Case Studies Handouts
-
Upload
fathy-shokry -
Category
Documents
-
view
227 -
download
0
Transcript of Case Studies Handouts
-
8/3/2019 Case Studies Handouts
1/28
Hazardous and Safety Engineering GPE 412
Case Studies 1
Case Studies
Explosions and Fires in Chemical and
Petrochemical Plants
Contents
1. Bhopal Disaster (Sherif Murad)
2. Buncefield Fire (Ahmed Habib- Mohamed El Nahas)
3. Flixborough Explosion(Mohamed Awad - Mina Zarif)
4. Guadalajara disaster (Amr Elbadry- Khaled Habib)
5. Phillips Petroleum Chemical Plant Explosion and Fire (A.Hamdy)
6. Piper Alpha Explosion (A.El-shora- M.Sherif- A.FoadA.Thabet )
7. T2 laboratory Inc. Runaway Explosion (A.Shamaa- A.Harraz)
8. Chemical Explosion in Toulouse (Omar zanana- Hazem Essam)
9. Valero Propane Fire (Mina George- Josephine Ezzat)
10. Waste Fuel Oxidizer (Ehab Gamal- Mahmoud Abdel-Fatah)
-
8/3/2019 Case Studies Handouts
2/28
Hazardous and Safety Engineering GPE 412
Case Studies 2
1.Bhopal Disaster During the night of December 23, 1984, large
amounts of water entered tank 610,
containing 42 tonnes of methyl isocyanate.
The resulting exothermic reaction increased
the temperature inside the tank to over 200 C
(392 F), raising the pressure to a level the
tank was not designed to withstand The
reaction sped up because of the presence of
iron in corroding non-stainless steel pipelines.
Factors leading to this huge gas leak include:
1-The use of hazardous chemicals (MIC) instead ofless dangerous ones
2-Failure of several safety systems (due to poormaintenance and regulations).
3-Safety systems being switched off to save money.The flare tower and the vent gas scrubber hadbeen out of service for 5 months before thedisaster.
4-Possible corroding material in pipelines.
-
8/3/2019 Case Studies Handouts
3/28
Hazardous and Safety Engineering GPE 412
Case Studies 3
Handling of the disaster
Police are alerted. Residents of the area evacuate.
Isolation of the explosion took place but however
this was not efficient because it was so large.
Getting all the workers out and sending the
impaired ones to hospital . The first people
reached Hamidia hospital. Symptoms include
visual impairment and blindness, respiratory
difficulties, frothing at the mouth, and vomiting.
Precaution
Four manual back up system must beimplemented in all factories dealing with toxic
substance. The prevention of using corroding materials
must be diminished in pipe lines.
High maintenance and regulations arerequired for safety systems.
The prevention of using corroding materialsmust be diminished in pipe lines
-
8/3/2019 Case Studies Handouts
4/28
Hazardous and Safety Engineering GPE 412
Case Studies 4
After treatment
Within weeks, the State Government establisheda number of hospitals, clinics and mobile units inthe gas-affected area.
When the factory was closed in 19851986,pipes, drums and tanks were cleaned and sold
The area around the plant was used as a dumping
area for hazardous chemicals. In order to provide safe drinking water to the
population around the UCC factory, there is ascheme for improvement of water supply.
Company Overview
The terminal was the fifth largest oil-products storage depot in the
United Kingdom.
Capacity of about 60,000,000 imperial gallons (272,765,400 l) of
fuel.
The terminal is owned by TOTAL UK Limited (60%) and Texaco 40%.
The HOSL is a major hub on the UK's oil pipeline network (UKOP)
with pipelines to Humberside and Merseyside .
2.Buncefield Fire
-
8/3/2019 Case Studies Handouts
5/28
Hazardous and Safety Engineering GPE 412
Case Studies 5
Accident & Explosion Overview
Date : December 11th , 2005
Time : 06:01 UTC
Location : Hemel Hempstead,
Hertfordshire, England.
