Cert Ambient Generation And Transmission
-
Upload
evansdevelopment -
Category
Documents
-
view
275 -
download
0
description
Transcript of Cert Ambient Generation And Transmission
Modeling Work Group
Two Primary Tasks Model Development WECC Transmission Planning
Work Group Composition 64 members; all sectors represented Regular meetings, mostly via
phone/webinar Interface with other WREZ Work
Groups Zone Identification (ZITA) Environment & Lands
2
WREZ Model Development
Review of Existing Models Model Features
Resource cost & operational characteristics Transmission cost & operational characteristics Sensitivity Analyses Scenario Analyses
Model Development Validation Application Documentation and Training
3
Model Features – Primary Considerations Users: Resource planners, public policymakers & regulators to
evaluate situations/scenarios Approach: Incremental Additions – Renewables Focus
Interstate vs. intrastate deliveries Driven by Input Assumptions –
Resource cost and operating characteristics Transmission cost and operating characteristics
Value Determination: characteristics of deliveries at load (sink) Delivered power costs: capacity & energy Integration costs and dependability Geographic diversity and overbuilding
Source/Sink Relationships – Single vs. Linked Resources: Renewable types and locations Role of gas: benchmark and/or to support wind
Scenario Analysis Options? Time Issues: costs & technology Sensitivity: CO2 penalties & gas price Toggles (on/off): reliability value, storage value, seasonal
exchange, and regulatory incentives (PTCs & ITCs)4
Modeling Group Schedule
Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09Task 1: Model Development Existing Models Assessment Features for Model Model Development Validation of Model Application of Model Model Documentation & Training
Task 2: WECC Transmission Planning Sub-Regional Venues WECC Transmission Planning
GTMWG Meeting Schedule Co-Chair Coordination Calls Conference Calls On-Site Meetings/Webcasts
WeeklyMonthly and at Critical Junctures
Bi-Monthly and at Critical Junctures
5
6
Power Delivery Tool Development:Review of Previous Work
Lawrence Berkeley National Laboratory
Black & Veatch
Generation & Transmission Modeling Work Group
7
OutlineOutline Review Previous Analyses and Models
What are objectives of analysis/model? How is the value of the remote resource determined? How is the cost of the remote resource estimated? How is the cost of transmission estimated?
Previous Analyses That Compares Remote Renewable Resources: ERCOT CREZ Analysis Wind Deployment System (WinDS)
Previous Spreadsheet-based Resource Planning Models that Include Transmission:
E3 Greenhouse Gas Calculator B & V Renewable Energy Transmission Initiative
Previous Spreadsheet-based Transmission Economic Analysis Models Frontier Line Economic Assessment Screening Tool (FEAST) Northwest Transmission Assessment Committee: Canada–
Northwest–California Transmission Options Study
8
FrameworkFramework
All studies and models can be reduced to evaluating the question:
Do the benefits of obtaining power from a remote resource outweigh the cost of accessing the resource?
If so, transmission should be built to access the remote resource
In other words, is: Value of Remote Resource >
Bus-bar Cost of Remote Resource + Transmission Cost?
9
ERCOT CREZ Analysis (2008)ERCOT CREZ Analysis (2008) Objectives of Analysis:
Determine the transmission required to access various levels of new wind in several CREZs
Estimate the relative attractiveness of each option Value of Remote Resource:
Production cost savings from security constrained economic dispatch and unit-commitment of ERCOT system (inherently includes time-of-delivery energy value)
No fuel sensitivity or carbon price Cost of Remote Resource:
Generic estimate of wind capital cost ($1000/kW) and site specific capacity factors.
