CGS Cross Canada Presentation Spring Tour 2013 and De… · Syncrude Geotechnical Engineering...
Transcript of CGS Cross Canada Presentation Spring Tour 2013 and De… · Syncrude Geotechnical Engineering...
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
CGS Cross Canada Presentation Spring Tour 2013
Compaction & Design Tips for Construction of Dam Fills Year‐Round at rates up to 25 Million m3/year
Bob Cameron, B.A.Sc., M.A.Sc., P. Eng.Principal Geotechnical Engineer, Syncrude Canada Ltd.
Prepared with assistance from Ana Pastolero, E.I.T.
Tailings Storage
Plant Site
SouthWest Dam•Construction: 1996 to 2009 (13 years)•Maximum Rate: 25 Mm3/year•114 million m3 of engineered fill and 37 million m3 of existing uncontrolled fill•Dimensions: Length‐2.5km, Height‐75m
Highway #63 Berm•Construction: 1992 to 1994 (2.5 years)•Maximum Rate: 17 Mm3/year•42 million m3 of engineered fill and 40 million m3 of existing uncontrolled fill•Dimensions: Length‐2.5km, Height‐63m
2
Future Tailings Storage
Plant Site
NorthSouth Dyke•Construction: 2007 to 2012 (5 years)•Maximum Rate: 15 Mm3/year•76 million m3 of engineered fill •Dimensions: Length‐2.7km, Height‐37m
EastWest Dyke•Construction: 2007 to 2017 (10 years)•Maximum Rate: needs to be 50 Mm3/year•180 million m3 of engineered fill •Dimensions: Length‐4km, Height‐61m
3
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Presentation IntentTo describe the iterative processes involved with balancing the Design of Earth Dam Structures with year‐round Construction
rates of up to 25 Mm3/year due to Business Needs.
(No tailings sand dykes will be discussed in this presentation)
2) DesignDam Geometries Dam Footprint
Abutment ConsiderationsMaterial Parameters
4) Quality Control / Quality AssuranceMonitoring Processes
Regulatory DocumentationDesign Tolerances
Construction SpecificationsConfirmatory Testing
Geotechnical Review Board
3) Year‐Round ConstructionSummer ConstructionWinter Construction
Material Selection / AvailableClean‐up Requirements
Settlement Considerations
5) Testing / AnalysisField testing to confirm Design Assumptions
Lab testing to confirm Field ValuesAnalysis of Material Parameters for Dam
Geometries to meet Design Intent
1) Business NeedsTime Sensitive Tailings ManagementOverburden Material Availability
Large Scale Mining Operations Equipment
4
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Business NeedDesign and Construct large fill volume, time‐critical tailings retaining structures considering:
‐ site conditions (e.g. foundation treatment / base preparations, and abutment considerations)
and
‐ minable ore requirements (e.g. dig limits)
~80m high Mining Pitwall Dam AbutmentDam Foundation Treatment ‐ Base of Feed In‐Situ 2H:1V sloping of the Dam Abutment
5Foundation and Abutment Treatment
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Foundation Treatment/Base PreparationBase Preparation is not as elaborate as most industry‐standard dams since SCL dams are generally designed: •To be very wide quasi‐homogenous earthen dams with no grout curtains or grouted abutments
•To have relatively short operational lives (~ 10 years)•With multiple lines of defense:
– With large (100s of meters) external downstream or upstream sand filters
– With large (15 to 20 meters) internal filters
– Or other 2nd lines of defense
Foundation Treatment 6
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Foundation Treatment/Base PreparationBase Preparation generally involves:
•De‐watering / De‐slopping / De‐icing to ensure the design pore pressure parameters are met• Removal of softened pond muds and softened paleosol/limestone which could cause
instability due to pore water pressure above design•Further construction considerations for:– management of expanded rich feed which could cause low density zones by:
• removal of all rich feed• bulk cleaning the softest rich feed away with re‐cleaning the foundation in front of the
advancing 2 to 3m of lifts to prevent gas exsolution• elaborate gravel weighting with venting pipes with later grouting for civil foundation
work (e.g. manhole bases) • NOTE:mud slabs do not work
– evaluation of limestone fractures/fissures or watersands which may require design considerations such as:
• upstream engineered fills to seal• generous widths
– existing dump fills:• incorporated into the design when applicable
Foundation Treatment 7
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Foundation Treatment /Base Preparation QA/QC
Geotechnical Construction Monitor approves the dam foundation quality
Foundation Treatment QA/QC
Geotechnical Construction Monitor documents:•GPS coordinates of the approved area•Elevation of the approved base•Material type at the approved base (in‐situ or fill, type of fill, geology of in‐situ)•Material type of first constructed lift•Date of approval•Monitor approving•Pictures•Summary Base Preparation drawing
