Case Study-Al Bab-Tadef PS Perfromance Feasibilty

download Case Study-Al Bab-Tadef PS Perfromance Feasibilty

of 24

Transcript of Case Study-Al Bab-Tadef PS Perfromance Feasibilty

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    1/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    AL BAB TADEF IRRIGATION PROJECT

    Technical evaluation and Feasibility study of

    Pumping stations performance

    Study prepared by

    Ghassan Al Salem

    28/5/2011

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    2/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 2 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    INDEX

    1. General 3

    2. Description of the pumping plant 3

    2.1. Design Data 3

    3. Plant Operation evolution 4

    3.1. Historical sequence of problems 4

    3.2. Operation parameters 4

    3.3. Causes of Problems: 5

    4. Technical measures taken by the administration and its suitability 7

    4.1. Operating the plant in manual regime 7

    4.2. Casting pump foundation with concrete: 7

    4.3. Erecting a concrete slab extending over the suction openings (Beginning of 2009) 7

    4.4. Installation of air release valves at pump casing crown 7

    4.5. Repair of impellers 7

    4.6. Installation of weed screen at PS1 Inlet 8

    4.7. Installation of control system 8

    5. Extra implementation Costs in plants at actual operation regime 8

    5.1. Losses due to reduced efficiency after repair 8

    5.2. Losses caused by Partial valve closure 10

    6. Other technical remarks 12

    6.1. Discharge valves 12

    6.2. non return valve 13

    6.3. Pump packing 13

    7. technical Recommendations and proposals for improving performance 13

    7.1. immediate maintenace measures 13

    7.2. Measures during maintenance period 14

    7.3. Measures required for reducing energy loss 14

    8. Conclusions 23

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    3/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 3 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    TECHNICAL AND ECONOMICAL EVALUATION

    For the performance of the Pumping stations

    At Al Bab-Tadef Irrigation development project

    1. GENERALThe purpose of this report is the evaluation of the technical performance, feasibility of pumping

    process, determining the causes of problems occurred during start up and recommending

    optimum operation method

    Project Owner: Ministry of Irrigation, General Establishment for Land Development Function of the pumping plant: elevating water from Maskaneh west irrigation

    Channel to a number of elevated and ground tanks to provide for the irrigation of

    6700 ha in Al Bab Tadef area

    This study is based on the measurements made at the first and second pumpingstation and the results are generalized to the third PS

    2. DESCRIPTION OF THE PUMPING PLANTAccording to adopted design, the water is pumped using 3 pumping stations on different levels

    according to levels of irrigated areas using main pumps for providing the main flowrate and

    secondary pumps to supply partial demand required at each pumping level and according to

    served area.

    The pumps used are of the double suction type2.1. DESIGN DATADescription Unit PS1 PS2 PS3

    Group 1 Group 2Area served by the plant Ha 6700 5945 3061Design flow m3/s 5.17 3.8 0.71 2.31Total Static head< mWC 61.83 62.76 45.6 45.43Number of main pumps (Op-Std.by) No 4(3+1) 3(2+1) 3(2+1) 4(3+1)Number of secondary pumps No 2 2 I 2Main pump design flow m3/s 1.25-1.4 1.23-1.35 0.22-0.30 0.5-0.65Secondary pump design flow m3/s 0.62-0.7 0.61-0.7 I 0.25-0.32NPSHR at pump design flow mWC 8 8 8 8Min. Suction level mASL 366.19 419.24 419.24 471.57Max suction level mASL 367.17 421.24 421.24 473.57Min Discharge level mASL 425.6 479.7 Direct 515.00Max Discharge level mASL 428.02 482.00 Direct 517.00Pressure line length m 3509 3258 Direct 512.00Pressure line size mm 1x1400 1x1200 1x800 1x1000Table 1

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    4/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 4 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    3. PLANT OPERATION EVOLUTION3.1. HISTORICAL SEQUENCE OF PROBLEMSThe plant started operation by the local staff on 18/03/2007; the start up was accompanied by agroup of problems summarized as follows:

    Vortices in PS1 suction basins entrained Air in pumped water Vibration in Pumps One of pumps packing does not pass cooling water One of the non-return valves has a defected piston Cavitation and wear in pumps impellers (Figure 1- Cavitation in pump impeller)

