Chapter 13

61
Chapter 13 MRP: Material Requirement Planning ERP: Enterprise Resource Planning

description

Chapter 13. MRP: Material Requirement Planning ERP: Enterprise Resource Planning. MRP. Material requirements planning Computer-based Information System for Ordering and Scheduling of Dependent Demand Inventories. Independent and Dependent Demand. - PowerPoint PPT Presentation

Transcript of Chapter 13

Page 1: Chapter 13

Chapter 13

MRP: Material Requirement Planning

ERP: Enterprise Resource Planning

Page 2: Chapter 13

Material requirements planning Computer-based Information System for Ordering and Scheduling of Dependent Demand Inventories

MRP

Page 3: Chapter 13

A

B(4) C(2)

D(2) E(1) D(3) F(2)

Independent Demand

Dependent Demand

Independent and Dependent Demand

Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods.

Page 4: Chapter 13

MRP Inputs MRP Processing MRP Outputs

Masterschedule

Bill ofmaterials

Inventoryrecords

MRP computerprograms

Changes

Order releasesPlanned-orderschedules

Exception reports

Planning reportsPerformance-controlreports

Inventorytransaction

Primaryreports

Secondaryreports

Information Flow, Processes, Data Bases

Page 5: Chapter 13

Inputs to MRP

(1) Master schedule: Identifying (a) which end items are to be produced, (b) in what quantities, and (c) when these are needed.

(2) Bill of Material : a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.

(3) Inventories

Page 6: Chapter 13

Bill-of-MaterialsProduct structure tree: Visual depiction of the

requirements in a bill of materials, where all components are listed by levels.

Product Structure Tree

Lead Times

Page 7: Chapter 13

Product Structure Tree

Page 8: Chapter 13

Product Structure Tree

Chair

Seat

Legs (2) Crossbar

SideRails (2)

Crossbar

BackSupports (3)

Front LegAssembly

BackAssembly

Level 0

1

2

3

Page 9: Chapter 13

Product Structure Tree

Chair

Seat

Legs (2) Crossbar

SideRails (2)

Crossbar

BackSupports (3)

Front LegAssembly

BackAssembly

Level 0

1

2

3

Page 10: Chapter 13

Example

A

D (3) E E (2) F (2)

B (2) C

Level 0

1

2

3 E (4)

Determine the quantities of B, C, D, E, and F to produce one unit of A

Page 11: Chapter 13

Extend Level 1

A

D (3*2) E(2) E (2) F (2)

B(2) C

Level 0

1

2

3 E (4)

Page 12: Chapter 13

Extend Level 2

A

D (3*2) E(2) E (2) F (2)

B(2) C

Level 0

1

2

3E (4*3*2)

Page 13: Chapter 13

Compute the Quantities

A

D (6) E(2) E (2) F (2)

B(2) C

Level 0

1

2

3 E (24)

We needB=2C=1D=6E=28F=2

Page 14: Chapter 13

ExampleInventory B=4C=10D=8E=60F=0

Determine the quantities of these components that we need to order or assemble to satisfy demand of 10A

A(10)

D (3) E E (2) F (2)

B (2) C

Level 0

1

2

3 E (4)

Page 15: Chapter 13

Extend Level 0

A(10)

D (3) E E (2) F (2)

B (20) C (10)

Level 0

1

2

3 E (4)Inventory B=4C=10

Page 16: Chapter 13

Level 1 Computations

A(10)

D (3) E E (2) F (2)

B (20- 4=16) C (10-10=0)

Level 0

1

2

3 E (4)

Page 17: Chapter 13

Extend Level 1

A(10)

B (16) C (0)

Level 0

1

2

3

Page 18: Chapter 13

Extend Level 1

A(10)

D (3*16) E(1*16) E (2*0) F (2*0)

B (16) C (0)

Level 0

1

2

3 E (4)

Page 19: Chapter 13

Extend Level 1

A(10)

D (48) E(16) E (0) F (0)

B (16) C (0)

Level 0

1

2

3 E (4)Inventory D=8E=60F=0

Page 20: Chapter 13

Level 2 Computations

A(10)

D (48-8=40) E(16) E (0) F (0)

B (16) C (0)

Level 0

1

2

3 E (4)

Page 21: Chapter 13

Level 2 Computations

A(10)

D (40) E(16) E (0) F (0)

B (16) C (0)

Level 0

1

2

3 E (4)

Page 22: Chapter 13

Extend Level 2

A(10)

D (40) E(16) E (0) F (0)

B (16) C (0)

Level 0

1

2

3E (4*40)

Page 23: Chapter 13

Extend Level 2

A(10)

D (40) E(16) E (0) F (0)

B (16) C (0)

Level 0

1

2

3E (160)

Page 24: Chapter 13

Extend Level 2

A(10)

D (40) E(16) E (0) F (0)

B (16) C (0)

Level 0

1

2

3E (160)

Inventory E=60Requirement E = 160+16-60=116

E=60F=0

Page 25: Chapter 13

Extend Level 2

A(10)