8
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Pit Wall Abutment Considerations• Low stress zones in the abutment due to movement along In‐Situ pond muds or rich
feed addressed by:• Delayed & Segmental mining with staged construction of compacted lifts
• Continuous In‐Situ units with preferential seepage paths and/or continuous joint issues addressed by:
• Flaring out compacted fills to increase the seepage path length and/or blind off the permeable units
• Key‐in In‐Situ sloping of the abutment tie‐in to change joint seepage paths • Differential settlement of In‐situ units vs. engineered fills
• Abutment fill geometry designed to be overloaded and so taking into consideration settlement parameters
EW Dyke
NS Dyke
Mining Pitwall
Abutment
Mining Pitwall
Abutment
Abutment Treatment
2km
9
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Pit Wall Abutment Considerations
Abutment Treatment
Abutment In‐situ sloping key‐in of mining pitwall for a longer seepage path length
SI 110071
10
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Pit Wall Abutment Considerations
Abutment Treatment
KccKcb
KcaKcw
F15
F9WF21F10F12
F1211W
F12F11F7
F6
F11F25F63F61F63
41WF34F32F33
HO1 0.0
32.8
65.6
98.4
131.2
164.0
196.9
229.7
262.5
-1312 -1148 -984 -820 -656 -492 -328 -164 0 164 328 492 656 820 984 1148 13120
10
20
30
40
50
60
70
80-40 -35 -30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30 35 40
Dept
h (ft
)
Incremental Displacement From Set 1 (August 16, 2011) in mm
Dept
h (m
)
Incremental Displacement From Set 1 (August 16, 2011) in SI units
SI VP 110071 - A EW Dyke 1 East Abutment SI - Incremental Displacement52938.84N, 48052.56E, 296.5m Elevation A(-ve) Azimuth = 262o
16-Aug-1123-Aug-1131-Aug-116-Sep-1113-Sep-1114-Sep-1115-Sep-1116-Sep-1118-Sep-1121-Sep-1124-Sep-1127-Sep-1130-Sep-113-Oct-117-Oct-119-Oct-1112-Oct-1115-Oct-1118-Oct-1124-Oct-1127-Oct-1130-Oct-113-Nov-116-Nov-119-Nov-1112-Nov-1115-Nov-1120-Nov-1123-Nov-1126-Nov-111-Dec-118-Dec-1120-Dec-113-Jan-1226-Jan-12
Downslope Upslope
286.5m
226.5m
236.5m
246.5m
256.5m
266.5m
276.5m
displacement & v elocityv elocity & acceleration
lowmedhighconcern lev el: highest
Marine Oil Sands
Estuarine Oil Sands
Devonian
Clearwater
Fluvial
3 to
7.5
mm
7.5
to 1
5mm
15 to
18m
m
(> 1
8mm
)
100
to 2
50 U
nits
250
to 5
00 U
nits
500
to 6
00 U
nits
(>60
0) U
nits
0 to
100
Uni
ts0
to 3
mm
11
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future Abutment Treatment
Pit Wall Abutment Considerations
KccKcb
KcaKcw
F15
F9WF21F10F12
F1211W
F12F11F7
F6
F11F25F63F61F63
41WF34F32F33
HO1 0.0
32.8
65.6
98.4
131.2
164.0
196.9
229.7
262.5
-1804 -1640 -1476 -1312 -1148 -984 -820 -656 -492 -328 -164 0 165 329 493 657 821 985 11490
10
20
30
40
50
60
70
80-55 -50 -45 -40 -35 -30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30 35 40
Dept
h (ft
)
Cmulative Displacement From Set 1 (August 16, 2011) in mm
Dept
h (m
)
Culumative Displacement From Set 1 (August 16, 2011) in SI units
SI VP 110071 - A EW Dyke 1 East Abutment SI - Cumulative Displacement52938.84N, 48052.56E, 296.5m Elevation A(-ve) Azimuth = 262o
Downslope Upslope
286.5m
226.5m
236.5m
246.5m
256.5m
266.5m
276.5m Marine Oil Sands
Estuarine Oil Sands
Devonian
Clearwater
Fluvial
24mm on Marine at 94.3mfrom mined pitwall face
28.2mm on PM at 231m from mined pitwall toe
Pond Mud slickensides in core
12
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
For construction of large volume dams at rates of 25 Mm3/year:
Foundation treatment involves:•Cleaning the base to meet design intent by removal of slop and softened In‐situ units (critical areas reserved for premium construction conditions – summer)•Management of low density zones (e.g. rich feed)•Design against preferential seepage paths (e.g. limestone fractures/fissures, watersands) with generous widths or sealing with upstream engineered fills •QA/QC Documentation
Foundation and Abutment Treatment
Summary ‐ Foundation and Abutment Treatment
Abutment treatment involves:•Designing for long seepage path lengths with In‐situ cut‐only key‐ins (critical area reserved for premium construction conditions – summer)•Designing for differential settlement of In‐situ units vs. engineered fills•Management of low stress zones due to movement along weak units (e.g. pond muds) and gas exsolution of rich feed oil sand
In‐situ sloping key‐in of mining pitwall for improved abutment tie‐in
13
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Business NeedDesign and Construct large fill volume, time‐critical tailings retaining structures by using readily available overburden materials above ore.
