Case 3 Cemex
-
Upload
asep-kurniawan -
Category
Documents
-
view
156 -
download
11
description
Transcript of Case 3 Cemex
-
Assignment
Multinational Financial Management
Case 3
CEMEX ENTERS INDONESIA
Lecturer: Erni Ekawati, Ph.D
By: GROUP 5
Ariefka Sari Dewi 12/341231/PEK/17320
Dwi Wahyu R.S 12/341246/PEK/17335
Hartatiek 12/341257/PEK/17346
Niken Andry 12/341279/PEK/17368
Rifqa 12/341295/PEK/17384
PROGRAM MAGISTER MANAJEMEN
FAKULTAS EKONOMIKA DAN BISNIS
UNIVERSITAS GADJAH MADA
YOGYAKARTA
2013
-
1
A. FACTS Cementos Mexicanos (Cemex) is a multinational company that produces cement in
Mexico. Cemex is the largest cement manufacturer in the Americas, and third largest in
the world. Cemex began its international expansion in an effort to reduce its reliance on
the Mexican market to capitalize on demand in many countries. Cemex competes in the
global marketplace for both market share and capital. The international cement market,
like markets in other commodities such as oil, is a dollar-based market. For this reason
and for comparisons against its major competitors in both Germany and Switzerland, so
Cemex considers the U.S. dollar its functional currency. Cemex wants to increase its
market capitalization through global expansion and entering in Asia market. In the year
1998, Cemex was considering the construction a cement manufacturing facility on the
Indonesian island of Sumatra. The project, Semen Indonesia, would be a wholly owned
greenfield investment with a total installed capacity of 20 million metric tons per year
(mmt/y). There were three driving reasons for this project:
1. Initiate a productive presence in Southeast Asia. 2. Favorable long-term prospects for Asian infrastructure development and growth. 3. Positive prospects for producing and exporting from Indonesia due to the depreciation
of the Indonesian rupiah (Rp) in 1997.
In analyzing feasibility of this project, Cemex make a road map of the complete
multinational capital budgeting to enter in Indonesia market.
Figure 1: a Road Map of to the Construction of Semen Indonesias Capital Budget
The basic principle is that, the parent company invests US$-denominated capital in
FDI project, project capital budget evaluated, and then project cash flows are remitted to
Cemex in order to make parent viewpoint capital budget. The first step to construct
capital budget, Cemex was analyzing a set of pro forma financial statements for Semen
Indonesia, all in Indonesian rupiah (Rp). The next step is to create two capital budgets
like project viewpoint and parent viewpoint. The following analysis was conducted
assuming that purchasing power parity (PPP) holds for the Rp/US$ exchange rate for
analysis this project. The projected inflation rates for Indonesia was 30% per annum and
3% per annum for United States inflation.
-
2
B. SITUATION ANALYSIS 1. Financial Assumption
This project would be held in Indonesia so the calculation was in Indonesian
Rupiah. Before the capital budgets (NPV and IRR) were calculated, financial assumptions
must be made. Based on the case, the financial assumption will be explained below.
a. Capital Investment Cemex had production capacity of 20 million metric ton per year (mmt/y) with cost of
installed capacity $110/tonne. Cemex assumed exchange rate of Rp 10,000/US$ in the
year 1 and would be change consistent with inflation rate. Therefore, cost of initial
investment can be calculated by 20 million mmt/y*$110/tonne = $2.2 billion or Rp 22
trillion. The amount cost of plant and equipment were Rp 17,6 trillion and Cemex
assumed an annual depreciation charge of Rp 1.76 million (10 years straight-line
depreciation schedule).
b. Foreign Exchange Rate This project was assuming that PPP holds for the Rp/US$ exchange rate. The spot rate
in year 0 was Rp 10.000/US$. The projected inflation rates for Indonesia were 30%
per annum and 3% per annum for United States. This table below shows that
calculation of spot rate Indonesian Rupiah against U.S. Dollar
Table 1: Spot Rate (Rp/US$)
Project year 0 1 2 3 4 5
Calculation (1.3/1.03)*
10,000
((1.3/1.03)^2)*
10,000
((1.3/1.03)^3)*
10,000
((1.3/1.03)^4)*
10,000
((1.3/1.03)^5)*
10,000
Spot rate
(Rp/US$) 10,000 12,621 15,930 20,106 25,376 32,028
c. Financing Capital structure was used by project viewpoint consists of 50% equity and 50% debt.
All equity form Cemex, 75% debt from Cemex, and 25% from a bank consortium
arranged by the Indonesian government. When, capital structure was used by parent
viewpoint consist of 60% equity and 40% debt. The loan is denominated in U.S.
dollars and Indonesian Rupiah. In U.S. dollars, the loan has 10% of annual interest
with maturity 5 years. In Indonesia Rupiah, the loan has 35% of annual interest with
maturity 8 years. This capital structure makes the difference of weighted average cost
of capital (WACC) between project viewpoint (used in Indonesian Rupiah) and parent
viewpoint (used in U.S. Dollar). This is calculation of WACC from project and parent
viewpoint:
Table 2: Calculation of WACC from Parent Viewpoint
Information Calculation Result
Risk-free rate 6%
Credit spread 2%
Cost of debt 8%
Cost of debt, after-tax 8%*(1 0.35) 5.2% Debt proportion 40%
Cemex Beta 1.5
Equity premium (13% - 6%) 7%
Cost of equity (6% + 7%)*1.5 16.5%
Equity proportion 60%
WACC = (0.4)*(5.2%) + (0.6*16.5%) = 11.98%
-
3
Table 3: Calculation of WACC from Project Viewpoint
Information Calculation Result
Risk-free rate
33%
Credit Premium
2%
Cost of debt in Rupiah
35%
Cost of debt, after-tax 35%*(1 - 0.3) 24.5%
Cost of debt, after tax to be paid (24.5%*0.25) 6.125%
Cost of US$ debt
38.835%
Cost of US$ debt, after-tax 38.835%*(1 0.3) 27.184% Cost of debt, after tax to be paid (27.184%*0.75) 20.388%
Total Cost of debt 6.125% + 20.388% 26.513%
Debt Proportion
50%
Cemex Indonesia of beta
1
Equity premium (40% - 33%) 7%
Cost of equity (33% + 7%)*1 40%
Equity Proportion
50%
WACC = (0.5*26.513%) + (0.5*40%) = 33.527%
d. Revenues Cemex assumes that the 20 mmt/y facility is expected to operate at only 40% capacity
(producing, 8 million metric tonnes). Sales price of cement was $58/tonne and would
remain constant over the life project. Capacity is expected to be 50% in year 2 and
60% from year 3 on.
