Case Study - PT Newmont

download Case Study - PT Newmont

of 25

description

Etap PT Newmont Steel Plant CS

Transcript of Case Study - PT Newmont

  • 5/26/2018 Case Study - PT Newmont

    1/25

    ETAP RealETAP Real--Time ProjectsTime ProjectsPT NewmontPT Newmont

  • 5/26/2018 Case Study - PT Newmont

    2/25

    ConfidentialETAP Rep Symposium December 2005

    System DescriptionSystem Description -- LocationLocation

    Copper-Gold Mine

    Sumbawa-Indonesia

    Project held by PT Newmont Nussa Tenggara

    (PTNNT)

  • 5/26/2018 Case Study - PT Newmont

    3/25

    ConfidentialETAP Rep Symposium December 2005

    System DescriptionSystem Description -- ProcessProcess

    Open Pit Mine

    Use Electrical Shovels

    and Mechanical Drive Trucks to Transport the Ore

    Handles Around 600,000 t/d of Ore and Waste

    0.49% Copper and 0.39g/t Gold

  • 5/26/2018 Case Study - PT Newmont

    4/25

    ConfidentialETAP Rep Symposium December 2005

    System DescriptionSystem Description -- ProcessProcess

    From Primary Crusher Ore Transported on a

    6.8 km Overland Conveyor

    In Concentrator Sag and

    Ball Mills Produce32% Copper and

    19.9 g/t of Gold

    Ore is Pipelined to Benette (port) for Sea

    Transport

  • 5/26/2018 Case Study - PT Newmont

    5/25

    ConfidentialETAP Rep Symposium December 2005

    System DescriptionSystem Description -- ElectricalElectrical

    Power Plant

    4 Steam Turbine Generators 34MW each

    9 Diesel Generators 5 MW each

    Power Plant Located Next to Benette Transmission

    2 - 15kM Lines to Concentrator and MineSubstations

  • 5/26/2018 Case Study - PT Newmont

    6/25

    ConfidentialETAP Rep Symposium December 2005

    System DescriptionSystem Description -- ElectricalElectrical

    Concentrator Loads

    4 Ball Mills (10K HP) and 2 Sag Mills (13.4MW)

    Other Process Loads Including Pumps, Fans,etc.

    Mine Loads

    Shovels, Primary Crusher Motors, Township,etc.

  • 5/26/2018 Case Study - PT Newmont

    7/25

    ConfidentialETAP Rep Symposium December 2005

    System DescriptionSystem Description -- ElectricalElectrical

  • 5/26/2018 Case Study - PT Newmont

    8/25

    ConfidentialETAP Rep Symposium December 2005

    Why ETAP RealWhy ETAP Real--TimeTime

    for PT Newmont ?for PT Newmont ?

  • 5/26/2018 Case Study - PT Newmont

    9/25

    ConfidentialETAP Rep Symposium December 2005

    Process Time LossesProcess Time Losses

    Repeated Productions Losses

    Faults caused by animals in the transmissionsystem

    Load variation caused instability in thegenerators when operating at maximum load

    Too Much Load Variation

    Could not shed shovels, port, or other variableloads because never knew how much wasshed

  • 5/26/2018 Case Study - PT Newmont

    10/25

    ConfidentialETAP Rep Symposium December 2005

    Process Time LossesProcess Time Losses

    Only Constant Loads

    Sag Mills, Ball Mills, Overland Conv. Process time lost if any of those loads tripped

    $300K+ lost every trip on those loads

    High Generation Cost

    Had to run many diesels generators during

    normal operation Keep spinning reserve high and improve

    reliability

  • 5/26/2018 Case Study - PT Newmont

    11/25

    ConfidentialETAP Rep Symposium December 2005

    ETAP RealETAP Real--TimeTime -- SolutionSolution

    ETAP ILS Provides PTNNT

    Monitoring of each sheaddable feeder and

    load

    Right combination of loads to trip

    Unlimited Load Priority Tables i.e. Winter

    process changes and therefore load priority

    changes

  • 5/26/2018 Case Study - PT Newmont

    12/25

    ConfidentialETAP Rep Symposium December 2005

    ETAP RealETAP Real--TimeTime -- SolutionSolution

    Load Shedding against:

