CERN
Alberto Di Meglio
Brussels, 3 April 2009
Project Achievementsand Consortium ManagementETICS 2 Periodic Review
INFSO-RI-223782
Content
Overall project report, providing an overview of:
• Review agenda
• Project structure
• Project goals
• Reviewer Recommendations
• Major achievements
• Deviations and issues
• Consortium management
•2ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Review Agenda
•3ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
14:00 – Demos Andras Milassin (4DSOFT)
14:30 – Future plans, conclusions Alberto Di Meglio (CERN)
14:45 – Q/A session
15:15 – Reviewers Closed Session followed by Feedback
MorningMorning
AfternoonAfternoon
INFSO-RI-223782
•5ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
Project Structure
INFSO-RI-223782
•6ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
Project Structure
Project Technical Committee
Project Manager (PM)
NA1 NA2 SA1
SA2
Advisory Board
Project Management Board
JRA1 JRA2
INFSO-RI-223782
Project Goals
Objective 1
• Extension of the ETICS services to new infrastructures
Objective 2
• Enhancement of the services, federation and customization of resources
Objective 3
• International collaborations, procedures and standards
Objective 4
• Commercial exploitation and business strategies
•7ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Recommendation 1
Work on producing an uninterruptible, fully-operational service, leaving exotic features for a follow up phases, and concentrate in offering users a rewarding experience. Pay emphasis to elements crucial to future commercial viability, such as charging, registration, service level agreements, user feedback processes, etc.
• ETICS 2 is focusing on making the service as stable and usable as possible
• Great attention has been paid to improving the user experience both from the functionality point of view and the service provision point of view
• The identification and definition of requirements for commercial exploitation has been an explicit task of the project within NA2.
•8ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Recommendation 2
Continue the establishment of stronger collaborations with other projects and to promote the use of the ETICS services by as many projects as possible in the research and industrial sector. Lobby for the inclusion of the ETICS build and test system as a function in EGI.
• Collaboration with other projects and infrastructures is the major goal of ETICS 2
• Created links with new infrastructures such as NorduGrid (KnowARC and interoperability tests), BalticGrid (organization of the Summer School of Computing in July 2009) and See-Grid.
• ETICS 2 has taken part in several EGI-DS and UMD workshops
• The ETICS System has been proposed as the underlying software engineering platform for managing UMD
•9ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Recommendation 3
Work towards the establishment of a Grid Quality Certification Standard and provide a full implementation of the model in follow up collaborations.
• The implementation of the Grid-QCM model (now called A-QCM or Automated Quality Assurance Model) is an explicit task of the project.
• Plugins collecting the metrics required by the model have been developed and released with the standard ETICS client.
• An A-QCM report generator has been designed and is being implemented.
• A number of external experts have been consulted to get feedback on the model
• The model will be proposed during the second year to international standardisation bodies like ISO to start the roadmap towards full inclusion in existing or new QA standards
•10ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
1
Build/TestArtefacts
ConfigurationWeb Service
Report/MetricsDB
ConfigurationDB
Execution Engines(Metronome, gLite, UNICORE, etc)
Command Line User Interface
RepositoryWeb Service
ETICS Infrastructure
Physical WorkerNodes
Web Portal
Virtual OS Images
Architecture and responsibilities
•11
SA2
SA1
SA1
SA1
SA1
SA1
SA1
SA1
NA2
NA2
NA2
SA2
NA1
SA2SA1
INFSO-RI-223782
Project AchievementsObjective 1: Extension to new infrastructures
• UNICORE built with ETICS
• Started integration tools for Maven-based projects
• Job submitter redesigned to support pluggable JMS
• Condor, gLite and UNICORE submitters designed and implemented
• Agreement with EGEE on ETICS integration roadmap
• ETICS VO created as a first step, later on users will use their own VOs
• Started integration of ARC, implemented interoperability tests between ARC, UNICORE and partially gLite
• Aerospace applications selected, first build examples implemented
•12ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Project AchievementsObjective 2: Enhancement of services
• Better infrastructure and release management
• Extensive use of virtualization
• Performance improvements in the clients and services
• Extension of repository service with APT/YUM integration
• Several other functional enhancement strongly driven by user requirements
• New SLA and service monitoring tools
• Prototypes of new plugin manager and test workflow designer
•13ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Project AchievementsObjective 3: International collaborations and standards
• Grid-QCM A-QCM