    Figure 1- Cavitation in pump impeller

    Those phenomena have a very bad effect on pump performance as they cause wear in moving

    and fixed parts of the pump and reduce the plant efficiency in general due to the reduction in

    pumped water quantity against same consumed power

    Those problems or part thereof continued during the years 2008-2009 when the administration

    has applied some solutions to the problems, this shall be discussed in the following clause 5 in

    detail

    3.2. OPERATION PARAMETERSThe following operation parameters were collected during the site visit on 8/04/2011, in

    addition to some measurement which were carried out by the administration during thepreparation of this study; According to this data we indicate the following

    3.2.1. OPERATION POINTS AT SITE VISIT DATEDepth

    cm W.LMASL CurrentA PowerkW Flowm3/hr PressurebarPS1, 3 Pumps operating

    Pump1 293 366.25 117 1170 4200 8.2Pump2 293 366.25 117 1170 4200 8.2Pump3 293 366.25 117 1170 4200 8.2PS2, 2 main Pumps +1 sec.Main pump 250 419.48 122 1220 4350 8.4Secondary Pump 250 419.48 68 684 2300 8.4Table 2

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    5/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 5 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    3.2.2. OPERATION POINTS BEFORE AND AFTER REPAIRSPumps operated at the points shown in the following table before and after the repairs

    W. Depth Current Power Flow PressurePS2 cm A kW m3/hr barMain Pump before repair 250 N.A 1240 4300 8.4Main Pump after repair 250 N.A. 1200 4400 8.4Table 3

    3.2.3. PRESSURE UP AND DOWNSTREAM THE PUMPSThe Administration has provided us, thankfully, the pressure readings upstream and

    downstream the control valves according to number of operating pumps, this is shown in the

    following tableNo of operating pumps 1 2 3 4PS1 Pressure Upstream valve (bars) 8.17

    Pressure downstream valve (bars) 5.9 6.18 6.7 7.29PS2 Pressure Upstream valve (bars) 8.4

    Pressure downstream valve (bars) 6.0 6.8 8.0Table 4

    3.2.4. IRRIGATION PROGRAMMonth Mar Apr May June July Aug Sep Oct

    Pumped volume 1000m3 1,906 7,652.3 6,469.1 4,755.6 8,176 8,483 6,464 2,520Table 5

    3.3. CAUSES OF PROBLEMS:3.3.1. VORTICES AND ENTRAINED AIRThe design did not take into consideration the critical submersion depth (hc)

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    6/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 6 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    This value is not available according to suction conditions in the station, and which is calculated

    as shown in the following Table 8

    Description Symb Unit PS1 Reference

    Data InputNo of Operating Pumps n 1

    Flow rate Q m3/hr 4,200 Measured

    Water temp T C 20 Estimated

    Water specific weight at working Temp S.G kg/m3 998.000 Physical

    Gravity Acceleration g m/s2

    9.806 Physical

    Discharge pressure Pd Bar 8.20 Measured

    Gauge correction gc m 0.50 Measured

    Suction Pipe size Ds mm 1000 Drawings

    Discharge Pipe size Dd mm 800 Drawings

    Suction Pipe Length Ls m 20 Drawings

    Vapor pressure @ 20C Hvp m 0.24 Physical

    Atmospheric pressure @350 mASL Pa m 9.89 Physical

    Zero Reference level LVL0

    mASL 367.52 Drawings

    water depth from Tank bottom H1 m 2.93 Measured

    Suction pipe centerline depth H2 m 3.50 Drawings

    Suction opening radius Rs m 0.70 Drawings

    Discharge pipe depth from Ref. 0.00 H3 m 2.70 Drawings

    Impeller Eye depth below ref 0.00 H4 m 2.09 Drawings

    Friction Factor f 0.0104

    Suction local losses factor Ks 0.99 Chimbar

    Discharge local losses factor up to Gauge Kd 0.90 Bohl Pg 137-bild 4.71

    Efficiency to test curve @ head tpc % 88.49% Curve

    Net positive suction Head Required NPSHR mWC 5.28 Curve

    Measured Motor Power Pm kW 1,170 Measured

    Shaft Power to test curve Pact kW 1106.42 Curve

    Motor efficiency m % 94.1% Data

    Pressure @ collector Pd1 Bar 5.90 Measured

    Voltage U V 6000 Measured

    Current I A 117 Measured

    Cos phi Cos() 0.962 Measured

    Calculated power kW Pc kW 1170 Measured

    Table 6

    General calculations

    Tank Bottom level LVL1 mASL 363.32 LVL0-(H2+Rs)

