INTRODUCTION
Construction waste recycling is aprocess of separating and recyclingwaste material produced during
construction, building renovation anddemolition. A lot of this constructionwaste can be re-used. Duringrenovation, all used brick, windows,doors and timbers can be recycled.
-
8/9/2019 Chapter 12 Edit
4/16
SOLID AND WASTE CONSTRUCTION MATERIAL
MANAGEMENT
Construction and demolition contribute large proportion ofwaste which occupy large area of landfill. Therefore,recycling the waste can solve the critical shortage of landfillarea we are facing nowadays.
Demolition and construction waste sources include:
1.Waste arise from demolition of entire, or part of buildingand public infrastructure.
2.Waste arise from building and public infrastructure
construction3.Soil, stones and trees arise from site clearing, public workand foundation work.
4.Road construction material and related material arisefrom road maintenance activities.
-
8/9/2019 Chapter 12 Edit
5/16
Various type of waste sources
Crushed tileCrushed brickCrushed concrete
Crushed ceramic
Construction wasteOil, paint & container
MatelPlywood and timber
Construction waste
-
8/9/2019 Chapter 12 Edit
6/16
Re-use of construction material wasteWith proper management technique, re-use of
construction waste can reduce the need to disposethem. Among the steps to be taken are to:
(a)Have an early planning
(b)Systematically separating construction waste,
and
(c)Have good management of construction waste
-
8/9/2019 Chapter 12 Edit
7/16
-
8/9/2019 Chapter 12 Edit
8/16
Separation of construction waste
Among ways to separate construction waste are:
Providing sufficient containers and dustbins forrecycling.
Identify types of waste containers and dustbins.Label should be clear.
Train construction staff and workers to separateconstruction waste accordingly.
Provide proper place to store and protect theconstruction waste from rain or sun
Construction site which is not
properly managed
-
8/9/2019 Chapter 12 Edit
9/16
Management of construction waste
Management of construction waste can be
seen as a way to ensure waste produced is
properly managed and can be recycled
-
8/9/2019 Chapter 12 Edit
10/16
CONSTRUCTION
MATERIAL
WASTE MANAGEMENT METHOD
Timber Whenever possible, specify building dimensionaccording to standard timber size.
Modify structure specification to optimise timber
usage and reduce waste
Store timber on top flat blocks with cover
minimize timber bending and twisting
Set aside cut timber and plywood which can be
re-used
Store clean timber sawdust to be used in
composting pile or other usage Timber chunks can be sliced up and used as a
material for fuel or fibre
-
8/9/2019 Chapter 12 Edit
11/16
CONSTRUCTION
MATERIAL
WASTE MANAGEMENT METHOD
Wallboard Order wallboard in optimum dimension to minimise
cutting waste Mortarboard can be obtained in variety of sizes.
Design dimension should match the standard size.
Excessive large of mortarboard can be re-used
Bricks andconcrete
Re-use concrete blocks and old bricks which are stillin good condition.
Crush and re-use as ready-mix concrete aggregate,
or road foundation and as building foundation layer.
Estimate carefully to overcome wastage
Collect, accumulate and cover bricks and otherbrickwork during construction to prevent them from
getting dirty.
Concrete blocks, old brick, crushed block and
brickwork rubble can be buried on site during the
filling of foundation work
-
8/9/2019 Chapter 12 Edit
12/16
CONSTRUCTION
MATERIAL
WASTE MANAGEMENT METHOD
Matel During construction and renovation works,separate metal materials such as grill and piping
for recycling
Sell re-use materials such as iron, lead, copper
and aluminium.
Avoid dispose of lead into landfill because it can
dissolve into the soil.
Paint and
solven
Send unused parts to a recycling centre.
Store materials for future works.
Miscellaneous During building renovation, identify unused or
unwanted cabinets, lamps, bath tub, mortar mix,
iron, nails, screws, stationary, piping equipments
and transport them to recycling centres.
-
8/9/2019 Chapter 12 Edit
13/16
EROSION CONTROL
Soil erosion is the wearing and movement of
soil layer due to water, wind and ice.
Deforestation, construction anddevelopment always cause serious soil
erosion. This situation is becoming worst at
hillsides
-
8/9/2019 Chapter 12 Edit
14/16
Erosion Control MethodHydroseeding
Hydroseeding is a method of planting grass tominimise erosion. Hydroseeding material mix ismade-up timber fibre, compost, bonding materials,water and seeds. Strong grass rooting will grip
loose soil and thick leaf can protect soil fromrunning water.
Timber fibre helps even distribution of seeds andacts as a cover layer after spraying.
Hydroseeding spraying
-
8/9/2019 Chapter 12 Edit
15/16
Erosion Control Method
Diverting drainThe perpose of diverting drain is to reduce rapidwater flow at the hill slopes. Diverting drainnormally can be seen along the North-SouthHighway
Diverting drain on hill slope
-
8/9/2019 Chapter 12 Edit
16/16
Erosion Control Method
GunitingGuniting or shotcrete is the spraying ofsand, cement and water mixture using highpressure spray. Guniting enables concrete
be sprayed to uneven, vertical and highsurfaces. It is normally used to protect rockslope from erosion.
Examples of guniting