CARLSBAD MUNICIPAL SCHOOL DISTRICT FACILITIES MASTER...

132
CARLSBAD MUNICIPAL SCHOOL DISTRICT FACILITIES MASTER PLAN 2014-2019 Volume 1

Transcript of CARLSBAD MUNICIPAL SCHOOL DISTRICT FACILITIES MASTER...

CARLSBAD MUNICIPAL SCHOOL

DISTRICTFACILITIES MASTER

PLAN

2014-2019Volume 1

i

Facili es Master Plan 2014 -2019 Carlsbad Municipal Schools

Table of Contents Carlsbad, New Mexico

1.0 Goals / Process - Volume - 1

1.1 Goals ........................................................................................................................ 1|1

1.2 Process .........................................................................................................................1|8

1.3 Acronyms/Defi ni ons .................................................................................................. 1|17

2.0 Exis ng and Projected Condi ons

2.1 Programs ....................................................................................................................2|1

2.2 Sites/Facili es .................................................................................................................2|7

2.3 District Growth .............................................................................................................2|15

2.4 Enrollment ..................................................................................................................2|34

2.5 U liza on & Capacity ...................................................................................................2|54

2.6 Technology ..................................................................................................................2|66

2.7 Energy Management Program ......................................................................................2|69

2.8 Capital Funding .............................................................................................................2|77

3.0 Capital Improvement Plan

3.1 Total Capital Needs .........................................................................................................3|1

3.2 Priori za on Process ...................................................................................................3|12

3.3 Capital Plan ..................................................................................................................3|25

4.0 Master Plan Support Material - Volume 2

4.0 School Site & Facili es ....................................................................................................4|1

PRE-K / KINDERGARTEN SCHOOLS

Dr EM Smith Pre School ..............................................................................................4|4 (Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Early Childhood Educa on Center ............................................................................4|20 (Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

ELEMENTARY SCHOOLS

Cra Elementary School ...........................................................................................4|34 (Facility Information, Floor Plan, Site Information, Facility Excutive Summary

Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Acknowledgements

ii

Facili es Master Plan 2014 -2019 Carlsbad Municipal Schools

Table of Contents Carlsbad, New Mexico

Hillcrest Elementary School ................................................................................... 4|50

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Joe Stanley Smith Elementary School .................................................................... 4|67

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Monterrey Elementary School ............................................................................... 4|81 (Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Pate Elementary School ......................................................................................... 4|96

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Pucke Elementary School ................................................................................. 4|112

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Riverside Elementary School ................................................................................ 4|127

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

Sunset Elementary School ................................................................................... 4|142

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

MIDDLE SCHOOLS

Alta Vista Middle School (6th Grade Academy) ................................................... 4|158

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

P.R. Leyva Middle School ..................................................................................... 4|178

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

HIGH SCHOOLS

Carlsbad High School .......................................................................................... 4|201

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

ALTERNATIVE/ CHARTER SCHOOLS

Eddy Alterna ve School ....................................................................................... 4|253

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, and Capital Improvement Needs)

iii

Facili es Master Plan 2014 -2019 Carlsbad Municipal Schools

Table of Contents Carlsbad, New Mexico

Jeff erson Montessori Charter School ................................................................... 4|269

(Facility Information, Floor Plan, Site Information, Facility Excutive Summary Report,Evaluation Summary, Capital Improvement Needs, and Utilization)

DISTRICT FACILITIES

Administra on/ Central Offi ce .................................................................................... 4|289

(Facility Information, Floor Plan, Site Information, Evaluation Summary, and Capital Improvement Needs)

Edison Special Educa on Center ................................................................................. 4|297

(Facility Information, Floor Plan, Site Information, Evaluation Summary, and Capital Improvement Needs)

Warehouse Facility ...................................................................................................... 4|305

(Facility Information, Floor Plan, Site Information, Evaluation Summary, and Capital Improvement Needs)

iv

Facili es Master Plan 2014 -2019 Carlsbad Municipal Schools

Carlsbad, New Mexico

Acknowledgements

Carlsbad Municipal School Board of Educa on:Dr. Doris Bruton Carleton, President Abel Montoya, Vice PresidentAndrew Harris, Board SecretarySteve West, MemberRon Singleton, Member

Facili es Advisory Commi ee Par cipantsCarlsbad Municipal School District Administra on:Gary Perkowski, SuperintendentKelli Barta, Director of Secondary Educa onLaVern Shan, Director of Elementary Educa on and Federal ProgramsDon Owen, Director of Opera ons Gene Bradley, Maintenance SupervisorLaura Garcia, Director of Finance

Carlsbad Municipal School District Administra ve Staff and Teachers:Tammy HealeyGerry Frye Andrea Molina Bill Gunkel Sandra WhiteTamara Faulk

Community Representa ves:Be e Anne Brantley Donnie Rodriguez Lisa Chavez Michelle RodriguezNick Mills Rachelle Thompson Stephanie Shumsky Yve e Mendoza

PSFA Representa ve:Brian Stephens, PSFA

Consultants:Denise A. Davis, Facility Planning AssociatesColleen Mar nez, Visions in PlanningMolly Smith, thinkSmart Planning

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 1 

 

 

1.1 Goals 

1.1.1 District Mission Statement 

The mission of the Carlsbad Board of Education is to create 

a  public  school  environment  which  meets  the  individual 

educational needs of all children regardless of their ability, 

ethnicity,  creed,  gender  or  social  standing.  We  are 

dedicated  and will provide  each  student  the opportunity 

to  develop  intellectually  emotionally,  physically,  and 

socially in a safe and orderly environment.1 

1.1.2 District Educational Goals 

Changes have occurred  in the way  instruction  is delivered 

to today’s students such as: lower class sizes (as mandated 

by  the  state);  the  addition  of  space  allocated  for  critical 

supplemental  instruction  such  as  reading,  English  as  a 

Second  Language,  and  special  education;  and  school 

choice  provided  to  families  in  the  community  through 

student transfer requests. 

 

The  following  educational  goals  are  established  by  the 

District.  Specifically, the District instructional program will 

be designed and  implemented  to provide  for at  least  the 

minimum instructional areas required by statute and shall 

include1:   

                                                            

1 CMSD website, www.edline.net/pages/Carlsbad_Municipal_Schools 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 2 

 

 

Skills in communication ‐ to include reading and 

language arts skills, including phonemic awareness, 

phonics, comprehension, grammar and writing. 

Skills in computation ‐ mathematics.     

Appreciation of the world of work.     

Pride of workmanship and skills for economic survival.   

Appreciation of the importance of physical fitness.   

Research and problem‐solving skills in science and 

mathematics.     

Ability to think analytically, critically, and 

independently.     

Skills in foreign or Native American language.     

Ability leading to citizen responsibility. 

Understanding and respect for our cultural heritage 

and history. 

Appreciation for the intrinsic value of education.  

Appreciation of the fine arts. 

Skills in the use of topographical and standard maps. 

Skills in technology.       

 

1.1.3 Decisions Affecting Future Educational Programs 

One of Carlsbad Municipal  Schools’  long  term  goals  is  to 

improve  educational  equity  and  opportunities  in  its 

facilities  districtwide.    The  district’s  goal  for  elementary 

schools  is  to  reduce overcrowding,  improve programs,  in 

operationally  efficient  facilities.    The  district  intends  to 

replace  seven  of  the  existing  schools  with  four  larger 

capacity elementary schools for 600 students each and to 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 3 

 

 

either  replace  or  renovate  with  an  addition  to  increase 

capacity  at  the  remaining  elementary  existing  school 

(Hillcrest) to create a STEM magnet elementary school that 

will accommodate the growing needs of the district in the 

future.     As of the 2014‐2015 school year, the District will 

create a  standalone 6th Grade Academy which will  affect 

P.R.  Leyva  Middle  School  and  Alta  Vista  Middle  Schools.  

The  Alta  Vista  location  will  become  the  new  6th  Grade 

Academy and all 7th and 8th graders will attend P.R. Leyva 

Middle  School.      At  the  high  school  level,  CMS  the  long 

term  goal  is  to  construct  a new  facility  for  the  9th  grade 

academy  to  provide  for  the  educational  program  that  is 

hindered in the current facility in addition to implementing 

the new early college program at NMSU in 2014/15. 

 

1.1.4 District Community Involvement Goals 

The  District  strives  to  involve  the  community  in  its 

educational process.   A primary  goal  as  indicated by  the 

District is to: 

Ensure parental and community trust and involvement 

through clear, open, and timely communication. 

 

In support of this goal the District has an established web‐

site  with  a  wealth  of  information  ranging  from  school 

calendars to detailed Board minutes.   

 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 4 

 

 

1.1.5 Facility Goals 

Facility  goals were developed during  the  FMP process  in 

order  to  guide  decision‐making.    Overall  principles  were 

developed; the principles and analysis were: 

 

Consolidate Elementary Schools, Build New, Higher 

Capacity Schools 

The District  has  considered  the  impact  of  building  larger 

schools  versus  expansion  of  current  school  facilities.    A 

primary  implication  is  the  decrease  in  operational  costs.  

Some of the benefits identified include: 

Improve Educational Programs 

A new facility provides the opportunities to better 

create school communities within the larger 

population and configure facilities in support of this 

educational concept. 

Impact to Staff  A prime goal will be the retention of staff; staff will 

only be decreased through attrition or staff will be 

re‐assigned to needed positions.  Staff is funded 

per student and not facility however, there is a 

concern that consolidation would result in staff 

reductions and was included in the discussion. 

A larger school will result in more efficient use of 

staff time which impacts ancillary staff.  Currently 

ancillary staff travels from school to school to 

provide services.  The typical travel time per day is 

30 minutes or more.  Having school‐based ancillary 

staff will provide better services to the students 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 5 

 

 

with increased accessibility to the staff and reduce 

if not eliminate travel time. 

New Schools vs. Old Schools with Renovation 

The expansion of each of the current schools is less 

desirable due to the age and condition of the 

facilities.  With the exception of Craft Elementary 

School (1920), all of the remaining elementary 

schools in the district were constructed in the 

1950’s with various additions over the years to 

accommodate growth.  Historically, the District has 

only passed GO Bonds of up to $7,500,000 and has 

relied on HB‐33 and SB‐9 to support maintenance 

and small construction projects.  The February 

2014 GO Bond for $60 Million is the largest in the 

District’s history. 

Expansion of the existing schools rather than 

consolidation and building new schools would 

mean that the old facilities would still require 

major renovation which when costs for renovation 

are included they fast approach that of a new 

facility.   

The safety  issues  identified during  the assessment 

will  be  rectified  with  the  design  of  the  new 

elementary facilities.  Traffic issues will be resolved, 

mechanical  will  provide  efficient  systems  that 

provide improved air quality, electrical will provide 

essential  outlets  (rather  than  cords  that  are 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 6 

 

 

sometimes  used  now),  security  will  be  greatly 

enhanced. 

The current sites are small and rely heavily on city 

streets to support student drop‐off/pick‐up and 

staff parking.  There are significant safety issues 

with the heavy volume of traffic at some of these 

schools.  The Master Plan has identified funding 

requirements for upgrades of the site 

infrastructure in an effort to improve these site 

issues if new schools are not constructed.   The 

new school projects will allow for the optimal 

design for site safety.  The larger sites will be used 

to consolidate schools while other schools will be 

developed on other school property nearby in 

order to increase the site areas. 

Impact to School Size and Cost Implications 

Replacing each school District‐wide rather than 

consolidation would result in additional 

construction costs.  Consider building two new 

schools vs. building one new school.  The PSFA 

Planning Guide recently revised Total Facility GSF 

to Adequacy.  Using these figures a 600 student 

school is 73,740 GSF vs. two schools of 300 

students at 41,112 GSF each or 82,224 GSF.  The 

estimated probable construction cost savings is 

about $1.8 million.  This also translates into 

reduced utility costs. 

 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 7 

 

 

Impact to Operations 

New facilities will not immediately have 

maintenance issues that impact HB‐33 and SB‐9 

funding due to warranties.  This allows these to be 

direct to needed projects at the district’s other 

facilities. 

 

Replace Portable Classrooms 

Portable  classrooms  will  be  replaced  with  permanent 

classrooms  unless  those  portable  classrooms  are  being 

utilized  for  temporary  housing  during  renovation  or 

remodel  projects,  or  to  address  a  temporary  (3  years  or 

less) bubble in enrollment. 

 

Provide Adequate Art, Science and Media Centers 

Adequate art, science, and library instructional areas are a 

problem  in  all  elementary  schools.    New  schools  will 

provide  for  the  adequacies  of  these  functions.    A 

proposed, combined art/science space will be provided at 

each elementary school.   

 

Media Centers will be provided at each elementary school.  

Each  media  center  is  to  meet  state  and  PSFA 

recommended sizes per school capacity and enrollment. 

Respond to Future Programs 

The  focus  of  this  bonding  cycle  is  the  construction  of 

replacement  elementary  schools.    However,  un‐funded 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 8 

 

 

projects have been identified to respond to changes in the 

educational  programs.    These  projects  are  included  in 

Section 4 under each school assessment document. 

Comply with Educational Adequacy Standards 

Compliance with  the educational adequacy standards will 

be  addressed  in  the  elements  of  the  goals  as  described 

above.   

1.2 Process 

1.2.1 Responsibility and Authority 

The Carlsbad Municipal School District Board of Education 

has  commissioned  the  development  of  this  Facilities 

Master Plan 2014‐2019 to serve as a reference and guide 

to the District over the next five years.  It is recommended 

that  this document be utilized  as  a  “living document”  to 

record district  facility goals and accomplishments as  they 

are  achieved.    It  is  the  responsibility  of  CMSD  to  review 

and  revise  this Facilities Master Plan as  changes occur  in 

the  district  and  to  complete  a  new  document  every  five 

years.  It  is  the  responsibility  of  the  CMSD  Board  of 

Education to review and adopt the FMP.   

CMSD regularly reviews and approves the progress of the 

Facilities Master Plan through the Operations Department.  

A Facility Advisory Committee  (FAC) has been established 

to  guide  the  FMP  process.    The  committee  includes  the 

Superintendent,  Director  of  Operations,  Maintenance 

Supervisor;  Carlsbad  school  staff  and  citizens  invited  by 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 9 

 

 

the District, comprise the voting members of the FAC. It is 

the responsibility of the FAC to establish FMP goals, review 

FMP progress,  and make  recommendations  to  the Board 

of Education for approval and adoption. 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 10 

 

 

1.2.2 Facilities Master Plan Process 

The  Facility  Advisory  Committee  (FAC)  was  assigned  the 

task  of  working  together  with  district  planners  and 

architects  to  review  data  and  establish  priorities  for  the 

FMP.  A diagram of the overall process and steps utilized in 

this FMP are detailed in Figure 1‐1:   

 

 

 Figure 1‐1 Master Plan Process Diagram

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 11 

 

 

 

Pre‐Assessment  activities,  field,  and  data  assessments  of 

all school and district facilities were conducted in 2010 and 

updated  in  2014.    The  following  types  of  activities  and 

information  were  gathered  in  order  to  compile  the 

eventual recommendations to the FAC committee: 

 

Community and School District Information 

Information  was  gathered  in  a  variety  of  methods  from 

gathering current demographic  information, maintenance 

records,  FAD  reports  from  the  PSFA  Facility  Assessment 

Database, current technology plan, and current staffing.  A 

summary of these activities include: 

 

School staff were contacted to gain additional information 

about  current  school  programs,  community  programs, 

after‐school programs, and the facility goals. 

 

The  2010  walk‐through  assessments  were  updated  with 

current  maintenance  projects,  enrollment,  staffing,  and 

reflect  the  plan  to  consolidate  the  schools.    During  the 

facility  walk‐throughs  the  team  strived  to  be  as 

undisrupted  as  possible  to  the  school  programs  but,  to 

also  gain  insight  from  teachers  and  students.    It  was 

estimated  that  40‐50%  of  the  teachers  provided 

comments  during  the  tours.    Students  were  questioned 

about their schools as the opportunity presented itself.   

 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 12 

 

 

Community involvement in the project was through public 

representatives  serving  on  the  FAC  and  Board 

presentations which are publicized and open to the public. 

 

Additional  community  involvement  was  accomplished 

through a series of public presentations conducted by the 

District prior to the 2014 GO Bond election. 

 

Community and  school district  information was  gathered 

and utilized in the overall assessment of each of the facility 

for the district. This information included: 

Maintenance records for a three year period, 

Floor plans and site plans, 

Previous Master Plan update, 

FAD reports, 

Technology Plan, 

Maintenance Plan, 

Special education needs report, 

FAC reports on tours of all District facilities, 

Instructional  needs  for  educational  programs  and 

program goals gained through interviews, 

Individuals’  thoughts  concerning  the  educational  and 

physical  environment  gained  through  one‐on‐one 

interaction with teachers and students, 

Community  program  offerings  and  facilities  gained 

through principal interviews. 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 13 

 

 

 

Educational Facilities Assessments 

 

Facilities Analysis’ 

Walk‐through Assessments of each school were conducted 

in  2010  and  were  updated  in  2014.    The  assessments 

include the following facilities:  

Dr. E.M. Smith Pre‐ School 

Early Childhood Education Center 

Craft Elementary School 

Hillcrest Elementary School 

Monterrey Elementary School 

Joe Stanley Smith Elementary School 

Pate Elementary School 

Puckett Elementary School 

Riverside Elementary School 

Sunset Elementary School 

Alta Vista Middle School2 

P.R. Leyva Middle School 

Carlsbad High School 

Eddy Alternative School 

Jefferson Montessori Academy Charter School 

District Warehouse 

Edison Building – Special Education Center 

District Administration Building 

                                                            

2 As of  the 2014/15 school year Alta Vista will become  the 6th Grade 

Academy 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 14 

 

 

 

 

The  walk‐through  assessment  included  a  visual  or  plan review assessment of the following: 

Landscaping 

Drainage/Storm Water  Retention/Erosion/Ponding 

Issues 

Hardscape 

Site Recreation Amenities 

Site Safety and Security 

School Plant Assessment 

Educational Environment 

 Current  information  was  collected  to  update  the 

assessment  documents  including  the  current  school 

enrollment,  staffing,  maintenance  records,  and  FAD 

reports. 

 

Capacity/ Utilization Studies 

  Utilizing  the  Public  Schools  Facilities  Authority 

recommended worksheets for capacity and utilization, the 

planning team calculated the enrollment capacity of each 

school based on programs, enrollments, and scheduling.  

 

School Information 

Information about each school was gathered and included 

in the overall assessment including: age of facilities, facility 

construction, maintenance records, neighborhood growth 

and conditions, and community goals and priorities. 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 15 

 

 

 

Demographics/ Enrollment 

Demographics  for  Eddy  County  were  gathered  for  input 

and  analysis  into  the  overall  trends  within  the  area.  

Migratory  information  within  the  district  is  revealed 

through  the  growth  rates  at  individual  schools.    Historic 

enrollment  information  was  gathered  from  the  District’s 

40‐day  counts  for  a  five  year  period.    The  following 

categories of demographic and enrollment  information  is 

utilized as informational in this FMP: 

Overall population trends 

Birth rates 

Household size 

Age composition 

Economic trends 

Development activity 

Decision‐making Process  

Decision‐making  for the FMP was based on a non‐biased, 

collaborative  process.  The  2010  Facility  Advisory 

Committee  worked  together  with  the  planning  team  to 

analyze  the  information as  it was gathered and establish 

priorities for ranking each potential project. The FAC, prior 

to the commencement of the project, toured every facility.  

The  principals  and  staff  were  prepared  to  discuss  the 

issues, as they perceived them, with the committee.   The 

FAC then rated elements of each facility.  Their findings are 

included  in  the  Appendix,  facility  evaluation  summaries, 

for  reference.    As  a  result  of  this  prior  knowledge,  the 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 16 

 

 

committee  was  well  prepared  to  provide  the  planning 

team with guidance.   