No renewable incentives, no integration cost estimates Cost of Transmission
Least cost transmission designed to reduce wind curtailment to below 2% in all scenarios
Generic capital cost estimates for 345 kV single and double circuit lines Line utilization not explicitly calculated but implicit in economic dispatch
10
ERCOT CREZ Analysis (2008)ERCOT CREZ Analysis (2008) Results:
Table in main report details site specific capacity factors, total wind capital cost, total new transmission cost, and annual production cost savings for each CREZ option
Derived Results: Ranking cost
(Bus-bar Cost + Transmission Cost – Production Cost Savings) was calculated for each option and plotted on the right
ERCOT CREZ Analysis: Ranking Cost Curve (Assuming 15% Capital Recovery Factor for Wind and Transmission Capital Costs)
0.0
5.0
10.0
15.0
20.0
25.0
0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000
Cummulative Wind (MW)
Ran
kin
g C
ost
($/
MW
h)
Coastal, 1 GW
Central Western, 2 GW
Panhandle, 4.6 GW
11
WinDS: 20% Wind Energy by 2030 Analysis WinDS: 20% Wind Energy by 2030 Analysis (2008)(2008)
Objectives of Analysis: Determine the least cost regional expansion of generation and transmission for the
next 50 years Value of Remote Resource:
Resources are built to satisfy load requirements in 136 balancing areas within 16 time slices.
Renewable energy resources are compared to conventional generation options Includes option to model nation-wide carbon cap or carbon taxes Includes integration cost estimates for wind energy (based on additional operating reserves)
Cost of Remote Resource: Capital cost estimates and performance estimates include technological learning
with time. Performance is based on 358 different wind regions in the U.S. Bus-bar cost includes estimate of interconnection cost to nearest transmission line
Cost of Transmission Assumes 10% of existing transmission capacity is available for new wind energy at
no cost above interconnection costs. New transmission lines can be built between balancing regions at a fixed cost of
$1,600/MW-mi (only 50% of cost is assigned to wind due to shared reliability benefits)
No lumpiness or economies of scale are accounted for Line utilization: New lines are only used by new resources, no “over-build” or
curtailment Line losses: fixed line loss assumption (0.236 kW/MW-mi)
12
WinDS: 20% Wind Energy by 2030 Analysis WinDS: 20% Wind Energy by 2030 Analysis (2008)(2008)
Results:
Global optimization determines the least cost options for meeting load in each balancing area.
Chart shows the projected use of existing (blue) and new (red) transmission to transport wind energy between balancing areas by 2030.
Model results: Wind is
transported across multiple states on existing lines
New lines are built within states or between states
13
Black & Veatch Renewable Energy Black & Veatch Renewable Energy Transmission Initiative (RETI) (2008)Transmission Initiative (RETI) (2008)
Objectives of Tool: Identify and quantify renewables for CA RPS requirement and transmission necessary to
deliver that energy Value of Remote Resource:
Value of remote resource is based on capacity and energy value: Capacity value: Capacity credit based on capacity factor of resource-specific generation profile
during peak period, capacity cost based on CT peaker plant Energy value: Resource-specific generation during three periods and zone-specific prices in each
period based on economic dispatch model
No sensitivity to carbon or fuel prices in base case No integration cost
Cost of Remote Resource: Range of capital cost and performance provided in Phase 1A, Phase 1B will provide more
detail Levelized cost based on pro-forma financial worksheet with Federal incentives, capital
costs, and performance Cost of Transmission:
In-state: Utilize utility transmission ranking cost reports (TRCRs) to estimate transmission needs, transmission costs, and step-size (primarily based on power-flow studies).
Out-of-state: Transmission based on distance of resource to delivery point in CA. Transmission cost based on pro-rata share of 500-kV line with generic $/MW-mi cost estimate.
