to HK Electric for record. A UPVC drain pipe of 75 mm diameter shall be provided with the drain hole for the discharge pipe of HK Electric’s portable pump. UPVC screw type cap shall be installed on the drain pipe to prevent odour / waste water overflow to the substation in case the floodgate fails. The drain hole shall be covered with a stainless steel lid of 3 mm thick, engraved “FLOOR DRAIN” about 8-mm letter high on external surface of the lid. The lid shall be fixed using 4 Nos. of 5-mm-diameter stainless steel screw with counter-sunk Philip screw head and air-tight gasket or O-ring. The lid and the fixing screws shall be flush with the finished floor surface.

1.13 SUBSTATION CEILING Except for the dedicated staircase/passage within the area locked up by HK Electric for personnel access and equipment transportation only but outside HV switchgear and transformer compartments, the entire substation ceiling shall be of double reinforced concrete slab construction. The following requirements shall be met for all types of substations:

a. The clear separation between the upper slab and the lower slab shall not be less than 100 mm. The thickness of lower slab shall not be less than 125 mm.

b. All finished surfaces of lower slab shall be smooth, firm and free of

voids, surface projections, loose materials, oil, grease and all foreign matter. No pipes, ducts, conduits nor services of any nature are to be embedded inside the lower slab.

c. No drain pipes shall be allowed to run inside the substation enclosure.

d. No timber left in formwork shall be allowed within the separation void.

e. The top surface of the lower slab shall be designed with gravity fall of 1:100 to avoid ponding of water. At least two drain holes with drain pipes of not less than 38 mm diameter shall be provided for the lower slab to discharge water to outside of the substation.

3.41

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

f. A side inspection panel of minimum size of 150 mm wide by 100 mm high shall be provided to inspect the void between the upper and lower slabs. The side inspection panel shall be easily accessible from public area and be fitted with stainless steel label engraved“SUBSTATION DOUBLE-SLAB CEILING INSPECTION PANEL 電力分站雙層天 花板檢查面板”. The characters shall be in minimum 10 mm high in black colour. The side inspection panel shall be fixed using stainless steel screws.

g. In case the lower slab is divided into multi-compartment by ceiling

beams, each compartment shall have its own drain holes / drain pipes and side inspection panel.

h. A caution label of 300 mm by 200 mm shall be posted immediately

adjacent to each entrance of substation stating "DOUBLE-SLAB CEILING! NO DRILLING WORK!" and the Chinese translation 「雙 層天花板! 禁止鑽探!」. Same bilingual wording shall be stencil painted on the ceiling in red in character not less than 75 mm high at every 5m interval.

i. Unless otherwise specified in this Drawing, the lower and upper slabs

shall have waterproofing and water tightness conforming to the requirements regarding material and workmanship on “Roofing” as stipulated in the latest edition of General Specification for Building by ASD.

j. Drainage plan for lower and upper slabs, waterproofing details for

lower and upper slabs and waterproofing details for drain points serving lower and upper slabs shall be submitted. Cementitious type waterproofing for double slab will not be accepted.

Waterproofing material for upper and lower slab shall be materials of proprietary sheet or liquid membrane type roofing system. Proprietary roofing system shall be laid by specialist contractors. The asphalt / bituminous waterproof sheet membrane to ASTM standard, thickness not less than 3 mm and longitudinal elongation not less than 200% will be acceptable:- Other types of membrane, provided that technical details are submitted indicating equivalent waterproofing performance, will also be considered. Before commencing work, the contractor shall demonstrate on site that all adhesives and materials are fully compatible and shall be certified by the suppliers/manufacturers in writing.

3.42

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

k. Waterproofing material shall be wrapped onto the inner face of water outlet or any case-in drains and drain pipes.

l. A copy of design drawing clearly indicating the locations of the

substation ceiling, drain holes, drain pipes, void area, vertical grating, side inspection panel etc. shall be submitted at early design stage.

m. An as-built drawing for substation ceiling shall be certified by an

Authorised Person (Cap.123) and be submitted to HK Electric at the time of substation inspection. The as-built drawing shall clearly indicate the locations of the drain holes, drain pipes, side inspection panel. A copy of the drawing shall be laminated and posted on substation wall for quick reference on site.

n. To ensure the effectiveness of waterproofing system for the double slab,

the following tests / inspections shall be carried out at the time of substation inspection and the details of results shall be certified by an Authorised Person and submitted to HK Electric: -

i. Flood test on lower slab with minimum 50-mm-depth water for at least 72 hours;

ii. Visual inspection on soffit of lower slab after the flood test;

iii. Flood test on upper slab with minimum 150-mm-depth water for at least 72 hours;

iv. CCTV inspection for soffit of upper slab through the Side Inspection Panel after the flood test; A DVD/VCD showing the CCTV inspection through the side inspection panel after the flood test shall be submitted to HK Electric for reference and record; and

v. The separation void shall be left clean and dry after the flood tests.

3.43

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

2. CABLE ENTRY TO SUBSTATION 2.1 The architect is required to obtain information from utility companies and

conduct site survey (including trial trenches excavation) regarding the details of underground services and roadside trees in the vicinity of substation. The architect is to ensure early in the design stage that the cable entry points to the substation will not be obstructed by other underground services or located within the no-excavation zone of any roadside tree according to Register of Old and Valuable Trees of LCSD and code of practice published by authorities of HKSAR Government. Details of underground services and any roadside trees near cable entries shall be indicated on the Ground Floor Plan submitted to HK Electric.

2.2 Normally the width of cable trench to be excavated for commissioning a new

substation shall be taken as 1000 mm. The architect shall arrange excavation at the cable entry points within the site boundary for inspection by HK Electric engineer during hand-over of the substation. Where necessary the architect shall be responsible for clearing underground obstacles with other utility companies and any road side trees near cable entries before hand-over of substation.

2.3 Unless otherwise specified, all the cable entry point shall be at 1050 mm to

1300 mm below the pavement level outside the substation.

2.4 The cable entry of substation shall be properly sealed and watertight against ingress of water by the developer.

a. The last section of 4 m long (max) of 150-mm and 75-mm UPVC cable ducts will be provided by HK Electric. For cable ducts longer than 4m, the extra lengths of cable ducts are to be provided by the developer. Cable ducts of diameter other than 150 mm or 75 mm shall also be provided by developer.

b. The developer is required to collect UPVC ducts, duct spacers, sockets & end caps suitable for UPVC ducts or sleeves in nominal diameter of 150 mm and 75 mm provided and delivered to site by HK Electric. The developer is also required to install the cable ducts at site to ensure ducts or sleeves are constructed with correct spacing and level before concrete surroundings and application of sealings according to drawing No. P627/05/R-1.

c. All cable entry ducts or sleeves shall be capped by UPVC cap and sealed against water ingress or any noxious or explosive liquid or gas into the substation at the outside of substation before handing over the substation to HK Electric.

3.44

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

d. The developer shall be responsible for re-sealing the occupied ducts or sleeves using cementitious mortar with waterproofing additive and/or expansible polyurethane foam or other waterproofing material at the ends outside substation of the ducts or sleeves after installation of cables by HK Electric. The thickness of sealant shall not exceed 75 mm so as to facilitate future removal of sealant inside the ducts when cables are installed by HK Electric. Fibre-glass cotton can be inserted inside the ducts to separate the sealants where necessary.

2.5 Where the substation entrance is via back lane, the architect shall be responsible

for aspects of flooding and illegal structure up to the point of public access which will obstruct the equipment transportation and cabling works by HK Electric. For preformed cable trench inside customer premises leading to the substation, suitable drains should be included to prevent lodgement of water inside the preformed trench. The preformed cable trench and draw pits (if any) shall be fully filled up with nylon sandbags by the builder after HK Electric’s cables have been installed.

2.6 Ducts or sleeves other than substation cable entry duct shall be of G.I. or UPVC

as specified. Where UPVC ducts or sleeves of nominal diameter 150 mm are specified, the material shall comply with BS 3506:1969, Class D and internal diameter shall be 146 mm +/-1 mm in order to suit the duct plugs used by HK Electric. Ducts of 200 mm diameter shall also comply with BS 3506:1969, Class D. If required, sockets shall be used to joint up duct lengths to ensure that the inside surface of ducts and sockets is smooth after being installed and assembled together.

3. SUBSTATION LIGHTING & POWER 3.1 The installation of substation lighting and power must comply with Electricity

Ordinance, Electricity (Wiring) Regulations and HK Electric’s Supply Rules. 3.2 Unless otherwise specified and except those wirings passing from customer's

switchroom to HK Electric substation, electrical wirings shall be enclosed in surface mounted G.I. conduit. Conductor size of wirings to be controlled by 5-A or 6-A MCB shall be of 1.5 mm² Cu and similarly 2.5 mm² Cu for 15-A or 16-A MCB; 6 mm² Cu for 30-A or 32-A MCB. Phase identification using L1, L2, L3 and N for 3-phase supply or L and N for 1-phase supply should be provided for all switches and final circuits. L1, L2, L3 label shall be attached to socket outlet and lighting switch to denote the supply phase.

3.3 The main MCB for substation lighting and power shall be of TP&N 4-pole

construction. All MCB used shall have a breaking capacity of not less than 9 kA. 3.4 A 32-A TP&N 4-pole 3-position selection switch supplied by HK Electric for

connection of supply to substation main MCB board shall be collected and installed by customer according to Drawing No. P561/01/R-7.

3.45

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

3.5 Unless otherwise specified, fluorescent lamp on wall shall be at 2800 mm above

substation floor level. For substation with headroom over 3600 mm, the lamps below ceiling shall be supported such that the lamps are at 3200 mm above ground. Lighting in substation shall be fed by at least two final circuits of different phases. The layout of lamps shall be arranged in such a way that adjacent lamps are fed by different final circuits. The number of fluorescent tubes fed by each final circuit shall be approximately equal and no more than 8 per circuit.

3.6 Normal type fluorescent lamp fitting shall be installed unless Impact Resistant

Type Fluorescent Lamp Fitting is specified in the substation layout drawing. Impact Resistant Type Fluorescent Lamp Fitting will be marked "IR" next to the symbol in the drawing, and shall be installed in area of cable chamber, cable pit and cable shaft. The Impact Resistant Type Fluorescent Lamp Fitting shall comply with either (a) or (b) of the following requirements:

a. Diffuser of flame retardant material tested to withstand a mechanical

shock of not less than 10 Joules to EN60598 and stainless steel toggles as diffuser clips shall be fitted onto the lamp fitting.

b. A wire guard in approximately mesh size of 25 mm x 75 mm made from

stainless steel wire and not thinner than 3.25 mm diameter shall be fitted onto the lamp fitting or wall by stainless steel screws. The wire guard shall be of swing-down design and locked by wing-head nuts on both sides to facilitate replacement of fluorescent lamp.

3.7 Fluorescent lamp to be installed in HV cable pit shall be controlled by an

independent switch via an independent MCB, impact resistant type and fixed as close to the top of R.C. slabs or beams as practicable.

3.8 Emergency lighting, if so required by FSD, shall be backed up by emergency power supply from the building’s emergency generator, and according to FSD requirement. Each emergency light shall be labelled “EMERGENCY LIGHT” and the Chinese translation 「緊急照明」. Future maintenance / replacement of such emergency lighting and the associated fitting shall be the responsibilities of customer.

3.9 Socket outlets in substation shall be of 13 A in ring circuits and be provided with

L1, L2, L3 labels for phase identification in permanent manner. Socket outlets shall be installed at 600 mm above substation floor level unless otherwise specified. Socket outlets to be installed in HV cable pit shall be protected by an independent MCB, to IP65 standard and fixed as close to the top of R.C. slab or beam as practicable.

3.46

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30 3.10 Test on phase sequence, earth fault loop impedance, operating characteristics of

residue current device and 500-V megger test on the substation lighting and power installation shall be carried out and be witnessed by HK Electric engineer at the time of substation hand-over. Customer shall submit a copy of Work Completion Certificate (Government Form WR1) duly signed by a registered electrical worker for lighting & power installation in substation before substation handing over.

3.11 i. For staircase, passage, etc. within the area to be locked up by HK Electric,

where layout of fluorescent lamps is not specified by HK Electric, customer shall ensure that the lamps are installed so as to provide an illumination of not less than 150 lux measured at floor level.

ii. For staircase, passage, etc. outside the area to be locked up by HK Electric,

but forming part of the route of escape for the substation, illumination must be provided according to FSD requirement. Also the electricity supply to the lightings shall be from the essential board in the building.

3.12 Exposed metallic parts inside substation should be bonded to the substation

earthing connection in the manner laid down in Electricity (Wiring) Regulations. Brass or stainless steel bolts, nuts and washers shall be used at the equipotential bonding of exposed metallic parts for long lasting purpose.

3.13 Before energization of substation by HK Electric, the temporary wirings for

substation lighting and power shall be properly connected to the 5-pin male type socket of the 32-A T.P. & N. 4-pole 3-position selection switch via a female connector having corresponding rating and dimensions by customer for safety purpose.

4. CONDUITS IN SUBSTATION 4.1 Conduits, be they metallic or PVC, shall be supported and fixed to ceiling/side

wall at an interval of not more than 1200 mm. The method of anchoring conduits must be by red-head or similar device. Anchoring by raw plug or wood plug will not be accepted. No painting of G.I. conduit is required.

4.2 Unless otherwise specified, conduits shall not traverse low voltage busbar route

nor be running above HK Electric’s supply equipment marked on the substation drawing. All horizontal conduits of any purposes shall be installed at a level of 2200 mm above substation floor. Connection to cubicles / boxes mounted onto substation wall shall be by means of top entry vertical conduits dropped from the horizontal conduits. Where necessary to install conduits across substation door, the conduits shall be fitted above the door.

4.3 All electrical metallic conduits shall be continuous with good electrical joints at

boxes and couplings etc.

3.47

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30 4.4 For the purpose of installation of HK Electric’s trunking and earthing tapes, the

400 mm space on wall above substation floor should be free from any installation or conduit unless otherwise specified in this requirement.

5 VENTILATION SYSTEM IN SUBSTATION 5.1 Hangers for air duct shall be of U-shape, 40 mm x 7 mm thick hot dip galvanized

steel plate (or equivalent size) at interval of not more than 1200 mm. Hangers shall be provided on either side of air duct joint. The method of anchoring the hanger onto the ceiling/side wall must be by red-head or similar device. Anchoring by raw plug or wood plug will not be accepted. The air duct must be securely fixed to the hangers by means of hot dip galvanized steel or stainless steel bolts and nuts with washers.

5.2 The air duct shall be made of hot dip galvanized steel sheet of not less than

0.8 mm thick. No painting of the air duct is required. The headroom under the air duct shall be 2700 mm minimum, but not greater than 3200 mm. The air duct, fan and silencers shall not traverse low voltage busbar route nor be running above HK Electric’s supply equipment marked on the substation drawings.

5.3 Silencers, acoustic lining and/or acoustic plenum, etc. shall be installed to reduce

noise level to be not exceeding the values as stipulated in Noise Control Ordinance (NCO). In case of axial flow fans being provided by customer, the following must be submitted early at planning stage:

a. Drawings to show the configuration of the ventilation system. b. Drawings to show the locations of the existing or assumed nearest noise

sensitive receivers (NSR) and the corresponding distances away from the substation and supply/exhaust louvres.

c. Detailed acoustic calculation of the ventilation system to verify

compliance with the NCO, including tonality consideration, if any.

d. Description clearly indicating the approach and methodology on which the calculation is based.

e. A copy of the detailed references for the technical data adopted in the

calculation, including catalogues of ventilation fans and silencers, attenuation figures, etc.

If the acoustic calculation is not conclusive due to any reasons, a post-commissioning noise measurement at the identified NSR with entire 1/3 octave frequency spectrum from 31.5 Hz to 16 kHz has to be carried out by the developer to ensure compliance with the NCO.

3.48

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

5.4 The noise level measured at any location within the substation and at 2 m above finished floor level of substation shall not exceed 85 dB(A) while all the intake/exhaust fans for the substation are in operation.

5.5 The as-measured noise level of ventilation system must not exceed the values

stipulated in Noise Control Ordinance. 5.6 Where two or more ventilation systems are installed, the ducting, fan, silencer,

control panel and other major parts shall be numbered in a permanent manner at intervals not exceeding 3 m.

5.7 Where intake fan system and exhaust fan system are installed, the ducting, fan,

silencer, control panel and other major parts shall be labelled "INTAKE 入風" and "EXHAUST 出風" accordingly and direction of air flow shall be indicated by using arrows in a permanent manner. Inter-tripping control box shall be provided for the intake and exhaust fans. The customer must demonstrate by calculation and on-site measurement that the INTAKE and EXHAUST paths will not be short-circuited.

5.8 Unless otherwise specified by HK Electric, the air duct shall be so designed that

the average air velocity at any cross-section shall not exceed 4.2 m/s.

5.9 For substations to be equipped with exhaust fan only, the average air velocity at exhaust louvres shall not exceed 3.0 m/s. Also the inclined angle at the gradual expansion of exhaust louvres shall not be more than 30°.

5.10 For substations to be equipped with intake/exhaust fans, the average air velocity

at intake/exhaust louvres shall not exceed 3.0 m/s. Also the inclined angle at the gradual expansion of intake/exhaust louvres shall not be more than 30°.

5.11 For remote on/off control of substation ventilation system, customer is required

to install fan control box(es) which will be supplied by HK Electric in the substation according to HK Electric drawing No. P382/98/R-2 before handing over the substation. A pair of dry contact (220 V, 5 A) shall be provided to HK Electric for controlling the ventilation fan if central control system is used by customer where control box provided by HK Electric is not applicable. Such details of electrical control system shall be submitted to HK Electric for approval at design stage.

5.12 Local emergency switch shall be provided at a level not exceeding 500 mm

above the bottom of fan and within 1 metre from each ventilation fan. The switch may be installed on wall, ceiling or an independent steel framework, but shall be installed as close as possible to the ventilation fan junction box and must not be fixed onto the axial flow fan or silencers.

6. VENTILATION LOUVRES ON SUBSTATION WALL 6.1 Ventilation louvres shall be provided on substation walls as specified in HK

Electric drawings. The constructional details are shown on drawing No. P638/06.