Casualties : 43 injuries & 2 serious injuries
In the early hours of Sunday 11th December 2005, there were a number of
explosions heard at the Buncefield Storage Depot.
The first and largest explosion occurred at 06:01 UTC near container
912. Further explosions followed which eventually overwhelmed 20 large
storage tanks.
Causes
Unleaded motor fuel was being pumped into storage tank 912, in the north west
corner of the site.
Safeguards on the tank failed and none of the staff on duty realized its capacity
had been reached.
An automatic high level safety switch should trigger an alarm if the tank reaches
its maximum capacity.
Automatic shutdown did not happen and when fuel continued to be pumped in,
it overflowed through roof vents.
The overflow from the tank led to the rapid formation of a rich fuel and air vapor
-
8/3/2019 Case Studies Handouts
6/28
Hazardous and Safety Engineering GPE 412
Case Studies 6
How fire was spread
Fuel cascaded down the tank and formed a rich fuel/air mix, which
collected in the area surrounding the tank bounded by a low wall
designed to prevent leaked liquid spreading.
Between 5.45 am and 6 am the rate at which fuel was being pumped
into tank 912 gradually increased from 550 cubic meters (1,805 cubic
feet) an hour to around 890 cubic meters (2,920 cubic feet) an hour
At 6.15 am, with the vapor cloud cloaked over a large area and reaching
buildings next to the site, the first explosion occurred.
Fire Handling Artificial pool with water pumped from nearby lake used to create foam and
water mix.
Fire engines, foam cannon and fixed fire-fighting units already at depot used to
pump mixture onto blaze.
Fire brigade water curtain protected intact tanks on eastern part of site.
The bunds around each tank fail to contain all the contaminated liquid run-off - a
mix of firefighting water and escaped fuel.
Investigations find "large amounts" of run-off escaped from the site,
contaminating ground and surface water.
-
8/3/2019 Case Studies Handouts
7/28
Hazardous and Safety Engineering GPE 412
Case Studies 7
Recommendations
Tank operating practices, staffing levels and systems, must provide effective
safety margins to prevent a release.
Joints in bunds must be capable of resisting fire. Existing bunds should be
modified to meet this requirement.
Tertiary containment measures must be capable of preventing the
uncontrolled escape of firewater and other products to the environment.
Effective shift/crew handover communication arrangements must be in place
to ensure the safe continuation of operations.
Event The Flixborough disaster was an explosion at a chemical plant
used for production of Nylon on 1st June 1974.
It killed 28 people and seriously injured 26. 8 of the Dead
Bodies were never Found
A temporary by-pass pipe Jack-knifed and failed under
thermal expansion stress.
Due to Failure,40 of 120 ton of cyclohexane(raw material)
escaped from the reactors forming a vapor cloud.
Within two minutes, the vapor cloud ignited and Vapor Cloud
Explosion (VCE) took place (35 tons TNT equiv).
3.Flixborough
-
8/3/2019 Case Studies Handouts
8/28
Hazardous and Safety Engineering GPE 412
Case Studies 8
causes Two months before the incident, R-5 was found to be leaking. A 6
ft. long crack had developed
A water stream was directed to the crack to cool and quench the
small cyclohexane leak. The cooling water contained nitrates which encourage stress
corrosion of certain carbon steels.
The Reactor was Removed for Maintenance & To Keep The Process
Operating, a Dog-leg bypass Pipe Was Used
Thy bypass Pipe was Poorly designed and it Caused The Leakage
that led to Explosion
-
8/3/2019 Case Studies Handouts
9/28
Hazardous and Safety Engineering GPE 412
Case Studies 9
Handling Controlling (¬ Extinguishing) fire lasted 3 days and 250 firemen
were employed at the height of operations on the1st of June.
The last fires in some storage vessels were allowed to burn under
controlled conditions and were extinguished on the 13th of June
Plant was declared safe 13 days after the accident and it was a
mound of ash and fused metal (i.e Totally destroyed)
.