D (40) E(16) E (0) F (0)

B (16) C (0)

Level 0

1

2

3E (100)

Page 26: Chapter 13

Assembly Time Chart

1 2 3 4 5 6 7 8 9 10 11

Procurement ofraw material D

Procurement ofraw material F

Procurement ofpart C

Procurement ofpart H

Procurement ofraw material I

Fabricationof part G

Fabricationof part E

Subassembly A

Subassembly B

Final assemblyand inspection

Page 27: Chapter 13

Shutter, 1 Frame (LT=2W), and 4 Wood Section (LT=1W)

1 2 3

Frame (2, 2)

Wood Sections (4,1)

ShutterAssembly (1)

Page 28: Chapter 13

Week BegInv

1 2 3 4 5 6 7 8

Quantity 100 150

ShutterLT = 1W

Gross Requirement

Scheduled Receipts

Projected on Hand

Net Requirement

Planned Order Receipts

Planned Order Releases

100 150

100 150

100 150

100 150

Master Schedule; Lot for Lot Ordering

Shutter has two frames and four wood sections

Page 29: Chapter 13

FrameLT = 2W

Gross Requirement

Scheduled Receipts

Projected on Hand

Net Requirement

Planned Order Receipts

Planned Order Releases

200 300

200 300

200 300

200 300

ShutterLT = 1W

Gross Requirement 100 150

Scheduled Receipts

Projected on Hand

Net Requirement 100 150

Planned Order Receipts 100 150

Planned Order Releases 100 150

Frame; 2 per unit, LT=2 W

Page 30: Chapter 13

Wood SectionLT = 1W

Gross Requirement

Scheduled Receipts

Projected on Hand

Net Requirement

Planned Order Receipts

Planned Order Releases

400 600

70

600

330 600

330 600

ShutterLT = 1W

Gross Requirement 100 150

Scheduled Receipts

Projected on Hand

Net Requirement 100 150

Planned Order Receipts 100 150

Planned Order Releases 100 150

70 70 70

330

Wood Section; 4 per unit, LT=1 W

Page 31: Chapter 13

FrameLT = 2WEOQ 320

Gross Requirement 200 300

Scheduled Receipts

Projected on Hand

Net Requirement 200

Planned Order Receipts

Planned Order Releases 320

180

320 320

ShutterLT = 1W

Gross Requirement 100 150

Scheduled Receipts

Projected on Hand

Net Requirement 100 150

Planned Order Receipts 100 150

Planned Order Releases 100 150

Master Schedule; Lot Size Ordering; EOQ 320, 70

120 120 120 120 140

320

Page 32: Chapter 13

Wood SectionLT = 1WEOQ 70

Gross Requirement 400 600

Scheduled Receipts 70

Projected on Hand 70 70 70

Net Requirement 330

Planned Order Receipts

Planned Order Releases580

350 630

350 630

ShutterLT = 1W

Gross Requirement 100 150

Scheduled Receipts

Projected on Hand

Net Requirement 100 150

Planned Order Receipts 100 150

Planned Order Releases 100 150

20 20 20

Lot Size Ordering: EOQ 70

20 50

Page 33: Chapter 13

Practice; Example (pp 606, P2), Units Required, Lead Times

Item End B C D E F G HLT (WK) 1 2 3 3 1 2 1 2InvOnHand 0 10 10 25 12 30 5 0For 20 units of the end item, how many additional units of each item is required

A

E (2) F(3) G (2) E (2)

B (2) D(3)

Level 0

1

2

C

E (2) H (4)

Page 34: Chapter 13

Units Required

A(20)

E (2) F(3) G (2) E (2)

B (2) D(3)

Level 0

1

2

C(1)

E (2) H (4)

Item End B C D E F G HInvOnHand 0 10 10 25 12 30 5 0

Page 35: Chapter 13

A(20)

E (2) F(3) G (2) E (2)

B (40) D(60)

Level 0

1

2

C(20)

E (2) H (4)

Item End B C D E F G HInvOnHand 0 10 10 25 12 30 5 0

Units Required

Page 36: Chapter 13

A(20)

E (2) F(3) G (2) E (2)

B (40-10) D(60-25)

Level 0

1

2

C(20-10)

E (2) H (4)

Units Required

Page 37: Chapter 13

A(20)

E (2) F(3) G (2) E (2)

B (30) D(35)

Level 0

1

2

C(10)

E (2) H (4)

Units Required

Page 38: Chapter 13

A(10)

E (2*30) F(3*30) G (2*10) E (2*35)

B (30) D(35)

Level 0

1

2

C(10)

E (2*10) H (4*35)

Units Required

Page 39: Chapter 13

A(10)

E (60) F(90) G (20) E (70)

B (30) D(35)

Level 0

1

2

C(10)

E (20) H (140)

Item E F G HInvOnHand 12 30 5 0

Units Required

Page 40: Chapter 13

A(10)

E (60-12) F(90-30) G (20-5) E (70)

B (30) D(35)

