Case Studies and Success Stories Swedish International Development Agency S ESSION 10 United Nations...
-
Upload
natalia-gadbury -
Category
Documents
-
view
213 -
download
0
Transcript of Case Studies and Success Stories Swedish International Development Agency S ESSION 10 United Nations...
Case Studies and Success Stories
Swedish International Development Agency
SESSION 10
United Nations Environment ProgramDivision of Technology Industry and Economy
ACME Applying CLEANER PRODUCTION to MULTILATERAL ENVIRONMENTAL AGREEMENTS
OUTLINEObjectives of this session
1/ Cases studies on CP and UNFCCC > Case #1 - Pulp and Paper > Case #2 - Textile > Other examples
2/ Cases studies on CP and Basel Convention > Case #1 - Tannery > Case #2 - Electroplating > Other examples
3/ Cases studies on CP and Stockholm Convention > Case #1 - Pulp and Paper > Other examples
ACME - Session 10 – Cases studies and success stories - 2 / 36
Name of the Company: Agarwal Duplex LTD., Muzaffarnagar, INDIA
Production:Kraft paper and board from waste paper.
Context: Cleaner Production studies were conducted in the industry. The CP Team was formed and the entire plant was taken as focus area.
CP & UNFCCCCase #1 - Pulp and Paper
ACME - Session 10 – Cases studies and success stories - 3 / 36
OperationSources of
wasteNature of
wasteProbable Causes of waste
generated
Electricity Generation
DG sets - GHG emissions
- Noise
- Solid
- Capacity Utilization
- Due to frequent power failures of the electricity through grid supply the paper machines use to stop and there by the waste of paper because of breaking of paper while rolling them into reels
- The capacity utilization of the machines was low
- High GHG emissions from the use of Diesel in DG Sets
- Low quality of electricity supplied
Steam Production
Coal fired Boile GHG - Use of fossil fuel
CP & UNFCCCCase #1 - Pulp and Paper
CAUSE ANALYSIS OF THE WASTE STREAM
ACME - Session 10 – Cases studies and success stories - 4 / 36
CP technique used:
> Process optimization
> Input material change
> Technology change
CP options identified:
1. Replace the existing boiler with a new fluidised bed boiler of hogh pressure which uses bagasse as a fuel in place of coal in the old boiler.
2. Replace the diesel generating set for electricity production with a extraction cum condensing turbine and use the steam from the new high pressure boiler.
CP & UNFCCCCase #1 - Pulp and Paper
CLEANER PRODUCTION OPTIONS IDENTIFIED
ACME - Session 10 – Cases studies and success stories - 5 / 36
RESULTS OF THE CP OPTION IMPLEMENTATION
Investment
Operational cost
Net annual savings
Payback period
Reduction in GHG emissions
2 million US$
same as earlier
1.5 million US$
16 months
~ 37.366 Tons per year
CP & UNFCCCCase #1 - Pulp and Paper
ACME - Session 10 – Cases studies and success stories - 6 / 36
CP & UNFCCCCase #2 - Textile
ACME - Session 10 – Cases studies and success stories - 7 / 36
Name of the Company: Luthra Dyeing and Printing Mills, Surat, INDIA
Production:Printed and dyed fabric of polyester, cotton, rayon.
Context: Cleaner Production studies were conducted in the industry. The CP Team was formed and the boiler house was taken as focus area.