Line utilization based on capacity factor of remote resource
14
Black & Veatch Renewable Energy Black & Veatch Renewable Energy Transmission Initiative (RETI) (2008)Transmission Initiative (RETI) (2008)
Details of Ranking Cost: Each resource is
compared to other resources on equivalent basis using ranking cost method:
Ranking Cost = Generation Cost + Transmission Cost – Capacity Value – Energy Value
Resources with lowest ranking cost are most valuable to CA
15
E3 Green House Gas Calculator (2008):E3 Green House Gas Calculator (2008):Renewable Energy Supply CurvesRenewable Energy Supply Curves
Objectives of Tool: Overall: Enable regulators to determine the cost of various policy options to reduce green house gas emissions in the
electricity and natural gas sector in California. Policy options include in-state and out-of-state renewables. Rank several renewable zones based on delivered cost and cost adders (integration, capacity adjustment, etc)
Value of Remote Resource: “Firming” cost adder used to reflect less than nameplate capacity contribution of resources toward capacity
requirements Integration cost for wind. Integration costs estimated from previous studies in other states. Increasing penetration
leads to increasing integration cost. No consideration for geographic diversity No adjustment for differences in time-of-delivery energy value between renewable resources in ranking cost. However
four time slices are used in separate estimate of total state-wide impact Cost of Remote Resource:
Bus-bar cost for all resources in a zone based on user-defined capital costs, performance, incentives, and interconnection costs
Interconnection costs based on $1,600/MW-mi estimate with collector system distances that differ for each type of renewable technology
Cost of Transmission In state renewable zones: Transmission costs based on previous studies (mostly based on power flow analysis) Out-of-state: Assume new lines must be built to import any new resources.
New lines are very lumpy – 250 MW of new renewables from out-of-state triggers new transmission line. All costs assigned to new resource.
New lines in default case are all HVDC lines. User can define 230 and 500 kV AC lines too. Line utilization based on capacity factor of remote resource
16
0
50
100
150
200
250
300
1.8E
+03
1.4E
+05
2.6E
+05
3.8E
+05
5.3E
+05
6.8E
+05
7.9E
+05
9.0E
+05
1.0E
+06
1.1E
+06
1.2E
+06
1.3E
+06
1.3E
+06
Cummulative Renewable Resources (GWh/yr)
Del
iver
ed C
ost
+ A
dd
ers
($/M
Wh
)
Transmission Cost ($/MWh)
Integration Cost ($/MWh)
Firming Cost ($/MWh)
Bus-bar Costs ($/MWh)
E3 Green House Gas Calculator (2008):E3 Green House Gas Calculator (2008):Renewable Energy Supply CurvesRenewable Energy Supply Curves
Results: Chart shows relative
ranking of in-state and out-of-state renewable options.
Total cost is decomposed into components
Significant variation in costs due to default assumption that HVDC lines are built for even small resource imports.
Results indicate integration costs are minor compared to other components
17
Frontier Economic Assessment Screening Frontier Economic Assessment Screening Tool (FEAST) (2007)Tool (FEAST) (2007)
Objectives of Tool: Determine the cost/benefit ratio of individual transmission lines based on the
line utilization and the energy price basis between the source and sink Value of Remote Resource:
Remote resources displace user-defined mix of generation resources in the sink.
Capacity valued based on fixed cost of peaker and ‘dependable’ capacity of remote resource. Dependable capacity is technology-specific but does not vary based on geographic location
User-defined integration cost, conventional fuel price forecasts, and carbon taxes
Cost of Remote Resource: User defined mix of resources in remote ‘source’ location Levelized bus-bar cost based on capital cost, performance, incentives, and
‘levelizing factors’ for merchant or utility financing. No interconnection cost estimates
Cost of Transmission: 500 kV AC or DC transmission lines with user defined line utilization
Line utilization is assumed to be higher for wind with 20% ‘overbuild’ (1200 MW of wind on a 1000 MW line)
Capital cost estimates based on engineering judgment, generic equipment cost assumptions, and distance from source hub to sink hub
Peak-load losses based on length and type of line
18
BC Ratio Break-Even Curve
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%Line Utilization Factor
Reg
ion
Co
st D
iffe
ren
ce N
eed
ed f
or
BC
=1
($/M
Wh
)
BC > 1
BC < 1