After Explosion
-
8/3/2019 Case Studies Handouts
10/28
Hazardous and Safety Engineering GPE 412
Case Studies 10
Future prevention1. The storage of hazardous material to be kept to aminimum
2. Better Plant Layout(To avoid the domino effect)
3. Ensure they employment of qualified and experienced
staff to make critical decisions.
4. Modifications to be designed, constructed, tested and
maintained to the same standards
5. Sufficient inerting material on site. ( Using N2 for Putting
Out Fires )
Location ,problem identification & humaninvestigation prior to the explosion
Mexicos historic 475-year-old Guadalajara, the capital of Jalisco state, islocated on a dry and arid mile-high plain 300 miles west of Mexico City.
The heart of downtown Guadalajara began to notice a persistent odor
reminiscent of gasoline and other chemical odors emanating from their
toilets and drains
Official members of the state measured explosivity in the separating
tank and discharge reading area, but found nothing [unusual]. [Explosivity
readings are based on the proportion of gaseous vapor in the air trapped
in the sewer pipes.] SIAPA took samples of water at the Pemex plant
outlets and made no mention of having found any irregularities
4.Guadalajara disaster
-
8/3/2019 Case Studies Handouts
11/28
Hazardous and Safety Engineering GPE 412
Case Studies 11
Samples took from in between Rio Atotonilco and Tototlan avenues.
On Doctor R. Michel Avenue ,concentrations were measured up to
100% explosivity were found. The suspected solvent appeared to be
coming from the La Central S.A. oil processing plantIt was reported
that hexane was stored at this plant.
At least one radio station had deployed personnel to the area
endangered by the gasoline spill hours prior to the explosion.
The Red Cross treated a police officer, a fireman, and a worker from
[Pemex] for gasoline inhalation
Cause(s) of the sewer explosion
New water pipes, made of zinc-coated iron, were built too close to anexisting steel gasoline pipeline. The underground humidity caused thesemetals to create an electrolytic reaction, which eventually caused themetal to corrode, creating a hole in the pipelines that caused gasoline toleak into the ground and into the main sewer pipe.
The sewer pipe had been recently rebuilt into a U-shape so that the citycould expand their underground railway system. Usually sewers are builtin a slope so that gravity helps move waste along. In order to get the U-shape to work, an inverted siphon was placed so that fluids could bepushed against gravity. The design was flawed, however. While liquidswere successfully pumped through, gases were not, and gasoline fumeswould build up.
A small spark was all that was needed to ignite the dangerous gases
-
8/3/2019 Case Studies Handouts
12/28
Hazardous and Safety Engineering GPE 412
Case Studies 12
Lessons to be taught
Any industrial waste (specially that from a petrochemical or oil industry)should be pipelined away in a private sewage away from that of domesticones
Sewage line should be away from the city, incase of any explosions, nohuman sole loss will occur
Parts of pipes(specially u tubes)should be bought from a trusted company
Any activity in a company or factory should be stopped immediately incaseof feeling of any leakage
Official regulations should be respected
The hole in pipe that leaked
-
8/3/2019 Case Studies Handouts
13/28
Hazardous and Safety Engineering GPE 412
Case Studies 13
Explosion map
The IncidentTime 1:42pm 23th of October, 1989.
A small explosion occurred in Gas plant No. 1, followed a short while later by a series
of 3 large explosions and a major fire.
Two employees were killed and several received serious injuries.
Because of the risk of further explosions, the entire site was shut down and people
living within 5 kilometers of the plant were evacuated.
Site fire teams, a local air force fire crew, and the public fire brigade fought the fire for
2 days before it was finally brought under control.
5.Phillips Petroleum
Explosion and Fire
-
8/3/2019 Case Studies Handouts
14/28
Hazardous and Safety Engineering GPE 412
Case Studies 14
The cause
The immediate cause of the first explosion was the catastrophic failure of a heat
exchanger in the absorption oil circuit.