3.49

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30 6.2 The ventilation louvres and frame shall be made of stainless steel sheet and

thickness of 1.5 mm. A frame shall be provided for louvre leaves. 6.3 For substations at ground level, the bottom edge of lower louvres shall be at

300 mm above finished floor level unless otherwise specified. 6.4 For lower louvres at ground level substations, a wire mesh with frame and

handle shall be provided at the inner side. The wire mesh shall be of 10 mm x 10 mm and be made from stainless steel wire and not thinner than 2.0 mm diameter. The frame and handle of wire mesh shall be of rigid construction and be stainless steel. The frame and handle of wire mesh shall be so designed and constructed for slot-in installation and removal. Where necessary, two or more pieces of wire meshes shall be provided for large size louvre to facilitate removal and installation work. The overall weight of each wire mesh shall not exceed 25 kgf. Installation of wire mesh shall be by means of a vertical sliding-down or horizontal sliding-in action and that no bolts, nuts nor tools shall be required for fixing. It shall be ensured that the gap between frames of louvres and wire mesh after installation shall not exceed 10 mm. For easy cleaning of wire mesh, the earthing wire shall be fixed using a wing-head nut.

7. SUBSTATION DOOR 7.1 Ventilation louvres shall be provided on substation doors as specified in HK

Electric drawings. 7.2 For lower louvres of ground floor substation, a wire mesh with frame and handle

shall be provided at the inner side. The wire mesh shall be of 10 mm x 10 mm and be made from stainless steel wire and not thinner than 2.0 mm diameter. The frame and handle of wire mesh shall also be stainless steel and they shall be so designed and constructed for slot-in installation and removal. Installation of wire mesh shall be by means of: (a) a horizontal sliding-in action from the free edge of door leaf and then securing using a bolt; or (b) a vertical sliding-down action and that no bolts, nuts nor tools shall be required for fixing. It shall be ensured that the gap between frames of louvres and wire mesh after installation shall not exceed 10 mm. For easy cleaning of wire mesh, the earthing wire shall be fixed using a wing-head nut.

7.3 Substation door with its path of swing within passage of vehicular traffic or

within area of car park space will not be accepted. 8. FIRE SERVICES INSTALLATION IN SUBSTATION 8.1 The architect shall be responsible for ensuring that the substation complies with

the latest requirements set out by FSD. Unless fixed fire fighting installation is definitely required by FSD, there is no need to install fixed fire fighting equipment in HK Electric substation because non oil-filled high voltage switchgear and transformer(s) will be installed in the substation.

3.50

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30 8.2 Unless otherwise specified in this drawing, the installation shall comply with the

latest edition of "Code of Practice for Minimum Fire Service Installations and Equipment" published by FSD. Letters or certificates certifying the compliance with the COP and the proper functioning of the fixed fire fighting system (if any) shall be submitted prior to formal hand-over of substation.

8.3 Please note that HK Electric will install totally oil-less transformer(s) and switchgear in new substations. FSD has already granted exemption to HK Electric in the provision of portable fire extinguishers at this type of substations. Therefore, the developer is required not to include portable fire extinguishers in the substation during the building plan submission stage. During take-over of substation by HK Electric, no portable fire extinguisher shall be placed inside the substation.

8.4 Should fixed fighting system be required for the substation, an automatic/manual

(A/M) change-over panel should be installed and the following arrangements shall be adopted.

a. A key box of stainless steel and thickness not less than 1.5 mm shall be

provided immediate adjacent to the A/M change-over panel. The key box shall be not less than 100 mm high x 150 mm wide x 100 mm deep with a hinged front cover. A lock hole of 14 mm diameter shall be provided for HK Electric pad lock to lock the key box. On the front cover of key box, an engraved label stating "KEY BOX FOR FIRE SERVICES PANEL" and Chinese translation 「消防控制台匙箱」 shall be provided.

b. The key for A/M change-over panel shall be attached to a stainless steel

chain secured at the inside of key box. The chain must be of sufficient length to enable A/M change-over operation and chain must not break when a 500-N tensile force is applied.

c. Another spare key for A/M change-over panel shall be handed to HK

Electric engineer during substation inspection for keeping in HK Electric operations room.

8.5 Fixed fire fighting piping (if any) shall be supported and fixed to ceiling/side

wall at an interval of not more than 1200 mm. Such piping shall not traverse low voltage busbar route nor be running above HK Electric’s supply equipment marked on the substation drawings. The method of anchoring fixed fire fighting piping (if any) must be by red-head or similar device. Anchoring by raw plug or wood plug will not be accepted.

8.6 Automatic fixed fire fighting installation using water within the locked area of substation is not allowed. Fixed fire fighting installation (if any) should be submitted to HK Electric for approval before handing over the substation to HK Electric.

3.51

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30 8.7 Fire detection system, if required in the latest edition of "Code of Practice for

Minimum Fire Service Installations and Equipment" published by FSD, shall be installed in substation. Detection heads of heat detecting type may be installed if deem necessary.

8.8 Where fire dampers are required by FSD, the fire dampers shall be installed onto

the external side of opening such that checking and maintenance of the fire dampers could be carried out without entering the substation. To avoid overloading of ventilation fan system, proper electrical cut-off of ventilation fan should be provided.

9. MISCELLANEOUS 9.1 No drain, water sewer pipes or other services are to pass through or enter

substation and the exclusive access(es) to the substation or to run inside the substation enclosing.

9.2 Heavy duty type telephone socket outlets supplied by HK Electric shall be

collected and fixed to substation wall at 1300 mm above substation floor level as specified in substation layout drawings. The fixing details are shown on drawing No. P431/99/R-1.

9.3 The appliance/gear and the associated I-beam or other equipment for lifting of

equipment shall be with a safe working load specified by HK Electric in the substation drawing and tested with a safety factor of 2. Certificate proving such shall be submitted prior to the acceptance of the substation. The lifting appliance/gear after the initial test shall also be tested periodically in accordance with the current Factories and Industrial Undertakings (Lifting Appliances and Lifting Gear) Regulations by customers. Certified copies of such certificates of periodical test shall also be submitted to HK Electric for record.

9.4 Transit block shall be installed at a height measured above substation floor level

as specified in the substation drawing.

9.5 Wall opening for emergency wirings shall be provided as indicated on drawing No. P638/06 .

9.6 All labels shall be engraved and be in both English and Chinese. White

characters on red background shall be used for warning labels. Black characters on white background shall be used for indicative labels.

9.7 To inform personnel entering the substation of the route of escape from

substation to open space, for:

i. all substations not situated at ground level; and

3.52

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

ii. ground level substations where there is change in direction in the route of escape or the measured distance along the route of escape from substation door to open area exceeds 20 m,

A plan showing the route of escape should be affixed onto the wall near the substation door. Also illuminated exit signs and directional signs at turning corners shall be provided outside substation. All the illuminated signs shall conform to FSD requirements. Unless it is definitely required by FSD, illuminated exit signs shall not be installed inside substation area locked up by HK Electric. The future maintenance of the route of escape plan, exit sign and directional sign shall be the responsibility of the customer.

9.8 No fluorescent lamp fitting, heat detector, axial flow fan, flexible conduit for fan

and emergency push button for fan shall be installed within the high level hazard zone as specified in drawing No. P346/97 unless they are at less than 2300 mm high measured from substation floor.

9.9 For safety purpose,

a. Black/yellow strips in 50 mm high shall be painted at conspicuous

positions, such as beams, slabs, removable supporting steels, etc. at top of the HV cable pit with luminous paint. The same shall be applied to locations of sudden change in level.

b. No protruded objects which may cause injury are allowed along the

passage up and down the HV cable pit.

c. Sharp edges at the heavy duty grating and the cat ladder shall be eliminated.

9.10 An earthing bracket bonded to the building main earthing shall be provided at

the cable entry of substation according to Drawing No. P574/02/R-1.

9.11 The developer shall prepare the necessary Temporary Traffic Measures (TTM) proposal and obtain the approval from Transport Department (TD) and Traffic Police for HK Electric’s equipment transportation to the substation if the substation door is opened to carriageway designated as “Restriction Zone – Clearways” by TD or there are other site constraints that application of TTM from the Government Authorities is necessary.

9.12 The developer shall arrange to revise the hoarding of the construction site at their

own costs to provide sufficient space for HK Electric to excavate the cable trench outside the construction site for provision of supply if the hoarding or its foundations are found to be obstructing HK Electric’s trenching and cabling work.

3.53

Notes for Drawing Nos. GCS/3/11, GCS/3/12 & GCS/3/30

9.13 Stainless steel shall mean stainless steel of grade 316 unless otherwise specified.

9.14 The customers in the development shall ensure that the substation equipment

transportation route within the customer’s premises is properly maintained and cleared from obstruction at all times. The facilities (including lifting appliances, lifting gear, freight lifts, etc.) provided by the developer for the purpose of transportation of equipment shall be properly maintained by the customers in the building at their own costs to satisfy the legal requirements.

TM

C1a

TM

C1b

TM

C2a

TM

C2b

TM

C3a

TM

C3b

TM

C4a

TM

C4b

AM

I1b

AM

I1a

AM

I2a

AM

I2b

AM

I3a

AM

I3b

AM

I4a

AM

I4b

ST

AN

DA

RD

T

ER

MIN

AL B

LO

CK

S

WA

LL M

OU

NT

IN

G B

RA

CK

ET

FO

R M

6 C

ON

CR

ET

E A

NC

HO

R B

OLT

( IN

CLU

DIN

G W

AS

HE

R A

ND

N

UT

)

BY

C

US

TO

ME

R

TM

C B

OX

T

O B

E S

UP

PLIE

D

BY

H

K E

LE

CT

RIC

EA

RT

HIN

G T

ER

MIN

AL

( Y

ELLO

W / G

RE

EN

)

CA

BLE

G

LA

ND

S

2

CO

VE

RB

AS

E

300 m

m

300 mm

40 m

m

370 mm

132 m

m

6-m

m E

AR

TH

IN

G W

IR

E

BY

C

US

TO

ME

R

3 T

MC

C

AB

LE

S, E

AC

H W

IT

H 1M

SP

AR

E LE

NG

TH

A

ND

IN

DIV

ID

UA

L

CA

BLE

G

LA

ND

. T

WO

O

F T

HE

T

MC

CA

BLE

S S

HA

LL B

E T

ER

MIN

AT

ED

WIT

H N

UM

BR

ED

F

ER

RU

LE

S

IN

SID

E F

RO

NT

V

IE

WS

ID

E V

IE

W

92 m

m

Drg

. No.

GC

S/3/

13A

RR

AN

GEM

ENT

FOR

TA

RIF

F M

ETER

CO

MM

UN

ICA

TIO

N (T

MC

) TER

MIN

ATI

ON

BO

X(P

383/

98/R

-6) S

HEE

T 1

OF

2

3.54

HK

E

LE

CT

RIC

SU

BS

TA

TIO

N

CA

BLE

TR

EN

CH

CLA

MP

S

BY

C

US

TO

ME

R

TM

C

TE

RM

IN

AT

IO

N

BO

XE

S T

O B

E

SU

PP

LIE

D B

Y

HK

E

LE

CT

RIC

CU

ST

OM

ER

SW

IT

CH

R

OO

M

FLO

OR

(S

EE

N

OT

E 5)

750 mm

1400 mm

150 mm

2200 mm

1400 mm

WA

LL

50-m

m

PV

C C

ON

DU

IT

BY

C

US

TO

ME

R

50-m

m

PV

C C

ON

DU

IT

BY

C

US

TO

ME

R

150-m

m

CA

BLE

D

UC

T

3x 4-P

AIR

TM

C C

AB

LE

S

TO

B

E S

UP

PLIE

D

BY

H

K E

LE

CT

RIC

DR

G. N

O. G

CS/

3/13

AR

RA

NG

EMEN

T FO

R T

AR

IFF

MET

ER C

OM

MU

NIC

ATI

ON

(TM

C) T

ERM

INA

TIO

N B

OX

(P38

3/98

/R-6

) SH

EET

2 O

F 2

3.55

3.56

Notes for Drawing No. GCS/3/13 1. 2 Nos. of termination boxes and 3 piece of 4-pair 8-core (1.5 sq. mm stranded

conductor) cable to be supplied by HK Electric for Tariff Meter Communication (TMC) purpose shall be collected by customer and installed at site by customer. One of the termination boxes shall be at customer's main switch room and the other termination box shall be at HK Electric substation. Exact position is indicated on the substation layout plan. The boxes shall be linked up with the 8-core TMC cables provided by HK Electric. Customer shall complete the cabling including fixing of cable glands and wire terminations before handing over the substation to HK Electric.

2. Each termination box is fully fitted with rail-mounted terminal block comprising 20 Nos. terminals. Two of the TMC cables shall be terminated with numbered ferrules as specific below:

1st TMC Cable TMC1a & TMC1b for pair 1 white & black cores TMC2a & TMC2b for pair 2 white & black cores TMC3a & TMC3b for pair 3 white & black cores TMC4a & TMC4b for pair 4 white & black cores

2nd TMC Cable AMI1a & AMI1b for pair 1 white & black cores AMI2a & AMI2b for pair 2 white & black cores AMI3a & AMI3b for pair 3 white & black cores AMI4a & AMI4b for pair 4 white & black cores

3rd TMC Cable Termination and numbered ferrule are not required

The two TMC cables shall be terminated on the left hand side & right hand side of terminals for the termination boxes in customer's main switch room and HK Electric substation respectively. Terminal connection is by means of bare conductor and lugs are not required. The TMC cable shall be enclosed in surface mounted 50-mm PVC conduits at customer's main switch room and HK Electric substation. Requirements for installation of 50-mm PVC conduit at HK Electric substation are: — Conduit bends should have an internal radius of at least 4 times the outside

diameter of the conduit.

— Conduit shall be supported and fixed to side wall at an interval of not more than

1200 mm. The method of anchoring conduit must be by red-head or similar

device.

3.57

Notes for Drawing No. GCS/3/13 — Adaptable boxes should be provided immediately after every two bends, or after

a bend plus a total maximum straight run of 10 metres or after a maximum

straight run of 15 metres.

— The method of carrying out the conduit bends, fixing conduits to boxes, and the

tools and materials to be used should be as recommended by the manufacturer

of the conduit.

3. Each termination box is fitted with a yellow/green earthing terminal at the end of the terminal block. A 6-sq. mm earthing wire shall be provided and terminated by the customer to the corresponding substation/switch room electrical conduit system.

4. Each box shall be mounted on wall of substation/switch room at 1400 mm above finished floor level.

5. The 150-mm-diameter cable duct shall be properly sealed off with fire resistant material and water-proofed against ingress of water by customer after TMC cable installed.

144

10

300

3045

90

234

40

500

555

100

100 500

25

L1L2

L3N

E

L1L2

L3N

E

PLAN

SEC

TIO

N B

- B

Cu. BAR

Cu. BAR

Cu. BAR

Cu. BAR

Cu. BAR

SEE

VIEW

CSE

ED

ETAI

L D

THICKNESSWALL

CU

STO

MER

'SSW

ITC

H R

OO

M

HK

ELEC

TRIC

SUBS

TATI

ON

BB

A

300 1570

SUBS

TATI

ON

FLO

OR

CO

NC

RET

E

LABE

L ST

ATIN

G" T

RAN

SIT

BLO

CK

No.

"

WH

ERE

NEC

ESSA

RY

SEC

TIO

N A

- A

THICKNESSWALL

50 40 69 45 30

30

2323

76x1

0 C

u. B

AR

CO

NC

RET

E

THIS

TR

ANSI

T BL

OC

K IS

FO

R C

UST

OM

ER'S

MAI

N S

WIT

CH

OF

RAT

ING

NO

T EX

CEE

DIN

G 2

250

A.

INSU

LATI

ON

LEV

EL O

F TR

ANSI

T BL

OC

K SH

ALL

BE 3

kV

RM

S FO

R

1 M

INU

TE.

1 )

2) 3) 4)

L1 L2 L3 N E

NEU

TRAL

EAR

THG

REE

N /

YELL

OW

CO

LOU

R T

APE

NO

TES

: 8 no

s. 1

1 D

IA. H

OLE

S

4 no

s.11

DIA

.H

OLE

S23

3023

VIEW

CD

ETAI

L D

1010

1010

10

CO

PPER

SPAC

ER

CO

NC

RET

E

ELEC

TRIC

AR

C &

FIR

E PR

OO

FIN

G T

APE

CO

PPER

SPA

CER

DET

AIL

E

SEE

DET

AIL

E

76x1

0 C

u. B

AR

HEA

T SH

RIN

KABL

ETU

BIN

G F

OR

INSU

LATI

ON

150

9001100

WAL

L SU

RFA

CE

TO B

E C

LEAR

OF

ANY

CO

ND

UIT

S, S

OC

KET

OU

TLET

S, E

TC.

FOR

INST

ALLA

TIO

N O

F SW

ITC

HBO

ARD

BY H

K EL

ECTR

IC. F

OR

SU

BSTA

TIO

N W

ITH

MO

RE

THAN

ON

E TR

ANSI

T BL

OC

K, T

HE

CEN

TRE-

TO-C

ENTR

E SE

PAR

ATIO

NBE

TWEE

N A

DJA

CEN

T TR

ANSI

T BL

OC

KSSH

ALL

BE 1

600

mm

MIN

IMU

M

7017

017

023

070

T TR

EFER

ENC

E LI

NE

T - T

OF

TRAN

SIT

BLO

CK

TO B

E R

EFER

RED

WH

EN T

HE

HO

RIZ

ON

TAL

SEPA

RAT

ION

TO E

DG

E O

F TR

ENC

H F

OR

HK

ELEC

TRIC

L.V.

FU

SEBO

ARD

IS S

PEC

IFIE

D IN

SUBS

TATI

ON

LAY

OU

T D

RAW

ING

* (SAM

E FO

R L

1, L

2, L

3, N

)

( SAM

E FO

R L

1, L

2, L

3, N

, E )

PHAS

E

PHAS

E

PHAS

E

CO

LOU

R T

APES

AS P

ER R

EQU

IRM

ENTS

IN E

LEC

TRIC

ITY

(WIR

ING

)R

EGU

LATI

ON

S

CO

DE

EN

L3L2

L188

0

300

VIEW

ED F

RO

M H

K EL

ECTR

IC S

UBS

TATI

ON

5A.