e. Costs Costs of this project consist of manufacturing cost, production costs, and loading
costs. Manufacturing costs (labor, materials, power, etc.) were estimated at Rp
115,000 per tonne for 1999 and increasing in accordance with inflation rate of 30%
per year. Production costs are estimated Rp 20,000 per tonne for 1999 and increasing
in accordance with inflation rate of 30% per year.
2. Project Viewpoint Capital Budget Evaluation of a project from local viewpoint serves some useful purposes, but it
should be subordinated to be evaluated from the parents viewpoint. In evaluating a foreign projects performance relative to the potential of a competing project in the same host country, we must pay attention to the projects local return. Almost any project should at least be able to earn cash return equal to the yield available on host government
bonds (with the same maturity as projects economic life). For project viewpoint, net cash flow or free cash flow is calculated by summing
EBITDA, recalculated taxes, and changes in net working capital. Capital budgeting is
estimated by using EBITDA, not EBT, which contains both depreciation and interest
expense. Furthermore, taxes are recalculated on the basis of EBITDA. The firms cost of capital used in discounting also includes the deductibility of debt interest in its
calculation.
The initial investment of Rp 22 trillion is the total capital invested to support these
earnings. Although receivables average 50 to 55 days sales outstanding (DSO) and
inventories 65 to 70 DSO, payable and trade credit are also relative long at 114 DSO in
the Indonesian cement industry. Semen Indonesia expects to add approximately 15 net
DSO to its investment with sales growth.
The terminal value (TV) of project represents the continuing value of the cement
manufacturing facility in the years 5, last year of detailed pro forma financial analysis.
-
4
TV calculated as perpetual net operating cash flow after year 5. TV from Semen
Indonesia can be estimated by using form below.
The result of the capital budget from the project viewpoint indicate a negative
present value (NPV) of Rp 9,443,460 million or about Rp 9,4 trillion and internal rate of
return (IRR) of only 15.4% less than cost of capital about 33.257%. According to this
calculation, the project is not acceptable.
Tabel 4: Capital Budget: Cemex Indonesia (millions RP)
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
EBITDA
2,979,029 4,499,067 6,504,982 7,813,589 9,352,941
Recalculated taxes
(@30%) (893,709) (1,349,720) (1,951,495) (2,344,077) (2,805,882)
Net Operating
cash flow 2,085,320 3,149,347 4,553,487 5,469,512 6,547,059
Additions to NWC
(240,670) (139,028) (436,049) (289,776) (625,314)
Initial Investment (22,000,000)
Terminal Value
19,686,258
Free Cash Flow
(FCF) (22,000,000) 1,844,650 3,010,319 4,117,438 5,179,736 25,608,003
NPV @ 33.257% ($9,443,460)
IRR 15.4%
3. Parent Viewpoint Capital Budgeting All incremental earnings to Cemex from the prospective investment project in
Indonesia are important in parent viewpoint. For Cemex, investment must be analyzed in
terms of US dollar cash inflows and outflows associated with the investment over the life
of project, after-tax, discounted at its appropriate cost of capital.
Parent viewpoint capital budget can be estimated in two ways. First, isolate
individual cash flows, adjusted for any withholding taxes imposed by the Indonesia
government and converted to US dollars. In the case of Semen Indonesia, dividends will
be charged a 15% withholding tax, 10% on interest payments, and 5% license fees.
Mexico does not repatriated earnings since they have already been taxed in Indonesia.
After isolate individual cash flows the second step is to calculate the actual parent
viewpoint capital budget, combines these US dollar after-tax cash flows with initial
investment to determine the net present value of proposed Semen Indonesia subsidiary
eyes of Cemex. A specific peculiarity of this parent viewpoint capital budget is that only
the capital invested into the project by Cemex itself, $1,925 million, is included the initial
investment, $1,100 million in equity and $825 million loan. The Indonesia debt of Rp
2.75 billion ($275 million) is not included in the Cemex parent viewpoint capital budget.
58RP19,686,2033257.0
)01(059,547,6
gk
g)1(NOCFValue Terminal
WACC
5
-
5
Table 5: Semen Indonesias Remittance and Capital Budget: Parent Viewpoint (millions of Rp and US$)
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
Dividend Remittance
Dividends paid (RP)
0 0 560,423 555,757 651,450
Withholding tax @ 15%
0 0 (84,063) (83,364) (97,717)
Net dividend remitted (RP)
0 0 476,360 472,393 553,732
Net dividend remitted ($)
0 0 24 19 17
License Fees Remittance
Fees remitted
117,126 184,787 279,871 353,235 445,831
Withholding tax @ 5%
(5,856) (9,239) (13,994) (17,662) (22,292)
Net dividend remitted (RP)
111,270 175,547 265,877 335,573 423,539
Net license fees remitted ($)
8.8 11.0 13.2 13.2 13.2
Debt Service Remittance
Promised interest paid ($)
82.5 69.0 54.1 37.8 19.8
Withholding tax @ 10%
(8.25) (6.90) (5.41) (3.78) (1.98)
Net interest remitted ($)
74.3 62.1 48.7 34.0 17.8
Principal payments remitted
($) 135.1 148.6 163.5 179.9 197.8
Capital Budget: Parent Viewpoint
(US$ million)
Dividends
0.0 0.0 23.7 18.6 17.3
License fees
8.8 11.0 13.2 13.2 13.2
Debt service
209.4 210.7 212.2 213.9 215.7
Total
218.2 221.8 249.1 245.7 246.2
Initial Investment (1,925)
Terminal Value
614.66
Free Cash Flow (FCF) (1,925) 218.2 221.8 249.1 245.7 860.8
NPV @ 17.98% (925.62)
IRR -1.84%
In order to evaluate the projects cash flows that are returned to the parent company, Cemex must discount these at the corporate cost of capital. If Cemex were
undertaking an investment of the same relative degree of risk of the firm itself, a simple
discount rate of 11.98% might me adequate. Cemex, however, requires new investment to
yield an additional 6% over the cost of capital for international projects. The discount rate
for Semen Indonesias cash flows repatriated to Cemex will therefore be discounted at 11.98% + 6%, or 17.98%. From the parent viewpoint capital budgeting, it is indicated a
negative NPV of US$925.6 million with IRR -1.84%. Based on this result yhis
investment is unacceptable from the parents viewpoint. Multinational firm should invest only if they can earn a risk-adjusted return greater
than locally based competitors can earn on the same project. If they are unable to earn
superior returns on foreign projects, their stockholders would be better off buying shares
in local firms, where possible, and letting those companies carry out the local projects.
