Chapter 12: The Cost of Capital

131
1 The Cost of Capital

Transcript of Chapter 12: The Cost of Capital

Page 1: Chapter 12: The Cost of Capital

1

The Costof Capital

Page 2: Chapter 12: The Cost of Capital

Learning Goals

• Sources of capital• Cost of each type of funding• Calculation of the weighted average cost of capital

(WACC)• Construction and use of the marginal cost of capital

schedule (MCC)

2

Page 3: Chapter 12: The Cost of Capital

Factors Affecting the Cost of Capital

• General Economic Conditions– Affect interest rates

• Market Conditions– Affect risk premiums

• Operating Decisions– Affect business risk

• Financial Decisions– Affect financial risk

• Amount of Financing– Affect flotation costs and market price of

security3

Page 4: Chapter 12: The Cost of Capital

• Compute the cost of each source of capital• Determine percentage of each source of

capital in the optimal capital structure• Calculate Weighted Average Cost of Capital

(WACC)

4

Weighted Cost of Capital Model

Page 5: Chapter 12: The Cost of Capital

• Required rate of return for creditors• Same cost found in Chapter 12 as yield to maturity

on bonds (kd).• e.g. Suppose that a company issues bonds with a

before tax cost of 10%.• Since interest payments are tax deductible, the true

cost of the debt is the after tax cost.• If the company’s tax rate (state and federal

combined) is 40%, the after tax cost of debt • AT kd = 10%(1-.4) = 6%.

5

1. Compute Cost of Debt1. Compute Cost of Debt

Page 6: Chapter 12: The Cost of Capital

• Cost to raise a dollar of preferred stock.

6

11.90% $5.00 $42.00kp = =

The cost of preferred stock:

Example: You can issue preferred stock for a net price of $42 and the preferred stock pays a $5 dividend.

Dividend (Dp)

Market Price (PP) - F

Required rate kp =

2. Compute Cost Preferred Stock2. Compute Cost Preferred Stock

Page 7: Chapter 12: The Cost of Capital

• Two Types of Common Equity Financing– Retained Earnings (internal common

equity)– Issuing new shares of common stock

(external common equity)

7

3. Compute Cost of Common3. Compute Cost of Common EquityEquity

Page 8: Chapter 12: The Cost of Capital

• Cost of Internal Common Equity– Management should retain earnings

only if they earn as much as stockholder’s next best investment opportunity of the same risk.

– Cost of Internal Equity = opportunity cost of common stockholders’ funds.

– Two methods to determine• Dividend Growth Model• Capital Asset Pricing Model 8

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

Page 9: Chapter 12: The Cost of Capital

• Cost of Internal Common Stock Equity– Dividend Growth Model

9

D1

P0kS = + g

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

Page 10: Chapter 12: The Cost of Capital

• Cost of Internal Common Stock Equity– Dividend Growth Model

10

Example:The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%.

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

D1

P0kS = + g

Page 11: Chapter 12: The Cost of Capital

• Cost of Internal Common Stock Equity– Dividend Growth Model

11

3(1+0.10) 60kS = + .10 =.155 = 15.5%

Example:The market price of a share of common stock is $60. The dividend just paid is $3, and the expected growth rate is 10%.

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

D1

P0kS = + g

Page 12: Chapter 12: The Cost of Capital

• Cost of Internal Common Stock Equity– Capital Asset Pricing Model (Chapter 7)

12

kS = kRF + (kM – kRF)

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

Page 13: Chapter 12: The Cost of Capital

• Cost of Internal Common Stock Equity– Capital Asset Pricing Model (Chapter 7)

13

Example:The estimated Beta of a stock is 1.2. The risk-free rate is 5% and the expected market return is 13%.

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

kS = kRF + (kM – kRF)

Page 14: Chapter 12: The Cost of Capital

• Cost of Internal Common Stock Equity– Capital Asset Pricing Model (Chapter 7)

14

kS = 5% + 1.2(13% – 5%) 14.6%

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

=

Example:Example:The estimated Beta of a stock is 1.2. The risk-free rate is 5% and the expected market return is 13%.

kS = kRF + (kM – kRF)

Page 15: Chapter 12: The Cost of Capital

• Cost of New Common Stock– Must adjust the Dividend Growth Model equation for

floatation costs of the new common shares.

15

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

D1

P0 - Fkn = + g

Page 16: Chapter 12: The Cost of Capital

• Cost of New Common Stock– Must adjust the Dividend Growth Model equation

for floatation costs of the new common shares.

16

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

Example:If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%, Price is $60 as before.

D1

P0 - Fkn = + g

Page 17: Chapter 12: The Cost of Capital

• Cost of New Common Stock– Must adjust the Dividend Growth Model equation for

floatation costs of the new common shares.

17

3. Compute Cost of Common Equity3. Compute Cost of Common Equity

3(1+0.10) 52.80kn = + .10 = .1625 =

D1

P0 - Fkn = + g

16.25%

Example:Example:If additional shares are issued floatation costs will be 12%. D0 = $3.00 and estimated growth is 10%, Price is $60 as before.

Page 18: Chapter 12: The Cost of Capital

18

Weighted Average Cost of Capital Weighted Average Cost of Capital

Gallagher Corporation estimates the following costs for each component in its capital structure:

Gallagher’s tax rate is 40%

Source of Capital Cost

Bonds kd = 10%Preferred Stock kp = 11.9%Common Stock

Retained Earnings ks = 15%New Shares kn = 16.25%

Page 19: Chapter 12: The Cost of Capital

19

Weighted Average Cost of Capital Weighted Average Cost of Capital If using retained earnings to finance the

common stock portion the capital structure:

WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)

Page 20: Chapter 12: The Cost of Capital

20

If using retained earnings to finance the common stock portion the capital structure:

Weighted Average Cost of Capital Weighted Average Cost of Capital

Assume that Gallagher’s desired capital structure is 40% debt, 10% preferred and 50% common equity.

WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)

Page 21: Chapter 12: The Cost of Capital

21

Weighted Average Cost of Capital Weighted Average Cost of Capital

WACC = .40 x 10% (1-.4) + .10 x 11.9%+ .50 x 15% = 11.09%11.09%

WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)

If using retained earnings to finance the common stock portion the capital structure:

Assume that Gallagher’s desired capital structure is 40% debt, 10% preferred and 50% common equity.

Page 22: Chapter 12: The Cost of Capital

22

If using a new equity issue to finance the common stock portion the capital structure:

Weighted Average Cost of Capital Weighted Average Cost of Capital

WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)

Page 23: Chapter 12: The Cost of Capital

23

Weighted Average Cost of Capital Weighted Average Cost of Capital

WACC = .40 x 10% (1-.4) + .10 x 11.9%+ .50 x 16.25% = 11.72%11.72%

If using a new equity issue to finance the common stock portion the capital structure:

WACC= ka= (WTd x AT kd ) + (WTp x kp ) + (WTs x ks)

Page 24: Chapter 12: The Cost of Capital

Marginal Cost of CapitalMarginal Cost of Capital• Gallagher’s weighted average cost will

change if one component cost of capital changes.

• This may occur when a firm raises a particularly large amount of capital such that investors think that the firm is riskier.

• The WACC of the next dollar of capital raised in called the marginal cost of capital (MCC).

24

Page 25: Chapter 12: The Cost of Capital

Graphing the MCC curveGraphing the MCC curve• Assume now that Gallagher Corporation

has $100,000 in retained earnings with which to finance its capital budget.

• We can calculate the point at which they will need to issue new equity since we know that Gallagher’s desired capital structure calls for 50% common equity.

25

Page 26: Chapter 12: The Cost of Capital

Graphing the MCC curveGraphing the MCC curve• Assume now that Gallagher Corporation

has $100,000 in retained earnings with which to finance its capital budget.

• We can calculate the point at which they will need to issue new equity since we know that Gallagher’s desired capital structure calls for 50% common equity.

26

Breakpoint = Available Retained EarningsPercentage of Total

Page 27: Chapter 12: The Cost of Capital

Graphing the MCC curveGraphing the MCC curve

27

Breakpoint = ($100,000)/.5 = $200,000

Page 28: Chapter 12: The Cost of Capital

Making Decisions Using MCC

28

Wei

ghte

d C

ost o

f Cap

ital

Total Financing

10%

11%

12%

13%

0 100,000 200,000 300,000 400,000

Marginal weighted cost of capital curve:

Using internal common equity

Using new common equity

11.72%11.72%11.09%11.09%

Page 29: Chapter 12: The Cost of Capital

Making Decisions Using MCCMaking Decisions Using MCC• Graph MIRRs of potential projects

29

Wei

ghte

d C

ost o

f Cap

ital

Total Financing

9%

10%

11%

12%

0 100,000 200,000 300,000 400,000

Marginal weighted cost of capital curve:

Project 1Project 1MIRR = MIRR = 12.4%12.4%

Project 2Project 2MIRR = MIRR = 12.1%12.1%

Project 3Project 3MIRR =MIRR = 11.5%

Page 30: Chapter 12: The Cost of Capital

Making Decisions Using MCCMaking Decisions Using MCC

• Graph IRRs of potential projects

30

Wei

ghte

d C

ost o

f Cap

ital

Total Financing

9%

10%

11%

12%

0 100,000 200,000 300,000 400,000

Marginal weighted cost of capital curve:

Project 1Project 1IRR = IRR = 12.4%12.4%

Project 2Project 2IRR = IRR = 12.1%12.1%

Project 3Project 3IRR =IRR = 11.5%

Graph MCC Curve

11.09%11.09%11.72%11.72%

Page 31: Chapter 12: The Cost of Capital

Making Decisions Using MCCMaking Decisions Using MCC• Graph IRRs of potential projects• Graph MCC Curve

31

Wei

ghte

d C

ost o

f Cap

ital

Total Financing

9%

10%

11%

12%

0 100,000 200,000 300,000 400,000

Marginal weighted cost of capital curve:

Project 1Project 1IRR = 12.4%IRR = 12.4% Project 2Project 2

IRR = 12.1%IRR = 12.1%Project 3Project 3IRR =IRR = 11.5%

Accept Projects #1 & #2Accept Projects #1 & #2

Choose projects whose IRR is above the weighted marginal cost of capital

11.72%11.72%11.09%11.09%

Page 32: Chapter 12: The Cost of Capital

32

Answer the following questions and do the following problems and include them in you ECP Notes.

If the cost of new common equity is higher than the cost of internal equity, why would a firm choose to issue new common stock?

Why is it important to use a firm’s MCC and not a firm’s initial WACC to evaluate investments?

Calculate the AT kd, ks, kn for the following information:Loan rates for this firm = 9%Growth rate of dividends = 4%Tax rate = 30%Common Dividends at t1 = $ 4.00Price of Common Stock = $35.00Flotation costs = 6%

Your firm’s ks is 10%, the cost of debt is 6% before taxes, and the tax rate is 40%. Given the following balance sheet, calculate the firm’s after tax WACC:

Total assets = $25,000Total debt = 15,000Total equity = 10,000

Page 33: Chapter 12: The Cost of Capital

33

Your firm is in the 30% tax bracket with a before-tax required rate of return on its equity of 13% and on its debt of 10%. If the firm uses 60% equity and 40% debt financing, calculate its after-tax WACC.