Frontier Economic Frontier Economic Assessment Screening Tool Assessment Screening Tool
(FEAST) (2009)(FEAST) (2009)
Financing
Installed Capacity
MWEnergy GWh
Source: Montana/WyomingWind - Wyoming Merchant 3,600 15,137
Sink: CaliforniaCombined Cycle - CA Merchant 2,215 15,137
Trans Option No. 7b Installed Cost ($Million) 4,300
Capacity (MW) 3,000
Description Wyoming - Mona (Utah) - S. Nevada - Southern CALine Utilization 58%
Regional Difference Annual AnnualSource Sink Diff Benefits Cost
($/MWh) ($/MWh) ($/MWh) ($/MWh) ($Million) ($Million)Line Cost 28.0 424
Power Cost 39.8 66.5 26.7 405GHG Adder 0.0 16.0 16.0 242CO2 for EOR 0.0 0.0 0.0 0Renewable Credit 0.0 0.0 0.0 0System Integration 3.0 0.0 -3.0 -45Prod Tax Credit 0.0 0.0 0.0 0Losses 1.7 -1.7 -25Grid Eff 0.0 0.0 0Dependable Cap Value -2.1 -2.1 -32 *TOTAL 44.5 80.4 35.9 544 424Benefit to Cost Ratio 1.28
•Results:
- Table shows results of one case analyzed in study of Frontier transmission line with 20% overbuild of wind in Wyoming displacing energy from CCGT and capacity from CT in CA
- Chart shows sensitivity of results to line utilization and regional cost spread (basis) between source and sink
19
Northwest Transmission Assessment Northwest Transmission Assessment Committee (NTAC) (2009)Committee (NTAC) (2009)
Objectives of Tool: Comparison of delivered cost of inventory of new generation resources in Western Canada
and the Pacific Northwest to options in the Northwest and California. Evaluates specific transmission line options
Value of Remote Resource: Compares delivered cost of remote resource to CCGT in PNW or California No capacity value or time-of-delivery energy value adjustment No integration costs User-defined carbon and fuel price
Cost of Remote Resource: Levelized bus-bar cost based on capital cost, performance, incentives, and single capital
charge rate No interconnection cost
Cost of Transmission: Transmission options designed outside of tool. Most options evaluated using powerflow
analysis. Transmission cost estimates based on detailed equipment requirement and cost
assumptions Transmission line utilization is a user-defined assumption (e.g. 35% for wind only, 65% for
hydro only, or 75% for combined wind and hydro option). Includes transmission losses based on length and type of line
20
Northwest Transmission Assessment Northwest Transmission Assessment Committee (NTAC) (2009)Committee (NTAC) (2009)
Results: Comparison of delivered
cost of energy for mix of resources using different transmission line options
Options are compared to CCGT in PNW or S. CA load centers
Tool only reports total delivered cost:
Tool does not adjust costs for capacity value, time-of-delivery energy value, or integration costs
Real Levelized Unit Costs, 2005$
$0.0 $10.0 $20.0 $30.0 $40.0 $50.0 $60.0 $70.0 $80.0 $90.0 $100.0
South California Combined Cycle
US Pac NW Combined Cycle
3000 MW Montana Coal
Syngas Cogen & Coal
3000 MW Syngas Cogen
3000 MW Mont. Coal to L. Vegas
3000 MW Montana Coal
Syngas Cogen & Coal
Syngas Cogen & Coal
3000 MW Syngas Cogen
3000 MW Syngas Cogen
1500 MW Syngas Cogen
1500 MW Syngas Cogen
1500 MW AB Coal
1500 MW AB Coal
Hydro in BC&AB Sngas Cogen
Hydro in BC&AB Sngas Cogen
1500 MW Syngas Cogen
1100MW Wnd, 680 Hyd, 500 CC
1100 MW wnd, 680 Hyd, 400 CC
1100 MW Wind, 680 MW Hydro
3200 MW wind, 1800 MW Hydro
8b
8a
7d
7c
'7
c7
b7
a6
d6
c6
b6
a5
b5
a4
b4
a3
2b
2a
2a
'1
$US/MWh
Generating Cost Transmission to Pac NW Transmission to California
21
SummarySummary
Tool/ Analysis WinDS ERCOT RETI (Out-of-state)
E3 GHG - Renewable Supply Curve Component FEAST NTAC
General
User-friendly Spreadsheet Analysis X X P P P PGlobal Optimization P X X X X X
Production Cost Model/ Economic Dispatch X P X X X X
Focus of Analysis
Relative Ranking of Multiple Resources X P P P X X
Detailed Estimate of Delivered Cost X X X X P PValue of Remote Resource
Capacity Value P X P P P X
Time-of-Use Energy Value P P P X X X
Integration Cost P X X P P X
Cost of Remote Resource
Detailed Pro-forma Analysis of Bus-bar Cost X X P X X X
Regulatory Incentives (PTC, ITC, etc) P X P P P PCost of Transmission
Transmission Capacity = Resource Nameplate Capacity
P X P P X X
Detailed Transmission Routing X P X X P PTransmission Cost Discounted for Reliabiltiy Benefits
P X X X X X
Seaonal Exchange Benefits X X X X X X
Storage X X X X X X
22
ReferencesReferences
ERCOT Electricity Reliability Council of Texas (ERCOT). 2006. Analysis of Transmission Alternatives for
Competitive Renewable Energy Zones in Texas. December. http://www.ercot.com/news/presentations/2006/ATTCH_A_CREZ_Analysis_Report.pdf.
