Case Study : Project Risk Management...Case Study : Project Risk Management Jeremy Harrison Head of...

10
Case Study : Project Risk Management Jeremy Harrison Head of Project Risk & Value Management The Headline Case s tudy Project ris k managemen t • Using s care resources effectively through risk management • Managing risk profile in a complex environment • Deliv ering confidence to stak e holders a nd customers Jeremy Harrison Head o f Project Risk & Value Management, NetworkRail

Transcript of Case Study : Project Risk Management...Case Study : Project Risk Management Jeremy Harrison Head of...

  • Case Study : Project Risk Management

    Jeremy Harrison

    Head of Project Risk & Value Management

    The Headline

    Case studyProject risk management

    • Using scare resources effectively through

    riskmanagement• Managing risk profile in a complex

    environment• Delivering confidence to stakeholders and

    customersJeremy HarrisonHead of Project Risk & Value

    Management,NetworkRail

  • The Possession

    • The Problem

    • The Response – the detail

    • The Effect – the benefits.

  • Possessions

    • What are ‘possessions’?

    – What do we want? – confidence in hand back to operation.

    • Mini projects within the overall project with

    Start and End points

    • Worksites within possessions.

    An example – possession complexity

    TLP Core Area possession

    TLP Other works

    TLP Outer Areas possession

    ATF cable works

    Platform

    electrical works

    Harpenden

    bridge works

    Bi-diturnback West

    HampsteadOLE works

    Blackfriars

    Bridge Slide

    Fleet Sewer

    Diversion

    Farringdon

    Jn

    Manhole 4ATF prep works

    BFR CTK ZFD

    SPI

    MOG ZBB

    KTN WHPEPH STP

    CRI HEN MIL ELS RDT SAC HPD LTN LUT LEA HLN FLT BDM

    KGX FPK

    BFR CTK ZFD

    SPI

    MOG ZBB

    KTN WHPEPH STP

    CRI HEN MIL ELS RDT SAC HPD LTN LUT LEA HLN FLT BDM

    KGX FPK

    St Albans

    track slew

    Luton OLE

    works

    KX possessionKings Cross

    Platform Y commissioning

    London Bridge Box Works (Maintenance

    contracted to manage)

    N229 Shard of Glass piling

    works

    N244 Gipsy Hill TP Hut prep

    works

  • Structure of the Process

    • Worksites and hence possessions

    booked months (years in advance)

    • Worksites – simple risk assessment

    – Risk Factor – 1 to 3

    – Profile Factor – 1 to 3

    – Impact Factor – 1 to 3.

  • Possession Quantified Schedule Risk Assessment (QSRA)

    • What is it in layman's terms?

    – Modelling effect of uncertainty and risks on the deterministic plan

    – The challenge

    • ‘Everything should be made as simple as possible,

    but no simpler’ Albert Einstein

    • ‘1000 line plans’ into something that can be

    modelled.

    What was the job?

    Tipton Level

    Crossing

    Replacement

    Easter 2009

  • The context

    What is driving the schedule?

    0120 - Jack the box (main push) 65%

    0160 - Backfill stage 2 42%

    0180 - Track ballast lower layer 24%

    0190 - Ballast top layer and track laying 24%

    0090 - Excvn Stage 3 & bottom up East of S&T 19%

    0060 - Excavation stage 1 from West 19%

    0140 - Bottom layer stone 13%

    0080 - Excavation stage 2 13%

    0210 - Tamp track 8%

    0220 - Top up ballast etc (incl reinstate track circuit leads, H&S) 5%

    0260 - Handback worksite 5%

    0050 - Excavation stage 1 from East 4%

    0010 - Take possession 3%

    0290 - Risk - high winds/weather delays work 1%

    Tipton Easter possession clamping in lieu weld and stressSchedule Sensitivity Index

    Analysis

    Simulation: Latin HypercubeIterations: 1000

    Schedule Sensitivity Index

    Values are displayed for:All tasks in the plan

    Display settings

    Normal tasks onlyShowing 14 highest tasks

  • Delivering Confidence

    Cum

    ula

    tive F

    requency

    Hits

    0

    29

    58

    87

    116

    145

    Distribution (start of interval)

