Changing the Logic from Batch to Flow

36
Changing the logic from Batch to Flow Ian Glenday

description

by Ian Glenday of Lean Enterprise Academy shown at the Lean Supply Chain Forum on 5th June 2007 ran by Lean Enterprise Academy

Transcript of Changing the Logic from Batch to Flow

Page 1: Changing the Logic from Batch to Flow

Changing the logic from Batch to Flow

Ian Glenday

Page 2: Changing the Logic from Batch to Flow

Conventional wisdom

is often shown to be wrong

– Low cost airlines won’t take off

– Diesel engines are slow

– Millennium bug will cause chaos

Page 3: Changing the Logic from Batch to Flow

Is there another example of

existing systems where

conventional thinking

could be wrong?

Page 4: Changing the Logic from Batch to Flow

Current Supply Chain Logic Issues

Batches (EOQ’s) cause

peaks & troughs

= bull whip effect

Page 5: Changing the Logic from Batch to Flow

Retailer’s orders to manufacturer

7209 VSPN 24x200g-orders in cases

0

1000

2000

3000

4000

5000

1 6 11 16 21 26 31 36 41 46 51 3

Actual sales

Page 6: Changing the Logic from Batch to Flow

EPOS data for same item- actual consumer demand

7209 VSPN 200G - sales in units

0

50000

100000

150000

1 6 11 16 21 26 31 36 41 46 51

UNITS

Page 7: Changing the Logic from Batch to Flow

Current Supply Chain Logic Issues

Page 8: Changing the Logic from Batch to Flow

Current Supply Chain Logic Issues

Result:

• A different plan every time

Page 9: Changing the Logic from Batch to Flow

Current Supply Chain Logic Issues

Consequences:

• Increased fixed costs• Increased communication • Increased risk

High chance somethingwill go wrong resulting in:

Page 10: Changing the Logic from Batch to Flow

Supply Chain Logic Issue

Do your business evermake short term plan changes?

Page 11: Changing the Logic from Batch to Flow

Supply Chain Logic IssueDifferent

plansThings

go wrong

More

wasteMore

Change-overs

Finish Good

shortages

Unplanned

changes

Loss of

capacity

Page 12: Changing the Logic from Batch to Flow

Current supply chain logic of EOQ:

• Creates peaks & troughs

But also responsible for creating:

• Different plans• Short term plan changes

Yet still the fundamental supply chain logic used by most retailers and

manufacturers

Page 13: Changing the Logic from Batch to Flow

Alternative logicBuffer Tank

Page 14: Changing the Logic from Batch to Flow

PARADIGM SHIFT

What today seems impossible to do

but

if it could be done

would fundamentally change what you do.

Page 15: Changing the Logic from Batch to Flow

PARADIGM SHIFT

FLOWBATCH TO

Page 16: Changing the Logic from Batch to Flow

What is LEAN ?

Page 17: Changing the Logic from Batch to Flow

Toyota Production System

Jidoka

-Andon

-Poka-Yoke

-Visual control

-5S, etc.

Just-in-time

-continuous Flow

-Takt time

-Pull system

Customer service

Continuous Improvement

AndElimination of MUDA (waste)

Lead TimeCostQuality

Stability & Standardized Work

Levelled production (heijunka)

Page 18: Changing the Logic from Batch to Flow

Levelled Production - Heijunka

mixed sequence one piece flow matched to market pullthroughTAKT time

= perfect flow

Page 19: Changing the Logic from Batch to Flow

mixed sequence one piece flow matched to market pullthroughTAKT time

• Final step in the process, not how Toyota started

• What you see is different to how it was achieved

• Need to know the “secret” of how it was done

Page 20: Changing the Logic from Batch to Flow

• Understanding levelled production– Steps of levelling

Page 21: Changing the Logic from Batch to Flow

Steps for implementing levelling

- starting point batch Production

• One batch per month per product

• Min. change overs• Max. batch sizes

Page 22: Changing the Logic from Batch to Flow

Steps for implementing levelling

- step 1 Twice Monthly Production

• Halve batch sizes• Identical sequence• Two cycles

Every Product Every Cycle

Page 23: Changing the Logic from Batch to Flow

Steps for implementing levelling

- step 2 Weekly Production

• Halve batch sizes• Identical sequence• Same ratios

Every Product Every week

Page 24: Changing the Logic from Batch to Flow

Steps for implementing levelling

- step 3 Daily Production• One batch per day• Identical sequence• Same ratios

Every Product Every day

Page 25: Changing the Logic from Batch to Flow

Steps for implementing Heijunka

- step 3 Daily Production• One batch per day• Identical sequence• Every product

every day

Continuous production of all products

Page 26: Changing the Logic from Batch to Flow

Steps for implementing levelling

Remainingsteps of levelling

Page 27: Changing the Logic from Batch to Flow

Steps for implementing levelling

- step 4 Fixed Volume Production

• Daily multiple batches of same product at a fixed size

• Fixed sequence broken

Every product every cycle = means to reach the real goal

Page 28: Changing the Logic from Batch to Flow

Steps for implementing levelling

- step 5 Synchronised Production• Batch sizes of one =

One piece flow• Mixed stream • Synchronised to

market pull through takt time

Final resultnot how it was achieved

Page 29: Changing the Logic from Batch to Flow

Flow Logic- false bridge steps

• Objective is a fixed “drumbeat” leading to stability & standardised work

• Counter-intuitive as demand seen as variable

• A rigid disciplined PUSH process

• Opposite of the final objective = flexible responsive PULL process

Page 30: Changing the Logic from Batch to Flow

Flow Logic

But why do it?

Page 31: Changing the Logic from Batch to Flow

ECONOMIES

OF

REPETITION

Making the apparently impossible

POSSIBLE !

Page 32: Changing the Logic from Batch to Flow

Economies of Repetition

• Repetitive Flexible Supply game

• Happens in actual implementation

• Reason why EPEC has to be EVERY

• Three separate aspects

Page 33: Changing the Logic from Batch to Flow

Economies of Repetition

• Learning Curve

• Routines

• Stability– Foundation for continuous improvement– Helps root cause identification & resolution– Encourages standardisation

Page 34: Changing the Logic from Batch to Flow

Economies of RepetitionFasterEPEC

- Learning curve- Routines- Stability

AboveExpectation

results

Economiesof

Repetition

NaturalContinuous

improvement

Page 35: Changing the Logic from Batch to Flow

Economies of Repetitionfine in theory, but………

Product Everycan’t do Every Cycle with current systems & equipment, therefore…….

won’t get Economies of Repetition !

Page 36: Changing the Logic from Batch to Flow

Flow Logic

and

Every Product Every Cycle

How to start