5B.

LABE

L O

F 88

0 m

m W

IDE

BY 1

00 m

m H

IGH

MAR

KED

WIT

H

5)TH

E FO

LLO

WIN

G E

NG

RAV

ED L

ABEL

S O

F IN

SULA

TED

MAT

ERIA

L AN

D

SHAL

L BE

PR

OVI

DED

ON

BO

TH S

IDES

OF

WAL

L. T

HE

LETT

ERS

SHAL

L BE

IN B

LAC

K O

N W

HIT

E BA

CKG

RO

UN

D.

THE

BOTT

OM

ED

GE

OF

LABE

L SH

ALL

BE A

T 30

0 m

m A

BOVE

THE

CEN

TRE

LIN

E O

F TR

ANSI

T BL

OC

K.

L1, L

2, L

3, N

, E O

R E

, N, L

3, L

2, L

1 ( A

S AP

PRO

PRIA

TE )

WIT

H L

ETTE

R H

EIG

HT

NO

T LE

SS T

HAN

50

mm

.

( AS

SHO

WN

IN S

UBS

TATI

ON

LAY

OU

T D

RAW

ING

) W

ITH

LET

TER

H

EIG

HT

NO

T LE

SS T

HAN

15

mm

.

WH

ERE

MO

RE

THAN

ON

E TR

ANSI

T BL

OC

K AR

E IN

STAL

LED

INA

SUBS

TATI

ON

, LAB

EL IN

DIC

ATIN

G T

RAN

SIT

BLO

CK

NU

MBE

RIN

G

8585

ALL

CO

PPER

BAR

S SH

ALL

BE T

INN

ED A

ND

HAR

D D

RAW

N O

F H

IGH

CO

ND

UC

TIVI

TY A

CC

OR

DIN

G T

O C

W00

4A O

F BS

EN 1

3601

OR

C11

000

OF

ASTM

B18

7M O

R E

QU

IVAL

ENT.

FIXE

D U

SIN

G M

6 C

ON

CR

ETE

ANC

HO

RS

AND

M6

G.I.

HEX

BO

LTS

TAPE

CO

NFO

RM

ING

TO

BSEN

604

54 W

ITH

CO

LOU

R A

ND

/ O

RPH

ASE

CO

DIN

GL1

, L2,

L3,

N

PHAS

E ID

ENTI

FIC

ATIO

N L

ABEL

50

325

6)AL

L D

IMEN

SIO

NS

ARE

IN m

m.

Drg

. No.

GC

S/3/

14D

ETA

ILS

OF

L.V

. TR

AN

SIT

BLO

CK

AT

MID

LEV

EL (P

314/

96/R

-4)

3.58

45

85

45

30

40

76

11 H

OLE

GE

NE

RA

L LA

YO

UT

F

OR

E

AC

H P

HA

SE

/ N

EU

TR

AL

76

x1

0 T

HIC

K

CO

PP

ER

B

US

BA

R

BY

H

K E

LE

CT

RIC

( P

HA

SE

T

O P

HA

SE

SE

PA

RA

TIO

N IS

17

0 m

m )

MA

X. 4

N

os. C

AB

LE

L

UG

ON

E

AC

H P

HA

SE

/ N

EU

TR

AL

BU

SB

AR

( M

AX

. 2

N

os. C

AB

LE

LU

G O

N E

AC

H S

ID

E O

F H

K

EL

EC

TR

IC

B

US

BA

R )

Drg

. No.

GC

S/3/

15A

RR

AN

GEM

ENT

FOR

SIN

GLE

-CO

RE

CA

BLE

S C

ON

NEC

TED

TO

HK

ELE

CTR

IC S

UB

STA

TIO

N(C

UST

OM

ER'S

MA

IN S

WIT

CH

NO

T EX

CEE

DIN

G 2

250

A) (

P31/

88/R

-6)

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.59

3.60

Notes for Drawing No. GCS/3/15 1. The single-core cables and accessories shall be supplied and installed by customer.

The cables shall be non-metallic sheathed with an installed rating of not less than the rating of the main switch to which they are to be connected.

2. A maximum of four (4) cables per phase/neutral may be used. The neutral conductor shall be of same installed rating as the phase conductor unless otherwise agreed by HK Electric.

3. The route length of the single-core cables must not exceed twenty (20) metres. Customer is required to ensure that the routing complies fully with current FSD's regulations.

4. The installation shall comply with the HK Electric Supply Rules, the latest edition of Code of Practice for the Electricity (Wiring) Regulations and relevant Government Ordinance.

5. Customer shall be responsible for providing and installing cable support facilities for his single-core cables inside HK Electric substation. Full details of the proposed method of installation must be submitted for HK Electric's reference prior to installation work.

6. Customer shall be responsible for designing and installing single-core cables in order to minimize the electromagnetic interference generated from single-core cables. The physical layout of single-core cables must be submitted for HK Electric’s consideration prior to installation work.

7. For the purpose of compliance with Code 11 and 12 in the latest edition of Code of Practice for the Electricity (Wiring) Regulations, the customer shall use a single-core cable to be terminated in a lug with centre hole of diameter 11 mm for bonding his main earthing terminal to HK Electric's bonding terminal that connects to the earthed point of transformer. Customer's bonding conductor shall not be less than 150 sq. mm copper equivalent.

8. Each single-core cable for phase/neutral connection shall be terminated in a lug as indicated in this drawing for connection to HK Electric equipment. The necessary bolts, nuts, washer, spring washer and penetrox grease (if necessary) shall be supplied by customer.

3.61

Notes for Drawing No. GCS/3/15

9. Durable and legible vinyl phase identification labels (such as cable ties, PVC sleeves, PVC ferrule tubes etc.) marked in L1, L2, L3 and N with character size not less than 25 mm shall be provided at the cable ends terminated to HK Electric substation. PVC insulation tape of width not less than 25 mm conforming to BSEN 60454 with phase coding L1, L2, L3 and N could also be used.

10. Termination work of the cable lugs onto HK Electric equipment shall be done by customer's registered electrical worker and under the supervision of HK Electric engineer.

2000 ~ 2500

TYPI

CAL

WO

RKI

NG

PLA

TFO

RM

S

1100

1100

1100

DIR

ECTI

ON

OF

SWIN

G

DIR

ECTI

ON

OF

SWIN

G

DO

OR

STO

PPER

FIXE

D O

NSW

ING

ING

GAT

E

DO

OR

STO

PPER

FIX

ED O

NSW

ING

ING

GAT

E

2500

2500

0.0

0.0

R.C.C. CANOPY

I R

I R

PLAN

OF

TYPI

CAL

WO

RKI

NG

PLA

TFO

RM

SLOT

OPE

NING

AT

FLOO

R SL

AB &

ABO

VE

600x

600(

H) S

TAIN

LESS

STE

EL LO

UVRE

AT

HIGH

LEVE

L

STAI

NLES

S ST

EEL

LADD

ER W

ITH

EQUA

L RI

SES

AT 2

50 m

m D

OWN

TO C

ABLE

RIS

ER D

UCT

ROOM

AT

LEVE

L 0.

0

1100

-mm

HIG

H ST

AINL

ESS

STEE

L RA

ILIN

GW

ITH

TOE

PLAT

E OF

200

mm

HIG

H

600x

600

CLEA

R OP

ENIN

G AB

OVE

STAI

NLES

S ST

EEL

SELF

-CLO

SING

SAF

ETY

GATE

AT 1

100

mm

HIG

H W

ITH

TOE

PLAT

E OF

200

mm

HIG

H

DOOR

STO

PPER

FIX

ED O

N SW

INGI

NG G

ATE

CABL

E CL

EATS

AT

EVER

Y 10

00 V

ERTI

CAL

INTE

RVAL

HEA

DR

OO

M B

ETW

EEN

PLAT

FOR

MS

TO B

E20

00 m

m T

O 2

500

mm

TO S

UIT

TH

E H

EIG

HT

OF

CAB

LE S

HAF

T /

CO

MPA

RTM

ENT

NO

TES:

-

THE

VER

TIC

AL L

ADD

ERS

SHAL

L N

OT

BE F

IXED

SO

LELY

BY

THEI

R O

WN

WEI

GH

T.

THE

RU

NG

S O

F LA

DD

ER IS

DES

IGN

ED W

ITH

A C

ON

CEN

TRAT

ED L

OAD

OF

1.5

KN T

O B

S539

5 : P

ART

3.

THE

WO

RKI

NG

PLA

TFO

RM

IS D

ESIG

NED

WIT

H U

NIF

OR

MLY

DIS

TRIB

UTE

D L

OAD

IN 5

KPa

AN

DA

CO

NC

ENTR

ATED

LO

AD O

F 1.

0 KN

TO

BS5

395

: PAR

T 3

FOR

GEN

ERAL

DU

TY U

SE.

FOR

SAF

ETY

PUR

POSE

, O

NE

PER

SON

ON

EAC

H V

ERTI

CAL

LAD

DER

AT

A TI

ME.

FOR

SAF

ETY

PUR

POSE

, A

MAX

IMU

M O

F 4

PER

SON

S AT

A T

IME

ON

EAC

H W

OR

KIN

G P

LATF

OR

M.

1 )

3)2) 4) 5) 6) 7) 8) 9) 10)

11)

12)

13 )

ARO

UN

D A

LL O

PEN

SID

ES O

F TH

E W

OR

KIN

G P

LATF

OR

M (

UN

LESS

OTH

ERW

ISE

SPEC

IFIE

D )

SH

ALL

BE IN

STAL

LED

WIT

H F

IXED

PRO

TEC

TIVE

BAR

RIE

RS

IN 1

100

mm

HIG

H &

TO

E PL

ATES

OF

200

mm

HIG

H. S

HAR

P ED

GES

OF

FIXI

NG

RAI

LS S

HAL

L BE

FIT

TED

WIT

H P

RO

TEC

TIVE

EN

D C

APS

TO G

UAR

D A

GAI

NST

PER

SON

AL IN

JUR

Y.

THE

FLO

OR

OF

WO

RKI

NG

PLA

TFO

RM

AN

D R

UG

S O

F LA

DD

ER S

HAL

L BE

SLI

P R

ESIS

TAN

T.

THE

SELF

-CLO

SIN

G S

AFET

Y G

ATE

SHAL

L BE

UN

DER

A S

LOW

CLO

SIN

G O

PER

ATIO

N A

ND

SH

ALL

BE D

ESIG

NED

TO

SW

ING

ON

LY IN

TO T

HE

ACC

ESS

HO

LE.

NO

HO

LD-O

PEN

OR

HO

LD-C

LOSE

DEV

ICES

SH

ALL

BE F

ITTE

D.

LIG

HTI

NG

S AN

D 1

3-A

SOC

KET

OU

TLET

S IN

TH

E C

ABLE

SH

AFT

/ CO

MPA

RTM

ENT

SHAL

L BE

PR

OVI

DED

.D

ETAI

LS W

ILL

BE S

PEC

IFIE

D IN

TH

E SU

BSTA

TIO

N L

AYO

UT

DR

AWIN

G.

ENG

RAV

ED W

ARN

ING

LAB

ELS

WIT

H E

ACH

CH

ARAC

TER

OR

LET

TER

NO

T LE

SS T

HAN

15

mm

HIG

H IN

WH

ITE

ON

RED

BAC

KGR

OU

ND

SH

ALL

BE F

IXED

TO

EAC

H V

ERTI

CAL

LAD

DER

AN

D W

OR

KIN

G P

LATF

OR

M.

UN

LESS

OTH

ERW

ISE

SPEC

IFIE

D ,

THE

CO

DE

OF

PRAC

TIC

E FO

R D

ESIG

N O

F PL

ATFO

RM

S ,

ETC

. IN

BS

5395

: PA

RT

3 SH

ALL

BE F

OLL

OW

ED.

PLEA

SE R

EFER

TO

SU

BSTA

TIO

N D

RAW

ING

FO

R T

HE

NU

MBE

R O

F C

ABLE

CLE

ATS

TO B

E IN

STAL

LED

IN T

HE

CAB

LE S

HAF

T.

AN E

ARTH

ING

TAP

E O

R E

QU

IVAL

ENT

SHO

ULD

BE

PRO

VID

ED A

ND

INST

ALLE

D B

Y TH

E D

EVEL

OPE

R F

RO

M T

HE

EAR

THIN

G T

ERM

INAL

OF

THE

SUBS

TATI

ON

DO

WN

TO

TH

E BO

TTO

M O

F TH

E C

ABLE

SH

AFT

FOR

BO

ND

ING

ALL

TH

E M

ETAL

PAR

TS IN

SID

E TH

E C

ABLE

SH

AFT.

2000

x260

0(H)

STA

INLE

SS S

TEEL

DOU

BLE

LEAF

DOO

R W

ITH

LOUV

RES

AT G

/F

STAI

NLES

S ST

EEL

LADD

ER W

ITH

EQUA

L RI

SES

AT 2

50 m

m U

P TO

WOR

KING

PLA

TFOR

M A

BOVE

CAB

LE S

HAF

T/C

ABLE

CO

MPA

RTM

ENT

SHAL

L BE

NO

T LE

SS T

HAN

2.5

m(L

)x2.

5 m

(W)

TWO

CAB

LE S

HAF

TS/C

OM

PAR

TMEN

TS O

R O

NE

CAB

LE S

HAF

T/C

OM

PAR

TMEN

T W

ITH

TW

O C

ABLE

EN

TRY

POIN

TSO

F M

INIM

UM

350

0 m

m A

PAR

T SH

OU

LD B

E PR

OVI

DED

.

BEFO

RE

HAN

DIN

G O

VER

TH

E FI

RST

LEV

EL S

UBS

TATI

ON

, T

HE

ARC

HIT

ECT

MU

ST S

UBM

IT A

CER

TIFI

CAT

E IN

DIC

ATIN

G T

HAT

THE

WO

RKI

NG

PLA

TFO

RM

TO

GET

HER

WIT

H T

HE

LAD

DER

S IS

DES

IGN

ED A

ND

CO

NST

RU

CTE

D T

O R

EQU

IREM

ENTS

AS

MEN

TIO

NED

IN A

BOVE

NO

TE N

os. 1

1-12

FO

R H

K EL

ECTR

IC'S

REC

OR

D.

800

STAI

NLE

SS S

TEEL

SELF

-CLO

SIN

GSA

FETY

GAT

E IN

1100

mm

HIG

H W

ITH

TOE

PLAT

E O

F20

0 m

m H

IGH

STAI

NLE

SS S

TEEL

SELF

-CLO

SIN

GSA

FETY

GAT

E IN

1100

mm

HIG

H W

ITH

TOE

PLAT

E O

F20

0 m

m H

IGH

FOR

INST

ALLA

TIO

N O

F C

ABLE

CLE

ATS

, PL

EASE

REF

ER T

O D

RAW

ING

No.

P67

1/08

/R-3

. T

HE

DEV

ELO

PER

SH

OU

LD B

E R

ESPO

NSI

BLE

FOR

TEM

POR

ARY

REM

OVA

L O

F TH

E C

ABLE

CLE

ATS

FOR

HK

ELEC

TRIC

'S C

ABLE

INST

ALLA

TIO

N F

OR

SU

BSTA

TIO

N C

OM

MIS

SIO

NIN

G A

ND

RE-

INST

ALLI

NG

TH

E C

ABLE

CLE

ATS

AFTE

R H

K EL

ECTR

IC'S

CAB

LE L

AYIN

G ,

IF S

O R

EQU

IRED

BY

HK

ELEC

TRIC

DU

RIN

G T

HE

CO

UR

SEO

F TH

EIR

CAB

LIN

G W

OR

K.

400

NO

TE:

HD

GS

= H

OT

DIP

GAL

VAN

ISED

STE

ELAL

L D

IMEN

SIO

NS

IN m

m

Drg

. No.

GC

S/3/

16TY

PIC

AL

DES

IGN

OF

WO

RK

ING

PLA

TFO

RM

AT

CA

BLE

SH

AFT

/ C

AB

LE C

OM

PAR

TMEN

T FO

R F

IRST

LEV

EL S

UB

STA

TIO

N (P

605/

04/R

-4)

3.62

Drg

. No.

GC

S/3/

17EA

RTH

ING

BR

AC

KET

FO

R N

EW S

UB

STA

TIO

N (P

574/

02/R

-2)

3.63

Drg

. No.

GC

S/3/

18SU

BST

ATI

ON

MA

IN S

UPP

LY &

SC

HEM

ATI

C D

IAG

RA

M (P

561/

01/R

-8)

3.64

55

35 51

35 51

55

303030 30

5050

1 )

3)

REINFORCED CONCRETE

5) THE CABLE ENTRY OF SUBSTATION SHALL BE PROPERLY SEALED AND WATER-PROOFEDAGAINST INGRESS OF WATER BY DEVELOPER.

4)

ASSEMBLY OF UPVC DUCTS & UPVC DUCT SPACERS

'BASE' TYPEUPVC DUCT SPACER

'DOUBLE' TYPEUPVC DUCT SPACER

DUCT SPACERS FOR 150-mm DUCTS / SLEEVES SHALL BE INSTALLED AT BOTH ENDSOF THE PRE-CAST CABLE ENTRY DUCT BANK

3" ( 75 mm ) DIA.DUCTS / SLEEVES

THE MINIMUM SPACING AMONG CABLE ENTRY DUCTS AND BUILDING STRUCTURE ,SUCH AS WALLS , COLUMNS , BEAMS , PILING CAPS ETC. FOR A TYPICALARRANGEMENT OF DUCTS IN SUBSTATION CABLE ENTRY AS SHOWN BELOWSHALL BE FOLLOWED.

6" ( 150 mm ) DIA.DUCTS / SLEEVES

UPVC PIPE , DUCT SPACER , SOCKET & END CAP FOR 150-mm DUCTS / SLEEVESWILL BE PROVIDED BY HK ELECTRIC AND COLLECTED BY THE DEVELOPER.THE NOMINAL LENGTH OF THE UPVC PIPE IS 4 m AND THE DEVELOPER SHALL CUTTHE PIPE TO THE REQUIRED LENGTH.