    Water level in Basin LVL2 mASL 366.25 LVL1+H1

    Pump Discharge pipe Centerline level LVL3 mASL 364.82 LVL0-H3

    Impeller eye level LVL4 mASL 365.43 LVL0-H4

    Suction pipe Area As m2 0.79 Ds2./4

    Discharge pipe Area Ad m2 0.50 Dd2./4

    Table 7

    NPSHA Calculations

    Velocity in suction pipe Vs m/s 1.49 Q/As

    Suction Velocity head Hv mWC 0.113 Vs2/2g

    Available positive head Hz mWC 0.82 LVL2-LVL4

    Friction losses in pipe Hfs mWC 0.023 f x Ls / Ds x Hv

    Suction Local losses HLs mWC 0.111 Ks x Hv

    Suction total losses Hs mWC 0.135 Hfs + HLs

    Net positive suction Head Available NPSHA mWC 10.45 =Ha+Hz-Hs+Hv-Hvp

    NPSH difference mWC 5.18 NPSHA-NPSHR

    Table 8

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    7/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 7 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    It is known that the condition to operate the pump safely is to have an

    NPSHA>NPSHR+(0.51.5)m; the operation of the pump at the rate of 5900 m3/hr is a result of

    the hydraulic considerations in the design of the pumping station, this point will be discussed

    further in the following clause 7

    4. TECHNICAL MEASURES TAKEN BY THE ADMINISTRATION AND ITS SUITABILITY4.1. OPERATING THE PLANT IN MANUAL REGIMEBased on recommendations proposed to the administration, the pumps were operated by

    applying a manual control regime in the year 2008; this was achieved by sliding the operation

    point from the rightmost end of the curve which was causing cavitation, to another operation

    point by partially closing the discharge side valve thus creating an extra local loss in the valve and

    force the pump to operate at a point where there is no cavitation

    This measures is considered to be good solution to save the pumps, but this came at the account

    of the pumping economy as an unjustified extra cost of energy should be paid to overcome an

    artificial loss created to solve a mechanical problem resulting from design considerations.

    Clause 5 demonstrates the extra cost resulting from applying such a solution.

    In addition, the use of butterfly valve for flow control is an impractical application due to high

    potential of cavitation in the valve components as explained in clause 6-1 hereinafter.

    4.2. CASTING PUMP FOUNDATION WITH CONCRETE:The fixing of pump foundation by casting concrete is an excellent technical solution, this has

    resulted in increasing the structure inertia and stabilized the operation, especially that other

    reasons such as entrained air and cavitation were eliminated.

    Also this solution has resulted in maintaining the pump alignment during operation which will

    save the rotating parts of the pump (Sleeves, bearings, wear rings, etc)

    4.3. ERECTING A CONCRETE SLAB EXTENDING OVER THE SUCTION OPENINGS (BEGINNING OF 2009)This solution has reduced the flow velocity of the incoming water which resulted in increasing

    the pressure within its bulk and eliminating the vortices and entrained air

    4.4. INSTALLATION OF AIR RELEASE VALVES AT PUMP CASING CROWNAlso, this measures is a good solution to evacuate accumulated air which is produced naturally

    due to local circulation in suction pipes during pump operation, even after solving the Vortices

    problem in suction basin

    4.5. REPAIR OF IMPELLERSThe administration has repaired the impellers by coating with Belzona (Figure 2-Impeller after

    repair) in order to be able to operate the pumps and operate the plants

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    8/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 8 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    Figure 2-Impeller after repair

    There are few reservations on repairing the impellers of such size and importance resumed in

    the following This material is used to repair the roughened surfaces subject to cavitation and

    erosion for the purpose of increasing the smoothness of the surface.

    This material has good resistance in locations with slow flow velocity, but it was used

    to repair holes extending through the whole thickness of the impellers without any

    metallic material to hold it in place, this is an unconventional use of this material and

    there is a high potential for the collapse of such repair in the holes areas

    As shown in the repaired impeller picture, the vanes ends are not neat and have notbeen properly machined; this results in local vortices at entrance area especially that

    it is a high velocity area, and as Belzona has bad resistance to high velocities, this

    area is subject to accelerated wearing.

    It is not possible to restore the impeller to its initial dimensions and surface curvaturewhich will lead to a change in the pump performance.

