CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD...

15
July 16 SCDP public session (Montlake lid) SR 520 Project/MOU Implementation Process Flowchart DRAFT - Updated: July 9, 2012 Project Implementation Project Financing May June July August September October November December 2012 2013 2014 Draft SCDP Report MOU Implementation Seattle Community Design Process Other Pre-Construction Arboretum Agreement Final SCDP Report Draft NTMP Final NTMP Second bascule bridge triggers report Legislative update: --Cost/funding --TIFIA --MOU update (incl. SCDP) Abbreviations CCMP: Community Construction Management Plan NTMP: Neighborhood Traffic Management Plan SCDP: Seattle Community Design Process WABN: West Approach Bridge North CEVP: Cost Estimation Validation Process TIFIA: Transportation Infrastructure Finance and Innovation Act Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Conceptual – For Planning Purposes Only Develop CCMP (WABN) Final CCMP (WABN) Implement CCMP Advance Seattle designs (pending funding) – WAB-South, Portage Bay Bridge, Montlake interchange, I-5 interchange Seek funding for unfunded project elements NTMP early implementation Advance design for next construction phase (WABN) / Technical coordination External Coordination Legislative update: --Cost/funding --Design update --Planning July Stake holder meetings (Montlake lid) Public comment June 20 MOU executive group meeting Dec. MOU executive group meeting Design decisions needed Public open house Contract ready for advertisement Finalize design and contract preparation Technical coordination / Permit compliance Nov.26 Council briefing (Mayor date TBD) Dec. 10 Council briefing / Council action (Mayor date TBD) Topics include: --SCDP draft report --MOU update --TIFIA Sept. 10 Council briefing (Mayor date TBD) Preliminary TIFIA Decision Final TIFIA Decision I-90 Tolling Update I-90 Tolling Environmental Assessment Contract procurement Construction Aug. 28. MOU executive group meeting

Transcript of CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD...

Page 1: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

July 16 SCDP public

session(Montlake

lid)

SR 520 Project/MOU Implementation Process FlowchartDRAFT - Updated: July 9, 2012

Project Implementation

Project Financing

May June July August September October November December2012 2013 2014

Draft SCDP Report

MOU Implementation

Seattle Community Design Process

Other

Pre-Construction

Arboretum Agreement

Final SCDP Report

Draft NTMP

Final NTMPSecond bascule

bridge triggers report

Legislative update:--Cost/funding--TIFIA--MOU update

(incl. SCDP)

Abbreviations

CCMP: Community Construction Management Plan

NTMP: Neighborhood Traffic Management Plan

SCDP: Seattle Community Design Process

WABN: West Approach Bridge North

CEVP: Cost Estimation Validation Process

TIFIA: Transportation Infrastructure Finance and Innovation Act

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Conceptual – For Planning Purposes Only

Develop CCMP

(WABN)Final CCMP

(WABN)Implement CCMP

Advance Seattle designs (pending funding) – WAB-South, Portage Bay Bridge, Montlake interchange, I-5 interchange

Seek funding for unfunded project elements

NTMP early implementation

Advance design for next construction phase (WABN) / Technical coordination

External Coordination Legislative update:

--Cost/funding--Design update--Planning

JulyStakeholder

meetings (Montlake

lid)

Public comment

June 20 MOU executive group

meeting

Dec. MOU executive

group meeting

Design decisions needed

Public open house

Contract ready for

advertisement

Finalize design and contract preparation

Technical coordination / Permit compliance

Nov.26 Council briefing

(Mayor date TBD)

Dec. 10 Council briefing / Council

action(Mayor date TBD)

Topics include:--SCDP draft report--MOU update--TIFIA

Sept. 10 Council briefing

(Mayor date TBD)

Preliminary TIFIA Decision

Final TIFIA Decision

I-90 TollingUpdate

I-90 TollingEnvironmental Assessment

Contract procurement Construction

Aug. 28. MOU executive group

meeting

Page 2: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

Attachment 1: Seattle/SR 520 MOU ImplementationFramework for Coordination Draft / Work in Progress -- Updated April 19, 2012

West Side Executive Leadership Group

Co-led: WSDOT (Julie Meredith, Dave Dye, Ron Judd) and City of Seattle (CM Conlin, Peter Hahn, Ethan Raup, Christopher Williams)

Purpose: Coordinates on legislative direction, technical recommendations and funding availability.

