Chanakya Round 1 Case 3
-
Upload
aniket-pallav -
Category
Documents
-
view
215 -
download
0
Transcript of Chanakya Round 1 Case 3
-
8/13/2019 Chanakya Round 1 Case 3
1/5
Case #3
Of MAN, MACHINE & MANUFACTURING
Chanakya, IIM Indore
ROUND1
CASECHALLENGE
-
8/13/2019 Chanakya Round 1 Case 3
2/5
Case #3 Of Man, Machine & Manufacturing
OF MAN, MACHINE & MANUFACTURING
Sitting in his office on the first floor with a clear view of the 4 assembly lines, the highly dynamic and energetic
Production Manager of Innovat Electronics Rajat Dubey, had been rather gloomy since morning. On his
insistence, Innovat had taken the highly ambitious project of manufacturing the latest K-Series laptops in-
house with the advance orders simply 4 months away. While Rajat and his team were successful in establishing
and starting the assembly line, various issues had now creeped in. He now seeks solutions to these challenges.
The Company
Innovat Electronics was an Indian Manufacturing Firm set up in the early 1980s mainly as a vendor to various
multinationals. Having been in trade for several years and developing its own contacts in the industry, the
company decided to start designing and manufacturing its products. The latest in the portfolio of products
being developed by Innovat was its K-series Laptop.
The Production
Rajat and his team had designed and were able to start production of the K-series laptops in a record time.
Rajat himself was at the heart of the entire process, right from designing to the implementation of the
assembly line which he considered to be his most important contribution to the organization. Innovat had
asked Trusted Inc. to develop the motherboard which was one of its kinds both in terms of complexity and
design and which would make Innovatslaptops the fastest and the most robust ones in the market.
Process
Rajat and his team had designed 4 assembly lines each 20 meters with a total number of workers required per
line to be 14 and 1 line manager or the supervisor taking care of the assembly line assigned to him (Exhibit 1
gives the overview of the assembly line and Exhibit 2gives the summary of tasks and planned and actual time
taken per station). Rajat designed the operations of each line to produce 700 laptops per nine hour shift
(including an hours lunch break), with two shifts per day, 26 days per month. The companys goal was to meet
peak monthly demand and wanted to keep the inventory of finished laptops as low as possible. The marketing
team gave the production team a 5 month demand forecast which was also adjusted monthly if need arose
(Exhibit 3). Each assembly line had 2 floaters who were trained in the complete process and who could help
out the line workers with any issues and delays. Apart from that the line also had different type of workers
trained on particular skill sets and these workers could be used interchangeably but only within the type which
they were assigned to. (See Exhibit 4which gives the type of worker and their salaries).
Challenges Faced
Rajat had designed the line such that each station took 40 seconds, but few stations were giving problems and
presently they were able to produce a laptop every 50 seconds. The station where webcam was attached was
a problem which had crept in recently. The vendor had provided a lot of webcams which required additional
rework before it could be installed. Rajat expected this problem to be solved after this lot was over. Since the
motherboard was unique and quite complex, workers were facing issues installing it and connecting it to other
components. (Exhibit 5gives the breakup of the tasks and time taken per task for certain stations).
Page 1
-
8/13/2019 Chanakya Round 1 Case 3
3/5
Case #3 Of Man, Machine & Manufacturing
Additional Information
4 assembly lines Planned output was 700 laptops per line per line per shift 2 shifts of 9 hours each with a 1 hour lunch break Presently taking 50 seconds to assemble one laptop Overtime labor cost is Rs. 75 per hour per worker Cost of overtime for floater is Rs. 120 per hour Workers of particular type can stay and work within those stations though interchangeably Cost of training a new worker is Rs. 1000 Cost of holding inventory Rs. 1500/laptop.
The Dilemma
While pondering over how to meet the demand set by the marketing team Rajat was thinking about few ideas:
Should he hire new workers, add one more assembly line to the existing 4 lines, add a floater who could help
increase the number of laptops per line, talk to the management for maintaining inventory for meetingdemand or increase the shift time such that workers are made to work over time.
Rajat has hired ATK Consulting firm to solve his dilemma. As a consultant you have to come up with a most
efficient and a cost effective solution keeping in mind the constraints of the organization. Help Rajat solve his
dilemma.
Page 2
-
8/13/2019 Chanakya Round 1 Case 3
4/5
Case #3 Of Man, Machine & Manufacturing
Exhibits
Exhibit 1
Exhibit 2
Station Summary of operations
Planned
Time(Seconds)
Workers
perstation
Actual
Time(seconds)
Type of
Worker
Actual
Workers
1
Put all the components required on
conveyor belt and look out for defects if
any
40 1 40 L1 1.5
2Attaching Web cam into cover assembly
and preparing the laptop for next station40 1 50 L2 1.5
3Connect LCD Cable and install LCD display
panel40 2 38 L3 2
4Install and secure motherboard onto the
base40 1 50 L3 1
5Install and screw in the hard disk and
connect it to mother board40 2 41 L3 2
6Install microphone to base assembly and
connect it to mother board40 1 50 L3 1
7Install speaker holders and speakers and
connect speaker cable to sound card40 2 38 L4 2.25
8Connect battery and clock battery; install
wireless card to mother board40 1 42 L4 1.5
9 Install touchpad, keyboard support plate 40 2 41 L5 2.25
10 Tighten the srews; install connectorprotective flap and battery pack
40 1 40 L5 1
Total assembly line workers per line 14
Supervisors per line 1
Floaters per line 2
Page 3
-
8/13/2019 Chanakya Round 1 Case 3
5/5
Case #3 Of Man, Machine & Manufacturing
Exhibit 3: Monthly Demand Forecast
Exhibit 4:
Exhibit 5: Monthly Demand Forecast
Station Summary of operations
Planned
Time
(Seconds)
Workers
per
station
Actual
Time
(seconds)
Type of
Worker
3
1. Connect LCD cable to display
2. Install LCD display panel in cover assembly
3. Put screw for next station in tray
15
20
5
2
14
19
5
L3
4
1. Install motherboard onto base assembly
2. Secure mother board with screws
3. Place screws for next station in the tray
15
18
7
1
25
18
7
L3
5
1. Install and screw in solid state hard drive
2. Connect harddrive cable to mother board
3. Place insulator sheet on hard drive
4. Put screws in tray for next station
20
11
4
5
2
20
11
5
5
L3
6
1. Screw in microphone to base assembly
2. Connect microphone to motherboard
3. Install support frame on base
4. Put screws for next station
13
9
13
5
1
20
12
13
5
L3
136000
120000
130000
120000
135000
110000
115000
120000
125000
130000
135000
140000
January February March April May
Type of Worker Wage per Day (Rs.)
L1 450
L2 450
L3 450
L4 450
L5 450
Supervisor 900
Floater 750
Page 4
Chanakya, IIM Indore