    13/Apr/09 10:45 13/Apr/09 19:45 14/Apr/09 04:45 14/Apr/09 13:45

    5% 13/Apr/09 15:45

    10% 13/Apr/09 17:00

    15% 13/Apr/09 17:45

    20% 13/Apr/09 18:15

    25% 13/Apr/09 19:00

    30% 13/Apr/09 19:15

    35% 13/Apr/09 19:45

    40% 13/Apr/09 20:15

    45% 13/Apr/09 20:45

    50% 13/Apr/09 21:15

    55% 13/Apr/09 21:30

    60% 13/Apr/09 22:15

    65% 13/Apr/09 22:30

    70% 13/Apr/09 23:15

    75% 13/Apr/09 23:45

    80% 14/Apr/09 00:30

    85% 14/Apr/09 01:30

    90% 14/Apr/09 02:30

    95% 14/Apr/09 04:00

    100% 14/Apr/09 14:30Analysis

    Simulation: Latin HypercubeIterations: 1000

    Convergence

    Plan Finish Date:Converged in 200 iterations(variation < 1% over 100 iterations)Total Plan Cost:Converged in 200 iterations(variation < 1% over 100 iterations)

    Statistics

    Minimum: 13/Apr/09 11:00Maximum: 14/Apr/09 14:30Mean: 13/Apr/09 21:15Max Hits: 158Std Deviation: 14.94

    Selected Confidence90%: 14/Apr/09 02:30Deterministic Finish: 13/Apr/09 17:45Probability 15%

    Tipton Easter possession clamping in lieu weld and stressEntire Plan : Finish Date

    Network Rail

    Delivering Confidence

    Likelihood of completing the works

    50% 80% 95%

    Possession hand back Time

    Tues 14th Apr 05:00

    Tues 14th Apr 05:00

    Tues 14th Apr 05:00

    Modelled Completion Time

    Mon 13th Apr 21:15

    Tues 14th Apr 00:30

    Tues 14th Apr 04:00

    Project Float 7hrs 45mins 4hrs 30mins 1hr

  • The QSRA

    • Creating confidence

    – 90% confidence as normal threshold

    – The other 10% -

    • Contingency planning for the works

    • Contingency planning for the train service

    – Using the QSRA to full advantage

    • When do you need to react?

    The QSRA Programme

    ID DescriptionRemainingDuration Start Finish

    XMAS 2009

    XMAS 2009.4

    XMAS 2009.4.0010

    XMAS 2009.4.0010.0400

    XMAS 2009.4.0010.0400.0420

    A5560

    A5570

    A5580

    A5590

    A5600

    A5610

    A5660

    A5670

    A5680

    A5690

    A5700

    A5710

    A5770

    A5780

    A5790

    XMAS 2009.4.0010.0400.0430

    A5720

    A5730

    A5740

    A5750

    A5760

    XMAS 2009.4.0010.0080

    A5170

    A5170: B

    A5170:035

    A5180

    A5180: B

    A5180:035

    WK40-2100

    WK40-2105

    WK40-2105: B

    WK40-2105:021

    WK40-2175

    WK40-2240

    WK40-2355

    WK40-3350

    XMAS 2009.4.0010.0110

    A5370

    A5380

    XMAS 2009.4.0010.0380

    A1460

    A2140

    A2140: B

    A2140:040

    A2370

    A3090

    A3120

    A5190

    BF0005

    BF1660

    XMAS 2009.4.0010.0390

    A1600

    A5010

    A5035

    A5040

    A5050

    A5450

    A5460

    A5470

    A5480

    A5490

    A5500

    A5510

    A5520

    BF1640

    BF1670

    XMAS 2009.4.0010.0140

    A5390

    A5400

    XMAS 2009.4.0010.3

    WK40-6

    WK40-6: B

    WK40-6:015

    WK40-6:018

    WK40-6:019

    WK40-6:022

    WK40-6000

    WK40-6010

    WK40-7

    XMAS 2009.4.0010.0120

    Master Programme - Christmas 2009

    Farringdon Integrated Programme

    Possession Milestones & Key Events

    HANDOVER MILESTONES

    Mainline Works

    N246 - Support Works Part 1 Complete

    Start of CoLOR Works Part 1 - Fleet Sewer Works

    CoLOR Works Part 1 Complete - Fleet Sewer Works

    Start of N246 Support Works Part 2

    CoLOR Works Part 2 Complete - Manhole 4 Construction

    Start of N246 Support Works Part 3

    N246 - Main Line Completion of Plain Lining for WSRL

    WSRL - Start of Cable/Equipment Re-Instatement

    0440 - CoLOR Float of 24hrs in main programme but exclude...

