CenTennial STudenT union BallRoom...The cost of duct cleaning and re-coating the interior of damaged...
Transcript of CenTennial STudenT union BallRoom...The cost of duct cleaning and re-coating the interior of damaged...
Predesign Report
CenTennial STudenT union BallRoom
Submitted to:laurie Woodwarddirector of the Centennial Student unionminneSoTa STaTe univeRSiTy, mankaToCentennial Student union, Room Su 220mankato, minnesota 56001
Prepared by:Paulsen architects209 South Second Street, Suite 201Mankato, MN 56001507.388.9811 phone507.388.1751 fax
July 29, 2009Revised: august 6, 2009
CSU Ballroom Summary Report
SECTION 1. SUMMARY 1.2.a. Background
Minnesota State University, Mankato (MSU) is located in the south-central region of the state on a bluff above the Minnesota River approximately 75 miles from the Twin Cities of Minneapolis and St. Paul. The Mankato area is a regional economic center with a population of approximately 50,000. MSU was founded in 1868 as Mankato Normal School with 27 students. Now a comprehensive university, MSU serves approximately 13,000 students. Most are Minnesota residents, but the University's strong academic programs and excellent faculty attract students throughout the United States and from more than 60 other countries. Faculty and staff number approximately 1,300. The original "Valley" campus was located in downtown Mankato. In 1959 the first buildings were completed on the new "Highland" campus, and in 1978-1979 the campus was consolidated into the Highland area. Currently total square footage on the MSU campus is approximately 2.5 million. Alumni now number approximately 90,000. The 2009 Facilities Master Plan provides the framework to accommodate continued growth within the well-established physical patterns of the campus.
1.2.b. Process
Paulsen Architects was engaged to provide the predesign document in December 2005 and an update in 2009. Through a series of interviews and meetings with the users, we were able to develop a concept that addresses the needs of MSU and the user. Our design team then developed several options with feedback from users resulting in the final document included in this study.
1.2.c. Project Scope
The goal of the project is to address and update the CSU Ballroom with the following scope of work: Architectural and Interior Design Demolition
• Remove the existing plaster ceiling and wood veneer on the walls and soffits • Remove the operable partitions • Remove the carpet panels in the lobby
New Construction
• New acoustic ceilings and soffits in the ballrooms and lobby • New carpet panels in the lobby • Replace the operable partitions • New table and chair storage rooms in each ballroom • Add new exit corridors for each ballroom • New acoustic and wood walls in the ballroom • New acrylic wall and ceiling panels in the lobby • Canopies at the existing ticket windows • Paint and install abuse resistant wall covering in ballrooms and lobby
CSU Ballroom Summary Report
CENTENNIAL STUDENT UNION BALLROOM REMODELING
MECHANICAL AND ELECTRICAL COST
MINNESOTA STATE UNIVERSITY, MANKATO
MECHANICAL INFORMATION A. BALLROOM AND LOBBY -MECHANICAL COST ESTIMATE
1. Removal of existing ductwork $ 8,000 2. New ductwork and duct wrap @ $12/sq.ft. x 11,760 sq.ft. $141,120 3. New outlets -50 @ $250 each $ 12,500 4. Lobby -3,605 sq.ft. @ $8/sq.ft. $ 28,840 5. Revise automatic controls -4 units @ $2000 each $ 8,000
Sub Total $198,460 B. ADDITIONAL DUCTWORK -NORTH & SOUTH CONFERENCE ROOMS
1. Supply air ductwork in side wall soffits for North and South Conference Rooms -$4,000 each for 8 spaces $ 32,000
Sub Total $ 32,000 C. ENERGY RECOVERY UNITS
1. Ballrooms -3 systems $ 80,000 2. Install energy units -3 @ $6,000 each $ 18,000 3. Duct modifications for recovery -3 units $ 6,000 4. Automatic Temperature Control Interface -3 units $ 3,000
Sub Total $107,000 D. AIR HANDLING UNIT REPLACEMENT
1. Removal of four (4) air handling units for Ballroom and Lobby at $2,000 each $ 8,000
2. Four new air handling units @ $13,000 each $ 52,000 3. Piping in Third Floor Mechanical Room -chilled water and steam $ 12,000 4. New and upgraded automatic temperature controls and
frequency drives -4 @ $18,500 each $ 74,000 Sub Total $146,000
E. REVISE FIRE PROTECTION PIPING
1. Ballroom -11,760 sq. ft. @ $2/sq.ft. $ 23,520 2. Lobby -3,605 sq.ft. @ $1/sq.ft. $ 3,605
Fire Protection/Sprinkler $ 27,125 F. OPTIONAL RETURN AIR DUCTWORK -201 THROUGH 205, 217 THROUGH 219
1. Main Ducts 100 feet @ $50/ft = $5,000 x 2 sides $ 10,000 2. Ducts into Meeting Rooms -12 ft @ $60/ft = $720 x 9 $ 6,480 3. Summary of Conference Room Return Ducts
$10,000 with no Corridor work. $16,480 with new soffit or ceilings in two existing corridors.