Level 0

1

2

C(10)

E (20) H (140)

Units Required

Page 41: Chapter 13

A(10)

E (48) F(60) G (15) E (70)

B (30) D(35)

Level 0

1

2

C(10)

E (20) H (140)

Item End B C D E F G HRequired 20 30 10 35 138 60 15 140

Units Required

Page 42: Chapter 13

Example (pp 673, P2); Lead Times

A(1)

Item End B C D E F G HLT (WK) 1 2 3 3 1 2 1 2Required 20 30 10 35 138 60 15 140

Page 43: Chapter 13

Lead Times

A(1)

B DC

Item B C D E F G HLT (WK) 2 3 3 1 2 1 2Required 30 10 35 138 60 15 140

Page 44: Chapter 13

Lead Times

A(1)

B (2) D(3)C(3)

Page 45: Chapter 13

Lead Times

A(1)

E F

G E

B (2) D(3)C(3)

E H

Item E F G HLT (WK) 1 2 1 2Required 138 60 15 140

Page 46: Chapter 13

Lead Times

A(1)

E (1) F(2)

G (1) E (1)

B (2) D(3)C(3)

E (1)H (2)

Page 47: Chapter 13

Lead Times

A(1)

E (1) F(2)

G (1) E (1)

B (2) D(3)C(3)

E (1) H (2)

Page 48: Chapter 13

Week BegInv

1 2 3 4 5

Quantity 120

Product XLT = 1W

Gross Requirement

Scheduled Receipts

Projected on Hand

Net Requirement

Planned Order Receipts

Planned Order Releases

120

120

120

120

Master Schedule; Lot for Lot Ordering

Part X (LT=1) is formed by three Part A (LT=1) Part A is formed by two Part B (LT=2)

Page 49: Chapter 13

Part A (3)LT = 1W

Gross Requirement

Scheduled Receipts

Projected on Hand

Net Requirement

Planned Order Receipts

Planned Order Releases

360

60

60 60 60

Product XLT = 1W

Gross Requirement 120

Scheduled Receipts

Projected on Hand

Net Requirement 120

Planned Order Receipts 120

Planned Order Releases 120

Part A; 3 per unit, LT=1 W

300

300

300

Page 50: Chapter 13

Part B(2)LT = 2W

Gross Requirement

Scheduled Receipts

Projected on Hand

Net Requirement

Planned Order Receipts

Planned Order Releases

600

100

100 100 100

Part B; 5 per unit, LT=2 W

500

500

500

Part A (3)LT = 1W

Gross Requirement

Scheduled Receipts

Projected on Hand

Net Requirement

Planned Order Receipts

Planned Order Releases

360

60

60 60 60

300

300

300

Page 51: Chapter 13

Solved Problems 1 and 2 on pages 602-604.First solve the problem yourself.Then look at the solution.

Need More Practice ?

Page 52: Chapter 13

MRP Secondary Reports• Performance-control reports

• Planning reports

• Exception reports

Page 53: Chapter 13

Other Considerations• Safety Stock• Lot sizing

– Lot-for-lot ordering– Economic order quantity– Fixed-period ordering– Part-period model

Page 54: Chapter 13

Capacity PlanningCapacity requirements planning: The process

of determining short-range capacity requirements.

Load reports: Department or work center reports that compare known and expected future capacity requirements with projected capacity availability.

Time fences: Series of time intervals during which order changes are allowed or restricted.

Page 55: Chapter 13

MRP Planning

Develop a tentativemaster production

schedule

Use MRP tosimulate material

requirements

Convert materialrequirements to

resource requirements

Firm up a portionof the MPS

Is shopcapacity

adequate?

Cancapacity be

changed to meetrequirements

Revise tentativemaster production

schedule

Changecapacity

Yes

No

Yes

No

Page 56: Chapter 13

• Food catering service– End item => catered food– Dependent demand => ingredients for

each recipe, i.e. bill of materials• Hotel renovation

– Activities and materials “exploded” into component parts

MRP in Services

Page 57: Chapter 13

Benefits of MRP

• Low levels of in-process inventories

• Ability to track material requirements

• Ability to evaluate capacity requirements

• Means of allocating production time

Page 58: Chapter 13

Requirements of MRP• Computer and necessary software• Accurate and up-to-date

– Master schedules– Bills of materials– Inventory records

• Integrity of data

Page 59: Chapter 13

• Expanded MRP with and emphasis placed on integration– Financial planning

– Marketing

– Engineering

– Purchasing

– Manufacturing

MRP II

Page 60: Chapter 13

MarketDemand

Productionplan

Problems?

Rough-cutcapacity planning

Yes No YesNo

Finance

Marketing

Manufacturing

Adjustproduction plan

Masterproduction schedule

MRP

Capacityplanning

Problems?Requirements

schedules

Adj

ust m

aste

r sch

edul

e

MRP II

Page 61: Chapter 13

• Enterprise resource planning (ERP): An expanded effort to integrate standardized record-keeping that will permit information sharing throughout the organization

ERP