CCPM in Construction Industry - Practical Guide for Top Executives by Prabhakar Jadhav-libre
-
Upload
marcelo-j-ramos -
Category
Documents
-
view
16 -
download
0
description
Transcript of CCPM in Construction Industry - Practical Guide for Top Executives by Prabhakar Jadhav-libre
WeCare SESSION ON CCPM TO THCL AT
GURGAON
03-06-2013 17:39:21
G U R G A O N
G A T E W A Y
An Epitome of
Luxury
WeCare SESSION ON CCPM TO THCL AT
GURGAON
An Epitome of Luxury
Exquisite cluster of towers form the new latest landmark
which would be the New Gateway to Gurgaon and will
redefine the Skyline forever.
Strategically located and endowed with unique
concepts of vertical greens and sky gardens this new
gateway would provide a perfect ambience to match
your lifestyle.
With the best in class specification and world class
amenities a home at The Gateway will make it certain
that your choice is a Gateway into the abode of the lux.
WeCare SESSION ON CCPM TO THCL AT
GURGAON
Sessions on CCPM
for Tata Housing – 7 th June 2013
19:33:46
WeCare SESSION ON CCPM TO THCL AT GURGAON
Introduction
Prabhakar Jadhav
Advisor to Ashoka foundation – “Housing for All” &
Mentor for WeCare
Retired as Head – Planning, Quality/Safety Systems and Change
Leader
B. Tech. [Hons ] IIT Kharagpur
Chartered Engineer , Fellow of Engineering
Work experience – 36+ years
Core competencies: Projects , Quality /safety Systems,
Business Processes , Business Excellence & Change Management
5
SESSION ON CCPM TO
THCL AT GURGAON
Agenda
Sampoorna Parivartan- It Starts with ME!
Duration = 60+10 min
Introduction & Ice Breaker
Introduction to CCPM
Typical Project Management - The Problems & Core Conflict
Direction of Solution - CCPM Approach
CCPM Implementation at Brigade
Introduction to CCPM
Introduction to Critical Chain Project Management
SESSION ON CCPM TO
THCL AT GURGAON
Critical Chain Project Management (CCPM)
is a method of planning and managing
projects that puts the main emphasis on the
resources required to execute project tasks
It was developed by Eliyahu M. Goldratt,
A Guru of aggressive Management Theories
WeCare
CCPM mainly uses the principles of ‘Theory of Constraint’ (TOC)
Which is;
A new management philosophy
New research method
Robust applications
8 Sampoorna Parivartan- It Starts with ME!
Critical Chain Project Management
Definition used by Eli Goldratt
for TOC is:
‘A Thinking Process that
enables people to invent
simple solutions to seemingly
complex problems.'
9 Sampoorna Parivartan- It Starts with ME!
TOC & CCPM
What does this mean?
Theory of Constraints thinking means a Project is viewed as
a System /Process , not just the sum of the individual tasks
In practical terms, the “System /Process ” can be visualized
as a Chain
– A Chain is no stronger than its Weakest Link or “Constraint”
Therefore, the speed that can be attained in a Project /
System /Process is paced by the Constraint
CCPM vs the traditional way
Has A Plan that includes logical links and resource links
– The same resource cannot do two or more things at once
– Predecessors And Successors are part of the plan
This type of Project Management is not the traditional way of
doing business
– Human nature is to give each project a little attention in
order to show progress
– Keeping all the balls in the air is considered “Success”
Typical Project
Management
Sampoorna Parivartan- It Starts with ME!
Project Life Cycle
Project initiation
Project
planning
Project Execution
Project
Closure
Deliverable of a project
Any project has 4 deliverables
1. The specifications
2. Time line
3. Budget
4. Safety & environmental concern
Characteristics of projects
Projects Are:
1. Unique
2. Dependent on Precedence
3. Activities not well known
4. Highly Variable
5. Share Resources
6. Concurrent with other Projects
7. Valued by Scope, Schedule and Cost
“A Project is a series of related jobs usually directed toward
some major output and requiring a significant period of time
to perform.”
What is unique about projects ?
Everything is uncertain in a project.
Unlike Factory Production , everything is
done for the first time.
And yet, the project is expected to deliver
All the specifications in the agreed time and
within the predetermined budget
1. Due dates not met by Architects, Departments, Contractors…
2. There are too many changes in scope
3. Too often resources are not available when needed
4. Mismanagement of / by multiple contractors on site
5. Fights about priorities between projects
6. Budget overrun
7. Too much rework
8. Communication gap between the departments
General list of Problems in Project Management
Sounds familiar ?!?
So, how do we put Buffer in the task ?
We have seen that project estimates are built with plenty of Buffer, spread across the tasks.
What happens to this Buffer ?
Then why most of the projects does not finish on time ?
