Outline
Commissioning
Product Physical Layout
Information Needed
Start up Procedure
Testing and Adjusting
CAT PC Software
Gain Settings
-
7/28/2019 CDVR COMMISIONING
3/47
-
7/28/2019 CDVR COMMISIONING
4/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
CAUTION
-
7/28/2019 CDVR COMMISIONING
5/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Information Needed
Generator Set Rating
Voltage
Current
Frequency
Power
Power Factor
Generator Time Constants (Td0 & Te)
Protection Settings
Generator Over / Under Voltage Trip Value and Time Delay
Over Excitation Type, Trip Value and Time Setting
Reverse kvar Trip Value and Time Delay Exciter Diode Monitor Ripple Current Trip Value
Loss of Sensing Time Delay
-
7/28/2019 CDVR COMMISIONING
6/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Startup Procedure
Connect per Wiring Diagrams section of I/M
Apply battery power
Connect serial cables
Install CAT PC Software if necessary (see I/M)
Start PC Software
Establish Communications
Verify parameter settings
-
7/28/2019 CDVR COMMISIONING
7/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Startup Procedure (contd)
Changing Settings
Press EEPROM button to save settings
Start Engine, Make final adjustments
Press EEPROM button to save settings
Record all Settings
Press Get From Unit verify all settings were saved
Disable CAT PC Software Communications
Verify Communications with CAT ET (CANbus)
Enjoy benefit of electricity
-
7/28/2019 CDVR COMMISIONING
8/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup ConnectionsPMG Power, ABC Rotation 3-Phase Sensing
-
7/28/2019 CDVR COMMISIONING
9/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup ConnectionsPMG Power, 3-Phase Direct Sensing
-
7/28/2019 CDVR COMMISIONING
10/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup ConnectionsPMG Power, 1-Phase Sensing
-
7/28/2019 CDVR COMMISIONING
11/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup ConnectionsPMG Power, 1-Phase Direct Sensing
-
7/28/2019 CDVR COMMISIONING
12/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup Connections3-Phase Self Excited, 3-Phase Sensing
-
7/28/2019 CDVR COMMISIONING
13/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup Connections3- Phase Self Excited, 1-Phase Sensing
-
7/28/2019 CDVR COMMISIONING
14/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup ConnectionsSelf Excited, Direct L-N Connect, 1-Phase Sensing
-
7/28/2019 CDVR COMMISIONING
15/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Startup ConnectionsAREP Power, 3-Phase Sensing
-
7/28/2019 CDVR COMMISIONING
16/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Typical Cross Current Connection with 2 CDVRs
-
7/28/2019 CDVR COMMISIONING
17/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Typical Cross Current Connection with 3 CDVRs
-
7/28/2019 CDVR COMMISIONING
18/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Typical Cross Current Connection with 1 CDVR and 1 DVR
-
7/28/2019 CDVR COMMISIONING
19/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Typical Connection with Manual Voltage Control
-
7/28/2019 CDVR COMMISIONING
20/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Establish Communications
-
7/28/2019 CDVR COMMISIONING
21/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Establish Communications
Password = CAT
-
7/28/2019 CDVR COMMISIONING
22/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Establish Communications
-
7/28/2019 CDVR COMMISIONING
23/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Communications Established
-
7/28/2019 CDVR COMMISIONING
24/47
-
7/28/2019 CDVR COMMISIONING
25/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
-
7/28/2019 CDVR COMMISIONING
26/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
Settings
Setpoint
AVR Voltage (limited by Volt Adj Band, 120V default) VAR (% of rated, +/- 100%, 0% default)
Power Factor (+/- 0.6, 1.0 default)
AVR Voltage Control (CAN / Switch, CAN default)
VAR/PF Control (CAN / Switch, Switch default)
Load Compensation Mode (Off, Droop, LDC, Off default)
Load Comp Setpoint (0 to +/-10%, 0% default)
Voltage Adjustment Band (0 to +/- 15%, 15% default)
-
7/28/2019 CDVR COMMISIONING
27/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
-
7/28/2019 CDVR COMMISIONING