    The change in pump efficiency after repair according to available data is shown inTable 1, the lost power calculations due to repairs are shown in the following Table 9,

    clause

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    9/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 9 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    Flowrate of 4200 m3/hr Pressure at pressure gauge installed downstream the discharge taper equals 8.2 bars Consumed motor power of 1170 kW Motor efficiency of 94.1% according to contractor guaranteed values

    The calculated efficiency and head of the pump at current operation setup are 86.14% and 83.06

    m respectively.

    Compared to curve values there is a loss of efficiency equal to 2.35% and in head equal to 2.78m

    according to the following Table 9

    Description Symb Unit PS1 Reference

    Generated head calculations

    Discharge measured Head Hdm mWC 83.61 Hd+GC

    Discharge Corrected Head Hdc mWC 84.11 Hdm O 10.196

    Velocity in Discharge pipe Vd m/s 2.32 Q/Ad

    Discharge Velocity head Hvd mWC 0.275 Vd2/2g

    Losses In discharge up to gauge location Hd mWC 0.247 KdxHvd

    difference between Pipe C/L and water Hps mWC -1.43 LVL3-LVL2

    Generated head Hp mWC 83.059 Hdc+Hps+Hs+Hd

    Power losses Due to repair

    Motor net output Pm_net kW 1101.0 P x Etm

    Pump Hydraulic power Phyd kW 948.3 Q x Hp x SGx g/3.6x106

    Power required (test curve efficiency) Ptc kW 1071.6 Phyd/Etpc

    Pump Calculated efficiency P 86.14% Phyd/Pmnet

    Pump head @ Q acc. To test curve Hpc mWC 85.75 From Curve

    Lost Head due to Impeller repair HL mWC 2.70 Hpc-Hp

    Lost Power /103m

    3@ Motor eff. 94.1% PL1000 kw/10

    3m

    39.0396 HL x SGx g/3.6x106/Etp/m

    Total Demand Volume V 103m

    3/yr 46,426 Data

    Total Irrigated area A Ar

    Ha 6,656 Data

    Irrigated Area by PS1 A1 Ha 755 Data

    Pumped volume from PS1/year V1 103m

    3/yr 46,426 Calculated

    Irrigated Area by PS2 A2 Ha 2,840 Data

    Pumped volume from PS2/year V2 103m

    3/yr 41,160 Calculated

    Irrigated Area by PS3 A3 Ha 3,061 Data

    Pumped volume from PS3/year V3 103m

    3/yr 21,351 Calculated

    Total lost Power/season in PS1 P1 k.W.h 419,673 PLxV1

    Table 9

    According to above calculations, the total lost energy in PS1 due to reduced efficiency after

    repairs is equal to

    419,673 M.W.hr in PS1

    The ratio of consumed energy in each plant to the total energy is estimated based on the

    following table:

    Description Unit PS1 PS2 PS3Total irrigated area by station Ha 6700 5945 3061Required head in station M 80.7 83.59 50.6Rate of consumed energy to total energy % 45.32 41.62 13.07Table 10

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    10/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 10 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    Considering that the changes in the three plants are similar, the total lost energy in the three

    plants due to reduced efficiency is equal to:

    926,081 K.W.hr in three plants during the irrigation season

    according to following table

    Description Symb Unit PS1 Reference

    Total lost Power/season in PS2 P2 k.W.h 375,590 PLxV2xH(PS2)/H(PS1)

    Total lost Power/season in PS3 P3 k.W.h 196,557 PLxV3xH(PS3)/H(PS1)

    Total Losses PL_Total k.W.h 991,821 P1+P2+P3

    Table 11

    Losses in PS1 are calculated based on current operation set point applied by administration; it

    may vary towards increase-decrease depending on the change in operation parameters

    5.2. LOSSES CAUSED BY PARTIAL VALVE CLOSUREPump operation points were selected based on the engineer and contractor calculations, the

    pumps were also supplied based on this basis, it was found out, according to current

    measurements, that the actual losses in the system are less than the calculated losses, the

    required pressure in the collector is 5.9 to 7.29 bars to pass a flowrate of 4200 to 16800 m3/hr in

    the main pressure pipe respectively. These measurements confirm the measurements made at

    the startup phase, which showed that the pump operated at 6.22 bars at startup which resulted

    in operating the pump at the end of the curve (even outside the curve) when one pump was

    operating; This caused NPSHR to exceed NPSHA by approximately 1.75m as mentioned in clause

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    11/24

    L BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    age 11 of 24 CASE STUDY-AL BAB-TADEF PS P ERFROMANCE FEASIBILTY.DOCX