Overburden Materials for Engineered Fill
Oil Sand Ore
Materials ‐ Availability 14
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Mining Construction Material
Materials ‐ Selection
The intent is to split the pitwall benches such that the mined material for engineered fill is of similar SPD, ductility, and compatibility.
15
*
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future Materials ‐ Selection
Possible Contamination At the Shovel Face
Base of Feed
Oil Sand Ore
Ponded Water
Material for Engineered
Fill
Large Icicles
Regrowth Brush
Frozen Face
Frozen Cap
Padded non‐spec material
Berm of non‐spec material
Slop filled ditch
Siltstones
16
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Possible Contamination At the Shovel Face
Materials ‐ Selection
White 1‐2mm thick vein ice is a sign of frozen ground.
Black micro‐thin discontinuousice <1mm is a sign of frozen ground.
Icicles on the face is unacceptable and must be removed.
17
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
QA/QC: Checking for Frost in Shovel Faces
Materials – Selection QA/QC
Mining fill material during winter that meets the design intent of the structure is required when constructing at rates of 25Mm3/year.
Some checks:•A ledge under the shovel face (an "overhang” of frozen material) is a good indication of frost thickness•Comparing the frozen material above with the non‐frozen material below if similar materials•Asking the shovel operator if they "feel" it as they dig•Looking for black ice (very thin film) or ice crystals/flakes.
• These melt (sublimate) very fast so it is important to look at a fresh face
•Feeling how cold the material is ‐ The Pain Test•Using thermometers
• Salinity can affect readings
A mining shovel pit in winter
• Taking bag samples from the fresh face and melting on a truck heater/defrosting• Fresh test‐pitting above the shovel with a backhoe to determine frost depth and catching ice crystals before sublimation
18
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Material Tolerances for 25 Mm3/year Construction
Allowable material tolerances at the borrow source for compacted 1m lifts (SC‐SM)
Materials ‐ Selection
Allowable material tolerances at the borrow source for compacted 0.75m lifts (CH)
• To deliver on such high construction rates, a zero tolerance method concerning engineered fill is not feasible.
• The tolerances may need review with respect to critical areas in the dam design.• The dam designs use generous widths to accommodate non‐premium material
conditions.
19
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Material Selection – QA/QC ConsiderationsGeotechnical Construction Monitors activities:
• Inspection at the shovel face is required every 2 to 6 hours due to the changing geology and changing site conditions• Considerations during summer – safety berms, regrowth brush, etc.• Considerations during winter – frozen soil, etc.
• Providing input to the mining of the face so the mined material meets the design intent at the structure such as:• Utilizing the engineered fill tolerance tables• Full face raking with electric shovels for blending the material• Top and bottom cuts to selectively mine with hydraulic shovels• Etc.
• Documentation of material quality at the borrow source highlight:• What is seen (e.g. shovel mining a 10m high face with no ponded water on the bench
above)
• The quality (e.g. good quality CH for compacted 0.75m lifts in face)
• Where the fills are going (e.g. engineered fill going to the appropriate structure)
Materials – Selection QA/QC 20
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Compacted 1m Lifts (SC‐SM)
Materials – Properties and Selection
2010 Data
21
35 of 43 samples are non‐plastic
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
2011 DataEast West Dyke 1650 Interior Shell
3/4m lift Mid-Bench Kc Clays (Kcc)"1650 kg/m
3" Material - Proctor Data (April 12, 2011 to Nov 7, 2011)
Moisture Content (%)0 5 10 15 20 25 30 35
Dry
Den
sity
(kg/
m3 )
1400
1500
1600
1700
1800
1900
2000
2100
2200
% C
ompa
ctio
n
90
100
110
120
130
Zero Air Void LineGs=2.75 S=1.00
Troxler Data (Kcc) n=612Troxler Data (Kcc) - Moisture Corrected (+4.9%)Standard Proctor - (Kcc) n=11Avg SPDD & OMCAvg Troxler Data - Moisture Corrected
Syncrude Canada Ltd. Geotechnical Engineering Geotech Lab Prepared By : Kent Wong Date : March 26, 2012
Average CorrectedField Dry Density1718 kg/m3 (104.1%)
Avg O
pt Mo
istur
e : 20
.5%
Avg Std Proctor : 1610 kg/m3, n=11
Avg A
ll Lab
Nat
Moist
ure :
16.2%
4.3%
Dry
of Op
timum
115% SPDD = 1897 kg/m3
Spec > 105% ( 1732 kg/m3)
100% SPDD = 1650 kg/m3 (Oct 2008)
Average Correction:Troxler Sample Natural Lab Moisture Content - Troxler Measured Field Moisture Content = 4.9%
% Corrected Field SPDD>115% : 1.6%+
+(>5% Review)% Corrected Field SPDD<105% : 55.9%% Corrected Field SPDD<100% : 13.9%* *(10% or less allowable)
Materials – Properties and Selection 22
Compacted 0.75m Lifts –Kcc (CH)
2011 Data
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future Materials – Properties and Selection 23
Compacted 0.75m Lifts –Kca/Kcb (CH)
2011 Data
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
1300
1400
1500
1600
1700
1800
1900
10 15 20 25 30
Moisture Content (%)
07289 Mod.07289 Std09620 Mod.21767 Mod.21771 Mod.21771 Std.21772 Mod.22205 Mod.22205 Std.22460 Std.Field DataS i 12
Air Content 5%
10%
0%
Mid‐Bench Kc Clays (CH) – Lab and Field DataField Testing Intent:•To determine what Standard Proctor Dry Density (SPD) value to use for the well dry‐of‐optimum high plastic dispersive clays
Findings:• Modified Standard Proctor
Densities (MSPD) = 1.15xSPD for high plastic clays= 1.08xSPD for sandy fill
• 105% SPD was chosen because:• The chunky, blocky fill had to
be broken down• To address the dispersive
nature of the material• Troxler/Nuclear densiometer
average field fluid correction of approximately 5%
• Material is dry of optimum
Field and Lab Testing – Placement and Compaction
SPDD
24
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Loose 2m or 5m Lifts – Pl, Kc‐clays, Kcw, Marine Oilsand
Fills used for buttressing stability support rather than seepage control.