Buffer Buffer Buffer Buffer
project’s due finish date project’s start date
Accumulation of Buffer over the project
What kills the Buffer ?
1. Bad Multi-tasking
2. Murphy
3. Students Syndrome
4. Parkinson’s Law
What kills the Buffer of a task ?
Mindset / Human elements
Dateline
start end
Delay
And the delay is passed on to the next task.
"Whatever can go wrong, will go wrong, and at the worst possible time."
-- Murphy's Law
Uncertainty ( Strike of Murphy )
Student Syndrome
I have plenty of time, I’ll start tomorrow!
23 Sampoorna Parivartan- It Starts with ME! Sampoorna Parivartan- It Starts with ME!
24
Student Syndrome
Question: If you have 16 days to do a 10 day project, when do you start?
Immediately!
Or,
After 6 days.
Or,
After 10 days
(since you know you are faster than average and can
probably do it in 6 days).
Normal level of effort
Assigned Due Date
Student Syndrome
start
Deadline Deadline
Scheduled start date
Start
Start
Lost !!!
End
Gain
The gain is not passed on to next task.
"Work expands to fill (and often exceed) the time allowed." -- Parkinson's Law
Parkinson’s Law
1. How can we protect the promise date of an entire project from
uncertainty without freezing all the individual task deadlines?
3. How can we manage the execution of a project if we
don't have due dates to track?
2. How can we take advantage of early task finishes ?
Summarizing the problems
The challenges in front of us:
If we take care of these 3, we will find an answer, right ?
The Key Factors for successful projects are:
1. Well defined scope
2. Extensive early planning
3. Good leadership, management and first line supervision
4. Positive client relationship with client involvement
5. Proper project team chemistry
6. Quick response to changes
7. Project Heads concerned with the total project, not just
the engineering elements
27
Sampoorna Parivartan- It Starts with ME!
Planning
Sampoorna Parivartan- It Starts with ME!
Quality
Cost
Scope
Time
Key Project Constraint
30
Plan Schedule Execute
Plan Execute Schedule
Duration
Duration
Traditional method:
CCPM method:
Time taken for completion of project is more.
Time taken for completion of project is less.
Sampoorna Parivartan- It Starts with ME!
How to overcome constrains
Criteria for good planning
Provide financial benefits
Be realistic
Immunize against disruptions
Murphy
Uncertainty
Sampoorna Parivartan- It Starts with ME!
Sampoorna Parivartan- It Starts with ME!
On time Delivery
32 KEY NOTE ADDRESS TO AIT
33
Planning & Execution / Monitoring
Scheduling of drawing, approvals
Sequencing activities
Resource management
Coordination & Communication
Understanding & Adherences to PESTLE
On time Delivery
KEY NOTE ADDRESS TO AIT
Approach to Planning & Control
Top
do
wn
Ap
pro
ac
h
Bo
tto
ms
up
Ap
pro
ac
h
Overall Plan
Every Project / Sub project broken into major activities
Start, 25%, 50%, 75% and 100% dates captured
Critical Activities identified and drilled down
Red, Amber, Green Categorization with Issues/Challenges
All planned activities tracked on actual work
All Project/Sub project give Weekly Plan
Weekly Dashboard
34 KEY NOTE ADDRESS TO AIT
Weekly Dashboard
GATEWAY
METROPOLIS
CITY, MYSORE PROJECTS
99801 41457
Sl. No ActivityPlanned
Quantity
Unit of
measure
Planned Start
Date
Planned Finish
DateStatus
Any Remarks /
Reasons for Not Completed
Action Required
CategoryAction Required
Cash Required
(if any)
Action Required
By (Name)
1Block Work For Various Rooms 25
th Floor 1000 Sqm 29-Jun-09 5-Jul-09 Completed
2Civil works in the observation lift for the pit slab.1 Nos 29-Jun-09 5-Jul-09 Completed
3Plastering of walls at various levels 1200 sqm 29-Jun-09 5-Jul-09 Completed
4VDF work from 20th & 21st floor 2400 sqm 29-Jun-09 5-Jul-09 Completed
5 start work on the Spider glazing at triple
height lobby -one bay - GF 1 bay 29-Jun-09 5-Jul-09Not
Completed
Few design changes causing delay in
the resumption of work.Drawing Architect - VA & BEL team
MNBala - time line - 10
days
6Glazing work - progress 75 panel 29-Jun-09 5-Jul-09 Completed
7Lift Installation work by Schindler - Mid
rise -50%5 lift 29-Jun-09 5-Jul-09
Not
Completed
Due to power restriction requiring
phased workDecision
Additional power to be arranged.
