CE 405 - SCHEDULING The term that you will use throughout the rest of your career to define the...
-
Upload
katrina-bridges -
Category
Documents
-
view
215 -
download
1
Transcript of CE 405 - SCHEDULING The term that you will use throughout the rest of your career to define the...
CE 405 - SCHEDULING
The term that you will use throughout the rest of your career to define the individual work items is “Activity”.
Depending on the Project, Activities can be excessively detailed, or they can be extremely broad.
CE 405 - SCHEDULING
A billion dollar nuclear power plant summary schedule would be an example of a “broad” schedule – an entire multi-million dollar building might be a single Activity on this Schedule.
CE 405 - SCHEDULING
A weekend bridge demolition requiring a railroad closure would be an example of a very “detailed” Schedule where Activities are broken down on an hour-by-hour basis.
ACTIVITIES
Review: What is the Definition of a Construction Project Activity?
“An Activity is a discrete part of a Project that can be identified for planning, scheduling, monitoring, and controlling the Project.”
ACTIVITIES
“An Activity is a discrete part of a Project that can be identified for planning, scheduling, monitoring, and controlling the Project.”
Where have we seen these 4 terms before?
ACTIVITIES
Planning, scheduling, monitoring, and controlling are the four Project Management functions.
ACTIVITIES
Planning, scheduling, monitoring, and controlling are the four Project Management functions.
Extrapolating these two concepts – Activities are what you use to Manage your Project
You get to decide how detailed or broad you want your Activities to be.
ACTIVITIES
5 characteristics of Activities?
1. Activities consume time.
2. Usually consume resources.
ACTIVITIES
5 characteristics of Activities?
1. Activities consume time.
2. Usually consume resources.
3. Have a definable start and finish.
ACTIVITIES
5 characteristics of Activities?
1. Activities consume time.
2. Usually consume resources.
3. Have a definable start and finish.
4. Activities are assignable.
ACTIVITIES
5 characteristics of Activities?
1. Activities consume time.
2. Usually consume resources.
3. Have a definable start and finish.
4. Activities are assignable.
5. Activities are measurable.
ACTIVITIES
What is the number one fundamental purpose of a Schedule?
Communicates When each Activity is planned to be accomplished.
ACTIVITIES
When is each Activity planned to be accomplished?
It logically follows that:
1. Activities consume time.
ACTIVITIES
1. Activities consume time. You will have events that you
want to include on your Schedule that mark a point in time – these events are referred to in Scheduling jargon as milestones.
ACTIVITIES
1. Activities consume time. You will have events that you
want to include on your Schedule that mark a point in time – these events are referred to in Scheduling jargon as milestones.
What is jargon?
ACTIVITIES
What is jargon? Every trade has unique
definitions for specific words The Glossary at the end of your
text contains common Scheduling terms – study it – You will need it for the midterm & final
ACTIVITIES
Definition of “course”:
1. Highway work – a layer of gravel or bituminous (base course)
2. Masonry – a horizontal row of brick or CMU block
3. Golf – a grassy pasture where you knock a ball around
ACTIVITIES
2. Activities consume Resources. (Usually, but not always) Review: What is the definition of
Resources on a Construction Job?
ACTIVITIES
Resources:What you build into your Estimate
for a ProjectLabor, materials, equipment,
subcontractorsMoney will sometimes also be
considered a resource (financing)
ACTIVITIES
3. Activities have a definable start and finish.
What determines when a work Activity can Start?
ACTIVITIES
What determines when a work Activity can Start?
When all the required preceding work is Finished (Predecessors).
When you have all the Resources available on the Jobsite that are needed to Start the work.
ACTIVITIES
3. Activities have a definable start and finish.
What determines when a work Activity has Finished?
ACTIVITIES
What determines when a work Activity has Finished?
When you can Start any follow-on work Activities (Successors) that depend on the completion of that Activity
ACTIVITIES
1. When you can Start any follow-on work Activities (Successors) that depend on the completion of that Activity.
What is the term we use to define this degree/level of completion on a Construction Project?
