CERC Paper on Open Access Presentation by the MPERC Bhopal At New Delhi 25 September 2003.
-
Upload
jocelin-kelly -
Category
Documents
-
view
217 -
download
0
Transcript of CERC Paper on Open Access Presentation by the MPERC Bhopal At New Delhi 25 September 2003.
CERC Paper on Open Access
Presentation by the MPERC Bhopal
At New Delhi
25 September 2003
Madhya Pradesh Electricity Regulatory Commission2
In this presentation
The Open Access Paper– Pricing design objectives – Existing Scenario– Open access transmission tariff– Methodology and procedure– Energy accounting
Other Discussion Points
Objective(s) of the Paper: 1. To generate a debate on the important issues
a. Identification of key issuesb. Understanding the implicationsc. Understanding stakeholder perspectives
2. Frame regulations
Madhya Pradesh Electricity Regulatory Commission3
Transmission Pricing DesignDefinition of Objectives (3.1)
Objectives defined in the Paper– Efficiency of operations and trading– Efficient use of resources– Signal for investment– Signal for location of generation/load– Compensate owner of the wires– Simple and practical
Comments on Objectives– Agree– Agree– Agree– Agree– Agree– Agree– Ensure safety of grid (Needed for all
users)– Provide regulatory certainty (For overall
development of the power market and removal of uncertainty to attract investors)
– Provide level playing field (To new transmission utilities and transmission users)
Madhya Pradesh Electricity Regulatory Commission4
Existing ScenarioRole of the CTU (2.1), CTU Tariffs (2.2)
Proposals– Current lines based on BPTA’s– Open access only for spare capacity– “Existing transmission agreements will have to
be honored…” for current and future lines built
on BPTA’s
Comments– Agree that open access only for spare capacity– Agree that existing arrangements should be
honored.
– Who is the successor entity to SEB –
State Trader / STU / DICSOM’s?
Division ratio?– What when a BPTA expires, say at the end of 5
years? Consider as Open Access.
Proposals– TSC apportioned based on CGS allocation– Spare capacity paid for by beneficiaries– Open access will reimburse them partially
Comments– Need to decide who pays for unapproved
expansion of system.
– Transmission pays: Transmission
should not be allowed to take
uncovered risks
– Beneficiary pays: In effect he is
subsidizing later users. Preferable.– Relevant Commission must approve the
excess investment in capacity at a certain
margin above what is immediately required
Madhya Pradesh Electricity Regulatory Commission5
Open Access Transmission TariffAlternatives (4.1)
Contract path– May be adopted for those transactions where clear line of power flow can be
determined. Exhibit.
Contract Path
Contract PathB
SellerExporting Region
A
CBuyerImportin
g Region
IPS
IPS
Incremental postage stamp method– Adopt for places where clear lines cannot be determined.– Minimum charge should be fixed for use of transmission facility for very small
distances– Grid support charges also to be levied
Madhya Pradesh Electricity Regulatory Commission6
Open Access Transmission TariffPricing Philosophy (4.2)
Proposals– Ceiling on an all-India basis: Purpose is to
provide a signal for location of lines and transmission system users.
Observations– Purpose of allowing market forces to
operate and create correct economic signals for siting of generation, loads and new lines may not be adequately met
Region
Total TSC
(Rs. Crores)
Ckt-km
Unit TSC
(Rs / km / MW /
Month)
Incremental Postage Stamp Charge
NR 97.06 12525 154.99 2.16
WR 43.40 9168 94.68 1.32
SR 77.15 6847 225.35 3.14
ER 19.13 4752 80.51 1.12
Total 236.74 33292 142.22 1.98
Suggestions– Different postage stamps for different
regions– Concern: Determination of IPS For cross-
regional squares
Madhya Pradesh Electricity Regulatory Commission7
Open Access Transmission TariffPricing Philosophy (4.2)
Proposals– Levy on capacity reservation
Observations– Paper proposes that open access ceiling
be determined assuming average loading of 500 MW as per Annexure I.