Would a firm use WACC or MCC to identify which new capital budgeting projects should be selected? Why?

A firm's before tax cost of debt on any new issue is 9%; the cost to issue new preferred stock is 8%. This appears to conflict with the risk/return relationship. How can this pricing exist?

What determines whether to use the dividend growth model approach or the CAPM approach to calculate the cost of equity?

Page 34: Chapter 12: The Cost of Capital

Capital BudgetingDecision Methods

1

Page 35: Chapter 12: The Cost of Capital

• The capital budgeting process.• Calculation of payback, NPV, IRR, and MIRR for

proposed projects.• Capital rationing.• Measurement of risk in capital budgeting and

how to deal with it.

Learning Objectives

2

Page 36: Chapter 12: The Cost of Capital

• Capital Budgeting is the process of evaluating proposed investment projects for a firm.

• Managers must determine which projects are acceptable and must rank mutually exclusive projects by order of desirability to the firm.

The Capital Budgeting Process

3

Page 37: Chapter 12: The Cost of Capital

Four methods:• Payback Period

– years to recoup the initial investment

• Net Present Value (NPV)– change in value of firm if project is under taken

• Internal Rate of Return (IRR)– projected percent rate of return project will earn

• Modified Internal Rate of Return (MIRR)

The Accept/Reject Decision

4

Page 38: Chapter 12: The Cost of Capital

• Consider Projects A and B that have the following expected cashflows?

Capital Budgeting Methods

5

P R O J E C TP R O J E C TTime Time A BB

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

Page 39: Chapter 12: The Cost of Capital

• What is the payback for Project A?

Capital Budgeting Methods

6

P R O J E C TP R O J E C TTimeTime A BB

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

Page 40: Chapter 12: The Cost of Capital

• What is the payback for Project A?Capital Budgeting Methods

0 1 2 3 4

3,500-6,500

3,500-3,000

3,500+500

3,500(10,000)Cumulative CF

7

P R O J E C TP R O J E C TTimeTime A BB

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

Page 41: Chapter 12: The Cost of Capital

• What is the payback for Project A?

Capital Budgeting Methods

Payback in 2.9 years

P R O J E C TP R O J E C TTime Time A BB

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

8

0 1 2 3 4

3,500-6,500

3,500-3,000

3,500+500

3,500(10,000)Cumulative CF

0 1 2 3 4

3,500-6,500

3,500-3,000

3,500+500

3,500(10,000)Cumulative CF

Page 42: Chapter 12: The Cost of Capital

• What is the payback for Project B?

Capital Budgeting Methods

9

0 1 2 3 4

500 500 4,600 10,000(10,000)

P R O J E C TP R O J E C TTimeTime AA B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

Page 43: Chapter 12: The Cost of Capital

Payback in 3.4 years

• What is the payback for Project B?Capital Budgeting Methods

10

0 1 2 3 4

500-9,500

500-9,000

4,600-4,400

10,000+5,600

(10,000)Cumulative CF

P R O J E C TP R O J E C TTimeTime AA B

00 (10,000.) (10,000.)11 3,500 50022 3,500 50033 3,500 4,60044 3,500 10,000

Page 44: Chapter 12: The Cost of Capital

• Accept project if payback is less than the company’s predetermined maximum.

• If company has determined that it requires payback in three years or less, then you would:– accept Project A – reject Project B

Payback Decision Rule

11

Page 45: Chapter 12: The Cost of Capital

• Present Value of all costs and benefits (measured in terms of incremental cash flows) of a project.

• Concept is similar to Discounted Cashflow model for valuing securities but subtracts the cost of the project.

Capital Budgeting Methods

Net Present ValueNet Present Value

12

Page 46: Chapter 12: The Cost of Capital

• Present Value of all costs and benefits (measured in terms of incremental cash flows) of a project.

• Concept is similar to Discounted Cashflow model for valuing securities but subtracts of cost of project.

Capital Budgeting MethodsNet Present ValueNet Present Value

NPV = PV of Inflows - Initial Investment

NPV = + + – Initial Investment

CF1 (1+ k)1

CF2

(1+ k)2 …. CFn (1+ k )

n 13

Page 47: Chapter 12: The Cost of Capital

What is the NPV forProject B?

14

P R O J E C TP R O J E C TTimeTime AA B

0 (10,000) (10,000)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Capital Budgeting Methods

Page 48: Chapter 12: The Cost of Capital

455 $500 (1.10)1

What is the NPV forProject B?

15

P R O J E C TP R O J E C TTimeTime AA B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Capital Budgeting Methods

Page 49: Chapter 12: The Cost of Capital

413

$500 (1.10) 2

What is the NPV forProject B?

16

P R O J E C TP R O J E C TTimeTime AA B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

455

k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Capital Budgeting Methods

Page 50: Chapter 12: The Cost of Capital

3,456

$4,600 (1.10) 3

What is the NPV forProject B?

17

P R O J E C TP R O J E C TTimeTime AA B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

413

$500 (1.10) 2

455

k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Capital Budgeting Methods

Page 51: Chapter 12: The Cost of Capital

6,830

$10,000 (1.10) 4

What is the NPV forProject B?

18

P R O J E C TP R O J E C TTimeTime AA B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

3,456

$4,600 (1.10) 3413

$500 (1.10) 2

455

k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Capital Budgeting Methods

Page 52: Chapter 12: The Cost of Capital

$11,154

What is the NPV forProject B?

19

P R O J E C TP R O J E C TTimeTime A B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

6,8303,456

413

455

k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Capital Budgeting Methods

Page 53: Chapter 12: The Cost of Capital

PV Benefits > PV Costs$11,154 > $ 10,000

What is the NPV forProject B?