Adsorption oil is a light hydrocarbon oil, chilled to -20 C which is used to remove
ethane, propane and butane from the natural gas to produce LPG.
The adsorption oil and natural gas were contacted in an absorber tower, then the oil,
rich with absorbed gases, was fed to a de-ethaniser columnand a fractionationcolumn to flash of the gases.
Why did it happen ?
A Royal Commission of Inquiry was established to investigate the incident, and after 8
months produced the following findings.
No HAZOP study had ever been carried out on Gas Plant No. 1. If it had been, the
hazards associated with a loss of absorption oil flow could have been identified,
and appropriate operating procedures developed.
The personnel charged with responsibility for operating the plant did not have the
necessary knowledge to deal with the situation, and steps taken to resolve the
problem were inappropriate.
-
8/3/2019 Case Studies Handouts
15/28
Hazardous and Safety Engineering GPE 412
Case Studies 15
25 hours after the initial explosion
Lessons Learned
Having good Risk Management systems and procedures is important.
Making sure that they are being used correctly is even more important.
Training of employees in understanding the hazards of the processes they are
operating is a critical element of running a safe business.
Application of effective Hazard Analysis techniques could have averted the disaster
and prevented unnecessary loss of life.
-
8/3/2019 Case Studies Handouts
16/28
Hazardous and Safety Engineering GPE 412
Case Studies 16
INTRODUCTIONThe Piper Alpha was a North Sea Oil Production platform operated by
Occidental Petroleum(Caledonia)Ltd.
The platform began production in 1976,first as an oil platform and
then later converted to gas production.
An explosion and resulting fire destroyed it on July 6,1988, killing 167
men.
To date it is the worlds worst offshore oil disaster in terms of lives lost
and impact to industry.
6.Piper Alpha ACCIDENT
Timeline of the incident
Two pumps on the platform, A and B, displaced the condensate
for transport to the coast
On the morning of July 6, Pump A's pressure safety valve was
removed for routine maintenance and The open Condensate
pipe was temporarily sealed with a blind flange(flat metal disc).
The on-duty engineer filled out a permit which stated that Pump
A was not ready and must not be switched on under any
circumstances.
-
8/3/2019 Case Studies Handouts
17/28
Hazardous and Safety Engineering GPE 412
Case Studies 17
As he found the on-duty custodian busy, the engineer neglectedto inform him of the condition of Pump A.
9:45 p.m. Pump B stopped suddenly and could not be restarted.pump A was activated.
9:55 p.m. an overpressure was produced which the metal discdid not withstand, Gas audibly leaked out at high pressure. andbefore anyone could act, the gas ignited and exploded, firewallswere set to withstand fire not explosions, so it was easilybroken.
10:04 p.m. The control room was abandoned. Shut down wasn'tactivated
10:20 p.m. Tartan's gas line melted and burst. releasing 15-30
tones of gas every second, which immediately ignited. A massivefireball 150 meters in diameter engulfed Piper Alpha
12:45 a.m., July 7 The entire platform had gone. Module (A) wasall that remained of Piper Alpha.
AftermathThe main problem was that most of the personnel who had the
authority to order evacuation had been killed when the first explosion
destroyed the control room.
Another contributing factor was that the nearby platforms Tartan and
Claymore continued to pump gas and oil to Piper Alpha until itspipeline ruptured in the heat in the second explosion.
By the time civil and military rescue helicopters reached the scene,
flames over one hundred meters in height and visible as far as one
hundred km away prevented safe approach
Total insured loss was about 1.7 billion (US$ 3.4 billion). To date it is
the world's worst offshore oil disaster in terms both of lives lost and
impact to industry167 men were killed , with only 59 survivors
-
8/3/2019 Case Studies Handouts
18/28
Hazardous and Safety Engineering GPE 412
Case Studies 18
The term runaway reaction is often improperly used to refer to any uncontrolled chemical
reaction.