 

In  2013  and  2014,  multiple  evening  and  day‐long 

workshops  were  conducted  to  communicate  background 

and  gather  additional  committee  guidance  on  the 

proposed plan.  The FAC meetings were open to the public 

and  public  representatives  who  were  invited  to  attend, 

were present.   

 

Project priorities were determined through discussion, FAC 

knowledge of the schools, first‐hand experience during on‐

site  school  tours,  response  from  FAC  members  in 

reference to project sheets provided by the planning team, 

review of schools deferred  from  the previous bond cycle, 

consideration  of  the  goals,  and  particular  goals  from 

District Administration. 

 

The planning team sorted all potential projects into several 

categories:  potential  general  obligation  bond  (GO  Bond) 

projects,  SB9  funded  projects,  HB33  projects,  and  those 

items requiring only normal maintenance.   

 

Develop Financial Strategies 

The  primary  focus  of  the  Facilities  Master  Plan  was  the 

development of projects  for  the 2014 General Obligation 

Bond.    The  Board  of  Education  approved  the  financial 

strategy that is included in this FMP.   

 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 17 

 

 

Projects were also identified for SB‐9 and HB‐33 funding to 

be implemented by the CMSD Operations Department.   

 

Develop Implementation Plan 

The  implementation plan was developed to coincide with 

the  list of projects and the financial strategy approved by 

the Board of Education. 

 

Public Presentation and Board Approval 

The  Facilities Master  Plan was  presented  for  approval  in 

public forum at the Board the Education meeting on April 

22,  2014.        The  2014‐2019  Carlsbad  Municipal  Schools 

FMP was approved at this Board meeting. 

1.3 Acronyms / Definitions 

 

Building Efficiency –   The ratio of NASF / GSF 

CMSD –            Carlsbad Municipal School District 

FAC –            Facility Advisory Committee 

DD Program –   Developmentally Delayed Program 

ES –              Elementary School 

ESL –             English as a Second Language 

FAD –            Facility Assessment Database 

FCI–     Facility Condition  Index (the ratio of 

need repairs to current replacement 

value) 

FMP –           Facilities Master Plan 

GSF –   Gross Square Feet, or the sum of the 

net  assignable  square  feet  plus  all 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 18 

 

 

other  building  area  that  is  not 

assignable.  The  “left  over”  area  is 

called  “tare”  which  includes 

circulation  area,  mechanical  area, 

toilets and wall areas 

HS –              High School 

MACC –       Maximum  Allowable  Construction 

Cost 

MECH –         Mechanical 

MS –             Middle School, Media Storage 

NASF –       Net  Assignable  Square  Feet,  or 

building area that can be assigned to 

specific  task,  not  including  building 

circulation,  wall  thickness, 

mechanical  equipment  and  toilet 

facilities 

NMCI –         New Mexico Condition Index 

OT/PT –      Occupational  Therapy  /  Physical 

Therapy 

PMP –           Preventative Maintenance Plan 

PSCOC –        Public School Capital Outlay Council 

PSFA –          Public School Facilities Authority 

PTR –            Pupil / Teacher Ratio 

SF –               Square Feet 

SLP –             Speech / Language Pathology 

SPED –          Special Education 

State FCI –    State Facilities Condition Index 

State ID –     State Building Identification Number 

Facilities Master Plan 2014‐2019    Carlsbad Municipal School District 

         1.0 Goals and Process                                                                                  Carlsbad, New Mexico 

  Section 1 | 19 

 

 

TPC –    Total Project Cost, or  the  total  cost 

of the project including architectural 

and  engineering  fees,  moveable 

equipment,  land acquisition (if any), 

administration and contingencies 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 1 

2.1 Programs 

The  Carlsbad  Municipal  School  District  (CMSD)  is  located  in 

Eddy County, New Mexico, and covers an area of 2,497 square 

miles, although all schools are  located within the Carlsbad city 

limits.   CMSD enrolled 6,390  students  for  the 2013/14  school 

year (40‐day)  in grades K‐12.   The district  is comprised of 51% 

Hispanic,  21%  White,  1%  African‐American,  1%  Native 

American, and  less than 1% Asian students.   Free and reduced 

lunch for district students ranges from 33‐88 percent in district 

schools.    According  to  a  2011‐12  report  by  the  New  Mexico 

Department of Public Education, 16.8% of CMSD students were 

living  in  poverty.    District  schools  range  from  walkable, 

neighborhood  schools  to  schools  that  serve  larger geographic 

areas. 

2.1.1 Number of Schools, Types / Grade Configuration 

The  district  is  comprised  of  fourteen  (15)  school  facilities, 

including one pre‐school, one early education center, eight (8) 

elementary schools, two middle schools, one high school, and 

one charter school.   During the course of the previous Master 

Plan,  the  District  closed  one  elementary  school,  Eddy 

Elementary,  this  facility  is  currently  being  partially  used  to 

house  the  district’s  alternative  school  program  (1)  and 

technology department.  

 

 

 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 2 

 

Table 2‐1:  School Numbers, Types, and Grade Configuration 

School Configuration  # of schools 

Early Education Center:  

Pre‐K – K  2 

Elementary Schools:   

Grades 1‐5  8 

Middle Schools:   

Grades 6‐8  2 

High School:   

Grades 9‐12  1 

Alternative School:   

Grades 3‐12  1 

Charter School:   

Grades K‐12  1 

Total  15 

 

As  of  2013/14,  40‐day  enrollment,  Pre‐kindergarten  and 

Kindergarten  schools  enrolled  108  and  561  students 

respectively;  elementary  schools  range  from  241  (Pate 

Elementary,  to  443  (Sunset  Elementary)  students;  middle 

schools  enrolled  594  and  872  students;  and  the  high  school 

enrolled  1,667  students  for  the  2013‐14  school  year.  The 

Jefferson  Montessori  Charter  School  enrollment  is  190 

students. 

 

 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 3 

The following is a list of CMSD school facilities: 

 

Table 2‐2:  CMSD School Facilities 

Schools  Grades

Elementary Schools:   

  Early Childhood Education (ECE) Center  K 

  Dr. E.M. Smith Elementary  Pre‐K  

  Craft Elementary  1‐5 

  Hillcrest Elementary  1‐5 

  Joe Stanley Smith Elementary  1‐5 

  Monterrey Elementary  1‐5 

  Pate Elementary  1‐5 

  Puckett Elementary  1‐5 

  Riverside Elementary  1‐5 

  Sunset Elementary  1‐5 

Middle Schools:   

  Alta Vista1  6‐8 

  P.R. Leyva   6‐8 

High School:   

  Carlsbad High  9‐12 

Alternative Schools:   

  Eddy Alternative School  3‐12 

Charter School:   

  Jefferson Montessori  K‐12 

Total  15 

1 As of the 2014/15 school year this will be the Alta Vista 6th Grade Academy 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 4 

2.1.2 Assumptions, Anticipated Changes in Program 

The  following are  changes  to  school  configuration and  school 

choices anticipated at CMSD within the next five years. 

School Size 

The  Carlsbad  Municipal  School  District  made  the  decision  to 

close Eddy Elementary School during  the  course of  the 2011‐

2015 Facilities Master Plan.  Students were reassigned to other 

schools; this change was reflected in the demographic analysis.  

CMSD  through  its most  recent GO Bond  Election  in  February 

2014, will be constructing four new elementary schools with a 

capacity of 600  students  each  in order  to  improve  education 

programs at the elementary  level. With the  larger schools, the 

district will be reducing the eight elementary schools  into five. 

The  district  intends  to  replace  or  renovate/expand  the 

remaining  elementary  (Hillcrest  Elementary)  as  part  of  the 

2018 GO Bond election.   

Class Size 

Due  to  the  economic  situation  facing  all  schools,  the District 

requested from the State Department of Education an increase 

in  class  size  in  the  past,  so  the  District  is  unlikely  to  pursue 

further increases. 

Grade‐level Configuration and Other Special Programs 

Grade‐level  configurations  include  Pre‐kindergarten, 

Kindergarten  in  devoted,  district‐wide  facilities.    The  Pre‐

kindergarten students were relocated from the Early Childhood 

Education  Center  to  E.M  Smith  Elementary  in  the  2009‐2010 

school  year  and  once  the  new  600  student  Pate  Elementary 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 5 

replacement  school  is  constructed,  the  Pre‐Kindergarten 

program  may  be  considered  for  relocation  to  Puckett 

Elementary facility when vacated.   The district anticipates that 

demand  for  the  preschool  and  kindergarten  programs  will 

continue to grow based on the  local demographic trends. The 

Early Childhood Center  that kindergarten  students attend has 

the  ability  to  be  expanded  in  the  future  to  be  able  to 

accommodate  increased  enrollment, however,  the pre‐school 

program is restricted to the existing facilities capacity and does 

not  have  opportunities  to  grow  in  its  current  location.    The 

district will need to consider alternate locations in the future to 

accommodate the needs of the pre‐school program. 

 

All elementary schools are configured with grades 1‐5; middle 

schools 6‐8; and the high school are 9‐12.   With the exception 

of  the middle  schools,  these  levels will  continue  for  the next 

five  years.  As  of  the  2014/15  school  year,  CMSD  will  be 

establishing  a  6th  grade Academy  at Alta Vista Middle  School 

and  reconfigure  the  grade  levels  at  P.R.  Leyva  to  7th  and  8th 

grade only. 

 

At  the high  school  level,  the district will be  implementing  an 

early college high school program which will be  located at the 

NMSU‐Carlsbad Campus starting in the 2014/15 school year for 

eligible students. 

 

CMSD  has  also  created  a  special  alternative  program  that 

utilizes  a  portion  of  the  former  Eddy  Elementary  to  house 

students  in  grades  3‐12th  that  are  at  risk  of  dropping  out  or 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 6 

being expelled.  These students are included in the enrollment 

of  their  home  schools  but  attend  Eddy  Alternative  School  in 

lieu of being expelled for their at‐risk behaviors.  Academic and 

behavioral  interventions  are  used  to  help  students  transition 

back  into  the  traditional  school  environment  when 

appropriate. 

Curriculum 

CMSD  is  not  currently  considering  changes  to  the  curriculum 

that would require major modifications to school facilities. 

Year‐round Schools and Magnet Programs 

While CMSD  is not considering a change to year‐round school, 

it  is however, considering a STEM magnet program at Hillcrest 

Elementary,  once  the  new  four  new  elementary  schools  are 

constructed  to  provide  additional  school  program  choice  for 

parents in Carlsbad.  

 

2.1.3 Shared or Joint Use Facilities Opportunities 

CMSD provides  for after  school programs which are provided 

by  others  such  as  DARE  and  Reading  buddies  from  the 

Assistance  League.    School  grounds  are  used  for  sports 

programs  such  as  Little  League  Football,  Softball  and  T‐ball.  

Indications are, these programs will continue.   

2.2 Sites and Facilities 

2.2.1 Map, Boundaries, and Locations 

Carlsbad  Municipal  School  District  is  located  within  Eddy 

County in southeastern New Mexico.  Eddy County includes the 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 7 

towns of Artesia, Carlsbad, Hope, and Loving.   Carlsbad  is  the 

county seat and largest city in the county. 

 

The  county  covers  4,182  square  miles  and  is  home  to  over 

50,000 people.   The CMSD covers 2,497 square miles and has 

6,390  students  per  the  official  40‐day  count  for  the  2013/14 

school  year.  Two  other  school  districts  are  included  in  Eddy 

County:  Artesia and Loving. 

CMSD school facilities are all located within the municipal limits 

of the City of Carlsbad.  The map in  

1  illustrates the  location of CMSD  in relation to other districts 

in  the  state.    Figure 2‐2  shows population distribution within 

the state, as per the 2010 US Census. 

 

Figure 2‐3 to 2‐4 shows the Carlsbad Municipal School District 

boundaries  for  Elementary  and  Middle  Schools  including 

changes  due  to  the  closing  of  Eddy  Elementary.    A  separate 

High School Boundary map  is not necessary as  it  includes  the 

entire district boundary.  The boundary encompasses all of the 

area shown in the Elementary/Middle Schools Map. 

 

 

 

 

 

 

Figure 2‐1:  New Mexico School Districts 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 8 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 9 

Figure 2‐2:  County Population, New Mexico, 2010 US Census 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 10 

Figure 2‐3:  Elementary/Middle School Boundary Map, The High School and as of 2014/15 school year the 6th Grade 

Academy & P.R. Leyva Middle School attendance zone will encompass the entire district boundary. 

Figure 2‐4:  Zone Changes with the Closing of Eddy Elementary School 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 11 

 

 

2.2.2 Existing Facilities / Site Inventory Summary 

The district has 1,170,987 gross square feet (GSF) of permanent 

facilities  and  20,007  GSF  of  portable  facilities,  an  average  of 

161 GSF of permanent  space per  student or 165 GSF of  total 

space per student including portable classrooms.  Figures 2‐5 to 

2‐8  illustrates  the breakdown of early  childhood, elementary, 

middle, high  school, charter  school, and administrative  space.  

Additionally, the district has 529 acres of  land as noted  in the 

Site Inventory Chart. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 12 

Figure 2‐5:  CMSD Permanent Facilities, by Type* 

Figure 2‐6:  CMSD Portable Facilities, by Type* 

 

 

 *Note: As of the 2014/ 15 school year Alta Vista Middle School will become the 6th Grade Academy 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 13 

Figure 2‐7:  CMSD Facilities, by Type* 

  *Note: As of the 2014/ 15 school year Alta Vista Middle School will become the 6th Grade Academy 

Facilities Master Plan 2014‐2019                                       Carlsbad Municipal School District 

          2.0 Existing and Projected Conditions                                                                                       Carlsbad, New Mexico 

                                                                                                                          

Section 2 | 14  

2

 

Facility Name District ID State ID Address ZIP Phone Fax Principal / Site Manager Open

DateAge

(Years) Construction Dates State FCI Site Acreage Owned or Leased?

Total Perm Bldg Area

Total Port Bldg Area

Total Bldg Area (GSF) Grades

2013/14Enrollment

(40 day)

Full-Size Classrooms

Half-Size Classrooms

Gym/Multi-Purpose

No. of Permanent

Classrooms

No. Double Portables

No. of Portable Class- rooms

Total Class- rooms

Port CR % of Total

GSF Per Student

Early ChildhoodEarly Childhood Education Center ECEC 011907 1801 West Lea Street 88220 (575) 234-3303 (575) 234-3445 Misti Fernandez 1994 20 27.60% 9.70 Owned 49,396 0 49,396 Kinder 561 32 0 1 33 0 0 33.0 0 88.0E. M. Smith Pre-School EM Smth 011907 2415 Carver Street 88220 (575) 234-3313 (575) 234-3570 Misti Fernandez 1960 54 1994, 2009 14.29% 4.13 Owned 17,983 0 17,983 Pre-K 108 9 0 1 10 0 0 10.0 0 166.5

Sub-Totals 13.83 67379.00 0.00 67,379 669 43.00 0.00 0.00 43.00 0.0% 100.72

Elementary Level

Craft Elementary School Craft ES 1 011907 406 West Lea Street 88220 (575) 234-3304 (575) 234-3492 Merci Renteria 1920 94 1947, 1968 27.39% 2.57 Owned 33,345 0 33,345 1st-5th 252 15 1 1 17.0 0.0 0.0 17.0 0% 132.3

Hillcrest Elementary School Hillcrest ES 2 011907 215 North Sixth Street 88220 (575) 234-3308 (575) 234-3522 Denice Peterson 1948 66 1961 25.29% 6.80 Owned 45,590 0 45,590 1st-5th 311 19 2 1 22.0 0.0 0.0 22.0 0% 146.6

Joe Stanley Smith Elementary School JS Smith ES 3 011907 505 Alta Vista Street 88220 (575) 234-3314 (575) 234-3581 Kim Arrington 1956 58 1964 47.61% 7.10 Owned 37,184 0 37,184 1st-5th 290 21 2 1 24.0 0.0 0.0 24.0 0% 128.2

Monterrey Elementary School Monterrey ES 4 011907 1001 North 9th Street 88220 (575) 234-3309 (575) 234-3531 Fran McCarthy 1954 60 1980 25.42% 7.17 Owned 39,930 896 40,826 1st-5th 330 18 1 1 20.0 0.0 1.0 21.0 5% 123.7

Pate Elementary School Pate ES 5 011907 120 Kircher Street 88220 (575) 234-3310 (575) 234-3543 Therese Rodriguez 1955 59 1994 47.71% 5.45 Owned 32,064 2,580 34,644 1st-5th 241 15 0 1 16.0 1.0 3.0 19.0 16% 143.8

Puckett Elementary School Puckett ES 6 011907 2212 Primrose Street 88220 (575) 234-3311 (575) 234-3552 Deborah Beard 1956 58 1963, 1994, 2003 29.40% 7.23 Owned 30,094 3,368 33,462 1st-5th 248 13 1 1 15.0 2.0 4.0 19.0 21% 134.9

Riverside Elementary School Riverside ES 7 011907 1600 Johnson Street 88220 (575) 234-3312 (575) 234-3561 Sandra Nunley 1956 58 1960, 1994 44.70% 6.16 Owned 31,660 896 32,556 1st-5th 283 12 1 1 14.0 0.0 1.0 15.0 7% 115.0

Sunset Elementary School Sunset ES 8 011907 923 North Walter Street 88220 (575) 234-3315 (575) 234-3593 Lee White 1952 62 1980 49.15% 10.07 Owned 36,197 4,480 40,677 1st-5th 443 17 1 1 19.0 2.0 5.0 24.0 21% 91.8

Sub-Totals 52.55 286,064 12,220 298,284 2398 147.00 5.00 14.00 161.00 8.7% 124.39* Middle or Junior High LevelAlta Vista Middle School* Alta Vista MS 1 011907 301 Alta Vista Place 88220 (575) 234-3316 (575) 234-3478 Mark Barela 1949 65 1955, 1968, 1977, 1990, 1993, 1995, 1998 37.19% 22.45 Owned 124,700 0 124,700 6th-8th 594 44 0 2 46 0 0 46.0 0% 209.9

P. R. Leyva Middle School PR Leyva MS 2 011907 800 West Church Street 88220 (575) 234-3318 (575) 234-3452 Mark McAlister 1940 74 1949, 1956, and 1967 21.62% 15.68 Owned 159,798 1,792 161,590 6th-8th 872 50 0 3 53 1 2 55.0 0% 185.3

Sub-Totals 38.13 284,498 1,792 286,290 1466 99.00 1.00 2.00 101.00 2.0% 195.29

High SchoolCarlsbad High School Carlsbad HS 1 011907 3000 West Church Street 88220 (575) 234-3319 (575) 234-3399 Mark Driskell 1961 53 1966, 1978, 1992,2007,2009, 23.43% 63.03 Owned 373,892 5,995 379,887 9th-12th 1,667 86 0 3 89 0 6 95.0 0% 227.9

Sub-Totals 63.03 373,892 5,995 379,887 1667 89.00 0.00 6.00 95.00 6.3% 227.9

Alternative Schools

Eddy Alternative School Eddy Alt 1 011907 700 W. Stevens Street 88220 (575) 234-3305 (575)234-3267 Dale Ballard 1948 66 1968 26.38% 2.57 Owned 21,420 0 21,420 3rd-12 N/A 8.0 0.0 0.0 8.0 0% -

Sub-Totals 2.57 21420 0.00 21,420 0 8.00 0.00 0.00 8.00 0.0% 0.0

Charter SchoolsJefferson Montessori Academy 011907 500 West Church Street 88220 (575) 234-1703 (575) 887-9391 Cindy Holguin 1954 60 1960, 1994, 2012 12.68% 5.00 District Owned 48,296 0 48,296 K-12th 190 10 0 1 11 0 0 11.0 0 254.2

Sub-Totals 5.00 48,296 0.00 48,296 190 11.00 0.00 0.00 11.00 0.0% 254.2

Administration and SupportDistrict Administration Administration 011907 408 N. Canyon Street 88220 (575) 234-3300 (575) 234-3367 Don Owen 1978 36 2.57 Owned 19,230 19,230 0.0 NA NA

District Warehouse Warehouse 011907 201 Alta Vista Street 88220 (575) 234-3322 (575) 234-3367 Gene Bradley 1963 51 1.00 Owned 24,304 24,304 0.0 NA NA

District Storage @ JMA Storage 011907 500 West Church Street 88220 (575) 234-1703 (575) 887-9391 Gene Bradley 1954 60 1960, 1994, 2012 13% - Owned 18,792 18,792

Edison Building Edison 011907 406 North Alameda Street 88220 (575) 234-3300 (575) 234-3367 Gene Bradley 1931 83 2.57 Owned 17,932 17,932 0.0 NA NA

Eddy Tech Center Tech Center 011907 700 West Stevens Street 88220 (575) 234-3300 (575) 234-3367 Gene Bradley 1948 66 1968 26.38% - Owned 9,180 9,180 0.0 NA NA

Sub-Totals 6.14 89,438 0 89,438 0.00

District Totals 181.26 1,170,987 20,007 1,190,994 0.00 6,390.00 397.00 6.00 22.00 419.00* Alta Vista 6th Grade Academy as of the 2014/15 School Year

Facilities Inventory DataFacility Inventory

 

Table 2‐3 Facility Inventory 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 15 

2.3 District Growth 

This section analyzes the following demographic information to 

determine growth trends in the district that may impact district 

educational programs and student enrollment: 

Overall population trends 

Birth rates 

Household size 

Age composition 

Economic trends 

Local Area Housing 

2.3.1 Carlsbad Area Population Growth Trends 

According to the 2010 U.S. Census, 26,168 residents lived in the 

City of Carlsbad, while 53,902  residents  lived  in Eddy County, 

see Figures 2‐8, 2‐9, 2‐10 and 2‐11. 