    Figure 3 - Pump operation curves

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    30

    35

    40

    45

    50

    55

    60

    65

    70

    75

    80

    85

    90

    95

    100

    105

    110

    115

    120

    1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 5,000 5,500 6,000 6,500 7,000

    Efficiency%

    NPSHRx10mWC

    HmWC

    Q m3/hr

    Pump Operation Curves

    Suggested Operation Point

    Q=5363 m3/hr

    H=71.15mNPSHR=8.44m

    Operation Point at startupQ=6070 m3/hr

    H=59.5 m

    NPSHR=12m

    Actual Operation Point

    Q=4200 m3/hr

    H=83.06 m

    NPSHR=5.28m

    NPSHR=8.44m

    H=71.15m

    Saved Head 11.91m

    Flowrate = 5363 m3/hr

    Efficiency 87.49

    =88.49%

    Q=5363m

    3/hr

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    12/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 12 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    6. OTHER TECHNICAL REMARKS6.1. DISCHARGE VALVESThe use of a butterfly valve as a control valve is not recommended as the partial closure shallforce the flow to pass through a small cross section, thus increasing the flow velocity; this in

    turn, shall result in a pressure drop on the downstream face of the disk causing:

    Cavitation on the downstream face of the valve disk Excess torsion on the valve shaft causing wear of the gear box

    Figure 4

    For those reasons, it is not recommended to use this type of valve for control

    The following Figure 5 shows the opening ratio (23%)at a flowrate of 4200 m3/hr under a

    deferential pressure of 22.4 m

    According to Figure 6 It is clear that the valve will be subject to wear due to cavitation

    Fowra

    tem3

    r

    Opening %

    Opening degree @

    4200 m3/hr flow

    and P=22.4 m

    Cavitation areas

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    13/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 13 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    Figure 5

    Figure 6

    Remark: the area where the cavitation no. in the valve (Red curve) is greater than the audible,

    visible and full cavitation lines is considered as cavitation area. At an opening degree of 23% all

    cavitation lines are below the red line, which means audible, visible and full cavitation will occur.

    6.2. NON RETURN VALVEHydraulic piston of one or more non-return valves required repair and calibration, it is very

    important to calibrate the NRVs pistons to facilitate the self-opening of the valve. This should be

    calibrated according to manufacturers recommendations by modifying the location of the

    counterweight and the piston throttling valve.

    6.3. PUMP PACKINGOne of the pump packing is not passing cooling water, this will cause overheating of bearing

    areas.

    This should be repaired to guarantee proper cooling of the bearing area

    7. TECHNICAL RECOMMENDATIONS AND PROPOSALS FOR IMPROVING PERFORMANCE7.1. IMMEDIATE MAINTENACE MEASURES

    Cavitation no.@ 23% opening

    CavitationNumber

    Opening %

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    14/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 14 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    Calibrate NRVs on pump discharge pipe (Counter weight and hydraulic piston Repair of packing of pump in PS1

    7.2. MEASURES DURING MAINTENANCE PERIOD Check the control valve for cavitation evidence on valve disk and body Check repaired pumps impellers and durability of Belzona Installation of the following instruments if not available Accurate pressure gauges in the following locations Directly at the centerline of the pump suction flange Directly at the centerline of the pump discharge flange at the centerline of the main pressure pipe Level measurement in suction and discharge basins

    The purpose of those measurements is to evaluate the performance of the pumps and

    calculating the actual losses in system accurately according to flowrate

    7.3. MEASURES REQUIRED FOR REDUCING ENERGY LOSSBefore making future decisions to be applied to improve the plant performance, measurements

    of different operation parameters should be carried out during at least one irrigation season,

    readings should be made at every change, start and stop of all pumps including direct irrigation

    pumps

    The records should be made for the following parameters:

    Tag of each operating pump Pressure at pump discharge flange Pressure at pump suction flange Pressure at the beginning of the main pressure pipeline Variation in water level at suction basin Variation in water level at discharge basin (the levels of PS2 suction basin should be

    transmitted to PS1 and in PS3 to PS2)

    Power withdrawn from the motor Enhanced Power factor Withdrawn current Actual voltage

    7.3.1. IMPROVING EFFICIENCYIt is recommended to replace the impellers by new impellers of the same material, as the change

    to a higher grade will not contribute to eliminating the cavitation and this phenomenon should

    be eliminated by applying different approach.