West Side Oversight Group

Co-led: WSDOT (Kerry Pihlstrom, Rob Berman, Sarah Brandt) and City of Seattle (Mike Fong, Jennifer Wieland, Peter Harris, David Hiller,

Michael Shiosaki, Phyllis Shulman)

Participants: City Council, Mayor’s Office, SDOT, Seattle Parks & Recreation, WSDOT staff

Purpose: Integrates feedback from all processes and sets direction for policy recommendations.

Neighborhood Traffic Management Planning

Lead: Jennifer Wieland (SDOT)WSDOT Lead:

Michael HorntvedtParticipants: City depts, partner

agencies and neighborhood representatives

Purpose: Provide feedback to WSDOT and City of Seattle on

strategies to identify solutions to neighborhood traffic concerns.

Recommendation of 6392, ROD

Urban and Sustainable Design

WSDOT Lead: Rob Berman Participants: City depts, partner

agencies and neighborhood representatives

Purpose: Provide feedback on urban design features for

communities on the Seattle side of the corridor

Recommendation of 6392 (Urban Design and Streetscapes

White Paper)

Montlake Bascule Bridge Planning

Lead: Mike Fong (Council),Tim Payne

WSDOT Lead:Michael Horntvedt

Participants: City depts, partner agencies and neighborhood

representatives

Purpose: Provide feedback to WSDOT and City of Seattle on

triggers for constructing and design alternatives for the second

bascule bridge

Recommendation of 6392, ROD

Permitting/Regulatory Agency Coordination

WSDOT Lead: Jenifer Young, Scott White

Participants: Resource and permitting agencies

Purpose: Implement regulatory commitments identified in FEIS,

ROD, and permits

General regulatory requirements

Arboretum Coordination/Mitigation

Implementation

WSDOT Lead: Kerry PihlstromParticipants: ABGC

Purpose: Implement mitigation projects identified in 2010 Arboretum Mitigation Plan

Recommendation of 6392, ROD

Section 106 Programmatic

Agreement Implementation

WSDOT Lead: Steve Archer Participants: Section 106

concurring parties, including Seattle Historic Preservation

Officer (Dept. of Neighborhoods)

Purpose: Implement commitments made in 2010 Section 106 Programmatic

Agreement

Regulatory requirement, ROD

Partner agency executive updates

Seattle Community Design ProcessWSDOT Lead: Rob Berman

Participants: Partner agencies, neighborhood representatives, general public

Purpose: Provides connectivity between various design and stakeholder coordination processes. Provides input to appropriate processes, listens to

and synthesizes community feedback, and informs West Side Oversight Group. Provides input to SR 520/Seattle Technical Working Group, as

appropriate.

Existing WSDOT Practices

WSDOT Lead: Daniel Babuca (TBD)

520 Liaison:Jennifer Wieland

Participants: City depts, (SDOT, DPD, Dept of Neighborhoods, Parks & Rec, SPU, SCL, etc.)

and advisory boards, as needed

Purpose: Coordinate with city depts

Standard coordination processes

Community Construction Management Planning

WSDOT Lead:Dave Becher (FB&L)

Participants:Public, City depts

Purpose: Minimize the effects of construction on the public by

providing timely and responsive information, as well as implementing standard

specifications and best practices.

Requirement of Section 106 Programmatic Agreement, ROD,

and Seattle shoreline permit conditions

NOTE: This chart illustrates how the City of Seattle and WSDOT will coordinate to implement commitments agreed to in the 2011 Memorandum of Understanding. This is not a decision-making diagram.

Mitigation, Regulatory Compliance, and Standard PracticesInternal processes (interagency agreements and protocols involving participants with standing)

Design and Construction: General Public Engagement ProcessesExternal outreach and involvement opportunities

SR 520/Seattle Technical Working GroupWSDOT Lead: Kerry Pihlstrom

Participants: WSDOT, Seattle Departments

Purpose: Interagency coordination and information sharing to support project design, implementation, and timely compliance with agreements,

regulatory requirements, and other standard practices. Identifies key areas and appropriate timing of input needed from Seattle Community Design

Process.