    WSRL - Cable/Equipment Re-Instatement Complete

    WSRL - Test Track Circuit in P'Way Area Complete

    N246 - Support Works Part 3 Complete - Siding Reinstateme...

    WSRL - Start of Wheels Free Correspondence Testing

    WSRL - Wheels Free Correspondence Testing Complete

    N246 - Start of Signal Documentation

    Smithfield Sidings Work

    WSRL - Start Recconection/Test Smithfields Sidings

    WSRL - Recconection/Test Smithfields Sidings Complete

    WSRL - Start Test & Correspond Track Circuits

    WSRL - Test & Correspond Track Circuits Complete

    N246 - Site Handback Checks

    NR Possession & Handback - Main Line

    Train Movement - Train Arrival (TBC)

    Train Movement - Train Arrival (TBC)

    RS: Class 73 loco failure

    Train Movement - Train Departs (TBC)

    Train Movement - Train Departs (TBC)

    RS: Class 73 loco failure

    NR Possession Main Line TLP - Setup Worksite/ Issue Permits

    NR Possession Main Line TLP - Take Possession/Isolation (...

    NR Possession Main Line TLP - Take Possession/Isolation (AC & DC)

    RISK - Late Hand Over of Possession - 5% 0.25h 0.5h 0.5h

    NR Possession Main Line TLP - Start of Possession (Poss R...

    NR Possession Main Line TLP - Energise & Handback AC/DC

    NR Possession Main Line TLP - End of Possession (Poss Re...

    NR Possession Main Line TLP - Works Complete

    N246 Support Works Part 1 - Remove Mainline & Siding

    N246 Support Works Part 1 - Remove Mainline & Siding Com...

    Start of N246 Support Works Part 1 - Remove Mainline & Siding

    WRSL Works - R North

    Shorten Possession

    Take Possession & Isolation

    Take Possession & Isolation

    Late possession and isolation for St Pancras Bi-Di

    Start of Wheels Free Testing - R North

    Sign Out Signalling

    Sign Signalling Back Into Use - R North

    COSS Briefings

    Start of Possession

    End of Possession - R North

    WRSL Works - R South

    R South Disconnection

    Testing Documentation

    Sign Smithfield Sidings Back Into Use

    Handback Possession - R South

    Start of Wheels Free Testing - R South

    Fit S&T Cables & Equipment - Main Line

    Fit S&T Cables & Equipment Completed- Main Line

    S&T Testing - Main Line

    S&T Testing Completed- Main Line

    Fit S&T Cables & Equipment - Smithfield Sidings

    Fit S&T Cables & Equipment Completed- Smithfield Sidings

    S&T Testing - Smithfield Sidings

    S&T Testing Completed - Smithfield Sidings

    Sign-in Signalling - R South

    End of Possession - R South

    N246 Works - Moorgate Branch Recovery & Plain Line Dbl Jnc

    Start of N246 Works - Moorgate Branch Recovery & Plain Dbl ...

    N246 Works - Moorgate Branch Recovery & Plain Dbl Jnc Co...

    CoLOR Works Part 1 - Fleet Sewer Works

    Mobilise Plant into Position (CoLOR Fleet Sewer Works)

    Mobilise Plant into Position (CoLOR Fleet Sewer Works)

    RISK - RRV Breakdown - 20% 1h 2h 3h

    RISK - Operator Illness - 1% 1h 2h 3h

    RISK - Off track access blocked by others (Access point pending) - ...

    RISK - Disruption by third Parties (NR track replacement etc) - 20% 3...