-
6
Most firms appear to evaluate foreign projects from both parent and project NPV and the
overall effect on consolidated earning of the firm. For foreign projects, must adjust for
agency cost and foreign exchange rate risks and costs.
B. KEY ISSUES Cemex was using traditional capital budgeting for considering expansion in
Indonesia. From traditional capital budgeting, Cemex got negative NPV and IRR that is
less than WACC, not only from project viewpoint but also from parent viewpoint. These
calculations meant the investment should be rejected. Is there any wrong assumption that
Cemex use?
Cemex was considering expansion to Indonesia yet Cemex did not consider the
additional risk or sensitivity analysis from both project viewpoint and parent viewpoint.
From project viewpoint, sensitivity analysis could be measured from foreign exchange
risk and other sensitivity variable such as the capacity utilization rate. Furthermore, from
parent viewpoint, the additional risk can be measured in at least two ways, adjusting the
discount rates or adjusting the cash flows. What will happen if Cemex considers these
additional risks?
C. ALTERNATIVE SOLUTIONS 1. Changing in Foreign Exchange Rate
Cemex should consider additional risks for both project viewpoint and parent
viewpoint. Cemex should consider whether if the rate of rupiah was depreciated or
appreciated. We try to make some estimation based on this consideration, rupiah
depreciate and appreciate.
a. Rupiah depreciate When the rate of rupiah depreciation were greater than US dollar at the PPP it
would make the assumed cash flows to Cemex worth less in dollars and the cheaper
rupiah made Semen Indonesia more competitive. It will happen caused by cash flow of
Semen Indonesia both cash inflows (export to Taiwan) and outflows (imported
components from parent company) are denominated in foreign currencies. Rupiah
depreciation would make higher inflation, so we would like to forecast the capital budget
with Indonesia inflation rate 40% (>30%). And the result is capital budget have the
negative NPV of Rp -6,435,034 and IRR of 24.5%, compared to 36.06%. This result
shows that the project should be rejected.
b. Rupiah appreciate Rupiah appreciates because of the decreasing of inflation rate. For this estimation,
we assume that inflation Indonesia decrease 10% or become 20%, inflation America stays
the same or 3%, WACC for project is 30.45% and 17.98% for parent. Based on these
assumptions, we try to estimate NPV and IRR for both project viewpoint and parent view
point. For project viewpoint, we got a negative NPV of Rp 12,126,108 million and IRR
6.1% that is less than WACC. And for parent viewpoint, we got a negative NPV of
$921.83 million with a negative IRR 1.65%. Based on this estimation, we can assume that
this investment should be rejected.
c. Real Option We can find the NPV and IRR based on the financial assumptions. When the NPV
value is negative, for example $-614.710 it mean that the project must be rejected. In this
-
7
session, we use several assumptions, whether we got changes on inflation rate or at
capacity amount.
When the inflation rate is assumed very high than 30% like 40%. The NPV value is
($6,435,034). So that when inflation rate higher to 40% and capacity volume of sales
increased became 12,000 on year 1, then 14,000 on year 2, then 16,000 in year 3-5, the
NPV value is still negative ($-614.710).
And if inflation rate is still on 30% but we changes on the capacity as telling above,
it shown at exhibit 4 and we can see that NPV value is ($4,650,934). It is better than cash
flow without changes on capacity but it still got negative value and the project has to
reject.
Figure 2: Real Option for Changing in Foreign Exchange Rate
Actually we dont know exactly the probability so we assume that the probability is about 33.3% each inflation rate (we divided into 40%, 30% and 20% without change on
capacity). Based on those analyses, the total NPV is Rp -9,325,532. When the inflation
rate going higher or lower, but NPV value is still negative. From these analyses we can
conclude that the project still must be rejected because the NPV is still negative.
2. Changing in Capacity Furthermore, we try to estimate NPV and IRR for project and parent by increasing
the capacity utilization rate. We assume that capacity for year 1 is 50%, year 2 is 60%,
year 3 is 70%, year 4 is 80%, and year 5 is 90%. We use the same inflation rate from the
case, 30%. Based on this assumption, we got the results of the capital budget from the
project viewpoint indicate a negative NPV of Rp -4,677,058 million and an IRR of only
25.4%, compared to the 33.257 % cost of capital. Even we optimist with the condition is
different, which means that the production capacity is higher than that so NPV will be
positive. But this projects NPV is still negative and would not acceptable. Then we use probability 50% on each condition (project of 30% inflation rate and project of 30%
inflation rate plus change in capacity), the total NPV is Rp 7,060,259. The project still must be rejected.
