CA_VINE_RMP

download CA_VINE_RMP

of 11

Transcript of CA_VINE_RMP

  • 8/2/2019 CA_VINE_RMP

    1/11

    Risk Management Plan

    Project Name: California Statewide VINE

    Department: Professional Services

    Project Manager: Stephen Adams

    Date: November 19, 2007

  • 8/2/2019 CA_VINE_RMP

    2/11

    Risk Management Plan

    INTRODUCTION.................................................................................................3

    PURPOSE AND SCOPE.....................................................................................3

    RISK MANAGEMENT PLANNING......................................................................4

    RISK IDENTIFICATION.......................................................................................5

    RISK ANALYSIS.................................................................................................6

    RISK PLANNING.................................................................................................6

    RISK MONITORING AND CONTROL.................................................................7

    RISK MANAGEMENT ASSIGNMENTS..............................................................7

    RISK CLASSIFICATION.....................................................................................8

    REFERENCED DOCUMENTS..........................................................................11

    DOCUMENT REVISION HISTORY....................................................................11

  • 8/2/2019 CA_VINE_RMP

    3/11

    Risk Management Plan

    INTRODUCTION

    The Appriss approach to risk management starts with a plan that defines the scope and process for

    the identification, assessment, and management of risks which could impact the implementation ofthe project. The objective of the Risk Management Plan is to define the strategy to manage project-

    related risks such that there is acceptable minimal impact on cost and schedule, as well as

    operational performance.

    PURPOSE AND SCOPE

    The purpose of the Risk Management Plan is to establish an approach to monitoring, evaluating,and managing risks throughout the life of the project. A risk is an uncertain event or condition that,

    if it occurs, has a negative or positive effect on the projects objectives.

    The risk management process will identify potential risk sources; assess individual risks andimpacts on performance, cost, and schedule; evaluate alternative approaches to mitigate high and

    moderate risks; and develop action plans to handle individual risks.

    The product of risk management planning will be the Risk Register. The Risk Register willdocument the various risks with their classification, mitigation and handling strategies, impact on

    cost and schedule, and action items.

    The risk management process includes these five elements.

    1) Risk Management Planning Deciding how to approach and conduct the risk

    management activities for the project.

    2) Risk Identification An initial and continuous effort to identify, quantify and

    document risks as they are identified.

    3) Risk Analysis Evaluate identified risks to determine probability of occurrence,

    impact, and timeframe.

    4) Risk Planning / Mitigation Establish an action plan for risk and assign

    responsibility.

    5) Risk Monitoring and Control Capture, compile, and report risk.

    03/16/2012 3 Version 1.0

  • 8/2/2019 CA_VINE_RMP

    4/11

    Risk Management Plan

    RISK MANAGEMENT PLANNING

    Risk management planning is the process of determining how to approach and conduct risk

    activities for the project. Planning is critical to establish the importance of risk management,allocating proper resources and time to risk management and establish the basis for evaluating risk.

    The diagram illustrates the functional relationships of the five risk management process elements:

    03/16/2012 4 Version 1.0

    LEGEND

    Decision

    Activity

    Output

    Identify Risk

    Analyze:

    Classify

    Evaluate

    Analyze:Prioritize

    Risk

    Statement

    Risk

    Class,

    Probability,

    impact,

    timeframe

    Prioritized list

    of task

    Plan:

    Assignresponsibility,

    Approve plans

    Assignments

    approved plans

    Plan:

    Define Mitigationapproach.

    Determine

    Mitigation plan

    Track: Control

    Risk mitigationplan

    Status Reports

    Decision

    - Close Risk

    - Take Planned Action

    - Continue Tracking

    - Replan

    Individual Activities

    Individual Activities

    Weekly and Monthly

    Weekly and Monthly

  • 8/2/2019 CA_VINE_RMP

    5/11

    Risk Management Plan

    RISK IDENTIFICATION

    A baseline set of risks will be created and entered into the project Risk Register. These baseline

    risks will be identified through the normal course of the project planning process. Risk statementswill be written for each identified risk. Risk statements will be clear concise and contain only one

    risk condition and one or more consequences of that condition.