As properly used, it refers to loss of control of a kinetically limited, exothermic reaction that
proceeds at a stable, controlled rate under normal conditions and that includes adequate
removal of the heat of reaction.
Methylcyclopentadienyl manganese tricarbonyl (MCMT) is used as an octane-increasing
gasoline additive.
T2 manufactured MCMT in three steps sequentially within a single process batch reactor. The
first step of the reaction required heating to initiate the reaction. After that, all three steps
were exothermic (heat-producing) and required cooling.
Heating and Cooling system
A heating system circulated hot oil through 3-inch piping installed around the inside of the
reactor.
A cooling jacket covered the lower of the reactor. A pipe from the city water system
connected to the bottom of the jacket. Water was injected into the jacket and allowed to
boil steam from the boiling water vented to atmosphere.
7.T2 Laboratories Inc.
Runaway Explosion
Process Description
First, reactants are charged through the top of the
reactor, Then the operators began to adjust the
conditions of the reactor at 50 psig and hot oil
temperature control at 360oF.
At a reaction temperature of about 300F, theprocess operator turned off the hot oil system; heat
generated by the metalation reaction continued to
raise the mixture temperature.
At a temperature of about 360F, the process
operator initiated the control system cooling
program.
The operating procedures used at the time of the
incident included no emergency instructions for
loss of cooling.
-
8/3/2019 Case Studies Handouts
19/28
Hazardous and Safety Engineering GPE 412
Case Studies 19
Incident Description
On December 19, T2 was producing its 175th batch of (MCMT). At 1:23 pm,
the process operator had an outside operator call the owners to report a
cooling problem and request they return to the site. Upon their return, one
of the two owners went to the control room to assist.
A few minutes later, the reactor burst and its contents exploded, killing the
owner and process operator who were in the control room and two outside
operators who were exiting the reactor area.
The energy release of this explosion to be equivalent to 1,400 pounds of
TNT. The blast was felt 15 miles away in downtown Jacksonville (FL).
The blast occurred due to a runaway chemical reaction that generated hightemperature and pressure in the reactor.
Emergency Responses
Within 10 minutes of the incident, two hazardous
materials stations dispatched.
The Jacksonville Fire and Rescue Department completeda hazard analysis using (MSDSs) from the T2 website.
The incident commander (IC) ordered a half-mile
evacuation radius, The IC ordered full personal protective
equipment.
The Jacksonville Planning and Development Department
surveyed surrounding buildings and condemned unsafe
structures, including the four businesses closest to T2.
-
8/3/2019 Case Studies Handouts
20/28
Hazardous and Safety Engineering GPE 412
Case Studies 20
Causes
The CSB found that a runaway exothermic reaction occurred during thefirst (metalation) step of the MCMT process.
1. The route cause was that T2 did not recognize the runaway reactionhazard associated with the MCMT it was producing.
2. The cooling system employed by T2 was susceptible to single-pointfailures due to a lack of design redundancy (during scale-up).Water supply valve failing closed or partially closed.
Water drain valve failing open or partially open.
Failure of the pneumatic system used to open and close the water valves.
Blockage or partial blockage in the water supply piping.
Faulty temperature indication.
Mineral scale buildup in the cooling system.
3. The MCMT reactor vessel relief system was incapable of relieving thepressure from the runaway reaction.
Future Precautions1. Frequent periodic maintenance for all equipments and utility must be scheduled, especially
for cooling systems and fire fighting units including piping systems, pumping, valves,housekeeping.etc.
2. Operating Procedures used must include emergency instructions for loss of cooling; whendealing with exothermic reactions that are ready to be exothermic runaway reactions.
3. A secondary (backup) source of water stored on site (for cooling) must be immediately
available to process operator in emergency.
4. Overpressure Relief Device and Rupture disks must be properly designed to prevent runawayreactions in their initial stages.
5. Cooling Requirements in a small-scale process do not usually accurately indicate the amountof cooling needed in full scale reactor. So take into consideration the effect of scaling on theprocess hazards as well as the yield.
