CER Update Industry Governance Group 21 st September 2011.

17
CER Update Industry Governance Group 21 st September 2011

Transcript of CER Update Industry Governance Group 21 st September 2011.

CER Update

Industry Governance Group

21st September 2011

Publications

Customer Protection Consultation Decision

Prepayment Metering in the Electricity and Gas Markets (CER/166)

Electricity and Natural Gas Supplier Handbook (CER/11/168)

Demand Side Consultation Decision

Proposed Changes to the Winter Peak Demand Reduction Scheme and Powersave Scheme 2011/12 (CER/11/165)

Market Information – Regular Reports ww.cer.ie – elec retail - reports & publications

Change of Supplier weekly update

Electricity and Gas Customer Disconnections Report July – August 2011

Work streams

Working Groups

Prepayment Meter Project Supplier Group

Forthcoming consultations

Market Monitoring

Licence Review

Smart metering Timelines

Gas trial & Cost Benefit Assessment (CBA) September

Consultation on Smart Metering national rollout design & implementation

October

Decision on Smart Metering national rollout design & implementation

November/December

Sean Mac an Bhaird
I guess we should be referencing debt flagging somewhere here.........

Debt Flagging for Electricity & Gas Customers – Industry Code

Industry Code - Drafting

• Drafting – Input from– Electricity & Gas Market Participants– Office of the Data Protection Commission (ODPC)

• August GMARG/IGG – High Level Aspects

• Draft Code – pre Commission approval circulated to Industry & ODPC

• Commission approval – Re-circulated

• Main points presented today

1. Grounds to Raise a Flag (I)

• As per decision;

• From when amount fell due, not bill issued, this typically 14 days from bill issued.

Customer Category Customer Category Debt Value & Duration Threshold

Domestic > €250 for > 60 days from due

Small Business Elec (LV-NonMD/DG5)Gas (NDM <73MWh)

> €750 for > 60 days from due - TBC

Medium Business Elec (LVMD/DG6)Gas (NDM >73MWh)

> €1,500 for > 60 days from due - TBC

• Outstanding deposits excluded

• Cannot raise a Flag where customer pursuing complaint re monies owed

• Must adhere to Industry thresholds & timings

• Must issue a flag where relevant criterion per customer category has been satisfied.

1. Grounds to Raise a Flag (II)

• Change of Legal Entity (All Customers)– Cannot flag new tenant CoS where debt

accumulated by previous tenant– Elec: CoLE signalled on 110 message

• Losing supplier cannot raise flag • Inferred CoLE – flag not forwarded to new supplier

– Gas: CoLE not signalled → • Options Discussed at August GMARG• ODPC Advice• New supplier ascertain whether new tenant & not yet

signed up – if site flagged – flag ignored.

1. Grounds to Raise a Flag (III)

2. Timings

• Old supplier to raise flag:– Elec: Lists submitted to MRSO by COB on

Mondays & Wednesday– Gas: Within 2 business days

• New supplier to decide action– Elec: Within 2 business days– Gas: Within 3 business days

3. Customer Communication (I)

• Communication Re Flagging Process– ODPC Advice: Domestic Sign Up Process– Customer must be made of aware of debt

flagging at sign up– Notice must be included on domestic customer

application forms – online, paper, phone– Terms & Conditions only not sufficient – Tick Box – read & understood notice– Standard wording, otherwise ODPC sign off

3. Customer Communication (II)

• Communication Re CoS Cancellation• Within 5 business days;• Gaining supplier issue notification in writing:

– CoS request cancelled & why– Advise customer contact current supplier– contact details for MABS or an appropriate

alternative, in the case of domestic customers -TBC.

4. Dual Fuel

• Dual Fuel – Losing Supplier– Can only flag account which meets the industry debt

flagging criterion

• Dual Fuel – Gaining Supplier– Where 1 account is flagged and not the other:– Supplier can only proceed with CoS for non-flagged

account only if obtained customer agreement to switch for one fuel and not dual fuel

– If no agreement obtained, proceed or cancel CoS requests for both accounts

6. Reporting

• CER monitoring debt flagging process

• On monthly basis, receive from DSOs– # CoS requests flagged by losing supplier– # CoS cancellations following flag– Elec Market Only –

• # CoS requests with CoLE

• # Debt flags not forwarded to gaining supplier by MRSO due to inferred CoLE

• CER conduct spot checks from time to time

PPM in Electricity & Gas Markets

Consultation - Background

• Current Economic Climate– CER/10/217 Disconnection CoP Guidelines– Keep disconnection to a minimum: Customer must

be offered a PPM before a Supplier can request a disconnection

– CER/11/106 Debt Flagging Decision– Losing Supplier can flag to gaining supplier where

customer debt above industry thresholds

• Suppliers concern over compatibility of CER/10/217 & CER/11/106

Consultation - Options

• PPM Customer Repaying Debt – 2 Options:

• Option A – Status Quo– Customer ceases paying debt when changes

supplier - supplier pursues customer for outstanding debt separately

• Option B – Debt Travels– Customer must continue to pay off outstanding

arrears after they switch supplier

Consultation – Next Steps

• Responses due 15th September

• Decision Paper issued asap.