CDBI Inspection Changesand Insights for 2008

Russ Bywater

Engineering Branch 1 Chief, RIV

Page 2: CDBI Inspection Changes and Insights for 2008

2

Preview

Changes to scheduling for 2008 and beyond

Changes to the IP 71111.21 module for 2008

Overview on implementation (more details in the next presentation from Kelly)

Recent issues (OE and IN 2008-02)

Summary

Page 3: CDBI Inspection Changes and Insights for 2008

3

Changes to scheduling for 2008 and beyond

Starting this CY, all CDBI inspections are triennial

Reason for the change

Other inspections affected in this change

Page 4: CDBI Inspection Changes and Insights for 2008

4

Changes to IP 71111.21 for 2008

Current Revision date: 01/31/08

Draft version out for review

Major changes are:(1) provide flexibility in selection of samples in categories of components, operator actions, and operating experience; (2) generally preclude re-inspection of items previously inspected by SSDPCs and CDBIs.; and (3) perform CDBIs on a triennial cycle.

Page 5: CDBI Inspection Changes and Insights for 2008

5

Overview on Implementation

The sample selection is based on a risk-informed and low margin approach to identify the highly risk-significant components and operator actions at the facility.

HighRisk items

LowMargin items

Page 6: CDBI Inspection Changes and Insights for 2008

6

Recent issues (OE and IN 2008-02)

Repeated violations on same issues (OE)

Information Notice 2008-02

Safety Culture changes (RIS-2006-13)

Page 7: CDBI Inspection Changes and Insights for 2008

7

Summary

To have a successful CDB Inspection:

1. Review the IP and plan accordingly

2. Have a strong Design Margin program

3. Have a strong Corrective Action program

4. Review OE and implement as necessary