20

P R O J E C TP R O J E C TTimeTime A B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

$11,1546,8303,456

413

455

k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Page 54: Chapter 12: The Cost of Capital

NPV > $0$1,154 > $0

- $10,000 = - $10,000 = $1,154$1,154 = = NPVNPV

What is the NPV forProject B?

21

P R O J E C TP R O J E C TTimeTime AA B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

PV Benefits > PV Costs$11,154 > $ 10,000

$11,154$11,1546,8303,456

413

455

k=10%

0 1 2 3 4

500 500 4,600 10,000(10,000)

Page 55: Chapter 12: The Cost of Capital

22

• Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV)

Financial Calculator:

Page 56: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Key used to enter expected cash flows in order of their receipt.NoteNote:: the initial investment (CF0) must be entered as a negative number since it is an outflow.23

• Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV)

Financial Calculator:

Page 57: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

• Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV)

Financial Calculator:

Key used to calculate the net present value ofthe cashflows that have been entered in thecalculator.

24

Page 58: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

• Additional Keys used to enter Cash Flows and compute the Net Present Value (NPV)

Financial Calculator:

Key used to calculate the internal rate of returnfor the cashflows that have been entered in the calculator. 25

Page 59: Chapter 12: The Cost of Capital

Calculate the NPV for Project B with calculator.

26

NPV IRRP/YR

CF

N I/Y PV PMT FV

P R O J E C TP R O J E C TTime ATime A B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

Page 60: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

Keystrokes for TI BAII PLUS:CFCF00 = -10,000 = -10,000

27

CF 10000 +/- ENTER

Page 61: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

C01 = C01 = 500500500 ENTER

28

CF 10000 +/- ENTER

Keystrokes for TI BAII PLUS:

Page 62: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

F01 = F01 = 22

F stands for “frequency”. Enter 2 since thereare two adjacent payments of 500 in periods 1 and 2.

29

2 ENTER500 ENTER

CF 10000 +/- ENTER

Keystrokes for TI BAII PLUS:

Page 63: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

C02 = C02 = 46004600

4600 ENTER

30

2 ENTER500 ENTER

CF 10000 +/- ENTER

Keystrokes for TI BAII PLUS:

Page 64: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

F02 = F02 = 11

1 ENTER31

4600 ENTER 2 ENTER

500 ENTERCF 10000 +/- ENTER

Keystrokes for TI BAII PLUS:

Page 65: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

C03 = C03 = 1000010000

10000 ENTER 32

1 ENTER

4600 ENTER 2 ENTER

500 ENTERCF 10000 +/- ENTER

Keystrokes for TI BAII PLUS:

Page 66: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

F03 = F03 = 1 1

1 ENTER33

10000 ENTER 1 ENTER

4600 ENTER 2 ENTER

500 ENTERCF 10000 +/- ENTER

Keystrokes for TI BAII PLUS:

Page 67: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

I = I = 1010

k = 10%

34

Keystrokes for TI BAII PLUS:

10 ENTERNPV

Page 68: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the NPV for Project B with calculator.

NPV = 1,153.95

CPT

The net present value of Project B = $1,154as we calculated previously.

35

10 ENTERNPV

Keystrokes for TI BAII PLUS:

Page 69: Chapter 12: The Cost of Capital

• Accept the project if the NPV is greater than or equal to 0.

Example:NPVA = $1,095

NPVB = $1,154

NPV Decision Rule

> 0> 0

> 0> 0

AcceptAccept

AcceptAccept•If projects are independent, accept both projects.

•If projects are mutually exclusive, accept the project

with the higher NPV.

36

Page 70: Chapter 12: The Cost of Capital

• IRR (Internal Rate of Return)– IRR is the discount rate that forces the NPV to equal

zero.– It is the rate of return on the project given its initial

investment and future cash flows.• The IRR is the rate earned only if all CFs are reinvested at the

IRR rate.

Capital Budgeting Methods

37

Page 71: Chapter 12: The Cost of Capital

Calculate the IRR for Project B with calculator.

39

NPV IRRP/YR

CF

N I/Y PV PMT FV

P R O J E C TP R O J E C TTime ATime A B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

Page 72: Chapter 12: The Cost of Capital

Enter CFs as for NPV

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the IRR for Project B with calculator.

IRR = IRR = 13.5%13.5%

40

P R O J E C TP R O J E C TTime Time A B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

IRR IRR CPTCPT

Page 73: Chapter 12: The Cost of Capital

• Accept the project if the IRR is greater than or equal to the required rate of return (k).

• Reject the project if the IRR is less than the required rate of return (k).

Example:k = 10%IRRA = 14.96%IRRB = 13.50%

IRR Decision Rule

> 10%> 10%> 10%> 10%

AcceptAcceptAcceptAccept

41

Page 74: Chapter 12: The Cost of Capital

• MIRR (Modified Internal Rate of Return)– This is the discount rate which causes the project’s PV of

the outflows to equal the project’s TV (terminal value) of the inflows.

– Assumes cash inflows are reinvested at k, the safe re-investment rate.

– MIRR avoids the problem of multiple IRRs.– We accept if MIRR > the required rate of return.

Capital Budgeting Methods

PVPVoutflowoutflow == TVinflows

(1 + MIRR)n

42

Page 75: Chapter 12: The Cost of Capital

What is the MIRR forProject B?