    Due to the great effect of the efficiency on pumping cost, especially in a plant of this size, it is

    advised to replace the impellers by original impellers made by the manufacturer in order to

    guarantee the efficiency and to warrant the performance of the pump unless there is another

    supplier who can guarantee the test curve efficiency as minimum and guarantee the

    performance of the pump.

    7.3.2. REDUCING LOCAL LOSSES IN DISCHARGE VALVEA program was developed to calculate the consumed energy required during the irrigation

    season, the following figure shows the user interface of the program

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    15/24

    L BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    age 15 of 24 CASE STUDY-AL BAB-TADEF PS P ERFROMANCE FEASIBILTY.DOCX

    Motor Power kW m3/hr

    Total Consumed Power kW

    2 Lost Power/Pump kW m3/hr

    5 Total Lost power kW m3/hr (24 hrs operation)

    % lost power

    31 Net kW/m3 Level mASL

    Daily Op. hrs 744 Motor efficiency P mWC

    D1/D or N1/N Pg m Gauge correction m

    D Pg Bar P @ Collector mWC

    Gauge correction m P @ Collector Bar H

    Level Min. Hs Hst

    NPSHA-NPSHR Level f

    m3/hr

    f mm 3

    Ds NPSHA mWC m 4

    L= [m] NPSHR mWC 5

    = mm Vs m/s Hpump Curve mWC Dd mm 6

    = m/s

    2

    Kfs pump curve Vd m/s m/s 7

    Ks Kd mWC 8

    Hs mWC QPump m3/hr Hd mWC mWC 9

    Trim Ns 10

    62.95

    V pipe 1.940.21

    1400

    98.74%

    0.8704

    0.8754

    0.8866

    0.8932

    0.8704

    0.8704

    0.8704

    0.8704

    2.96

    421.24

    19.46

    Op. hrs

    94.1%

    May Qmin

    7.85

    603 0.231

    54.99

    8.44

    800.00

    Month All 274.96

    Volume 6,469,100 11.1%

    6.97 63.41

    0.50 6.22 56.42

    71.61 1.00

    0.0111

    27.89

    L pipe 3509

    K pipe 3.496

    10725

    5.99

    0.220 5363

    49.40

    5363

    1.75 Total Head

    0.99 3.90 H pipe

    D pipe

    1000

    Variable NRPM 988.00

    2.00 364.82

    2.00

    QBEP

    100.00%

    88.49%

    10.44

    70.80

    790.00

    0.0104

    4347.51

    Kf pipe

    Q pipe

    4750.00

    1,239.52 Recomm end ed flow 53 63

    2,479.05 1,495,304

    137.48

    PS1 Operation System

    366.25

    4.60E-02

    1.00E-06

    1.90

    20.00

    No of Operating pumps

    Start

    Figure 7

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    16/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 16 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    The total consumed energy required for PS1 during the irrigation season when pump operates at

    current designated flow rate of 4200 m3/hr and at calculated efficiency is shown in the following

    Table 12

    Q Pump 4200 m3/hr - N=988 rpm (Reduced=781.73 mm)

    1xPumps 2xPumps 3xPumps All pumps

    Month

    Mar 530,741 530,741 530,741

    Apr 2,130,845

    May 1,801,373

    Jun 1,324,235 1,324,235

    Jul 2,276,673

    Aug 2,362,160

    Sep 1,799,953

    Oct 701,714 701,714 701,714

    Total 12,927,696

    Total losses under current operation conditions 991,821

    Table 12

    The above table is shown in graphical form in the following Chart

    Chart 1

    It is proposed to use one of the following methods to reduce losses in valves:

    7.3.2.1. CHANGE OF PUMP OPERATION POINTThe purpose of the pumping process is to supply the maximum volume of water with minimum

    required head, this implies that minimizing the required head and increasing the flowrate is the

    right approach to reach an economical cost of pumping, at the same time, consideration should

    be made not to operate the pump in under cavitation conditions

    This can be achieved by shifting the operation point to the right side of the curve.