WinDS: U.S. Department of Energy (DOE). 2008. 20% Wind Energy by 2030: Increasing Wind Energy's Contribution
to U.S. Electricity Supply. Appendix B. May. http://www.20percentwind.org/20percent_wind_energy_report_05-11-08_wk.pdf.
E3 GHG: http://www.ethree.com/cpuc_ghg_model.html
RETI: Black & Veatch. 2008. Renewable Energy Transmission Initiative Phase 1A. RETI Stakeholder Steering
Committee, March. http://www.energy.ca.gov/reti/documents/2008-03_RETI_PHASE-1A_DRAFT_REPORT.PDF.
FEAST: Western Regional Transmission Expansion Partnership (WTREP). 2007. Frontier Line Feasibility Study .
April 30. http://www.ftloutreach.com/workinggroups/economicanalysis.html.
NTAC: Northwest Transmission Assessment Committee. 2006. Canada–Northwest–California Transmission
Options Study. Northwest Power Pool, May 16. http://www.nwpp.org/ntac/pdf/CNC%20Report%20-%20Final%2016%20May%202006.pdf.
Adequacy of Exiting Models
Existing Modeling Approaches Source/Sink Pairs (Excel): FEAST & NTAC Regional Rankings (Excel): RETI & E3-GHG System Optimization (non-Excel): CREZ, WinDS,
What is the Desired Approach? Hybrid to evaluate scenarios for selected load
centers Selection-driven vs. optimized Optimized for shortest transmission
23
Wind Solar Load Flow
CASE A
WREZ Delivery Scenarios
Other
CASE B
CASE C
INC
RE
AS
ING
CO
MP
LE
XIT
Y
Gas-at-load
Remote Gas
24
25
Screening-Level REZ Analysis Tool:
Straw-man Proposal
Lawrence Berkeley National Laboratory
Black & Veatch
Generation & Transmission Modeling Work Group
26
OutlineOutline
Objectives of REZ Analysis Tool Proposed Tool Outline Strengths and Weaknesses of
Proposed Tool Select Questions for Workgroup
27
Objectives of REZ Analysis Objectives of REZ Analysis ToolTool
Assist resource planners and regulators to evaluate the relative attractiveness of geographically broad renewable resource options at a screening level
Estimate “delivered cost” of both in-state and out-of-state RE options from REZs to LSE load areas
Highlight potential and benefits of collaboration between LSEs to build transmission lines
Highlight potential for competition for limited renewable resources
28
Proposed Tool OutlineProposed Tool Outline Delivered Cost:
Tool calculates delivered cost of each renewable resource type from each REZ to an LSE within a load zone
Delivered Cost = Bus-Bar Cost + Interconnection Cost + Transmission Cost + Local Delivery Charges
Relative Ranking: Tool will provide market value adjustments to the delivered cost to determine
the relative attractiveness of resources
Adjusted Delivered Cost = Delivered Cost +/- Market Value Adjustments Potential for Collaboration and Competition:
Tool highlights resources that are well-ranked for multiple load zones Collaboration: User can modify default assumptions to evaluate benefits of
shared lines Competition: User can choose which resources to include in analysis. A user
may decide to exclude a resource that they expect to not be available due to competition for a limited resource (or other reasons)
Tool Output: Reports including the relative ranking of REZs and the underlying data used to
generate relative ranking (Delivered cost, transmission cost, market value adjustments, etc.)
