Ce presentation 17 08 2010

24
NEW ECONOMICAL CONNECTION SOLUTION FOR FLEXIBLE PIPING SYSTEMS Christian Engel Thermaflex International Holding

Transcript of Ce presentation 17 08 2010

Page 1: Ce presentation 17 08 2010

NEW ECONOMICAL CONNECTION SOLUTION

FOR FLEXIBLE PIPING SYSTEMS

NEW ECONOMICAL CONNECTION SOLUTION

FOR FLEXIBLE PIPING SYSTEMS

Christian Engel

Thermaflex International Holding

Page 2: Ce presentation 17 08 2010

I will show you a new generation of house connections that result in 4 to 5 times faster installation Significant reduction of number of

connections on site Lower overall investment costs

25% of network costs are related to house connections

Page 3: Ce presentation 17 08 2010

What are typical problems you are facing with connections?

Page 4: Ce presentation 17 08 2010

Corrosion problems have to be solved

Page 5: Ce presentation 17 08 2010

Problems from Weather & Installation conditions

gjb
in all these following picture slides, the layout and size of the pics should be quite the same
Page 6: Ce presentation 17 08 2010

Problems from tight installation situations

Page 7: Ce presentation 17 08 2010

Problems with pressure to complete

the site ?

Page 8: Ce presentation 17 08 2010

What are the basic requirements for connections?

Page 9: Ce presentation 17 08 2010

Connections should be as SAFE as the pre-fabricated pipe!

Page 10: Ce presentation 17 08 2010

Current Systems don‘t provide this safety

Page 11: Ce presentation 17 08 2010

The new Solutions from Thermaflex

Pre-fabricated BranchesPre-fabricated Networks

Page 12: Ce presentation 17 08 2010

FlexaLink the flexible house connection

Main pipe

House connection

.. mtr

.. mtr

Page 13: Ce presentation 17 08 2010

FlexaLink in a typical project

Straight connection

Page 14: Ce presentation 17 08 2010

FlexaLink Reference Projects

• Eneco Heating– Wijk Schollevaar, Capelle a/d/ IJssel– Ca. 300 houses with Installer Niessink– 2010-2011 ca. 1.500 houses

• District Heating Purmerend– Wijk Walakker– 16 houses with contractor A.Hak– 2010 ca. 400 houses tot. ca. 4.000

Page 15: Ce presentation 17 08 2010
Page 16: Ce presentation 17 08 2010
Page 17: Ce presentation 17 08 2010
Page 18: Ce presentation 17 08 2010
Page 19: Ce presentation 17 08 2010
Page 20: Ce presentation 17 08 2010
Page 21: Ce presentation 17 08 2010

FlexaLink shows overall top results

Hot water system Installed house Total cost per "Energy label" Lifetimecost per house per day - Hot Water house system Realised / expected

Expected:Traditional Flexalen 3 á 4 houses € 646,59 B 50 yearsincl. circulation line

ExpectedPrefab Tees Flexalen 2 houses € 1.108,39 A NAincl. circulation line Not installed

Expected:Flexalen FlexaLink 8 á 9 houses € 831,49 A+ 50 yearsincl. circulation line

Realised:Copper system 2 houses € 901,70 C * minimal: 6 yearsincl. circulation line max: 15-20 years

Realised:Steel system 2 houses € 869,54 C * minimal: 10 yearsincl. circulation line max: 25-35 years

Installation time per day per person 6,5 uur netto(5 man)Labour cost per hour á € 35,-Material cost nett per house is the average of 10 houses

Page 22: Ce presentation 17 08 2010

Conclusions

Flexalen FlexaLink – the cost efficient and safe Solution:

Reducing the installed cost up to 30%

Increasing the speed of installation 4-5 times

Reducing disturbance for neigbourhoods

Confirmed by practical experiences in NL

Page 23: Ce presentation 17 08 2010

From pre-fabricated branches to pre-fabricated networks is the next step

Page 24: Ce presentation 17 08 2010

Thank you for your attention!

 

Time for questions...