79% of district residents lived in the city of Carlsbad. 

21% lived outside the city limits. 

Census estimates indicates the number of residents in Carlsbad 

increased by an estimated 2.1% between 2000 and 2010. 

Population 2000 2010 % of Change

Eddy County 51,658 53,902 4.3%

Over 18 yrs 36,751 39,827 8.4%

Under 18 yrs 14,907 14,075 ‐5.6%

City of Carlsbad 25,625 26,168 2.1%

Over 18 yrs 18,668 19,454 4.2%

Under 18 yrs 6,957 6,714 ‐3.5% Total population  growth  in Eddy County  increased 4.3%  from 

2000‐2010,  while  the  state  population  grew  13.2%  and  has 

increased another 1.7% since 2010.  While growth in the City of 

Carlsbad City and Eddy County  is  less than that of the State of 

New Mexico  it too has grown 2.9% since 2010. The significant 

Figure 2‐8:  Population Change – City / County, 2000‐2010 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 16 

economic  investment  in  this area has prevented a population 

decline  that  has  occurred  in  several  other  areas  of  the  state 

and is beginning to grow.   

 

Figure 2‐9:  Population Change – City / County, 1920‐2010 

 

S

o

u

 

S

ource:  Bureau of Business and Economic Research, University of New Mexico 

 

Figure 2‐10:  Local Area Population – City / County, 2010 ‐2015 

 

 

 

 

 

 

 

 

 

 

 

Source:  Bureau of Business and Economic Research (Population Estimates), University of New Mexico 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 17 

Figure 2‐11:  New Mexico County Population Percent Change, 2000‐2010 

   Source:  US Census Bureau, 2010

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 18 

From 2015 through 2040, BBER projects population growth rates 

to  stay  below  1%  for  Eddy  County  and  to  slow  to  1%  for  the 

statewide.  See Figure 2‐12. 

Figure 2‐12:  Annual Growth Rate, 2010‐2040 

    Source:  Bureau of Business and Economic Research, University of New Mexico 

 

This projection results  in a total growth of 21.2% between 2015 

and  2040,  to  a  population  of  65,258  over  a  twenty‐five  year 

period.  Eddy County population is expected to continue to grow 

well  into  2040,  however  after  2020,  the  rate  of  growth  is 

expected to progress at a slower pace. See Figures 2‐13 and 2‐14. 

 

Figure 2‐13:  Projected Total Population, Eddy County, 2010‐2040 

    Source:  Bureau of Business and Economic Research, University of New Mexico 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 19 

Figure 2‐14:  Projected Growth Rate, 2015‐2040 

 Source:  Bureau of Business and Economic Research, University of New Mexico 

 

According  to  the 2010 US Census,  the  community population 

by age group for school age children has decreased 3.4% since 

2000  for  the City of Carlsbad  and decreased  at  total of  5.6% 

countywide.    The  chart  below  identifies  the  community 

population for school age children for both 2000 and 2010. 

Figure 2‐15:  School Age Population, 2000‐2010 

Source:  US Census, 2000 & 2010 Census 

Five Year Projected Growth Rate Percentage (%) 2015 - 2040

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 20 

2.3.2 Birth Rates 

Birth  rates  in  the United States began  to decline  in 2007 and 

are at their lowest  levels nationwide since World War II, while 

New Mexico and Eddy County did not begin to experience this 

decline until 2009 and began to rebound in 2011.  Birth rates in 

Eddy County over the past two years to more than the State of 

New Mexico average, and are rebounding back to the county’s 

historic average of 14.1  (births per 1,000)  in  the early part of 

the 2,000’s.  See Figure 2‐16.  

Figure 2‐16:  Birth Rates, 2003‐2012 

 

 

 

 

 

 

     Source:  New Mexico Department of Health, Bureau of Vital Statistics and Health Statistics 

Of  those  children  born  in  Eddy  County  (outside  the  City  of 

Carlsbad)  from  2001  to  2012  between  11‐23%  enrolled  in 

kindergarten  in  the  Carlsbad  Municipal  School  District  five 

years later.  Due to the increase of births county‐wide in 2006, 

elementary  enrollment  has  steadily  increased  each  year  and 

will continue  this  trend over  the next  five years.   On average, 

CMSD provided schooling for 68% of the children born in Eddy 

County for the period.  See Figure 2‐17. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 21 

Figure 2‐17:  Eddy County Actual Births vs. Impact to CMSD 

Source:  New Mexico Department of Health, Bureau of Vital Statistics and Health Statistics  

 

2.3.3 Household Size 

The number of households  increased  in both Eddy County and 

Carlsbad  from  2000  and  2010  (300  households)  and  the 

percent  of households with  children  under  age  18  increased, 

contributing, in part, to the increase in school enrollment. 

 

Figure 2‐18:   Household Type and Size 

Source: U.S. Census Bureau, 2010 Census Table DP‐1 Profile of General Population and Housing Characteristics. 

 

 

 

 

 

 

Source: U.S. Census Bureau, 2010 Census Table DP‐1 Profile of General Population and Housing Characteristics. 

 

City of Carlsbad  Average Household Size: 2.5 Average Family Size: 3.03 Eddy County Average Household Size: 2.59 Average Family Size: 3.08

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 22 

2.3.4 Age Composition of Residents Living in the District 

The  school age  cohort has  increased  slightly  since 2000.   The 

population under 5 years of age declined slightly between 2000 

and 2010.  The cohort of women of child‐bearing age increased 

between 2000 and 2010, while  the proportions of main  labor 

force and  retiree cohorts have  increased  substantially. During 

the  same  period,  the  Census  estimates  Eddy County’s  school 

age cohort was 28.9 % of the total population. 

 

The U.S. Census estimates  the median age  for 2010 was 48.2 

years  old  in  Eddy  County  and  37.6  years  old  for  the  city  of 

Carlsbad  and  the  CMSD.    The  median  age  in  New  Mexico  is 

higher, at 45.5 years old.  See Figures 2‐19 and 2‐20. 

 

Figure 2‐19:  Eddy County Residents by Age Group, 2000 & 2010 

 

 

 

 

 

 

 

 

Source:  US Census, Total County Population by Sex and Five‐Year Age Groups: 2000 and 2010 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 23 

Figure 2‐20:  Carlsbad Incorporated Area Residents by Age Group, 2000 & 2010 

           

Source:  US Census, Total Incorporated Area Population by Sex and Five‐Year Age Groups: 2000 and 2010 

2.3.5 Income 

Per capita personal income was $42,466 in the City of Carlsbad 

for 2010, according to the US Census which is higher than that 

of  Eddy  County.    The median  family  income  in  Carlsbad was 

$51,394  as  compared  to  the  New  Mexico  median  family 

income of $51,994 in 2010.  See Figure 2‐21. 

 

The  US  Department  of  Commerce  reports  the  following  per 

capita income trend for the ten year period from 2000‐2010 for 

Eddy County. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 24 

Figure 2‐21:  Per Capita Income, Eddy County, 2000‐2010 

 

Source:  U.S. Dept. of Commerce, Bureau of Economic Analysis.  Data released April 25, 2012. 

 

Estimated  household  income  in  2010  was  $40,748  for  Eddy 

County,  a  47.4%  increase  compared  to  2000  ($21,460).  

Household  income  in  New  Mexico  in  2010  was  lower,  at 

$33,342.2 

2.3.6 Local Area Housing 

While  new  housing  has  been  built  on  an  individual  basis 

throughout  the  City  of  Carlsbad,  no  new  major  housing 

developments  have  been  constructed  since  the  mid  to  late 

1960’s.  Apartment complexes have also followed this trend as 

well and no new apartments have been built  in the area since 

the 1970’s.   With  lack of available housing  in the area, people 

are  living  in  local motels/hotels,  sharing or multi‐generational 

living  in  single  family  residences and also  renting  space  in RV 

2 U.S. Dept. of Commerce, Bureau of  Economic Analysis.   Data  released April  25, 

2012. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 25 

parks  and  living  in  their  RV’s  and  fifth‐wheels.  According  to 

Denise Griffith, a  local realtor for Means Realty, when existing 

housing  stock  typically  comes  on  the  market,  they  are  sold 

quickly.    With  local  banks  primarily  being  the  lenders  for 

mortgages, sub‐prime lending has been minimal and foreclosed 

homes in the area average 10 or less per year. 

 

According  to  Stephanie  Shumsky  (Carlsbad  City  Planner),  the 

pent up demand for housing is causing a shift of demographics 

in  the  city  of  the  existing  population  as  new  housing  is 

constructed; not a  large  in‐migration of new residents.   While 

new people have moved  into the area  in response to the  local 

economic conditions, many of these people are temporary.  In 

response to pent up demand in the area, three new apartment 

complexes  and  three  new  housing  developments  (by  Ken 

Thurston  Homes)  are  being  constructed  in  Carlsbad  to  help 

relieve  the housing shortage.   Many of  the new houses being 

constructed are being purchased by  local  residents  looking  to 

move‐up  into another area of town and are selling their older 

homes.   

 

The new housing and apartment developments are  located  in 

three  areas  of  the  city:  north,  south  and  central  area.   The 

northern  developments  (both  completed  and  under 

construction)  will  add  approximately  240  new  single  family 

homes  and  371  apartment  homes  over  the  next  four  years, 

they consist of: 

Spring Hollow  (off of Callaway Dr.)  –  Eight  floor plans 

available with square footages ranging between 1,461 – 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 26 

2,244.  At  this  site will be  a  combination of 190  three 

and  four bedroom units with 1 ¾  ‐2 ½ baths both  in 1 

and  2  story  configurations.   Costs  at  this  site  range 

between $188,900 – 234,395.  At  this  time 110 of  the 

Phase 1 houses have been sold and are occupied. Phase 

2 of this project will add an additional 80 houses. 

 

Copperstone  Apartments  ‐  1101  Calloway  Drive.  

Currently being constructed  in  three phases,  there will 

be  a  total  of  371  one,  two  and  three  bedroom  units. 

Phase 1 consisted of construction of 118 one and  two 

bedroom units have been completed and are currently 

100%  leased. Phase 2  consisted of 128  two  and  three 

bedroom units and is also 100% leased. Phase 3 is in the 

pre‐leasing stage and will consist of 125 two and three 

bedroom units. Construction  is anticipated  to begin  in 

April  2014,  and  take  a  year  for  complete  build  out 

although units will be occupied as they are completed.   

 

North  of  Copperstone  and  next  to  the  Assisted  Living 

Center there is a 14‐lot subdivision that has been plated 

will  be  constructed  for  senior  living  in  the  next  two 

years. 

La Heurta Subdivision – This area consists of 1 acre lots 

and custom homes.  Currently  the area  is experiencing 

in‐fill  development  at  the  rate  of  approximately  8 

homes per year for the next five years. 

Future:  

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 27 

o Copperstone  has  an  additional  fifteen  acres  of 

land as part of its existing property available that 

it could construct an additional 225 units as part 

of  a  future  phase  (unit  configuration  is 

unavailable at this time). 

o North  of  Copperstone  Apartments,  there  is 

another  228 unit  apartment  complex  in  the 

planning  stage.   This  area  was  rezoned  by  the 

City of Carlsbad and platted in 2012. 

 

The  local  elementary  school  that  will  be  impacted  by 

these developments is Riverside Elementary. 

The central area developments will add approximately 60 new 

single family homes and 192 apartment homes, they consist of: 

Cottonwood  (off  of  Center  Street)  –  At  this  location, 

sixty  new  homes  will  be  constructed  with  three  floor 

plans available and the square footages range between 

1,500 – 1,862.  There will be a combination of three and 

four bedroom units with 2  ‐2 ½ baths both  in 1 and 2 

story  configurations.  Costs  at  this  site  range between 

$155,500  –  184,900.  Currently  growth  in  this 

subdivision  is  slow  and  there  are  only  20  constructed 

and occupied. 

 

Avalon  at  Carlsbad  (Affordable Housing Designation)  ‐ 

1907 San Jose Blvd. This project was completed  in two 

phases, with the first phase of construction of 112 units 

(24 ‐ 2 bed/ 2 bath units, 40 ‐ 2 bed/ 1 bath units, 48 ‐ 1 

bed/ 1 bath units)  was completed  in August 2012. The 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 28 

Phase  2  construction was  completed  in  summer  2013 

and consisted of 80 units (20 ‐ 2 bed/ 2 bath units, 24 ‐ 

2 bed/ 2 bath units, 36 ‐ 1 bed/ 1 bath units), all of the 

units are leased to 95% of capacity. 

 

The  local  elementary  school  that  has  potential  for 

impact by these developments is Puckett Elementary. 

The  remaining  south  and  central  area developments will  add 

approximately  114  new  single  family  homes  and  243 

apartment homes, they consist of: 

 

The Village at Carlsbad ‐ 3821 National Parks Hwy. Two 

phases  of  construction  for  this  location, with  the  first 

phase of construction of 144 units  (64  ‐ 2 bed/ 2 bath 

units, 24 ‐ 2 bed/ 2 bath units, 56 ‐ 1 bed/ 1 bath units) 

that  will  be  finishing  construction  in  February  2014  – 

pre‐leasing  is  currently  at  96%.  Phase  2  construction 

should  start  late‐summer  2014  and  will  consist  of  an 

additional 96 units (24 ‐ 2 bed/ 2 bath units, 24 ‐ 2 bed/ 

1 bath units, 48 ‐ 1 bed/ 1 bath units). There is a waiting 

list for the Phase 2 units. 

Farmview  (off  of  the  Loving  Hwy  just  past  Calvani’s 

orchard).  With  four  floor  plans  available  the  square 

footages range between 1,789 – 2,540.  There will be a 

combination of 114 three and four bedroom units with 

2 ‐2 ½ baths both in 1 and 2 story configurations.  Costs 

at  this  site  range  between  $224,990  –  281,800. 

Currently  the  first  two  construction phases have been 

completed and have resulted in 52 new homes. Many of 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 29 

these  homes  have  been  sold  and  are  occupied.  There 

are  three  remaining  phases  in  this  area  that  will  be 

required to achieve the final build‐out of 114 homes. 

 

The  local  elementary  school  that  has  potential  for 

impact by these developments is Pate Elementary. 

 

With  this  shift  of  existing  population,  we  can  determine  the 

schools  impacted  by  the  new  developments  but  it  is  very 

difficult  to determine  the out‐migration of  students  from  the 

remaining elementary schools as their families may or may not 

seek  to  relocate  into  the  new  housing  that  is  becoming 

available.  With that in mind, there is a need to consider a new 

larger  replacement school  located  in  the Riverside area and a 

boundary  adjustment  to  reallocate  the  remaining  elementary 

population  through  the  remainder  of  the  district’s  schools.  

Additionally,  it  appears  that  there  may  be  an  impact  to  the 

capacity of both of the district’s two middle schools due to an 

increase in birth rates in the early 2000’s. 

Figure 2‐22:  Housing Data, City of Carlsbad / Eddy County 

Carlsbad New MexicoHomeownership rate, 2007-2011 71.7% 69.6%Housing units in multi-unit structures, percent, 2007-2011 11.9% 15.0%

Median value of owner-occupied housing $90,700 $161,800Households, 2007-2011 9,909 762,002Persons per household, 2007-2011 2.56 2.62  

Source: U.S. Census Bureau, 2009‐2011 American Community Survey 

2.3.7 Employment Trends 

Major  industries  that  provide  employment  in  the  area  are 

tourism,  retail, government, and mining.   Carlsbad’s economy 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 30 

is  also  driven  by  oil  and  gas  production,  potash  mining,  the 

Waste Isolation Pilot Plant (WIPP), retirement, and agriculture.  

All areas of  the  job sector have seen  the  largest growth since 

1980, from 22 to 36% of all employment.3  See Figure 2‐23. 

 

The growth in Eddy County and Carlsbad’s economy and as well 

as  population  can  be  attributed  to  a  specific  in‐migration 

pattern of workers that include: 

• Temporary Worker – Assigned to the area for a short period 

of time (1 week to 6 months).   Typically a single worker or 

with a family that is unlikely to move to the area. 

• Transient  (Traveler)  Worker  –  Assigned  to  the  area  for  a 

specific period of time (6 months to 18 months +).  Typically 

a single worker or with a family that unlikely to move to the 

area. 

• Resident  Permanent  Worker  –  Assigned  to  the  area 

permanently. Many of these workers have families that will 

move with  them  from another  area  or  currently  reside  to 

the Carlsbad Area. 

• Non‐Resident  Permanent  Worker  –  Assigned  to  the  area 

permanently. Many of these workers have families that will 

move with  them  from  another  area  or  currently  reside  in 

communities  outside  of  Carlsbad,  such  as  Loving,  Artesia, 

rural settings. 

 

It  is  the Resident Permanent Workers  that have  families  that 

will impact Carlsbad Municipal Schools. 