Reports will highlight resources that are well-ranked for multiple load-zones
29
General Tool FunctionalityGeneral Tool Functionality Excel-based tool
Tool is provided with default assumptions
User can evaluate relative ranking of resources to each load zone based on default assumptions
Tool includes considerable flexibility for user to change default assumptions
Users can evaluate user-defined “what-if” scenarios
User can examine impact of their own view of the future:
Tax incentives, cost changes, value of energy and capacity etc.
Changes to default assumptions will primarily be based on external analysis
30
Aggregate REZ ResourcesAggregate REZ Resources
Core data of tool: REZ list Bus-bar and
interconnection cost by renewable resource type
(specific ZITA deliverables TBD)
Primary assumption: REZ interconnection cost
based on new high-voltage substation within REZ
User defined assumptions: User can change bus-bar
cost (specific bus-bar cost
modeling TBD)
Example REZ and load hubs
31
Load ZoneLoad Zone
Each LSE will be represented within a Load Zone worksheet (e.g. APS and SRP in Arizona Load Zone)
On the order of 20 load zones
Tool will have empty placeholders for user to define non-REZ resources to include in relative ranking (e.g. distributed photovoltaics or CCGT sited at load)
Tool will allow user to select which REZs and resource types within REZs to include in analysis
Arizona Load Zone – LSEs are represented within nearest load zone
32
Load ZoneLoad ZoneUser can deselect resources they think should not be included in analysis
• Each LSE will be represented within a Load Zone worksheet (e.g. APS and SRP in Arizona Load Zone)
• On the order of 20 load zones
• Tool will have empty placeholders for user to define non-REZ resources to include in relative ranking (e.g. distributed photovoltaics or CCGT sited at load)
• Tool will allow user to select which REZs and resource types within REZs to include in analysis
33
Delivered CostDelivered CostTool will calculate total delivered cost from selected resource types in selected REZs
Tool will calculate delivered cost for each resource type in each REZ to the load zone
Primary Assumptions: Distance from
interconnection point to load zone hub:
Distance will be based on routing via existing rights-of-way to the appropriate extent (from GTM sub-group)
Incremental transmission additions – assume no existing transfer capability
34
Delivered CostDelivered CostTool will calculate total delivered cost from selected resource types in selected REZs
Transmission cost component: Transmission Capital Cost (Based
on voltage and distance) Transmission utilization Distance multiplier Per mile losses based on line
voltage assumption Delivery charge from load zone hub
to LSE load center Operating costs
All are user-defined assumptions with default assumptions provided with tool
35
Relative RankingRelative Ranking Tool will determine the relative
ranking of resource types from each REZ based on the delivered cost adjusted for market valuation factors
Important market value adjustment factors:
Capacity value Time-of-Use Energy Value Integration costs Externalities (e.g. Carbon taxes if
comparing to load-based CCGT)
More detail on assumptions and methods will be provided in a Market Valuation White paper by LBNL
Tool will rank resource types and REZs to highlight most attractive options
36
Comparison to other Load Comparison to other Load ZonesZones
Separate worksheets will be used for each load zone
The same ranking cost process will be performed simultaneously for each load zone
Similar ranking process will be done for each load zone on separate worksheets
37
Comparison to other Load Comparison to other Load ZonesZones
Similar ranking process will be done for each load zone on separate worksheets
Separate worksheets will be used for each load zone
The same ranking cost process will be performed simultaneously for each load zone
38
Collaboration and CompetitionCollaboration and Competition
The tool will highlight resources that rank well for multiple load zones
Users can explore the impact of competition by examining the new resource ranking if they assume the resource will be fully utilized by another load zone
Resources that rank well for multiple load zones will be highlighted in the tool
39
Collaboration and CompetitionCollaboration and Competition
After determining the well ranked resources for different load zones, a user can modify default assumptions to determine the benefits of collaboration in “what-if” scenarios
For example, a user could model a shared line by changing default assumptions for utilization and line distance
Tool, as proposed, may be able to accommodate this type of investigation, but it would require significant amount of external analysis.