Governor and LegislatureWSDOT executives updates

Full Council and Mayor’s Office briefings

Page 3: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

West Side Design Progression

Vision

Funding for construction

Subarea focus

Design opportunities

Design preferences

Design development

Design recommendations

Contract

preparation,

procurement and

construction

Co

ntain

ed in

the SC

DP

20

12

Final R

epo

rt

DRAFT - FOR INTERNAL

DISCUSSION August 16, 2012

Funding for design

Page 4: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

DRAFT – for internal discussion 8/16/12

Page 1 of 1

Proposed schedule through 2012:

SDC and Seattle Community Design Process (SCDP) (With special attention to SDC endorsement for Sept. 10, 2012 Seattle City Council briefing)

SCDP project team intends to carry the following to City Council: 1. Update on MOU process through August 2012

2. Overview of expected process through December, including expected endorsement of ‘preferences’ by

various stakeholder groups, such as Cascade Bicycle Club, Seattle Design Commission, Seattle Bicycle

Advisory Board, and Seattle Pedestrian Advisory Board, by the end of October 2012.

3. Overall Vision for the west side of the SR 520 corridor, including the Vision for user experiences, and

supporting diagrams

4. Explanation of project design progression

In order to maximize the SCDP project team’s effectiveness and credibility with City Council, we

need SDC’s written endorsement of: 1. SCDP (and next steps)

2. Overall Vision

3. Guidance on specific design elements

SDC meeting dates and expected outcomes August 16 Full SDC

1. Discuss the nature/extent of SDC endorsement and guidance we are seeking

2. Endorsement of Vision

3. Preliminary discussion of design preferences

August 22 Subcommittee

1. Further discussion of design preferences

2. Final review/discussion of SDC endorsement/guidance letter to City Council/Mayor

3. Continue conversation of tiered delivery approach

September 6 SDC internal business meeting (no SR 520 staff attend)

1. SDC reviews and endorses letter to provide to City Council

September 10 Seattle City Council briefing

1. MOU implementation progress update

2. SCDP and overview of design preferences (TBD)

3. Second bascule bridge triggers analysis update (TBD)

September 20 Full SDC

1. Outcomes of council briefing

2. Continue conversation of design preferences, design delivery approach, and design progression

October – December 2012

1. West Approach Bridge design coordination

2. Continued coordination on west side design development

Page 5: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

DRAFT – FOR INTERNAL DISCUSSION 8/16/12

Our Overall Vision The SR 520 Corridor is a critical, regional highway facility that enters the northern edge of downtown Seattle. Our vision for this corridor is to become the premier gateway to the City of Seattle by reconnecting to the early Seattle vision of Nature meets City. On the Seattle side, the SR 520 corridor aims to restore two important, intersecting axes that are shown in the historic 1909 “Seattle Parks and Boulevard Plan” that was created by the Olmsted brothers for the City of Seattle. The first is an east-west (natural) axis wherein a forested SR 520 corridor completes a gap in an “Emerald Necklace” by linking Interlaken Blvd. and the Arboretum as well as providing the primary gateway opportunities into downtown Seattle. The second is a north-south (urban) axis that begins with Montlake Blvd. at the University of Washington and extends along 23rd Ave. to Capitol Hill. The SR 520 Project has the opportunity to take the northern portion of this axis along Montlake Blvd. and create grand “parkway” that extends though East Lake Washington Blvd. into the Arboretum.

Our Vision for Current Users and Future Generations We intend to implement our Program in a manner that yields affordable solutions and fosters groundbreaking sustainability practices that support regional and local connectivity, ecology and the use of low-carbon materials. Further, the design of the corridor will balance aesthetics, functionality, proportion and sense of speed along the SR 520 facility to provide a memorable experience for all users. Specifically:

As motorists progress westbound from Lake Washington they will continue to experience a safe, efficient highway corridor that also represents a series of gateways from the edge of the lake into Montlake, across Portage Bay, and into downtown Seattle.

Pedestrians will always feel comfortable, visible, and safeguarded from vehicles on adjacent roadways. Their pathways will be well marked. Some pathways will allow pedestrians to efficiently move to their destinations such as transit stops or playgrounds. Other pathways will allow them to linger and enjoy their surroundings.

Cyclists will have great connections, good sight distances, and reasonable grades. Their wait times and passage through intersections will be equal to or shorter than motorized vehicles.

Transit users will enjoy convenient access to buses as well as safe, comfortable shelters.

All users should experience features that are scaled to their location and vantage points including bridge elements, tunnel portals, and overlooks.

The aesthetic expression of all constructed features shall be “naturalistic-contemporary” and complement their natural and residential surroundings.