Mail sent to electrical deptMNB
8 Office tower sprinkler line Hydro testing
at 21st
Floor & 22nd floor235 nos 29-Jun-09 5-Jul-09 Completed
9 office tower 200 dia Rain water pipe
errection50 rmt 29-Jun-09 5-Jul-09 Completed
10 office tower Granite Steps for staircase -
East side3 Floor 29-Jun-09 5-Jul-09 Completed
11STP - raft & 1st lift wall 1 pour 29-Jun-09 5-Jul-09 Completed
Project Gateway North Star
Previous Week's Actual
Sub project
Filled by M.N.Balasubramanian
99801 41457
Sl. No ActivityPlanned
Quantity
Unit of
measure
Planned Start
Date
Planned Finish
Date
Activity -
Fresh/Pending from
prev week
4-J
ul
5-J
ul
6-J
ul
7-J
ul
8-J
ul
9-J
ul
10-J
ul
Remarks
1 Block work at various levels 1000 sqm 4-Jul-09 10-Jul-09 Fresh
2 Plastering at various levels 1500 sqm 4-Jul-09 10-Jul-09 Fresh
3 VDF activity at 20th floor 2400 sqm 4-Jul-09 10-Jul-09 Fresh
4 STP civil works - balance raft completion 75 cum 4-Jul-09 10-Jul-09 Fresh
5 STP civil works - RCC walls for anoxin / MBR tank - 1 lift 50 cum 4-Jul-09 10-Jul-09 Fresh
6 Staircase on East side - Granite for steps & landing 4 flights 4-Jul-09 10-Jul-09 Fresh
7 Glazing work - Fixing of panels 100 panels 4-Jul-09 10-Jul-09 Fresh
8 Erection of mid rise elevators - schindler team 1 lift 4-Jul-09 10-Jul-09 Fresh
9 Staging for service lift - thyssenkrup team 1 lift 4-Jul-09 8-Jul-09 Fresh
10 Fire fighting - Sprinkler lines 21st & 22nd floor - balance 50% 235 nos 4-Jul-09 10-Jul-09 Fresh
11 Plumbing - Erection of rainwater & GI lines in one of the shaft4 floors
4-Jul-09 10-Jul-09 Fresh
12 Fire doors fixing - smaple work in Staircase room1 door
6-Jul-09 8-Jul-09 Fresh
13 Ms handrail work in staircase2 flights
7-Jul-09 10-Jul-09 Fresh
Weekly Plan
Project Gateway North Star
Sub project
Filled by MNB
Previous Week’s Actual
Next Week’s Plan
Dashboard
Actions to be taken
Last Week’s Action Status
War
Room
Members
35 KEY NOTE ADDRESS TO AIT
Sampoorna Parivartan- It Starts with ME!
Theory of constraints
38
• Mindset/ Human elements
• Planning
• Control of the execution
Aspects for CCPM Solution
Sampoorna Parivartan- It Starts with ME!
Sampoorna Parivartan- It Starts with ME!
CCPM Approach
SESSION ON CCPM TO THCL AT GURGAON 40
41
The concept uses buffer management
dashboard to assess the performance of a
project.( Fever Chart)
Brigade is the pioneering developers in India
to use CCPM methodology.
All projects in Brigade are taken through
CCPM route
CCPM Implementation
KEY NOTE ADDRESS TO AIT
CCPM Approach
End
Start
Activity
Buffer in the
task
P1
20 d
20 d
20 d
20 d
20 d
CCPM Approach
43
End
Start
Activity
P1
Cut Safety, Crash durations
P1’
10 d
10 d
10 d
10 d
10 d
20 d
20 d
20 d
20 d
20 d
20/2
20/2
20/2
20/2
20/2
Safety in
tasks
SESSION ON CCPM TO THCL AT
GURGAON
CCPM Approach
End
Start
Activity
buffer in
tasks
P1
End
Project Buffer
Remove buffer from Tasks,
Create buffer for project
P1’
20 d
20 d
20 d
20 d
20 d
10 d
10 d
10 d
10 d
10 d 25 d
20/4 20/4
20/4
20/4
20/4
End
Start
Activity
Safety in
tasks
P1
P1’
End
Project Buffer
0 75 100
CCPM Approach
Start
45 KEY NOTE ADDRESS TO AIT
46
CCPM
0 2% 6% 12%
13%
40%
25% 30%
34%
38% 50%
62% 66%
69%
0
10
20
30
40
50
60
70
80
90
100
100 90 80 70 60 50 40 30 20 10 0
% B
uffe
r C
on
sum
ptio
n
% Project Progress
Brigade Rubix Fever Chart
Amber
Green
% Buffer Consumed
As on 13th nov.’12, project buffer consumption is 69% (Out of 100
days of project buffer, 69 days buffer is consumed); with 63%
completion. However the project progress needs to be closely
monitored as it might go into the delay zone.