    Two operation pints were investigated

    531 7

    02

    531

    1,324

    702

    531

    2,131

    1,801

    1,324

    2,277

    2,362

    1,800

    702

    12,927.70

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    14,000

    -

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    Mar Apr May Jun Jul Aug Sep Oct Total

    PumpingEnergyin1000kW

    MonthlyPumpingEnergyK.W.hr

    Month

    1xPumps 2xPumps 3xPumps All pumps

    991,821Energy Lost in 3 plants kW.hr

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    17/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 17 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    a. Operating the pump at best efficiency pointOperation at BEP Q =4750 m3/s

    1xPumps 2xPumps 3xPumps All Pumps

    Month

    Mar 491,181 491,181 491,181

    Apr 1,972,015

    May 1,667,102 1,667,102

    Jun 1,225,529 1,225,529

    Jul 2,106,974

    Aug 2,186,088

    Sep 1,665,788 1,665,788

    Oct 649,410 649,410 649,410

    Total 11,964,086

    Saved energy in PS1 963,610

    Total Annual Saved energy in 3 Plants kW.hr 2,277,316

    Total Annual Savings in Syrian Pounds (3.00 SP / kW.hr) 6,831,948

    Table 13

    The total consumed energy required for PS1 during the irrigation season when pump operates atBest efficiency point is shown in the following Chart 2

    Chart 2b. operating the pump at maximum possible flowrateThe other possibility is to operate the pump at the maximum possible flowrate by shifting the

    operation point to the leftmost side of the curve without causing cavitation by opening the valve

    to the maximum possible opening

    it is advisable to operate the pump at a point where the NPSHA NPSHR 2m, this will

    guarantee sufficient positive pressure without cavitation

    According to Figure 3 - Pump operation curves, to achieve a suction pressure of +2 m, the pump

    should operate at a flowrate of 5363 m3/hr, where NPSHR is 8.44m and NPSHA is 10.44 m, the

    pump head in this case is 71.15 m

    491 6

    49

    491

    1,667

    1,2

    26

    1,666

    649

    491

    1,972

    1,667

    1,2

    26

    2,107

    2,186

    1,666

    649

    11,964.0

    9

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    14,000

    -

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    Mar Apr May Jun Jul Aug Sep Oct Total

    PumpingEnergy

    in1000kW

    MonthlyPum

    pingEnergy

    Month

    1xPumps 2xPumps 3xPumps All Pumps

    2,277,316Energy Saving in 3 plants kW.hr

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    18/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 18 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    This can be realized by changing the pressure set point at the discharge valve to a value of 6.84

    bars

    In all cases, the performance of the pump should be closely monitored during valve opening for

    vibration and cavitation.

    As a better Measures, and in order to guarantee the pressure in the suction pipe

    above the 2 m set point, it is recommended to control the discharge valve using a

    pressure sensor with a range from -5 to +5 m, installed at the suction side and the

    valve shall continue to open until the suction pressure is in the range of 2 m., by this

    we guarantee the maximum flowrate without cavitation

    As mentioned above, it is always necessary to monitor the pump operation during the first

    calibration

    Calculation of energy saving when operating the pump at 5636 m3/hr

    Q Pump 5363 m3/hr Impeller Dia=790@N=988 rpm

    1xPumps 2xPumps 3xPumps All pumps

    Month

    Mar 440,563 440,563 440,563

    Apr 1,768,795 1,768,795

    May 1,495,304 1,495,304

    Jun 1,099,236 1,099,236

    Jul 1,889,846

    Aug 1,960,808

    Sep 1,494,125 1,494,125

    Oct 582,487 582,487 582,487

    Total 10,731,165

    Saved energy in PS1 2,196,531

    Total Annual Saved energy in 3 Plants kW.hr 5,191,098

    Total Annual Savings in Syrian Pounds (3.00 SP / kW.hr) 15,573,295

    Table 14

    The total consumed energy required for PS1 during the irrigation season when pump operates at

    5363 m3/hr is shown in the following Chart 3

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    19/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 19 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    Chart 3

    7.3.2.2. CHANGE OF IMPELLER DIAMETERIf sufficient measurements were made according to requirement of clause

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    20/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 20 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    It is worthy to indicate that the pump operation curves with the new impeller size should be

    obtained by the manufacturer to carry out an exact calculation of consumed energy

    Also, the above table clearly indicate that operating less number of pumps for longer periods of

    time is more feasible than operating many pumps for shorter time despite of the losses in valves

    due to valve closure to avoid cavitation, so it is advisable to operate the minimum number ofpumps for longer periods

    In all cases, the number of required pumps is related to many factors, such as water demand,

    reservoir volumes power availability, water levels in suction and discharge tanks

    The above table is shown in graphical form in the following

    Chart 47.3.2.3. CHANGING PUMPING SPEEDOne of the proposed technical solutions to reduce losses in valves, is to reduce pump rotating

    speed to cope with required head

    The effect of changing pump speed is hydraulically similar to changing impeller diameter except

    that it has the following advantages

    Maintaining the impeller diameter to produce any extra required head if necessary(Better maneuverability)