CSU Ballroom Summary Report
G. SUMMARY OF MECHANICAL 1. Ballroom/Lobby $198,460 2. Supply Air North and South Conference Rooms $ 32,000* 3. Energy Recovery Units $107,000 4. Replace AHU's -4 thus $146,000* 5. Fire Protection $ 27,125 6. Optional Corridor Return Air Ductwork $ 16,480 Mechanical = $510,585
* = Work that could be done at a later date Mechanical Total "A" -Work Done with Ballroom Renovation $332,585 Mechanical Total "B" -Work in Ballroom Plus Air Handling Units $478,585 Mechanical Total "C" -Ballroom, Air Handling Units, Ductwork for Corridors $527,065
CSU Ballroom Summary Report
I. MSU BALLROOM AREA
A. The three existing Ballroom air handling units (#4, #7, #9) are all the same size. Delivering 8,400 CFM each -Total = 25,200 CFM 45% Outside Air each = 3,780 CFM each x 3 = 11,340 CFM O.A. Cooling coil listed @ 38.4 tons x 3 = 115.3 tons
Listed coil leaving conditions of 55 DB/54.3 WB. Will not dehumidify the space with the large percentage of outside air for the people with the large load
B. Our Projected Cooling Loads
1) With Food-Dining Tons CFM OA CFM South Ballroom 19.64 3,519 3,000 Center Ballroom 25.78 4,540 4,000 North Ballroom 19.64 3,519 3,000
(Total of 500 people) Loads Total With Dining 65.06 11.578 10,000
(20 MAC)
2) Non Food Meeting Tons CFM OA CFM South Ballroom 28.47 4,917 4,500 Center Ballroom 37.56 6,414 6,000 North Ballroom 28.47 4,917 4,000
(Total of 1,000 people) Loads Total For a Meeting 94.5 16,248 15,000
(14.1 MAC) (Using approximately 300 CFM/ton, new systems should supply 33,000 CFM @ 45% O.A.) (7 MAC)
II. MSU BALLROOM LOBBY
A. One existing Air Handling Unit #6. Delivering 6,200 CFM (6.2 MAC) @ 24% outside air = 1,550 CFM. Cooling capacity listed @ 17.4 tons.
Existing cooling coil leaving conditions were listed at 58° dry bulb/57.5° wet bulb. These conditions will not effectively cool the space and dehumidify at the same time especially with an estimated 115 people in the space.
B. Our projected load for the Lobby is 12.27 tons, 2,508 CFM of supply air, 1,725 CFM
of outside air. 38,468 cu.ft. (2508 CFM = 15 MAC) @ 350 CFM/ton = 4,300 CFM @ 8.6 MAC.
Existing 6,200 CFM would be a good air change. The 1,725 CFM OA will be 27% OA. Meets load requirements.
CSU Ballroom Summary Report
III. MSU BALLROOM AREA GENERAL COMMENTS
A. All of the existing supply air and return air ductwork has duct liner, including the fresh air intake ductwork. MNSCU Standards require that the ductwork be replaced with new wrapped ducts. No liner.
The cost of duct cleaning and re-coating the interior of damaged duct liner costs the same as new wrapped supply and return air ductwork. As such, all of this ductwork will need to be replaced.
The fresh air intake ductwork should be replaced to meet indoor air quality standards for all four units.
B. The existing three Ballroom spaces have two gravity relief vents in each space. Our
recommendation will be to provide a heat recovery unit over each Ballroom for exhaust air discharge above the roof and a fresh air intake system with energy being reclaimed from the exhaust air into the fresh air through a heat recovery wheel.
IV. EQUIPMENT/LOAD REDUCTION A. The three energy recovery units that are being proposed to reduce cooling and heating
coil loads will have a payback of 2 to 3 years. (Based on a run-time of 60 hours per week.) With 30 hours per week run-time, the payback will be 4 to 6 years.)
B. Any structural revision costs and roofing patching costs are not included in the cost
estimates. C. Past MSU,M comments indicated that the Ballroom roof is in need of replacement and
should be looked at during this study. V. EXISTING EQUIPMENT
A. The existing air handling units are all past their full life expectancy of 20 to 25 years. (They are 40 years old.)
B. Valves, fittings, traps and controls are all at or over the useful life expectancy also and
should be replaced.