28/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Droop vs. Load Compensation
Load Compensation
96979899
100
101102103104105106
-100 -50 0 50 100 150
% Reactive Load
%R
ate
dVoltage
Voltage Droop
99
100
101102
103
104
105
106
-100 -50 0 50 100 150
% Reactive Load
%Rate
dVoltage
Shown with3% Droop
Shown with5% Load
Comp
-
7/28/2019 CDVR COMMISIONING
29/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
Settings
Startup
Soft Start Mode Soft Start Bias (0 90%, 10% default)
Soft Start Time (0 120s, 5s default)
Under Frequency Mode
Knee Frequency (45 64Hz, 50Hz default)
Freq. Dev. From Knee Freq.(5Hz - fixed)
Slope #1 and #2 (0 10Hz, 2Hz default for both)
Min Voltage (50 100%, 50% default)
Min Frequency (20 40Hz, 25Hz default)
-
7/28/2019 CDVR COMMISIONING
30/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
-
7/28/2019 CDVR COMMISIONING
31/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Soft Start
Vref
SS bias
SS time
0
generator voltage
-
7/28/2019 CDVR COMMISIONING
32/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Under Frequency Mode
-
7/28/2019 CDVR COMMISIONING
33/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
Settings
Control Gain
PID Pre-Settings 1 20 pre-programmed, 1 custom PID settings
PID Calculator
AVR
Kp, Ki, Kd (0 1000, 200/600/50 defaults)
Td (0 1s, 0 default)
Kg (0 1000, 50 default)
VAR/PF
Ki, Kg (1 1000, 5/2.5 & 5/3 defaults)
-
7/28/2019 CDVR COMMISIONING
34/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
-
7/28/2019 CDVR COMMISIONING
35/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
PID Gains
PID Calculator
Tdo & Te required (2.0 & 0.33s defaults) Adjust Kg to achieve desired response
Good generic values: PID = 80,20,10 then adj Kg as needed
-
7/28/2019 CDVR COMMISIONING
36/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
-
7/28/2019 CDVR COMMISIONING
37/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Tdo from Generator Data Sheet
Te ranges from 0.06s to 0.26s see Table 9
-
7/28/2019 CDVR COMMISIONING
38/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
PID Gains
var / PF Integral and Loop Gain Settings
Use factory defaults as a staring point Increase Kg to increase speed of response (suggest
keeping it slow)
Increase Ki if var/PF regulation not acceptable
-
7/28/2019 CDVR COMMISIONING
39/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
Protection
Shutdown Override (Enable to override shutdowns, Disabled is
default value) Function not affected:
Gen. Overvoltage
Gen. Undervoltage
Reverse VAR Fault Reset too long
Cannot be saved in EEPROM Cycling power causesfunction to become disabled on power up
Generator Overvoltage (105 135%, 2 30s, 135%, 2s default) Generator Undervoltage (60 95%, 10 120s, 60%, 30s
default)
-
7/28/2019 CDVR COMMISIONING
40/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
Protection
Over Excitation Threshold is default (0 12A, 0 10s, 12A
& 10s default) Over Excitation Inv Time(0 12A, TD = 0 10, 12A & TD =
10 default)
Reverse VAR (10 100%, 0.1 9.9s, 10% & 3s to be
defaults soon) Fault Reset Too Long
Exciter Diode Monitor (1 10A, 2A default)
Loss Of Sensing (0 25s, 2A default)
-
7/28/2019 CDVR COMMISIONING
41/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
-
7/28/2019 CDVR COMMISIONING
42/47
-
7/28/2019 CDVR COMMISIONING
43/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Verify Parameter Settings Contd
Settings
Metering
Gen Voltage Gen Current
Gen Freq
Gen Power
Aux DC Input Exciter Field
Operating Mode
Fine Adjustment
Setpoint
Status
Alarms
Contact Inputs
-
7/28/2019 CDVR COMMISIONING
44/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
-
7/28/2019 CDVR COMMISIONING
45/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Dont Forget
Press EEPROM button to save settings
Record all Settings
Press Get From Unit verify all settings were saved Disable CAT PC Software Communications
-
7/28/2019 CDVR COMMISIONING
46/47
EAME/CIS TC Conference EP/Petroleum - Malaga, October 2007
Testing and Adjusting
Wrap up
Press EEPROM button to save settings
Start Engine, Make final adjustments
Press EEPROM button to save settings Record all Settings
Press Get From Unit verify all settings were saved
Disable CAT PC Software Communications
Verify CAT ET operation
-