• First A-QCM Report design, start of implementation
• All required QA plugins implemented and deployed
• Strong link with EGI_DS and UMD
• ETICS proposed as software engineering platform for UMD
• New collaborations with major middleware providers (UNICORE, KnowARC) on standard compliances and interoperability
• Collaborations with NorduGrid, BalticGrid, SeeGrid for in technical and dissemination fields (BalticGrid Summer School of Computing)
• Revision of ETICS process towards existing standards (ITIL v2, ISOxxx)
• Active participation to European and international events and in eInfrastructure coordination events
•14ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Project AchievementsObjective 4: Exploitation and business strategies
• Started definition of potential business models
• SWOT analysis, competitors analysis, identification of unique value proposition
• Identified the most suitable targets for commercial exploitation
• Requirements for commercial exploitation collected, prioritized and planned for implementation
• Defined possible post-ETICS 2 scenarios and collaborations
• Presentations, demos, discussions have been organized with several commercial companies to explore the possible exploitation scenarios
•15ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Deviations and Issues
Recruitment and retention
• Several partners have had issues in recruiting and retaining personnel. The problems have affected several partners in the first 6-8 months of operations, mainly in SA1 and SA2
• As a consequence delays in some tasks have been experienced
• Additional effort being recruited in year 2 to compensate
•16ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
Integration of new job submitters PM9 PM12
Implementation of A-QCM report PM9 PM15
A-QCM certification of ETICS, gLite and UNICORE
PM12 PM18
Integration with SourceForge and other repos PM12 PM18
Web applications improvements (wizards) PM12 PM15
INFSO-RI-223782
Deviations and Issues
High-load from gLite development
• Several new requirements
• Many requirements not well-defined, controversial or scarcely used after being implemented
• Requirements communicated late and always urgent (ex. SLC4 to SL5 migration)
• But gLite is a major user who has also greatly contributed to the growth of ETICS, it cannot be ignored
• Now discussing MoU between EGEE and ETICS
• ‘Single contact point’ for requirements agreed
•17ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Deviations and Issues
Advisory Board
• Not established despite the effort put into the task
• The people contacted either did not wish to assume ‘yet another role’ or requested to be paid as consultants
• The only person that accepted, left his job soon afterwards
• Change of strategy• Not a permanent Advisory Board, but ‘requests for advice’ to
specific experts as needed
• Works better, people do not feel constrained by a ‘collaboration’ and contribute more willingly
• Demonstrated with the revision of A-QCM and the planning of the EGEE services deployment roadmap
•18ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
Deliverables and milestones
Deliverables (PM1-12)
• All 24 deliverables submitted
• DSA2.2 should be moved from Public to Restricted since it contains details about the internal organization of ESOC contractors, which cannot be made public
Milestones (PM1-12)
• 11 milestones achieved
• 2 milestones delayed
•19ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
MNA2.4 Two projects are issued with an A-QCM certificate (gLite, UNICORE)
PM12 PM18
MSA2.2 ETICS has integrated support for new identified services
PM12 PM15
INFSO-RI-223782
Financial status
The provisional financial information included in the Periodic Report covering the 1st reporting period shows a total cost of 1,743,991.37€. It represents 92% of the budgeted cost for P1 and 46% of the total budget as per Annex I of the Contract.
Internal Cost Claims (Form C) are being submitted by all partners to the Coordinator and from the Coordinator to the Commission.
The breakdown of expenses is as follows:
Direct Costs: xx%
Indirect Costs: xx%
Personnel: xx%
Travel, subsistence and other costs: xx%
•20ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
INFSO-RI-223782
PPT tool used to monitor project effort consumption (timesheets)
• Total of 169 PM equivalent to 14 FTE/year
• 43 people registered across Europe and USA
Consumed EffortVs. Planned Effort
in P1
Funded Unfunded Total
74.49% 85.47% 77.43%
•21
Effort status
ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009
Total effort planned and consumed (P1)
INFSO-RI-223782
Summary
• The project has achieved most of its planned tasks for the first year
• It has expanded the collaboration with new infrastructures, projects and initiatives
• It has strengthened the functionality and quality of its services
• It has positioned itself at the core of the eInfrastructures software development activities with strong ties with EGI and UMD
• It has developed an initial sustainability strategy with strong focus on potential commercial exploitation
• Some deviations from the plan have been addressed and plans to recover the delays are available
•22ETICS 2 Periodic Review - Project Achievements - Brussels, 3 April 2009