Density controlled in the field through placement specifications.
Considerations on settlement further discussed in this presentation.
Materials – Properties and Semi‐Selection 25
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Engineered Fills
Materials – Properties 26
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Testing/Analysis for Design/Construction
Materials – Lab and Field Testing 27
Many of the papers can be found in the 38th, 48th, and 54th Canadian Geotechnical Conference publications (Canadian Geotechnical Society)
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Testing/Analysis for Design/Construction
Materials – Lab and Field Testing 28
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Summary – Material Selection
Material Selection
For construction of large volume dams at rates of 25 Mm3/year:
Mine for engineered fills of similar density, ductility, and compatibility:•Compacted 1m lifts of clayey sand – silty sand (SC‐SM) for seepage control•Compacted 0.75m lifts of high plastic clay (CH) for seepage control•Loose, semi‐select 5m lifts (moving towards 2m lifts) of readily available mine overburden fills for buttressing support•Still confirm that the fill is suitable
• Not too wet/dry/sandy/clayey/ chunky/indurated
Robust dam design to accommodate reasonable material tolerance.•Loose snow, Frozen soil, Siltstones
Knowledgeable Geotechnical Construction monitors, Dam Design Engineers, and Operations Representatives working together to optimize mining especially during challenging winter conditions.
29
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Business NeedDesign and Construct large fill volume, time‐critical tailings retaining structures by using readily available large scale mining equipment.
Dozer cleaning the lift
High plastic chunky clay fills (CH)
Grader cleaning in front of the advancing lift
Placement and Compaction 30
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Highway Berm – Single Thick Lift Test Strips
Field Testing Intent:•To determine the possibilities with constructing lifts ranging from 1.0m to 2.5m thick with mostly clayey sand and silty sand based fills.•Further testing (e.g. seepage test pits, slug tests) discussed later
Field Testing – Material Selection and Placement and Compaction
Answer:
31
Answer: To a depth of 1.0mand 2 passes with a D11 dozer or
equivalent to spread the lift
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future Field Testing – Placement and Compaction
Compaction Equipment – Haul Trucks
Compacted lift with almost no rut and roll
240T haul truck
Field Testing Intent:•To determine what truck type worked best for the compaction performance required•Rut and Roll is useful for self‐proofing bad fills out but is not useful for monitoring densityFindings:
• Mechanical drive works well• DC‐drive truck motors would
burn out• DC‐drive trucks could not get
out of ruts• AC‐drive trucks converted from
DC‐drive trucks could not all drive the 5km/hr required compaction speed for extended periods
• Some truck steering would heat up• It was necessary to have trucks pulled out of the truck‐and‐shovel ore mining fleet or rental
trucks for dedicated uniform compaction activities on the dam structures
32
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Field and Lab Testing Intent:•To determine the possibilities with constructing multiple lifts ranging from 0.75m to 1.5m thick with clayey sand and silty sand fills.•To review achievable density, compaction methodology, lift fabric quality, determine the impact of allowable defects, and measure hydraulic conductivity. •Other tests: field falling head tests in standpipes and slug tests
Permeability and Seepage Studies on 1m Compacted Lifts of Clayey Sand and Silty Sand (SC‐SM)
1.6m wide, 8.0m long, 2.5m deep
1.00E-09
1.00E-08
1.00E-07
1.00E-06
1.00E-05
1.00E-04
90.0 91.0 92.0 93.0 94.0 95.0 96.0 97.0 98.0 99.0 100.0 101.0 102.0 103.0 104.0 105.0
Per
mea
bilit
y (c
m/s
ec)
Percentage of Selected Standard Proctor Density (1800 Kg/m3)
2011 East West Dyke 1 Main Shell Permeability Testing
EW Historic Data
2011 Data
Trend Line
Min
imum
Spe
c fo
r Mai
n Sh
ell D
ensi
ty =
95.