    All project stakeholders are responsible for identifying new risks. New risks identified duringproject related meetings shall be captured and added to the Risk Register within two working days

    of the meeting. It will be the responsibility of the Appriss Project Manager to make sure this is

    accomplished.

    Appriss brings ten years of experience to the project in implementing similar systems. This

    experience has provided Appriss with a unique insight to common operation and system risks.

    Some of the common risks are documented in the table below. This table is not intended to be anexhaustive list.

    Risk Area Potential Risk

    Project Scope and Complexity Scope is not understood

    Requirements not documented properly

    Requirements not agreed upon by

    customer

    Complexity not understood in terms of:

    o Technology

    o Adapters needed

    o Number of users

    o Business process

    Technology Technology not proven

    Unreliable performance record ofvendors

    Inexperience with the technologies to be

    used

    Vendor infrastructure is not sound

    Staffing Inadequate resources committed to theproject

    Project team does not contain membersthat have experience with similar

    projects

    Resources pulled from project before

    completion

    Culture Users not willing to make business

    process changes

    Customer does not make a strong

    03/16/2012 5 Version 1.0

  • 8/2/2019 CA_VINE_RMP

    6/11

    Risk Management Plan

    commitment to project

    Organization changes within agency,

    removes key personnel

    Project Management Executive oversight committee is not

    actively engaged in project Project issues are not addressed

    Change is not controlled and project

    scope grows beyond original boundaries

    RISK ANALYSIS

    Appriss will use a qualitative approach to Risk Analysis. This methodology uses a risk level matrix

    based on probability and impact. This allows for an independent assessment of probability and

    consequence of risk.

    Each risk shall be evaluated to determine impact, probability of occurrence, and timeframe. Each

    risk shall be examined to determine its relationship to other risks identified. Initially, the identifier

    of the risk shall provide an estimate of these attributes. The Project Manager shall be responsiblefor further analyses and prioritization of the risks. The criteria for analyzing risks are established

    later in the Risk Classification section of this plan.

    RISK PLANNING

    Risk handling is the identification of a course of action or inaction selected for the purpose of

    effectively managing a given risk. All identified risks shall be handled. Specific handling methodsshould be selected after the probable impact on the project has been determined.

    The Appriss Project Manager will determine what action should be taken for each risk as it brought

    to his attention through weekly team meetings and database reports. The Appriss Project Managershall determine whether to keep the risk, delegate responsibility, or transfer the risk responsibility

    up the project organization chain. The Project Manager, if necessary, may transfer a risk(s) to

    external organizations if that organization is best suited to handle the risk.

    Risk planning requires a decision to perform further research, accept the risk (documentacceptance rationale in the Risk Register and close the risk), watch the risk attributes and status

    (define tracking requirements, document in the Risk Register, and assign a "watch" action), ormitigate the risk (create a Mitigation Plan, assign action items, and monitor the activities and risk).

    Mitigation activities shall be documented on the Risk Register or by creating a separate MitigationPlan. A Mitigation Plan shall be written for any effort that requires re-allocation of project

    resources. The Project Manager shall determine when to use a Mitigation Plan.

    03/16/2012 6 Version 1.0

  • 8/2/2019 CA_VINE_RMP

    7/11

    Risk Management Plan

    RISK MONITORING AND CONTROL

    Risk information and metrics defined during planning shall be captured, tracked and analyzed fortrends. The person assigned responsibility for the risk shall provide routine trend and status reports

    on research and/or mitigation activities to the Appriss Project Manager during the weekly projectmeetings. Watched risks shall be reported on during the monthly project meetings. The RiskRegister shall be used to report summary status, and a Stoplight Status Report shall be used by the

    Appriss Project Manager to report progress to senior management at the monthly reviews.

    Decisions shall be made by the Project Manager during the weekly and monthly meetings to close

    risks, continue to research, mitigate or watch risks, re-plan or re-focus actions or activities, orinvoke contingency plans. This is also the time when the Project Manager authorizes and allocates

    resources toward risks.

