Cftest by Navneetkrishnan
-
Upload
rashm006ranjan -
Category
Documents
-
view
217 -
download
0
Transcript of Cftest by Navneetkrishnan
7/27/2019 Cftest by Navneetkrishnan
http://slidepdf.com/reader/full/cftest-by-navneetkrishnan 1/6
CASE STUDY ON CLEAN AIR FLOW TEST OF MILLS
BY: Navneetha Krishnan
INTRODUCTION:
Coal fired thermal power plants with corner fired burner arrangements
are having different lengths of coal piping emanating from the
pulveriser. The primary air supplied, to pulverisers for drying the coal
powder and transporting the powders through the coal piping to the
burners, shall have equal distribution for effective combustion in boiler.
The equal distribution of the transportation air is ensured by
conducting the Clean air flow test prior to the initial admission of coal
in to the pulveraisers. The test is carried out in boiler with status
confirming to the coal firing conditions, i.e. running of one set of ID fan,
FD fan, PA fan, Pulveriser and seal air fan.
TESTING CONDITIONS:
Boiler furnace Air Tightness Test is completed and furnace
bottom seal trough is in service
Primary air and secondary air ducting from fans to boiler and
pulveriser is completed and ATT is completed
Flue gas ducting from furnace to chimney is completed with ATT
ESP is ready after air in leak test completion with all internals
assembled
Pulveriser and seal air fan trial run completed
Coal piping from pulveriser to burner is completed with all
supports and the tapping points provided (2 nos. at 900 apart) as
in Figure 3, in piping at all four corners for taking measurements
of air velocity
The pneumatic gates and control dampers provided in the
primary air circuit should be operable from control room
7/27/2019 Cftest by Navneetkrishnan
http://slidepdf.com/reader/full/cftest-by-navneetkrishnan 2/6
Erection of Raw coal feeder and the piping to pulveriser should
be completed
Instrumentation of air, flue gas and pulveriser system should be
completed and parameters shall be available in control room
Proper approach and platforms shall be provided in all corners
nearer to the measurement locations of coal piping
Pitot tube, manometer and thermometer are available for
measurements
Markings are done on Pitot tube with values, 0.0436R, 0.135R,
0.238R, 0.358R, 0.507R, 1.492R, 1.642R, 1.762R, 1.816R and
1.956R (R- inner radius of coal pipe) to ensure measurements
from equal area inside the coal pipe (Figure 2)
TEST PROCEDURE:
One set of ID fan, FD fan, PA fan, Seal air fan and the Mill are
started and PA header pressure (750 – 800 mmwc), furnace draft
(-5 mmwc) and secondary air flow (30 %) are adjusted
Pitot tube measurement is taken from inside the coal pipe at the
centre of the coal pipe and air flow is adjusted to around 110 %
of the design air flow by regulating hot and cold primary air
control dampers.
The condition established as above should be continued for the
complete period of test.
Velocity profile in each coal pipe shall be obtained by traversing
the pitot tube at two directions (Figure 3) wrt the markings made
on the pitot tube
Mill air temperature, airflow, mill DP and PA header pressure
indications are noted from control room.
The pitot tube velocity head readings are converted into air
velocity inside the coal pipe using the formula,
V = 0.2365227 √h(t)
7/27/2019 Cftest by Navneetkrishnan
http://slidepdf.com/reader/full/cftest-by-navneetkrishnan 3/6
where V = air velocity in m/sec
h = DP measured using pitot tube and manometer in mmwc &
t = temperature in deg Kelvin
Average velocity is calculated for each coal pipe. The maximum
and minimum velocity of air in the pipe and their deviations from
the average of the four pipes are also calculated
The deviations shall be within ± 5% of the average velocity for
successful completion of the test.
The velocity measured can be converted into the air flow and can
be compared with control room readings
Airflow = velocity x area x air density
PROBLEMS FACED IN BHILAI UNIT 1:
⇒ The tests were conducted on 01/08/08 on mills A & B maintaining
110 % of design air flow and the deviations from average were
calculated as 10 % & 8 %
⇒ The tests were repeated on 10/10/08 on mills A & B maintaining
140 % of design air flow and the deviations calculated were 7 %
& 8 %
⇒ Mills A & B were thoroughly inspected for choking in MDVs,
classifier vanes and rechecking of orifices at mill & burner ends
also done. Coal pipes of Mill A was cut at two locations and
cleanliness was also ensured
⇒ The tests were repeated on 20/10/08 on mills A & B maintaining
140 % of design air flow and the deviations calculated were 7 %
& 8 %
⇒ The test was conducted on Mill C on 01/09/08 and Mill D on
10/09/08 and deviations calculated from the readings, were not
within acceptable limits
7/27/2019 Cftest by Navneetkrishnan
http://slidepdf.com/reader/full/cftest-by-navneetkrishnan 4/6
⇒ The measurements taken and calculations done were sent and
clarifications regarding the orifice sizes’ selection were obtained
from BHEL Trichy Designers. BHEL Trichy confirmed that the
selection of orifices was in order
⇒ PA fan was kept running more than a day to ensure the
cleanliness of the coal pipings and the test was repeated in Mills
A & B on 01/11/08. The test results were not satisfactory and the
deviations calculated from the pitot tube measurements were
not within acceptable limits.
SOLUTION OBTAINED:
√ Pitot tube was arranged from BHEL site/ JPL, Raigarh and the
test was done on Mills E, F & G. The calculated results were
within acceptable limits.
√ The clean air flow tests were carried out in other mills ( A, B, C &
D) also and the test results were all within acceptable limits.
√ Customer insisted to repeat the tests with the new PITOT tube
and after getting repeatability of results, cleared all the tests and
cleared for coal firing operation of the unit.
CONCLUSION;
Lot of efforts were put to identify the problem faced in the clean airflow
tests conducted and finally the instrument used (PITOT TUBE) for
measurement was found defective. Hence it is concluded that the
calibration, accuracy and correctness of Instruments used for all tests
are to be doubly verified and ensured for successful completion of the
tset.
Markings done End to beput insidecoal pipe
7/27/2019 Cftest by Navneetkrishnan
http://slidepdf.com/reader/full/cftest-by-navneetkrishnan 5/6
Connections to U tube Manometer
FIGURE 1