Project p=33,3%
p=33,3%
p=33,3%
Inflation rate 40%
Inflation rate 30%
NPV= Rp -6,435,034
NPV= Rp -9,443,460
NPV= Rp -12,126,108
Total NPV = (0,333 x Rp -6,435,034) + (0,333 x Rp -9,443,460) + (0,333 x Rp -
12,126,108)
= Rp -9,325,532
Inflation rate 20%
-
8
Figure 3: Real Option for Changing in Capacity
3. Real Market Condition From inflation rate data on the appendix, we are assuming that the Indonesian
inflation rate is expected to normalize. Therefore, we are using inflation rate decrease in
30% every year. Based on IMF data, Indonesian inflation rate in 1998 was 77.54% and
we are assuming that it is expected to normalize, so it will decrease into 54.28% then
37.99% in year 2000. While the inflation rate of United States is expected 2%/year with
Indonesian Rupiah exchange rate Rp 10,375 against U.S dollar. Therefore, changing in
the inflation rate will affect in Indonesian Rupiah exchange rate against U.S dollars.
Cemex allocated production capacity was 20,000 mmt/y, but it would not
maximizing the production capacity. It only used 40% from maximum capacity in year 1.
Cemex can use 50% from maximum production capacity in year 1 and it capacity will
increase 10%/year. Thus, Cemex production capacity is 60% in year 2, 70% in year 3,
80% in year 4, and 90% in year 5. We are assuming that Cemex has increased in export
sales because one of Cemex purpose to build plant in Indonesia was global expansion
especially in Southeast Asia market. We believe that the plant can operate at optimum
capacity. Then we used the same additional expenses include license fees, general
administrative expenses and depreciation as the case assumed. We also build this parent
view point capital budget. Dividends are not distributed in the first and second year but it
will distribute at a 50% rate in the year 3-5. Dividends will be charged a 15% withholding
tax, 10% interest payments and 5% license fees. This is illustrated in the Appendix 5
which shows all incremental earnings to Cemex from the prospective investment project.
Based on World Bank data, the components of cost of capital will be changed in
accordance with market condition. The components of cost of capital will describe in the
appendix. We found that the new WACC or WACC adjusted is 16.26% from parent
viewpoint and 46.87% from project viewpoint. The new WACC or WACC adjusted and
exchange rate will affect in free cash flow (FCF) and capital budgets (NPV and IRR) for
Cemex. Based on our calculation, we found that NPV is Rp -3,983,785 million and IRR is
37.7% form project viewpoint. This negative NPV indicates that Cemex should reject this
project. An IRR calculation is less that cost of capital 45.29%, so this project is not
acceptable (reject) from project viewpoint. While NPV and IRR from parent viewpoint
also rejected because of NPV has negative value and IRR less than cost of capital.
Project
p=50%
p=50%
Pesimist NPV= Rp -9,443,460
NPV= Rp -4,677,058
Total NPV = (0.5 x Rp -9,443,460) +(0.5 x Rp -4,677,058) = Rp -7,060,259
Optimist
-
9
Therefore, using the real inflation rate and cost of capital data, this project is not
acceptable. Cemex should not build plant and equipment in Indonesia.
D. RECOMMENDATION From all of our estimate with sensitivity analysis, this project should be rejected.
We adjusts increase and decrease in inflation rate, the project should not acceptable. We
also adjusts the sales volume into 50%-90%, but still the NPV is negative and IRR still
less than WACC. And we adjust the NPV and IRR by using real market condition, the
result stays the same, NPV still negative and IRR still less than WACC. This investment
could not applied in Indonesia and also the timing of investment was not in good
condition because Indonesia was suffering crisis during 1997-1998.
If Cemex really want to make a greenfield investment in Indonesia, there are
several recommendations that we can give for Cemex:
1. Cemex should use optimist assumption for calculating capital budgeting, both project viewpoint and parent viewpoint.
2. Cemex should use Rupiah for the all debt. Cemex use US dollar as functional currency, so the all revenue will be in US Dollar. At that time Rupiah was
depreciated, Cemex will get more Rupiahs if Cemex converted US Dollar to Rupiah.
3. In 1998, Indonesia faced economic crisis, but the crisis will not last forever. Cemex should make assumption that crisis and hyperinflations are expected to normalize.
E. BIBLIOGRAPHY
Saphiro, Alan C. (2010). Multinational Financial Management 9th
Edition. John Wiley
& Sons, Inc.