    RISK MANAGEMENT ASSIGNMENTS

    The following table describes the responsibilities of the project stakeholders:

    Who Responsibilities

    Individual Members Identify new risks

    Estimate probability of risk, impact, and time frame

    Classify risk

    Recommend action

    Assist in prioritizing risk

    Appriss Project

    Manager

    Collect all risk information from individuals

    Ensure accuracy of probability, impact and time frame Build the Risk Register

    Collect and report risk measures and metrics

    Report risk to senior management

    Prioritize Risk

    Executive Oversight

    Committee Authorize expenditures of resources for mitigation

    Authorize additional cost or time to mitigate risk.

    03/16/2012 7 Version 1.0

  • 8/2/2019 CA_VINE_RMP

    8/11

    Risk Management Plan

    The following table describes the criteria for communicating and documenting risk

    Who Responsibilities

    Individual Members

    to Project Manager

    Any risk that impacts performance

    Any risk that impacts >10 percent of budgetAny risk that exceeds schedule milestones

    Any risk that needs to be transferred to another team

    Project Manager toExecutive Oversight

    Committee

    Mitigation activity status

    Any risk that impacts mission success

    Any risk that causes the project budget to be exceeded by

    more that 10 percent

    Any risk that may negatively impact Appriss or their

    customers

    Risk status

    RISK CLASSIFICATION

    Risk shall be analyzed qualitatively using impact, likelihood and timeframe classifications definedin this section. Impact is based on project success, resources, cost, and schedule. Likelihood is

    used to provide an order of magnitude based on quantitative data and qualitative experience.

    Impact Classification

    High

    Schedule Slip Slip of delivery beyond two month of milestone schedules. Cost Overrun - > 10 percent increase in budget allocation.

    Technical Loss of critical function or major objective.

    Political Bad press for TOHS, DIR, TDEx, or other entities

    Significant

    Schedule Slip - > 1 month 5 percent but < 10 percent increase to budget

    Technical -Major function objective not fully met.

    Political - Senior Management has concerns about project success or

    development progress

    Low

    Schedule Slip - > 2 weeks

  • 8/2/2019 CA_VINE_RMP

    9/11

    Risk Management Plan

    Cost Overrun minor impact

    Technical Small impact to technical performance

    Likelihood Classification

    High (>70% chance of occurrence)

    Occurrence is very likely and may not be controlled by following existingprocesses, procedures and plans.

    Significant (40% - 70% chance of occurrence)

    Occurrence is likely and may not be entirely controlled by following existingprocesses, procedures and plans.

    Low (20% - 39% chance of occurrence)

    Occurrence is unlikely and may not be entirely controlled by following existing

    processes, procedures and plans.

    Negligible (

  • 8/2/2019 CA_VINE_RMP

    10/11

    Risk Management Plan

    Risk Classification Chart

    Green - Items classified as green are acceptable without further mitigation and will be routinely

    tracked.

    Yellow - Items classified as yellow may require mitigation. For these items, alternative

    dispositions will be identified and trade-offs conducted to determine the mitigation required.

    Red - Items classified as red are considered primary risk drivers. For these items, mitigationoptions will be developed. Red risks will be assessed for impact to budget reserves and will be

    tracked to closure.

    03/16/2012 10 Version 1.0

    High RED

    Significant YELLOW

    Low

    GREEN

    Negligible

    Negligible Low Significant High

  • 8/2/2019 CA_VINE_RMP

    11/11

    Risk Management Plan

    Timeframe is used in conjunction with the Risk Classification Chart to determine priorities,

    establish when risks need to have actions taken, and how long risks may need to be watched ortracked before they no longer are a concern or can be closed.

    Each project review meeting will result in an update to the project Risk Register that will be sent toall project personnel.

    REFERENCED DOCUMENTS

    1. Risk Register

    2. Mitigation Plan

    3. Stoplight Status Report

    Document Revision History

    Version Date Changes Updated By

    1.0 4/30/07 Original document C. Higginbotham

    03/16/2012 11 Version 1.0