    One steam generator trip

    Multiple generators trip

    Boiler trips

  • 5/26/2018 Case Study - PT Newmont

    13/25

    ConfidentialETAP Rep Symposium December 2005

    Old SCADA LimitationsOld SCADA Limitations

    Costly to expand

    Low performance

    Limited trending and no reporting features

    Primitive calculations techniques i.e. wrongfrequency display for 2 min when one Gen goesoffline

    No remote control for line breakers and processloads

  • 5/26/2018 Case Study - PT Newmont

    14/25

    ConfidentialETAP Rep Symposium December 2005

    ETAP RealETAP Real--TimeTime -- SolutionSolution

    Real-Time Monitoring provides PTNNT:

    Complete monitoring of the system

    Control of their transmission and distributionbreakers

    Trending, archiving, reporting of mainparameters:

    Frequency, generation, powertransmission, power generation, energyconsumption

  • 5/26/2018 Case Study - PT Newmont

    15/25

    ConfidentialETAP Rep Symposium December 2005

    How was it accomplished?How was it accomplished?

  • 5/26/2018 Case Study - PT Newmont

    16/25

    ConfidentialETAP Rep Symposium December 2005

    ETAP RealETAP Real--TimeTime -- ProjectProject

    Divided on Three Phases

    Phase 1

    Modeling and system studies

    Communication network design and

    implementation Phase 2

    Data collection system and ETAP Real-Time setup

    Phase 3

    Load shedding setup and installation

  • 5/26/2018 Case Study - PT Newmont

    17/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    ETAP Model Verification

    Newmont already have an ETAP model

    System data sent to OTI office for modelverification

    Metering Evaluation

    General Electric SR relays in place

    Studies data collection speed requirements

    Load variation

  • 5/26/2018 Case Study - PT Newmont

    18/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    System Studies to determine:

    Steady and transient stability limits

    Max. allowable load shedding time

    Min. load to shed for certain events Triggers

  • 5/26/2018 Case Study - PT Newmont

    19/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    Communication Network Design

    Best method of networking existing metersDetermined meters to replace

    Report and drawings submitted to Newmont

    Communication Network Implementation

    Done in house by PT Newmont Engineers

    Replacement of 12 relays to URs for maximumdata collection

    Phase 1 completion, about 3 Months

  • 5/26/2018 Case Study - PT Newmont

    20/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

  • 5/26/2018 Case Study - PT Newmont

    21/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    Data Collection System Setup

    OPC Server installation and setup

    Setup done at OTI offices

    Installation and tuning done onsite 1 weektrip

    ETAP Real-Time Server Installation

    Done in conjunction with OPC Server setup

  • 5/26/2018 Case Study - PT Newmont

    22/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    Primary and Auxiliary Console Setup

    Remote Control

    Playback

    Real-Time MonitoringArchive Server for Reporting

    Phase 2 Completion 2 Months

  • 5/26/2018 Case Study - PT Newmont

    23/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    PLC Programming

    Trigger Handling

    Priority Table Handling

    Performed in OTI Tested Onsite by OTI and Newmont Engineers

    Timing Fine Tuned Onsite

  • 5/26/2018 Case Study - PT Newmont

    24/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    ETAP ILS Server installed

    Separate from Real-Time Server for reliabilitypurposes

    Trigger Communication

    Wired triggers to PLCs

    Routed some triggers using IP tunneling

  • 5/26/2018 Case Study - PT Newmont

    25/25

    ConfidentialETAP Rep Symposium December 2005

    Project StepsProject StepsPhase 1Phase 1

    Complete test of communication

    Monitoring

    ILS calculations with real system data

    Triggers tested Final SAT

    Phase 3 completion, about 3 months