    Start of CoLOR Works Part 1 - Fleet Sewer Works

    CoLORWorks Part 1 - Fleet Sewer Works Completed

    Protect Existing Track & S&T

    N246 Support Works Part 2 - Main Line Reinstatement

    202.00h

    201.75h

    201.75h

    190.25h

    181.50h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    8.75h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    145.00h

    0.25h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.75h

    1.50h

    1.50h

    0.00h

    0.00h

    1.50h

    0.00h

    0.00h

    6.00h

    0.00h

    0.00h

    49.50h

    1.00h

    1.50h

    1.50h

    0.00h

    0.00h

    0.25h

    0.50h

    0.75h

    0.00h

    0.00h

    196.75h

    2.50h

    1.00h

    0.25h

    0.50h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    29.50h

    0.00h

    0.00h

    99.00h

    6.00h

    6.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    0.00h

    6.00h

    35.25h

    24/12/2009 23:15

    24/12/2009 23:30

    24/12/2009 23:30

    25/12/2009 07:45

    25/12/2009 07:45

    25/12/2009 08:45

    29/12/2009 11:45

    01/01/2010 15:45

    30/12/2009 01:00

    30/12/2009 12:00

    30/12/2009 18:00

    30/12/2009 22:00

    01/01/2010 21:15

    01/01/2010 21:15

    02/01/2010 03:45

    02/01/2010 05:45

    24/12/2009 23:30

    25/12/2009 01:45

    25/12/2009 01:45

    25/12/2009 01:45

    30/12/2009 02:15

    30/12/2009 02:15

    25/12/2009 01:00

    24/12/2009 23:30

    24/12/2009 23:30

    25/12/2009 01:00

    *24/12/2009 23:30

    30/12/2009 23:00

    25/12/2009 01:45

    25/12/2009 01:45

    24/12/2009 23:30

    27/12/2009 00:00

    24/12/2009 23:30

    24/12/2009 23:30

    25/12/2009 01:00

    25/12/2009 11:00

    25/12/2009 01:00

    26/12/2009 23:30

    25/12/2009 01:00

    *24/12/2009 23:30

    25/12/2009 01:45

    25/12/2009 01:45

    30/12/2009 22:00

    02/01/2010 06:15

    30/12/2009 23:00

    30/12/2009 18:00

    29/12/2009 23:00

    30/12/2009 12:00

    01/01/2010 21:15

    02/01/2010 03:45

    25/12/2009 07:45

    25/12/2009 07:45

    25/12/2009 08:45

    25/12/2009 08:45

    25/12/2009 08:45

    25/12/2009 14:45

    25/12/2009 14:45

    25/12/2009 14:45

    25/12/2009 14:45

    25/12/2009 08:45

    25/12/2009 14:45

    29/12/2009 11:45

    02/01/2010 09:15

    02/01/2010 09:15

    02/01/2010 09:15

    02/01/2010 06:00

    01/01/2010 21:15

    25/12/2009 07:45

    29/12/2009 11:45

    01/01/2010 15:45

    30/12/2009 01:00

    30/12/2009 12:00

    30/12/2009 18:00

    01/01/2010 21:15

    30/12/2009 22:00

    02/01/2010 06:00

    02/01/2010 03:45

    02/01/2010 05:45

    31/12/2009 00:30

    25/12/2009 02:00

    25/12/2009 01:45

    30/12/2009 02:15

    30/12/2009 02:15

    30/12/2009 02:15

    25/12/2009 01:45

    25/12/2009 01:00

    25/12/2009 01:00

    25/12/2009 01:00

    31/12/2009 00:30

    31/12/2009 00:30

    30/12/2009 23:00

    25/12/2009 07:45

    25/12/2009 07:45

    27/12/2009 01:00

    27/12/2009 01:00

    25/12/2009 01:00

    25/12/2009 01:00

    25/12/2009 01:00

    25/12/2009 01:15

    27/12/2009 00:00

    25/12/2009 01:45

    27/12/2009 01:00

    02/01/2010 06:30

    25/12/2009 04:15

    30/12/2009 23:00

    02/01/2010 06:30

    30/12/2009 23:30

    30/12/2009 12:00

    30/12/2009 18:00

    02/01/2010 03:45