Page 6: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

ExExExExExExExpapapapapandndndndnd a a a aandndndndnddd l l l llananananandsdsssddsscacacacacacaapepepepepepepe a a aaaaa p p pp pp pedededededededestrian anannd bibb cyccycyclcc e eee cocooconnnnnneccectitititionononn oo ovevevever rr I-I-I-5555●●●●●●PrPrPrPrPrPrProvovovovovidididididee e e e aaa aa liliililid dd dd thththththt atatatatat s s s s supupupupuppopopopoportrtrtrtrtrtts s sssss momomomomomomoststststststs llylyllyll passis vevv uuuseseses,ss, bbbicicicycycyclelee a dddndnd ppppppedededededededesesesee ttrtrtrtriiiaiaiaian n n n cococococococonnnnnnnnnnnnnnnnnnnnnnecececececececececeecececececeee tittitititiitt ononononons,s,s,s,s,s,s, a a a aaaandndndndndnn b b bb blelelelelendndndndndddddddddddddds sssss ssss ssssss ininininininninininninininnntototoototototototototototooooto ttt tt ttttttttttthehehehehheh ●●●●hihihihihiih lllllllllll sississidedededededee tt t to ooo ththththhe e e ee sossososossoutututututtthhhhhhhnInInnInncllclclclcclududududduddee e e ee aaa aa neneneeneeneww w ww inininininnteteteteteteteersrsrsrsrsrsrseeeeece tion dddddesigigigigigiggnn n n n nn ataaaaaa 10tth hh AvAvAvenenenueueue EEEasasasst ttt aaaananannd d d d DeDeDeDeeelmlmlmlmaraaaaaa DDDDDDDrivevevevvvee E EEE EEEasasasasasastttt●●●●●ExExExExExExExpapapapapapaandndndndndndnd B B BB BBBBBBBBBBBBagagagagagaaaa leleleleley yy y y vivvvviviviewewewewewewewpoint and provide stststststststrererreeeeetett pparara kikiingngngn o o on n n DeDeDeDeelmlmlmmar Drive Easssstttttt●●

Expand and landscape a pedestrian and bicycle connection over I-5 ●Provide a lid that supports mostly passive uses, bicycle and pedestrian connections, and blends into the ●hillside to the southInclude a new intersection design at 10th Avenue East and Delmar Drive East ●Expand Bagley viewpoint and provide street parking on Delmar Drive East ●

ROANOKE AREA

West Side Design Preferences

PrPrPrPrProcococococoo eeeeeeeeeed d d d d wiwiwww thththththtt f f f f furururururthththththererererere t t t t tececececece hnhnhnhnhniciciciccalalalalal a a a aanananananan lylylylylyysisisisis ss s sss ananananana d d d dd rererererefi fi fi fifi nenennenementntntntsss s fffoff r twtwtwtwtwo o oo oo brbrbrbrbrridididididdgegegegege t t t t typypypypypy eseseseses,, ,, thththththeee e e bobobobobooxx x x x gigigigig rdrdrdrdrdererererer aa a a andndndndnd cc cc cccabababababaa lelelelele ●●●●ststs ayayyyyededededed b bbbbriririririiidgdgdgdgdgeeeeeExExExExExplplplplplororororore e ee e wawawawawaw ysysysysys t t t tt tttttttttttooo ooooooooooo rererereredududududucecececee v v v vvisisisisisuauauauaaual l l l eeefefefefefeeeeeeeeffefefefefeff ctctctctctss sss s ananananandd d dd inininnntetetetetegrgrgrgrgrgg atatatatate e e e e thththththht e e e e ee stststststruruuuuuctctctctctururururure e e e e wiwiwiwiwithththththht ss s s surururururrorororrooounuununundididididingngngngng nnnnnn ieiieieieieieighghghhhhghhhghghbobbbbbobobbbobbbobob rhrhrhrhrhoooooooooodsdsdsdsds●●●●●PrPrPrPrPrP ovovovovovo idididididde ee e e ee pepepepepeeedededededestststststststtststststtsttriririririrrrr ananananann c c c c c cconononononnenenenenenen ctctctctctc ioioioioionsnsnsnsnsnsnsnsnssssnn fffffrororororromm m m mm DeDeDeDeDeDeDelmlmlmlmlml ararararar D D D DDriririririvevevevevev E EEE E EEasasasasast tttt tototototoo BB B B BBoyoyoyoyoyoyerererereree A A A A Avevevevevev nununununueeee e Eaaaaaststststst u uuuundndndndndderererererr P P P PPorororororrtatatatatagegegegege B B BB Bayayayayayy BBB BBBririririridgdgdgdgdgeeee●●●●StStStStStudududududy y y y y sasasasasafefefefefe a aaandndndndnd e e eeeffffffffececececectititittiveveveveve bb b b bicicicicicycycycycyclelelelee a a a a andndnddnd p p pp ppedededededesesesesestrtrtrtrtriaiaiaiaiannn nn cococococonnnnnnnnnnececececectititititionononononsss ss frfrfrfrfromomomomom M M MM Mononononontltltltlakakakakake eeee tototooto d ddowowowowwowntntntntntowowowowown n n nn SeSeSeeSeatatatata tltltltltlee ee e ananananana d dd d d nononononortrtrrtrtr h hh h h ●●●CaCaCaCaCapipipipipitototototol l ll l HiHiHiHiHiHH llllllllll