P R O J E C TP R O J E C TTime ATime A B

0 (10,000.) (10,000.)1 3,500 5002 3,500 5003 3,500 4,6004 3,500 10,000

Safe =2%

0 1 2 3 4

500500 500500 4,6004,600 10,00010,000(10,000)(10,000)

(10,000)(10,000)

10,000(1.02)0

10,000

4,600(1.02)1500(1.02)2500(1.02)3

4,692 520

53115,74310,000 =

15,743

(1 + MIRR)4

(10,000)/(1.02)0

MIRR = .12 = 12%MIRR = .12 = 12%

43

Page 76: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the MIRR for Project B with calculator.

10000 ENTER

1 ENTER

1 ENTER

4600 ENTER 2 ENTER

500 ENTERCF 0 +/- ENTER

Keystrokes for TI BAII PLUS:

Step 1. Calculate NPV using cash inflows

44

Page 77: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the MIRR for Project B with calculator.

NPV = 14,544NPV = 14,544

CPT

The net present value of Project B cash inflows = $14,544(use as PV)

45

2 ENTERNPV

Keystrokes for TI BAII PLUS:

Step 1. Calculate NPV using cash inflowsStep 1. Calculate NPV using cash inflows

Page 78: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the MIRR for Project B with calculator.

FV =FV = 15,743 15,743

46

Step 2. Calculate FV of cash inflows using previous NPVThis is the Terminal Value

Calculator Enter:N = 4I/YR = 2PV = -14544PMT = 0CPT FV = ?

Page 79: Chapter 12: The Cost of Capital

NPV IRRP/YR

CF

N I/Y PV PMT FV

Calculate the MIRR for Project B with calculator.

MIRRMIRR 12.0112.01

47

Step 3. Calculate MIRR using PV of outflows and calculated Terminal Value.

Calculator Enter:N = 4PV = -10000PMT = 0FV = 15,743CPT I/YR = ??

Page 80: Chapter 12: The Cost of Capital

• Capital rationing is the practice of placing a dollar limit on the total size of the capital budget.

• This practice may not be consistent with maximizing shareholder value but may be necessary for other reasons.

• Choose between projects by selecting the combination of projects that yields the highest total NPV without exceeding the capital budget limit.

What is capital rationing?

54

Page 81: Chapter 12: The Cost of Capital

• Calculate the coefficient of variation of returns of the firm’s asset portfolio with the project and without it.

• This can be done by following a five step process. Observe the following example.

Measurement of Project Risk

55

Page 82: Chapter 12: The Cost of Capital

• Step 1:Step 1: Find the CV of the Existing Portfolio– Assume Company X has an existing rate of return

of 6% and standard deviation of 2%.

Measurement of Project Risk

56

Standard DeviationMean, or expected valueCV=

= .02.06

= .3333, or 33.33%

Page 83: Chapter 12: The Cost of Capital

• Step 2:Step 2: Find the Expected return of the New Portfolio (Existing plus Proposed)– Assume the New Project (Y) has an IRR of 5.71%

and a Standard Deviation of 2.89% – Assume further that Project Y will account for 10%

of X’s overall investment.

Measurement of Project Risk

57

(wx x E(Rx)) + (wy x E(Ry))

= (.10 x .0571) + (.90 x .06)= .00571 + .05400= .05971, or 5.971%

E(Rp) =

Page 84: Chapter 12: The Cost of Capital

• Step 3:Step 3: Find the Standard Deviation of the New Portfolio (Existing plus Proposed). – Assume the proposed is uncorrelated with the

existing project. rxy = 0

Measurement of Project Risk

58

[wx2σx

2 + wy2σy

2 + 2wxwyrxyσxσy]1/2

= [(.102)(.02892) + (.902)(.022) + (2)(.10)(.90)(0.0)(.0289)(02)]1/2

= [(.01)(.000835) + (.81)(.0004) + 0]1/2

= .0182, or 1.82%= [.00000835 + .000324]1/2

= [.00033235]1/2

σp =

Page 85: Chapter 12: The Cost of Capital

• Step 4:Step 4: Find the CV of the New Portfolio (Existing plus Proposed)

Measurement of Project Risk

59

Standard DeviationMean, or expected valueCV=

= .0182.05971

= .3048, or 30.48%

Page 86: Chapter 12: The Cost of Capital

• Step 5:Step 5: Compare the CV of the portfolio with and without the Proposed Project.– The difference between the two coefficients

of variation is the measure of risk of the capital budgeting project.

Measurement of Project Risk

60

CV without Y Change in CVCV with Y33.33% -2.8530.48%

Page 87: Chapter 12: The Cost of Capital

• Firms often compensate for risk by adjusting the discount rate used to calculate NPV.– Higher risk, use a higher discount rate.– Lower risk, use a lower discount rate

• The risk adjusted discount rate (RADR) can also be used as a risk adjusted hurdle rate for IRR comparisons.

Comparing risky projects using risk adjusted discount rates (RADRs)

61

Page 88: Chapter 12: The Cost of Capital

• Non-simple projects have one or more negative future cash flows after the initial investment.

Non-simple Projects

62

Page 89: Chapter 12: The Cost of Capital

• How would a negative cash flow in year 4 affect Project Z’s NPV?

Non-simple projects

Project Z should be rejected in this case.63

8,336 -4,098 3,757

4,132

4,545

k=10%

0 1 2 3 4

5,000 5,000 5,000 -6,000(10,000)

- $10,000 = -$1,664 NPV

Page 90: Chapter 12: The Cost of Capital

• Mutually exclusive projects with unequal project lives can be compared by using two methods:

– Replacement Chain– Equivalent Annual Annuity

Mutually Exclusive Projects With Unequal Lives

68

Page 91: Chapter 12: The Cost of Capital

• Assumes each project can be replicated until a common period of time has passed, allowing the projects to be compared.

