Case study on Data Analytics for Improved Schedule Quality

23
Copyright @ 2011. All rights reserved Case Study on Data Analytics on improved Schedule Data Quality Project Controls Expo – 16 th Nov 2016 Emirates Stadium, London Ritesh Yadav Associate Consultant - Projcon Group

Transcript of Case study on Data Analytics for Improved Schedule Quality

Copyright @ 2011. All rights reserved

Case Study on Data Analytics on improved Schedule Data Quality

Project Controls Expo – 16th Nov 2016Emirates Stadium, London

Ritesh YadavAssociate Consultant - Projcon Group

Copyright @ 2011. All rights reserved

ProjCon Group

Consulting

Offering innovation, advice, implementation, technical support inProject Controls.

Know more on http://projcon-group.com/

Project Controls Institute

Blended Learning Platform

Multi-accreditation system

Know more on http://www.projectcontrolsinstitute.com/

Copyright @ 2011. All rights reserved

About the Speaker

Ritesh Yadav Associate Consultant, Projcon Group.

Currently working for ProjCon Group; delivering & setting-up project controls processes and reporting framework for its clients.

Previously worked as a Sr. Planning Engineer in Dedicated Freight corridor CTP 1 & 2 Railway Project (1200 kms. Track laying) worth 1.2 Billion Dollar.

Holds Bachelors Degree in Civil Engineering; practicing application of Project Controls; expertise are in Earned Value Management, MI Reporting, Monitoring & Controls, and Schedule management.

Copyright @ 2011. All rights reserved

EVM Reporting

People Systems

Data Processes

Copyright @ 2011. All rights reserved

Data Cycle

Create

Schedule data

Progress data

Cost data

Evaluation

Evaluate and Assess the

Performance Parameters

Re-Baseline

Used to baseline other similar

projects

Lesson Learnt

Optimization

Location

Copyright @ 2011. All rights reserved

Data Cycle

Create

Schedule data

Progress data

Cost data

Evaluation

Evaluate and Assess the

Performance Parameters

Re-Baseline

Used to baseline other similar

projects

Lesson Learnt

Optimization

Location

What Happens if the Data

Quality is not up to the

mark?

Copyright @ 2011. All rights reserved

Effects of Poor Data Quality

Risk of Delays and Cost over-runincreases

Affects Progress Parameters (Reporting failure)

Reserve adequacy risk (Cash flow)

Material/Resource/Manpowerforecasting

Optimization failure

Difficulty to Baseline similar projects

Data driven decisions impacted

Image Source : Google

Copyright @ 2011. All rights reserved

EVM Reporting

Contractor

MSP/P6Client

MSP/P6

SAP/Oracle

Cobra/Equivalent

WBS Dictionary

CBS

Data

migration

Cost Booking System

Planning System

Cost & Forecast

Baseline

Progress

Baseline

Progress

Copyright @ 2011. All rights reserved

Contractor

MSP/P6Client

MSP/P6

SAP/Oracle

WBS Dictionary

CBS

Cost Booking

System

Planning System

Cost & Forecast

Baseline

Progress

Baseline

Progress

Data

migration

Not on sync

Change in WBS

Dictionary.

Baseline

Management

Progress

Rollback

Cost

Rollback

Planning/Physical progress

& Cost booking/forecast

not in sync

EVM Reporting – Data Quality Issues

Schedule

Quality

Cobra/Equivalent

Copyright @ 2011. All rights reserved

Data Quality Assessment

Schedule Data (Planned / Baseline data)

Schedule quality metrics (Schedule Auditor)

Baseline management

Reporting Challenges & Limitations

Cost booked in invalid CBS (WBS – CBS integration)

Change in WBS Dictionary

Systems/Software induced issues

Cost & Progress Data

Cost Rollback (negative cost booking)