ACTIVITIES
What is the term we use to define this degree/level of completion?
Substantial Completion
We are talking about Activity Substantial Completion in this case – not Project Substantial Completion
ACTIVITIES
The terms Predecessor, Successor, and Concurrent are fundamental terms within Scheduling jargon
These are the three basic Activity inter-relationships when you are establishing your Project’s logic
ACTIVITIES
4. Activities are “assignable”. What does this mean? Responsibility and Accountability
for completing a given Activity can be delegated to either:
1) Individual (Foreman)
2) Entity (Subcontractor, Supplier)
ACTIVITIES
Importance of Activities being assignable?
When you have hundreds or thousands of Activities on a Project – you need to delegate Responsibility for as many of those Activities as possible to someone else rather than yourself.
ACTIVITIES
Responsibility (per Webster)
1. “liable to be called on to answer”
2. “liable to legal review, or in case of fault – to penalties”
3. “marked by or involving accountability”
ACTIVITIES
Accountability (per Webster)
1. “Answerable”
2. “A statement explaining one’s conduct”
3. “A statement of reasons, causes, grounds, or motives”
ACTIVITIES
Back to the original question: What is the difference between
Responsibility and Accountability?Which is the more powerful term?
ACTIVITIES
Which is the more powerful term?Accountability.When the day of reckoning comes for
anything that you are responsible for – your ability to accurately account for what happened may make the difference as to whether you keep your Job or not
ACTIVITIES
What gives you the ability to accurately account for everything that occurs on a Construction Project?
ACTIVITIES
What gives you the ability to accurately account for everything that occurs on a Construction Project?
DocumentationThe notes/reports/diary that you write
up at the end of every day!!!!!This can not be over-emphasized
ACTIVITIES
5. Activities are measurable. In order to determine the status of
your Project (degree of completion) – you will need to periodically assess how much work has been done (i.e. 25% complete) on each Activity, and then sum those up to determine the total Project status.
ACTIVITIES
5. Activities are measurable. Since monthly progress payments
are based on work completed, the Schedule is the tool used to determine how much money that the Contractor should receive each month
ACTIVITIES
5. Activities are measurable. All of the basic contract formats
(AIA, AGC, FAR, MDT) require the Contractor to submit an updated Schedule with the monthly payment request – otherwise the payment request will be rejected
ACTIVITIES
5. Activities are measurable. What will make your life easier
when it comes to “measuring” how much work has been completed?
ACTIVITIES
5. Activities are measurable. What will make your life easier
when it comes to “measuring” how much work has been completed?
Detailed Schedule
ACTIVITIES
What are the 5 types (Categories) of Activities that you will have on a Construction Project?
ACTIVITIES
Types (Categories) of Activities:
1. Administration
2. Mobilization/Demobilization
(Mob/Demob)
ACTIVITIES
Types (Categories) of Activities:
1. Administration
2. Mobilization/Demobilization
3. Procurement
ACTIVITIES
Types (Categories) of Activities:
1. Administration
2. Mobilization/Demobilization
3. Procurement
4. Construction
ACTIVITIES
Types (Categories) of Activities:
1. Administration
2. Mobilization/Demobilization
3. Procurement
4. Construction
5. Start-up and Testing
ACTIVITIES
“Administration” Activities Notice-to-Proceed (NTP)
> What is the significance of the
NTP?
ACTIVITIES
“Administration” Activities Significance of the NTP? This is when the Owner gives the
Contractor a written “directive” to start work
Day One of your contract performance period
ACTIVITIES
“Administration” Activities Notice-to-Proceed (NTP) Permits/Licenses Change Orders (Contract
“Modifications”)
ACTIVITIES
“Administration” Activities Notice-to-Proceed (NTP) Permits/Licenses Change Orders (Modifications) Quality Control Procedures
ACTIVITIES
“Administration” Activities Notice-to-Proceed (NTP) Permits/Licenses Change Orders (Modifications) Quality Control Procedures Acceptance – Substantial and
Final Completion
ACTIVITIES
2. Mob/Demob Activities What are some examples of
Mobilization and Demobilization Activities?