• Example– Project Cheap Talk has a 3-year life, with an NPV

of $4,424.– Project Rolles Voice has a 12-year life, with an

NPV of $4,510.

Replacement Chain Approach

69

Page 92: Chapter 12: The Cost of Capital

• Project Cheap Talk could be repeated four times during the life of Project Rolles Voice.

• The NPVs of Project Cheap Talk, in years t3, t6, and t9, are discounted back to year t0.

Replacement Chain Approach

70

Page 93: Chapter 12: The Cost of Capital

• The NPVs of Project Cheap Talk, in years t3, t6, and t9, are discounted back to year t0, which results in an NPV of $12,121.

Replacement Chain Approach

3,324

12,121

2,4971,876

0 3 6 9

4,424 4,424 4,4244,424

k=10%

71

Page 94: Chapter 12: The Cost of Capital

• Amount of the annuity payment that would equal the same NPV as the actual future cash flows of a project.

• EAA = NPV PVIFAk,n

Equivalent Annual Annuity

72

Page 95: Chapter 12: The Cost of Capital

Equivalent Annual Annuity

73

Project Rolles VoiceProject Rolles Voice $4,510 ((1-(1.1)-12) / .1) = $661.90

• Project Cheap TalkProject Cheap Talk $4,244

((1-(1.1)-3) / .1)

= $1778.96

Page 96: Chapter 12: The Cost of Capital

ECP HomeworkECP Homework1. The following net cash flows are projected for two separate projects. Your required rate of return is 12%.

Year Project A Project B0 ($150,000) ($400,000)1 $30,000 $100,0002 $30,000 $100,0003 $30,000 $100,0004 $30,000 $100,0005 $30,000 $100,0006 $30,000 $100,000

 a. Calculate the payback period for each project.b. Calculate the NPV of each project. c. Calculate the MIRR of each project. d. Which project(s) would you accept and why?

Page 97: Chapter 12: The Cost of Capital

2. What is meant by risk adjusted discount rates?

3. Explain why the NPV method of capital budgeting is preferable over the payback method.

4. A firm has a net present value of zero. Should the project be rejected? Explain.

5. You have estimated the MIRR for a new project with the following probabilities:  Possible MIRR Value Probability

4% 5%7% 15%10% 15%11% 50%14% 15%

 a. Calculate the expected MIRR of the project.

 b. Calculate the standard deviation of the project.

 c. Calculate the coefficient of variation.

 d. Calculate the expected MIRR of the new portfolio with the new project. The

current portfolio has an expected MIRR of 9% and a standard deviation of 3% and will represent 60% of the total portfolio.

ECP HomeworkECP Homework

Page 98: Chapter 12: The Cost of Capital

98

Business Valuation

Page 99: Chapter 12: The Cost of Capital

Learning Objectives

• Understand the importance of business valuation.• Understand the importance of stock and bond

valuation.• Learn to compute the value and yield to maturity of

bonds.• Learn to compute the value and expected yield on

preferred stock and common stock. • Learn to compute the value of a complete business.

99

Page 100: Chapter 12: The Cost of Capital

General Valuation Model

• To develop a general model for valuing a business, we consider three factors that affect future earnings:– Size of cash flows– Timing of cash flows– Risk

• We then apply the factors to the Discounted Cash Flow (DCF) Model (Equation 12-1)

100

Page 101: Chapter 12: The Cost of Capital

Bond Valuation Model

• Bond Valuation is an application of time value model introduced in chapter 8.

• The value of the bond is the present value of the cash flows the investor expects to receive.

• What are the cashflows from a bond investment?

101

Page 102: Chapter 12: The Cost of Capital

Bond Valuation Model

• 3 Types of Cash Flows– Amount paid to buy the bond (PV)– Coupon interest payments made to the

bondholders (PMT)– Repayment of Par value at end of Bond’s life

(FV).

102

Page 103: Chapter 12: The Cost of Capital

Bond Valuation Model

• 3 Types of Cash Flows– Amount paid to buy the bond (PV)– Coupon interest payments made to the

bondholders (PMT)– Repayment of Par value at end of Bond’s life

(FV).

103

Discount rate (I/YR)• Bond’s time to maturity (N)

Page 104: Chapter 12: The Cost of Capital

104

Cur Net Bonds Yld Vol Close ChgAMR6¼24 cv 6 91¼ -1½ATT 8.35s25 8.3 110 102¾ +¼IBM 63/8 05 6.6 228 965/8 -1/8

Kroger 9s99 8.8 74 1017/8 -¼

IBM 63/8 09 6.6 228 965/8 -1/8

IBM Bond Wall Street Journal Information:

Page 105: Chapter 12: The Cost of Capital

105

Suppose IBM makes annual coupon payments. The person who buys the bond at the beginning of 2005 for $966.25 will receive 5 annual coupon payments of $63.75 each and a $1,000 principal payment in 5 years (at the end of 2009). Assume t0 is the beginning of 2005.

IBM Bond Wall Street Journal Information:

Cur Net Bonds Yld Vol Close ChgAMR6¼24 cv 6 91¼ -1½ATT 8.35s25 8.3 110 102¾ +¼IBM 63/8 05 6.6 228 965/8 -1/8

Kroger 9s99 8.8 74 1017/8 -¼

IBM 63/8 09 6.6 228 965/8 -1/8

Page 106: Chapter 12: The Cost of Capital

106

IBM Bond Timeline:

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

Suppose IBM makes annual coupon payments. The person who buys the bond at the beginning of 2005 for $966.25 will receive 5 annual coupon payments of $63.75 each and a $1,000 principal payment in 5 years (at the end of 2009).