    Maintaining the efficiency at its optimal values as the change in diameter will reducethe efficiency due to local circulation caused by reduced diameter, and because the

    losses inside the pump are inversely proportional to rotation speed

    The pump speed can be change by changing the electrical frequency using Variable frequency

    drives (VFD)

    The minimum rotation speed, which gives the least cost of pumping, was estimated to be theequivalent to the minimum impeller trim on the pump commercial curve, i.e. by reducing the

    speed by approximately 13%

    367

    486

    389

    1,322

    972

    1,321

    515

    418

    1,677

    1,418

    1,042

    1,792

    1,85

    9

    1,417

    552

    9,795.06

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    -

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    Mar Apr May Jun Jul Aug Sep Oct Total

    PumpingEnergyin1000kW

    PumpingEnergyK.W.hr

    Month

    1xPumps 2xPumps 3xPumps All pumps

    7,403,403Energy Saving in 3 plants kW.hr

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    21/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 21 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    The total consumed energy required for PS1 during the irrigation season when pump operates at

    860 rpm speed is shown in the following Table 16

    The decision to install VFDs should be made taking into consideration the following factors:

    Pump operation characteristics at 860 rpm (Q, H, , NPSHR) which should be suppliedby the manufacturer

    Ability of the existing motor to run at 860 rpm without considerable reduction inefficiency

    The initial and O&M cost and Power loss of the VFD Saved energy during the lifetime of the plant

    Impeller D=790, N=860 rpm

    1xPumps 2xPumps 3xPumps All Pumps

    Mont

    h

    Mar 355,475 370,311 390,253

    Apr 1,566,805

    May 1,324,545

    Jun 923,952 973,707Jul 1,674,032

    Aug 1,736,891

    Sep 1,323,501

    Oct 469,987 489,603 515,969

    Total 9,375,188

    Saved energy in PS1 3,552,508

    Total Annual Saved energy in 3 Plants kW.hr 8,395,702

    Total Annual Savings in Syrian Pounds (3.00 SP / kW.hr) 25,187,105

    Table 16

    Cost of lost energy was calculated based on energy unit price of 3.00 SYP/k.W.hr

    The relatively high savings in energy is a result of two reasons1- Increasing the useful energy by increasing the flowrate and reducing the head, either by

    reducing the impeller size or pump speed accompanied by shifting the operation point to

    a higher efficiency point. Which is the main factor in increasing pumping economy

    2- The increase of efficiency after replacing the impellers with original impellersTable 16 is shown in graphical form in the following Chart 5

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    22/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 22 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    Chart 5

    355 4

    70

    370

    924

    490

    390

    1,567

    1,325

    974

    1,674

    1,737

    1,324

    516

    9,375.19

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    10,000

    -

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    Mar Apr May Jun Jul Aug Sep Oct Total

    PumpingEnergyin1000kW

    MonthlyPumpingEnergyK.W

    .hr

    Month

    1xPumps 2xPumps 3xPumps All Pumps

    8,395,702Energy Saving in 3 plants kW.hr

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    23/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    Page 23 of 24 CASE STUDY-AL BAB-TADEF PS PERFROMANCE FEASIBILTY.DOCX

    8. CONCLUSIONSFrom discussion and calculations shown in this report, one can conclude the following

    There are some design and execution blunders, which caused operational problemssome of those problems are corrected by the administration in a good way

    There are still minor repair works which needs to be tackled There are major energy losses estimated at 8400 M.W.hr annually caused by 2

    reasons

    The method of impellers repairs which resulted in efficiency loss The difference between the actual operation conditions and the design

    considerations, forced the administration to operate the pumps at non economical

    operation points to avoid deterioration of pumps due to cavitation

    A considerable amount of energy can be saved by applying one or more of the following

    solutions

    I. It is important to change the impellers by new impellers from the manufacturer with thesame material, but the decision of changing the impeller diameter should be made in

    light of operation parameters

    II. Modify the operation points as detailed in

  • 7/27/2019 Case Study-Al Bab-Tadef PS Perfromance Feasibilty

    24/24

    AL BAB TADEF IRRIGATION PROJECT Technical evaluation and Feasibility studyof Pumping stations performance

    V. All measurements of operation parameters and required instruments mentioned inclause