OperationSources of
wasteNature of
wasteProbable Causes of waste generated
Steam generation
Boiler Flue Gases
Un-burnts in Ash
- Air-fuel ratio is not maintained
- No monitoring of relevant parameters (O2 or CO2)
- No device/method for heat recovery
- Air ingress through various portion
- Air quantity and pressure is not sufficient
- Distribution of primary air through grate
- Sizing of coal not proper
- Design of grate not appropriate
- Firing rate is not uniform
- Manual ash removal
- Poor fuel quality and combustion is not proper
CAUSE ANALYSIS OF THE WASTE STREAM (1)
ACME - Session 10 – Cases studies and success stories - 8 / 36
CP & UNFCCCCase #2 - Textile
OperationSources of
wasteNature of
wasteProbable Causes of waste generated
Steam generation
Boiler Blow-down
Radiation Loss
- Bad Boiler feed water quality
- Condensate is not recovered
- Boiler drum TDS is not maintained as required
- Un-insulated portions of boiler
- Openings
CAUSE ANALYSIS OF THE WASTE STREAM (2)
CP & UNFCCCCase #2 - Textile
ACME - Session 10 – Cases studies and success stories - 9 / 36
CP technique used :
> Good House Keeping
> Operational Practices
> Process Optimization
> Raw Material Substitution
> New Technology
> New Product Design
> Onsite Recycle & Reuse
> Equipment Modification
CLEANER PRODUCTION OPTIONS IDENTIFIED (1)
CP & UNFCCCCase #2 - Textile
ACME - Session 10 – Cases studies and success stories - 10 / 36
Waste Stream CP Options
Heat Loss due to - Install air heater for recovery of waste heat
Flue gas - Plug all the air leakages into boiler furnace
Unburnt in Ash - Conversion of existing boiler to the FBC boiler
- Replacing existing boiler to FBC Boiler
- Optimize the coal sizing by proper crushing & sieving
- Modify the existing grate by reducing the gaps between the rods
- Optimize the firing rate by use of stoker firing
Blow down loss - Install water treatment system (RO) plant
- Change the water used in the boiler from tanker water to Municipal - Supply Water
- Install conductivity meter to check boiler drum water quality and therefore optimize the blow down rate
- Recover flash steam from boiler blow down
- Re-circulate condensate from steam separator and wherever possible
Radiation Loss - Insulate all the bare and damaged portions
- Insulate the flanges (125 Flanges)
- Installation of Steam Traps ( Thermo Dynamic Traps)
CP & UNFCCCCase #2 - Textile
ACME - Session 10 – Cases studies and success stories - 11 / 36
RESULTS OF THE CP OPTION IMPLEMENTATION
Investment
Net annual savings
Payback period
Reduction in GHG emissions
204.000 US$
196.300 US$
11 months
1300 Tons per year
CP & UNFCCCCase #2 - Textile
ACME - Session 10 – Cases studies and success stories - 12 / 36
CP & UNFCCCOther examples - A
ACME - Session 10 – Cases studies and success stories - 13 / 36
ILUKA MINING AND MINERAL PROCESSING
Focus area Air emissions and heat from kiln
CP Option Waste heat recovery, initially thinking of installing high-cost wet scrubber technology.
Results Large investment (but feasible) especially when compared to traditional end-of-pipe treatment system.
Reduction in GHG emissions by 52.000 Tons/year
CP & UNFCCCOther examples - B
ACME - Session 10 – Cases studies and success stories - 14 / 36
BUTTERCUP BAKERIESAUSTRALIA
Focus area Baking oven
CP Option Installation of heat exchangerfor a waste heat recovery system.
Results Investment 10,000 US$
Annual savings 2.000 US$
Reduction in GHG 20 %
CP & UNFCCCOther examples - C
ACME - Session 10 – Cases studies and success stories - 15 / 36
G STEEL PUBLIC COMPANY LIMITEDTHAILAND
Focus area Electric Arc Furnaces (EAF)
CP Option Repositioning of EAF burner to increase consistency of injection and consumption of oxygen via oxygen lance.
Results Investment 10,000 US$
Annual savings 3.839.168 US$
Reduction in GHG 42.943 Tons/year
ASSOCIATED MOTORWAYS LIMITEDSRI LANKA
CP & UNFCCCOther examples - D
ACME - Session 10 – Cases studies and success stories - 16 / 36
Focus area Compressors and Compressed Air System
CP Option Replacement of old inefficient compressor with screw compressors.
Results Investment 29,500 US$
Annual savings 43,137 US$
Reduction in GHG 102 Tons/year
CP & UNFCCCOther examples - E
ACME - Session 10 – Cases studies and success stories - 17 / 36
HANOI CERAMIC TILESVIETNAM
Focus area Vertical dryer
CP Option Use of waste hot air from rapid and final cooling in the vertical dryer.
Results Investment 21,500 US$
Annual savings 36,720 US$
Reduction in GHG 328 Tons/year
Name of the Company: Mohd. Usman Tanneries, INDIA
Production:Leather from sheep and goat skins (from raw hides to finished stage).