Cur Net Bonds Yld Vol Close ChgAMR6¼24 cv 6 91¼ -1½ATT 8.35s25 8.3 110 102¾ +¼IBM 63/8 05 6.6 228 965/8 -1/8

Kroger 9s99 8.8 74 1017/8 -¼

IBM 63/8 09 6.6 228 965/8 -1/8

Page 107: Chapter 12: The Cost of Capital

107

Compute the Value for the IBM Bond given that you Compute the Value for the IBM Bond given that you require an 8% return on your investment.require an 8% return on your investment.

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

IBM Bond Timeline:IBM Bond Timeline:

Page 108: Chapter 12: The Cost of Capital

108

$63.75 Annuity for 5 years$63.75 Annuity for 5 years

VB = (INT x PVIFAk,n) + (M x PVIFk,n )

$1000 Lump Sum in 5 years$1000 Lump Sum in 5 years

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

IBM Bond Timeline:IBM Bond Timeline:

Page 109: Chapter 12: The Cost of Capital

109

VB = (INT x PVIFAk,n) + (M x PVIFk,n )= 63.75(3.9927) + 1000(.6806)= 254.53 + 680.60 = 935.13

$63.75 Annuity for 5 years$63.75 Annuity for 5 years $1000 Lump Sum in 5 years$1000 Lump Sum in 5 years

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

IBM Bond Timeline:IBM Bond Timeline:

Page 110: Chapter 12: The Cost of Capital

110

.01 rounding differenceN I/YR PV PMT FV

––935.12935.12

5 8 ? 63.75 1,000

IBM Bond Timeline:IBM Bond Timeline:

$63.75 Annuity for 5 years$63.75 Annuity for 5 years

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

$1000 Lump Sum in 5 years$1000 Lump Sum in 5 years

Page 111: Chapter 12: The Cost of Capital

111

Most Bonds Pay Interest Semi-Annually:

e.g. semiannual coupon bond with 5 years to maturity, 9% annual coupon rate.

Instead of 5 annual payments of $90, the bondholderreceives 10 semiannual payments of $45.

0 1 2 3 4 5

2005 2006 2007 2008 2009

45 451000

45 45 45 45 45 45 45 45

Page 112: Chapter 12: The Cost of Capital

112

Compute the value of the bond given that you require a 10% return on your investment.

Since interest is received every 6 months, we need to usesemiannual compounding

VB = 45( PVIFA10 periods,5%) + 1000(PVIF10 periods, 5%)

10%2

Semi-AnnualCompounding

Most Bonds Pay Interest Semi-Annually:Most Bonds Pay Interest Semi-Annually:

0 1 2 3 4 5

2005 2006 2007 2008 2009

45 451000

45 45 45 45 45 45 45 45

Page 113: Chapter 12: The Cost of Capital

113

Most Bonds Pay Interest Semi-Annually:

= 45(7.7217) + 1000(.6139)= 347.48 + 613.90 = 961.38

Compute the value of the bond given that you Compute the value of the bond given that you require a 10% return on your investment.require a 10% return on your investment.

Since interest is received every 6 months, we need to usesemiannual compounding

VB = 45( PVIFA10 periods,5%) + 1000(PVIF10 periods, 5%)

0 1 2 3 4 5

2005 2006 2007 2008 2009

45 451000

45 45 45 45 45 45 45 45

Page 114: Chapter 12: The Cost of Capital

114

Calculator Solution:

N I/YR PV PMT FV

––961.38961.38

10 5 ? 45 1,000

0 1 2 3 4 5

2005 2006 2007 2008 2009

45 451000

45 45 45 45 45 45 45 45

Page 115: Chapter 12: The Cost of Capital

Yield to Maturity• If an investor purchases a 6.375% annual coupon

bond today for $966.25 and holds it until maturity (5 years), what is the expected annual rate of return ?

115

-966.25??

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

+ ??966.25966.25

Page 116: Chapter 12: The Cost of Capital

Yield to Maturity

116

VB = 63.75(PVIFA5, x%) + 1000(PVIF5,x%)Solve by trial and error.

• If an investor purchases a 6.375% annual coupon bond today for $966.25 and holds it until maturity (5 years), what is the expected annual rate of return ?

-966.25??

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

+ ??966.25966.25

Page 117: Chapter 12: The Cost of Capital

Yield to Maturity

7.203%

117

Calculator Solution:

N I/YR PV PMT FV

5 ? -966.25 63.75 1,000

-966.25

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

Page 118: Chapter 12: The Cost of Capital

Yield to Maturity

118

If YTM > Coupon Rate bond Sells at a DISCOUNT

If YTM < Coupon Rate bond Sells at a PREMIUM

-966.25

0 1 2 3 4 5

2005 2006 2007 2008 2009

63.75 63.75 63.75 63.75 63.751000.00

Page 119: Chapter 12: The Cost of Capital

Interest Rate Risk

• Bond Prices fluctuate over Time– As interest rates in the economy change,

required rates on bonds will also change resulting in changing market prices.

119

Interest Rates VVBB

Page 120: Chapter 12: The Cost of Capital

Interest Rate Risk

120

• Bond Prices fluctuate over Time– As interest rates in the economy change,

required rates on bonds will also change resulting in changing market prices.

Interest Rates VVBBInterest

Rates VVBB

Page 121: Chapter 12: The Cost of Capital

Valuing Preferred Stock

121

P0 = Value of Preferred Stock

= PV of ALL dividends discounted at investor’s Required Rate of Return

52 Weeks Yld Vol NetHi Lo Stock Sym Div % PE 100s Hi Lo Close

Chgs 42½ 29 QuakerOats OAT 1.143.3 24 5067 35 34¼ 34¼ -¾s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾

237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...