0% S
PD .
Mai
n Sh
ell A
vg F
ield
den
sity
for 2
011
= 1
02.3
% S
PD
5x10-6 cm/sec Main Shell Design
1.0x10-6 cm/sec Main Shell
1.0x10-7 cm/sec Main Shell Design Low End
Permeability vs. % SPDD for Compacted 1m LiftsAt 95% design compaction - k = 5 x 10E-8 cm/sec
At average field density ~102% - k = 1 x 10E-7 cm/secTrend shows higher compaction then lower permeability
Compacted 1m Lifts
Field Testing – Material Selection and Placement and Compaction : Design Consideration – Permeability
Field Testing: Lab Testing:
Answer:
33
Answer: Design Kh
Vertical Kv
Likely Kh
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Kc‐clay Fill Placement
Field Testing Intent:•To determine the possibilities with constructing with high plastic clay fills•To review achievable density, compaction methodology, lift fabric quality, …
Compacted 0.75m Lifts
Chunky, blocky Kc‐clay
D10, D11, or other dozer of equivalent
size
Placement and Compaction
Answer:
34
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Field and Lab Testing Intent:•To determine the possibilities with constructing multiple lifts ranging from 0.75m to 1.5m thick with high plastic clay fills and with clayey sand and silty sand fills.•To review achievable density, compaction methodology, lift fabric quality, measure hydraulic conductivity, …
Permeability and Seepage Studies on dry‐of‐optimum high plastic (CH) Compacted Lifts
-0.2
0
0.2
0.4
0.6
0.8
1
1.2
1.40 6 12 18 24 30 36 42 48
Time since filling (hours)
Test Pit #1 (1.5m lifts)Test Pit #3 (1.0m lifts)Test Pit #4 (1.0m lifts)Test Pit #8 (1.0m lifts)Test Pit #5 (0.75m lifts)Test Pit #6 (0.75m lifts)Test Pit #7 (0.75m lifts)
Field Testing – Material Selection and Placement and Compaction : Design Consideration – Permeability
Answer:Less than or equal
to 0.75m
35
Compacted 0.75m CH lifts shown to swell and plug up if flow is stopped.Designed to be backed with the compacted 1.0m SC‐SM lifts to act as a quasi‐filter.
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Lab Testing Intent:•To determine the potential dispersive qualities of the readily available fill materials when exposed to tailings fluid•Considerations applied to design of future tailings retaining structures
Dispersive vs. Erosive
Design Considerations – Piping 36
Answer:
Kc‐clay fills (CH) shown to be dispersive.
Designed to have a high density in the field and usually backed with the compacted 1.0m SC‐SM lifts to act as a quasi‐filter to any defects in the clays.
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Lab Testing Intent:•To determine potential strength characteristics for varying Kc fills mixed at varying ratios of dry chunks and wet clay•Parameters applied to analysis for future similar structures
Design Considerations – Shear Strength 37
Total Stress:
SLIDING
CROSS‐BEDDED
Effective Stress:Strength Parameters for Kc‐clay (CH) Fill
How will chunky partially saturated dry of optimum fills act?
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Loose 5m thick lifts Placement
Placement and Compaction
Field Testing Intent:•To determine the possibilities with constructing with loose, semi‐select Pl, Kc‐clays, Kcw, Marine Oilsand pushed in 5m thick lifts used for stability support/buttressing•To review achievable density, compaction methodology, and lift fabric quality•Design: used to support the compacted engineered lifts when the foundation consists of weak In‐situ units such as pond muds (construction optimization: reduces costs)
Haul truck dumping semi‐select fill Dozer pushing a 5m lift
38
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Field and Lab Testing Intent:•Loose 5m lifts are not compaction tested during construction•The chunky fabric observed from 2 to 5m provides evidence towards dropping the lift thickness to 2m (still untested during construction)
2m Compacted zone at the surface of the previously constructed 5m lift (top 2
meters).
3m Loose, uncompacted zone at the base of the 5m
lift (bottom 3 meters).