Figure 2‐23:  Employment by Industry, City of Carlsbad / Eddy County 

3 Regional Economic  Information System, Bureau of Economic Analysis, US 

Department of Commerce 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 31 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Source: U.S. Census Bureau, 2009‐2011 American Community Survey 

Partial Listing of Carlsbad Employers: Carlsbad Employers:  

• Intrepid Potash   • Constructors, Inc. • WIPP • URS‐ EPD 

(manufacturing) • PVT • Devon Energy  • Carlsbad Medical 

Center • Department of 

Interior • City of Carlsbad • Westinghouse • Retail (Lowes, 

Walmart, etc) 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 32 

Sector 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010Grand Total 19,219 19,531 19,677 19,743 20,234 21,051 22,030 23,207 23,280 23,547Total Private 15,956 16,224 16,335 16,343 16,797 17,539 18,500 19,628 19,483 19,712 Ag. For. Fish. & Hunting 378 454 406 366 356 318 325 325 395 367 Mining 2,580 2,480 2,492 2,699 2,821 3,124 3,359 3,752 3,545 4,025 Utilities 130 130 132 128 122 122 137 140 169 175 Construction 1,101 1,088 1,162 931 1,064 1,113 1,491 1,921 1,801 1,689 Manufacturing 828 876 872 823 783 707 720 801 850 841 Wholesale Trade 453 441 433 461 471 483 531 562 511 527 Retail Trade 2,263 2,185 2,178 2,093 2,115 2,184 2,239 2,307 2,341 2,276 Transportation & Warehousing 764 724 752 760 787 793 847 808 687 729 Information 301 301 259 229 244 238 232 244 256 D Finance & Insurance 513 581 590 601 587 620 646 647 637 662 Real Estate & Rental & Leasing 336 439 403 389 407 410 442 393 397 414 Professional & Technical Services 355 386 446 473 515 406 449 782 881 D Management of Companies & Enterprises 37 42 42 186 179 230 206 194 146 D Administrative & Waste Services 1,306 1,331 1,311 1,291 1,396 1,734 1,729 1,487 1,429 1,455 Educational Services 31 36 53 44 41 40 38 37 36 42 Health Care & Social Assistance 1,981 2,171 2,248 2,306 2,240 2,258 2,332 2,434 2,633 2,605 Arts, Entertainment & Recreation 78 57 68 78 82 50 42 38 38 46 Accommodation & Food Services 1,725 1,701 1,686 1,664 1,750 1,834 1,924 2,004 2,020 1,911 Other Services, ex. Public Administration 793 798 802 820 831 868 810 752 712 694 Unclassified 2 7 2 2 6 7 1 1 0 DTotal Government 3,262 3,306 3,342 3,400 3,436 3,512 3,530 3,579 3,797 3,834 Federal 501 533 530 560 596 654 736 763 853 881 State 565 569 580 603 606 609 596 601 600 582 Local 2,196 2,204 2,232 2,237 2,235 2,250 2,198 2,215 2,344 2,371

Note: All years have been revised in accordance with U.S. Dept. of Labor, Bureau of Labor Statistics, databases.

New Mexico unemployment insurance (UI) law and related statutes. For a complete definition of covered employment see the attached definition sheet

AVERAGE ANNUAL COVERED WAGE AND SALARY EMPLOYMENT BY MAJOR INDUSTRIAL SECTOR EDDY COUNTY

D Withheld to avoid disclosing confidential data. Data that are not disclosed for individual industries are always included in the totals. Therefore, the individualindustries may not sum to the totals.

 Figure 2‐24:  Total Employees by Industry, Eddy County, 2001‐2010 

Source: U.S. Dept. of Labor, Bureau of Labor Statistics, Quarterly Census of Employment and Wages.  Table prepared by:  Bureau of Business and Economic Research, University of New Mexico. 

 

As  Figures  2‐23  and  2‐24  indicates,  total  employment  has 

grown  overall  since  2000,  from  19,219  employees  to  almost 

23,547 employees in 2010, an increase of 22.5% over ten years. 

Economic Opportunities have increased in the area through oil 

production and other industries over the past several years: 

• Intrepid Potash  

• Yates Petroleum 

• WIPP 

• SunEdison 

• Washington Tru Solutions 

• Westinghouse 

• Increase in Commercial & Retail (Ex. Lowes/ IHOP) 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 33 

Figure 2‐25:  Total Employment, Eddy County, 2009 – 2014 (January) 

 

 

 

 

 

 

 

 

 

 

 

 

 

   Source:  New Mexico Dept. of Workforce Solutions, Economic Research and Analysis Bureau, Table A (2009‐2014) 

 

According  to  the  New  Mexico  Economic  Development 

Department,  the  unemployment  rate  for  Eddy  County  in 

January 2009 was only 3.8%, compared  to 5.7%  for  the state.  

As of January 2014, Eddy County had an unemployment rate of 

3.9%, compared with 6.6% for the state.  See Figure 2‐26. 

Figure 2‐26:  Unemployment Rate, New Mexico & Eddy County, 2009‐2014 (January)  

 

 

 

 

 

 

 

 

 

 

 

 

Source:  New Mexico Dept. of Workforce Solutions, Economic Research and Analysis Bureau, Table A (2009‐2014) 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 34 

2.4 Enrollment 

2.4.1 Enrollment 2012‐2018 

The  Carlsbad  Municipal  School  District  enrollment  has 

increased from 6,018 to 6,390 students over the  last 10 years, 

reflecting an overall average increase of almost 3.8%. However, 

the  district  experienced  a  4.7%  decrease  in  enrollment  from 

2003/04 to 2008/09 due to poor economic conditions but has 

since  rebounded as of  the 2013/14 school year by 7.3%.   See 

Figures 2‐27 and 2‐28. 

 

This  increase  can be  attributed  to  several population  factors.  

U.S. census data shows population stability or  increase for the 

county  during  the  decade  since  the  2000  census,  indicating 

stable or increasing enrollment.  Of this population, the portion 

of  those  in  their  child‐bearing  years  has  increased.    Because 

Carlsbad  is the  largest school district  in the county,  increasing 

birth  rates  in  Eddy  County  since  2006  also  correlates  to  an 

increase  in elementary enrollment  in  the CMSD over  the past 

several  years  as  well  as  future  enrollment.    Long  term,  the 

increase  in  elementary  enrollment  will  begin  to  impact  the 

district’s middle schools4 and high school in 2015 ‐2019. 

 

 

4 As of the 2014/ 15 school year Alta Vista will become the 6th Grade Academy and PR Leyva will serve only grades 7th and 8th. 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 35 

Figure 2‐27:  District‐wide 40‐Day Count Total Enrollment, 2004‐2013 

   Source:  New Mexico Public Education Department 

 

  Figure 2‐28:  Student Enrollment by School Type 2008‐2013 

Source:  New Mexico Public Education Department School Fact Sheets, 40‐Day Count Enrollment by District and Grade 

Level, http://www.ped.state.nm.us/IT/schoolFactSheets.html 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 36 

The  following  tables  and  charts  (Figures  2‐29  through  2‐35) 

reflect demographic information gathered from CMSD and the 

New Mexico Department of Education. 

 

Figure 2‐29:   District Enrollment by Grade, 2004‐2013 

 

 

 

2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14

Pre-Kindergarten 88 97 95 94 96 92 94 96 125 114

Kindergarten 451 493 474 468 497 470 469 469 494 555

Grade 1 464 480 462 464 462 436 458 463 482 510

Grade 2 440 445 471 464 447 470 419 451 470 477

Grade 3 391 447 458 465 476 440 477 435 450 466

Grade 4 474 393 430 453 467 462 441 486 441 473

Grade 5 479 484 395 437 471 450 456 440 506 471

Total 2,787 2,839 2,785 2,845 2,916 2,820 2,814 2,840 2,968 3,066

Grade 6 359 502 489 409 443 461 477 471 446 507

Grade 7 438 420 503 482 400 443 455 485 480 469

Grade 8 499 440 431 491 473 398 442 445 494 490

Total 1,296 1,362 1,423 1,382 1,316 1,302 1,374 1,401 1,420 1,466

Grade 9 510 590 445 474 527 467 392 460 485 482

Grade 10 455 495 522 435 415 473 468 389 457 450

Grade 11 398 357 409 407 362 374 426 408 351 414

Grade 12 365 360 321 349 384 339 387 373 376 321

Total 1728 1802 1697 1665 1688 1653 1673 1630 1,669 1,667Charter School 123 92 81 82 126 147 164 169 204 191

Total Enrollment 5,811 6,003 5,905 5,892 5,920 5,775 5,861 5,871 6,057 6,390

High School

Carlsbad Municipal Schools Historic Enrollment

Elementary

Middle School

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 37 

Figure 2‐30:  Early Childhood Education Student Enrollment by School and Grade, 2004‐2013 

 

In  the 2010‐2011  school  year,  the District  created  a  separate 

Pre‐school  program  to  increase  capacity  for  Kindergarten 

students  at  the  Early  Childhood  Center.    At  that  time,  pre‐

school students were moved to the Dr. E. M. Smith Elementary.  

That school showed an enrollment of 96 students for the 2010‐

2011  school  year  and  is  currently  at  108.    Kindergarten 

enrollment  at  the  Early  Childhood  Center  has  increased  over 

the  last  several  years  and  is  expected  to  continue  that  trend 

due to increased birth rates in the area over the past few years.  

See Figure 2‐30. 

 

Enrollment districtwide over  the past  five years has  increased 

in all grade levels and at all of the district’s schools. See Figures 

2‐31 through 2‐34. 

School Name 2004/2005 2005/2006 2006/2007 2007/2008 2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/2014

Early Childhood Education Center Historic

Pre- Kindergarten 88 97 95 94 96 92 94 0 0 6

Kindergarten 451 493 474 468 497 470 469 469 494 555

458 430 437 449 464 510

%Change 9% -4% -1% 5.5% -5.2% 0.2% -16.7% 5.3% 13.6%

Total 539 590 569 562 593 562 563 469 494 561

Dr Emmitt Smith ECC Historic

Pre- Kindergarten 96 125 108

Kindergarten

%Change 30.2% -13.6%

Total 0 0 0 0 0 0 0 96 125 108

TOTAL 539 590 569 562 593 562 563 565 619 669

Carlsbad Municipal Schools Pre-K and Kindergarten Enrollments

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 38 

Figure 2‐31:  Elementary School Student Enrollment, 2004 – 2013 

Figure 2‐32:  Elementary School Student Enrollment, 2004 ‐ 2013 

School Name 2004/2005 2005/2006 2006/2007 2007/2008 2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/2014

Craft Elementary Historic

Kindergarten

First 39 37 33 43 36 48 35 63 53 47

Second 37 34 36 45 40 35 46 42 59 58

Third 27 41 34 39 36 44 40 46 44 53

Fourth 32 30 36 38 44 43 46 46 42 48

Fifth 38 46 35 40 42 35 45 47 44 46

%Change 9% -7% 18% -3.4% 3.5% 3.4% 15.1% -0.8% 4.1%

Total 173 188 174 205 198 205 212 244 242 252

Eddy Elementary Historic

Kindergarten

First 38 57 44 38 38 32

Second 41 41 53 42 40 31

Third 27 40 46 47 40 35

Fourth 45 27 39 48 46 34

Fifth 49 47 26 40 47 46

%Change 6% -2% 3% -1.9% -15.6% -100.0% 0.0% 0.0% 0.0%

Total 200 212 208 215 211 178 0 0 0 0

Hillcrest Elementary Historic

Kindergarten

First 51 51 51 52 59 46 76 71 55 64

Second 45 52 43 48 44 52 57 72 71 65

Third 36 48 56 45 50 43 71 51 55 67

Fourth 40 35 35 55 40 41 50 60 43 67

Fifth 42 36 38 38 59 41 53 49 66 48

%Change 4% 0% 7% 5.9% -11.5% 37.7% -1.3% -4.3% 7.2%

Total 214 222 223 238 252 223 307 303 290 311

Joe Stanley Smith Elementary Historic

Kindergarten

First 63 45 51 39 46 55 56 44 61 66

Second 42 55 50 47 46 60 52 57 40 58

Third 49 45 57 46 61 44 66 53 56 45

Fourth 47 54 39 55 48 49 47 68 50 61

Fifth 49 49 46 41 55 39 58 49 67 60

%Change -1% -2% -6% 12.3% -3.5% 13.0% -2.9% 1.1% 5.8%

Total 250 248 243 228 256 247 279 271 274 290

Monterrey Elementary Historic

Kindergarten

First 59 58 61 72 57 40 66 64 69 74

Second 62 56 51 56 72 65 46 62 62 65

Third 59 48 51 53 57 69 72 51 63 70

Fourth 65 58 46 49 55 57 75 73 53 67

Fifth 70 63 57 56 48 53 64 71 76 54

%Change -10% -6% 8% 1.0% -1.7% 13.7% -0.6% 0.6% 2.2%

Total 315 283 266 286 289 284 323 321 323 330

Carlsbad Municipal Schools Elementary Enrollments

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 39 

 

School Name 2004/2005 2005/2006 2006/2007 2007/2008 2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/2014

Pate Elementary Historic

Kindergarten

First* 55 56 44 50 50 38 38 41 56 56

Second* 53 55 60 48 46 48 29 46 53 50

Third 50 55 49 57 48 47 37 36 44 51

Fourth 67 40 51 45 54 48 40 43 35 36

Fifth 68 59 34 45 50 51 36 42 45 48

%Change -10% -10% 3% 1.2% -6.5% -22.4% 15.6% 12.0% 3.4%

Total 293 265 238 245 248 232 180 208 233 241* EM Smith 2003-2008 Enrollment for Grades 1 & 2 before schools combined

Puckett Elementary Historic

Kindergarten

First 35 57 48 45 44 51 56 41 52 52

Second 38 37 51 47 38 43 55 48 40 49

Third 30 39 42 49 44 41 53 44 46 42

Fourth 52 34 41 38 52 44 43 46 52 51

Fifth 46 51 38 40 37 51 42 40 50 53

%Change 8% 1% 0% -1.8% 7.0% 8.3% -12.0% 9.6% 2.9%

Total 201 218 220 219 215 230 249 219 240 247

Riverside Elementary Historic

Kindergarten

First 47 40 58 51 46 57 45 46 45 62

Second 54 44 46 62 46 47 55 45 45 49

Third 48 62 54 51 61 48 44 62 50 49

Fourth 54 52 64 57 48 64 54 47 61 55

Fifth 57 61 52 64 55 54 65 51 49 68

%Change 0% 6% 4% -10.2% 5.5% -2.6% -4.6% -0.4% 13.2%

Total 260 259 274 285 256 270 263 251 250 283

Sunset Elementary Historic

Kindergarten

First 77 79 72 74 86 69 86 93 91 89

Second 68 71 81 69 75 89 79 79 100 83

Third 65 69 69 78 79 69 94 92 92 89

Fourth 72 63 79 68 80 82 86 103 105 88

Fifth 60 72 69 73 78 80 93 91 109 94

%Change 4% 5% -2% 9.9% -2.3% 12.6% 4.6% 8.5% -10.9%

Total 342 354 370 362 398 389 438 458 497 443

TOTAL 2248 2249 2216 2283 2323 2258 2251 2275 2349 2397

Carlsbad Municipal Schools Elementary Enrollments

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 40 

School Name 2004/2005 2005/2006 2006/2007 2007/2008 2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/2014

Alta Vista Middle School Historic

Sixth 173 199 223 172 198 217 203 193 185 208

Seventh 186 178 206 218 179 200 212 203 190 186

Eighth 231 183 200 198 211 172 188 201 211 210

%Change -5% 12% -7% 0.0% 0.2% 2.4% -1.0% -1.8% 3.1%

Total 590 560 629 588 588 589 603 597 586 604

Feeder Schools: All Elementary Schools - Grade change effective 2014/15

P.R. Leyva Middle School Historic

Sixth 186 303 266 237 245 244 274 278 261 299

Seventh 252 242 297 264 221 243 243 282 290 283

Eighth 268 257 231 293 262 226 254 244 283 280

%Change 14% -1% 0% -8.3% -2.1% 8.1% 4.3% 3.7% 3.4%

Total 706 802 794 794 728 713 771 804 834 862

Feeder Schools: Alta Vista Middle School - Grade change effective 2014/15

TOTAL 1296 1362 1423 1382 1316 1302 1374 1401 1420 1466

Carlsbad Municipal Middle School Enrollments

Figure 2‐33:  Middle School Student Enrollment, 2004 – 2013 

 

Figure 2‐34:  High School Student Enrollment, 2004 – 2013 

 

Carlsbad Municipal Schools High School Enrollments

School Name 2004/2005 2005/2006 2006/2007 2007/2008 2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/2014

Carlsbad High School Historic

Ninth 510 590 445 474 527 467 392 460 485 482

Tenth 455 495 522 435 415 473 468 389 457 450

Eleventh 398 357 409 407 362 374 426 408 351 414

Twelfth 365 360 321 349 384 339 387 373 376 321

%Change 4% -6% -2% 1.4% -2.1% 1.2% -2.6% 2.4% -0.1%

Total 1728 1802 1697 1665 1688 1653 1673 1630 1669 1667

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 41 

Figure 2‐35:  District Charter School Enrollment, 2004 – 2013 

School Name 2004/2005 2005/2006 2006/2007 2007/2008 2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/2014

Jefferson Montessori Historic (District Charter)

Kindergarten 7 4 3 8 16 21 15 16 21 20

First 10 5 5 4 6 21 14 18 11 16

Second 18 14 5 6 6 10 22 17 23 15

Third 12 3 8 4 7 11 23 23 17 23

Fourth 7 9 4 6 11 10 11 21 26 9

Fifth 6 6 6 3 8 13 9 8 24 23

Sixth 6 8 6 4 9 11 10 7 14 18

Seventh 13 3 8 12 14 10 16 10 12 11

Eighth 7 8 6 7 10 11 14 14 15 15

Ninth 10 8 12 7 11 6 6 11 14 9

Tenth 18 11 7 10 10 7 11 10 12 15

Eleventh 9 8 6 6 6 8 9 8 9 9

Twelve 0 5 5 5 12 8 4 6 6 8

%Change -25% -12% 1% 53.7% 16.7% 11.6% 3.0% 20.7% -6.4%

Total 123 92 81 82 126 147 164 169 204 191

Carlsbad Municipal Schools District Charter School Enrollments

 

 

2.4.2 Projected Enrollment 2014‐2019 

District  enrollment  projections  are  developed  based  on  a 

cohort  survival  method  which  is  the  standard  for  projecting 

school enrollments. In this method: 

The number of students  in a cohort  (a group of students  in a 

certain age group who move together through one grade level 

to the next) is tracked through past grades. 

 

Survival  rates  (ratios  of  the  number  of  students who  remain 

from  one  year  to  the  next)  are  calculated  from  historical 

enrollments. 

 

Prevailing  birth  rates  (for  kindergarten)  and  average  survival 

rates  (for  other  grades)  are  used  to  calculate  future 

enrollments. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 42 

As  warranted,  ratios  were  adjusted  slightly  to  reflect  major 

factors  identified  during  the  growth  analysis  such  as  the 

construction  of  additional  housing.  Since  the  cohort  survival 

method addresses students who are currently in the system, it 

tends to be fairly accurate from five to seven years. 

Three enrollment projection scenarios were developed, based 

on trends during the past seven years: 

Low  Range  ‐  based  on  the  average  enrollment  trends  from 

2007‐08  to  2013‐14.  It  assumes  that  the  longer  range  trends 

will prevail over the current faster growth rate and will have an 

average  annual  growth  rate  of  ‐0.4%  including  the  District’s 

Charter School. 

Mid  Range  ‐  based  on  the  average  enrollment  trends  of  the 

past  seven  years,  2007‐08  to  2013‐14, with  some  downward 

adjustment  for  the  middle  school,  consistent  with  current 

trends. This range  is considered to be the most  likely scenario 

since  it assumes continuing growth over the planning horizon. 

Its average annual growth  rate  is 2.5%  including  the District’s 

Charter School. 

High  Range  ‐  based  on  the  average  enrollment  trends  from 

2007‐08 to 2013‐14. This range assumes escalating elementary 

enrollment  that  progresses  through middle  and  high  schools. 

Its average annual growth  rate  is 4.0%  including  the District’s 

Charter School. 