http://www.bps.go.id/aboutus.php?inflasi=1
http://www.usinflationcalculator.com/inflation/historical-inflation-rates/
http://www.imf.org/external/pubs/ft/weo/2013/02/weodata/weorept.aspx?sy=1997&ey=2
003&scsm=1&ssd=1&sort=country&ds=.&br=1&pr1.x=85&pr1.y=8&c=536%2C111&
s=PPPEX%2CPCPI%2CPCPIPCH%2CPCPIE%2CPCPIEPCH&grp=0&a=
http://data.worldbank.org/indicator/FR.INR.RINR?page=3
-
10
Appendix
Exhibit 1: Semen Indonesia Debt Service Schedule
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
Indonesian Loan @ 35% for 8
years (million Rp)
Loan Principal 2,750,000 2,654,061 2,524,543 2,349,694 2,113,648 1,794,985
Interest Payment
(962,500) (928,921) (883,590) (822,393) (739,777)
Principal Payment (95,939) (129,518) (174,849) (236,046) (318,662)
Total Payment (1,058,439) (1,058,439) (1,058,439) (1,058,439) (1,058,439)
Cemex Loan @ 10% for 5 years
(million US$)
Loan Principal 825 689.9 541.2 377.7 197.8 0.0
Interest Payment
(82.5) (69.0) (54.1) (37.8) (19.8)
Principal Payment
(135.1) (148.6) (163.5) (179.9) (197.8)
Total Payment
(217.6) (217.6) (217.6) (217.6) (217.6)
Cemex loan converted to Rp
(million Rp)
Scheduled @
Rp10,000/$
Interest Payment
(825,000) (689,867) (541,221) (377,710) (197,848)
Principal Payment
(1,351,329) (1,486,462) (1,635,108) (1,798,619) (1,978,481)
Total Payment
(2,176,329) (2,176,329) (2,176,329) (2,176,329) (2,176,329)
Actual (@ current
spot rate)
Interest Payment
(1,041,262) (1,098,949) (1,088,160) (958,480) (633,669)
Principal Payment
(1,705,561) (2,367,915) (3,287,494) (4,564,190) (6,336,691)
Total Payment
(2,746,823) (3,466,864) (4,375,654) (5,522,670) (6,970,360)
Cash flow in RP on Cemex Loan
(million RP)
Total Actual Cash
Flow 8,250,000 (2,746,823) (3,466,864) (4,375,654) (5,522,670) (6,970,360)
IRR of cash flow: 39%
Foreign Exchange Losses on Cemex Loan (million
RP)
Forex Loss on
Interest:
(216,262) (409,082) (546,940) (580,770) (435,821)
Forex Loss on
Principal:
(354,232) (881,453) (1,652,385) (2,765,571) (4,358,210)
Total Forex Loss on
Debt: (570,494) (1,290,535) (2,199,325) (3,346,341) (4,794,031)
Exhibit 2: Semen Indonesia Pro Forma Income Statement
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
Sales Volume
10,000 12,000 14,000 16,000 18,000
Sales Price ($)
58 58 58 58 58
Sales Price (RP) 732,039 923,933 1,166,128 1,471,813 1,857,627
-
11
Total Revenue ('000)
7,320,388 11,087,190 16,325,798 23,549,001 33,437,295
Cash costs ('000)
(1,150,000) (1,794,000) (2,720,900) (4,042,480) (5,912,127)
Additional production costs ('000) (200,000) (312,000) (473,200) (703,040) (1,028,196)
Loading costs ('000)
(252,427) (393,786) (597,243) (887,332) (1,297,723)
Shipping costs ('000) (1,262,136) (1,968,932) (2,986,214) (4,436,660) (6,488,616)
Total
(2,864,563) (4,468,718) (6,777,556) (10,069,512) (14,726,662)
Gross Profit
4,455,825 6,618,472 9,548,241 13,479,489 18,710,633
License Fees
(146,408) (221,744) (326,516) (470,980) (668,746)
General & Admin
Expenses
(585,631) (997,847) (1,632,580) (2,590,390) (4,012,475)
EBITDA
3,723,786 5,398,881 7,589,146 10,418,119 14,029,412
Depreciation &
Amortization
(1,760,000) (1,760,000) (1,760,000) (1,760,000) (1,760,000)
EBIT
1,963,786 3,638,881 5,829,146 8,658,119 12,269,412
Interest on Cemex Debt
(825,000) (689,867) (541,221) (377,710) (197,848)
Forex Losses on Debt
(570,494) (1,290,535) (2,199,325) (3,346,341) (4,794,031)
Interest on Local Debt
(962,500) (928,921) (883,590) (822,393) (739,777)
EBT
(394,208) 729,557 2,205,010 4,111,675 6,537,756
Income taxes (30%)
0 0 0 1,995,610 1,961,327
Net Income (RP)
(394,208) 729,557 2,205,010 2,116,064 4,576,429
Net Income ($ million) (31) 46 110 83 143
Exhibit 3: Rupiah Depreciates
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10.000 13.592 18.475 25.111 34.132 46.393
Sales Volume
8.000 10.000 12.000 12.000 12.000
Sales Price ($)
58 58 58 58 58
Sales Price (RP) 788.350 1.071.543 1.456.466 1.979.663 2.690.804
Total Revenue ('000)
6.306.796 10.715.430 17.477.595 23.755.954 32.289.647
Cash costs ('000)
(920.000) (1.610.000) (2.704.800) (3.786.720) (5.301.408)
Additional production
costs ('000)
(160.000) (280.000) (470.400) (658.560) (921.984)
Loading costs ('000)
(217.476) (380.583) (639.379) (895.130) (1.253.182)
Shipping costs ('000) (1.087.379) (1.902.913) (3.196.893) (4.475.650) (6.265.911)
Total
(2.384.854) (4.173.495) (7.011.472) (9.816.061) (13.742.485)
Gross Profit
3.921.942 6.541.935 10.466.123 13.939.894 18.547.162
License Fees
(126.136) (214.309) (349.552) (475.119) (645.793)
General & Admin
Expenses
(504.544) (964.389) (1.747.760) (2.613.155) (3.874.758)
EBITDA
3.291.262 5.363.238 8.368.812 10.851.620 14.026.611
Depreciation &
Amortization
(1.760.000) (1.760.000) (1.760.000) (1.760.000) (1.760.000)
EBIT
