Central Subway ProjectContract Modification 123Chinatown-Rose Pak Station Plaza
Wyman Lee, Resident Engineer
SFMTA Board of Directors
December 3, 2019
![Page 2: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/2.jpg)
Extending the T Third• Phase 1 of the 6.8-mile T Third line began
revenue service along the Third Street corridor in April 2007, restoring light rail after 50 years.
• Phase 2 adds 1.7 miles to San Francisco’s first north-south subway with service to SoMa, Downtown, Union Square and Chinatown.
2
![Page 3: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/3.jpg)
Central Subway Overview
Benefits• Connecting dense housing, job
centers, hospitals and growing neighborhoods
• Becoming busiest Muni rail line• Reducing crowding on the 8, 30, 45• Quick BART, CalTrain & Muni transfers
4 New Stations• Chinatown• Union Square/Market• Yerba Buena/Moscone• 4th & Brannan (surface)
Timeline• Conceptual Design (2003–2009)• Final Design (2010–2012)• Construction (2010– Summer 2020)• Revenue Service (Summer 2021)
3
![Page 4: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/4.jpg)
4
Chinatown-Rose Pak Station
Original Station Concept
New Rooftop Plaza Design• Based on community input• “Chinatown’s living room”• Public space to serve the
community• Plans to activate the space
![Page 5: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/5.jpg)
5
Chinatown-Rose Pak Station
Station structural rendering showing the plaza location
![Page 6: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/6.jpg)
6
Contract Modification 123Approval From SFMTA Board:• The project is beyond the monetary threshold that allows the Director of
Transportation approve the contract modification• Seeking approval of this modification and funding increase
Work is Ongoing Today:• As a sign of good faith, Tutor Perini Corporation (TPC) already started the
work• Construction of Plaza Walls began in September 2019 and continues today • The two elevators that serve the plaza are being fabricated and scheduled
to be delivered early February 2020
![Page 7: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/7.jpg)
7
Ongoing Plaza Wall Work
![Page 8: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/8.jpg)
8
Ongoing Steel and Staircase Work
![Page 9: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/9.jpg)
9
Contract Modification 123
• Original Budget - $6,980,000.00
• Expended Budget - $837,876.73
• Current Budget - $6,142,123.27
• Total Contract Modification Amount - $9,360,183.48
• Additional Budget Needed - $3,218,060.21
![Page 10: Central Subway Project Contract Modification 123 Chinatown … · 2019-12-19 · • Final Design (2010–2012) • Construction (2010–Summer 2020) • Revenue Service (Summer 2021)](https://reader034.fdocuments.us/reader034/viewer/2022042221/5ec74cf0158f504a5e4fcc42/html5/thumbnails/10.jpg)
10
RecommendationApprove Contract Modification 123 to have Tutor Perini Corporation construct the new Plaza for Chinatown-Rose Pak Station.