ACTIVITIES
Mob/Demob Activities:
1. Field Office/Secure Storage Area
2. Utilities – Power, Water, Electric
ACTIVITIES
Mob/Demob Activities:
1. Field Office/Secure Storage Area
2. Utilities – Power, Water
3. Hire/Train Work Crews
ACTIVITIES
Mob/Demob Activities:
1. Field Office/Secure Storage Area
2. Utilities – Power, Water
3. Hire/Train Work Crews
4. Obtain/Deliver/Set-up Equipment
- Cranes, Forklifts, Heavy Equip
ACTIVITIES
Mob/Demob Activities:
1. Field Office/Secure Storage Area
2. Utilities – Power, Water, Toilets
3. Hire/Train Work Crews
4. Obtain/Deliver/Set-up Equipment
5. Layout Work (Surveys)
ACTIVITIES
Types (Categories) of Activities:
1. Administration
2. Mobilization/Demobilization
3. Procurement
4. Construction
5. Start-up and Testing
ACTIVITIES
Procurement Activities: What is the definition of
Procurement? The process of obtaining
materials, supplies, etc. that you will need to get the Project done
ACTIVITIES
Procurement Activities: Your primary work effort be
associated with Procurement on your Job will be the preparation and processing of Submittals.
ACTIVITIES
Submittals are:
1. Shop Drawings,
2. Fabrication Drawings,
3. Catalog Cuts,
4. Manufacturer’s Literature, etc. They describe what you intend to
install in the Project
ACTIVITIES
Preparing Submittals: Submittals are done in advance –
before you start work on the Activity they are associated with
Proactive, prevention oriented
ACTIVITIES
Preparing Submittals:
Communication tool used to inform the Owner and the A/E of the materials and equipment that you intend to install in the finished product
ACTIVITIES
Submittals: The Owner and/or A/E’s review of
your Submittals provides them with the opportunity to agree or disagree with your interpretation of the contract requirements before the material is installed
ACTIVITIES
Submittals: What potential pitfalls do you see
with the Submittal process regarding your Schedule?
ACTIVITIES
Potential Submittal process pitfalls? How long will it take the A/E to
review the submittals? What happens if a submittal is
rejected?
ACTIVITIES
Potential Submittal process pitfalls? How long will it take the A/E to
review the submittals? 30 Calendar Days is standard
What happens if a submittal is rejected? You start all over again!
ACTIVITIES
3. Procurement Activities On a Construction Project, what
are the steps in the Procurement process?
ACTIVITIES
Procurement Process Steps:
1. Identify what you need
2. Obtain quotes from different potential Suppliers
ACTIVITIES
Procurement Process Steps:
1. Identify what you need
2. Obtain quotes
3. Select a Supplier
ACTIVITIES
Procurement Process Steps:
1. Identify what you need
2. Obtain quotes
3. Select a Supplier
4. Shop Drawing Preparation
ACTIVITIES
Procurement Process Steps:
1. Identify what you need
2. Obtain quotes
3. Select a Supplier
4. Prepare Shop Drawings
5. Submit/Review of Shop Drawings
PROCUREMENT PROCESS STEPS
1. Identify what you need
2. Obtain quotes
3. Select a Supplier
4. Prepare Shop Drawings
5. Submit/Review of Shop Drawings
6. Receive Shop Drawing Approval
PROCUREMENT PROCESS STEPS
1. Identify what you need
2. Obtain quotes
3. Select a Supplier
4. Prepare Shop Drawings
5. Submit/Review of Shop Drawings
6. Receive Shop Drawing Approval
7. Prepare/Process Purchase Order
PROCUREMENT PROCESS STEPS
1. Identify what you need
2. Obtain quotes
3. Select a Supplier
4. Prepare Shop Drawings
5. Submit/Review of Shop Drawings
6. Receive Shop Drawing Approval
7. Prepare/Process Purchase Order
8. Supplier Fabricates Item
PROCUREMENT PROCESS STEPS
1. Identify what you need
2. Obtain quotes
3. Select a Supplier
4. Prepare Shop Drawings
5. Submit/Review of Shop Drawings
6. Receive Shop Drawing Approval
7. Prepare/Process Purchase Order
8. Supplier Fabricates Item
9. Delivery of Item to Jobsite
PROCUREMENT LADDER
1. Identify what you need2. Obtain quotes3. Select a Supplier4. Prepare Shop Drawings5. Submit/Review of Shop Drawings6. Receive Shop Drawing Approval7. Prepare/Process Purchase Order8. Supplier Fabricates Item9. Delivery of Item to Jobsite10. Install Item in the Project
PROCUREMENT PROCESS STEPS
How Long might it take you to get a unique, specialty fabricated item (i.e. not “off-the-shelf”) for your Project?