1.531.262 3.603.238 6.608.812 9.091.620 12.266.611
-
12
Interest on Cemex Debt
(825.000) (689.867) (541.221) (377.710) (197.848)
Forex Losses on Debt
(781.788) (1.844.413) (3.288.757) (5.251.943) (7.920.352)
Interest on Local Debt
(962.500) (928.921) (883.590) (822.393) (739.777)
EBT
(1.038.026) 140.037 1.895.244 2.639.573 3.408.635
Income taxes (30%)
0 42.011 299.176 1.091.048 1.022.590
Net Income (RP)
(1.038.026) 98.026 1.596.067 1.548.525 2.386.044
Net Income ($ million) (76) 5 64 45 51
Capital Budget: Cemex Indonesia (million RP) Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10.000 13.592 18.475 25.111 34.132 46.393
EBITDA
3.291.262 5.363.238 8.368.812 10.851.620 14.026.611
Recalculated taxes
(@30%)
(987.379) (1.608.971) (2.510.644) (3.255.486) (4.207.983)
Net Operating
cashflow
2.303.883 3.754.266 5.858.168 7.596.134 9.818.628
Additions to NWC
(240.670) (139.028) (436.049) (289.776) (625.314)
Initial Investment (22.000.000)
Terminal Value
27.228.531
Free Cash Flow (FCF) (22.000.000) 2.063.213 3.615.238 5.422.119 7.306.358 36.421.845
NPV @ 36,06% (Rp6.435.034)
IRR 24,5%
Semen Indonesias Remittance and Capital Budget: Parent Viewpoint (million RP & million US$)
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10.000 12.621 15.930 20.106 25.376 32.028
Dividend Remittance
Dividends paid (RP)
0 0 798.034 774.263 1.193.022
Withholding tax @ 15%
0 0 (119.705) (116.139) (178.953)
Net dividend remitted (RP)
0 0 678.329 658.123 1.014.069
Net dividend remitted ($)
0 0 34 26 32
License Fees Remittance
Fees remitted
126.136 214.309 349.552 475.119 645.793
Withholding tax @ 5%
(6.307) (10.715) (17.478) (23.756) (32.290)
Net dividend remitted (RP)
119.829 203.593 332.074 451.363 613.503
Net license fees remitted ($)
9,5 12,8 16,5 17,8 19,2
Debt Service Remittance
Promised interest paid ($)
82,5 69,0 54,1 37,8 19,8
Withholding tax @ 10%
(8,25) (6,90) (5,41) (3,78) (1,98)
Net interest remitted ($)
74,3 62,1 48,7 34,0 17,8
Principal payments remitted ($)
135,1 148,6 163,5 179,9 197,8
Capital Budget: Parent
Viewpoint (US$ million)
-
13
Dividends
0,0 0,0 33,7 25,9 31,7
License fees
9,5 12,8 16,5 17,8 19,2
Debt service
209,4 210,7 212,2 213,9 215,7
Total
218,9 223,5 262,5 257,6 266,5
Initial Investment (1.925)
Terminal Value
586,91
Free Cash Flow (FCF) (1.925) 218,9 223,5 262,5 257,6 853,4
NPV @ 17.98% (912,79)
IRR -2%
Exhibit 4: Rupiah Appreciates
Cost of Capital: Cemex Indonesia
Risk-free rate 33% Cemex Indonesia 1
Credit Premium 2%
Equity premium 7%
Cost of debt in Rupiah 35%
Cost of equity 40%
Cost of debt, after-tax 24.50%
% equity 50%
Cost of US$ debt 28%
Cost of US$ debt, after-tax 19.71%
% debt 50% WACC 30.4533%
Capital Budget: Cemex Indonesia (million RP)
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 11,650 13,573 15,814 18,424 21,464
EBITDA
2,666,796 3,708,909 4,936,898 5,457,526 6,009,723
Recalculated taxes
@30%
(800,039) (1,112,673) (1,481,070) (1,637,258) (1,802,917)
Net Operating cash
flow
1,866,757 2,596,237 3,455,829 3,820,268 4,206,806
Additions to NWC
(240,670) (139,028) (436,049) (289,776) (625,314)
Initial Investment (22,000,000)
Terminal Value
13,813,958
Free Cash Flow (FCF) (22,000,000) 1,626,087 2,457,209 3,019,780 3,530,492 17,395,450
NPV @30.4533% ($12,126,108)
IRR 6.1%
Capital Budget: Cemex Indonesia (million RP & million US$)
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
Dividend Remittance
Dividends paid (RP)
0 0 798,034 774,263 1,193,022
Withholding tax @ 15%
0 0 (119,705) (116,139) (178,953)
Net dividend remitted (RP)
0 0 678,329 658,123 1,014,069
Net dividend remitted ($)
0 0 34 26 32
License Fees Remittance
Fees remitted
126,136 214,309 349,552 475,119 645,793
Withholding tax @ 5%
(6,307) (10,715) (17,478) (23,756) (32,290)
-
14
Net dividend remitted (RP)
119,829 203,593 332,074 451,363 613,503
Net license fees remitted ($)
9.5 12.8 16.5 17.8 19.2
Debt Service Remittance
Promised interest paid ($)
82.5 69.0 54.1 37.8 19.8
Withholding tax @ 10%
(8.25) (6.90) (5.41) (3.78) (1.98)
Net interest remitted ($)
74.3 62.1 48.7 34.0 17.8
Principal payments remitted ($)
135.1 148.6 163.5 179.9 197.8
Capital Budget: Parent
Viewpoint (US$ million)
Dividends
0.0 0.0 33.7 25.9 31.7
License fees
9.5 12.8 16.5 17.8 19.2
Debt service
209.4 210.7 212.2 213.9 215.7
Total
218.9 223.5 262.5 257.6 266.5
Initial Investment (1,925)
Terminal Value
586.91
Free Cash Flow (FCF) (1,925) 218.9 223.5 262.5 257.6 853.4
NPV @ 17.98% (912.79)
IRR -2%
Exhibit 5: Changing in Capacity
Semen Indonesia Pro Forma Income Statement
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
Sales Volume
10,000 12,000 14,000 16,000 18,000
Sales Price ($)
58 58 58 58 58
Sales Price (RP) 732,039 923,933 1,166,128 1,471,813 1,857,627
Total Revenue ('000)