2m Compacted zone not shown due to trench bench
Field Testing ‐ Placement and Compaction
Loose 5m Lift Profiles
39
(Buttressing Fills, Truck Traffic Only)
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Lab Testing Intent:•To determine the maximum dry density and optimum fluid content for various bitumen grades for reject oil sand fills ‐ soils with two fluids•Basis of the single value 1800 kg/m3 for the maximum SPDD for compacted 1m lift fills to accommodate monitoring for construction rates of 25 Mm3/year
Compaction with Respect to Bitumen%
Lab Testing – Materials – Selection 40
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Lab vs. Field (Troxler) Fluid Content Correlation
Field Monitoring and Lab Testing Intent:•To determine the moisture content difference and the impact to the actual density•Basis of the 105% of SPDD construction specification to account for the 3.6% lower moisture content reading of the field vs. the lab which is tracked over time (currently about 5% lower for Kc clays) Do not correct when the corrections are small
For soils with no bitumen like Kc clays
QA/QC on Field Monitoring 41
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Corrections to Nuclear Densometers for dry density
Element
Hydrogen (H) 19 .0 0 .33Boron (B) 109 .2 750 .0Carbon (C) 120 .6 0 .34Nitrogen (N) 139 .5 1 .9Oxygen (O) 158 .5 0 .2Sodium (Na) 224 .9 0 .53Magnesium (Mg) 237 .4 0 .63Aluminum (Al) 262 .8 0 .23Silicon (Si) 273 .3 0 .16Phosphorous (P) 300 .8 0 .19Sulfur (S) 311 .1 0 .51Chlorine (Cl) 343 .3 33 .0Potassium (K) 378 .0 2 .1Calcium (Ca) 387 .3 0 .43Titanium (Ti) 461 .6 6 .1Manganese (Mn) 528 .5 13 .3Iron (Fe) 537 .2 2 .53Cadmium (Cd) 1074 .6 2390 .0Lead (Pb) 1975 .5 0 .17Uranium (U) 2268 .6 4 .2
Absorption Cross Section
# of Collisions to Thermalize a neutron
QA/QC on Field Monitoring
Field Monitoring and Lab Testing Intent:•To determine the source for the fluid content discrepancy between field and lab
• Iowa Dept. of Transportation (1999)• gauge reading higher: materials containing hydrogen other than free water such as bitumen, asphalt• gauge reading lower: materials absorbing thermalized neutrons such as iron and chlorine
• Box Test of Plant 5 Rejects : bulk/wet density error (ρw:‐0.03% to ‐1.8%) (ρd:+0.4% to +2.1%) • Bulb Test: bulk/wet density correction• Standardizing: If testing many materials throughout the day, it is critical to use a neutral site
to standardize
Possible Sources for Fluid Content Error:
42
Box Test
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
1995 to 2007 9632 troxlers 85 proctors
200954 troxlers 5 proctors
QA/QC on Field Monitoring
Field Monitoring and Lab Testing Intent:•To confirm that the current construction season data with the continued use of the single density value for the maximum SPDD for compacted lift fills still applies versus the historical data
Confirmation of Design % SPD
43
Compacted 1.0m lifts (SC‐SM) Compacted 1.0m lifts (SC‐SM)
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Frozen Fill Compaction
Lab Testing Intent:•To determine the influence of various combinations of bitumen and water contents on the compacted density for oil sand fill that is at a temperature below 0°C•All frozen fills do not compact regardless of bitumen content, water content, or grain size.
95% SPD
Density for soil samples at temperatures below 0°C before compaction
Materials – Selection 44
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Lab and Field Testing Intent:•To establish the compaction characteristics of fills constructed at below 0°C
• Useful for extending the construction season through October/November/December and even later if frozen ground is stripped off at the borrow source/shovel face
•Basis of the construction specification on max time to begin compacting 1.0m thick SC‐SM lifts at varying ambient air temperatures
Materials – Selection, Placement, and Compaction
Lab Testing: Field Testing:
45
Tim
e (h
ours
)
Below 0°C Construction in Lab Testing to Field Application
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Field Testing Intent:•To measure the rate of thawing in the fill placed during the winter months•To determine the effect on settlement and hydraulic fracture potential caused by placing fills in the winter
Rate of Thaw of Winter Construction
• Most fill that was placed in winter thawed within 8 to 20 months after winter placement had occurred• 10m of fill placed in winter had thawed through the summer construction season upon measurement that October
• Largest winter fill section constructed, after thawing for 12 months, still had 13m of frozen fill out of the original 32m
Design Consideration – Settlement After Thaw 46
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Summary ‐Winter Construction of Compacted SoilsFor construction of large volume dams at rates of 25 Mm3/year accounts for year long construction in both summer and winter (‐30C) conditions.Base Prep:
• Focus on non‐critical dam areas and save critical areas for optimal construction conditions (summer)
Material Selection:• Non‐frozen fill (<2% frozen fill allowed) from
a large mining face• Frozen layer of the top of the bench is
stripped off with dozers or backhoes • Frozen layer at the face of the bench is
stripped with a shovel• Appropriate monitoring to determine
the depth of frost (e.g. test pits done above shovel)
Winter Construction
Placement: • Do not use thin lifts. The full 1m lift thickness is required for heat
Compaction:• Time‐frame between mining from the face to compaction on the site is narrow with cooler temperatures• Dozers must keep all sides sloped and packed other than advancing lift to minimize frozen rubble contamination• Dry‐of‐optimum high plastic clays stop compacting at around ‐5C. During cooler temperatures, optimization with respect to
packing (e.g. at the end of fall only pack mid‐afternoon)
Inter‐lift Clean‐up:• Snow, ice, and frozen rubble defect tolerances to be applied