Progress Rollback

Co-relation between Cost & Progress booked

Copyright @ 2011. All rights reserved

Schedule Auditor

Project ID

Schedule Quality Score Average 71% ######### ####

Data Date

Performance % Complete

Schedule % Complete

Total No of Activities

Activities Completed

Activity % Complete

1 0% PASS 0 of 58 1% PASS 1 of 71

2 5% FAIL 3 of 58 4% PASS 3 of 71

3 0% PASS 0 of 58 0% PASS 0 of 71

4 0% PASS 0 of 58 0% PASS 0 of 71

5 45% FAIL 26 of 58 37% FAIL 26 of 71

6 Activities with Negative Float 0% PASS 0 of 58 0% PASS 0 of 71

7 65% FAIL 32 of 49 71% FAIL 41 of 58

8 0% PASS 0 of 58 0% PASS 0 of 71

9 8% FAIL 4 of 49 7% FAIL 4 of 58

10 97% FAIL 56 of 58 94% FAIL 67 of 71

11 87% FAIL 13 of 15

12 0% PASS 0 of 58 0% PASS 0 of 71

Project Name

PROJECT SUMMARY

Project Dates

Type of Activities

BaselineForecast

Start

Finish

F/B Cost(M)

15%

17%

71

Task Dependent

Milestones

Level Of Effort

NosPercentage

Incomplete Activities All Activities

Percentage

13

18% WBS Summary

58

13

0

0

0

Resource Dependent

DASH BOARD

Baseline Execution Index (BEI)

Schedule Quality Checks

Activities with High Float

Activities with Long Duration

Activities with Invalid Date

Activities W/o Predecessor

Activities W/o Successor

Dangling Activities

Activities with Constraints

Activities without Baseline

Result

S.No

Nos

Activities without Resources

Activities with Missing Target

Process All

Copyright @ 2011. All rights reserved

Schedule Auditor

SCHEDULE QUALITY REPORT - INCOMPLETE ACTIVITIES

03

0 0

26

0

32

0

4

56

000

10

20

30

40

50

60

70

Activities W/oPredecessor

Activities W/oSuccessor

DanglingActivities

Activities withConstraints

Activities withHigh Float

Activities withNegative Float

Activities withLong Duration

Activities withInvalid Date

Activitieswithout

Resources

Activities withMissing Target

BaselineExecution Index

(BEI)

Activitieswithout

Baseline

SCHEDULE QUALITY CHART: INCOMPLETE ACTIVITIES

Copyright @ 2011. All rights reserved

Schedule Auditor

ANALYSIS OF ACTIVITIES WITH HIGH DURATION ,FLOAT, CONSTAINTS, INVALID DATES

12%

27%

61%

Activities with High Duration

Btn. 2M to 4M

Btn. 4M to 6M

More Than 6M

8%8%

84%

Activities With High Float

Btn. 2M to 4M

Btn. 4M to 6M

More Than 6M

Copyright @ 2011. All rights reserved

Change in Baseline Historical Cost Profile

Copyright @ 2011. All rights reserved

Change in Baseline Historical Cost Profile

Copyright @ 2011. All rights reserved

Data Collection

Data

Normalization

Reporting

Database

Change in Baseline Historical Cost Profile

Analyse

Copyright @ 2011. All rights reserved

Reporting Challenges & Limitations

Alignment between the Core systems(Planning & cost control)

Dates

Forecast(cost & resource)

WBS – CBS integration

Invalid codes present systems

Old WBS codes remaining in the system;

Change in WBS dictionary

Transfer of Cost & Budget.

Systems/Software induced issues

Resource loading activity Start & Finish

% complete out of range

Invalid dates

Incomplete data transfer

Copyright @ 2011. All rights reserved

Cost & Progress Related Data Quality Issues

Copyright @ 2011. All rights reserved

75%

-25%

Actual Cost

Positive

Negative

Cost Rollback

-40000000

-20000000

0

20000000

40000000

60000000

80000000

100000000

Positive

Negative

77%

23%

WBS - AC Count

Positive

Negative

Copyright @ 2011. All rights reserved

-20000000

0

20000000

40000000

60000000

80000000

100000000

Positive

Negative

Progress Rollback

88%

12%

WBS - EV Count

Positive

Negative

86%

-14%

Earned Value

Positive

Negative

Copyright @ 2011. All rights reserved

Earned Value vs Actual Cost

Monthly plot for 2

Financial years

Linear Correl index = 0.3

Copyright @ 2011. All rights reserved

Data Quality Assessment is an important aspect of progress reporting, it helpsin

understanding the reporting gaps

Cleaning the data & make it reliable

Identifies the degree of variance in progress parameters

Creates a dependable back-up data for business decisions

Effective data quality management should be considered a basic requirementfor modern-day project management.

Create business rules for sustainable data quality improvement

Quality of data is a risk and should be monitored with other project/portfoliorisks.

Conclusion

Copyright @ 2011. All rights reserved