7,320,388 11,087,190 16,325,798 23,549,001 33,437,295
Cash costs ('000)
(1,150,000) (1,794,000) (2,720,900) (4,042,480) (5,912,127)
Additional production costs ('000) (200,000) (312,000) (473,200) (703,040) (1,028,196)
Loading costs ('000)
(252,427) (393,786) (597,243) (887,332) (1,297,723)
Shipping costs ('000) (1,262,136) (1,968,932) (2,986,214) (4,436,660) (6,488,616)
Total
(2,864,563) (4,468,718) (6,777,556) (10,069,512) (14,726,662)
Gross Profit
4,455,825 6,618,472 9,548,241 13,479,489 18,710,633
License Fees
(146,408) (221,744) (326,516) (470,980) (668,746)
General & Admin
Expenses
(585,631) (997,847) (1,632,580) (2,590,390) (4,012,475)
EBITDA
3,723,786 5,398,881 7,589,146 10,418,119 14,029,412
Depreciation &
Amortization
(1,760,000) (1,760,000) (1,760,000) (1,760,000) (1,760,000)
EBIT
1,963,786 3,638,881 5,829,146 8,658,119 12,269,412
Interest on Cemex
Debt
(825,000) (689,867) (541,221) (377,710) (197,848)
Forex Losses on Debt
(570,494) (1,290,535) (2,199,325) (3,346,341) (4,794,031)
Interest on Local Debt
(962,500) (928,921) (883,590) (822,393) (739,777)
-
15
EBT
(394,208) 729,557 2,205,010 4,111,675 6,537,756
Income taxes (30%)
0 0 0 1,995,610 1,961,327
Net Income (RP)
(394,208) 729,557 2,205,010 2,116,064 4,576,429
Net Income ($
million) (31) 46 110 83 143
Capital Budget: Cemex Indonesia (million RP)
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
EBITDA
3,723,786 5,398,881 7,589,146 10,418,119 14,029,412
Recalculated taxes
(@30%)
(1,117,136) (1,619,664) (2,276,744) (3,125,436) (4,208,824)
Net Operating cash
flow
2,606,650 3,779,217 5,312,402 7,292,683 9,820,588
Additions to NWC
(240,670) (139,028) (436,049) (289,776) (625,314)
Initial Investment (22,000,000)
Terminal Value
29,529,388
Free Cash Flow
(FCF) (22,000,000) 2,365,980 3,640,189 4,876,353 7,002,907 38,724,662
NPV @ 33.257% ($4,677,058)
IRR 25.4%
Capital Budget: Cemex Indonesia (million RP & million US$)
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
Dividend Remittance
Dividends paid (RP)
0 0 1,102,505 1,058,032 2,288,215
Withholding tax @ 15%
0 0 (165,376) (158,705) (343,232)
Net dividend remitted
(RP)
0 0 937,129 899,327 1,944,982
Net dividend remitted ($)
0 0 47 35 61
License Fees Remittance
Fees remitted
146,408 221,744 326,516 470,980 668,746
Withholding tax @ 5%
(7,320) (11,087) (16,326) (23,549) (33,437)
Net dividend remitted
(RP)
139,087 210,657 310,190 447,431 635,309
Net license fees remitted
($)
11.0 13.2 15.4 17.6 19.8
Debt Service Remittance
Promised interest paid ($)
82.5 69.0 54.1 37.8 19.8
Withholding tax @ 10%
(8.25) (6.90) (5.41) (3.78) (1.98)
Net interest remitted ($)
74.3 62.1 48.7 34.0 17.8
Principal payments
remitted ($)
135.1 148.6 163.5 179.9 197.8
Capital Budget: Parent Viewpoint
(US$ million)
-
16
Dividends
0.0 0.0 46.6 35.4 60.7
License fees
11.0 13.2 15.4 17.6 19.8
Debt service
209.4 210.7 212.2 213.9 215.7
Total
220.4 224.0 274.3 266.9 296.2
Initial Investment (1,925)
Terminal Value
921.98
Free Cash Flow (FCF) (1,925) 220.4 224.0 274.3 266.9 1,218.2
NPV @ 17.98% (739.57)
IRR 3.54%
Exhibit 5: Real Market Condition
Indonesian Inflation Rate
Year 0 1 2 3 4 5
Changing 598,54% -30,00% -30,00% -30,00% -30,00% -30,00%
Inflation Rate 77,54% 54,28% 37,99% 26,60% 18,62% 13,03%
Calculation of WACC from Parent Viewpoint Information Calculation Result
Risk-free rate 9.5%
Credit spread 2%
Cost of debt 11.5%
Cost of debt, after-tax 11.5%*(1 0.35) 7.48%
Debt proportion 40%
Cemex Beta 1.5
Equity premium 8.41%
Cost of equity (9.5% + 8.41%)*1.5 22.12%
Equity proportion 60%
WACC = (0.4)*(7.48%) + (0.6*22.12%) = 16.26%
Calculation of WACC from Parent Viewpoint Information Calculation Result
Risk-free rate
48.28%
Credit Premium
2%
Cost of debt in Rupiah
50.28%
Cost of debt, after-tax 50.28%*(1 - 0.3) 35.2%
Cost of debt, after tax to be paid (35.2%*0.25) 8.79%
Cost of US$ debt
50.49%
Cost of US$ debt, after-tax 50.49%*(1 0.3) 35.34%
Cost of debt, after tax to be paid (35.34%*0.75) 26.518%
Total Cost of debt 9.79% + 26.51% 35.31%
Debt Proportion
50%
Cemex Indonesia of beta
1
Equity premium (58.44% - 48.28%) 10.16%
Cost of equity (10.16% + 48.28%)*1 58.44%
Equity Proportion
50%
WACC = (0.5*35.31%) + (0.5*58.44%) = 46.87%
Semen Indonesias Debt Service Schedules and Foreign Exchange Losses (millions of Rp and US$) Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
-
17
Spot Rate (Rp/$) 10,375 15,692 21,230 26,349 30,642 33,956
Indonesian Loan @ 35% for 8
years (million Rp)
Loan Principal 2,750,000 2,654,061 2,524,543 2,349,694 2,113,648 1,794,985
Interest Payment (962,500) (928,921) (883,590) (822,393) (739,777)
Principal Payment (95,939) (129,518) (174,849) (236,046) (318,662)
Total Payment (1,058,439) (1,058,439) (1,058,439) (1,058,439) (1,058,439)