Benefits of collaboration can be modeled by users in “what-if”
scenarios
40
Strengths and WeaknessesStrengths and Weaknesses
Strengths: (Tool models well) Simultaneous relative ranking of resources across multiple
load zones
Well-ranked resources in multiple load zones present opportunities for collaboration or competition between LSEs
Wide geographic scope: relative comparison of both in-state and out-of-state resources
Flexibility: Default assumptions are provided, user can modify default assumptions to create their own “what-if” scenarios
Transparent screening of resources: Excel based tool with many user-defined assumptions
41
Strengths and WeaknessesStrengths and Weaknesses
Weaknesses: (Tool does not model well) Optimal resource mix: Tool complements traditional resource planning models, but will
not substitute for one Transmission to access multiple resource types in same zone
E3 GHG Model may be useful guide for how to incorporate this feature into the tool, but it may involve tradeoffs
Transmission to access multiple zones with one transmission line Transmission to access multiple loads and multiple zones with one transmission line
Default assumptions will be single resource in REZ. Multiple resources and multiple load hubs require user to modify default assumptions:
Blended Bus-bar and interconnection cost? Transmission utilization: User-defined transmission
utilization (e.g. default would assume 40% utilization for wind-only REZ, user could assume 60% for wind and solar in user-defined multiple resource-REZ)
Transmission line length: Multiple REZ and load hubs may require longer lines. User must specify increase in line length
Value of seasonal exchange Value of reliability Detailed transmission pricing (instead based on very simple assumptions)
42
Select Questions for Select Questions for WorkgroupWorkgroup
What is the primary use of the tool? Current focus: determine relative ranking of
resources in REZs for each load zone based on simple user-defined assumptions
Similar to E3 GHG and RETI analyses
Alternative focus: Focus more on specific transmission lines. Determine delivered cost of resources based on detailed modeling of specific transmission lines
Similar to NTAC and FEAST analyses
43
Select Questions for Select Questions for WorkgroupWorkgroup
Is proposed tool potentially too complex? Each load zone (~20 load hubs) will
potentially rank all resources in each REZ ( potentially 40 or more REZs with multiple technologies)
Tradeoffs between being comprehensive (ability to screen all resources for each load zone) and depth of modeling (detailed modeling of transmission line sizing, routing, and usage)
44
Select Questions for Select Questions for WorkgroupWorkgroup
Is the basic functionality of the tool sufficient to highlight potential for both competition and collaboration?
Tool simply highlights resources in REZs that are well ranked for multiple load zones.
Tool does not specify total demand for renewables in load zones
Competition: User can examine effect of competition by excluding resource from relative ranking in their load zone
Collaboration: User can develop changes to default assumptions to model different routing and line utilization that might occur with shared transmission lines. Tool will provide little guidance on how to develop and model these user-defined shared lines.
Transmission Work Tasks