6. Chemical Engineers and Chemists must be aware of Process Hazards as well as Processchemistry.
-
8/3/2019 Case Studies Handouts
21/28
Hazardous and Safety Engineering GPE 412
Case Studies 21
What Happened?
On Friday, September 21. the French town of Toulouse was
rocked by a devastating chemical explosion. Two production
halls of the AZF fertilizer factory, a literally flew into the air.
Initial reports spoke of 29 dead and. A total of 2,400 were
injured,
Two chimneys collapsed and all that remained from the two
halls at the centre of the explosion was a crater 10 meters
deep and 50 meters wide. The pressure from the explosion
was sufficient to send automobiles flying into the air, causing
a nearby shopping centre to collapse
8.Chemical Explosion in Toulous
Causes: For years the AZF petrochemical factory has been regarded as a
ticking time bomb..
Reports last year emphasized the danger of an explosion
Experts for factory safety had already received alarming
information lst week of leaks in the plant, through which liquid
ammonia gas could escape.
Three thousand tons of ammonium nitrate were stored at the
plant. It is well known that ammonium nitrate can detonate
when it is overheated or brought into contact with organic
material such as oil or coal.
-
8/3/2019 Case Studies Handouts
22/28
Hazardous and Safety Engineering GPE 412
Case Studies 22
How did they deal with it:
As a huge orange colored cloud of gas, smelling of ammonia,
moved towards the city centre for 3 kms. Gas masks were
distributed in the town centre and the metro system in
Toulouse was evacuated because of the spread of gas. The city
council issued a warning that people should stay indoors and
close their windowsa problem for those whose windows
had already been shattered.
The airport at Toulouse-Blagnac and the main railway station
were closed and 90 schools in the area evacuated. Over radio,
inhabitants were called upon to refrain from drinking tap
water and use as little water as possible.
Hazards of Fertilizers Industry:
The fertilizer plants, particularly those manufacturing ammonia
are amongst the most complex plants in the chemical industry.
The process involve handling of various hazardous substances
The operating conditions are also severe and affect the safety ofequipment, personnel involved and the environment.
-
8/3/2019 Case Studies Handouts
23/28
Hazardous and Safety Engineering GPE 412
Case Studies 23
How to Prevent Further Accidents: Many process vessels operate under pressure or vacuum.
These vessels are to be examined regularly.
Valves are used for isolating the piece of equipment in case of
maintenance work but these are liable to leak, valves alone
should not be used as the means of isolation.
The instrumentation in the process industry is vital and a key
factor in the safe operation. The logic followed in theinstrumentation coupled with the trips and interlocks should
have the intrinsically safe features.
9.Valero Propane Fire
Fire From IceOn February 16,2007, a liquid propane
released from a cracked control stationcaused massive fire in propane
deasphalting unit (PDA) caused injuries of
three employees and constructor. The fire
caused extensive equipment damage and
shutdown and evacuation of the refinery.
-
8/3/2019 Case Studies Handouts
24/28
Hazardous and Safety Engineering GPE 412
Case Studies 24
Process description:
The PDA unit recovered fuel feedstock and paving-grade asphaltfrom the heavy bottoms produced in the refinerys vacuumcrude oil fractionator. In the McKee PDA process, twoliquid/liquid extraction towers used liquid propane as a solventto extract gas oil from the pitch under approximately 500pounds per square inch (psi)pressure. The recovered gas oil wasprocessed into gasoline in another refinery unit. The asphaltproduced was sold for use in paving materials.
The relatively dense pitch entered an upper section of the extractorand flowed to the bottom of the tower. Less dense liquid washpropane entered a lower section and flowed to the top of theextractor. Internal structures in the tower promoted effectivecontact between the two streams. DeAsphalted Gas Oil (DAGO)extracted from the pitch flowed out of the top of the tower withmuch of the propane. This liquid flowed through a series of flashdrums8 to remove propane from the gas oil. The DAGO was sentelsewhere in the refinery for processing.