Cemex Loan @ 10% for 5 years
(million US$)
Loan Principal 825 689,9 541,2 377,7 197,8 0,0
Interest Payment (82,5) (69,0) (54,1) (37,8) (19,8)
Principal Payment (135,1) (148,6) (163,5) (179,9) (197,8)
Total Payment (217,6) (217,6) (217,6) (217,6) (217,6)
Cemex loan converted to Rp
(million Rp)
Scheduled @ Rp10,000/$
Interest Payment (825,000) (689,867) (541,221) (377,710) (197,848)
Principal Payment (1,351,329) (1,486,462) (1,635,108) (1,798,619) (1,978,481)
Total Payment (2,176,329) (2,176,329) (2,176,329) (2,176,329) (2,176,329)
Actual (@ current spot rate)
Interest Payment (1,294,619) (1,464,577) (1,426,066) (1,157,364) (671,806)
Principal Payment (2,120,553) (3,155,736) (4,308,356) (5,511,256) (6,718,058)
Total Payment (3,415,172) (4,620,313) (5,734,422) (6,668,619) (7,389,864)
Cash flow in RP on Cemex Loan
(million RP)
Total Actual Cash
Flow
8,250,000 (3,415,172) (4,620,313) (5,734,422) (6,668,619) (7,389,864)
IRR of cash flow: 50%
Foreign Exchange Losses on
Cemex Loan (million RP)
Forex Loss on Interest: (469,619) (774,710) (884,845) (779,654) (473,958)
Forex Loss on
Principal:
(769,224) (1,669,274) (2,673,248) (3,712,637) (4,739,577)
Total Forex Loss on
Debt:
(1,238,843) (2,443,984) (3,558,093) (4,492,290) (5,213,535)
Semen Indonesia Pro Forma Income Statement
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,375 15,693 21,230 26,350 30,643 33,957
Sales Volume
10,000 12,000 14,000 16,000 18,000
Sales Price ($)
58 58 58 58 58
Sales Price (RP) 910,176 1,231,326 1,528,293 1,777,314 1,969,508
Total Revenue ('000)
9,101,764 14,775,910 21,396,098 28,437,032 35,451,151
Cash costs ('000) (1,150,000) (1,752,600) (2,012,500) (2,244,800) (2,463,300)
Additional production costs ('000) (200,000) (304,800) (350,000) (390,400) (428,400)
Loading costs ('000) (313,854) (524,800) (782,728) (1,071,514) (1,375,882)
Shipping costs ('000)
(1,569,270) (2,623,998) (3,913,641) (5,357,571) (6,879,411)
-
18
Total
(3,233,124) (5,206,197) (7,058,870) (9,064,285) (11,146,993)
Gross Profit
5,868,640 9,569,713 14,337,228 19,372,747 24,304,158
License Fees
(182,035) (295,518) (427,922) (568,741) (709,023)
General & Admin
Expenses
(728,141) (1,329,832) (2,139,610) (3,128,074) (4,254,138)
EBITDA
4,958,464 7,944,363 11,769,696 15,675,932 19,340,997
Depreciation &
Amortization
(1,760,000) (1,760,000) (1,760,000) (1,760,000) (1,760,000)
EBIT
3,198,464 6,184,363 10,009,696 13,915,932 17,580,997
Interest on Cemex Debt
(825,000) (689,867) (541,221) (377,710) (197,848)
Forex Losses on Debt
(1,238,918) (2,443,965) (3,558,271) (4,492,673) (5,213,841)
Interest on Local Debt
(962,500) (928,921) (883,590) (822,393) (739,777)
EBT
172,046 2,121,610 5,026,614 8,223,156 11,429,531
Income taxes (30%)
51,614 636,483 2,196,081 4,663,028 3,428,859
Net Income (RP)
120,432 1,485,127 2,830,533 3,560,128 8,000,672
Net Income ($ million) 8 70 107 116 236
Capital Budget: Cemex Indonesia (million RP & million US$) Project Viewpoint
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,375 15,693 21,230 26,350 30,643 33,957
EBITDA
4,958,464 7,944,363 11,769,696 15,675,932 19,340,997
Recalculated taxes
(@30%)
(1,487,539) (2,383,309) (3,530,909) (4,702,780) (5,802,299)
Net Operating cashflow
3,470,925 5,561,054 8,238,787 10,973,153 13,538,698
Additions to NWC
(240,670) (139,028) (436,049) (289,776) (625,314)
Initial Investment (22,000,000)
Terminal Value
40,709,318
Free Cash Flow (FCF) (22,000,000) 3,230,255 5,422,026 7,802,738 10,683,377 53,622,702
NPV @ 45,29% (Rp3,983,785)
IRR 37.7%
Capital Budget from Parent Viewpoint
Project Year Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Spot Rate (Rp/$) 10,000 12,621 15,930 20,106 25,376 32,028
Dividend Remittance
Dividends paid (RP)
0 0 1,415,267 1,780,064 4,000,336
Withholding tax @ 15%
0 0 (212,290) (267,010) (600,050)
Net dividend remitted (RP)
0 0 1,202,977 1,513,055 3,400,286
Net dividend remitted ($)
0 0 60 60 106
License Fees Remittance
Fees remitted
182,035 295,518 427,922 568,741 709,023
Withholding tax @ 5%
(9,102) (14,776) (21,396) (28,437) (35,451)
Net dividend remitted (RP)
172,934 280,742 406,526 540,304 673,572
Net license fees remitted ($)
13,7 17,6 20,2 21,3 21,0
-
19
Debt Service Remittance
Promised interest paid ($)
82,5 69,0 54,1 37,8 19,8
Withholding tax @ 10%
(8,25) (6,90) (5,41) (3,78) (1,98)
Net interest remitted ($)
74,3 62,1 48,7 34,0 17,8
Principal payments remitted
($)
135,1 148,6 163,5 179,9 197,8
Capital Budget: Parent Viewpoint
(US$ million)
Dividends
0,0 0.0 59,8 59.6 106.2
License fees
13.7 17.6 20.2 21.3 21.0
Debt service
209.4 210.7 212.2 213.9 215.7
Total
223.1 228.4 292.3 294.8 342.9
Initial Investment (1,925)
Terminal Value
614,70
Free Cash Flow (FCF) (1,925) 223.1 228.4 292.3 294.8 957.6
NPV @ 22.26% (947,35)
IRR 0.97%