– This benefits open access users at the cost of “original beneficiaries”
Comments– Disincentive to BPTA!– Ceiling should be higher than derived
as above– Apply percentage markup – Alternative method may be used for
determination of OA-TSC ceiling based on actual loading and not total line capacity
1. Power flowLines capacity 500 MWFirm Usage 300 MWSpare 200 MWOpen access usage 100 MWIdle capacity 100 MW2. CostsCost (Transmission Charges - TC - for the month) 200 Crores
Unit TSC (Rs. / MW / Month) 0.4(As per proposed method = TC / 500 MW)
Evaluation : Ben - A Ben - B Pure OAAssuming 2 "original" beneficiaries with ratios 0.5 0.5 - Firm usage (MW) [Ratio X Total Firm Usage] 150 150 - Cost incurred for firm transmission (TC / Capacity) 100 100 -
Open access usage (MW) - 50 50 Cost incurred for open access (OA Capacity * Unit TSC) - 20 20 Refunds (OA Income divided among "original benef.") 20 20 - Effective charge 80 100 20 Charge per MW 0.53 0.50 0.40
Assumptions:
Derivation of open access ceiling charge :
Madhya Pradesh Electricity Regulatory Commission8
Open Access Transmission TariffSharing of TSC (4.6), LD Charges (4.7)
Sharing of TSC among beneficiaries (4.6)
Proposals– TSC to be apportioned to regions based
on CGS generation capacity
Comments– Inter-regional TSC should be apportioned
to regions based on BPTA share from CGS plus share of IPP’s
Sharing of LDC charges (4.7)
Proposal– Total LDC charges to be calculated from
the weekly LDC charges divided by installed capacity of CGS = 200 rupees per week per MW = 0.12 P/U
– Revenue to go to reduce costs to original beneficiaries / successors
Comments– Treat all as equal– Bill original beneficiaries also on a weekly
basis– Weekly LDC charges should be divided
by total generation capacity scheduled to be handled in the week = CGS + IPP + Traded power
Madhya Pradesh Electricity Regulatory Commission9
Methodology and ProcedureInformation Systems (5.1)
Proposals– Hourly updating of information – Dissemination over the Internet or other dedicated communication channel
Comments– Incorporate mechanism for advance declaration of available capacity. This will allow
users to plan for open access and a move towards the development of a spot and futures market.
– Frequency of advance declarations:
– Twelve months ahead spare availability information– Week ahead in hourly blocks– Day ahead in 30-minute blocks– Information updating frequency: 30 minutes for actual values in real time.
– Dissemination of information:
– Centrally at NLDC / RLDC’s in tandem– Dedicated communication channels connecting central database, traders,
distribution licensees, transmission utilities. – Information may also be posted on the Internet
Madhya Pradesh Electricity Regulatory Commission10
Methodology and ProcedureNodal Agency (5.2, 5.4)
Proposed: – Processes all applications on FCFS– In order of priority of service
Suggestions: Options may be considered– FCFS.– Bidding.– Beauty Contest. Who judges in case of beauty contest?– Mix of the above.
– What would be an appropriate mix?
– A pecking order should be defined
Madhya Pradesh Electricity Regulatory Commission11
Methodology and ProcedureSpecial Energy Meters (5.8) and Creditworthiness (5.11)
Special Energy Meters (5.8)
Proposals: – As and when required, open access
customer will have to install required special energy meters
Suggestions: – May be an expensive proposition for
small customers.
Credit worthiness (5.11)
Proposals:– Prospective open access consumer
must establish credit-worthiness
Suggestions: – Establish creditworthiness to whom?
CERC / RLDC– What shall be the measurement
basis for creditworthiness?– Creditworthiness of SEB’s very low– Alternatives to measurement of
credit-worthiness: Security deposit, margin money, LC, bank guarantee, advance
Madhya Pradesh Electricity Regulatory Commission12
Methodology and ProcedureTypes of Service (5.13), Priority of Allotment (5.15) and Penalty for Hoarding (5.16)
Types of Service (5.13)– Need to clearly define Firm and Non-Firm. Also, consider number of hours per day.– What is the treatment for Non-Firm agreement longer than 1 Month?– Need to outline difference of charges for Firm and Non-firm power transmission
Long Term >= 1 Y
ShortShort Medium Term: 1 M – 1 Y
Short Term: 1 W – 1 M
1 W – 1 M
1 D – 1 W
1 H – 1 D
{{
Firm Service
Non-Firm Service
Priority of Allotment (5.15)
Proposals:– Hierarchy defined.
Suggestions: – Agree
Penalty for Hoarding (5.16)
Proposal:– CERC to act on complaint.
Suggestions: – Suggest periodic review
Madhya Pradesh Electricity Regulatory Commission13
Methodology and ProcedureCurtailment Due to Constraints
Proposal– Non-Firm users before Firm users– Short-Term users before Long-Term
users1. What if there are two consumers of the same level in
pecking order, and one is paying more or offers to pay more? What considerations for payment history?
2. Why should open access original beneficiaries be the last to be disconnected? Why should they not be treated at par as far as their open access portion is concerned?
1
2
3
4
5
6 >= 1 Y
1 M – 1 Y
1 W – 1 M
1 W – 1 M
1 D – 1 W
1 H – 1 D
{{
Firm Service
Non-Firm Service
Money:The Third Dimension
Suggestion– Pecking order outlined as below.– What is the treatment of Non-Firm agreement
longer than 1 Month?