QA/QC:• Additional checks to confirm no slop on the lift surface prior to placement (e.g. chipping, thawing bag samples)
47
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Odometer Test Results with first-time wetting occurring at 800kPa for fills at 89% MSPDD
Odometer Test Results without soaking for fills at 89% MSPDD
Consolidation & Inundation Settlement
Lab Testing Intent:•To determine the potential first‐time wetting settlement of compacted fills•Settlement designed into freeboard geometries of future similar structures
Wetting
Design Consideration – Settlement – Consolidation and Inundation 48
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Consolidation & Inundation Settlement
Design Consideration – Settlement – Consolidation and Inundation
Compacted 1m lifts (SC-SM)
Loose 5m lifts
49
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Field Monitoring Intent:•To check the post‐construction performance of the design based on lab consolidation testing•To understand the timing of consolidation and inundation settlement•Settlement (estimated/recommended) designed into freeboard geometries of future similar structures
Consolidation & Inundation Settlement
Design Consideration – Settlement – Consolidation and Inundation
Answer:Some looser 5m thick lift fills settled less than compacted fills due to suspected matrix suction and so will settle more during inundation
50
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
GPS Monitoring – Settlement and Stability
Design Consideration – Settlement
Field Monitoring Intent:•To check the post‐construction performance of the design•To check the agreement between GPS monument stations and settlement gauges•To check the quality of the GPS monument stations with respect to other survey methods or slope inclinometers
• SIs are hard to use in thick compressing/settling fills where the effect of compression has to be weeded out of the data
Answer:Good agreement between the GPS monuments and settlement gauges.The deformation performance of the dam was very good considering the thick fills, winter construction, 1m lifts, and 2.5 year construction period.
51
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Pore Pressure Ratios (ru)
Field Monitoring Intent:•To determine potential pore pressure ratios for fills with similar grain size, fluid contents, compaction, and clean‐up specifications•Parameters applied to analysis for future similar structures
Design Consideration
Answer:•For a conservative slope stability analysis, higher ru.•For a conservative hydraulic fracture analysis, lower ru.•Dissipation of silty fine sands very slow.
52
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Slope Stability
Analysis:•To act as an undrained saturated fill, Total Stresses, the fills should not show a stress dependency in UU triaxial testing. If the fills show a stress dependency in UU triaxial testing and/or are dilative (not contractive), then Effective Stresses parameters could be used in the design.•For slope stability analysis, a higher ru provides more conservative results.
Design Consideration – Slope Stability
Compacted 1m lift of SC‐SM (ru~0) Effective Stress Analysis for Compacted 0.75m lift of CH
53
Piezo elevation
ru
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Hydraulic Fracture
Analysis:•Parameters applied to analysis for future similar structures•Dry of optimum fills with low ru Core – more prone to hydraulic fracture vs. wetted Core and cohesionless filters•For hydraulic fracture analysis, a lower ru gives more conservative results.•Crack Analysis also performed for seepage if there is a risk of hydraulic fracture•Breakout Pressure (Pb) and Propagation Pressure (Pp) adds to factor of safety
Compacted 0.75m Lifts – ru=0 Compacted 1.0m SC-SM Lifts – ru=0
Design Consideration – Hydraulic Fracture 54
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Summary ‐ Placement and Compaction For construction of large volume dams at rates of 25Mm3/year requires year‐round construction:
Field and Lab Testing with Continued Monitoring is required to determine the construction and monitoring boundaries of construction during both summer and winter conditions for the engineered fill thick lifts being used for seepage control, deformation control, stability control, and settlement control.
•Determine how thick a lift can be to achieve design density and meet required lift fabric quality.
•Determine which compaction methodology (which equipment, how many passes) achieves design density and meet required lift fabric quality.
•Determine which Standard Proctor Value applies.
•Determine which field effects (fluid content corrections) to account for.
•Confirm in the field during construction and with continued monitoring post‐construction that the design parameters of density, permeability, strength, and ru are still applicable and that the structure continues to perform.
Placement and Compaction 55
Dozer advancing a compacted 0.75m lift
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
BUSINESS NEEDDesign and Construct large fill volume, time‐critical tailings retaining structures considering:
‐ mining operations field staff abilities
‐ construction monitoring field staff abilities
‐ governmental documentation requirements
1m compacted lift winter clean‐up with a flat‐bar
attachment to the backhoe bucket
0.75m compacted lift density full depth test (0.3m from bottom of the lift) with a drill to get
the probe through the compacted fill
Inter‐lift Clean‐up, Field Monitoring, and QA/QC 56
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Construction Specifications
Inter‐lift Clean‐up, Field Monitoring, and QA/QC 57
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Defects – Compacted Lifts
Field Monitoring Intent: Clean‐up Terminology•Communicative tool to gauge the amount and degree of defects allowed.•Maintains consistency between and within all field personnel and the office design engineers.
