CDM 2007 MAKING A DIFFERENCE Ken Logan. CDM 2007 : – Making a Difference The Challenge To change...
-
Upload
jordan-russell -
Category
Documents
-
view
215 -
download
0
Transcript of CDM 2007 MAKING A DIFFERENCE Ken Logan. CDM 2007 : – Making a Difference The Challenge To change...
CDM 2007MAKING A DIFFERENCE
Ken Logan
CDM 2007 : –
Making a Difference The Challenge
• To change attitudes
• To change behaviours
• Achieve sensible risk management
CDM 2007 – Key Features
To improve the
Co-ordination and
Information Flow
during: - The pre-construction
phase The construction
phase
Aim of the revision Simplify the regulations and improve clarity Maximise their flexibility Focus on planning and management, not
‘The Plan’ and other paperwork Strengthen requirements on cooperation and
coordination- encourage better integration Simplify competence assessment; reduce
bureaucracy and raise standards
Main changes CHSW and CDM combined
Regulations apply to all construction work
New trigger for appointments and preparation of the plan
Clients duty on management arrangements
A new dutyholder- the CDM Coordinator
Designers to eliminate hazards; reduce risk
Clarity in relation to competence assessment
CDM 2007 – Making A Difference Structure of the Regs-
Five parts Part 1: Introduction Part 2: General management duties applying to
construction projects Part 3: Additional duties where projects are notifable Part 4: Health and Safety on Construction sites Part 5: General Schedules 1 to 4
CDM 2007 – Making A Difference Structure of the Regs
Regulations apply to all construction work Notification triggers appointments of duty holders
and duties in Part 3 of the Regulations: - Appoint a CDM Co-ordinator Duty to provide Pre-construction information Appoint a Principal Contractor Construction Phase Plan ; Health & Safety File
Duties remain on clients, designers, & contractors regardless of notification
CDM 2007 – Making A Difference Trigger for Appointments
CDM 1995 Demolition 30 days, 500
person days 5 or more workers
CDM 2007 30 days, 500 person
days
What difference do we want to see
The Regs have been revised to address past problems This means a distinct change in current
behaviour is required to achieve the aims The key messages are
Reduce risk Reduce bureaucracy Reduce paperwork Develop understanding and take ownership
Change in mind set is required “Pre tender health and safety
plan scrapped Competence assessment is
greatly simplifiedChanges needed include stopping :
Unhelpful DRAs Coordinators insisting on DRAs to
check compliance Coordinators checking PC’s RA
and method statements CDM policy statements Verification culture
Cutting back on paper Does it reduce risk on site?
should be the covering criteria for all actions.
CDM 2007 requires following: - Pre-construction information An NI 10 Notification Form A Construction Phase Health
and Safety plan The Health and Safety File
Reaction to CDM 2007 A “business as usual approach’’ with no
change achieved – not an option Failure to take the opportunity to reduce
paperwork and bureaucratic systems ‘Gold plating’ by advice and consultancy
services beyond what is required by the Regulations
Failure for duty holders to embrace changes where their role has changed
Take this as an Opportunity to Improve.
Expectation of Clients Makes them accountable
for the impact they have on H&S standards
They should make sure things are done not do them themselves
CDM Co-ordinator is their key advisor
Must provide enough time and resource to allow the project to be delivered safely
What clients must do Engage competent and
adequately resourced team members
Provide relevant information to the team
Ensure welfare is in place from the start
Comply with Workplace Regs Ensure work does not start
until the PC has a H & S plan Ensure the H & S File is
prepared
What clients must do Where there is more than one Client they
can elect in writing one to take on the client’s duties.
Allow the contractor time for planning and preparation before the construction phase starts.
CDM co-ordinators Key advisor to the Client on: - Appointment of competent designers and
contractors; Ensure adequate arrangements are in place to
manage the project; Notify HSENI Ensure proper co-ordination of the design
process – safe to build, use, maintain, and demolish
CDM co-ordinators Key advisor to the Client on: - Identify, collect and pass on pre-construction
information to the right people at the right time Suitability of the initial Construction Phase Plan &
arrangements to have Welfare Facilities on site from the start of the project
Manage the flow of health and safety information between clients, designers and contractors
Prepare and up-date the health and safety file
CDM Co-ordinators Are expected to adopt a
positive enabling role Brevity and clarity is key They must be discouraged
from developing unproductive paper based systems
Asking for proof from designers such as DRA
They do not have to approve RA or methods statements
Advise on management arrangements not the detail
Who can be a CDM Co-ordinator Anyone - so long as they fulfil competence given in
ACOP An appointment has to be made early The duties can be carried out by a
Designer Contractor Principal Contractor CDM Co-ordinator
On small jobs a combined role of designer and CDM Co-ordinator may have advantages
CDM Co-ordinator - Knowledge & Experience
Design & Construction process – Professionally qualified to Chartered level.
Health & Safety in construction eg NEBOSH construction certificate. Etc.
Experience relevant to the task – evidence of significant work on similar projects.
Designers Designs should be safe, to build, to
use, to clean, to maintenance, to demolish
Inform others of significant or unusual risks which remain
Amount of effort put in to risk reduction should be proportionate to the risk
Take account of relevant provisions of Workplace Regs
Eliminate hazards and reduce risks from the start of the design process subject to other relevant design considerations
Designers - Information Designers must provide information to identify and
manage remaining significant risks to those that need it. This can be achieved by brief: - Notes on drawings Written information provided with the design Suggested construction sequences when not
obvious
If in doubt discuss with a constructor.
Designers - Records CDM does not require Designers to keep records Designers are not required to produce copious
amounts of paperwork detailing hazards and risk This is potentially harmful and must be positively
discouraged May reflect a lack of competence But - brief records why key decision were made will
be helpful when designs are passed to another to prevent decisions being reversed
TRANSITION – on current projects –
Reg 47(2) – client to appoint CDM-C and/or PC as soon as is practicable
Reg 47(3) – if appointing existing PS and/or PC, Client has 12 months to take reasonable steps re: Reg 4(1) – ensure competence of those appointed.
TRANSITION – on current projects –
Reg 47(4) – with no express appointment by the client, existing PS and/or PC shall be treated as having been appointed as CDM-C and/or PC
Reg 47(5) – any PS and PC treated as being appointed shall take such steps as are necessary to ensure they are competent – within 12 months.
TRANSITION – on current projects –
Reg 47(6) – any Client-appointed agent MAY, if requested by Client, continue to act as Agent (under the new Regs) until (i) client revokes, (ii) project completes, or (iii) 5 years elapses – whichever comes first.
Reg 47(7) – any Notification under old Regs shall be construed as Notice under new CDM2007 - i.e. NO NEED FOR NEW NOTIFICATION (unless details change)
Competence - Organisations: Stage 1: An assessment of the company’s organisation
and arrangements for health and safety to determine whether these are sufficient to enable them to carry out the work safely and without risks to health
Stage 2: An assessment of the company’s experience and track record to establish that it is capable of doing the work; it recognises its limitations and how these will be overcome and it appreciates the risks from doing the work and how these will be tackled
Summary Achieve the next step change in
industry performance Focus on effective planning and
management of risk through integrated teams
Real investment in competence & skills of the workforce
Paperwork should be risk focussed and project specific
Actively drive out needless bureaucracy
Provide the right information to the right people at the right time;
Building on success
ACop & Industry Guidance ACoP Supported by Industry produced guidance
Guidance coordinated through ‘task and finish’ Working Group of CONIAC
Web sites HSE - http://www.hse.gov.uk SID - http://www.safetyindesign.org DBP - http://www.dbp.org.uk
Any Questions