KEY NOTE ADDRESS TO AIT
Sampoorna Parivartan- It Starts with ME!
CCPM Implementation
SESSION ON CCPM TO THCL AT GURGAON 47
How did we Apply CCPM at Brigade
• As a part of Sampoorna Parivartan initiative, it was decided to
implement Critical Chain Project Management at Brigade.
• A step wise approach was followed in this implementation:
SESSION ON CCPM TO
THCL AT GURGAON
Step 1
• Identifying a Project for CCPM Pilot Implementation
Step 2
• Selection of Sheraton Project Team and CCPM Training
Step 3
• Building up the Project Schedule
Step 4
• Workshop for Crashing the Durations
Step 5
• Project Progress Monitoring using Buffer Consumption Dashboard
• Delay and Early Gain Charts
WeCare
Step 3:
Building up the Project Schedule
The project schedule covered all key phases of a hotel project:
SESSION ON CCPM TO
THCL AT GURGAON
Design Phase
Contract Award Phase
Bought out Items Ordering
Construction Phase – Civil
Construction Phase – Services
Bought out Items Delivery
Interiors and Soft Furnishing
Public Area & BOH Area
Kitchen and Bar
Laundry
LPG Gas Bank & Associated Piping
Swimming Pool
External Developments
Snagging & Handing Over
WeCare
Crashed Duration
SESSION ON CCPM TO
THCL AT GURGAON
16 Sep’09 (Base date)
20 Aug’10
15 Nov’09 (Base date)
Sep’10
PB
July’10
20 Nov’09 (Base date)
31 Jan’11 Crashed durations Removed buffer from
activities, create Buffer for project
Shift due to delay in completion of activities
WeCare
Step 4:
Workshop for Crashing the Durations
SESSION ON CCPM TO
THCL AT GURGAON WeCare
Fever Chart
59
Schedule On-Track Act on Contingency
Plan Develop Contingency Plans
Identify and Solve Problems
100% %
Pro
ject B
uffe
r C
on
su
me
d
100% Percent Remaining
0%
Follow the Plan
0%
Time
Sampoorna Parivartan- It Starts with ME!
60
CCPM
As on 24th Mar’10, project buffer consumption is 85% (Out of 60 days of project buffer, 51 days
buffer is consumed); which represents that project is running with a delay of nearly 51 days on
its end date of 10th Jul’10
Fever Chart for Sheraton Hotel project
KEY NOTE ADDRESS TO AIT
Warroom had prepared templates for Delay and Early
Gain charts that are presented in this meeting to highlight
the activities which are delayed or can get delayed and
activities that can start early:
1. Delay in activities Started but Not Finished
2 (a) Possible Delay in Critical activities Not Started
2 (b) Possible Delay in Non-Critical activities Not Started
3. Activities (not started) having chance of Early Start
SESSION ON CCPM TO
THCL AT GURGAON
Step 5: Delay and Early Gain Charts
WeCare
SESSION ON CCPM TO
THCL AT GURGAON
Delay in activities Started but Not Finished
WeCare
Possible Delay in Critical activities Not Started
SESSION ON CCPM TO
THCL AT GURGAON WeCare
Possible Delay in Non-Critical activities Not Started
SESSION ON CCPM TO
THCL AT GURGAON WeCare
Activities (not started) having chance of Early Start
SESSION ON CCPM TO
THCL AT GURGAON WeCare
Sampoorna Parivartan- It Starts with ME!
Summary & benefits
SESSION ON CCPM TO THCL AT GURGAON 66
Before CCPM
After CCPM
67
997 days
932 days 60 days
Sampoorna Parivartan- It Starts with ME!
Time Estimate
Benefits Received
Speed
– We have had repeated success at shortening
delivery schedules by 4 months or
more.
– High Performance is contagious – Once they get a
feel for it, they want more.
Communication
– There is a feeling of being a better team -- workers
and managers better understand the connection
between their responsibilities and the program
results
– Priority and focus are communicated daily
Benefits Received
Management
– Greater awareness of where the program is
– Visibility of your constraints and what you can do
about them
– Informed decisions and improved understanding of
the effects as well has how to recover when bad
things happen
One customer said, “The Critical Chain process you are putting in place is fantastic. You are able to
bring resources to bear on the issues. Good work”
Pre - Implementation
Honeymoon
Crisis Recovery
Adjustment
Enthusiasm Mood Emotions
Implementation Roll - Out
Completing Roll –Out and Moving to Full Execution
Time
Phases of adaptation to a new culture and
stages of a new initiative Implementation
Sampoorna Parivartan- It Starts with ME!
Questions and Discussion
SESSION ON CCPM TO THCL AT GURGAON 73
WeCare SESSION ON CCPM TO THCL AT
GURGAON
Thank
You
6/4/2013
03-06-2013 17:39:21