Context: Cleaner Production studies were conducted in the industry. The CP Team was formed and the tanning section was taken as focus area.
CP & BASEL CONVENTIONCase #1 - Tannery
ACME - Session 12 – Cases studies and success stories - 18 / 36
OperationSources of
wasteNature of
wasteProbable Causes of waste generated
Chrome tanning
Spent tanning bath, wash streams
Wastewater - Improper water measurement
- Chemicals weighing
- Spillages of the chemicals from the drum feeding hole
- No recovery of spent chrome
CAUSE ANALYSIS OF THE WASTE STREAM
ACME - Session 10 – Cases studies and success stories - 19 / 36
CP & BASEL CONVENTIONCase #1 - Tannery
CP technique used: > Recovery, recycle and reuse.
CP options identified:> Recover the chrome by addition of magnesium oxide.
CLEANER PRODUCTION OPTIONS IDENTIFIED
ACME - Session 10 – Cases studies and success stories - 20 / 36
CP & BASEL CONVENTIONCase #1 - Tannery
RESULTS OF THE CP OPTION IMPLEMENTATION
Investment
Operational cost
Net annual savings
Payback period
Reduction in toxicity and volume of hazardous waste
generation
7.500 US$
2 000 US$/year
6.500 US$
14 months
~ 15 Tons per year due to negligible amount of chrome in waste water.
ACME - Session 10 – Cases studies and success stories - 21 / 36
CP & BASEL CONVENTIONCase #1 - Tannery
Name of the Company: Atlas cycles, Sonepat, INDIA
Production:Bicycles.
Context: Cleaner Production studies were conducted in the industry. The CP Team was formed and following focus areas identified:
1. Hazardous waste generation from electroplating section.
2. Cyanide bearing waste from case hardening section.
ACME - Session 10 – Cases studies and success stories - 22 / 36
CP & BASEL CONVENTIONCase #2 - Electroplating
Operation Sources of wasteNature of
wasteProbable Causes of waste generated
Chrome Plating
Spent plating bath and wash streams
Wastewater with Hexa valent Chrome
- High quantity of water used
- Hexavalent chrome used
- Conversion of hexavalent chrome to trivalent chrome by ferrous sulphate
Cyanide Plating for Case hardening
Spent plating bath and wash streams
Waste water with cyanide
- Chlorine for cyanide removal
- Large amount of lime used
- Presence of ferrocyanide compounds making the sludge hazardous
CAUSE ANALYSIS OF THE WASTE STREAM
ACME - Session 10 – Cases studies and success stories - 23 / 36
CP & BASEL CONVENTIONCase #2 - Electroplating
CP technique used:
> Process optimization
> Input material change
> Technology change
CP options identified:
1. Replacing use of ferrous sulphate by sodium met-bi-sulphite for reduction of hexavalent chrome to trivalent chrome.
2. Adoption of new technology to replace case hardening by cyanide plating to gas carburizing.
CLEANER PRODUCTION OPTIONS IDENTIFIED
CP & BASEL CONVENTIONCase #2 - Electroplating
ACME - Session 10 – Cases studies and success stories - 24 / 36
CP OPTION INVESTMENT SAVINGS/ BENEFITS PAY BACK
1 NIL No monetary savings in process but hazardous sludge reduced by 30% (15 Tons/year).
IMMEDIATE
2 US $ 10,000 No direct monetary savings but hazardous waste sludge reduced by 74% (50 Tons/year).
IMMEDIATE
RESULTS OF THE CP OPTION IMPLEMENTATION
ACME - Session 10 – Cases studies and success stories - 25 / 36
CP & BASEL CONVENTIONCase #2 - Electroplating
DUTCH IRON FOUNDRIES
Focus area Sand reclamation
CP Option Optimisation of the sand dosing system.
Results Investment: 0 US$
Annual savings: 40.000 US$
Reduction in hazardous wastes: - 560 Tons/year
Reduction of raw material used: - 7,5%
Other examples - ACP & BASEL CONVENTION
ACME - Session 10 – Cases studies and success stories - 26 / 36
DINTEX DYECHEM LTD. Vinyl Sulphone Intermediate Manufacturer.
