Case Study: ACORD led ARC consortium project in South Sudan

14
www.acordinternational.org Defending rights. Promoting justice. Case Study: ACORD- led consortium project for Addressing Root Causes of violent conflict, instability and irregular migration in South Sudan 12 October 2016 Fairview Hotel, Nairobi 1

Transcript of Case Study: ACORD led ARC consortium project in South Sudan

Page 1: Case Study: ACORD led ARC consortium project in South Sudan

www.acordinternational.org

Defending rights. Promoting justice.

Case Study: ACORD-led consortium project for Addressing Root Causes of violent conflict, instability and irregular migration in South Sudan

12 October 2016Fairview Hotel, Nairobi

1

Page 2: Case Study: ACORD led ARC consortium project in South Sudan

Brief on South Sudan country context• South Sudan remains a fragile country • Hope for a peaceful South Sudan rekindle in May 2016• July 8 incidence brought the country back into conflict• Intermittent fighting spread to Equatoria region that was not

previously battle ground• Most traders from the neighbouring countries left the

country-due to insecurity/inflation• Goods and commodities that are not produced locally have

become scarce and very expensive• Attacks along the roads to and out of Juba have become

common alongside increased criminality in the country• Food insecurity is likely to worsen as harvest was affected by

July 2016 violent eruption in Juba but also uncontrolled cattle grazing by pastoralists communities on farm lands.

2

Page 3: Case Study: ACORD led ARC consortium project in South Sudan

ACORD in South Sudan •One of the earliest ACORD country programmes

•Interventions thematically aligned; livelihoods and food security, peace building and conflict transformation, gender and right to health•Currently implement programmes/projects in the greater Equatoria region•ACORD’s operational areas had been relatively peaceful prior to July, 2016 incidence•Some localized insecurity incidences have been reported in some places where ACORD works but relates more to survival or alternative livelihoods.•Country operation has reduced due to insecurity and funding-resource mobilization ongoing with most recent-Addressing Root Causes (ARC) funding from the Dutch government.

3

Page 4: Case Study: ACORD led ARC consortium project in South Sudan

ARC Funding-Case Study•ACORD is the lead applicant; Dan Church Aid, and Centre for Conflict Resolution based in South Africa are co-applicants•ACORD leading consortium was inspired in part; by experience with Oxfam/Novib in June 2015 and comparative advantage in implementing more Dutch programmes•ACORD had worked with DCA prior to ARC application as DCA grant recipient in South Sudan-limited direct work with CCR•Consortium members- different levels in terms of in country operational capacity and resource flow-CCR, no office in SSU•No major challenge so far registered in the partnership-issues have been resolved through consensus

4

Page 5: Case Study: ACORD led ARC consortium project in South Sudan

ARC application process

• Call for application accessed in January 2016 and mobilization started

• Consortium formation negotiated and formalized• Very high level of team work exhibited between ACORD

Secretariat and South Sudan Country Programme and between ACORD and consortium members

• Application submitted in early March 2016• Application feedback-ACORD consortium selected with

CARE consortium as best applicants from South Sudan• Final part of the application process being concluded with

submission of final draft document by 20-21/10/2016• Final feedback from Dutch ministry of foreign affairs

expected by 02/12/2016

5

Page 6: Case Study: ACORD led ARC consortium project in South Sudan

About the programme• The overall purpose of ARC fund is to address the political and socio-

economic root causes of armed conflict and instability in South Sudan

• Geographical areas of focus: Central Equatoria State (CES), Eastern Equatoria State (EES) and Jonglei State

• Root causes and instability in the geographical areas of focus: 1. Food insecurity and limited livelihood diversification strategies2. Disengagement of youth3. Tensions and mistrust4. Lack of effective conflict resolution mechanisms • Root causes and instability to be addressed through:

Outcome 1: Resilient livelihoods and food securityOutcome 2: Social CohesionOutcome 3: Peaceful conflict resolution

6

Page 7: Case Study: ACORD led ARC consortium project in South Sudan

Monitoring, evaluation, accountability and learning to be realised though:

• Tracking outcomes and impact of interventions, and adjust programming accordingly

• Increasing knowledge of conflict drivers and multiple layers of conflict through research studies

• Implementing flexible and adaptive programming

7

Page 8: Case Study: ACORD led ARC consortium project in South Sudan

ARC funding and linkages to ACORD’s overall strategic objectives• ARC funding is consistent with ACORD South Sudan livelihoods

and food security, and peace building and conflict transformation thematic focus

• ARC is also consistent with the global ACORD strategic priorities

8

Page 9: Case Study: ACORD led ARC consortium project in South Sudan

Addressing Root Causes of violent conflict, instability and irregular migration• Euro 125 million from 2016-2021• Dutch policy goals on security & rule of law• Country-specific goals in one of 12 eligible countries

(Afghanistan, Pakistan, Jordan, Lebanon, Syria, Ethiopia, Somalia, Sudan, South Sudan, Mali, Burundi, DRC)– To select max 36 applications (and minimum 12)– Results matrix developed collaboratively with partners in the

knowledge platform under previous reconstruction tender– Single country proposals only. Multi-country not allowed.– Consortiums encouraged and any organisation could only be

in one application per country –to enclose signed MOU

9

Page 10: Case Study: ACORD led ARC consortium project in South Sudan

Appraisal procedure

• 124 applications, 77 assessed having passed the threshold check– checking the lead applicant and co-applicants (legal

compliance, income from NL, capacity assessment, office in country, min. 3 years experience last five years with budget +Euro 0.5mill)

– checking eligibility of the proposal (duration, budget, policy goals, country)

• 21 projects selected from 15 lead organisations for partnerships with the Minister

10

Page 11: Case Study: ACORD led ARC consortium project in South Sudan

Application: Track record

• Track Record in the form of two cases, experience in target country on the policy goals last 5 years– Reconstruction tender case mandatory to use– Allowed to use one case from a co-applicant– To be supported by external evaluation

• Assessed on duration and intensity of experience, context and relevance, effectiveness, sustainability, involvement of partner organisations and target groups, M&E, complementarity and added value, gender and conflict sensitivity

11

Page 12: Case Study: ACORD led ARC consortium project in South Sudan

Application: Concept note

Rated on:•Context analysis and actor mapping•Theory of change•Added value•Conflict sensitivity•Grant amount (min. and max. budget)

12

Page 13: Case Study: ACORD led ARC consortium project in South Sudan

Proposal development process – lessons learnt• Decide what to target: country and policy goal• Constitute consortiums: reach out• Sign teaming agreement• Skype meetings to get organised• Set up a working team with clear roles and

responsibilities• Enriching team work between country office and

Secretariat and with co-applicants• Rigorous review process against criteria

13

Page 14: Case Study: ACORD led ARC consortium project in South Sudan

Time frame• mid-January: Call launched and consortium constituted• Feb: proposal development• 4 March: proposal submission• 19 May: decision• 20 June: global kick-off meeting in the Hague on Refugee Day• 9-12 August: country kick-off meetings with consortium partners

and Dutch Embassy• 16 Sept: preliminary programme submission incl. draft tripartite

MOU• 21 Oct: final draft programme submission• October: validation workshop• December: award decision• March 17: inception phase ends

14