Proceed with further technical analysis and refi nements for two bridge types, the box girder and cable ●stayed bridgeExplore ways to reduce visual effects and integrate the structure with surrounding neighborhoods ●Provide pedestrian connections from Delmar Drive East to Boyer Avenue East under Portage Bay Bridge ●Study safe and effective bicycle and pedestrian connections from Montlake to downtown Seattle and north ●Capitol Hill

PORTAGE BAY BRIDGE

6 • Executive Summary

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 7: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

InInInInIncocococoorpprprprporororororaatatatate e e e e sisissimpmpmpmpppppppppmppleleleleleleleleleleleleleelee a a a aandndndnddnd c c c c cleleeeeanaananan dd dd desesesesesigigigigign nnn ofofofofoff tt tt theheheheheh sss s strtrtrtrtrtt ucucucucctututututurerererere●●●●●●MaMMMMaMaMMMaMaMaMM kekekkkekekkeekkkkke p p p ppatattttatttattathwhwhwhwhwayaaya s s s ss ununununundededededer r r r r thththt e e e brbrbrbrb idididididgegegegege s s s saffafe eee ananaanand dd d d atatattattrtrtrt acacacacactttitt ve ffffor ●●●●●●ususususu ererererersssssIIInI clclcllududududude eee e bebebebebelvlvlvlvlvedeedededererererereseseseses oo oo or r rr r rerererrestststststinininnng gg g g plplplplp acacacacaceseseseses a a a aalololololongngngngng t t tttheheheheheeeeeeeeeee n n n nnorororororththththth s s s s sididididideeee●●●●

Incorporate simple and clean design of the structure ●Make pathways under the bridge safe and attractive for ●usersInclude belvederes or resting places along the north side ●

Overall: ● Enhance connections for all users including bicyclists, pedestrians and transit users Canal Reserve area: ● Shift regional bicycle and pedestrian path onto the Montlake lid for better connections and to preserve open space Stormwater area: ● Integrate the stormwater wetland into the existing park and shorelineMontlake lid area: ● Activate the west portion of the lid and provide passive space at the east end. Option to lower transit/HOV ramps under the east side of the lid (see option B)Lake Washington Boulevard: ● Design the roadway to buffer neighbors from traffi c and integrate with the north entry of the ArboretumMontlake Boulevard: ● Provide planted medians for continuity and accommodate multimodal travel

●●●

WEST APPROACH BRIDGE

MONTLAKE AREA

Executive Summary • 7

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 8: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

1909 Seattle Parks and Boulevard Plan

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 9: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

SR 520 gateway opportunities and integration into the parks and boulevard network

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 10: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

Vision Key Map

Enhancing the Natural Blue-Green Axis Along the CorridorThe SR 520 project connects lakes, marshes, bays, shorelines, urban forests and open spaces.

Integrating an Historic BoulevardMontlake Boulevard East and East Lake Washington Boulevard are the historic footprint of the Olmsted multimodal parkway, providing varied users a sense of journey and arrival

Improving an Urban AxisMontlake Boulevard East connects two major activity centers: the University of Washington and downtown Seattle, with opportunities to work with partners to enhance the quality of experiences, safety and effi ciency of mobility, and the vibrancy of diverse neighborhoods.