2) UPVC PIPE , SOCKET & END CAP FOR 75-mm DUCTS / SLEEVES WILL BE PROVIDEDBY HK ELECTRIC AND COLLECTED BY THE DEVELOPER. THE NOMINAL LENGTH OFTHE UPVC PIPE IS 4 m AND THE DEVELOPER SHALL CUT THE PIPE TO THE REQUIREDLENGTH.

6 x 150-mm DUCTS IN 2 LAYERS + 6 x 75-mm DUCTS AT BOTH SIDES

Drg. No. GCS/3/19TYPICAL ARRANGEMENT OF CABLE ENTRY DUCTS IN

SUBSTATION (P627/05/R-1) SHEET 1 OF 2

NOTE:ALL DIMENSIONS ARE IN mm

3.65

16

5

90

130

150

6)

SILICON SEALANT TO BE APPLIED BY

DEVELOPER DURING CONSTRUCTION

OF DUCT BANK

DETAIL 'A'

INSIDE

SUBSTATION

OUTSIDE

SUBSTATION

OUTSIDE

SUBSTATION

INSIDE

SUBSTATION

CABLE ENTRY DUCT

EXTENDED TO THE

SITE BOUNDARY

MIN

. 7

5

DUCT SPACER

( PROVIDED BY HK ELECTRIC )

SHALL BE INSTALLED AT BOTH

ENDS OF THE PRE-CAST DUCT

BANK. REINFORCEMENT SHALL

BE ADDED BY DEVELOPER

ACCORDING TO THEIR OWN

DESIGN.

NOMINAL 800

( MINIMUM 500 MAY BE ACCEPTED

DUE TO SITE CONSTRAINT, PLEASE

REFER TO THE SUBSTATION LAYOUT DRAWING )

PRE-CAST DUCT BANK

( SEE DETAIL 'A' )

PRE-CAST CABLE ENTRY DUCT BANK

WATER PROOF CEMENT

WITH SUFFICENT

BONDING STRENGTH TO

UPVC DUCT TO ACHIEVE

A WATER TIGHT SEALING

150-mm UPVC PIPE

PROVIDED BY HK ELECTRIC

CONSTRUCTION OF PRE-CAST DUCT BANK SHALL BE IN GENERAL IN ACCORDANCE WITH THE

FOLLOWING :

TO BE SEALED OR GROUTED

IN-SITU BETWEEN PRE-CAST DUCT BANK AND

BUILDING WALL / SUBSTATION STRUCTURE.

REINFORCEMENT TO BE ADDED BY DEVELOPER

ACCORDING TO THEIR OWN DESIGN.

UPVC END CAP

FOR 150-mm

UPVC DUCT

PROVIDED BY

HK ELECTRIC

Drg. No. GCS/3/19TYPICAL ARRANGEMENT OF CABLE ENTRY DUCTS IN

SUBSTATION (P627/05/R-1) SHEET 2 OF 2

NOTE:

ALL DIMENSIONS ARE IN mm

3.66

EL

EV

AT

IO

N ( F

OR

H

EIG

HT

5

m

)

EL

EV

AT

IO

N ( F

OR

H

EIG

HT

>

5

m

)

1000 100

MIN

. 2

00

0

1000 100

SE

PA

RA

TIO

N

BE

TW

EE

N

AD

JA

CE

NT

CA

BLE

C

LE

AT

S

SH

ALL B

E N

OT

LE

SS

T

HA

N 150 m

m

CE

NT

RE

LIN

E

OF

C

AB

LE

SE

PA

RA

TIO

N

BE

TW

EE

N

AD

JA

CE

NT

CA

BLE

C

LE

AT

S

SH

ALL B

E N

OT

LE

SS

T

HA

N 150 m

m

VE

RT

IC

AL O

FF

SE

T

SE

PA

RA

TIO

N

TO

B

E 50 m

m

TW

O-B

OLT

CLE

AT

TR

EF

OIL

CLE

AT

SIN

GLE

-B

OLT

CLE

AT

F

OR

SO

LK

OR

C

AB

LE

CE

NT

RE

LIN

E

OF

C

AB

LE

CA

BLE

S T

O B

E

SU

PP

OR

TE

D

VE

RT

IC

ALLY

IN

S

NA

KIN

G

MA

NN

ER

SIN

GLE

-B

OLT

CLE

AT

TW

O-B

OLT

CLE

AT

SIN

GLE

-B

OLT

CLE

AT

TR

EF

OIL

CLE

AT

SIN

GLE

-B

OLT

CLE

AT

F

OR

SO

LK

OR

C

AB

LE

MIN

. 2

00

0

1000 100 1000 100 1000 100

1000 100 1000 1001000 100

1000 100 1000 100

1000 100 1000 100

PL

AN

480

MIN

. 2

00

0

FL

OO

R

MIN. 800

SP

AC

E B

ET

WE

EN

F

LO

OR

S

TO

B

E F

IT

TE

D / F

ILLE

D W

IT

H

FIR

E R

ES

IS

TA

NT

M

ES

HE

S /

SLA

BS

A

ND

S

EA

LE

D U

P W

IT

H

FIR

E P

RO

TE

CT

IV

E M

OR

TA

R

TO

F

SD

R

EQ

UIR

EM

EN

TS

A

ND

AT

LE

AS

T O

F 2-H

OU

R F

RP

200 m

m(H

)

TO

E B

OA

RD

FU

LL W

ID

TH

AC

CE

SS

PA

NE

L /

DO

OR

I R

Drg

. No.

GC

S/3/

20TY

PIC

AL

AR

RA

NG

EMEN

T O

F C

AB

LES

AN

D C

AB

LE C

LEA

TSIN

RIS

ER D

UC

T (V

ERTI

CA

L H

EIG

HT

7

MET

RE)

(P67

1/08

/R-3

) SH

EET

1 O

F 2

3.67

STU

D

TYPI

CAL

DES

IGN

OF

TWO

-BO

LT C

LEAT

CAB

LEC

LEAT

FIXI

NG

RAI

LTO

BE

ANC

HO

RED

ON

WAL

L

TYPI

CAL

DES

IGN

OF

TREF

OIL

CLE

AT

TYPI

CAL

DES

IGN

OF

SIN

GLE

-BO

LT C

LEAT

RU

BBER

PAD

( 2 N

os. )

STU

D

CAB

LEC

LEAT

FIXI

NG

RAI

LTO

BE

ANC

HO

RED

ON

WAL

L

Drg

. No.

GC

S/3/

20TY

PIC

AL

AR

RA

NG

EMEN

T O

F C

AB

LES

AN

D C

AB

LE C

LEA

TSIN

RIS

ER D

UC

T (V

ERTI

CA

L H

EIG

HT

7

MET

RE)

(P67

1/08

/R-3

) SH

EET

2 O

F 2

3.68

3.69

Notes for Drawing No. GCS/3/20 1. Customer is required to provide the appropriate type and size of cable cleat to suit

the following cables to be installed in riser duct. Exact type of cables to be used will be specified in the substation layout drawing.

2. The developer should be responsible for temporary removal of the cable cleats for

HK Electric’s cable installation for substation commissioning and re-installing the cable cleats after HK Electric’s cable laying, if so required by HK Electric during the course of their cabling work.

3. External diameters of HK Electric cables are: -

Designated code

of cable

Cable description Size Type of cable cleat

to be used

T-2 HV 300-mm2 3/C Cu cable 101±3 mm Two-bolt cleat

T-4 HV 300-mm2 1/C SUSWA Cu

cable

53±3 mm Trefoil cleat

R-3 HV 240-mm2 3/C Cu cable 91±3 mm Two-bolt cleat

G-1 LV 300-mm2 4/C AL cable 73±3 mm Two-bolt cleat

P-1 Telephone / pilot cable 32±3 mm Single-bolt cleat

Y-1 Earthing cable 25±3 mm Single-bolt cleat

S-1 Solkor cable 38±3 mm Single-bolt cleat

(The designated code of cable will be applied and quoted in the substation layout

drawing for reference)

4. Weight of each LV power cable shall be taken as 15 kgf per metre, where weight of

each HV 3/C cable or each set of HV 3 x 1/C cable should be taken as 20 kgf per

metre.

5. Material of cable cleat and the associated bolts, nuts, washers and spring washers,

etc. to be aluminium alloy, other metals or alloy with corrosion resistant coating /

plating. Cable cleats of non-metallic material will NOT be accepted.

6. Each trefoil cleat and two-bolt cable cleat shall be type tested to withstand a vertical

safe working load (SWL) of not less than 15 times the 1 metre length of the cable to

be cleated.

3.70

Notes for Drawing No. GCS/3/20

7. Design operating temperature of cable cleat shall be from 0oC to 85oC.

8. The cable cleats shall be mounted on suitable fixings. The stud size for trefoil cable

cleat and two-bolt cable cleat shall be not less than M12. Rubber pad as a

supplementary mat for securing the cable shall be provided for each cable cleat.

9. The horizontal fixing rail shall be of hot dip galvanised steel or other corrosion

resistant material and be designed and constructed to withstand a vertical SWL of

the higher value of (a) or (b) below.

a. 1000 kgf.

b. n times 200 kgf where n is the total number of cleats on the same fixing rail.

10. A clear working space of not less than 900 mm should be provided in front of the

cable cleats.

11. Customer is required to submit catalogues and/or samples of cable cleats for

approval.

ELEVATION

PLAN

VERTICAL OFFSET SEPARATIONTO BE FROM 100 mm TO 125 mm

CENTRE LINE OF CABLE

CABLES TO BESUPPORTED VERTICALLYIN SNAKING MANNER

TREFOIL CLEATFOR ONE CIRCUIT OF HV 1/C CABLE

FULL WIDTHACCESSPANEL /DOOR

MIN

. 80

0

SINGLE-BOLT CLEATFOR SOLKOR CABLE

TWO-BOLT CLEATFOR LV CABLE

FIXED GUARD RAILS AT500-mm INTERVAL WITHREMOVABLE GUARD CHAINSAT THE OPEN SIDE OFTHE WORKING PLATFORM ,THE REMOVABLE GUARDCHAINS TO BE FIXED AT500 mm HIGH & 1100 mm HIGH ,TOE BOARD OF 200 mm HIGHAT THE EDGE OF WORKINGPLATFORM

SEPARATION BETWEENADJACENT CABLE CLEATSSHALL BE NOT LESS THAN150 mm

SINGLE-BOLTCLEAT

TWO-BOLTCLEAT

SINGLE-BOLTCLEAT FORSOLKOR CABLE

TREFOILCLEAT

1400

± 1

00

1000

± 1

0040

0

'W'

'W'

FLOOR

W= 1500 mm (MIN.) IF NO WORKING PLATFORM IS TO BE INSTALLED INSIDE THE CABLE RISER DUCT ROOM

W= 2000 mm (MIN.) IF WORKING PLATFORM(S) IS / ARE TO BE INSTALLED INSIDE THE CABLE RISER DUCT ROOM

SPACE BETWEEN FLOORSTO BE FITTED WITHFIRE RESISTANT MESHES /SLABS AND SEALED UP WITHFIRE PROTECTIVE MORTARTO FSD REQUIREMENTS( BILINGUAL WARNING SIGN STATING " FIRE RESISTANT MATERIAL FILLER! DO NOT STEP ON ! ! ! " SHALL BE PROVIDED ON EACH SLAB )

1400

± 1

00

1000

± 1

0010

00 ±

100

Drg. No. GCS/3/21TYPICAL ARRANGEMENT OF CABLES AND CABLE CLEATS

IN RISER DUCT FOR UPPER FLOOR SUBSTATION OR BASEMENTSUBSTATION WITH LEVEL DIFFERENCE EXCEEDING 7 m

(P666/08/R-4) SHEET 1 OF 2

NOTE:ALL DIMENSIONS ARE IN mm

3.71

FIX

IN

G R

AIL

TO

B

E

AN

CH

OR

ED

ON

W

AL

L

CA

BL

E

CL

EA

T

ST

UD

TY

PIC

AL D

ES

IG

N O

F T

RE

FO

IL C

LE

AT

( N

ON

-M

ET

AL

LIC

P

AR

TS

T

O B

E L

SF

)

TY

PIC

AL D

ES

IG

N O

F S

IN

GLE

-B

OLT

C

LE

AT

LS

F P

AD

( 2

N

os. )

FIX

IN

G R

AIL

TO

B

E A

NC

HO

RE

D

ON

W

AL

L

CA

BL

E

CL

EA

T

ST

UD

TY

PIC

AL D

ES

IG

N O

F T

WO

-B

OLT

C

LE

AT

( N

ON

-M

ET

AL

LIC

P

AR

TS

T

O B

E L

SF

)

Drg

. No.

GC

S/3/

21TY

PIC

AL

AR

RA

NG

EMEN

T O

F C

AB

LES

AN

D C

AB

LE C

LEA

TSIN

RIS

ER D

UC

T FO

R U

PPER

FLO

OR

SU

BST

ATI

ON

OR

BA

SEM

ENT

SUB

STA

TIO

NW

ITH

LEV

EL D

IFFE

REN

CE

EXC

EED

ING

7 m

(P66

6/08

/R-4

) SH

EET

2 O

F 2

3.72

3.73

Notes for Drawing No. GCS/3/21 1. Customer is required to provide the appropriate type and size of cable cleat to suit

the following cables to be installed in riser duct. Exact type of cables to be used will be specified in the substation layout drawing.

2. The developer should be responsible for temporary removal of the cable cleats for

HK Electric’s cable installation for substation commissioning and re-installing the cable cleats after HK Electric’s cable laying, if so required by HK Electric during the course of their cabling work.

3. External diameters of HK Electric cables are: -

Designated code

of cable

Cable description Size Type of cable cleat

to be used

T-3 HV 300-mm2 1/C Cu LSF cable 50±3 mm Trefoil cleat

R-2 HV 240-mm2 3/C Cu LSF cable 81±3 mm Two-bolt cleat

G-2 LV 300-mm2 4/C AL LSF cable 73±3 mm Two-bolt cleat

S-2 LSF Solkor cable 38±3 mm Single-bolt cleat

P-2 Telephone / Pilot LSF cable 32±3 mm Single-bolt cleat

Y-2 Earthing LSF cable 25±3 mm Single-bolt cleat

(The designated code of cable will be applied and quoted in the substation layout

drawing for reference)

4. Material of cable cleat and the associated bolts, nuts, washers and spring washers,

etc. should be of aluminium alloy, other metals or alloy with corrosion resistant

coating / plating. Cable cleats of non-metallic material will NOT be accepted.

5. Each trefoil cleat and two-bolt cleat shall be type tested to withstand a vertical safe

working load (SWL) of not less than 15 times the 1.4 metre length of the cable to be

cleated. Each single-bolt cleat shall be type tested to withstand a vertical SWL of

not less than 15 times of the cable to be cleated which should be taken as 4 kgf per

metre.

6. Weight of each LV power cable shall be taken as 15 kgf per metre, where weight of

each HV 3/C power cable or each set of HV 3 x 1/C power cable shall be taken as

20 kgf per metre.

3.74

Notes for Drawing No. GCS/3/21

7. The horizontal fixing rail shall be of hot dip galvanised steel or other corrosion

resistant material and be designed and constructed to withstand a vertical SWL of

the higher value of (a) or (b) below.

a. 1000 kgf.

b. n times 200 kgf where n is the total number of cleats on the same fixing rail.

8. The cable cleats shall be mounted on suitable fixings. The stud size for trefoil cleat

and two-bolt cleat shall be not less than M12. LSF lining or pad as a supplementary

mat for securing the cable shall be provided for each cable cleat.

9. Design operating temperature of cable cleat shall be from 0oC to 85oC.

10. Customer is required to submit catalogues and/or samples of cable cleats for

approval.

11. LSF stands for low smoke fume and zero halogen to IEC, BS, UL or ASTM

standards.

HIG

H L

EV

EL

HA

ZA

RD

Z

ON

E

HIG

H LE

VE

L H

AZ

AR

D Z

ON

E U

NLE

SS

T

HE

Y A

RE

A

T LE

SS

T

HA

N 2300 m

m

SM

OK

E D

ET

EC

TO

R, A

XIA

L F

LO

W F

AN

, F

LE

XIB

LE

C

ON

DU

IT

F

OR

F

AN

A

ND

1. N

O F

LU

OR

ES

CE

NT

LA

MP

F

IT

TIN

G, E

XIT

LIG

HT

F

IT

TIN

G, H

EA

T D

ET

EC

TO

R,

EM

ER

GE

NC

Y P

US

H B

UT

TO

N F

OR

F

AN

S

HA

LL B

E IN

ST

ALLE

D W

IT

HIN

T

HE

2. A

LL D

IM

EN

SIO

NS

A

RE

IN

m

m.

HIG

H W

HE

N M

EA

SU

RE

D F

RO

M S

UB

ST

AT

IO

N F

LO

OR

.

NO

TE

S:

R=

11

50

700

RE

AR

400 780

SW

IT

CH

GE

AR

HV

FR

ON

T

AR

C F

AU

LT

80

0

700

VE

NT

RE

LIE

F

TR

AN

SF

OR

ME

R

R=950

300

70

04

00

1690

HV

C

AB

LE

70

0

BO

X

Drg

. No.

GC

S/3/

22H

IGH

LEV

EL H

AZA

RD

ZO

NE

(P34

6/97

)

3.75

Drg

. No.

GC

S/3/

23SU

BST

ATI

ON

LO

UV

RES

DET

AIL

S (P

638/

06/R

-1)

3.76

3.77

Drg. No. GCS/3/24

INFORMATION ON APPLICATION FOR EXCAVATION PERMIT SHEET 1 OF 2

香港電燈有限公司 THE HONGKONG ELECTRIC CO., LTD.

Do you know that HK Electric has to apply for an Excavation Permit from Highways Department of HKSAR Government before laying a cable to make electricity available to you? Here are some facts on how HK Electric applies for the Excavation Permit, how much it costs to HK Electric and how long it will take. Summary of amended Ordinance effective on 1st April 2004 for Excavations in Public Streets and Footpaths All excavations are controlled under the Land (Miscellaneous

Provisions) Ordinance, Cap. 28.

