Case Study - Injazat_Abu Dhabi - (Tier IV) - 20090325
Transcript of Case Study - Injazat_Abu Dhabi - (Tier IV) - 20090325
• Project Objective Deliver a TIER IV Compliant ‘Co-hosting Data Centre’ with a managed,
secure and environmentally controlled 2000m² Data Hall for hosting mission critical servers and other related IT equipment.
• Project Timescales - Design commenced October 2006 - Project commenced on-site May 2007 - Construction Completion May 2008 - Operational December 2008 • Operating Environment - Arid Desert - Remote Location - 46 Degree Ambient Temperature
Injazat Data Centre
• Construction - Two storey construction - Plant rooms at ground floor level
- Data Centre at first floor level - Physical separation of redundant power and cooling systems in
accordance with Tier IV
• Power Requirements - 6.6 MVA Building Load (5.4 MVA of Critical Load) - Utility power from 2 separate/redundant primary supplies (A & B) - Fully redundant power distribution systems - Simultaneous power from both distribution systems - Total system isolation until point of power delivery - Critical power equipment fully supported by DRUPS - Stand alone fuel capability for 72 hours operation
Injazat Data Centre
Injazat Data Centre
• Why Hitec Diesel Rotary UPS? The Hitec DRUPS provides the highest level of security to critical
services to maintain 99.995% Data Hall uptime regardless of utility service failure or maintenance activities.
Hitec’s tried and tested DRUPS equipment design is the most compact,
efficient and suitable for a Tier IV infrastructure that demands the highest possible level of Data Centre Resilience and Reliability.
• Injazat is the first facility of its type in the Middle East • Injazat is the first UTI certified Tier IV Data Centre
outside the USA
MV DRUPS
System ‘B’
MV DRUPS
System ‘A’
Non-Critical Load
Critical Cooling & Mech’ Load
Critical IT & Server Load
Low-Voltage
O/P Bus O/P Bus
ADWEA SUPPLY
A
ADWEA SUPPLY
B
Normal Operation (Mains Available)
Injazat Data Centre
Tier IV - 2 (N+1) Architecture
(Medium Voltage)
MV DRUPS
System ‘B’
MV DRUPS
System ‘A’
Non-Critical Load
Critical Cooling & Mech’ Load
Critical IT & Server Load
Low-Voltage
O/P Bus O/P Bus
ADWEA SUPPLY
A
ADWEA SUPPLY
B
Emergency Operation (Supply A Fails)
Injazat Data Centre
Tier IV - 2 (N+1) Architecture
(Medium Voltage)
MV DRUPS
System ‘B’
MV DRUPS
System ‘A’
Non-Critical Load
Critical Cooling & Mech’ Load
Critical IT & Server Load
Low-Voltage
O/P Bus O/P Bus
ADWEA SUPPLY
A
ADWEA SUPPLY
B
Injazat Data Centre
Tier IV - 2 (N+1) Architecture
(Medium Voltage)
Emergency Operation (Supply B Fails)
MV DRUPS
System ‘B’
MV DRUPS
System ‘A’
Non-Critical Load
Critical Cooling & Mech’ Load
Critical IT & Server Load
Low-Voltage
O/P Bus O/P Bus
ADWEA SUPPLY
A
ADWEA SUPPLY
B
Emergency Operation (Supply A and Supply B Fail)
Tier IV - 2 (N+1) Architecture
(Medium Voltage)
Injazat Data Centre
Essential Load
Critical Load
Essential Load
Critical Load
Essential Load
Critical Load
Mains Available
Supporting the Critical & Essential loads
Utility A
Utility B
TR1
TR3
TR2
High Voltage Network - Single System
Essential Load
Critical Load
Essential Load
Critical Load
Essential Load
Critical Load
Mains Failed
Utility A
Utility B
Supporting the Critical & Essential loads
TR1
TR3
TR2
High Voltage Network - Single System
Essential Load
Critical Load
Essential Load
Critical Load
Essential Load
Critical Load
Mains Failed + 8 Seconds
Utility A
Utility B
High Voltage Network - Single System
Supporting the Critical & Essential loads
TR1
TR3
TR2
Injazat Data Centre
Specialist Plant Handling • 150 Ton Mobile Crane • 8 No. 28,000 kg Lifts • ‘Zero Shock’ Requirement • Levelled Rails • Hydraulic Rams
• It is extremely RELIABLE
• It has a very HIGH operating EFFICIENCY
• It has a LOW LIFE COST
• It is a COMPACT & UNCOMPLICATED design
• provides ACTIVE POWER CONDITIONING
• It can support Leading pf and Motive Loads
• It is the GREENEST UPS solution
Why Hitec DRUPS?