Challenges with moving to Higher Level of RE Penetration ...devpolicy.org/Events/2016/Pacific...
Transcript of Challenges with moving to Higher Level of RE Penetration ...devpolicy.org/Events/2016/Pacific...
Mafalu Lotolua
2016 Pacific Update Conference
18th -19th July 2016, Suva, FIJI
Challenges with moving to Higher Level of RE Penetration in Tuvalu
RE Target for Power Generation – 100% by 2020
2-Stated Goals• To generate electricity with 100% renewable energy by 2020 (revised 2025), and• To increase energy efficiency on Funafuti (main island) by 30%
100% Target
Guided by the RE&EE Master Plan and isdirectly linked to the:
- Tuvalu National SustainableDevelopment Plan (Te Kakeega III),
- Tuvalu National Energy Policy 2009,
- Climate Change Policy (Te Kaniva) and
Master Plan has identified the mostpossible proven technologies for Tuvalu tomeet its 100% target.
Implementation Strategies
60 – 95% - Solar
0 – 40% - Wind
5% - Biodiesel
30% - Energy Efficiency
• Cannot achieve 100% renewable energy with ONE Renewable Energy source and needto include other potential PROVEN and MATURED technology, and
• Energy Efficiency is also important to avoid additional renewable energy generation.
IS
Tuvalu Electricity Corporation(TEC) – Diesel Replacement
Fully state owned Enterprise(SOE)responsible for managing andoperating diesel power generatorsand grid-connected systems on the 8-islands of Tuvalu
3xdiesel generators of totsl176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 208kW
3xdiesel generators of total 1800kW
3xdiesel generators of total144kW
Battery lighting
RE Space in Tuvalu
195kW PV mini-grid – 90% (2015)
232kW PV mini-grid – 90% (2015) 205kW PV mini-grid
– 90% (2015)
410kW PV mini-grid - 90% (2015)
60kW PV mini-grid – 50%Additional – 10kW (2015)
77kW PV mini-grid – 50%Additional – 10kW (2015)
45kW PV mini-grid – 50% (2015)
170kW PV grid-connected (2015)
Stand Alone Home System (SHS) (2016) 925kW PV/200kW wind/1MWh battery
storage (2017/2018)
Amatuku – 8kW PV mini-grid – 2% (2016)
NZ Funded
EU Funded
Italy Funded
UAE Funded
Japan Funded
Finland Funded
World Bank Funded
Funafala - Stand Alone Home System (SHS) (2016)
MSS – 46kW PV mini-grid – 60% (2009)
500kW PV grid-connected (2015)
66/20kW PV grid-connected (2014/2008)
Main Island
RE Space in Tuvalu (con’t)No Island Technology PV Capacity
(kW)Batt. AH % RE
1 Funafuti Solar PV grid-connected 756 Nil 17
2 Vaitupu, Niutao, Nanumaga and Nanumea
Solar PV mini-grid 1,042 (410,232,205,
195)
159,000 (60,000,36,000,33,000,30,000)
90
3 Nukulaelae, Nukufetauand Nui
Solar PV mini-grid 182(45,77,60)
46,020(12,228,18,432,
15,360)
50
4 Amatuku, TMTI Solar PV mini-grid 8 2,000 2
5 Niulakita and Funafala Standalone Home System (SHS)
100
6 Motufoua Solar PV mini-grid 46 12,000 60
• Funafuti – 756kWp installed capacity(Controlled (SMA Fuel Saver)– 436kWp and Uncontrolled – 320kWp)
• Outer islands – 1,270kWp PV installed capacity
Solar Growth in Tuvalu
0
500
1000
1500
2000
2500
3000
3500
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
kW Deployed
Source – TEC
Energy Efficiency Portfolio
No Activity Progress DevelopmentPartners
1 Energy Efficiency Act Endorsed by Parliament in April’16
Australian Govt. through SPC
2 EE Loan Scheme Launched end of June’16 GEF through IUCN
3 RE&EE Demo Fale Near Completion SIDS Dock through UNDP
4 Prepayment Meters Finalizing Specifications World Bank
5 Window Tinting for Govt. Main Office building
Yet to start World Bank
6 Replacing of container refeers with Cool Rooms
Yet to start World Bank
Overall Share of Renewable Energy
IMPLEMENTATION STRATEGIES
MASTER PLAN END2014
END 2015/2016
END2017/2018
Solar PV : 60 – 95% 4% 29% 43%
Wind : 0-40% 0 0 2%
Biodiesel : 5% 0 0 0
Energy Efficiency : 30% 0 0 0
Road to 100% RE
• KEMA analysis stated that at least one diesel generator need to run at 50% output at all time to provide Voltage and Frequency and to replace the sudden loss of renewable energy generation.
• TEC has engaged KEMA again to carry out a Renewable Resource Impact Study to identify the various technical issues involved in connecting more PV and wind generation facilities into TEC power system, and also the
• Economic evaluation for future growth of renewable resources with energy storage in TEC system
% RE Level
Without Storage
Storage (kW/kWh)
PV Capacity (kW)
OUTER-ISLANDS
100% • More PV’s and storage for 3-islands and also alternative fuel for generators in all islands
FUNAFUTI
50% 3,200
200/600 2,800
75% 10,000
85% 950/5,500 4,900Source – DNV KEMA report 2013
Challenges with moving to High Level of PV/Wind-Funafuti Have reached maximum level of penetration
and further increase in RE will raises thepotential interconnection and challengesassociated with system safety, reliability andimbalances and demand
Small overall system size (and there are nointerconnections to other systems)
Thermal ratings of the conductors
Limited ability of diesel generators to respondto sudden changes in renewable generationoutput
The loss of one operating generators can oftenresult in fairly wide swings in system voltageand frequency
Limited RE resources
Limited land space
Lack of finance and highly depended onpartners/ donor community
Technical Solutions
Using of storage to increase the PV/windpenetration and also helps in absorbingintermittent output from renewable resourcesand sustaining energy supply during the timewhen renewable resources not available.
Limit the maximum output of solar/windgeneration so that maximum limit is notexceeded during brief periods when there arewind gusts or the shine fully
Smart-Grid
Using of residential roof-top or other landspace such as pond, lagoon
Some Innovative ways to install PV modules
In front of the Power Station
Funafuti Island Natural bond - potential for floating PV’s system.
Space can be used for parking/recreation
Some Innovative ways to install PV modules(con’t)
Power station Site for PV
Nukufetau Island
Asset Management
Must have sufficient funding
Need qualified staff to look after the system
Islands are separated by sea and need goodinternet connectivity for daily remotemonitoring of the system, and
Need the on-going support of the contractor
• Good Asset Management prolongs the life cycle of an asset
Lessons Learnt
Grid Stability/Renewable Resource Impact Study is a MUST
Donor coordination in country
Establish coordinating committee between the donors and the recipient
To involve the inverter manufacturer to design an appropriate system not to affect thegrid
Ensure to know the process how to claim failed equipment, mainly the majorcomponents
Innovative ways to install panels – not to waste land space
BAU Vs RE&EE
-
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
2012 2014 2016 2018 2020 2022
BAU
REEE Master Plan
• BAU is steadily increasing and with the installation of RE, the dieselconsumption tend to decrease.
• Diesel Saved from January – June, 2016 (6months period) –~12% as comparedto the same period of 2015.
Lit
ers
Thank You