An Excavation Permit is required for excavations in unleased Government land, otherwise a fine up to $50,000 and an imprisonment for 6 months can be imposed. In majority of cases, HK Electric applies for Excavation Permit from Highways Department*. * For minority of cases, HK Electric has to apply for permit from other Government authority.

Fees to be paid by HK Electric for each Excavation Permit granted by

Highways Department.

Application Fee HK$2,050 / permit

Daily Fee HK$35 / day

Extension Fee HK$650 / permit

Unless with accepted reasons, a daily economic cost will be charged

to HK Electric if HK Electric does not complete the excavations involving carriageway on time and extension is required.

Strategic Streets HK$21,000 / day

Sensitive Streets HK$8,540 / day

Streets other than the above two classes HK$1,710 / day

3.78

Drg. No. GCS/3/24 INFORMATION ON APPLICATION FOR EXCAVATION PERMIT

SHEET 2 OF 2

Time required for HK Electric to register and submit an application for an Excavation Permit before work commencement: 1. Minimum Registration Lead Time:

Works on carriageway of trunk roads or works on any carriageway exceeding 3 months

6 months

Works on carriageway other than trunk roads not exceeding 3 months or works not on carriageway but exceeding 3 months

2 months

Works not on carriageway and not exceeding 3 months 1 month

2. HK Electric is also required to coordinate with other utility undertakers for the program of work such that the overall disturbance brought to the public will be kept to a minimum before Highways Department granting the Excavation Permit. These utility undertakers include the telecommunication service companies, Gas Company, Drainage Service Department, Water Supplies Department, and etc. Also, Highways Department imposes a 3-month excavation restriction period after excavation by all other Utilities Undertakings to avoid repeated excavation in the same location. A 6-month restriction period will be imposed by Highways Department after excavation by HK Electric at the same location.

3. HK Electric has to obtain consent from Transport Department and Hong Kong Police Force of the proposed excavation work before Highways Department grants the Excavation Permit to HK Electric. With the current arrangement, Transport Department and Hong Kong Police Force will only provide comments to HK Electric’s excavation proposals for the excavation works in Traffic Management Liaison Group Meeting (TMLG Meeting) with limited meeting time each month.

4. HK Electric may be required to approach the following parties for their comments or consent of the excavation work before Highways Department grants the Excavation Permit to HK Electric:

Environmental Protection Department MTR Corporation Limited

Leisure and Culture Services Department E&M Services Department

Architectural Services Department

5. Overall time required for obtaining an Excavation Permit from Highways Department:

More than 10 weeks (excluding the registration time) for a typical case in footpath.

For more information: You may visit the website of Highways Department http://www.hyd.gov.hk for more details on Excavation Permit.

900

1515

100 150

150 100

15

0

80

20

01

6

40

50

0

30

0

125

900

450

40

10

5

100

200

200

15

0

15

0

20

0

200

CU

BIC

LE

DO

OR

W

IT

H

GA

SK

ET

A

LL

A

RO

UN

D

FR

ON

T V

IE

W

DIR

EC

TIO

N

TO

S

EC

UR

E

10

10

SID

E V

IE

W

HIN

GE

HIN

GE

DO

OR

30

1

0 H

OL

E

MO

UN

TIN

G B

RA

CK

ET

OF

T

HIC

KN

ES

S

NO

T L

ES

S T

HA

N 4

.5

m

m

BE

TW

EE

N

16

00

A

ND

20

00

AB

OV

E

FL

OO

R

LE

VE

L

FL

OO

R

30

30

:

,

DA

NG

ER

S

IG

N

LA

BE

L T

O B

E

PA

IN

TE

D O

N D

OO

R

CH

IN

ES

E C

HA

RA

CT

ER

S O

F

15

m

m H

IG

H IN

B

LA

CK

HK

E

LE

CT

RIC

kW

h

30

HIN

GE

W

IT

H

ST

AIN

LE

SS

S

TE

EL

P

IN

10

0-A

NE

UT

RA

L

BL

OC

K

HA

ND

LE

HA

ND

LE

HA

ND

LE

W

IT

H

LO

CK

IN

G F

AC

IL

IT

Y

( S

EE

D

ET

AIL

S O

F

D

OU

BL

E L

OC

KIN

G

F

AC

IL

IT

Y )

HA

ND

LE

HA

ND

LE

HA

ND

LE

W

IT

H

LO

CK

IN

G

FA

CIL

IT

Y

( S

EE

D

ET

AIL

S

O

F D

OU

BL

E

L

OC

KIN

G

F

AC

IL

IT

Y )

20

CA

BL

E C

LA

MP

N

o.2

TO

B

E S

UP

PL

IE

D L

OO

SE

(S

AM

E S

IZ

E A

S C

LA

MP

N

o.1

)

CA

BLE

C

LA

MP

N

o.3

TO

B

E S

UP

PLIE

D LO

OS

E

(S

AM

E S

IZ

E A

S C

LA

MP

N

o.1 )

20

0 x 1

50

P

ER

SP

EX

W

IN

DO

W

FO

R M

ET

ER

R

EA

DIN

G

2 N

os. O

F C

AB

LE

C

LA

MP

TO

B

E IN

ST

AL

LE

D B

Y

CU

ST

OM

ER

O

N T

HE

SU

PP

OR

T F

RA

ME

F

OR

MO

UN

TIN

G H

K E

LE

CT

RIC

CA

BL

ES

O

F 3

7 m

m

OW

NE

RS

HIP

O

F T

HIS

E

NC

LO

SU

RE

B

ELO

NG

S T

O T

HE

U

SE

R,

CO

MP

AN

Y N

AM

E:

DIR

EC

TIO

N

TO

SE

CU

RE

LE

TT

ER

S O

F

10

m

m H

IG

H IN

B

LA

CK

TO

B

E

IN

ST

ALLE

D B

Y

CU

ST

OM

ER

ON

S

IT

E

HIN

GE

W

IT

H

ST

AIN

LE

SS

S

TE

EL

P

IN

LE

TT

ER

S O

F 1

0 m

m H

IG

H

IN

R

ED

CH

IN

ES

E C

HA

RA

CT

ER

S

OF

1

5 m

m H

IG

H IN

R

ED

HIN

GE

HIN

GE

W

IT

H

ST

AIN

LE

SS

S

TE

EL

P

IN

2 P

IE

CE

S O

F

46

0 W

ID

E x 4

30

H

IG

H

25

-m

m-T

HIC

K P

LY

WO

OD

BO

AR

D

20

3-P

HA

SE

M

ET

ER

1-P

HA

SE

M

ET

ER

10

0-A

P

VC

C

UT

OU

T

450

200

ME

TE

R

Drg

. No.

GC

S/3/

25M

ILD

STE

EL W

EATH

ERPR

OO

F EN

CLO

SUR

E FO

R S

ITE

SER

VIC

ES U

P TO

100

A 3

-PH

ASE

(P63

0/06

/R-2

) SH

EET

1 O

F 4

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.79

900

100 150

150 100

310

500

105

50

460

20 20860

170

430

21

55

5

46

0

430

46

0

149

21

0

150

L1

L2

L3

N

22 22

45

45

45

50

22

22

15

ED

GE

F

OL

DE

D U

P 1

5 m

m

TO

M

AT

CH

T

HE

G

AS

KE

T

ON

D

OO

R

2

100-A

N

EU

TR

AL B

LO

CK

IN

NE

R F

RO

NT

V

IE

W

HK

E

LE

CT

RIC

100-A

P

VC

C

UT

OU

T

LV

C

AB

LE

( B

Y H

K E

LE

CT

RIC

)

MO

UN

TIN

G

BR

AC

KE

T

CU

ST

OM

ER

'S

WIR

IN

G

TO

CU

ST

OM

ER

'S

LO

AD

CA

BL

E C

LA

MP

N

o.1

F

OR

HK

E

LE

CT

RIC

C

AB

LE

O

F

3

7-m

m ( S

EE

D

ET

AIL

S O

F

CA

BL

E C

LA

MP

N

o.1

)

SP

AC

E

RE

SE

RV

ED

F

OR

TE

RM

IN

AT

IO

N

OF

H

K E

LE

CT

RIC

UN

DE

RG

RO

UN

D

CA

BL

E

SP

AC

E

FO

R H

K

Electric

CA

BLE

LA

BE

L

AN

D S

N

LA

BE

L

CO

PP

ER

E

AR

TH

IN

G

TE

RM

IN

AL IN

O

NE

P

IE

CE

FO

R 2x 35-m

m

CO

ND

UC

TO

R

( E

AR

TH

IN

G O

F

T

HE

E

NC

LO

SU

RE

T

O B

E B

Y

C

US

TO

ME

R )

CO

PP

ER

E

AR

TH

IN

G S

TU

D

EA

RT

H

BO

ND

IN

G

FO

R D

OO

R

HK

E

LE

CT

RIC

2 P

IE

CE

S O

F

46

0 W

ID

E x 4

30

H

IG

H

25

-m

m-T

HIC

K P

LY

WO

OD

BO

AR

D

CU

ST

OM

ER

'S

MA

IN

S

WIT

CH

WIT

H R

CD

HK

E

LE

CT

RIC

CU

TO

UT

HK

E

LE

CT

RIC

ME

TE

R

LO

WE

R P

LY

WO

OD

B

OA

RD

WH

IT

E P

AIN

T

MA

RK

IN

G

20

m

m H

IG

H

UP

PE

R P

LY

WO

OD

B

OA

RD

MA

IN

S

W.

WH

IT

E P

AIN

T

MA

RK

IN

G

( E

NG

LIS

H L

ET

TE

RS

2

0 m

m H

IG

H ;

C

HIN

ES

E C

HA

RA

CT

ER

S

4

0 m

m H

IG

H )

DE

TA

ILS

O

F P

LY

WO

OD

B

OA

RD

ST

IC

K A

5 S

IZ

E

BIL

IN

GU

AL

RE

MIN

DE

R

NO

TIC

E H

ER

E

( T

EM

PO

RA

RY

)

WH

IT

E A

RE

A

FO

R F

IX

IN

G

CU

ST

OM

ER

'S

WIR

IN

G

3-P

HA

SE

ME

TE

R

TH

E C

AB

LE

E

ND

S T

ER

MIN

AT

ED

O

NT

O

HK

E

LE

CT

RIC

S

ER

VIC

E C

UT

OU

T

SH

AL

L B

E F

IT

TE

D W

IT

H P

RO

PE

R,

DU

RA

BL

E A

ND

L

EG

IB

LE

P

HA

SE

ID

EN

TIF

IC

AT

IO

N L

AB

EL

S ( S

UC

H A

S

CA

BL

E T

IE

S, S

LE

EV

ES

, F

ER

RU

LE

S

ET

C. ) M

AR

KE

D IN

L

1, L

2, L

3 A

ND

N

.

100

19

0

ME

TE

R

1-P

HA

SE

( E

NC

LO

SU

RE

D

OO

R O

MIT

TE

D F

OR

C

LA

RIT

Y)

kW

h M

ET

ER

kW

h M

ET

ER

Drg

. No.

GC

S/3/

25M

ILD

STE

EL W

EATH

ERPR

OO

F EN

CLO

SUR

E FO

R S

ITE

SER

VIC

ES U

P TO

100

A 3

-PH

ASE

(P63

0/06

/R-2

) SH

EET

2 O

F 4

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.80

16

50

0

95

15

2

5

10

5

60

80

BO

TT

OM

V

IE

W

HA

ND

LE

DO

OR

T

O

SW

IN

G 1

80

200

216

1 x 5

2 O

PE

NIN

G

WIT

H R

UB

BE

R B

UN

G

FO

R H

K E

LE

CT

RIC

UN

DE

RG

RO

UN

D C

AB

LE

DE

TA

IL

S O

F C

AB

LE

C

LA

MP

N

o.1

CA

BL

E C

LA

MP

N

o.1

HK

E

LE

CT

RIC

C

AB

LE

OF

3

7 m

m

HK

E

LE

CT

RIC

C

AB

LE

OF

3

7 m

m

3-m

m-T

HIC

K M

IL

D S

TE

EL

M4

S

CR

EW

S

37

TH

RE

E O

PE

NIN

GS

WIT

H R

UB

BE

R B

UN

G

FO

R C

US

TO

ME

R'S

IN

CO

MIN

G W

IR

IN

G &

OU

TG

OIN

G W

IR

IN

GS

FR

OM

M

ET

ER

6

4

6

4

6

4

45

0 W

ID

E x 8

85

H

IG

H

25

-m

m-T

HIC

K P

LY

WO

OD

BO

AR

D

80

80

Drg

. No.

GC

S/3/

25M

ILD

STE

EL W

EATH

ERPR

OO

F EN

CLO

SUR

E FO

R S

ITE

SER

VIC

ES U

P TO

100

A 3

-PH

ASE

(P63

0/06

/R-2

) SH

EET

3 O

F 4

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.81

100

20 20

40

100

100

HO

AR

DIN

G

CO

NS

TR

UC

TIO

N S

IT

E

PA

VE

ME

NT

LO

CA

TIO

N P

LA

N

WE

AT

HE

RP

RO

OF

EN

CLO

SU

RE

TH

IS

R

EC

ES

S A

RE

A

SH

AL

L B

E C

OV

ER

ED

CU

ST

OM

ER

S

HA

LL

P

RO

VID

E R

OB

US

T

ST

EE

L S

UP

PO

RT

F

RA

ME

F

OR

M

OU

NT

IN

G

TH

E E

NC

LO

SU

RE

T

O E

NS

UR

E S

AF

ET

Y

EV

EN

D

UR

IN

G T

YP

HO

ON

S

EA

SO

N.

1 )

2)

3)

DE

TA

IL

S O

F

DO

UB

LE

L

OC

KIN

G F

AC

IL

IT

Y

( F

RO

NT

)

EN

CLO

SU

RE

6-m

m-T

HIC

K L

OC

K B

AR

14

L

OC

K H

OL

E

CE

NT

RE

L

IN

E O

F E

NC

LO

SU

RE

14

L

OC

K H

OL

E

HA

ND

LE

1

0 R

OD

F

OR

HA

ND

LE

R

OT

AT

IO

N

HA

ND

LE

TH

E E

ND

T

O B

E

BE

NT

O

UT

WA

RD

S

BY

1

0 m

m

TH

E E

NC

LO

SU

RE

S

HA

LL

B

E C

OL

LE

CT

ED

AN

D IN

ST

AL

LE

D B

Y C

US

TO

ME

R A

ND

W

IL

L

BE

S

UB

SE

QU

EN

TL

Y L

OC

KE

D B

Y C

US

TO

ME

R

AN

D B

Y H

K E

LE

CT

RIC

.

CU

ST

OM

ER

S

WIT

CH

C

UB

IC

LE

FO

R H

OU

SIN

G T

HE

IR

D

IS

TR

IB

UT

IO

N B

OA

RD

( S

IZ

E T

O B

E D

EC

ID

ED

B

Y C

US

TO

ME

R )

2x M

IL

D S

TE

EL

CO

LL

AR

W

EL

DE

D

( IN

F

UL

L S

EA

M )

TO

C

AS

IN

G

DO

OR

3

-m

m

DR

AIN

H

OL

E

AT

B

OT

TO

M

MIL

D S

TE

EL C

OL

LA

R F

OR

10

R

OD

EN

CL

OS

UR

E

DO

OR

2x M

IL

D S

TE

EL

CO

LL

AR

W

EL

DE

D

( IN

F

UL

L S

EA

M )

TO

C

AS

IN

G

10

R

OD

W

IT

H 1

.5

-m

m-T

HIC

K x 1

5-m

m-H

IG

H

CO

PP

ER

S

LE

EV

ES

T

O B

E F

IR

ML

Y F

IT

TE

D T

O

TH

E U

PP

ER

E

ND

&

L

OW

ER

E

ND

F

OR

E

AS

Y

RO

TA

TIO

N

TH

E E

NC

LO

SU

RE

T

OG

ET

HE

R W

IT

H H

K E

LE

CT

RIC

SE

RV

IC

E C

UT

OU

T , M

ET

ER

A

ND

W

IR

IN

G

( E

XC

LU

DIN

G C

US

TO

ME

R'S

M

AIN

S

WIT

CH

)

IS

O

F A

PP

RO

XIM

AT

E W

EIG

HT

O

F 4

0 kg

.

NO

TE

S:

PO

SIT

IO

N O

F E

NC

LO

SU

RE

S

HA

LL

B

E A

T

TH

E B

OU

ND

AR

Y O

F C

ON

ST

RU

CT

IO

N

SIT

E A

ND

B

E F

AC

IN

G T

HE

P

AV

EM

EN

T. A

MIN

IM

UM

C

LE

AR

AN

CE

S

PA

CE

O

F 9

00

m

m

FO

R T

HE

F

UL

L W

ID

TH

IN

F

RO

NT

O

F

EN

CL

OS

UR

E S

HA

LL

B

E P

RO

VID

ED

. A

CL

EA

R A

CC

ES

S T

O T

HE

E

NC

LO

SU

RE

SH

AL

L B

E P

RO

VID

ED

W

IT

HO

UT

A

NY

OB

ST

RU

CT

IO

N F

RO

M C

OV

ER

ED

WA

LK

WA

Y.

4)

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m.

Drg

. No.

GC

S/3/

25M

ILD

STE

EL W

EATH

ERPR

OO

F EN

CLO

SUR

E FO

R S

ITE

SER

VIC

ES U

P TO

100

A 3

-PH

ASE

(P63

0/06

/R-2

) SH

EET

4 O

F 4

3.82

1.In

gen

eral

the

oper

atio

n of

a s

ubst

atio

n do

or w

ith d

ecor

atio

ncl

addi

ng o

r a d

ecor

ativ

e do

or in

add

ition

to th

e st

anda

rdsu

bsta

tion

door

wou

ld o

ccup

y m

uch

larg

er a

rea

of p

avem

ent i

nfro

nt o

f the

sub

stat

ion.