Identifying Gatewaysto SeattleThe SR 520 project provides a series of natural and built “gateways” or defi ned entries, into Seattle: bridges, forests, bays, and lid portals.

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 11: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

Geographical Area Studies Introduction • 29

I-5 Crossing

Delmar Lid and Bagley Viewpoint

Delmar Drive East to Boyer Avenue Connection

Bill Dawson Trail/East Portage Bay Underbridge Area

East Montlake Lid

Montlake Boulevard East

West Montlake Lid and Canal Reserve

West Approach Abutment and

Lake Washington Shoreline

Stormwater Treatment Area and East Montlake Park

Roanoke Area

PortageBay Bridge

Montlake Area

East LakeWashington

Boulevard

WestApproachBridge

Geographical Areas Key Map

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 12: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

Design Preferences

Montlake Area • 45

BILL DAWSON TRAIL/EAST PORTAGE BAY UNDERBRIDGE AREA

MONTLAKE BOULEVARD EAST

EAST LAKE WASHINGTON BOULEVARD

WEST APPROACH ABUTMENT AND LAKE WASHINGTON SHORELINE

STORMWATER TREATMENT AREA AND EAST MONTLAKE PARKWEST MONTLAKE LID

AND CANAL RESERVEEAST MONTLAKE LID

Baseline alternative with refi nements based on community input (July 2012)

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 13: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

42 • Portage Bay Bridge

PORTAGE BAY BRIDGEDESIGN CONCEPTS

TAIGN

Highlights of the Portage Bay Bridge: Cable Stay OptionThe Cable Stay bridge design option maintains the roadway operations of the baseline while being shifted slightly to the north to ease constructability issues. Other issues that relate to the three primary perspectives of the bridge are:

OverTwo sets of moderate height cable stay towers (approximately 180 ●feet tall) at west end of bridge

UnderOne hillside foundation west of Boyer Avenue East with main span of ●800 feet minimizing impacts on Queen City Yacht Club operationsLonger span reduces in-water foundations and allows improved ●visibility and water access across Portage BayGap of 15 feet between bridge structures reduces scale of structure ●from below and allows light and air fl ow

OnThin, light bridge deck supported by cable stays ●Eastern bridge type beam bridge with common span lengths ●

Benefi tsProvides a regional signature bridge at Portage Bay ●Represents a modern design with lightness and transparency ●The long span opens the bay below for access and visibility ●Less material and less in-water work ●

ConsiderationsHigher design complexity needs to stay within the budget ●The towers must have rational and beautiful design ●

Cable Stay Option Alignment

Cable Stay Option Elevation

EastWest

View from Montlake Playfi eld facing northwestView from Montlake Boulevard E. facing westView from West Montlake Park facing southwest

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 14: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

Portage Bay Bridge • 43

Highlights of the Portage Bay Bridge:Box Girder OptionThe box girder bridge design option maintains the roadway operations of the baseline while the alignment is shifted slightly to the north to ease constructability issues. Other issues that relate to the three primary perspectives of the bridge are:

OverNo structure above bridge deck ●

UnderBox girder bridge at the west end with a maximum span length of 360 ●feetMore structure under bridge ●

OnThicker bridge deck with segmental construction ●Beam bridge to the east with variable span lengths ●Modifi ed planted median ●

Benefi tsCost-effi cient structure with moderate span lengths ●Variable depth at the columns provides curvilinear form ●

ConsiderationsModerate span lengths create operational and construction impacts ●on west end of bridge More in-water and hillside foundations in poor soils because more ●spans are required

Box Girder Option Alignment

Box Girder Option Elevation

EastWest

View from Montlake Playfi eld facing northwestView from Montlake Boulevard E. facing westView from West Montlake Park facing southwest

goodwil
Text Box
Draft - Conceptual August 16, 2012
Page 15: CCMP: NTMP: SCDP: WABN: SR 520 Project/MOU Implementation ... · Recommendation of 6392, ROD Permitting/Regulatory Agency Coordination WSDOT Lead: Jenifer Young, Scott White Participants:

DELMAR LID ANDBAGLEY VIEWPOINT

DELMAR DRIVE EAST TO BOYER AVENUE CONNECTION

I-5 CROSSING

Roanoke Area • 33

Baseline design with refi nements based on community input (July 2012)

Design Preferences

goodwil
Text Box
Draft - Conceptual August 16, 2012