PROCUREMENT PROCESS STEPS
1. Identify what you need – 1 week2. Obtain quotes – 1 week3. Select a Supplier – 1 week4. Prepare Shop Drawings – 2 weeks5. Submit/Review of Shop Drawings – 1 wk6. Receive Shop Drawing Approval – 4 wks7. Prepare/Process Purchase Order – 1 wk8. Supplier Fabricates Item – 8 wks9. Delivery of Item to Jobsite – 1 wk> Total time = 20 weeks = 5 months
ACTIVITIES
This 10 step Procurement Process is often called the “Procurement Ladder”
One of your primary responsibilities as a Project Manager is to identify and control “long lead-time” materials and installed equipment, and build them into the Schedule
ACTIVITIES
Will each of the 10 steps in the “Procurement Ladder” be a separate Activity?
NoBut for your significant Procurement
Activities, the Procurement Ladder will generate several Activities
ACTIVITIES
Which of the “Procurement Ladder” steps on the following slide will be separate Activities when they relate to a significant part of your Project?
PROCUREMENT LADDER
1. Identify what you need2. Obtain quotes3. Select a Supplier4. Prepare Shop Drawings5. Submit/Review of Shop Drawings6. Receive Shop Drawing Approval7. Prepare/Process Purchase Order8. Supplier Fabricates Item9. Delivery of Item to Jobsite10. Install Item in the Project
PROCUREMENT LADDER ACTIVITIES
1. Identify what you need2. Obtain quotes3. Select a Supplier4. Prepare Shop Drawings5. Submit/ Review of Shop Drawings6. Receive Shop Drawing Approval7. Prepare/Process Purchase Order8. Supplier Fabricates Item9. Delivery of Item to Jobsite10. Install Item in the Project
PROCUREMENT LADDER ACTIVITIES
1. Prepare Shop Drawings
2. Submit/ Review of Shop Drawings
3. Prepare/Process Purchase Order
4. Supplier Fabricates Item
5. Install Item in the Project One significant Procurement related
item of work can easily result in five Activities on your Schedule
PROCUREMENT ACTIVITIES
Project Management is:
“having the right equipment and the right materials available at the right time and in the right quantities.”
Having too much can be as bad as not having enough – where do you store excess materials?
ACTIVITIES
4. Construction Activities
- These are pretty straight-forward: Sitework Building the Structure Work by MEP Subs (and others) Interior Finishes
ACTIVITIES
5. Start-up and Testing ActivitiesWhat are some examples of Start-
up and Testing Activities?
ACTIVITIES
5. Start-up and Testing Activities:
1. Major Installed Equipment – HVAC, Standby Generators, etc.
2. Life Safety and Security Systems
3. Sterilizing Water Piping
4. Manufacturing Processes – Mechanical Systems
ACTIVITIES
5. Start-up and Testing ActivitiesWhat “phase” of the Job will you
usually find these Activities?
ACTIVITIES
5. Start-up and Testing ActivitiesWhat “phase” of the Job will you
usually find these Activities?Commissioning Phase –
immediately prior to the final inspections
ACTIVITIES
Activity IdentificationHow do you determine what
Activities you are going to build into your Project Schedule?
ACTIVITIES
Activity Identification1. Detailed review of all contract
documents2. Past practices of your Company
on similar projects they have completed in the past
3. Bid Estimate/ Bidding Documents4. Subcontractor/Supplier input
ACTIVITIES
Activity Identification
1. What work has to be done?
2. Where is the work being done?
3. Who is responsible for the work?
ACTIVITIES
Activity Identification
1. What work has to be done?
2. Where is the work being done?
3. Who is responsible for the work?
4. When will the work be performed?
ACTIVITIES
Activity Identification
1. What work has to be done?
2. Where is the work being done?
3. Who is responsible for the work?
4. When will the work be performed?
5. How will the work be accomplished?
ACTIVITIES
Activity Detail
What is the appropriate level of detail for:
$500K residential home$5M Bozeman Library$10M highway road project
ACTIVITIES
Activity Detail
“Goldilocks Paradox”Too much detail – confusing Too little detail – lacking info
ACTIVITIES
Activity Detail
“Goldilocks Paradox”Too much detail – confusing Too little detail – lacking infoJust right – depends on who is
working on a given Activity
LEVEL OF ACTIVITY DETAIL
1. What’s the purpose of the Schedule
2. How complex is this part of the work
- different parts of a Project may require different levels of detail
LEVEL OF ACTIVITY DETAIL
1. What’s the purpose of the Schedule
2. How complex is this part of the work
3. What is your Company’s philosophy
- detailed for the Jobsite?
- summary for the Home Office?
LEVEL OF ACTIVITY DETAIL
1. What’s the purpose of the Schedule
2. How complex is this part of the work
3. What is your Company’s philosophy
4. What do you know about the work
- if it’s a Fast-Track Job, do you have enough info to Schedule the work?
LEVEL OF ACTIVITY DETAIL
1. What’s the purpose of the Schedule
2. How complex is this part of the work
3. What is your Company’s philosophy
4. What do you know about the work
5. Who is responsible for the work
- will a sub provide the Schedule for its work?
LEVEL OF ACTIVITY DETAIL
1. What’s the purpose of the Schedule
2. How complex is this part of the work
3. What is your Company’s philosophy
4. What do you know about the work
5. Who is responsible for the work
6. Will more or less detail make the Schedule more useful or accurate?
LEVEL OF ACTIVITY DETAIL
In Scheduling Jargon, what does the term “task” mean?
A “task” is a sub-element of an Activity
Tasks are individual items of work that all need to be accomplished for an Activity to get done
LEVEL OF ACTIVITY DETAIL
Tasks in a Concrete Footing Activity?1. Obtain formwork boards/stakes2. Obtain tools – maul, stringline, level3. Shoot grade/level subgrade4. Install forms5. Order/deliver/place concrete6. Finish/cure concrete7. Strip forms and backfill/compact
LEVEL OF ACTIVITY DETAIL
On large or repetitive work Projects, Activities may be broken down by location or station:
2nd floor concrete deck Base course – stations 5+00 - 10+00
LEVEL OF ACTIVITY DETAIL
Some Owners restrict the time length of Activities to a period that can be more accurately measured
The Montana Department of Transportation specs allow a maximum Activity duration of 20 workdays – thus Activities should only span two monthly payment periods
ACTIVITIES
It is very important that each Activity Description be:
1. Brief/Concise
2. Totally Unique
3. Mean the Same to Everyone
4. Consistent Abbreviations Don’t rely on numbers to group or
to make descriptions unique
ACTIVITIES
Work Breakdown Structures (WBS):In the past WBS and numbering
systems were used to group Activities for various purposes
Now WBS are used primarily for financial accounting purposes – tracking planned costs against actual expenditures (Earned Value)