INDIA
Focus area Unit processes : Sulfonation, Condensation
CP Option Acid recovery system and spray drier.
Results Investment 355.260 US$
Annual savings 415.790 US$
Reduction in hardous wastes - 6.100 Tons/year
Other examples - BCP & BASEL CONVENTION
ACME - Session 10 – Cases studies and success stories - 27 / 36
Manufacture of Chemicals and Chemical Products UNITED STATES
Focus area Reactor wash solution with alcohol, phenols formaldehyde resins and water.
CP Option On site recycling and recovery by distilling and reusing the alcohol.
Results Investment Not reported
Annual savings 15.000 US$
Reduction in hardous wastes - 67%
Other examples - CCP & BASEL CONVENTION
ACME - Session 10 – Cases studies and success stories - 28 / 36
Manufacture of Lead Acid Battery Plates FRANCE
Focus area Battery Plate Manufacturing line.
CP Option Process optimization of the manufacturing line by changing to automatic plant.
Results Investment 214.000 US$
Annual savings Not reported
Reduction in hardous wastes - 85%
Other examples - DCP & BASEL CONVENTION
ACME - Session 10 – Cases studies and success stories - 29 / 36
Other examples - ECP & BASEL CONVENTION
Manufacture of Fabricated Metal Products (Solar Cell Wafers, Submarine silencer, satellite dish components)
UNITED STATES
Focus area Chemical Etching on stainless steel and Nickle.
CP Option Baking soda/water developer has been substituted for a combination of methylene chloride, 1,1,1 trichloroethane and perchlorethylene solvent ; Alkaline cleaners have been substituted for methanol ; sulfuric acid-hydrogen peroxide mix has replaced a chrome-based brightener Process optimization of the manufacturing line by changing to automatic plant.
Results Investment Not reported
Annual savings Not reported
Reduction in hardous wastes - 20% (135 Tons)
ACME - Session 10 – Cases studies and success stories - 30 / 36
Name of the Company: ITC, Bhadrachalam Papers Ltd.Bhadrachalam, INDIA.
Production:Paper.
Context: Cleaner Production studies were conducted in the industry. The CP Team was formed and the paper bleaching section was taken as focus area.
ACME - Session 10 – Cases studies and success stories - 31 / 36
CP & STOCKHOLM CONV.Case #1 - Pulp and Paper
OperationSources of
wasteNature of waste
Probable Causes of waste generated
Bleaching Bleaching process
- Hazardous Air Emissions
- Water Pollution Load
- Energy Loss
- Use of elemental chlorine in form of bleaching powder/ NaOCl
- Old Technology
CAUSE ANALYSIS OF THE WASTE STREAM
CP & STOCKHOLM CONV.Case #1 - Pulp and Paper
ACME - Session 10 – Cases studies and success stories - 32 / 36
CP technique used:
> Input material change
> Technology change
CP options identified:
1. Installation of a new R8 process chlorine dioxide generation plant of 7 tons per day capacity.
2. Modify the bleaching sequence to “chlorine dioxide / ozone / chlorine dioxide”.
CLEANER PRODUCTION OPTIONS IDENTIFIED
CP & STOCKHOLM CONV.Case #1 - Pulp and Paper
ACME - Session 10 – Cases studies and success stories - 33 / 36
RESULTS OF THE CP OPTION IMPLEMENTATION
Investment
Net annual savings
Payback period
Results
10,32 million US$
4 million US$
2,15 years
- Reduction in AOX emissions.- Improved brightness quality
CP & STOCKHOLM CONV.Case #1 - Pulp and Paper
ACME - Session 10 – Cases studies and success stories - 34 / 36
Other exampleCP & STOCKHOLM CONV.
Polyerethane manufacturing GERMANY
Focus area Adsorption of CCl3F.
CP Option Use of charcoal bed for adsorption of CCl3F.
Results Investment 350000 US $
Elimination of CCl3F from the environment
ACME - Session 10 – Cases studies and success stories - 35 / 36
CONCLUSIONEnd of session 10
Thank you for your attention…Any questions?
ACME - Session 10 – Cases studies and success stories - 36 / 36