    02/01/2010 05:45

    30/12/2009 23:00

    30/12/2009 23:30

    26/12/2009 13:15

    26/12/2009 13:15

    29/12/2009 11:45

    25/12/2009 14:45

    25/12/2009 14:45

    25/12/2009 14:45

    25/12/2009 14:45

    25/12/2009 14:45

    25/12/2009 14:45

    29/12/2009 11:45

    25/12/2009 20:45

    30/12/2009 23:00

    MinimumDuration

    MostLikely

    MaximumDuration

    0.50h

    0.50h

    0.50h

    1.00h

    0.25h

    1.00h

    1.00h

    0.75h

    0.25h

    0.25h

    0.25h

    0.25h

    2.00h

    0.75h

    0.25h

    0.25h

    5.00h

    1.00h

    1.00h

    3.00h

    3.00h

    1.00h

    1.00h

    1.00h

    0.75h

    1.50h

    0.50h

    1.50h

    1.00h

    1.50h

    0.50h

    0.25h

    0.50h

    0.75h

    2.50h

    1.00h

    0.25h

    0.50h

    6.00h

    2.00h

    2.00h

    6.00h

    6.00h

    6.00h

    1.50h

    1.50h

    0.75h

    2.00h

    0.50h

    2.00h

    1.00h

    1.50h

    0.50h

    0.50h

    0.75h

    0.75h

    3.00h

    1.25h

    0.25h

    0.50h

    8.00h

    3.00h

    3.00h

    12.00h

    12.00h

    8.00h

    25 Dec '20091 3 5 7 9 11 13 15 17 19 21

    26 Dec '20091 3 5 7 9 11 13 15 17 19 21

    27 Dec '20091 3 5 7 9 11 13 15 17 19 21

    28 Dec '20091 3 5 7 9 11 13 15 17 19 21

    29 Dec '20091 3 5 7 9 11 13 15 17 19 21

    30 Dec '20091 3 5 7 9 11 13 15 17 19 21

    31 Dec '20091 3 5 7 9 11 13 15 17 19 21

    1 Jan '20101 3 5 7 9 11 13 15 17 19 21

    2 Jan '20101 3 5 7 9 11 13 15

    5%

    5%

    5%

    5%

    1%

    1%

    0%

    0%

    25/12/2009 07:45

    25/12/2009 08:45

    29/12/2009 11:45

    29/12/2009 11:45

    01/01/2010 15:45

    01/01/2010 15:45

    30/12/2009 01:00

    30/12/2009 01:00

    30/12/2009 12:00

    30/12/2009 12:00

    30/12/2009 18:00

    01/01/2010 21:15

    30/12/2009 18:00

    30/12/2009 22:00

    30/12/2009 22:00

    01/01/2010 21:15

    02/01/2010 03:45

    02/01/2010 03:45

    02/01/2010 05:45

    02/01/2010 05:45

    25/12/2009 01:45

    30/12/2009 02:15

    *24/12/2009 23:30

    31/12/2009 00:30

    30/12/2009 23:00

    25/12/2009 07:45

    25/12/2009 01:45

    25/12/2009 11:00

    *24/12/2009 23:30

    27/12/2009 01:00

    30/12/2009 18:00

    29/12/2009 23:00

    30/12/2009 12:00

    30/12/2009 12:00

    30/12/2009 18:00

    01/01/2010 21:15

    02/01/2010 03:45

    02/01/2010 03:45

    02/01/2010 05:45

    30/12/2009 23:00

    30/12/2009 23:30

    25/12/2009 07:45

    26/12/2009 13:15

    25/12/2009 08:45

    29/12/2009 11:45

    Master Programme - Christmas 2009 (Pre-mitigated)

    Xmas 2009 Primavera Gantt

  • Critical Review

    • Robust process tested, challenged,

    reliable and improving • (QSRA results data analysis)

    • Confidence – where are we?

    • Interdependences

    • Learning

    BS31100

    • Governance and structure

    – Are we doing what we say we are?

    • Risk appetite

    – What level of risk can we and are we taking?

    • The risk management process

    – Structured risk assessment process

    • Risk response

    – Do we have appropriate contingency processes in

    place?

  • What have we learnt?

    • Process vs Outcome for creating

    confidence - THINKING

    • Keep checking

    • QSRA accuracy improving

    • Quality of planning

    • NEVER ASSUME ANY THING