Any

suc

h de

cora

tive

feat

ures

on

the

subs

tatio

n do

or o

r the

add

ition

of a

dec

orat

ive

door

sho

uld

beav

oide

d as

far a

s pr

actic

able

from

ope

ratio

nal p

oint

of v

iew

.In

cas

e an

y su

bsta

tion

door

is o

f suc

h de

sign

and

/ or

an

addi

tiona

l dec

orat

ive

door

in fr

ont o

f the

sub

stat

ion

door

ispr

opos

ed, H

K El

ectri

c sh

all h

ave

the

disc

retio

n on

the

acce

ptan

ce o

f suc

h pr

opos

al d

epen

ding

on

the

actu

al s

itesi

tuat

ion.

The

arc

hite

ct /

deve

lope

r sha

ll su

bmit

thei

rpr

opos

al in

the

subs

tatio

n de

sign

sta

ge fo

r HK

Elec

tric’

sco

nsid

erat

ion.

Thi

s dr

awin

g de

pict

s on

ly th

e ge

nera

l con

ditio

nson

acc

epta

nce

of a

n ad

ditio

nal d

ecor

ativ

e do

or in

fron

t of t

hesu

bsta

tion

door

of a

gro

und

floor

sub

stat

ion

and

/ or a

ttach

ing

exte

rnal

dec

orat

ive

clad

ding

to s

ubst

atio

n do

or fo

r ref

eren

cepu

rpos

e.

2.G

ener

al re

quire

men

ts fo

r bot

h th

e su

bsta

tion

door

with

deco

ratio

n cl

addi

ng a

nd th

e ad

ditio

nal d

ecor

ativ

e do

or in

fron

tof

the

stan

dard

sub

stat

ion

door

of a

sub

stat

ion

at g

roun

d flo

or

2.1

A ca

nopy

abo

ve th

e su

bsta

tion

door

sha

ll be

pro

vide

dac

cord

ing

to H

K El

ectri

c dr

awin

g.

2.2

A sp

ace

of n

ot le

ss th

an 1

,000

mm

(H) x

600

mm

(W) a

t 1,4

00 m

mce

ntre

abo

ve p

avem

ent l

evel

, with

pro

per m

ount

ing

faci

litie

ssh

all b

e pr

ovid

ed fo

r mou

ntin

g th

e su

bsta

tion

nam

e pl

ates

and

war

ning

sig

n on

ext

erna

l sur

face

of t

he d

oor.

2.3

The

prop

osed

add

ition

al d

oor o

r dec

orat

ive

louv

res/

clad

ding

on th

e st

anda

rd s

ubst

atio

n do

or s

hall

not r

esul

t in

any

adve

rse

effe

ct o

n th

e su

bsta

tion

vent

ilatio

n sy

stem

and

a m

inim

um fl

owra

te a

s st

ipul

ated

in th

e su

bsta

tion

layo

ut d

raw

ing

shal

l be

achi

eved

whe

n th

e su

bsta

tion

vent

ilatio

n sy

stem

is o

pera

ting.

Asi

te m

easu

rem

ent i

s re

quire

d to

con

firm

com

plia

nce

afte

r the

deco

rativ

e lo

uvre

s/cl

addi

ng o

r the

add

ition

al d

ecor

ativ

e do

or is

inst

alle

d.

2.4

In c

ase

ther

e is

any

def

ect/m

alfu

nctio

n of

the

subs

tatio

nve

ntila

tion

syst

em w

hich

may

affe

ct th

e su

bsta

tion

tem

pera

ture

,th

e de

velo

per s

hall

be re

spon

sibl

e fo

r kee

ping

the

addi

tiona

ldo

or fu

lly o

pen

(or d

ism

antli

ng th

e ad

ditio

nal d

oor i

f kee

ping

the

addi

tiona

l doo

r ope

n in

a p

rolo

nged

man

ner i

s no

t allo

wed

due

to th

e po

ssib

le o

bstru

ctio

n at

site

) / d

etac

hing

the

deco

rativ

e lo

uvre

s/cl

addi

ng fr

om th

e su

bsta

tion

door

tofa

cilit

ate

the

air c

ircul

atio

n up

on re

ques

t by

HK

Elec

tric.

2.5

A co

nfirm

atio

n le

tter s

hall

be p

rovi

ded

from

the

deve

lope

rto

und

erta

ke th

e re

spon

sibi

litie

s fo

r fut

ure

repa

ir /

mai

nten

ance

of t

he a

dditi

onal

sub

stat

ion

door

and

the

prop

osed

deco

rativ

e lo

uvre

s/cl

addi

ng o

n th

e su

bsta

tion

door

in c

ase

ofda

mag

e by

HK

Elec

tric

durin

g in

itial

equ

ipm

ent d

eliv

ery

and

futu

re tr

ansp

orta

tion

of s

uppl

y ap

para

tus

to a

nd fr

om th

esu

bsta

tion.

The

lette

r sha

ll al

so c

onfir

m th

eir c

ompl

ianc

e w

ithal

l the

requ

irem

ents

stip

ulat

ed in

this

Dra

win

g.

2.6

Subs

tatio

n D

oor S

win

g

The

subs

tatio

n do

or s

hall

be a

ble

to fu

lly o

pen

with

180

deg

ree

swin

g w

ith a

cle

ar o

peni

ng o

f not

less

than

2.0

m (W

) x 2

.6 m

(H)

afte

r the

sub

stat

ion

door

and

the

addi

tiona

l dec

orat

ive

door

have

bee

n fu

lly o

pene

d fo

r tra

nspo

rtatio

n of

HK

Elec

tric’

seq

uipm

ent t

o an

d fro

m th

e su

bsta

tion.

A 1

50 d

egre

e sw

ing

of th

esu

bsta

tion

door

whi

le m

aint

aini

ng a

cle

ar o

peni

ng o

f not

less

than

2.0

m (W

) x 2

.6 m

(H) w

ill al

so b

e ac

cept

able

pro

vide

d th

efo

llow

ing

cond

ition

s ar

e m

et:

(i)Th

e su

bsta

tion

door

and

the

addi

tiona

l dec

orat

ive

door

, whe

nbe

ing

open

ed o

utw

ards

ove

r any

stre

et, m

ust n

ot c

ause

an

obst

ruct

ion

to a

ny p

erso

n or

veh

icle

usi

ng th

e st

reet

.

(ii)

The

subs

tatio

n do

or is

faci

ng a

stre

et w

ith fo

otpa

th o

fcl

ear w

idth

of m

ore

than

2.5

m w

here

man

ual t

rans

porta

tion

of H

KEl

ectri

c’s

equi

pmen

t to

and

from

the

subs

tatio

n is

allo

wed

, or a

2-m

-wid

e cl

eara

nce

in th

e fo

otpa

th in

fron

t of t

he s

ubst

atio

ndo

or o

peni

ng c

an b

e m

aint

aine

d w

hen

both

the

subs

tatio

n do

or a

ndth

e de

cora

tive

door

are

fully

ope

ned.

Oth

erw

ise

an a

rrang

emen

tfo

r tra

nspo

rtatio

n of

HK

Elec

tric’

s eq

uipm

ent t

o an

d fro

m th

esu

bsta

tion

via

the

subs

tatio

n do

or s

houl

d be

pro

vide

d by

the

arch

itect

/ de

velo

per f

or a

gree

men

t / a

ccep

tanc

e by

HK

Elec

tric.

(iii)

Stop

pers

sha

ll be

des

igne

d an

d pr

ovid

ed to

pre

vent

the

deco

rativ

e lo

uvre

s/cl

addi

ng fr

om b

eing

dam

aged

in th

e co

urse

of

mov

emen

t of t

he s

ubst

atio

n do

or.

Stop

per(s

) sha

ll al

so b

epr

ovid

ed fo

r the

add

ition

al d

oor b

y th

e sa

me

toke

n.

(iv)

Latc

h or

sim

ilar m

eans

sha

ll be

des

igne

d an

d pr

ovid

ed to

secu

re th

e de

cora

tive

door

and

the

stan

dard

sub

stat

ion

door

at

its fu

lly o

pen

posi

tions

to a

void

sw

ingi

ng b

ack

of th

e do

or(s

)in

cas

e of

stro

ng w

ind

cond

ition

.

2.7

The

deco

rativ

e lo

uvre

s/cl

addi

ng o

n th

e su

bsta

tion

door

and

/or

the

addi

tiona

l dec

orat

ive

door

sha

ll no

t obs

truct

the

oper

atio

ns o

f the

lock

bar o

f the

sta

ndar

d su

bsta

tion

door

and

shal

l not

end

ange

r the

ope

rato

r whe

n op

enin

g an

d ca

rryin

g ou

tth

e lo

ckin

g/un

lock

ing

oper

atio

n of

the

subs

tatio

n do

or /

addi

tiona

l doo

r.

3.O

ther

requ

irem

ents

for a

dditi

onal

doo

r in

front

of a

sta

ndar

dsu

bsta

tion

door

of a

gro

und

floor

sub

stat

ion

3.1

The

addi

tiona

l dec

orat

ive

door

fitti

ng s

hall

be o

f sui

tabl

esi

ze w

hich

cou

ld a

llow

sm

ooth

ope

ratio

n an

d sh

all c

ompl

y fu

llyw

ith th

e fo

llow

ing

requ

irem

ents

:

(i)At

leas

t 4 N

os. o

f hin

ges

shal

l be

prov

ided

at e

ach

door

leaf

. Th

e hi

nges

sha

ll be

so

desi

gned

suc

h th

at th

e D

oor w

illop

en in

the

dire

ctio

n of

egr

ess.

Life

lubr

icat

ed h

inge

s sh

all

be p

rovi

ded.

(ii)

For d

oubl

e do

or, t

he ri

ght h

and

side

leaf

sha

ll be

ope

ned

first

whe

n vi

ewed

from

out

side

.

(iii)

Pull

hand

les

of s

tain

less

ste

el s

hall

be p

rovi

ded

for

sing

le d

oor a

nd fo

r bot

h le

aves

of d

oubl

e do

or.

(iv)

Equi

pote

ntia

l bon

ding

sha

ll be

pro

vide

d fo

r the

add

ition

aldo

or a

ccor

ding

to th

e la

test

edi

tion

of C

ode

of P

ract

ice

for t

heEl

ectri

city

(Wiri

ng) R

egul

atio

ns p

ublis

hed

by H

ong

Kong

SAR

Gov

ernm

ent.

3.2

The

deco

rativ

e do

or a

nd it

s fra

me

shal

l not

obs

truct

futu

rem

aint

enan

ce /

repl

acem

ent o

f the

sta

ndar

d su

bsta

tion

door

.

3.3

The

deve

lopm

ent o

wne

r / m

anag

emen

t com

pany

is n

ot a

llow

ed to

appl

y lo

ck o

f any

form

on

the

addi

tiona

l doo

r. In

cas

e lo

ckin

gof

suc

h ad

ditio

nal d

oor i

s ne

cess

ary,

a s

tain

less

ste

el lo

ck b

arsh

all b

e pr

ovid

ed a

nd b

e su

itabl

e fo

r HK

Elec

tric

pad

lock

with

shac

kle

diam

eter

of 1

4 m

m, a

cle

ar in

side

wid

th o

f 20

mm

and

insi

de le

ngth

of 1

6 m

m.

The

posi

tion

of lo

ck b

ar s

hall

be a

t11

00 m

m to

150

0 m

m a

bove

fini

shed

floo

r lev

el.

For D

oubl

e D

oor,

the

lock

bar

sha

ll be

on

the

left

hand

sid

e le

af w

hen

view

edfro

m o

utsi

de.

Verti

cal b

olts

sha

ll be

pro

vide

d fo

r the

left

hand

sid

e le

af to

sec

ure

in p

ositi

on b

efor

e cl

osin

g th

e rig

htha

nd s

ide

leaf

.

3.4

In a

dditi

on to

the

requ

irem

ent o

f pro

vidi

ng p

rope

rfa

cilit

ies

for m

ount

ing

HK

Elec

tric’

s do

or la

bel /

war

ning

sig

nas

des

crib

ed in

abo

ve it

em 2

.2, t

he d

evel

opm

ent o

wne

r is

also

requ

ired

to p

ost a

dur

able

sig

n / l

abel

on

the

addi

tiona

lde

cora

tive

door

to e

xplic

itly

stat

e th

eir o

wne

rshi

p an

dre

spon

sibi

litie

s of

mai

nten

ance

/ re

pair

of th

e ad

ditio

nal d

oor

for e

asy

site

iden

tific

atio

n.

4.O

ther

requ

irem

ents

for a

ttach

ing

exte

rnal

dec

orat

ive

louv

res/

clad

ding

to a

sta

ndar

d su

bsta

tion

door

4.1

The

hing

es o

f the

doo

r sha

ll be

des

igne

d an

d co

nstru

cted

tow

ithst

and

the

oper

atin

g w

eigh

t of t

he d

oor w

ith th

e pr

opos

edde

cora

tive

louv

res/

clad

ding

plu

s 50

kg

(ass

umin

g at

cen

tre o

fdo

or le

af) i

n or

der t

o ca

ter f

or th

e w

eigh

t of a

cces

sorie

s w

hich

HK

Elec

tric

may

inst

all o

nto

the

door

and

min

imum

four

Nos

. of

door

hin

ges

shal

l be

prov

ided

on

each

leaf

of t

he d

oors

. For

door

exc

eedi

ng th

e st

anda

rd h

eigh

t and

wid

th, e

xtra

hin

ges

shal

lbe

pro

vide

d.

4.2

For 1

/F s

ubst

atio

n, d

ecor

ativ

e lo

uvre

s/cl

addi

ng s

hall

beat

tach

ed to

the

subs

tatio

n do

or a

s fa

r as

prac

ticab

le.

For

exce

ptio

nal c

ase

appr

oved

by

HK

Elec

tric

that

the

deco

rativ

elo

uvre

s/cl

addi

ng a

re m

ount

ed o

n th

e ex

tern

al w

all o

f bui

ldin

g,th

e de

velo

per i

s re

spon

sibl

e fo

r arra

ngin

g fa

cilit

ies

and

man

pow

er fo

r clo

sing

/ope

ning

of t

he d

ecor

ativ

e lo

uvre

s/cl

addi

ngfo

r HK

Elec

tric'

s eq

uipm

ent t

rans

porta

tion

wor

k, in

spec

tion

and

mai

nten

ance

wor

k, e

tc. a

s an

d w

hen

requ

ired

by H

K El

ectri

c.

Drg

. No.

GC

S/3/

26C

ON

DIT

ION

S O

N A

CC

EPTA

NC

E O

F A

TTA

CH

ING

EX

TER

NA

L D

ECO

RA

TIV

ELO

UV

RES

/CLA

DD

ING

TO

SU

BST

ATI

ON

DO

OR

OR

AD

DIT

ION

AL

DEC

OR

ATI

VE

DO

OR

IN F

RO

NT

OF

SUB

STA

TIO

N D

OO

R O

F G

RO

UN

D F

LOO

R S

UB

STA

TIO

N (P

753/

14)

3.83

3.84

Notes for Drawing No. GCS/3/26 1. In general the operation of a substation door with decoration cladding or a

decorative door in addition to the standard substation door would occupy much larger area of pavement in front of the substation. Any such decorative features on the substation door or the addition of a decorative door should be avoided as far as practicable from operational point of view. In case any substation door is of such design and / or an additional decorative door in front of the substation door is proposed, HK Electric shall have the discretion on the acceptance of such proposal depending on the actual site situation. The architect / developer shall submit their proposal in the substation design stage for HK Electric’s consideration. This drawing depicts only the general conditions on acceptance of an additional decorative door in front of the substation door of a ground floor substation and / or attaching external decorative cladding to substation door for reference purpose.

2. General requirements for both the substation door with decoration cladding and the additional decorative door in front of the standard substation door of a substation at ground floor

2.1 A canopy above the substation door shall be provided according to HK Electric

drawing.

2.2 A space of not less than 1,000 mm (H) x 600 mm (W) at 1,400 mm centre above pavement level, with proper mounting facilities shall be provided for mounting the substation name plates and warning sign on external surface of the door.

2.3 The proposed additional door or decorative louvres/cladding on the standard

substation door shall not result in any adverse effect on the substation ventilation system and a minimum flow rate as stipulated in the substation layout drawing shall be achieved when the substation ventilation system is operating. A site measurement is required to confirm compliance after the decorative louvres/cladding or the additional decorative door is installed.

2.4 In case there is any defect/malfunction of the substation ventilation system which

may affect the substation temperature, the developer shall be responsible for keeping the additional door fully open (or dismantling the additional door if keeping the additional door open in a prolonged manner is not allowed due to the possible obstruction at site) / detaching the decorative louvres/cladding from the substation door to facilitate the air circulation upon request by HK Electric.

3.85

Notes for Drawing No. GCS/3/26 2.5 A confirmation letter shall be provided from the developer to undertake the

responsibilities for future repair /maintenance of the additional substation door and the proposed decorative louvres/cladding on the substation door in case of damage by HK Electric during initial equipment delivery and future transportation of supply apparatus to and from the substation. The letter shall also confirm their compliance with all the requirements stipulated in this Drawing.

2.6 Substation Door Swing

The substation door shall be able to fully open with 180 degree swing with a clear opening of not less than 2.0 m (W) x 2.6 m (H) after the substation door and the additional decorative door have been fully opened for transportation of HK Electric’s equipment to and from the substation. A 150 degree swing of the substation door while maintaining a clear opening of not less than 2.0 m (W) x 2.6 m (H) will also be acceptable provided the following conditions are met:

i. The substation door and the additional decorative door, when being opened

outwards over any street, must not cause an obstruction to any person or vehicle using the street.

ii. The substation door is facing a street with footpath of clear width of more

than 2.5 m where manual transportation of HK Electric’s equipment to and from the substation is allowed, or a 2-m-wide clearance in the footpath in front of the substation door opening can be maintained when both the substation door and the decorative door are fully opened.

iii. Stoppers shall be designed and provided to prevent the decorative

louvres/cladding from being damaged in the course of movement of the substation door. Stopper(s) shall also be provided for the additional door by the same token.

iv. Latch or similar means shall be designed and provided to secure the

decorative door and the standard substation door at its fully open positions to avoid swinging back of the door(s) in case of strong wind condition.

2.7 The decorative louvres/cladding on the substation door and /or the additional

decorative door shall not obstruct the operations of the lockbar of the standard substation door and shall not endanger the operator when opening and carrying out the locking/unlocking operation of the substation door /additional door.