Incident Sequence
In this incident, water settling out of a propane streamlikely leaked through a 10 inlet block valve andaccumulated in the low point formed by a control
station. The control station was connected to theprocess, but had not been used for approximately 15years. A period of cold weather likely froze the water,fracturing the pipe elbow upstream of the controlvalve. Warmer weather then melted the ice, resultingin a release of highly pressurized liquid propanethrough the fractured elbow.
-
8/3/2019 Case Studies Handouts
25/28
Hazardous and Safety Engineering GPE 412
Case Studies 25
Near-Miss Events:
Butane Sphere Heat Exposure
One-ton Chlorine Containers
CSB Recommendation:
Replace chlorine with safer
biocide for cooling water.
Improve hazard analysis in process.Establish of freeze protection.
Periodic inspection of dead legs in frequentlyused in process (if possible isolate it with blindisolator to prevent linkage).
Management of change reviews.
-
8/3/2019 Case Studies Handouts
26/28
Hazardous and Safety Engineering GPE 412
Case Studies 26
Accident & immediate treatment
On March 26, 1997, at about 3 p.m. an explosion occurred within a fuel blending
tank at Chief Supply Corporation (Chief), in Haskell, Oklahoma. One worker was
killed and two others injured.
Several smaller explosions occurred as over 1,000 drums containing cleaning
solvents, assorted acids, bases, metal sludge, and four 5,000-gallon tanks
holding waste fuels became involved in the fire
A highway next to the site was closed
An area 1.5 miles north and one mile east of the facility in the path of a largesmoke plume were evacuated.
A solid stream of water should never be used to extinguish this type of fire
because it can cause the fuel to scatter, spreading the flames. The most effective
way to extinguish a liquid or gas fueled fire is by inhibiting the chemical chain
reaction of the fire, which is done by dry chemical and haloalkane extinguishing
agents.
10.Waste Fuel Oxidizer
Roots of the accident Chief instituted a practice of adding oxidizers to fuel blend mixture.
Chief blended wastes in two 1,000 gallon vertical tanks called dispersers
The disperser involved in the incident was equipped with a mixer, the mixer
was not supposed to be started until the liquid level reaches half of the tank
capacity.
The disperser was open to the atmosphere; no nitrogen or other inert gas
blanketing was used to suppress flammable vapors.
-
8/3/2019 Case Studies Handouts
27/28
Hazardous and Safety Engineering GPE 412
Case Studies 27
Oxidizers were to be added to the fuel blend only after ensuring that the
disperser was 3/4 full and the mixer running, according to an unwritten
procedure used by lab personnel.
two workers were on top of the disperser starting a new batch and only four
drums of liquid had been added to the tank when a lab employee at the top of
the tank added one bucket of chlorates, one bucket of perchlorates, and one
bucket of nitrites to the disperser.
An explosion and fireball. The fireball fatally engulfed the employee who was
pouring the drums and started a large fire in the building.
Causes of the explosion
Strong oxidizers generally are considered to be incompatible with many organic
substances because of the potential for dangerous reactions( fire, explosion, or
violent reaction) .
Only four drums had been dumped into the previously empty disperser, Thisallowed the solid oxidizers to pile up at the bottom of the tank, in direct contact
with each other and with flammable solvent liquid and vapor.
Ethanol in the fuel blending mixture reacted with the perchlorate salt , explosive
ethyl perchlorate could have been formed.
-
8/3/2019 Case Studies Handouts
28/28
Hazardous and Safety Engineering GPE 412
Precautions
Facilities need to conduct the necessary information searches or laboratory tests
to ensure that all reaction mechanisms are known and documented.
facilities need to ensure that process equipment, controls, and procedures are
designed, installed, and maintained to safely operate the process.
Standard Operating Procedures (SOPs) are essential to safe operations. Facilities
should establish a system to develop and maintain written SOPs.
Employees must be properly trained in the processes they work on,using theSOPs for that process or job tasks.