See Figures 2‐36 to 2‐47. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 43 

Figure 2‐36:  CMSD District Schools Projected Enrollment Low‐High Range, 2014‐19 

Figure 2‐37:  District‐Wide School Projected Enrollment ‐ Moderate, 2014‐19 

Note:  District Charter School is NOT included in the above charts (see Figure 2‐38 for inclusion).  Figure 2‐38:  District‐Wide School Projected Enrollment By Grade Level, 2014‐19 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 44 

Elementary Forecast

109 124 135 99 113 123 104 119 127 108 123 134 106 121 131 107 122 133

553 591 613 538 575 588 489 523 533 515 550 576 534 571 592 525 561 582

436 510 581 433 505 572 404 470 536 382 446 509 428 501 567 445 522 588

469 525 582 452 521 601 434 512 587 407 479 553 396 465 528 447 522 588

435 496 547 474 543 605 462 542 620 444 527 600 422 499 575 413 487 554

431 488 542 433 511 570 471 557 620 466 553 630 453 545 615 438 523 598

444 496 555 432 505 564 438 526 594 471 563 630 480 573 647 464 570 636

2,875 3,229 3,554 2,860 3,272 3,623 2,801 3,248 3,617 2,792 3,241 3,632 2,820 3,275 3,655 2,840 3,307 3,678

Middle School Forecast

496 513 529 523 540 558 532 550 568 554 572 591 593 613 632 604 624 644

496 517 540 502 522 546 529 551 575 539 561 586 560 583 609 600 624 652

442 466 475 487 513 547 493 519 553 519 547 583 529 557 593 550 579 617

1,435 1,495 1,544 1,512 1,576 1,650 1,554 1,619 1,695 1,612 1,680 1,759 1,682 1,753 1,835 1,754 1,827 1,913

High School Forecast

489 516 542 444 490 517 486 540 573 491 546 587 518 575 619 527 580 630

455 465 460 461 497 517 419 472 496 459 520 546 464 526 560 489 555 590

397 415 421 401 428 431 407 458 489 370 435 464 404 480 504 409 485 525

355 376 403 351 377 396 363 389 408 373 416 459 341 396 433 364 436 473

1,695 1,771 1,826 1,657 1,792 1,860 1,674 1,860 1,966 1,692 1,918 2,057 1,727 1,977 2,116 1,788 2,055 2,218

6,005 6,495 6,924 6,029 6,640 7,133 6,030 6,727 7,278 6,096 6,839 7,448 6,228 7,005 7,605 6,382 7,189 7,809

-3.1% 4.8% 11.7% 0.4% 2.2% 3.0% 0.0% 1.3% 2.0% 1.1% 1.7% 2.3% 2.2% 2.4% 2.1% 2.5% 2.6% 2.7%

Jefferson Montesorri Charter School Forecast

139 193 239 138 192 246 140 195 246 142 195 246 146 196 247 148 199 250

6,145 6,688 7,162 6,167 6,832 7,379 6,169 6,922 7,525 6,238 7,034 7,694 6,375 7,200 7,853 6,529 7,388 8,059

-3.8% 4.7% 12.1% 0.4% 2.2% 3.0% 0.0% 1.3% 2.0% 1.1% 1.6% 2.3% 2.2% 2.4% 2.1% 2.4% 2.6% 2.6%

2014-15 2015-16 2016-17 2017-18 2018-19

CARLSBAD MUNICIPAL SCHOOLS DISTRICTWIDE ENROLLMENT PROJECTIONS 2014-2019

Total District Enrollment WITHOUT Charter School Enrollment

Total District Enrollment Including Charter School

2019-20

 

 

 

 

 

 

Figure 2‐39:  CMSD District Schools Projected Enrollment Elementary Low‐High Range, 2014‐19 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 45 

 

 

Figure 2‐40:  Pre‐K and Kindergarten Schools Projected Enrollment, 2013‐18  

Early Childhood Education Center Forecast

Pre- Kindergarten

Kindergarten 553 591 613 538 575 588 489 523 533 515 550 576 534 571 592 525 561 582

509 591 578 495 575 562 450 523 511 474 550 538 492 571 558 483 561 549

%Change -1.4% 5.3% 9.2% -2.7% -2.7% -4.0% -9.1% -9.1% -9.4% 5.3% 5.3% 8.2% 3.7% 3.7% 2.7% -1.7% -1.7% -1.7%

Total553 591 613 538 575 588 489 523 533 515 550 576 534 571 592 525 561 582

Pre- Kindergarten 109 124 135 99 113 123 104 119 127 108 123 134 106 121 131 107 122 133

Kindergarten

%Change 0.7% 14.7% 25.2% -9.1% -9.1% -9.1% 5.3% 5.3% 3.7% 3.7% 3.7% 5.4% -1.7% -1.7% -2.4% 1.1% 1.1% 1.8%

Total109 124 135 99 113 123 104 119 127 108 123 134 106 121 131 107 122 133

Total662 715 748 637 687 711 593 641 660 623 673 711 640 692 723 632 683 715

2019/2020

Dr Emmitt Smith ECC Forecast

School Name

Carlsbad Municipal Schools - Early Childhood & Kindergarten Projections

2014/2015 2015/2016 2016/2017 2017/2018 2018/2019

 

 

 

 

Figure 2‐41:  CMSD Elementary School Enrollment Projections, 2014‐19 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 46 

School Name

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 46 55 63 45 54 61 43 49 56 44 51 58 44 53 61 44 54 63

Second 46 48 58 46 53 65 44 53 59 42 48 57 44 53 58 46 54 62

Third 51 59 67 44 48 61 47 55 65 44 50 57 41 47 58 45 54 59

Fourth 50 55 64 50 62 69 44 50 63 49 55 68 44 51 59 45 50 62

Fifth 46 52 62 48 57 66 52 63 71 44 51 65 51 57 70 46 52 62

%Change -5.4% 6.8% 24.6% -2.4% 1.2% 2.4% -1.2% -1.4% -2.4% -2.9% -4.9% -2.6% 0.7% 2.2% 0.3% 0.8% 1.0% 0.7%

Total 238 269 314 233 272 321 230 269 314 223 255 305 225 261 306 227 264 309

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 48 55 66 46 54 64 42 49 58 43 49 58 47 57 66 49 59 64

Second 57 65 73 48 56 68 45 54 68 41 50 61 44 54 62 47 59 70

Third 56 67 71 56 68 75 49 58 72 46 57 70 43 54 64 45 56 67

Fourth 57 68 75 54 68 74 52 68 77 48 58 73 45 60 72 46 57 68

Fifth 59 68 76 55 70 77 53 70 78 50 69 75 46 62 74 44 62 74

%Change -11.1% 3.8% 15.8% -6.3% -2.5% -0.8% -6.6% -4.8% -1.5% -5.6% -5.5% -4.4% -1.3% 1.4% 0.6% 2.8% 2.5% 1.9%

Total 277 323 360 259 315 357 242 300 352 228 283 336 225 287 338 232 294 345

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 50 63 71 52 61 69 48 56 63 45 53 60 50 61 69 53 62 70

Second 62 69 76 54 65 73 52 62 72 50 59 65 49 57 65 55 67 73

Third 54 62 64 65 71 78 53 66 75 53 64 73 53 62 68 52 59 68

Fourth 41 48 53 55 63 65 62 70 79 54 67 76 55 67 75 54 63 69

Fifth 56 63 69 43 50 55 54 62 66 60 68 78 57 69 77 56 67 75

%Change -9.6% 5.2% 14.9% 2.5% 1.8% 2.1% -0.1% 1.6% 4.4% -2.1% -1.5% -1.1% 0.5% 1.6% 0.8% 1.6% 0.7% 0.2%

Total 262 305 333 269 310 340 269 315 355 263 311 351 264 316 354 269 318 355

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 50 59 70 51 62 70 47 56 65 44 53 61 54 63 72 56 66 74

Second 67 76 80 55 63 73 53 63 71 48 57 67 49 58 62 57 67 75

Third 61 68 72 71 79 83 58 67 75 55 66 73 53 62 71 53 61 66

Fourth 67 73 78 61 72 76 73 81 85 60 69 77 60 71 77 56 66 75

Fifth 64 71 74 67 76 80 60 73 79 70 79 83 64 74 78 63 74 78

%Change -6.3% 5.1% 13.3% -1.2% 1.1% 2.2% -4.9% -3.1% -1.6% -4.5% -4.6% -4.0% 0.9% 1.1% -0.1% 1.8% 1.7% 2.1%

Total 309 347 374 306 351 382 291 340 376 278 324 361 280 328 360 285 334 368

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 50 58 66 54 61 70 48 55 66 43 51 60 50 59 68 51 60 69

Second 51 58 64 50 61 69 55 63 72 47 57 67 45 53 62 52 62 70

Third 46 52 57 50 59 67 51 64 71 56 64 73 49 59 69 47 56 64

Fourth 45 50 56 42 51 59 49 59 66 48 61 68 55 62 71 48 62 67

Fifth 33 38 43 44 52 57 43 53 61 50 60 66 50 62 70 57 66 73

%Change -6.3% 5.7% 18.7% 6.4% 11.7% 12.6% 2.5% 3.5% 4.4% -0.6% -0.6% -0.7% 1.4% 0.8% 1.7% 2.5% 4.0% 1.0%

Total 226 255 286 240 284 322 246 294 336 245 293 334 248 295 339 255 307 343

Carlsbad Municipal Schools Elementary Enrollment Projections

Craft Elementary Forecast

Hillcrest Elementary Forecast

Joe Stanley Smith Elementary Forecast

Monterrey Elementary Forecast

Pate Elementary Forecast

2019/20202014/2015 2015/2016 2016/2017 2017/2018 2018/2019

 

Figure 2‐42:  CMSD Elementary School Enrollment Projections, 2014‐19 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 47 

School Name

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 51 60 68 50 58 67 45 53 60 40 48 56 48 56 64 53 61 69

Second 48 53 60 52 61 70 49 59 69 46 54 62 41 48 57 48 57 65

Third 45 50 60 47 54 63 51 61 73 50 60 70 47 54 63 41 49 60

Fourth 39 46 53 44 50 64 47 55 65 52 62 74 51 61 71 48 55 67

Fifth 47 55 63 40 47 58 46 53 66 48 56 68 53 64 76 52 62 74

%Change -6.3% 6.5% 23.7% 0.8% 2.4% 5.2% 2.1% 4.4% 3.6% -1.0% -0.7% -1.2% 1.3% 1.4% 0.6% 1.4% 0.2% 1.1%

Total 231 263 306 233 269 321 238 281 333 236 279 329 239 283 331 242 283 335

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 57 69 76 55 67 74 54 66 72 50 60 67 55 65 72 58 71 80

Second 57 66 73 63 70 79 55 69 76 54 67 75 50 62 69 59 66 73

Third 46 51 60 58 69 74 65 74 82 56 72 80 56 71 78 52 64 72

Fourth 45 54 62 45 53 62 57 71 77 64 76 85 55 74 83 58 74 81

Fifth 55 59 68 47 58 67 47 58 68 59 78 84 67 81 91 58 82 90

%Change -8.3% 5.9% 19.8% 3.5% 6.1% 5.1% 3.8% 6.4% 5.4% 1.9% 4.8% 3.9% -0.2% -0.7% 0.5% 0.7% 1.6% 1.1%

Total 260 300 339 269 318 356 279 338 376 284 354 390 283 352 392 285 357 397

Kindergarten Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi Low Mid Hi

First 83 91 100 79 88 97 77 86 95 72 80 89 80 87 96 82 88 98

Second 80 90 98 84 92 105 80 89 99 77 87 100 74 81 93 82 91 100

Third 78 88 95 83 96 105 88 98 107 83 95 104 80 91 103 77 87 98

Fourth 86 94 102 81 93 101 87 101 109 92 103 110 87 98 108 84 97 108

Fifth 84 90 99 88 96 103 83 95 105 89 102 111 94 104 111 89 104 109

%Change -7.4% 2.2% 11.6% 1.2% 2.7% 3.4% -0.3% 1.0% 0.7% -0.2% -0.3% -0.1% 0.5% -1.2% -0.8% -0.2% 0.9% 0.5%

Total 410 453 495 415 465 512 414 470 515 413 468 515 415 462 510 414 467 513

Total 2,214 2,514 2,807 2,224 2,585 2,913 2,208 2,607 2,957 2,170 2,568 2,921 2,180 2,583 2,932 2,208 2,623 2,963

Puckett Elementary Forecast*

Sunset Elementary Forecast

Riverside Elementary Forecast*

Carlsbad Municipal Schools Elementary Enrollment Projections

2019/20202014/2015 2015/2016 2016/2017 2017/2018 2018/2019

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 48 

  Figure 2‐43:  Projected Middle School Student Enrollment ‐ Low‐High Range, 2014‐19 

 

Figure 2‐44:  Projected Middle School Student Enrollment, 2014‐19 (Grade Reconfiguration effective 2014/15) 

School Name

Sixth 496 513 529 523 540 558 532 550 568 554 572 591 593 613 632 604 624 644

Seventh

Eighth

%Change -17.9% -15.1% -12.4% 5.4% 5.4% 5.4% 1.8% 1.8% 1.8% 4.1% 4.1% 4.1% 7.0% 7.0% 7.0% 1.8% 1.8% 1.8%

Total 496 513 529 523 540 558 532 550 568 554 572 591 593 613 632 604 624 644

Sixth

Seventh 496 517 540 502 522 546 529 551 575 539 561 586 560 583 609 600 624 652

Eighth 442 466 475 487 513 547 493 519 553 519 547 583 529 557 593 550 579 617

%Change 8.9% 14.0% 17.7% 5.4% 5.4% 7.6% 3.3% 3.3% 3.2% 3.5% 3.6% 3.6% 3.0% 3.0% 2.9% 5.6% 5.6% 5.6%

Total 939 982 1,015 989 1,035 1,092 1,021 1,069 1,128 1,058 1,107 1,168 1,089 1,140 1,202 1,150 1,203 1,269

TOTAL 1,435 1,495 1,544 1,512 1,576 1,650 1,554 1,619 1,695 1,612 1,680 1,759 1,682 1,753 1,835 1,754 1,827 1,913

2014/2015 2015/2016 2016/2017 2017/2018 2018/2019 2019/2020

P.R. Leyva Middle School Forecast

Alta Vista 6th Grade Academy Forecast

Carlsbad Municipal Middle School Enrollment Projections

 

      

Figure 2‐45:  Projected High School Student Enrollment ‐ Low‐High Range, 2014‐19 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 49 

 

 

Figure 2‐46:  Projected High School Student Enrollment, 2014‐19 

Carlsbad Municipal Schools High School Enrollment Projections

School Name

Ninth 489 516 542 444 490 517 486 540 573 491 546 587 518 575 619 527 580 630

Tenth 455 465 460 461 497 517 419 472 496 459 520 546 464 526 560 489 555 590

Eleventh 397 415 421 401 428 431 407 458 489 370 435 464 404 480 504 409 485 525

Twelfth 355 376 403 351 377 396 363 389 408 373 416 459 341 396 433 364 436 473

%Change 1.7% 6.3% 9.5% -2.3% 1.2% 1.9% 1.0% 3.8% 5.7% 1.1% 3.1% 4.6% 2.0% 3.1% 2.9% 3.6% 4.0% 4.8%

Total 1,695 1,771 1,826 1,657 1,792 1,860 1,674 1,860 1,966 1,692 1,918 2,057 1,727 1,977 2,116 1,788 2,055 2,218

Carlsbad High School Forecast

2014/2015 2015/2016 2016/2017 2017/2018 2018/2019 2019/2020

 

 

 

 

 

 

Figure 2‐47:  Projected Alternative/ Charter School Enrollment, 2014‐19 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 50 

Kindergarten 17 20 23 15 19 23 17 21 24 16 20 23 16 20 23 14 18 20

First 15 19 23 12 17 21 13 16 20 12 15 19 13 17 21 13 18 22

Second 13 18 22 15 18 22 15 21 24 15 20 24 15 19 23 17 22 27

Third 8 12 17 12 16 18 11 15 18 13 16 21 11 15 20 12 14 18

Fourth 16 22 27 9 14 18 13 18 21 12 17 20 15 18 22 13 17 22

Fifth 5 8 13 15 21 26 9 14 19 13 18 22 12 17 21 15 18 22

Sixth 14 18 21 5 7 13 12 17 21 7 13 17 12 16 21 11 15 19

Seventh 12 16 19 12 17 22 4 6 12 11 15 19 6 11 16 10 14 19

Eighth 8 11 15 11 17 21 12 17 23 5 7 13 11 16 21 6 12 17

Ninth 9 14 17 7 15 18 12 16 21 11 16 21 5 7 10 10 15 20

Tenth 7 10 14 10 13 17 8 14 18 13 16 20 12 15 18 5 8 11

Eleventh 9 13 16 6 9 13 8 11 15 6 12 15 11 14 18 10 13 16

Twelve 6 9 12 8 10 14 5 8 12 8 10 13 7 11 14 11 14 18

%Change -27.0% 0.8% 24.9% -1.1% -0.3% 3.1% 1.2% 1.5% 0.1% 1.4% -0.1% 0.0% 3.3% 0.5% 0.4% 0.9% 1.7% 1.2%

Total139 193 239 138 192 246 140 195 246 142 195 246 146 196 247 148 199 250

2019/2020

Jefferson Montessori Forecast (District Charter)

School Name

Carlsbad Municipal Schools - District Charter School Projections

2014/2015 2015/2016 2016/2017 2017/2018 2018/2019

 

2.4.3   Methods Used to Project CMSD Enrollments 

Analysis of History 

First,  birth  trends  were  compared  to  kindergarten  trends.  

There  has  been  a  correlation  between  the  birth  rates  and 

students entering  kindergarten. Carlsbad  is  the  largest  school 

district in Eddy County and is the territory for which birth data 

can  be  studied.    The  birth  numbers  portend  a  rise  in 

elementary enrollment numbers over the next five years.  

 

The historical data  includes birth  trends only emerging at  the 

outset of the economic recession.   The recession has had two 

demographic  effects  on  Carlsbad  and  the  state  and  nation.  

First,  birth  rates  have  declined  (however  not  below  historic 

rates  for  Eddy  County),  and  appears  to  be  temporary  as 

families  delay  having  children  in  the  face  of  difficult  times.  

Second,  the  economic  recession  has  caused  a  notable 

reduction  in  migration  as  people  “stay  put”  in  the  face  of 

uncertainty,  including remaining  in multi‐generational housing 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 51 

situations.    Immigration  to  the  United  States  has  fallen  off 

dramatically according to US Census Bureau estimates. 

  

The  projections  employ  cohort  progressions,  for  example, 

ratios of  fifth graders  this year  to  fourth graders  last year.   A 

historical review of progression ratios was performed with and 

without  the  charter  school,  Jefferson  Montessori.    It  is  clear 

from  reviewing  these  data  that  Jefferson  Montessori  was 

growing  in  the  past  five  years  as  a  result  of  reductions  in 

enrollment potential for other schools in the district.  However, 

Jefferson  Montessori  has  no  further  plans  for  net  growth 

beyond current students, or student cohort numbers. 

 

United States census data shows a steady population  increase 

for  the  county during  the decade  since  the 2010  census, and 

these  data  form  a  basis  for  enrollment  projections.    The 

progression  ratios  confirm  that  there  has  been  some  net 

migration  growth  in  the  school  district  due  to  improving 

economic conditions.   

Projection Overview 

The  method  employed  is  a  modified  top‐down  method, 

meaning district  totals are projected  first.    In order  to  initiate 

the  projections  for  district  totals,  kindergarten  must  first  be 

projected and synchronized with birth trends.  Enrollments are 

within grade  for  this phase of calculation, and  include Special 

Ed C and Special Ed D students. 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 52 

The historical pattern of the progression ratios by grade shows 

stability  once  all  district  students  have  been  accumulated, 

including  Jefferson  Montessori  Charter  School.    The  grade 

progression  ratios  are  then  projected,  giving  more weight  to 

the most recent numbers.   