3.86

Notes for Drawing No. GCS/3/26 3. Other requirements for additional door in front of a standard substation door of a

ground floor substation 3.1 The additional decorative door fitting shall be of suitable size which could allow

smooth operation and shall comply fully with the following requirements: i. At least 4 Nos. of hinges shall be provided at each door leaf. The hinges shall

be so designed that the Door will open in the direction of egress. Life lubricated hinges shall be provided.

ii. For double door, the right hand side leaf shall be opened first when viewed

from outside.

iii. Pull handles of stainless steel shall be provided for single door and for both

leaves of double door.

iv. Equipotential bonding shall be provided for the additional door according to

the latest edition of Code of Practice for the Electricity (Wiring) Regulations published by Hong Kong SAR Government.

3.2 The decorative door and its frame shall not obstruct future maintenance /

replacement of the standard substation door.

3.3 The development owner / management company is not allowed to apply lock of any form on the additional door. In case locking of such additional door is necessary, a stainless steel lock bar shall be provided and be suitable for HK Electric pad lock with shackle diameter of 14 mm, a clear inside width of 20 mm and inside length of 16 mm. The position of lock bar shall be at 1100 mm to 1500 mm above finished floor level. For Double Door, the lock bar shall be on the left hand side leaf when viewed from outside. Vertical bolts shall be provided for the left hand side leaf to secure in position before closing the right hand side leaf.

3.4 In addition to the requirement of providing proper facilities for mounting HK

Electric’s door label / warning sign as described in above item 2.2, the development owner is also required to post a durable sign / label on the additional decorative door to explicitly state their ownership and responsibilities of maintenance / repair of the additional door for easy site identification.

3.87

Notes for Drawing No. GCS/3/26 4. Other requirements for attaching external decorative louvres/cladding to a standard

substation door 4.1 The hinges of the door shall be designed and constructed to withstand the operating

weight of the door with the proposed decorative louvres/cladding plus 50 kg (assuming at centre of door leaf) in order to cater for the weight of accessories which HK Electric may install onto the door and minimum four Nos. of door hinges shall be provided on each leaf of the doors. For door exceeding the standard height and width, extra hinges shall be provided.

4.2 For 1/F substation, decorative louvres/cladding shall be attached to the substation door as far as practicable. For exceptional case approved by HK Electric that the decorative louvres/cladding are mounted on the external wall of building, the developer is responsible for arranging facilities and manpower for closing/opening of the decorative louvres/cladding for HK Electric’s equipment transportation work, inspection and maintenance work, etc. as and when required by HK Electric.

FIG

UR

E (a

) : D

ETAI

LS O

F FI

XIN

G A

RR

ANG

EMEN

T FO

R L

ABEL

MO

UN

TIN

G P

LATE

20

205

50 330 120

800

500

1.5

400

110

8 x

7

HO

LES

(BY

HK

ELEC

TRIC

)

M8

WAS

HER

M8

CAP

NU

T

M8

STU

D W

ELD

ED O

NTO

DO

OR

DO

OR

LEA

F

(N.T

.S.)

M8

HEX

BU

T

Drg

. No.

GC

S/3/

27R

EQU

IREM

ENTS

ON

FIR

E R

ESIS

TIN

G D

OO

R F

OR

SU

BST

AIO

NS

(P33

9/97

/R-7

)

NO

TE:

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.88

3.89

Notes for Drawing No. GCS/3/27 1. Stainless steel referred in this Specification shall mean stainless steel of Grade 316.

2. The Fire Resisting Door (the Door) shall be installed in HK Electric substation only

if it is definitely required FSD of HKSAR Government.

3. The Door shall be type tested to the latest edition of BS 476 for:-

a. A Fire Resistance Period required by FSD; or

b. A Fire Resistance Period of 2 hours,

whichever the Fire Resistance Period is longer. 4. Before substation hand-over, the following documents shall be submitted to the HK

Electric Engineer:- a. A copy of certificate from the manufacturer stating that the Door has complied

with the above tests and all the FSD requirements.

b. A confirmation letter from the developer undertaking the responsibilities for future maintenance of the Door.

5. The Door shall be single swing. The Door shall be of double leaf or single leaf as

specified by HK Electric. For Double Leaf Door, the right hand side leaf shall be opened first when viewed from outside.

6. Unless otherwise specified by HK Electric in the substation layout drawing, clear opening of the Door shall be of:-

a. Height not less than 2600 mm and width not less than 2000 mm for Double

Door.

b. Height not less than 2300 mm and width not less than 920 mm for Single Door.

7. The facing of the Door shall be of stainless steel sheet of thickness not less than

1.5 mm.

3.90

Notes for Drawing No. GCS/3/27

8. Should there be a built-in cylinder lock in the original design of the Door, it shall be

rendered inoperative. A stainless steel lock bar shall be provided and be suitable for HK Electric pad lock with shackle diameter of 14 mm, a clear inside width of 20 mm and inside length of 16 mm. The position of lock bar shall be at 1100 mm to 1500 mm above finished floor level. For Double Door, the lock bar shall be on the right hand side leaf when viewed from outside. Vertical bolts shall be provided for the left hand side leaf to secure in position before closing the right hand side leaf.

9. Automatic door closer, if required by FSD or according to FSD Regulations, shall be

provided for the Door. Should self-closing device be installed on the Door, a substation door security rod as detailed in drawing No. P360/97/R-5 shall be provided.

10. Pull handles of stainless steel shall be provided for Single Door and for both leaves

of Double Door.

11. At least 4 Nos. of hinges each not less than 80 mm long shall be provided at each

door leaf. The hinges shall be so designed such that the Door will open in the direction of egress. Life lubricated hinges shall be provided. The hinges for each leaf of Door must be designed and constructed to withstand the operating weight of the Door plus 50 kgf (assuming at the centre of door leaf) in order to cater for the weight of accessories which HK Electric may install onto the Door.

12. Door stops shall be provided for the closing and the full opening of door leaves.

13. For mounting of HK Electric labels on the Door, a label mounting plate shall be

provided on the external surface of the Door for fixing various labels. The label mounting plate shall be:-

a. of stainless steel sheet not less than 1.5 mm thick with folding edges at the long

side.

b. of dimensions 800 mm high and 500 mm wide at the centre of door leaf at right hand side. Bottom of mounting plate shall be at 1400 mm above ground.

3.91

Notes for Drawing No. GCS/3/27

c. fixed by means of 6 Nos. of studs welded onto the facing of the Door. The fixing washers and nuts shall be provided. The mounting plate shall be 20 mm away from the door surface. All the studs, fixing washers and nuts shall be of stainless steel.

Details of fixing arrangement for label mounting plate are shown in Figure (a). The label mounting plate shall not obstruct the operation of the door lock bar.

14. Equipotential bonding shall be provided for the Door according to the latest edition of Code of Practice for the Electricity (Wiring) Regulations published by Hong Kong SAR Government.

15. The Door shall be covered with thick plastic sheets at the time the substation is

handed over and such plastic sheets shall not be removed until the building construction work is completed, in order to avoid staining of the Door caused by splashing of corrosive liquids used on site.

'A'

'A'

TYPI

CAL P

RECA

ST R

.C. C

OVER

ARR

ANGE

MENT

OF C

ABLE

DRA

WPI

T OR

PRE

FORM

ED T

RENC

H

REM

OVA

BLE

I-BEA

M F

OR

SU

PPO

RTI

NG

THE

PREC

AST

R.C

. C

OVE

R

PREC

AST

R.C

. C

OVE

RR

ECES

S AT

SID

E W

ALL

OF

DR

AWPI

TFO

R S

UPP

OR

TIN

G T

HE

REM

OVA

BLE

I-BEA

M

100

125

5

1010

HAND

LE F

OR P

RECA

ST R

.C. C

OVER

200(

L)x4

0(W

)x5

THIC

KSU

S PL

ATE

M10

SU

S N

UT

10 D

IA. S

US

HAN

DLE

FLU

SH W

ITH

PREC

AST

R.C

. C

OVE

R

FILL

ET W

ELD

ING

(ALL

AR

OU

ND

)

13 D

IA.

PVC

TU

BE

MIN. 900

SECT

ION

'A -

'A'

TYPI

CAL D

ETAI

L OF

PREC

AST

R.C.

COV

ER/ I-

BEAM

FOR

DRA

WPI

T OR

PRE

FORM

ED T

RENC

H

1 : 1

00 F

ALL

H

25 D

IA.

DR

AIN

HO

LE

CAB

LE D

UC

TS

SEE

DET

AIL

'G'

CAB

LE D

UC

TS

REC

ESS

AT S

IDE

WAL

L O

F D

RAW

PIT

FOR

SU

PPO

RTI

NG

TH

E R

EMO

VABL

E I-B

EAM

PREC

AST

R.C

. C

OVE

R

REM

OVA

BLE

I-BEA

M F

OR

SUPP

OR

TIN

GTH

E PR

ECAS

TR

.C.

CO

VER

SUS

= ST

AIN

LESS

STE

ELR

.C.

= R

EIN

FOR

CED

CO

NC

RET

E

( OR ASINDICATED INS/S DRAWING)

MIN. 900( OR AS

INDICATED INS/S DRAWING)

100

MIN

.

DETA

IL 'G

'

NO

T M

OR

E TH

AN 1

5 m

m

NO

T M

OR

E TH

AN 6

mm

HAND

LE F

OR P

RECA

ST R

.C. C

OVER

Drg

. No.

GC

S/3/

28R

EQU

IREM

ENTS

OF

PREC

AST

REI

NFO

RC

ED C

ON

CR

ETE

CO

VER

(P72

2/12

/R-1

)

NO

TE:

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.92

3.93

Notes for Drawing No. GCS/3/28 1. Each piece of R.C. cover shall be provided with lifting eyes and shall not weigh

above 80 kgf.

2. The precast R.C. covers shall be numbered in a sequential order by painting numbers of 50 mm high in white colour on both surfaces of each precast R.C. cover. Drawing showing the layout & numbering shall be displayed in substation.

3. Where the R.C. covers are along the route of transportation of substation equipment,

the R.C. covers shall be capable of withstanding an average loading of 20 kPa. Otherwise the R.C. covers shall withstand 10 kPa.

4. Certificate by a registered structural engineer shall be submitted.

5. If H exceeds 1200 mm, SUS CAT ladder in steps of 250 mm shall be provided at a

height 800 mm from bottom of drawpit or trench.

6. After HK Electric cables have been laid, the drawpit or trench shall be backfilled

with sandbags each not exceeding 25 kgf.

PLA

N

"A

"

"B

""B

"

"A

"

SU

BS

TA

TIO

N

"B

""B

"

MA

IN

D

OO

R F

OR

EQ

UIP

ME

NT

T

RA

NS

PO

RT

AT

IO

N

CE

NT

RE

L

IN

E O

F S

UB

ST

AT

IO

N D

OO

R

FO

R E

QU

IP

ME

NT

T

RA

NS

PO

RT

AT

IO

N

TO

TA

L 4

N

os. A

NC

HO

RIN

G E

YE

( ) ( 1

50

kg

f )

FO

R S

AF

ET

Y B

EL

T U

SE

A

T 1

50

0 m

m A

BO

VE

F

LO

OR

.

WA

RN

IN

G L

AB

EL

S

TA

TIN

G

SH

OU

LD

B

E A

FF

IX

ED

B

ES

ID

E T

HE

A

NC

HO

RIN

G E

YE

( ).

TH

E L

AB

EL

S

HO

UL

D B

E R

ED

IN

W

HIT

E B

AC

KG

RO

UN

D.

SIZ

E O

F S

IG

NA

GE

S

HO

UL

D B

E 5

0 m

m x 8

0 m

m.

" A

NC

HO

R E

YE

B

OL

T F

OR

S

AF

ET

Y B

EL

T

"

GU

AR

D C

HA

IN

( S

TA

IN

LE

SS

S

TE

EL

A

PP

RO

X. 3

kg

p

er m

etre

)

WIT

H S

PR

IN

G H

OO

KS

A

T A

PP

RO

X. 1

20

0 m

m A

BO

VE

F

LO

OR

( T

O B

E U

SE

D A

FT

ER

T

HE

B

AR

RIE

R IS

O

PE

NE

D )

FO

R D

OO

R O

PE

RA

TIO

N, A

R

IG

ID

P

IP

E O

F N

ON

-M

ET

AL

LIC

( S

UC

H A

S P

OL

YM

ER

) M

AT

ER

IA

L O

F 1

60

0 m

m L

ON

G,

DIA

ME

TE

R A

BO

UT

6

0 m

m, W

EIG

HT

N

OT

O

VE

R 1

0 kg

f W

IT

H

A S

AF

ET

Y R

OP

E A

TT

AC

HE

D T

O T

HE

E

ND

A

ND

W

AL

L.

AN

TI-S

KID

T

RE

AT

ME

NT

T

O B

E P

RO

VID

ED

A

T T

HE

E

ND

OF

P

IP

E A

ND

A

H

AN

DL

E T

O B

E P

RO

VID

ED

A

T 4

00

m

m

FR

OM

E

ND

O

F P

IP

E. W

AL

L B

RA

CK

ET

S S

HA

LL

B

E P

RO

VID

ED

FO

R V

ER

TIC

AL

S

TO

RA

GE

O

F P

IP

E W

HE

N N

OT

IN

U

SE

.

J

J

CE

NT

RE

L

IN

E O

F A

NC

HO

RIN

G E

YE

AN

CH

OR

IN

G E

YE

( )

I

OF

"B

"-"B

"

AL

TE

RN

AT

IV

E P

OS

IT

IO

N

SU

BS

TA

TIO

N D

EP

TH

T

O B

E 4

00

0 m

m M

IN

.

MA

X. 2

00

MA

X. 2

00

MA

X. 5

00

m

m

Drg

. No.

GC

S/3/

29A

NC

HO

RIN

G E

YE

AN

D F

AC

ILIT

IES

FOR

FIR

ST L

EVEL

SU

BST

ATI

ON

(P34

2/97

/R-3

) SH

EET

1 O

F 2

NO

TE

:

AL

L D

IM

EN

SIO

NS

A

RE

IN

m

m

3.94

COVE

R

500

mm

300 mm

LOCK

PLA

TE W

ITH

14-m

m-D

IA.

HOLE

HAND

LE O

N BO

TH S

IDES

MAD

E O

F 8-

mm

-DIA

. RO

D W

ELDE

D TO

THE

CO

VER

ANCH

ORI

NG E

YE (

)

DET

AILS

OF

ANC

HO

RIN

G E

YE (

)

I

SUBS

TATI

ON

WAL

L

MAX

.

CONC

RETE

BAS

E

SUBS

TATI

ON

FLO

OR

WAR

NING

LAB

EL

HORI

ZONT

AL P

ULLI

NG F

ORC

E

150 mmTO

Drg

. No.

GC

S/3/

29A

NC

HO

RIN

G E

YE

AN

D F

AC

ILIT

IES

FOR

FIR

ST L

EVEL

SU

BST

ATI

ON

(P34

2/97

/R-3

) SH

EET

2 O

F 2

NO

TE:

ALL

DIM

ENSI

ON

S AR

E IN

mm

3.95

3.96

Notes for Drawing No. GCS/3/29 1. The anchoring eye (I) will be used for transportation of equipment to and from the

substation. A horizontal pulling force in direction along the centre line “A” – “A” will be applied to the anchoring eye (I). The anchoring eye (I) shall be suitable for a “SAFE WORKING LOAD” of 1000 kgf for such application, however the “TESTING LOAD” shall be 2000 kgf.

2. A certificate from a registered professional engineer in accordance with the factories

and industrial undertakings ordinance shall be submitted to HK Electric certifying the above “TESTING LOAD” of anchoring eye (I) and the 150-kgf working load of anchoring eye (J).

3. All anchoring eyes shall be made of stainless steel, hot dip galvanised steel or steel

with suitable anti-corrosion treatment. A concrete base shall be provided for the anchoring eye (I) to minimize corrosion to the eye due to lodgement of water on floor.

4. A cover with handle (covering the front, the top and the 2 sides) made of stainless

steel or hot dip galvanised steel shall be provided to prevent the improper use of the anchoring eye (I). An engraved warning label stating:

“S.W.L. 1000 kgf DO NOT USE THE ANCHORING EYE BEFORE PROPER

TEST 未經測試不可使用”

shall be bolted on the front of cover. The lettering shall be approximately 15 mm high. A locking plate shall be provided on wall to lock the cover in position. The locking plate shall be suitable for padlocks with an 8 mm diameter shackle and a clear inside width of 20 mm and inside length of 16 mm.

Drg

. No.

GC

S/3/

30TY

PIC

AL

LAY

OU

T FO

R S

ING

LE T

RA

NSF

OR

MER

FIR

ST L

EVEL

SU

BST

ATI

ON

WIT

H H

V &

LV

CO

MPA

RTM

ENTS

(P38

1/98

/R-6

) SH

EET

1 O

F 6

NO

TE :

ALL

DIM

ENSI

ON

S A

RE

IN m

m

3.97

Drg

. No.

GC

S/3/

30TY

PIC

AL

LAY

OU

T FO

R S

ING

LE T

RA

NSF

OR

MER

FIR

ST L

EVEL

SU

BST

ATI

ON

WIT

H H

V &

LV

CO

MPA

RTM

ENTS

(P38

1/98

/R-6

) SH

EET

2 O

F 6

NO

TE :

ALL

DIM

ENSI

ON

S A

RE

IN m

m

3.98

Drg

. No.

GC

S/3/

30TY

PIC

AL

LAY

OU

T FO

R S

ING

LE T

RA

NSF

OR

MER

FIR

ST L

EVEL

SU

BST

ATI

ON

WIT

H H

V &

LV

CO

MPA

RTM

ENTS

(P38

1/98

/R-6

) SH

EET

3 O

F 6

NO

TE :

ALL

DIM

ENSI

ON

S A

RE

IN m

m

3.99

DRG. NO. GCS/3/30TYPICAL LAYOUT FOR SINGLE TRANSFORMER

FIRST LEVEL SUBSTATION WITH HV & LVCOMPARTMENTS (P381/98/R-6) SHEET 4 OF 6

NOTE :ALL DIMENSIONS ARE IN mm

3.100

Drg

. No.

