1. Which model is popular for students’ small projects? A. Waterfall Model B. Spiral Model C. Quick and Fix model D. Prototyping Model 2. Which is not a software life cycle model? A. Spiral Model B. Waterfall Model C. Prototyping Model D. Capability maturity Model. 3. Product quality is defined as: A. Delivering a product with correct requirements B. Delivering a product using correct development procedures C. Delivering a product which is developed iteratively D. Delivering a product using high quality procedures 4. SRS stands for? A. Software requirement specification B. Software requirement solution C. System requirement specification D. None of Above 5. Software that monitors / analyzes / controls real-world events as they occur is called__________. A. Embedded software B. Real time software C. Real world Software D. None of the above 6. RAD stands for? A. Rapid Application Development

description

software engineering

Transcript of CC- SE Mcqs

Page 1: CC- SE Mcqs

1. Which model is popular for students’ small projects?

A. Waterfall ModelB. Spiral ModelC. Quick and Fix modelD. Prototyping Model

2. Which is not a software life cycle model? 

A. Spiral ModelB. Waterfall ModelC. Prototyping ModelD. Capability maturity Model.

3. Product quality is defined as:

A. Delivering a product with correct requirementsB. Delivering a product using correct development proceduresC. Delivering a product which is developed iterativelyD. Delivering a product using high quality procedures

4. SRS stands for? 

A. Software requirement specification B. Software requirement solutionC. System requirement specificationD. None of Above

5. Software that monitors / analyzes / controls real-world events as they occur is called__________.

A. Embedded softwareB. Real time softwareC. Real world SoftwareD. None of the above

6. RAD stands for? 

A. Rapid Application Development B. Relative Application Development C. Ready Application Development D. Repeated Application Development.

Page 2: CC- SE Mcqs

7. Which type of risk factor is most likely to cause problems for a software project developing commercial software?

A. Inadequate user documentation B. Litigation expense C. Low productivity D. Cancellation of project

8. _______________ refers to the support phase of software development.

A. Adaption B. Enhancement C. Maintenance D. Actions

9. What term refers to the degree to which a system is easy to learn and use?

A. ValidityB. VisibilityC. ReusabilityD. Usability

10. Which statement best describes the meaning of "waterfall" life cycle model.

A. When a phase in the lifecycle is completed, the results fall down to the next phase and there is no going back.

B. When a phase in the lifecycle iterates like a ring on the spiral, moving outward from the centre.

C. When a phase in the lifecycle overlapping with each others.D. When a phase in the lifecycle is executed continuously without stop.