 The economic recession has not  impacted  the demography of 

Eddy  County  as  significantly  as  the  state  and  nation.    All 

indications are that recovery from the recession is happening in 

Carlsbad.    More  recent  historical  trends  are  expected  to  be 

good indicators to project the five‐year future.   

 The  birth  synchronized  Kindergarten  numbers  are  distributed 

to the ECEC and  Jefferson Montessori according to their most 

recent  proportions.    This  arithmetic  is  simple,  and  ECEC  has 

almost all the kindergarteners in the district. 

 For  all  but  Jefferson Montessori,  elementary  schools  use  the 

district  average  progression  ratios  applied  to  each  school, 

which  maintains  the  unique  school‐level  cohort  sizes  that 

existed  in  fall  2013.    Each  elementary  school  is  progressed 

individually in the projection until transition to middle school. 

The transition to middle school numbers returns to the district 

totals,  also  tracking  cohorts,  and  projected  totals  are 

proportionally  allocated  to  the  two  middle  schools.    With 

entering  cohorts  computed,  the  existing  cohorts  in  the  two 

middle schools are each progressed through grade according to 

district  progression  average  but  applied  to  each  school’s 

unique cohort size pattern.   

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 53 

Returning  to  the  transition district  total progressed numbers, 

entering high school numbers are apportioned to Carlsbad High 

based  upon  the  proportion  in  2013,  and  then  progressed  by 

grade to 12th grade.   As a comment, the progression ratios do 

not assume any change in drop‐out rates, which are a factor in 

cohort losses in Carlsbad. 

 All  of  those  computations  leave  a  residual  set  of  numbers, 

which  were  placed  into  Jefferson  Montessori  Charter  and 

Grace House  according  to  the  evaluation  of  cohort  sizes  and 

past  trends  now  tempered  by  no  expectation  of  future 

significant  growth  in  either  physical  facility.    Jefferson 

Montessori  has  some  growth  potential  already  built  into 

existing cohort sizes and district progression rates. 

2.4.4 Conclusions 

Enrollment  projections  will  increase  across  the  district  by 

approximately  2.5%  annually  as  a  mid‐range  projection  by 

2019. District elementary schools are expected to be impacted 

the most with an increase in enrollment as they have the least 

capacity to absorb additional students. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 54 

2.5 Utilization and Capacity 

In order to calculate the capacity of a district’s school facilities, 

it  is  important  to  first determine  the  total  space available  for 

teaching and how it is currently being utilized. Utilization is the 

total available space  for  teaching and how  this space  is being 

used,  and  capacity  is  the  amount  of  space  available  for 

teaching in the context of the current educational program of a 

school. 

 

Guidelines  developed  by  the  state  were  used  in  the 

determination  of  how  each  space  was  classified  in  terms  of 

utilization and capacity. A chart for each school was completed. 

Utilization  and  capacity  changes  from  year  to  year  are 

dependent  upon  the  use  of  the  facility;  therefore,  an  annual 

update of the use of each facility is recommended. 

 

Methodology  used  to  determine  utilization  and  capacity 

involved the following steps: 

1. Each  principal  was  asked  to  review  and  update 

information; 

2. Programs  and  current  on  site  educational  strategies 

were discussed and documented; 

3. A detailed walk  through  inventory of each  school was 

conducted in conjunction with a detailed assessment of 

the physical facilities; 

4. A classification of the current use and the availability or 

deficit  of  space  for  the  current  educational  programs 

was completed; 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 55 

5. Recommendations  based  on  additions  and 

reconfiguration of existing space were compiled; 

6. Additional  information  and  comments  were 

documented; 

7. A  summary of  these  findings was  sent  to  the District’s 

Superintendent for review. 

2.5.1 Existing and Future Classroom Needs 

An analysis of the future classroom needs is based on a facility 

inventory,  demographic  analysis,  and  capacity  and  utilization 

analysis.    The  conclusion  is  that  the  District  will  require 

additional classrooms to satisfy changing demographics before 

2018.    Additionally,  the  District  has  indicated  the  desire  to 

renovate  and  replace  aging  school  facilities.    The  following 

analysis was completed to aid in this decision. 

 An  identification and  inventory of all space within each school 

was conducted  in 2014 by the FMP planning team. A detailed 

inventory  of  each  school  includes  information  regarding  the 

number of classrooms and their current use (regular classroom, 

special education, music, art, etc.) as well as other spaces used 

for teaching.   

 Classroom  capacity  is  based  on  using  State  maximum  Pupil 

Teacher Ratios.   The District  strives  to  reduce  these  ratios  to 

improve educational  services.   Currently  the district has eight 

elementary schools, two middle schools, one high school, one 

kindergarten  (early  childhood)  center,  one  pre‐kindergarten 

center, and one K‐12 charter school. 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 56 

The  demographic  analysis  for  each  school  shows  some 

variables  in enrollment  from  year  to  year, with  some  growth 

enrollment  due  to  changing  economic  conditions  (incoming 

business  growth)  and  increased  birth  rates.  In  response,  the 

consolidation of  some  facilities and addition of others will be 

needed.    A  utilization  and  capacity  chart  was  developed  for 

each school and shown in the School Facility Summaries in the 

Appendix.    The  following  Capacity  Analysis  Summary  Table 

Figure 2‐48 was developed  from the  information generated  in 

these charts and updated in 2014.  

 

Figure 2‐48:  School Capacity Summary 

 

 

 

 

 

 

 

 

 

 

 

 

 

The  utilization  of  the  schools  is  shown  on  the  following 

utilization analysis summary.  The elementary school utilization 

is between 93 and 100 percent utilization.  The 93% utilization 

is  found  in only one  school,  all other elementary  schools  are 

Capacity Analysis

School Name Enrollment CapacityAvailable Seats 2014

Available Seats 2018

Growth/ Decline

EM Smith 109 67 (43) (55) 12

ECE 562 423 (139) (148) 9

Jefferson Montessori 204 269 65 73 (8)

Craft 252 258 6 (3) 9

Hillcrest 311 302 (9) 15 (24)

Joe Stanley 290 280 (9) (35) 26

Monterrey 321 325 4 (3) 7

Pate 254 258 4 (37) 41

Pucket 256 238 (19) (46) 27

Riverside 323 260 (63) (92) 29

Sunset 443 433 (10) (29) 19

Alta Vista 586 714 128 101 27

PR Levya 834 979 145 (161) 306

Carlsbad HS 1651 2118 467 141 326

Totals 6396 6924 527 (279) 806

ECEC 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 57 

utilized at 96‐100%.   The utilization of the middle schools and 

high school is low at 59 to 75%.  

 

 Utilization  and  capacity  analysis  support  the  conclusion  that 

there  is  sufficient  space  available  in  the  middle  and  high 

schools  to  accommodate  growth.    The  Facilities  Master  Plan 

emphasizes primarily upgrades to the Elementary Schools.  It is 

recommended  that  future  master  planning  efforts  consider 

changes  at  the  high  school  and  middle  school  to  increase 

efficiency and utilization.   

 

Figure 2‐49:  Utilization Summary 

 

 

 

 

 

 

 

 

 

 

 

 

 

The current number of available elementary school seats 

(capacity shown in Figure 2‐48) not including special use spaces 

for music, computer labs, bilingual programs and special 

education in ½ size classrooms, is ‐94 seats (calculated by the 

Utilization Analysis

School Start Time End Time # Periods Utilizaton Notes

EM Smith 8:00 2:25 100% High

ECEC 8:00 2:30 100% High

Jefferson Mont 8:00 3:30 6 100% High

Craft 8:00 2:50 5 100% High

Hillcrest 8:00 2:50 5 93% High

Joe Stanley 8:00 2:50 5 100% High

Monterrey 8:00 2:50 5 96% High

Pate 8:00 2:50 5 100% High

Puckett 8:00 2:50 5 100% High

Riverside 8:00 2:50 5 100% High

Sunset 8:00 2:50 5 100% High

Alta Vista 8:00 3:30 8 59% Low

PR Leyva 8:00 3:30 8 59% Low

Carlsbad HS 8:00 3:40 7 74% Adequate

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 58 

number of classrooms times the potential students per room 

minus the current enrollment).  By 2018, the number of 

additional needed seats will be 228, or approximately 10 

classrooms. 

 

Figure 2‐50:  Elementary School Capacity 

 

 

 

 

 

 

 

 

 

 

 

 

 

This deficit of  seats  indicates  that, due  to  the age and  size of 

some elementary schools, consolidation of boundary areas and 

replacement  of  at  least  some  facilities  will  be  needed  to 

provide additional capacity and improve programs.   

 

Elementary  school  re‐districting  is  recommended  to  create 

evenly populated  schools  in  the  600  student  range –  as  they 

are easier  to maintain and more efficient  in  terms of  staffing 

and facilities use. 

 

‐200

‐100

0

100

200

300

400

500

Craft Hillcrest JoeStanley

Monterrey Pate Pucket Riverside Sunset

Stu

den

ts

Enrollment

Capacity

Available Seats 2014

Available Seats 2018

Elementary Capacities 2014-18

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 59 

Currently,  the middle  schools  and high  school have  sufficient 

capacity  to  accommodate  current  and  projected  school 

populations.    See  Figure  2‐51.  The  middle  schools  have  273 

seats currently open, and the high school has 467 open seats.  

This available capacity  is expected to shrink  in 2018, however, 

to  ‐60 open middle school seats  in 2018, and 141 high school 

seats.   

 

Figure 2‐51:  Middle and High School Capacity 

 

 

 

 

 

 

(500)

0

500

1000

1500

2000

2500

Alta Vista PR Levya Carlsbad HS

Enrollment

Capacity

Available Seats 2014

Available Seats 2018

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 60 

2.5.2 Student Capacity Analysis at Each School Site 

The school capacities were analyzed using both the classroom 

square  footage  and  the  PTR  capacity.    A  summary  of  each 

school’s capacity and utilization analysis: 

 

Early Childhood Education Center 

ECEC  current  school  capacity  is  423  based  on  PTRs  of  15 

students per teacher.  The current student population is 562; a 

maximum  projection  of  710  or  an  increase  of  148  students.  

The  school  currently  is deficient by 139  seats  and  this deficit 

will  increase  to  148  by  2018.    Approximately  ten  (10)  new 

classrooms will be needed. 

 

E.M. Smith Pre‐School 

E. M. Smith current school capacity  is 67 based on PTRs of 10 

students per  teacher.   The current  student population  is 109.  

Overall  projected  population  could  increase  to  164  leaving  a 

deficit of 55  seats. Five new classrooms will be needed  if  the 

program were  to  remain at  its current  location. The district  is 

considering to relocate the program to the Puckett Elementary 

site once the new Pate Elementary is constructed. 

 

Craft Elementary School 

Craft  current  school  capacity  is  258 based on  classroom  size.  

The current student population  is 252; a maximum projection 

of 261 or an increase of 9 students.  The school currently has 3 

open seats and will be deficit by 3 in 2018.  No classrooms will 

be needed. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 61 

Hillcrest Elementary School 

Hillcrest current school capacity is 302 based on classroom size.  

The current student population  is 311; a maximum projection 

of 287 or a decrease of 15 students.  The school currently has a 

deficit of 9 seats but will have 15 available seats by 2018.   No 

new classrooms needed. 

 

Joe Stanley Elementary School 

Joe Stanley current school capacity  is 280 based on classroom 

size.    The  current  student  population  is  290;  a  maximum 

projection  of  316  or  an  increase  of  36  students.    The  school 

currently has a deficit of 10  seats and will be deficient by 56 

seats by 2018.   Approximately two  (2) new classrooms will be 

needed. 

 

Monterrey Elementary School 

Monterrey current  school capacity  is 325 based on classroom 

size.    The  current  student  population  is  321;  a  maximum 

projection  of  328  or  an  increase  of  3  students.    The  school 

currently has 4 available seats and will be deficient 3 seats by 

2018.  No new classrooms needed. 

 

Pate Elementary School 

Pate  current  school  capacity  is  258  based  on  classroom  size.  

The current student population  is 254; a maximum projection 

of 295 or an increase of 41 students.  The school currently has 

4 available seats and will be deficient 37 seats by 2018.  Two (2) 

new classrooms would be needed. 

Puckett Elementary School 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 62 

Puckett current school capacity is 238 based on classroom size.  

The current student population  is 254; a maximum projection 

of 283 or an increase of 27 students.  The school currently has 

a deficient of 19 seats and will be deficient 46 seats by 2018.  

Two (2) new classrooms would be needed. 

 

Riverside Elementary School 

Riverside  current  school  capacity  is  260  based  on  classroom 

size.    The  current  student  population  is  323;  a  maximum 

projection  of  352  or  an  increase  of  29  students.    The  school 

currently has a deficit of 63 seats and will be deficient 92 seats 

by 2018.  Five (5) new classrooms would be needed. 

 

Sunset Elementary School 

Sunset current school capacity  is 433 based on classroom size.  

The current student population  is 443; a maximum projection 

of 462 or an increase of 19 students.  The school currently has 

a deficit of 10 seats and will be deficient by 29 seats by 2018.  

Two (2) new classrooms would be needed. 

 

Alta Vista Middle School 

Alta Vista’s current school capacity  is 714 based on classroom 

size.   The current student population  is 604 students.   Overall 

projected population will  increase to 613 with reconfiguration 

into  the  district’s  6th  Grade  Academy  in  2014/15.    There  is 

sufficient  space  to  accommodate  changing  programs  and 

additional students.   

  P. R. Leyva Middle School 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 63 

P R Leyva’s current school capacity  is 979 based on classroom 

size.   The current student population  is 862 students.   Overall 

projected  population  will  increase  to  1,140  with 

reconfiguration  to a 7th  / 8th Grade school  in 2014/15.   There 

will be a deficit of 131 seats by 2018 necessitating six (6) new 

teaching spaces. 

 

Carlsbad High School 

Carlsbad High School’s  current  school  capacity  is 2,118 based 

on  classroom  size  and  2,040  based  on  PTRs.    The  current 

student  population  is  1,667  students.    Overall  projected 

population will  increase  to 1,977.  There  is  sufficient  space  to 

accommodate changing programs and additional students.   

 

Jefferson Montessori Academy 

Jefferson Montessori Academy’s current school capacity is 269.  

The  current  student population  is 191  students,  kindergarten 

through  twelfth grade.   There are currently 78 seats available 

and  will  be  73  seats  available  in  2018.  Classroom  space  is 

sufficient in the near future. 

2.5.3 Special Factors Influencing Facility Use 

Special  factors  influencing  the  facility  use  includes  special 

programs  for  Music,  Title  I  and  Bilingual  classes  at  the 

elementary school  level.   The special education programs also 

play  a  major  role  in  space  use  beyond  general  classrooms.  

Although  most  schools  currently  have  inclusion,  space  for 

resource rooms and Level D classrooms are present.   

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 64 

The District has open enrollment that allows students to attend 

schools  outside  of  their  zone  if  there  is  capacity  within  the 

school. 

 

Another  influence  is  the  current  configuration  of  the 

boundaries.    A  review  of  the  map  shows  that  some  schools 

draw  from  pockets  of  geographical  area.    Re‐districting  has 

been  discussed  in  above  and  is  recommended  as  part  of  the 

school replacement effort by the district.   No other  influences 

were identified. 

2.5.4 Strategies to Accommodate Needs 

The  CMSD  will  continue  to  experience  growth  over  the  next 

five  years  due  to  expanded  economic  growth  and  increased 

birth  rates  in  the  local  area.    These  factors  are  expected  to 

impact the district primarily at the elementary level.   

 

In  response  to  an  overall  growth  of  approximately  241 

elementary  students  by  2019,  and  the  need  to  improve 

elementary educational programs district wide  the district 

intends  to  replace  smaller  elementary  schools  with  new 

600  student  schools.    These new  schools will  provide  the 

needed  additional  capacity  as  well  as  operate  more 

efficiently  and  be  able  to  provide  more  programs  to 

students  such  as  music,  PE,  art,  and  extracurricular 

activities. 

 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 65 

The main  focus of  the 2014  ‐2019  Facilities Master Plan  is  to 

address  the  needs  of  the  Elementary  Schools.    The  District’s 

Elementary  Schools  were  all  constructed  between  1920  and 

1956. 

 

One of the District school goals is to upgrade all Elementary 

Schools  to  a  consistent  educational  environment  by 

providing  program  equity  at  all  schools.    Therefore,  the 

majority  of  projects  identified  are  Elementary  School 

replacements.   

Four  elementary  schools  have  been  identified  for  facility 

replacement.  Pate, Riverside, Sunset and Joe Stanley Smith 

Elementary  Schools  have  determined  by  the  District’s 

Facilities Committee for replacement and funding has been 

approved by the district’s voters through the February 2014 

GO Bond Election.  Two of schools have sufficient site area 

to build new facilities, improve school access, student drop‐

off,  parking,  playgrounds,  and  other  school  infrastructure 

needs.    However,  it  is  recommended  that  both  Pate  and 

Riverside  Elementary  School  sites  be  removed  to  new 

locations.   Once the new schools are constructed, the only 

remaining  original  elementary  school  will  be  Hillcrest 

Elementary. 

Once the new schools are constructed, re‐districting of the 

elementary  school  zones  to  evenly  disperse  the  student 

populations at each school will be required. 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 66 

2.6 Technology 

Carlsbad Municipal School District has an IT department which 

strives to keep the district and  its students current  in terms of 

available  technology  and  the  necessary  infrastructure.  

Inasmuch,  the  district  has  implemented  a  formal  technology 

plan.    The  most  current  version,  the  2012‐2014  Technology 

Plan, is included in the appendix of the Master Plan.   

The goals of the plan: 

Assure  that  at  every  grade  level,  students  progress  to 

become skilled computer users. 

Introduce  students  to  a  broad  array  of  technological 

skills with  opportunities  to develop  specialized  skills  in 

their interest area. 

Integrate  technology  as  part  of  each  teacher’s 

instructional tools by providing the necessary leadership 

and  skills  to  implement  and  support  a  technologically 

assisted plan of instruction. 

Through  technology,  foster  student  instruction  beyond 

the traditional school day and year. 

Develop  a  capital  improvements  purchase,  placement 

and replacement schedule.  

Develop,  implement  and  upgrade  the  systems  to 

manage  the  district’s  data  in  an  integrated  and 

computerized manner 

 

CMSD believes the District must strive to provide students with 

varied  experiences  to  enhance  the  development  of  creative 

and problem solving skills.  In the technological realm, students 

should be exposed to a variety of technological equipment and 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 67 

software.    Multiple  facet  exposures  equip  the  student  to 

evaluate  and  determine  which  tools  best  meet  personal  and 

professional objectives.  To this end, the District has computer 

labs,  smart  labs,  classroom  computers  and  software  in  place 

and available for use  in meeting the district’s Educational Plan 

for  Student  Success  (EPSS)  goals  and  for  meeting  state 

technology standards 

 

Professional  development  is  recognized  as  an  essential 

component  towards  teacher  effectiveness  in  the 

implementation of technology based curriculum.    In response, 

the  Technology  Plan  devotes  an  entire  section  to  define 

strategies for academic achievement and teacher effectiveness.   

 

The administrative needs of the district cover a wide range of 

functions:   

Student Information System (Principal’s Aide) for collecting 

and  reporting  consistent  information  regarding  student 

attendance,  grades,  graduation  rates  and  indicators  for 

meeting state standards and benchmarks.  

Electronic  Grade  Book  (Teacher’s  Aide)  for  input  and 

maintenance  of  student  grades  and  attendance  at  the 

classroom  level.   This  information  is  then  transferred  into 

the  student  information  system  to  produce  progress 

reports, report cards and transcripts. 

