Caspian Environment Programme

8

Transcript of Caspian Environment Programme

Page 1: Caspian Environment Programme
Page 2: Caspian Environment Programme
Page 3: Caspian Environment Programme

TDA/NCAP/SAP Process

• CEP made the conscious and early decision in development of the TDA, NAPs and SAP to stress equal importance to process and the final products themselves.

• Country involvement, dialogue and commitment were set as paramount goals.

• The final products were truly collaborative efforts, during two and a half years the following meetings were held:

- Thirty thematic meetings (biodiversity, ICZM, fisheries, emergency response, etc)

- Five major TDA workshops - Fifteen NAP workshops/consultation meetings (three per country) - Two major SAP workshops

Page 4: Caspian Environment Programme

TDA Barriers

• Fixed perceptions

• Information rich, data poor

• A wealth of anecdotal evidence – a hundred anecdotes are no better than one

• Institutes with vested interests in promoting a bleak picture

• No national prioritization of the problems and little knowledge of wider stakeholder concerns

Page 5: Caspian Environment Programme

NAPs vs SAP

What should be developed first, the National Action Plans or the Regional Strategic Action Programme?

Developing NAPs first:

• Enables countries to prioritize national and regional (transboundary) issues together.

• Countries are forced to enter into meaningful inter-sectoral dialogue and address the key question of resource mobilization at an early stage.

• Countries can commit to and endorse a NAP at the highest level and in doing take the first step towards collective stewardship of the environment.

• In reviewing each other’s NAPs countries are better able to prioritize regional issues and thereby produce a more focused SAP.

Page 6: Caspian Environment Programme

NAP vs SAP

Developing the SAP first:

• Gives priority to regional problems over national problems, and lays unfair and untenable claims to limited resources.

• With more than two or three countries Government endorsement of a SAP is difficult, if not impossible. SAP documents are often adopted at solely at the Ministry level and do not go through an inter-sectoral consultation procedure.

• If not supported by NAPs there is no true commitment to the SAP and retro-fitting seldom works.

Page 7: Caspian Environment Programme

National issues Regional issues

Regional issues National issues

Combining the NAP commitments to create a SAP

SAP

Page 8: Caspian Environment Programme

Tools for SAP prioritization

• The causal chain analysis is an excellent tool to show how an issue should be addressed, step-by-step, bottom-up and to help determine and shape required interventions.

• Environmental Quality Objectives helps to develop a broad stakeholder agreement on the priority regional environment issues and once agreed allows quantifiable targets to be set to meet those objectives. From there it is a relatively step to define interventions. A top-down approach.

• In drafting the Caspian SAP both tools were used, first CCA and then EQOs, with a final analysis of interventions to ensure the common and specific root causes had been addressed