GC

S/3/

30TY

PIC

AL

LAY

OU

T FO

R S

ING

LE T

RA

NSF

OR

MER

FIR

ST L

EVEL

SU

BST

ATI

ON

WIT

H H

V &

LV

CO

MPA

RTM

ENTS

(P38

1/98

/R-6

) SH

EET

5 O

F 6

NO

TE :

ALL

DIM

ENSI

ON

S A

RE

IN m

m

3.101

Drg

. No.

GC

S/3/

30TY

PIC

AL

LAY

OU

T FO

R S

ING

LE T

RA

NSF

OR

MER

FIR

ST L

EVEL

SU

BST

ATI

ON

WIT

H H

V &

LV

CO

MPA

RTM

ENTS

(P38

1/98

/R-6

) SH

EET

6 O

F 6

NO

TE :

ALL

DIM

ENSI

ON

S A

RE

IN m

m

3.102

3.103

Notes for Drawing No. GCS/3/30 1. Level of G/F is assumed at + 0.0, levels of working platforms are with reference to

the high level of G/F.

2. Direct vehicular access shall be available to the front of substation door at a horizontal distance not exceeding 4 m. Direct vehicular access shall mean accessibility of a standard 30 ton fire appliance of FSD of HKSAR Government.

3. The substation floor level must not be of 7 m higher than the pavement level measured at centre line of substation door.

4. The gradient of access road to substation (when measured along +/-10 m

horizontally from centre line of door ‘A’) must not be greater than 1:12.

5. There shall not be any protruded objects obstructing transportation of equipment to /

from substation when measured along +/-6 m horizontally from the centre line of door ‘A’ and vertically from 3m of top of door ‘A’ down to pavement level.

6. The separation of the two cable entry points shall be not less than 3500 mm.

7. The developer / landlord shall provide haulage lug(s) inside the cable riser duct as

and required by HK Electric for cable laying woks. The statutory loading tests of the haulage lug(s), when required, shall be arranged by the developer / landlord. These haulage lug(s) shall be of removable type such that it (they) could be removed after completion of cable laying.

DO

OR

W

IT

H

GA

SK

ET

A

LL

A

RO

UN

D

12

0 x 1

50

G

LA

SS

W

IN

DO

W

FO

R M

ET

ER

R

EA

DIN

G

150

12

0

FR

ON

T V

IE

W

DIR

EC

TIO

N

TO

S

EC

UR

E

HA

ND

LE

BO

TT

OM

V

IE

W

38

0

2x 5

2 O

PE

NIN

G

WIT

H R

UB

BE

R B

UN

G

FO

R H

K E

LE

CT

RIC

UN

DE

RG

RO

UN

D C

AB

LE

S

HA

ND

LE

160

105

HIN

GE

215 220

EA

RT

HIN

G T

ER

MIN

AL

FO

R 2

x 3

5-m

m

CO

ND

UC

TO

R

2

IN

NE

R F

RO

NT

V

IE

W

MO

UN

TIN

G B

RA

CK

ET

38

0 W

ID

E x 4

35

H

IG

H

20

-m

m-T

HIC

K

WO

OD

EN

B

OA

RD

SP

AC

E F

OR

SE

RV

IC

E

CU

TO

UT

SP

AC

E F

OR

CU

ST

OM

ER

'S

MA

IN

S

WIT

CH

SP

AC

E F

OR

ME

TE

R

DO

OR

T

O

SW

IN

G 180

MO

UN

TIN

G B

RA

CK

ET

( C

UB

IC

LE

D

OO

R O

MIT

TE

D F

OR

C

LA

RIT

Y )

2 x O

PE

NIN

G

WIT

H R

UB

BE

R B

UN

G

FO

R O

UT

GO

IN

G W

IR

IN

GS

FR

OM

M

ET

ER

NO

TE

:1.

2.

CU

ST

OM

ER

M

AY

S

LIG

HT

LY

E

NLA

RG

E T

HE

E

NC

LO

SU

RE

S

IZ

E

TO

S

UIT

T

HE

D

IF

FE

RE

NT

T

YP

E O

F C

US

TO

ME

R'S

M

AIN

S

WIT

CH

.

DO

UB

LE

-LO

CK

A

RR

AN

GE

ME

NT

S

HO

ULD

B

E P

RO

VID

ED

IF

T

HE

EN

CLO

SU

RE

IS

LO

CK

ED

-U

P B

Y C

US

TO

ME

R.

460

460

55

80

60

M4

B

OL

T A

ND

N

UT

( T

OT

AL

1

2 N

os. )

IN

SE

RT

P

LA

TE

1

IN

SE

RT

P

LA

TE

2

( T

OT

AL

2

N

os. )

80

IN

SE

RT

P

LA

TE

1

IN

SE

RT

P

LA

TE

2

38

0

52

60

20

0

50

15

03

03

0

70

40

55105

c

L

25

c

L

CO

PP

ER

E

AR

TH

IN

G S

TU

D

OP

EN

IN

G A

ND

B

OT

TO

M

IN

SE

RT

P

LA

TE

S 1

&

2

c

L

19

0

19

0

38

0

CO

PP

ER

EA

RT

HIN

G S

TU

D

EA

RT

H B

ON

DIN

G

FO

R D

OO

R

45

5050

80

60

19

0

19

0

3.

ALL D

IM

EN

SIO

NS

IN

m

m.

Drg

. No.

GC

S/3/

31M

ILD

STE

EL W

EATH

ER-P

RO

OF

ENC

LOSU

RE

FOR

SIN

GLE

PH

ASE

SU

PPLY

(P65

5/07

/R-1

)

3.104

NO

TE:

ALL

DIM

ENSI

ON

S AR

E IN

mm

.

LOC

ATIO

N O

FEN

CLO

SUR

EH

OAR

DIN

G O

F ST

ALL

AFTE

R C

LOSE

OF

BUSI

NES

SO

F ST

ALL

HK

ELEC

TRIC

'SC

ABLE

FOO

TPAT

H O

RPU

BLIC

AC

CES

S

THIS

PIE

CE

OF

SUPP

OR

TIN

G H

OAR

DIN

GTO

BE

MAI

NTA

INED

AT

ALL

TIM

ES

DO

OR

OF

ENC

LOSU

RE

(FR

ON

T)

DO

OR

OF

ENC

LOSU

RE

HO

ARD

ING

OF

STAL

LAF

TER

CLO

SE O

F BU

SIN

ESS

OF

STAL

L

THIS

PIE

CE

OF

SUPP

OR

TIN

GH

OAR

DIN

G T

O B

E M

AIN

TAIN

EDAT

ALL

TIM

ES

LOC

ATIO

N O

FEN

CLO

SUR

E

DO

OR

OF

ENC

LOSU

RE

FOO

TPAT

H O

RPU

BLIC

AC

CES

S

AREA

OF

STAL

LAP

PRO

VED

BY

GO

VER

NM

ENT

AUTH

OR

ITY

THIS

PIE

CE

OF

SUPP

OR

TIN

G H

OAR

DIN

GTO

BE

MAI

NTA

INED

AT

ALL

TIM

ES

LOC

ATIO

N O

F EN

CLO

SUR

E

DO

OR

OF

ENC

LOSU

RE

(FR

ON

T)

SEC

TIO

N '

X' -

'X'

( O

PTIO

N 1

)

AREA

OF

STAL

LAP

PRO

VED

BY

GO

VER

NM

ENT

AUTH

OR

ITY

'X''X' 'X''X'

300

mm

LOC

ATIO

N P

LAN

FO

R E

NC

LOSU

RE

( O

PTIO

N 2

)(C

UST

OM

ER IS

REQ

UIR

ED T

O E

NSU

RE

THAT

THE

ENC

LOSU

RE

WIL

L N

OT

AFFE

CT

PED

ESTR

IAN

S,SH

OPS

NEA

RBY

AN

D O

THER

CO

NC

ERN

ED P

ARTI

ES.)

THIS

PIE

CE

OF

SUPP

OR

TIN

G H

OAR

DIN

GTO

BE

MAI

NTA

INED

AT

ALL

TIM

ES

SEC

TIO

N '

X' -

'X'

( O

PTIO

N 2

)

THE

ENC

LOSU

RE

MU

ST A

LLO

W F

OR

MET

ER R

EAD

ING

BY

HK

ELEC

TRIC

AFT

ERC

LOSE

OF

BUSI

NES

S O

F ST

ALL

LOC

ATIO

N O

F EN

CLO

SUR

E M

UST

BE

ENTI

REL

Y W

ITH

IN T

HE

APPR

OVE

D A

REA

OR

APPR

OVE

D B

Y G

OVE

RN

MEN

T AU

THO

RIT

Y

LOC

ATIO

N P

LAN

FO

R E

NC

LOSU

RE

( OPT

ION

1 )

THE

ENC

LOSU

RE

MU

ST A

LLO

W F

OR

MET

ER R

EAD

ING

BY

HK

ELEC

TRIC

AFT

ERC

LOSE

OF

BUSI

NES

S O

F ST

ALL

G.I.

CAB

LE C

LEAT

S O

F 36

mm

DIA

MET

ER T

O B

E PR

OVI

DED

AN

DFI

XED

AT

HO

ARD

ING

OF

STAL

LBY

APP

LIC

ANT

BETW

EEN

1200

mm

~ 1

920

mm BE

TWEE

N12

00 m

m ~

192

0 m

m

BETW

EEN

600

mm

~ 1

100

mm

EAR

TH B

ON

DIN

G F

OR

G.I.

DU

CT

( IF

G.I.

DU

CT

IS P

RO

VID

ED )

POSI

TIO

N O

F G

.I./U

PVC

DU

CT

IF S

TALL

IS A

T C

ARR

IAG

EWAY

NEA

R R

OAD

KER

B

SUIT

ABLE

BU

SH /

GLA

ND

SH

ALL

BEPR

OVI

DED

AT

BOTH

EN

DS

OF

G.I.

DU

CT

( IF

G.I.

DU

CT

IS P

RO

VID

ED )

TO A

VOID

CU

TTIN

G H

K EL

ECTR

IC'S

CAB

LE

ALTE

RN

ATIV

E PO

SITI

ON

OF

G.I.

/UPV

C D

UC

T

100-

mm

-DIA

. G.I.

OR

UPV

C D

UC

T W

ITH

YELL

OW

/ BL

ACK

FLU

OR

ESC

ENT

MAR

KIN

G /

TAPE

BY

APPL

ICAN

T

Drg

. No.

GC

S/3/

32M

ILD

STE

EL W

EATH

ER-P

RO

OF

ENC

LOSU

RE

FOR

SIN

GLE

PH

ASE

SU

PPLY

TO

HA

WK

ER S

TALL

(P71

7/12

/R-3

) SH

EET

1 O

F 2

3.105

CU

STO

MER

'S W

EATH

ER-P

RO

OF

ENC

LOSU

RE

FOR

INST

ALLI

NG

CU

STO

MER

'S M

AIN

SW

ITC

H

HAN

DLE

DO

OR

WIT

H G

ASKE

TAL

L AR

OU

ND

CO

PPER

EAR

THIN

G S

TUD

DIR

ECTI

ON

TO S

ECU

RE

HIN

GE

MO

UN

TIN

G B

RAC

KET

CO

PPER

EAR

THIN

G S

TUD

SPAC

E FO

RSE

RVI

CE

CU

TOU

T

SPAC

E FO

RM

ETER

EAR

TH B

ON

DIN

GFO

R D

OO

RH

AND

LE

CU

STO

MER

'S W

EATH

ER-P

RO

OF

ENC

LOSU

RE

FOR

INST

ALLI

NG

CU

STO

MER

'S M

AIN

SW

ITC

H

140

x 18

0 G

LASS

WIN

DO

WFO

R M

ETER

REA

DIN

G

MO

UN

TIN

G B

RAC

KET

CO

PPER

EAR

THIN

G S

TUD

HIN

GE

EAR

TH B

ON

DIN

G F

OR

DO

OR

MO

UN

TIN

G B

RAC

KET

CO

PPER

EAR

THIN

G S

TUD

SPAC

E FO

RSE

RVI

CE

CU

TOU

T

SPAC

E FO

RM

ETER

FRO

NT

VIE

W

( OPT

ION

1)

( OPT

ION

1)

INN

ER F

RO

NT

VIE

W

BOTT

OM

VIE

W

FRO

NT

VIE

W

( OPT

ION

2)

INN

ER F

RO

NT

VIE

W

( OPT

ION

2)

INSE

RT

PLAT

E 1

INSE

RT

PLAT

E 2

8025

3030

DO

OR

WIT

H G

ASKE

TAL

L AR

OU

ND

215

105

55

380

55

460

105

460

190

380

380

55

55

5555

330

190

380

85

55

150

200

60

50

Ø52

FLO

OR

140

x 18

0 G

LASS

WIN

DO

WFO

R M

ETER

REA

DIN

G

DO

OR

TO

SWIN

G 1

80°

BETW

EEN

120

0 m

m ~

192

0 m

m

FLO

OR

2 x

Ø52

OPE

NIN

G W

ITH

RU

BBER

BU

NG

FO

R H

ECU

ND

ERG

RO

UN

D C

ABLE

S

BETW

EEN

120

0 m

m ~

192

0 m

m

MO

UN

TIN

G B

RAC

KET

OPE

NIN

G A

ND

BO

TTO

MIN

SER

T PL

ATES

1 &

2

380

WID

E x

435

HIG

H20

-mm

-TH

ICK

WO

OD

EN B

OAR

D

* SP

ACE

FOR

CU

STO

MER

'SM

AIN

SW

ITC

HM

4 BO

LT A

ND

NU

T( T

OTA

L 12

Nos

. )

CU

BIC

LE D

OO

R O

MIT

TED

FO

R C

LAR

ITY

OPE

NIN

G A

ND

BO

TTO

MIN

SER

T PL

ATES

1 &

2EAR

THIN

G T

ERM

INAL

FO

R2x

35-

mm

² C

ON

DU

CTO

R( F

OR

USE

BY

HK

ELEC

TRIC

)

CU

BIC

LE D

OO

R O

MIT

TED

FO

R C

LAR

ITY

INSE

RT

PLAT

E 1

G.I.

CO

ND

UIT

FO

R IN

STAL

LIN

GC

UST

OM

ER'S

MAI

N W

IRES

G.I.

CO

ND

UIT

FO

R IN

STAL

LIN

GC

UST

OM

ER'S

MAI

N W

IRES

EAR

THIN

G T

ERM

INAL

FO

R2x

35-

mm

² C

ON

DU

CTO

R( F

OR

USE

BY

HK

ELEC

TRIC

)

60

300

125

200

280

125

20

LETT

ERS

OF

10 m

m H

IGH

IN B

LAC

KC

HIN

ESE

CH

ARAC

TER

S O

F 15

mm

HIG

H IN

BLA

CK

LETT

ERS

OF

10 m

m H

IGH

IN B

LAC

KC

HIN

ESE

CH

ARAC

TER

S O

F 15

mm

HIG

H IN

BLA

CK

140

25

180 65

HAN

DLE

25

140

180 65

DIR

ECTI

ON

TO

SEC

UR

E

380

175

INSE

RT

PLAT

E 2

( TO

TAL

2 N

os. )

2 x

OPE

NIN

G W

ITH

RU

BBER

BU

NG

FOR

OU

TGO

ING

WIR

ING

S FR

OM

MET

ER

OW

NER

SHIP

OF

THIS

EN

CLO

SUR

EBE

LON

GS

TO T

HE

USE

RS,

STA

LL: :

OW

NER

SHIP

OF

THIS

ENC

LOSU

RE

BELO

NG

S TO

THE

USE

RS,

STAL

L: :

380

WID

E x

300

HIG

H20

-mm

-TH

ICK

WO

OD

ENBO

ARD

MAD

E O

F H

ARD

WO

OD

WIT

H V

ARN

ISH

TREA

TMEN

T

220

190

190

8060

5065

NO

TE :

1.TH

E EN

CLO

SUR

E IS

TO

BE

SUPP

LIED

AN

D IN

STAL

LED

BY

CU

STO

MER

AN

D O

WN

ED B

Y C

UST

OM

ER.

CU

STO

MER

ISR

ESPO

NSI

BLE

FOR

TH

E M

AIN

TEN

ANC

E O

F TH

E EN

CLO

SUR

E.

2. *

CU

STO

MER

MAY

SLI

GH

TLY

ENLA

RG

E TH

E EN

CLO

SUR

E SI

ZETO

SU

IT T

HE

DIF

FER

ENT

TYPE

OF

CU

STO

MER

'S M

AIN

SW

ITC

H.

3.

DO

UBL

E-LO

CK

ARR

ANG

EMEN

T SH

OU

LD B

E PR

OVI

DED

IF T

HE

EN

CLO

SUR

E IS

LO

CKE

D-U

P BY

CU

STO

MER

. TH

E D

IAM

ETER

OF

LO

CKI

NG

HO

LE S

HAL

L N

OT

BE L

ESS

THAN

8 m

m.

4.

EAR

THIN

G O

F TH

E EN

CLO

SUR

E TO

BE

BY A

PPLI

CAN

T.

5.

LEN

GTH

OF

CU

STO

MER

'S M

AIN

WIR

ES C

ON

NEC

TIN

G

H

K EL

ECTR

IC'S

CU

TOU

T AN

D C

UST

OM

ER'S

MAI

N S

WIT

CH

SH

ALL

NO

T EX

CEE

D 3

m.

6.

SEP

ARAT

E D

ESIG

N/A

RR

ANG

EMEN

T O

F W

EATH

ER -

PRO

OF

EN

CLO

SUR

E O

R F

ACIL

ITIE

S PR

OPO

SED

BY

CU

STO

MER

SH

OU

LD B

E SU

BMIT

TED

TO

HK

ELEC

TRIC

FO

R A

PPR

OVA

L.

7.

ALL

DIM

ENSI

ON

S IN

mm

.

Drg

. No.

GC

S/3/

32M

ILD

STE

EL W

EATH

ER-P

RO

OF

ENC

LOSU

RE

FOR

SIN

GLE

PH

ASE

SU

PPLY

TO H

AW

KER

STA

LL (P

717/

12/R

-3) S

HEE

T 2

OF

2

3.106