Caversham Tunnel Civil Work Planning for Success
Transcript of Caversham Tunnel Civil Work Planning for Success
![Page 1: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/1.jpg)
www.fultonhogan.com
Caversham Tunnel Civil WorkPlanning for Success
![Page 2: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/2.jpg)
www.fultonhogan.com
The Caversham Tunnel• Dual track tunnel
constructed in 1908 to replace old single line tunnel.
• Hand cut drainage channel through out the length
![Page 3: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/3.jpg)
www.fultonhogan.com
Back Ground to project
• Drainage issues within Caversham tunnel and approaches, leading to formation failure
• This leads to reduction in level of service from KiwiRail to external clients
• Drainage issues linked to bad ballast and completely blocked drainage system.
• Works designed to increase resilience of network within tunnel against ballast and formation degradation
![Page 4: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/4.jpg)
www.fultonhogan.com
Risk Management• Three main risk considerations
– Gas– Network Services– Rockfall
![Page 5: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/5.jpg)
www.fultonhogan.com
Gas
![Page 6: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/6.jpg)
www.fultonhogan.com
Gas
![Page 7: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/7.jpg)
www.fultonhogan.com
Gas
![Page 8: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/8.jpg)
www.fultonhogan.com
Network Services
• Up to 28 movements a day• Only 3-5 at night • Trains ran throughout the duration of the project
![Page 9: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/9.jpg)
www.fultonhogan.com
Network Services
Compulsory Stop Protection
![Page 10: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/10.jpg)
www.fultonhogan.com
Rock fall
• Unlined sandstone tunnel • Rock fall risk in certain area of tunnel
![Page 11: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/11.jpg)
www.fultonhogan.com
Planning and Logistics
• Block of Line in two 72 hour periods
• 3 separate contracting groups working together to deliver outcome
• FH to remove old ballast and regrade and compact formation
![Page 12: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/12.jpg)
www.fultonhogan.com
Planning and Logistics
![Page 13: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/13.jpg)
www.fultonhogan.com
Planning and Logistics
![Page 14: Caversham Tunnel Civil Work Planning for Success](https://reader031.fdocuments.us/reader031/viewer/2022012301/61e1902f72ce9639d95d42e1/html5/thumbnails/14.jpg)
www.fultonhogan.com
Planning and Logistics