CSU Ballroom Summary Report
ELECTRICAL INFORMATION A. BALLROOM -ELECTRICAL COST ESTIMATE
1. Demolition $ 5,000 2. General Lighting and Control $142,000 3. LED Lighting and Control $ 17,500 4. Distribution Panel $ 3,000
Sub-Total $167,500 B. LOBBY -ELECTRICAL COST ESTIMATE
1. Demolition $ 2,000 2. General Lighting and Control $ 11,000
Sub-Total $ 13,000 C. ENERGY RECOVERY UNITS -ELECTRICAL COST ESTIMATE
1. Power to (3) Units $ 4,000 Sub-Total $ 4,000
D. AIR HANDLING UNITS -ELECTRICAL COST ESTIMATE
1. Demolition of (4) Units $ 1,000 2. Power to (4) Units $ 9,000
Sub-Total $ 10,000 E. SUMMARY OF ELECTRICAL
1. Ballroom $167,500 2. Lobby $ 13,000 3. Energy Recovery Units $ 4,000 4. Air Handling Units $ 10,000
Total $194,500
CSU Ballroom Summary Report
1.2.d. Proposed Project Budget
MSU CENTENNIAL STUDENT UNION BALLROOM COST ESTIMATE
2010 Description Amount Division 1 General Conditions $201,000.00 Division 2 Demolition $39,000.00 Asbestos Abatement (includes ceiling demo) $604,500.00 Division 6 Rough Carpentry $13,000.00 Division 7 Thermal & Moisture Protection $19,500.00 Division 8 Doors $104,000.00 Division 9 Finishes $464,000.00 Division 10 Equipment $3,900.00 Division 15 Mechanical $390,100.00 Division 16 Electrical $223,000.00 Overhead & Profit $149,000.00
Subtotal $2,211,000.00 Contingency 10% $221,100.00 SUBTOTAL $2,432,100.00
A/E Fees $218,889.00 Reimbursable expenses $7,000.00
TOTAL $2,657,989.00
Add Alternates
Alternate #1 - Lobby General Conditions (10%) $15,095.00 Architectural $82,000.00 Mechanical $42,178.00 Electrical $16,900.00 Overhead & Profit (7%) $9,875.00
Subtotal $166,048.00 Contingency 10% $16,604.80 SUBTOTAL $182,652.80
A/E Fees $16,438.75 TOTAL $199,091.55
Alternate #2 - Air Handlers General Conditions (10%) $21,700.00 Mechanical $189,800.00 Electrical $13,000.00 Overhead & Profit (7%) $14,196.00
Subtotal $238,696.00 Contingency 10% $23,869.60
CSU Ballroom Summary Report
SUBTOTAL $262,565.60 A/E Fees $23,630.90
TOTAL $286,196.50
Alternate #3 - Additional Ductwork - North/South Conference Rooms General Conditions (10%) $4,451.00 Mechanical $41,600.00 Overhead & Profit (7%) $2,912.00
Subtotal $48,963.00 Contingency 10% $4,896.30 SUBTOTAL $53,859.30
A/E Fees $4,847.34 TOTAL $58,706.64
Alternate #4 - Return Air Ductwork General Conditions (10%) $2,292.00 Architectural/Mechanical $21,424.00 Overhead & Profit (7%) $1,500.00
Subtotal $25,216.00 Contingency 10% $2,521.60 SUBTOTAL $27,737.60
A/E Fees $2,496.38 TOTAL $30,233.98
CSU Ballroom Summary Report
1.2.e Project Schedule
PROJECT PHASES & TASKS Dates
Pre- Design • Confirm the original Pre-design document • Field verification of existing conditions — for site and buildings within scope of project • Evaluate existing building systems to determine capacities
9/2009
Schematic Design • On-site design charrettes/workshops to develop schematic design options • Development of interior design concepts, along with furnishing suggestions and concepts • Creation of phasing concepts to maintain ongoing classes, facility use, pedestrian circulation • Cost estimating based on the conceptual concepts generated • Review of building code and life safety code, accessibility and way finding design issues
10/2009-
11/2009
Design Development • Develop design concept: generate interior project massing, floor plans, sections, elevations, interior layouts, details, finishes, equipment layouts, and material selection • Conduct open house on campus for review with administration, students and faculty • Develop outline specification: project systems, products, & quality levels required • Cost estimate to ensure the project is within the previously established budget • Documentation and design complies with MnSCU construction standards • Local and state authorities having jurisdiction to ensure the project design complies with building and life safety codes, as well as the ADA guidelines for accessibility • Develop a project schedule meet the project deadline • Address V.E. items if required
11/2009-
1/2010
Construction Documents • Coordinate structural, mechanical, electrical, plumbing, and technology consultants • 50% Plan Set Review for CSU & MnSCU • Documents submitted for code review and permit application to the authority having jurisdiction • Final cost estimate to ensure the project budget is on track • 90% Plan Set Review with CSU & MnSCU • Issue CD’s
1/2010-
4/2010
Bidding • Documents will be distributed electronically or in print form • Field questions that arise and issue addenda as needed • Assist CSU to evaluate the bids & select the contractors based on state law
4/2010
Construction and Construction Administration • Lead and attend weekly owner / architect job site meetings to review construction progress, resolve questions and document the meeting proceedings • Review and approve pay applications for construction work, based on work completed meeting the project documents • Resolve contractor questions by on site meetings, Architect’s Supplemental Instructions, and Proposal Requests. Respond to the contractor’s Requests for Information • Final review of work to create punch lists, develop the Certificate of Substantial Completion + One year anniversary of substantial completion review warranty items as outlined in the specifications
5/2010-
8/2010
1.2.f Architectural Plans (see attached)