7¼ 5½ RJR Nab pfC .60 9.4 ... 2248 6½ 6¼63/8 -1/80 1 2 3

P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31

237/820 RJR Nab pfB 2.319.7 ... 966 24 235/8 23¾ ...

Page 122: Chapter 12: The Cost of Capital

Valuing Preferred Stock

122

P0 = + + +··· 2.31 (1+ kp)

2.31 (1+ kp)2

2.31 (1+ kp)3

52 Weeks Yld Vol NetHi Lo Stock Sym Div % PE 100s Hi Lo Close

Chgs 42½ 29 QuakerOats OAT 1.143.3 24 5067 35 34¼ 34¼ -¾s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾

237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...

7¼ 5½ RJR Nab pfC .60 9.4 ... 2248 6½ 6¼63/8 -1/80 1 2 3

P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31

237/820 RJR Nab pfB 2.319.7 ... 966 24 235/8 23¾ ...

Page 123: Chapter 12: The Cost of Capital

Valuing Preferred Stock

123P0 =

Dp kp

= 2.31 .10 = $23.10

P0 = + + +··· 2.31 (1+ kp)

2.31 (1+ kp )2

2.31 (1+ kp )3

52 Weeks Yld Vol NetHi Lo Stock Sym Div % PE 100s Hi Lo Close

Chgs 42½ 29 QuakerOats OAT 1.143.3 24 5067 35 34¼ 34¼ -¾s 36¼ 25 RJR Nabisco RN .08p ... 12 6263 29¾ 285/8 287/8 -¾

237/8 20 RJR Nab pfB 2.31 9.7 ... 966 24 235/8 23¾ ...

7¼ 5½ RJR Nab pfC .60 9.4 ... 2248 6½ 6¼63/8 -1/80 1 2 3

P0=23.75 D1=2.31 D2=2.31 D3=2.31 D=2.31

237/820 RJR Nab pfB 2.319.7 ... 966 24 235/8 23¾ ...

Page 124: Chapter 12: The Cost of Capital

Valuing Individual Shares of Common Stock

124

P0 = PV of ALL expected dividends discounted at investor’s Required Rate of Return

Not like Preferred Stock since D0 = D1 = D2 = D3 = DN , therefore the cash flows are no longer an annuity.

P0 = + + +··· D1 (1+ ks )

D2 (1+ ks )2

D3 (1+ ks )3

D1 D2 D3P0 D

0 1 2 3

Page 125: Chapter 12: The Cost of Capital

Valuing Individual Shares of Common Stock

125

P0 = PV of ALL expected dividends discounted at investor’s Required Rate of Return

Investors do not know the values of D1, D2, .... , DN. The future dividends must be estimated.

D1 D2 D3P0 D

0 1 2 3

P0 = + + +··· D1 (1+ ks )

D2 (1+ ks )2

D3 (1+ ks )3

Page 126: Chapter 12: The Cost of Capital

Constant Growth Dividend Model

126

Assume that dividends grow at a constant rate (g).

D1=D0 (1+g)D0 D2=D0 (1+g)2D3=D0 (1+g)3D=D0 (1+g)

0 1 2 3

Page 127: Chapter 12: The Cost of Capital

Constant Growth Dividend Model

127

Requires ks > g

Reduces to:

P0 = + + + ··· +

D0 (1+ g)(1+ ks )

D0 (1+ g)2

(1+ ks )2

D0 (1+ g)3

(1+ ks )3

P0 = = D0(1+g) ks – g

D1 ks – g

Assume that dividends grow at a constant rate (g).

D1=D0 (1+g)D0 D2=D0 (1+g)2D3=D0 (1+g)3D=D0 (1+g)

0 1 2 3

Page 128: Chapter 12: The Cost of Capital

Constant Growth Dividend Model

128

P0 = = $30.50 1.14(1+.07) .11 – .07

What is the value of a share of common stock if themost recently paid dividend (D0) was $1.14 per share anddividends are expected to grow at a rate of 7%?Assume that you require a rate of return of 11% on this investment.

P0 = = D0(1+g) ks – g

D1 ks – g

Page 129: Chapter 12: The Cost of Capital

Valuing Total Stockholders’ Equity

• The Investor’s Cash Flow DCF Model– Investor’s Cash Flow is the amount that is

“free” to be distributed to debt holders, preferred stockholders and common stockholders.

– Cash remaining after accounting for expenses, taxes, capital expenditures and new net working capital.

129

Page 130: Chapter 12: The Cost of Capital

130

Calculating Intrinsic Value

Coca Cola Example

Page 131: Chapter 12: The Cost of Capital

131

ECP Homework1. Indicate which of the following bonds seems to be reported incorrectly with respect to discount, premium, or par and explain why.  

Bond Price Coupon Rate Yield to Maturity 

A 105 9% 8%B 100 6% 6%C 101 5% 4.5%D 102 0% 5%

2. What is the price of a ten-year $1,000 par-value bond with a 9% annual coupon rate and a 10% annual yield to maturity assuming semi-annual coupon payments?

3. You have an issue of preferred stock that is paying a $3 annual dividend. A fair rate of return on this investment is calculated to be 13.5%. What is the value of this preferred stock issue?

4. Total assets of a firm are $1,000,000 and the total liabilities are $400,000. 500,000 shares of common stock have been issued and 250,000 shares are outstanding. The market price of the stock is $15 and net income for the past year was $150,000.

a.. Calculate the book value of the firm.b. Calculate the book value per share.c. Calculate the P/E ratio.

5. A firm’s common stock is currently selling for $12.50 per share. The required rate of return is 9% and the company will pay an annual dividend of $.50 per share one year from now which will grow at a constant rate for the next several years. What is the growth rate?