Inter‐lift Clean‐up, Field Monitoring, and QA/QC 58
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Example: Defect Tolerance for 90% Seepage Clean – Compacted Lifts
Field Monitoring Intent: 90% Seepage Clean•Maximum defect size of 5m by 5m in discontinuous pockets amounting to less than 10% of the cumulative area•Gridding method shown as a monitoring process to confirm tolerance is being met
Inter‐lift Clean‐up, Field Monitoring, and QA/QC 59
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Inter‐lift Clean‐up – Compacted Lifts
Winter – deep groves left from spinning dozer with ice cleats to clean is unacceptable to leave so spin a dozer without ice
cleats and grade to finish
Winter – rubber tire loader removing siltstones from in front of an advancing lift , tires minimize rubble and grader clean-up
Winter –frozen slop checked by
chipping and thawing a bag
sample
Winter and Summer – no scarifying due to the grooves in the very dry
compacted lifts fill with loose rubble
Inter‐lift Clean‐up, Field Monitoring, and QA/QC 60
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future 61
Inter‐lift Clean‐up – Freeze‐Thaw
Inter‐lift Clean‐up, Field Monitoring, and QA/QC
Compacted dam components (1.0m SC‐SM lifts, 0.75m CH lifts) left over winter for continued construction in the following spring require freeze‐thaw removal:
• Test pitting to determine the total depth of freeze‐thaw affected material
• Removal of freeze‐thaw affected material to firm, compacted ground
• Re‐compaction
If constructed dam components are built through the winter (year‐round construction), freeze‐thaw clean‐up is not required.
Loose 2m to 5m fills for buttressing, even if left over winter for continued construction in the following spring, do not require freeze‐thaw removal but do require:
• Slop removal• Proof‐rolling / Re‐compaction
Dry and brittle
Heavily layered and
soft
Minor layering and soft
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Placement and Compaction
Placement and Compaction, Field Monitoring, and QA/QC
Note:•Allowable rut and roll is for visual monitoring on material quality rather than compaction and placement.•The 240T hauler uniform compaction speed < 5km/hr is so packing gets to the full depth of the lift.•Packing trucks are separated out from Truck‐Shovel Mine Fleet.•The uniform compaction discussed above assumes at least 2 passes by equivalent trucks during placement.•Lift thickness is dropped by half if packing on a slope.
62
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Priorities of QA/QC when building at 25Mm3/year1. Right material at the borrow‐pit and at the dam structure.
2. Base or previous lift cleanup is approved prior to placement (limits of approved areas delineated by cross‐staking in the field).
3. Appropriate lift thickness and material type for the equipment placing (e.g. D9/D10/D11 for 1m SC‐SM lifts in summer only).
4. Observing field performance (e.g. rut and roll as a self‐correction for wet‐of‐optimum) and highlighting material concerns if appropriate.
5. Observing uniform compaction by a minimum 240 ton (often 400 ton) heavy hauler going at less than 5km/hr with a minimum 4 passes with a careful front‐wheel or rear‐wheel stagger and highlighting technique concerns if appropriate.
6. Confirmatory nuclear density testing done of each lift to full depth (0.3m from surface, 0.3m from bottom of the lift).
7. Soil samples for lab confirmation taken as per the structure schedule (e.g. every Wednesday and Friday: SPD, GSD, Atterberg, and moisture content ; testing for SPD corrections at every 200000m3 of material ; permeability testing every 1 Mm3).
8. Document all in daily journal and density test sheets.
9. Information reviewed by the Engineer of Record (may need to be an in‐house geotechnical engineer making final approvals with input from consultant designers/technical resources and in‐house operations representatives).
NOTE: Non‐negotiable on the interpretation of adherence to construction specifications; a hierarchy of design/construction issue escalation may be required for field problem resolution
Field Monitoring 63
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Licensing and Long Term Monitoring • Dam License – supporting documentation and analysis on the dam design for
governmental approval
• Dam As‐Built – supporting documentation and confirmatory testing that the construction met the design intent
• Annual Performance Review – supporting documentation and instrumentation monitoring (slope inclinometers, vibrating wire piezometers, standpipes, GPS monuments, etc.) that the dam structure is performing as designed
• Dam Safety Review – “cold eyes” reviews of the site conditions, dam documentation, analysis, and testing by qualified external consultant
Monitoring – Government Reporting 64
Syncrude Geotechnical Engineering
Securing Canada’s Energy Future
Compaction & Design Tips for constructing fills at rates up to 25 Million m3/year
Successfully balancing the Design Intent for Earth Dam Structures with Business Need and Construction Optimizations
EW Dyke•180 million m3 of engineered fill •Will need a construction rate of 50 Mm3/year
65
NS Dyke•76 million m3 of engineered fill •At a maximum construction rate of 15 Mm3/year
Hwy63 Berm•42 million m3 of engineered fill •At a maximum construction rate of 17 Mm3/year
SW Dam•114 million m3 of engineered fill •At a maximum construction rate of 25 Mm3/year
Sponsors For Cross Canada Lecture Tour, Spring 2013
The Canadian Foundation for GeotechniqueLa Fondation canadienne de géotechnique
The Canadian Geotechnical SocietyLa Société canadienne de géotechnique
Sponsors For Cross Canada Lecture Tour, Spring 2013
Organization:
Funding: