DSO tests Chamonix: 1 shift 2pm - 10pm 2 shifts (A/N) 7/7 days 3 shifts 7/7 days 1 2 3 Machine check-out

Transcript of Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... –...

Page 1: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

DSO tests

Chamonix:1 shift

2pm - 10pm

2 shifts (A/N)7/7 days

3 shifts7/7 days

1

2

3

Machine check-out

Page 2: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out• Interlocks

• BIS test– Extraction Beam 1 (sps side)– Final global tests– Vacuum interlock test (Alick, Gael)– Experiments injection and beam dump signals

• PIC – BIS connection – Need PC’s no interlock (pc’s Operational)

• FMCM – Need tests if we 4 TeV

• WIC TL’s and LHC – WIC – BIS connection

• SMP tests– System Test 31 January– Machine check out tests

» BCT,BPF,BETS,MTG,SIS» 4/5 5/6 6/7 7/8 closed

Page 3: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out

• RF– 20 Jan Start warm commissioning of power equipment with waveguide short-circuits in– 27 Jan Short-circuits out– 28 Jan Start powering of cavities & conditioning (needs about 1 week with no access in IP4 )– 4 Feb Start Low-Level RF setting-up (will need the remaining 2.5 weeks with no access in IP4)

– access may be needed during this period, but accesses should be grouped so as to take the minimum possible time.

• Co– Timing test ongoing.– Lsa change ongoing.

• Incorporation test– Partitioning – No Trims and Generation– Start Time: Friday (14 January) evening– Estimated End Time: Monday (17 January) morning– Schema changes and LSA release – LSA not available

Start Time: Monday (17 January) 14:00Estimated End Time: Wednesday (19 January) evening

3

Page 4: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out

• BI• TI2 BPMs:

– More detectors at start and end– Dual-plane for all pickups

• LHC BLMs:– Changes to capture mode

• Number of data values varies• LHC BPMs:

– Changes to capture mode• Data reduction reduced values to turn-by-turn except for some systems related to

injection (LSS2/LSS8) for IQC– Dedicated BPMs for bunch-by-bunch to be defined– Changes to UDP structure to include synchronous orbit mode (OFC)– Implementation of bunch-by-bunch orbits

• Tests– Transfer line Instrumentation

• BTV Movement • Image • Logging

4

Page 5: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out

• Vacuum– Ring by 14 FEB.– Alice 31 Jan– Atlas 16 Feb– CMS 7 Feb– LHC-B 15 Feb

• Electricity– EN EL network is fully operational 8 FEB

• Cooling– No change Deleval

5

Page 6: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out

• Collimators • Software change to improve protection

– Add gap limit as a function of Beta*– New interlock logic for Ring Injection protection (TDI ,TCLI)– New strategy for Injection collimator motion inhibit when limits are reached.

• System Test all calibration LVDT interlock positions sensor (Masi)– Need to repeat essentially all MPS check

• Global Collimator test– Ramp interlock – Sequence test

• Tests all collimators new software– Conditions:

» BIC Collimators operational » Energy & Beta available in timing (real or simulated)

6

Page 7: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Injection/extraction recommissioning

W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, J.Uythoven

Page 8: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

System changes 2010/2011

• Operational, procedural and SW changes• HW changes and activities • Electronics and control changes

Page 9: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Operational, procedure and SW changes

• Update LBDS for 4 TeV (tracking tables, voltage clamps)– If 4 TeV table and voltage updated with relatives tests associated. Etienne– If 4 TeV later in the year then time foreseen for test.

• New IQC functionality (LHCb BCM, TL trajectories, synchro error...)– System test Conditions MTG injection, SPS cycling Verena/Lene

• New IQC latching philosophy– Ongoing Lene/Delphine

• Implement operational settings for MKIs– Setting for MKI Brennan/Etienne– During setting up

• Tighten energy interlocks for TCDIs/TDIs/TCLIs– Setting up with Beam Brennan

• New XPOC data modules and BLM ratios– New module to compare TCDQ – Beam position BPMS – System Test Jan/Nicolas Magnin

Page 10: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Operational, procedure and SW changes

• BLM changes (to collate with BLM team)– System Test Brennan/ BLM team

• Shielding installed for TCDIs and TDIs– TCDIs done– TDIs not for start up

• New injection procedure and ppm requests for intermediate beam– Verena

• Additional interlocking of injection oscillations– Verena/ Lene

• TCDI automatic setting up– 2 priority not critical Brennan

Page 11: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

HW changes and activities

• MKD • Generator consolidation (to run up to 4 TeV), as we do during each small

tech. stop - exchange of 3 MKD generators– Done and tested (Jan/Senaj)

• Normal maintenance without any impact on LHC operation (equipment inspection, measurement of magnet contact resistance, change of one or two terminating resistors on MKI, etc.)

– Ongoing (Jan/Senaj)

• New TI2 BPMs and dual-plane acquisition for all– Check logging

Page 12: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

HW changes and activities

• MKI• MKI2 replacement (magnet B at point 2)

– Done Mike Barnes– Conditioning delayed due to vacuum activities (coils for electron cloud)– Conditioning expected to be finished 24/1– Careful PFN investigation on MKI2 – Commissioning start 17/2 – Access needed in UA23

• MKI 8– No change – Vacuum coils installation ongoing– Conditioning start 1/2

Page 13: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Electronics and controls activities• ALL systems

– Software upgrade Etienne• Ongoing >> When finished test from sequencer and application program (Arm, Inj Dump,

Circulate & Dump)• BIS ok Timing ok

– General maintenance Etienne• Ongoing

• LBDS– New dump triggering IPOC– New TSU IPOC

• Ongoing test after with conditions. Not critical for start up– TSU firmware upgrade (audit follow-up)

• Done test needed Etienne– Additional MKD internal current diagnostic

• Ongoing – Update BEM firmware to correct any bus communication errors between

BETS and PLC• Done ok

– New thermal working point for MKD generator cooling system. Validation required.

• Ongoing system test after.

Page 14: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Electronics and controls activities• MKI

– SbS extension (PFN secondary voltages + MAIN switch currents)• Ongoing system test after.

– Increase sensitivity of fast interlock• Will be done system test after.

– Implement additional diagnostic for KISS monitoring / failure diagnostic• Done Update By (G.H. &Lene )

– Fine synchronisation improvements (reject noise captured from CIBO)• Ongoing system test after. (Tentative improvement not sure will completely be

solved.)– Resynchronisation of AGK

• Needed machine check out condition ( timing synchro, prepulse BIS ok and all remote control 5 hrs.)

– Deployment of new KiTS software version with additional diagnostics for timing• Done update by G.H

Page 15: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Recommissioning• Specific tests of all modifications

– Will be done as far as possible in system tests– Integration tests involving ABT systems:

• Timing system upgrade: GPS down: no injections; injection sequencer, injection cleaning + soft interlocking strategy, ...

• Some need fully-connected systems (BIC loops, access, DCCTs, timing, pre-pulse, RF): estimate 2-3 days of connected checkout needed

Page 16: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out • Sequencer

– DATABASE– 1. New simplified database scheme that allows– 1.1. simplification of the sequence components definition ==> easy to maintain since the number

of components is greatly reduced;– 1.2. new functionality:– 1.2.1. inheriting mechanism;– 1.2.2. possibility to restrict the execution of sequence components to a given set of beam modes;– 1.2.3. who, why, when the sequence was modified;– 2. The sequences/tasks will be only accessible in the development database by the

ROLE lhcSeqEditor and tested using the development server of the sequencer. Once they work, they will be copied to the PRO database for normal execution. Therefore the PRO database won't be accessible directly anymore. A roll back mechanism will be supported to allow to roll back to the previous version in case of problems.

– 3. All the operational sequences will be moved to the new schema, the unused tasks/sequences will be deleted.

– The new database schema is already in the development DB and has been provided by CO/DM who is developing an API to easy the access to the data (no more direct queries). The API will be ready by end of January and then the Sequence Editor and the Sequencer Core will start implementation. This development will be done in the development servers and will be deployed as PRO once tested and validated. Most likely the full database functionality will be implemented in the sequencer core in steps. As first step the core will be updated to use the new schema; as a second step the inheriting mechanism will be implemented.

– SEQUENCE EDITOR With the new database schema, a new editor will be developed, more user friendly and with more functionality.

– NOMINAL SEQUENCE(S) Will be reviewed and re-structured to map the way we operate the machine.

– Components of the type CHECK-SET, where the SET is implemented as “on error task” will be substituted by ENSURE tasks where appropriate.

16

Page 17: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

planning

Machine check-out

Page 18: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

planning

Machine check-out

Page 19: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

BT test planning

Machine check-out

Page 20: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

planning

Machine check-out

Page 21: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

planning

Machine check-out

Page 22: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out page

• https://espace.cern.ch/LHCMachineCheckout/default.aspx

Page 23: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out

Ring closed

Driving magnets based on files for new Beta 90 meterFull LBDS interlock testsInjection system tests (MKI,TDI)SIS interlock RF power and frequency interlock BLM ,TL, Collimator,

.

Page 24: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out

• Access system – Lass software modification ready 31 January

24

HWCAim to be finished around 12-13/02

LHC DSO tests 12/13 FEB

Page 25: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Machine check out

• Injectors ready– Linac2 → 04/02 ;– PSB → 09/02 ;– PS et TT2 → 11/02 ;– SPS → 14/02

– SPS• 7-9 FEB DSO Test

• Extraction &Transfer Lines powering tests– RBI 81607 test– Powering – Heat run

25

Page 26: Chamonix: 1 - espace.cern.ch · Chamonix: 1 shift . 2pm - 10pm. 2 shifts (A/N) 7/7 days. ... – Setting for MKI Brennan/Etienne – During setting up • Tighten energy interlocks

Recommissioning• Specific tests of all modifications

– Will be done as far as possible in system tests– Integration tests involving ABT systems:

• Timing system upgrade: GPS down: no injections; injection sequencer, injection cleaning + soft interlocking strategy, ...

• Some need fully-connected systems (BIC loops, access, DCCTs, timing, pre-pulse, RF): estimate 2-3 days of connected checkout needed

• System beam tests– Subset of full 2010 checks: synchronisation, basic aperture checks, system

functionality tests, interlocking checks, steering, protection device setup and validation, asynch dumps, ...

– Full tests needed in areas where systems have been modified (MKI, MKD, TSU, ...)

– Specific tests also for 4 TeV (BETS, protection)– Abort/injection gap commissioning and full operational deployment– Needs full breakdown, but expect that this is of the order of 12-14 shifts with

beam – to be confirmed before fixing this number• Follow-up of intensity increase

– Standard tests as beam intensity increases