Finance  System  for  tracking  and  maintaining  all  funds 

received and all expenses on an annual basis.  Also includes 

an inventory tracking system of all capital outlay purchases. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 68 

Cafeteria System  for  tracking and maintenance of  student 

meals accounts. 

Library  System  for  the  tracking  and  maintenance  of  all 

library  materials  and  for  progress  reports  on  the  use  of 

these materials. 

The  utilization  of  video  cameras  in  crucial  surveillance 

areas. 

 

All  of  the  technology  labs  and  classroom  computer  units  are 

replaced on a rotational basis of approximately five to six years 

to  insure that the hardware  is the most current.   All operating 

system  software  installed  on  these  units  has  built‐in 

accessibility features. 

 

The Facilities Master Plan will provide funds that will utilize the 

existing  data  infrastructure  to  provide  improved 

communications District‐wide.   In addition, funds are provided 

to  increase  video  surveillance  at  the middle  school  level.   All 

other  District  needs  will  be  provided  with  HB‐33  funds  as 

defined in the Technology Plan. 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 69 

2.7 Energy Management Program 

The  Carlsbad  Municipal  School  District  has  made  energy 

reduction a primary goal  in all new projects and  renovations.  

Replacement  of  single  pane  windows  with  double  paned 

windows at  the Middle  Schools and  replacement of ballasted 

roofs with TPO, white reflective roofs are two of the initiatives 

the District has employed  in recent years.    It  is recommended 

that  as  major  projects  for  the  Facilities  Master  Plan  are 

implemented  that  the  following  energy  saving  initiatives  be 

considered: 

 

1. Lighting upgrades 

a. Lighting  accounts  for  35%  of  building  energy  use  (E 

source) 

Use better  lighting  technologies:   T8  lamps,  reflectors, 

compact fluorescents “High Performance” T8 lamps are 

a good option for retrofits because they are available in 

4’  lengths  and  can  be  used  to  replace  T12  or  less 

efficient T8.   T5  lamps are more efficient, but currently 

only come in metric sizes. 

Electronic  ballasts  average  12%  more  efficiency  than 

magnetic ballasts 

b. Controls 

Occupancy sensors 

Scheduling 

Daylight  harvesting  –  continuous  dimming  via 

photo‐sensor technology 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 70 

Demand  response  –  automatic  feedback  from 

energy management system/utility use signals 

c. Operations and Maintenance 

Manage lamp lumen depreciation 

Eliminate dirt accumulation 

Control system maintenance 

Control purchasing and inventory 

d. Daylighting 

Use highly reflective paints 

Light pipes to deliver light from roof or exterior wall 

mounted reflectors 

2. Reduce Supplemental Loads 

a. Corporate purchasing policy 

Energy Star or other high performance qualification 

DOE procurement policies (FEMP) 

EPA procurement resources 

Employee energy conservation training 

b. Upgrade the building envelope (general) 

Increase insulation values  

Decrease infiltration 

Manage radiation 

c. Upgrade the building envelope (windows) 

Window  films  –  retro‐application  to  reduce  heat 

transfer  ($1.35  ‐  $3.00/SF  installed,  energy  star 

building upgrade manual) 

Interior  window  shading  –  blinds,  retro‐fit  light 

shelves 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 71 

Exterior  shading  –  exterior  blinds,  shade  screen, 

awnings,  overhangs,  vegetation  (trees,  bushes, 

vines) 

New  window  upgrade  –  double  glazing,  low‐e, 

spectrally selective glass, gas fill, thermal break. 

d. Upgrade the building envelope (roof) 

Lower  roof  surface  temperature  by  50 ̊‐70 ̊F  with 

highly reflective surface 

Insulate  around  structural members  for  internally 

insulated roofs 

3. Ventilation/Air Handling System 

a. Optimize Zone‐Level Performance 

Zone mixing dampers 

Reheat coils 

Thermostat control (recalibrate) 

Prevent overcooling 

Disable reheat systems in summer months 

Regulate  static  pressure  (check  static  balancing 

dampers) 

b. Convert constant volume system to variable volume  

Achieve approximately 40% air volume reduction 

Average  costs  are  between  $1‐$4/SF,  Energy  star 

building upgrade manual 

c. Fan Sizing 

Replace oversize fans 

Install high efficiency motors, energy efficient belts, 

and variable speed drives, larger pullys 

Increase equipment life + occupant comfort 

d. Modify Controls 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 72 

Optimize  schedules  –  adjust  per  seasons 

/occupancy 

Supply air temperature set point adjustment 

Pressure modification 

e. Economizer  cooling  (must  consider  ventilation/IAQ 

issues) 

Basic dry‐bulb economizer 

Enthalpy economizer 

Differential enthalpy economizer 

f. Demand‐controlled ventilation 

CO2 sensors with feedback to outside air intake 

Can  save  $.05‐$1.00/SF/year,  Energy  Star building 

upgrade manual 

4. Heating and Cooling 

a. Central heating systems – boilers and furnaces 

Boiler  Tune‐up  –  water  treatment,  air/fuel  ratio, 

boiler pressure,  steam  leaks,  clean heat exchange 

surfaces  

Boiler system retro‐fit – add  insulation,  install VSD 

controls  on  pump  motors,  install  controls 

(combustion,  supply  temperature,  stack 

economizer to capture waste heat, baffle inserts to 

increase heat transfer,  

Replace  old  boiler  with  more  efficient  model, 

consider smaller (higher efficiency) boilers in series 

Steam system upgrades –  insulate distribution and 

return lines, install wide‐dead band thermostats to 

induce longer on‐off cycles + decrease demand 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 73 

Replace  existing  furnace  with  energy  efficient 

model 

Install supply temperature controls 

b. Packaged Roof Top Units 

Replace  old  equipment  with  new  high‐efficiency 

models.    Achieve  highest  EER  within  budget, 

consider control systems – setback scheduling, VAV 

capability,  interface  with  energy  management 

system 

Upgrade  existing  rooftop  system  –  verify  cooling 

capacity  and  duct  size  capacity  are  appropriately 

sized, Install EER+ heat‐exchange module 

c. Air‐side Economizers 

Uses dampers to use increasing amounts of outside 

air for space cooling 

d. Energy Recovery 

Technologies  capable  of  recovering  50‐80%  of 

heating/cooling energy 

e. Night Pre‐cooling 

Cost savings can range from 5%‐30% 

 

 

 

 

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 74 

2.8 Capital Funding 

2.8.1 History of Capital Funding 

 

General Obligation Bonds 

The Carlsbad community has generously supported the funding 

of capital  improvements within the Carlsbad Municipal School 

District in the past.  The community passed a $7.1 million bond 

authorization  in 2004 and 2007, $7.0  in 2011 and another $60 

million was approved in February 2014.   

 

The  district  has  worked  vigorously  to  implement  the 

community’s  mandate  for  improved  school  facilities.    Recent 

projects have included roof replacements, mechanical, window 

replacement,  small  projects  and  renovations.  The  2011‐2015 

Master Plan provided funding to  improved restroom, cafeteria 

and  communications  upgrades  throughout  the  District  which 

was completed in 2011‐2012. 

 

 

 

 

 

 

 

 

 

The declined debt service on  the 2004, 2007, and bonds kept 

tax  rates  at  a  stable  level  without  a  tax  increase.    However, 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 75 

with  the  increased  facility needs  in  the district,  a $60 million 

Bond  was  passed  in  February  2014  that  increased  taxes  by 

approximately  2.7%  over  the  previous  rate.   A  history  of  the 

bond sales are represented in Figure 2‐52.5 

 

Figure 2‐52  Bond Sales Authorized 2013‐2019; provided by RBC Capital Markets 

CURRENT DEBT

2007 ELECTION $7,100,000

EST TAX$6.000 SER 2004 $1.100 SER 8/1/04 TOTAL DEBT RATE

TYE 98%10/31 PRIN 8/1 COUPON INTEREST PRIN 8/1 COUPON INTEREST PRIN 8/1 COUPON INTEREST PRIN INTEREST TOTAL COLLEC

2014 500,000 3.90% 39,500 250,000 4.00% 164,725 750,000 204,225 954,225 1.3372015 500,000 4.00% 20,000 210,000 4.00% 154,725 710,000 174,725 884,725 0.4742016 500,000 4.00% 146,325 500,000 146,325 646,325 0.3362017 850,000 4.13% 126,325 850,000 126,325 976,325 0.4932018 1,225,000 3.70% 91,263 1,225,000 91,263 1,316,263 0.6452019 1,225,000 3.75% 45,938 1,225,000 45,938 1,270,938 0.605

Callable 8/1/12 TOTAL $1,000,000 $59,500 $0 $0 $4,260,000 $729,300 $5,260,000 $788,800 $6,048,800

Callable 8/1/16 11/20/2007 8/1/2008

CURRENT DEBT PROPOSED DEBT

2011 ELECTION 2012 EDUCATION TECH NOTES 2013 EDUCATION TECH NOTES 2014 ELECTION

EST TAX$7,000,000 SERIES 2011 $600,000 SERIES 2012 $0 SERIES 2013 $30,000,000 SERIES 2014 $30,000,000 SERIES 2016 TOTAL DEBT RATE

TYE 98%10/31 PRIN 8/1 COUPON INTEREST PRIN 2/1 COUPON INTEREST PRIN 10/1 COUPON INTEREST PRIN 8/1 COUPON INTEREST PRIN 8/1 COUPON INTEREST PRIN INTEREST TOTAL COLLEC

2014 435,000 2.00% 155,900 150,000 0.36% 3,870 1,335,000 363,995 1,698,995 1.3372015 315,000 2.00% 147,200 150,000 0.58% 3,330 4,675,000 3.75% 1,343,750 5,850,000 1,669,005 7,519,005 4.0012016 535,000 2.00% 140,900 150,000 0.79% 2,460 5,325,000 3.75% 949,688 6,510,000 1,239,373 7,749,373 4.0052017 425,000 2.00% 130,200 150,000 0.85% 1,275 1,000,000 3.75% 750,000 3,350,000 4.00% 1,200,000 5,775,000 2,207,800 7,982,800 4.0062018 300,000 3.00% 121,700 1,000,000 3.75% 712,500 3,750,000 4.00% 1,066,000 6,275,000 1,991,463 8,266,463 4.0282019 300,000 3.00% 112,700 1,775,000 3.75% 675,000 1,300,000 4.00% 916,000 4,600,000 1,749,638 6,349,638 2.9992020 500,000 3.00% 103,700 2,000,000 3.75% 608,438 2,000,000 4.00% 864,000 4,500,000 1,576,138 6,076,138 2.7852021 600,000 3.25% 88,700 2,000,000 3.75% 533,438 2,000,000 4.00% 784,000 4,600,000 1,406,138 6,006,138 2.6722022 650,000 3.25% 69,200 2,000,000 3.75% 458,438 2,000,000 4.00% 704,000 4,650,000 1,231,638 5,881,638 2.5402023 650,000 3.25% 48,075 2,000,000 3.75% 383,438 2,000,000 4.00% 624,000 4,650,000 1,055,513 5,705,513 2.3922024 770,000 3.50% 26,950 2,000,000 3.75% 308,438 2,000,000 4.00% 544,000 4,770,000 879,388 5,649,388 2.2992025 2,000,000 3.75% 233,438 2,000,000 4.00% 464,000 4,000,000 697,438 4,697,438 1.8532026 2,000,000 3.75% 158,438 2,000,000 4.00% 384,000 4,000,000 542,438 4,542,438 1.7392027 2,225,000 3.75% 83,438 2,500,000 4.00% 304,000 4,725,000 387,438 5,112,438 1.9022028 2,500,000 4.00% 204,000 2,500,000 204,000 2,704,000 0.9682029 2,600,000 4.00% 104,000 2,600,000 104,000 2,704,000 -0.018

TOTAL $5,480,000 $1,145,225 $600,000 $10,935 $0 $0 $30,000,000 $7,198,438 $30,000,000 $8,162,000 $71,340,000 $17,305,398 $88,645,398

Callable: 6/22/2011 8/1/2012 2/8/2012 2/1/2013 10/31/2012 10/1/2013 5/21/2014 8/1/2015 8/1/2016 8/1/2017

CARLSBAD MUNICIPAL SCHOOL DISTRICT$60 MILLION BOND ELECTION IN 2014 AND $20 MILLION BOND ELECTIONS THEREAFTER (TAX RATE = $4.00 LEVEL)

2004 APRIL ELECTION - $7,100,000$6,000,000 $1,100,000

$7,000,000 $60,000,000

 

 

Education Technology Notes (“ETNs”) 

CMSD  currently  utilizes  the  Education  Technology  Notes  for 

districtwide  technology  improvements  from  hardware, 

software to  infrastructure.  The district currently has $600,000 

outstanding and is expected to issue another $850,000 in June 

2014.  ETN’s impact 6% of the district’s bonding capacity. 

 

3 The District Financial Consultant is RBC Capital Markets, 6301 Uptown Blvd. NE, Suite 110, Albuquerque, New Mexico 87110, (505) 872‐5999.  In July, 2013 RBC provided an update of the financial outlook for the District.   

 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 76 

Mill Levies 

CMSD currently has a 2.0 mill levy in place to take advantage of 

state matching funds under the NM Senate Bill 9 Program.  The 

most  recent  election  was  in  February  2013.  CMSD  receives 

$2.5M under the program.   

 

CMSD currently has a 1.923 mill levy in place under NM House 

Bill  (HB33).    HB33  funding  is  used  most  extensively  for 

remodeling,  additions  to,  providing  equipment  for,  furnishing 

public  school  buildings,  and  purchasing  or  improving  public 

school grounds.  HB33 Revenues provides $2.5 million per year.  

 

Critical Capital Outlay Funds 

All  NM  public  school  districts  are  eligible  to  receive  New 

Mexico  Public  School  Capital  Outlay  Council  (PSCOC)  funds.  

The district must compete with other districts for this funding.  

CMSD’s match for this funding source  is 75%. The state match 

for this funding source is 25%.  At this time, CMSD receives no 

PSCOC funds. 

 

Legislative Appropriations 

CMSD  can  receive  special  appropriations  granted  by  the 

legislature.  At  this  time,  CMSD  has  direct  appropriations 

totaling $1,464,448 from the State Legislature.   

 

Federal Impact Aid and Public Capital Outlay Fund 

CMSD does not receive PL874 Federal Impact Aid funds.  CMSD 

does not receive funding from the Public School Capital Outlay 

fund.   

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 77 

 

History of Assessed Valuation 

As of 2013, Carlsbad has a higher assessed valuation from the 

oil  and  gas  industry which  accounts  for  up  to  53.07%  of  the 

Total  Assessed  Valuation.    This  value  has  also  increased  for 

Non‐residential  to  28.56%  and  decreased  for  Residential  to 

18.37% of  the Total Assessed Valuation.   The overall assessed 

valuation  has  increased  in  the  last  five  years  to  the  current 

2013 figure of $1,849,262,907.  

 

Figure 2‐53, History of Assessed Valuation 

2009 2010 2011 2012 2013

Residential 268,676,238$ 286,543,417$ 302,951,793$ 316,147,144$ 339,562,512$

Non-Residential 515,253,443 493,618,903 533,023,077 644,452,287 528,225,404

Oil and Gas 924,942,783 427,213,272 587,268,989 796,351,028 981,474,9911,708,872,464$ 1,207,375,592$ 1,423,243,859$ 1,756,950,459$ 1,849,262,907$

% Change Over Previous Year 23.4% -29.3% 17.9% 23.4% 5.3%  

 

Comparison of Tax Rates to Other School Districts 

CMSD has  a history of much  lower  than  average  tax  rates  as 

compared  to  surrounding area  school districts.   The  following 

chart is a comparison of Carlsbad Municipal School District’s tax 

rate  to other surrounding area Districts.   The current  tax  rate 

for CMSD is 5.837 mills and will increase to 8.510 in 2014/15. In 

tax  year  2014,  the  District’s  debt  service  tax  rate  will  be 

approximately at the same level of other similar‐sized schools. 

Figure 2‐54, Comparison of Tax Rates to Surrounding Area Districts 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 78 

 

 

 

Current Debt Management Plan 

The current Debt Management allowed for a $60 million bond 

election  in February 2014  that will  result  in a  tax  increase  for 

the community.  In addition, the district’s outstanding declining 

debt  service  could permit new bonds  in  future without  a  tax 

increase.   The  final maturity maximum  is  thirteen  years.   The 

parameters and approach to the current Debt Management is: 

Create capacity by retiring debt as quickly as cash 

flow from tax levy will permit; 

Attractive scheduling to bond buying community; 

Constitution limits amount of bonds outstanding to 

6% of  2013 Assessed Value; 

Valuation (A.V.) as follows: $ 1,849,262,907 x .06 = 

$ 110,955,774;

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 79 

A.V. growth assumption is 3%. Higher growth rates 

permit more rapid pay down of debt; 

Target debt service rate for tax year 2015: $4.00 level / 

$1,000 of assessed valuation. 

District is currently bonded to 37.3% capacity and 

will be bonded to 44.52% in 2018. 

2.8.2 Current and Future Financial Resources 

The current CMSD tax rate of 5.837 mills, is the result of the 

district’s current $11,340,000 outstanding in general obligation 

bonds, and a total of $8,397,000 for SB‐9 and HB‐33 funds.  The 

Carlsbad School District has an opportunity to impact the lives 

of the district’s young children with the replacement of four 

elementary schools over the next four years. The plan is as 

follows:

Increase GO Bond debt service tax rate to approximately 

$4. 010 mills which is lower than the State average of 

$4. 938 (based on the recent 2014 bond election). 

Maintain HB33 levy at $ 2.00 and SB9 levy at $2.00 

The District’s total capital improvements tax rate (SB9, 

HB33, G/O Bonds and Notes) would 

be approximately $ 8.510 (based on the recent 2014 bond 

election).  

Bond election in 2014 for $60 million 

$30 million available in 2014 

$30 million available in 2016 

Bond election in 2018 for $20 million with no additional tax 

rate increase. 

Facilities Master Plan 2014‐2019      Carlsbad Municipal School District 

         2.0 Existing and Projected Conditions    Carlsbad, New Mexico 

Section 2 | 80 

$10 million available in 2018 

$10 million available in 2020 

Bond election in 2022 for $20 million with no additional tax 

rate increase. 

• $10 million available in 2022 

• $10 million available in 2024 

• Total capital funding generated by the proposed plan: $100 

million.  

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 1 

3.1 Total Capital Needs 

The  total  capital  needs  are  derived  from  the  facility  needs 

identified  on  each  campus,  an  evaluation  of  capacity  versus 

available  area,  and  incorporates  overall  District  goals  for 

improvements.   A detailed evaluation and  list of  findings  for 

each school campus may be found in the Appendices.   

 

The 2010 Facility Advisory Committee (FAC) was assigned the 

task of working together with district planners and architects 

to review data and establish priorities for the FMP.   The new 

Facility Master Plan 2014‐2019 builds upon the findings of the 

previous  plan.    The  2014  Facility  Advisory  Committee  (FAC) 

prioritized  the  overall  District  goal  of  improving  facility 

conditions  district‐wide  and  program  equity  at  the  district’s 

elementary schools and worked with the district planners and 

architects  to  establish  a  pathway  in  which  to  replace  the 

district’s aging elementary  schools with  larger more efficient 

new schools.   A GO Bond was passed  in February, 2014 with 

the  expressed  intent  to  design  and  construct  four  new 

elementary schools. 

3.1.1 Facility and Project Needs 

This FMP updates and  incorporates changes which may have 

occurred  from  any  prior  documentation  of  facilities  and  the 

work completed  in 2010.   The enrollment of each facility was 

reviewed  to  determine  the  ability  of  the  facility  to 

accommodate changes in the programs.   