Define an order considering 1. Firm / Non-firm, 2. Duration and 3. Price Paid
Define an order considering 1. Firm / Non-firm, 2. Duration and 3. Price Paid
Madhya Pradesh Electricity Regulatory Commission14
Energy AccountingActive Energy (6.1), Reactive Energy (6.2) and Energy Loss (6.3)
Active Energy (6.1)
Proposals– Direct CTU users to comply with ABT– Embedded customers to comply with Intra-State
ABT– For embedded customer, STU / SEB to be billed
Suggestions– Fix a minimum threshold for applying ABT
(1. Avoids complexity, and 2. saves customer the cost of Special Energy Meters)
– Dependent on whether and when State implements ABT
– STU should not be billed because it is a pure wires company and has nothing to do with users of its wires adhering to schedules.
– Consider billing the SLDC (1. Incentive for SLDC to perform, 2. May be difficult since SLDC is non-profit). SLDC may pass on to embedded customers or deduct from margin money / advance
Reactive Energy (6.2)
Proposals– Apply to direct CTU customers– Not appropriate to apply to embedded customers
Suggestions– SERC’s shall decide whether to apply to since it
impacts the State system– May have very high cost implications for smaller
open access consumers
Energy Loss (6.3)
Proposals– Measure past weeks losses and apply to ensuing
week.
Suggestions– Agree. Simple, easy to implement and accurate– Consideration for incremental postage stamp
application of losses. It is complex and not necessarily accurate.
Madhya Pradesh Electricity Regulatory Commission15
Additional Discussion Points
Scheduling of direct contracts– Will direct contracts be incorporated into the ABT mechanism?– If yes, above what threshold level of MW contract?– If not, how will any variability on account of them be reconciled with ABT billing?
ABT in case of bilateral agreement / Dishonoring of bilateral agreement– A and B enter into agreement for 50 MW– How will ABT apply to A and B? – Case 1: A feeds the power, B does not draw fully– Case 2: A does not feed power, B continues to draw– Clear need to outline mechanism for settlement
– Wheeling charges
– Energy Accounting
Assessing transmission capacity (Section 5.2)– Uniform mechanism should be adopted by all constituents– CERC may like to outline assessment mechanism
Surcharge (4.9): – How will CERC determine surcharge?– Loss incurred by State utilities – SERC should decide.
MP Electricity Regulatory Commission
Madhya Pradesh Electricity Regulatory Commission17
Open Access Transmission TariffPricing Philosophy – Regional Ceilings
TSC in ER = 10TSC in SR = 41Total TSC = 51
Signal to generators:Move towards SR to reduce number of expensive SR zonesEffect:Generation moves towards load
Signal to transmission utilities:Invest in SR since there is more income to be made. Effect: This will reduce the SR postage stamp.
SR ER
Signal to load:Invest in ER since TSC costs are lower. Effect: Load moves towards generation
TSC in ER = 18TSC in SR = 26Total TSC = 43
Generation
Load
Madhya Pradesh Electricity Regulatory Commission18
Open Access Transmission TariffPricing Philosophy (4.2) – 1
1. Power flowLines capacity 500 MWFirm Usage 300 MWSpare 200 MWOpen access usage 100 MWIdle capacity 100 MW2. CostsCost (Transmission Charges - TC - for the month) 200 Crores
Unit TSC (Rs. / MW / Month) 0.4(As per proposed method = TC / 500 MW)
Evaluation : Ben - A Ben - B Pure OAAssuming 2 "original" beneficiaries with ratios 0.5 0.5 - Firm usage (MW) [Ratio X Total Firm Usage] 150 150 - Cost incurred for firm transmission (TC / Capacity) 100 100 -
Open access usage (MW) - 50 50 Cost incurred for open access (OA Capacity * Unit TSC) - 20 20 Refunds (OA Income divided among "original benef.") 20 20 - Effective charge 80 100 20 Charge per MW 0.53 0.50 0.40
Assumptions:
Derivation of open access ceiling charge :
Madhya Pradesh Electricity Regulatory Commission19
Open Access Transmission TariffPricing Philosophy (4.2) – 1
1. Power flowLines capacity 500 MWFirm Usage 300 MWSpare 200 MWOpen access usage 100 MWIdle capacity 100 MW2. CostsCost (Transmission Charges - TC - for the month) 200 Crores
Unit TSC (Rs. / MW / Month) 0.67(As per proposed method = TC / 300 MW)
Evaluation : Ben - A Ben - B Pure OAAssuming 2 "original" beneficiaries with ratios 0.5 0.5 - Firm usage (MW) [Ratio X Total Firm Usage] 150 150 - Cost incurred for firm transmission (TC / Capacity) 100 100 -
Open access usage (MW) - 50 50 Cost incurred for open access (OA Capacity * Unit TSC) - 33 33 Refunds (OA Income divided among "original benef.") 33 33 - Effective charge 67 100 33 Charge per MW 0.44 0.50 0.67
Assumptions:
Derivation of open access ceiling charge :