Model Development Sub-Group Model design & features Matrix of desired input to ZITA Workgroup
Transmission Segments Sub-Group Mileage and routes Existing corridors and to link/access REZs Build on prior work: Frontier, BC-CA & NTAC Default routes for each load
Transmission Costs & Operations Sub-Group Voltages and capacity ratings: AC & DC Configurations: single & double circuit Line losses Line-mile and associated costs Financial and operating costs
45
Example Model Inputs (FEAST)(to be populated by ZITA)
Heat-Rate CapacityDepend.Capacity
Installed Cost
Fixed O&M
Other Fixed
Variable O&M
Plant Type BTU/kWh Factor Factor 2006$/kW $/kW-Yr $/kW-Yr $/MWhBiomass 8,910 90% 100% $2,200 $95.70 $62.81 $5.20Gas Combined Cycle 6,920 78% 100% $1,000 $13.70 $39.19 $2.40Gas Combustion Turbine 9,300 10% 100% $750 $12.30 $26.10 $9.90Geothermal NA 95% 100% $3,600 $64.00 -$6.20 $23.60Solar Concen. NA 40% 87% $3,150 $38.00 $75.03 $1.50Solar Concen. (Storage) NA 40% 100% $3,150 $38.00 $75.03 $1.50Wind - California NA 36% 21% $1,300 $11.50 $0.00 $5.50Wind - Generic NA 35% 30% $1,300 $11.50 $0.00 $5.50Wind - Utah NA 36% 35% $1,300 $11.50 $0.00 $5.50Wind - Wyoming NA 48% 39% $1,300 $11.50 $0.00 $5.50
46
Primary WECC Transmission Paths
BUCKLEY
SUNDANCE
FT. PECK
PEACE CANYON
MICA
VANCOUVER
SEATTLE
PRINCE RUPERT
AREA
AREA
COLSTRIP
BOISE
PORTLANDAREA
MALIN
TABLE MTN
ROUND MTN
SALT LAKECITY AREA
MEXICO
EL PASOAREA
DEVERSLUGO
SAN FRANCISCO
MIDPOINT
AREA
LOS ANGELESAREA
ALBUQUERQUEAREA
NAVAJO
DENVERAREA
MOJAVE
HOOVER
PHOENIXAREA
LANGDON
HOT SPRINGS
HELLSCANYON
CHIEF JOSEPH
BURNS
PINTO
FOURCORNERS
SHASTA
LANGDON
CANADA
UNITED STATES
47
Example Transmission Segments (Frontier)
Segment Route MilesCapacity
(MW) Design $MM Lossesa S.E. Montana - S. Wyoming 205 1500 1-500 kV AC 800 2.1%b S. Wyoming - Southern CA 850 3000 1-500 kV DC 2,700 6.3%c S. Wyoming - Southern CA 1700 6000 2-500 kV DC 5,400 6.3%d S. Wyoming - N.E. Nevada 512 3000 1-500 kV DC 1,900 4.4%e S. Wyoming - N.E. Nevada 1024 6000 2-500 kV DC 3,700 4.4%f N.E. Nevada - S. Nevada 234 3000 2-500 kV AC 1,300 1.2%g N.E. Nevada - S. Nevada 468 6000 4-500 kV AC 2,400 1.2%h S. Nevada - Southern CA 200 3000 2-500 kV AC 1,200 1.0%i S. Nevada - Southern CA 400 6000 4-500 kV AC 2,200 1.0%j Northwest - N.W. Nevada 350 3000 2-500 kV AC 1,800 1.8%k S. Wyoming - N.W. Nevada 685 3000 1-500 kV DC 2,300 5.4%l S. Wyoming - N.W. Nevada 1370 6000 2-500 kV DC 4,500 5.4%
m N.W. Nevada - Northern CA 233 3000 2-500 kV AC 2,400 1.2%n N.W. Nevada - Northern CA 466 6000 4-500 kV AC 4,800 1.2%o Northern CA - Southern CA 325 3000 2-500 kV AC 1,800 1.6%p Northern CA - Southern CA 650 6000 4-500 kV AC 3,500 1.6%q Northwest - Northern CA 560 3000 1-500 kV DC 2,100 4.7%r S. Wyoming - S. Nevada 635 3000 1-500 kV DC 2,200 5.1%s S. Wyoming - S. Nevada 1270 6000 2-500 kV DC 4,300 5.1%t S. Wyoming - Arizona 900 3000 1-500 kV DC 2,800 6.6%u S. Wyoming - Arizona 1800 6000 2-500 kV DC 5,600 6.6%v Arizona - Southern CA 320 3000 2-500 kV AC 1,700 1.6%w Arizona - Southern CA 640 6000 4-500 kV AC 3,200 1.6%x Wyoming - Mona (Utah) 360 3000 2-500 kV AC 1,900 1.8%y Mona (Utah) - Southern Nevada 280 3000 2-500 kV AC 1,500 1.4%z Mona (Utah) - N.E. Nevada 170 3000 2-500 kV AC 1,000 0.9%
aa Wyoming - Midpoint (Idaho) 420 3000 2-500 kV AC 2,200 2.1%ab Midpoint (Idaho) - N.E. Nevada 220 3000 2-500 kV AC 1,200 1.1%ac Midpoint (Idaho) - N.W. Nevada 280 3000 2-500 kV AC 1,500 1.4%
48