 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 2 

Overall  enrollment  in  the  district  has  risen  over  the  past 

several years.   This  is a  significant  change  from  the previous 

FMP which  indicated a more moderate growth pattern.   This 

has  prompted  the  District  to  re‐assess  facility  needs  for 

elementary schools. 

 

The overriding goals for the 2014‐2019 FMP includes:  

The  district  intends  to  replace  seven  of  the  existing 

schools  with  four  larger  capacity  elementary  schools 

for 600 students each under the current GO Bond cycle 

and  to  either  replace  or  renovate  and  construct  an 

addition  to  the  remaining existing elementary    school 

(Hillcrest)  into  a  STEM  magnet  elementary  school  to 

accommodate the growing needs of the district  in the 

future.    

Growth at  the kindergarten and pre‐school  levels will 

impact  the  current  facilities  over  the  next  five  years.  

The plan  includes options  for  the pre‐school program 

at  EM  Smith  Pre‐school  and  the  Early  Childhood 

Education  Center.    The  projects  at  these  schools  are 

currently  un‐funded  in  this  FMP  cycle  through  the 

current  GO  Bond,  however,  may  receive  funding 

through SB‐9 or HB‐33 monies, or possible  future GO 

Bond. 

The  conversion  of  Alta  Vista  Middle  School  to  a  6th 

Grade  Academy  will  occur  in  school  year  2014‐2015.  

P.R Leyva Middle School will be dedicated to 7th and 8th 

grades.    The  planning  team  has  completed  a 

preliminary  evaluation  of  the  space  utilization  to 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 3 

determine  if  there are capacity  issues associated with 

this program change.   The 2010 projects  identified for 

these schools were then assessed to correspond to the 

program  needs.    The  projects  at  these  schools  are 

currently un‐funded  in  through  the  current GO Bond, 

however, may  receive  funding  through SB‐9 or HB‐33 

monies or possible a future GO Bond. 

 

The  following  illustrations  on  pages  3|6‐3|7,  show  School 

Replacement  Plans  based  on  Mid‐Range  and  High‐Range 

Elementary  Enrollment  Projections.    The  schools  that  are 

highest on the PSCOC ranking  list are those that are targeted 

for  replacement.    The  illustrations  show  the  schools  to  be 

replaced  (new, high capacity schools will  replace  the existing 

schools)  and  the  movement  of  students  from  the  other 

schools.    The  illustration  also  shows  the  40‐day  counts  for 

2012/13  and  2013/14,  the  2018/2019  projections  and  the 

current  classroom  capacity  of  the  schools.    The  “Additional 

Seats”  shows  the  available  seats  after  the  construction  and 

district attendance zone reboundering of the new 600 student 

school.   This  illustration was used as a tool for understanding 

not  only  the  plan  but  the  capacity  issues  at  each  of  the 

schools.   

 

The Mid‐range Consolidation Plan  indicates that will be some 

capacity in the new schools for growth beyond the 2018‐2019 

projections.    The  High‐range  Consolidation  Plan  shows 

minimal  capacity  for  growth  beyond  the  2018‐2019 

projections.    Hillcrest  Elementary  will  be  pivotal  in  the 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 4 

determination  of  accommodating  growth.    The  need  for  an 

additional  550  to  600  student  capacity  school  would  be 

determined  by  a  re‐examination  of  the  growth  in  the  next 

FMP or update. 

 

The  School  Consolidation  Plan  Mid‐Range  Projections 

explained: 

 

Riverside  Elementary  School  is  ranked  #45  and  has  a 

projected  enrollment  of  352  students.      Of  the 

projected capacity of Monterey Elementary School, the 

new  Riverside  Elementary  will  accommodate  220 

students  and  have  a  remaining  capacity  of  28  seats.  

This  will  allow  for  some  flexibility  to  accommodate 

additional grow.  

Pate  Elementary  School  is  ranked  #32  and  has  a 

projected  enrollment  of  295  students.    Puckett 

Elementary has a projected enrollment of 283 students 

to  be  accommodated  in  the  new  Pate  Elementary 

School.    A  22  seat  capacity  will  remain  after  this 

consolidation. 

Joe Stanley Smith Elementary School is ranked #33 and 

has  a  projected  enrollment  of  316  students.    Craft 

Elementary has a projected enrollment of 261 students 

to  be  accommodated  in  the  new  school.        An 

additional 23 seats will be available for future growth. 

Sunset Elementary  is  ranked #31 and has a projected 

enrollment  of  462  students.    An  additional  108 

students  from Monterrey  Elementary will  attend  this 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 5 

new school.  An additional 30 seats will be available for 

growth. 

 

The  School  Consolidation  Plan  High‐Range  Projections 

implications: 

If the High‐range projections are realized, then each of 

the new  schools will meet  the 600  student  capacities 

with no  room  for growth.   At  this point, Hillcrest will 

become important in relieving the capacity at the new 

schools.   Option 1. Build a 550  student  school, which 

would only allow  for 19 additional seats District‐wide; 

Option  2.  Build  a  600  student  school,  which  would 

allow  an  additional  69  seats  District‐wide.    In  other 

words,  more  students  could  be  housed  at  Hillcrest, 

allowing for growth at the other schools.  The decision 

to build a 550 or 600  student  school will be made  in 

the  next  FMP  cycle  based  on  a  re‐assessment  of  the 

projections.

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 6 

 Sch

oo

l Co

nso

lidat

ion P

lan 2

018‐

2019

 Mid P

roje

ctio

ns

248

30

52

84

13

8

Futu

re 5

50‐6

00 S

tud

ent 

Exp

ansi

on P

roje

ct

Riv

ersi

de

Elem

enta

ry 

Sch

oo

l(2

012‐

25

0/2

013‐

282

/P

roje

ctio

n‐3

52/C

apac

ity‐

260

)A

dd

itio

nal S

eats 2

8

Rep

lace

Exis

tin

g Sc

ho

ols

, In

crea

se 

Cap

acit

y

Joe 

Stan

ley 

Smit

hEl

emen

tary S

cho

ol

(201

2‐2

74

/20

13‐2

89/

Pro

ject

ion‐3

16/C

apac

ity‐

281

)A

dd

itio

nal

Seat

s 2

3

Pu

cket

tEl

emen

tary 

Sch

oo

l(2

012‐

24

0/2

013

‐256

/P

roje

ctio

n‐2

83/C

apac

ity‐

238

)

Sun

set

Elem

enta

ry 

Sch

oo

l(2

012‐

497

/20

13‐

44

7/

Pro

ject

ion‐4

62

/Cap

acit

y‐4

33

)A

dd

itio

nal S

eats 3

0

Sch

oo

l C

on

solid

atio

n

Cra

ft E

lem

enta

ry 

Sch

oo

l(2

012‐

24

2/20

13‐

252

/P

roje

ctio

n‐2

61

/Cap

acit

y‐25

8)

Mo

nte

rrey E

lem

enta

ry 

Sch

oo

l(2

012‐

323

/20

13‐

32

7/

Pro

ject

ion‐3

28

/Cap

acit

y‐3

25

)

22

0

Hill

cres

t El

emen

tary 

Sch

oo

l(2

012‐

298

/20

13‐

30

0/

Pro

ject

ion‐2

87

/Cap

acit

y‐3

02

)A

dd

itio

nal S

eats 1

5

261

Pat

e El

emen

tary 

Sch

oo

l(2

012‐

233

/20

13‐

25

0/

Pro

ject

ion‐2

95

/Cap

acit

y‐2

58

)A

dd

itio

nal S

eats 2

2

28

31

08

Fro

mM

on

terr

ey

#32

#20

1

#14

9

#31

#12

4

#33

#45

#19

6

Stat

e R

anki

ng‐

Ran

k fo

r C

on

dit

ion

/A

deq

uac

y/G

row

th 

Nu

mb

er o

f St

ud

ents

/Mo

ves

Cap

acit

ies 

are 

clas

sro

om

s o

nly

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 7 

Sch

oo

l Co

nso

lidat

ion P

lan 2

018‐

2019

 Hig

h P

roje

ctio

ns

248

305

284

138

If a 5

50 C

apac

ity 

Scho

ol i

s bu

ilt‐ 

19 A

ddit

iona

l Sea

ts

If a 6

00 C

apac

ity 

Scho

ol i

s bu

ilt‐ 

69 A

ddit

iona

l Sea

ts

Riv

ersi

de

Elem

enta

ry 

Sch

oo

l(2

012‐

250/

2013

‐282

/Pro

ject

ion 

387/

Cap

acit

y 26

0)

Rep

lace

Exis

tin

g Sc

ho

ols

, In

crea

se 

Cap

acit

y

Joe 

Stan

ley 

Smit

hEl

emen

tary S

cho

ol

(Cu

rren

t 27

4/P

roje

ctio

320/

Cap

acit

y 28

1)

Sun

set

Elem

enta

ry 

Sch

oo

l(C

urr

ent 

497/

Pro

ject

ion 

506/

Cap

acit

y 43

3)

Sch

oo

l C

on

solid

atio

n

213

Hill

cres

t El

emen

tary 

Sch

oo

l(C

urr

ent 

Stu

den

ts 

298/

Pro

ject

ion 3

65C

apac

ity 

346)

280

Pat

e El

emen

tary 

Sch

oo

l(C

urr

ent 

233/

Pro

ject

ion 

314/

Cap

acit

y 23

8)

208

#203

#151

#126

#198

Riv

ersi

de

Elem

enta

ry 

Sch

oo

l(2

012‐

250/

2013

‐282

/P

roje

ctio

n‐3

92/C

apac

ity‐

260)

Ad

dit

ion

al S

eats 0

Rep

lace

Exis

tin

g Sc

ho

ols

, In

crea

se 

Cap

acit

y

Joe 

Stan

ley 

Smit

hEl

emen

tary S

cho

ol

(201

2‐27

4/20

13‐2

89/

Pro

ject

ion‐3

54/C

apac

ity‐

281)

Ad

dit

ion

alSe

ats 

0

Puck

ett

Elem

enta

ry 

Sch

oo

l(2

012‐

240/

2013

‐256

/P

roje

ctio

n‐3

32/C

apac

ity‐

238)

Sun

set

Elem

enta

ry 

Sch

oo

l(2

012‐

497/

2013

‐447

/P

roje

ctio

n‐5

10/C

apac

ity‐

433)

Ad

dit

ion

al S

eats 0

Sch

oo

l C

on

solid

atio

n

Craf

t El

emen

tary 

Sch

oo

l(2

012‐

242/

2013

‐252

/P

roje

ctio

n‐3

06/C

apac

ity‐

258)

Mo

nte

rrey E

lem

enta

ry 

Sch

oo

l(2

012‐

323/

2013

‐327

/P

roje

ctio

n‐3

60/C

apac

ity‐

325)

208

Hill

cres

t El

emen

tary 

Sch

oo

l(2

012‐

298/

2013

‐300

/P

roje

ctio

n‐3

38/C

apac

ity‐

346)

Ad

dit

ion

al S

eats 1

9‐69

246

Pat

e El

emen

tary 

Sch

oo

l(2

012‐

233/

2013

‐250

/P

roje

ctio

n‐3

39/C

apac

ity‐

258)

Ad

dit

ion

al S

eats 0

261

90

Fro

mM

on

terr

ey

#32

#201

#149

#31

#124

#33

#45

#196

6271

60

Stat

e R

anki

ng‐

Ran

k fo

r C

on

dit

ion

/A

deq

uac

y/G

row

th 

Nu

mb

er o

f St

ud

ents

/Mo

ves

Cap

acit

ies 

are 

clas

sro

om

s o

nly

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 8 

 

Facility Resolution Plan 

What will happen  to  the  facilities once  the new  facilities are 

constructed? 

The  facilities  will  be  demolished,  sold  or  the  lower  ranking 

facilities  will  be  re‐purposed  to  accommodate  other  District 

needs.  The higher ranking facilities will be demolished or the 

property sold.   The  following  illustration on page 3‐10 shows 

the plan for each of the facilities.  

Riverside  Elementary  will  be  constructed  on  a  new  site 

acquired from the BLM.   The current site  is  in a desirable 

location that is conducive to residential development.  The 

property will be sold.   

The  new  Pate  Elementary  School  will  be  constructed  on 

the north end of the existing Puckett site which is currently 

vacant land owned by the district.  Depending on the final 

design  and  site  needs  of  the  new  facility,  if  the  existing 

Puckett facility is able to remain, the district may consider 

to  re‐purpose  the building  for use as a pre‐school  facility 

and  relocating  the  program  from  the  EM  Smith  facility.  

This will allow the pre‐school program to expand and the 

EM  Smith  location  to be possibly  sold.    It  should also be 

noted that the new Pate Elementary will be for grades 1st 

through  5th  only  and would  not  be  conducive  to  sharing 

facilities with the potential pre‐school program that could 

be relocated  into the Puckett facility as the programmatic 

needs of both  schools  are  vastly different  as well  as  the 

age groups of students. 

Joe  Stanley  Smith  Elementary  facility  will  either  be 

constructed  on  the  existing  site  or  a  site  nearby.      The 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 9 

building will be demolished  if  the new  school  is built on‐

site or the  land will be sold with the existing facility or be 

demolished.   

The new Sunset Elementary School will be constructed on 

the  existing  site  and  the  existing  structure  will  be 

demolished. 

Once  the new  schools are open,  then  the Pate and Craft 

Elementary sites will be sold; demolition of the schools will 

be  determined  as  part  of  the  sale  of  the  property.    The 

current  EM  Smith  School  may  be  sold  in  its  current 

condition  if  the  students  are  able  to  relocate  to  the  re‐

purposed Puckett facility. 

Once  Riverside  and  Sunset  are  complete,  the  students 

from  Monterrey  Elementary  will  move,  allowing  for  the 

demolition of that facility and the site will be re‐purposed 

for  a new  Freshman Academy.    This  site  is preferred  for 

this  use,  since  it  is  adjacent  to  the  high  school  which 

means  the  freshmen  can  utilize  the  existing  facilities 

without duplicating the space on the new campus. 

Hillcrest Elementary will be retained.   A new facility or an 

addition  to  the  facility  to  increase  the  capacity  will  be 

decided during the next master planning effort in 2018. 

Given the growth anticipated in the kindergarten program, 

the Early Childhood Education Center will likely require an 

addition.  This is an un‐funded project for this bond cycle. 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 10 

 

Sch

oo

l Co

nso

lidat

ion P

lan f

or 

Pre‐s

cho

ol a

nd E

lem

enta

ry F

acili

ties

Riv

ersi

de

Elem

enta

ry 

Sch

oo

lB

uild

on n

ew s

ite 

Rep

lace E

xist

ing 

Sch

oo

ls, I

ncr

ease 

Cap

acit

y

Joe 

Stan

ley 

Smit

hEl

emen

tary S

cho

ol

Bu

ildo

n e

xist

ing 

site o

rad

jace

nt 

pro

per

ty

Sun

set

Elem

enta

ry 

Sch

oo

lB

uild

on e

xist

ing 

site

Cra

ft E

lem

enta

ry 

Sch

oo

l

Mo

nte

rrey

 Ele

men

tary 

Sch

oo

lB

uild

 New

 On‐S

ite 

Fres

hm

an 

Aca

dem

y

Hill

cres

t El

emen

tary 

Sch

oo

l

Pat

e El

emen

tary 

Sch

oo

lB

uild

on P

uck

ett 

Site

Sell 

Pro

per

ties

Riv

ersi

de

Elem

enta

ry 

Sch

oo

lSe

ll Ex

isti

ng 

Site 

Bu

ild o

n B

LM D

on

ated

 Lan

d

Re‐

Pu

rpo

se 

Pro

per

ties

Ret

ain

Pu

cket

tEl

emen

tary 

Sch

oo

lR

e‐p

urp

ose

for 

Pre‐K 

pro

gram

 at 

EM S

mit

h

Pat

e El

emen

tary 

Sch

oo

l

EM S

mit

h S

cho

ol

May s

ell a

s is t

o r

eco

op 

rece

nt 

cost

s

Ad

dit

ion

sEa

rly 

Ch

ildh

oo

Cen

ter

*   D

epen

den

t o

n f

ina

l des

ign a

nd s

ite 

nee

ds 

of 

the 

new

 60

0 s

tud

ent 

Pa

te E

lem

enta

ry. C

MSD

 BO

E w

ill m

ake f

ina

l det

erm

ina

tio

n o

f h

ow f

aci

litie

(EM S

mit

h/ 

Pu

cket

t El

emen

tary

) w

ill b

e d

isp

ose

d o

f o

r re‐p

urp

ose

d d

uri

ng t

he 

des

ign p

roce

ss. 

*

*

*

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 11 

State Funding Assistance 

The  Carlsbad  Municipal  Schools  anticipates  application  for 

state  funding  assistance.    Therefore,  the  school  rankings  by 

PSCOC played a major role in the prioritization of the projects 

since  the  four  replacement  schools all  ranked within  the  top 

100  schools  in  the  state  to  receive  PSCOC  funding.    The 

district’s priorities are as follows: 

Pate Elementary ranked number 32; 

Riverside Elementary ranked number 45;  

Joe Stanley Smith ranked number 33; and 

Sunset Elementary ranked number 31. 

The  School  District  does  not  anticipate  applying  for  PSCOC 

funding for any other projects at this time.   

 

Cost Estimating 

Cost estimates  for  this FMP were based on  the most current 

construction data available.    Costs for major projects include 

the  maximum  allowable  construction  cost  (MACC)  and 

additional  funds  for  owner  incurred  project  costs.    Owner 

incurred project  costs  include  the  architect  and engineering, 

movable  furnishings  and  equipment,  a  small  percentage  for 

administration  which  includes  fees  and  surveys,  and  New 

Mexico  Gross  Receipts  Tax.    The  owner  incurred  soft  costs 

were generally determined using a percentage (15‐25%) of the 

MACC plus contingency and escalation factors.  The estimates 

a  construction  contingency  of  10%,  and  escalation  is 

calculated at 4% per year compounded.  

         

 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 12 

3.2 Prioritization Process 

3.2.1 Facilities Master Plan Process 

The Facility Advisory Committee  (FAC) was assigned  the  task 

of  working  together  with  district  planners  and  architects  to 

review data and establish priorities for the FMP.  A diagram of 

the overall process and steps utilized  in this FMP are detailed 

in Figure 3‐1 below:   

Figure 3‐1 Master Plan Process Diagram

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 13 

 

Pre‐Assessment  activities,  field,  and  data  assessments  of  all 

school  and  district  facilities  were  conducted  in  2010  and 

updated  in  2014.    The  following  types  of  activities  and 

information were gathered  in order  to  compile  the eventual 

recommendations to the FAC committee: 

 

3.2.2 Educational Facilities Assessments 

Facility Analysis 

Walk‐through Assessments of each school were conducted  in 

2010  and  deemed  sufficient  by  PSFA,  with  modifications  to 

include  projects  that  have  been  completed  since  that 

evaluation.   The assessments provided  in Section 4  include a 

detailed assessment of the following facilities:  

Dr. E.M. Smith Pre‐ School 

Early Childhood Education Center 

Craft Elementary School 

Hillcrest Elementary School 

Monterrey Elementary School 

Joe Stanley Smith Elementary School 

Pate Elementary School 

Puckett Elementary School 

Riverside Elementary School 

Sunset Elementary School 

Alta Vista Middle School1 

P.R. Leyva Middle School 

Carlsbad High School 

1 As of 2014/15 Alta Vista will be the 6th Grade Academy 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 14 

Eddy Alternative School 

District Warehouse 

Edison Building 

District Administration Building 

Jefferson Montessori Academy Charter School 

 

The  walk‐through  assessments  include  visual  or  plan  review 

assessment of the following: 

Landscaping 

Drainage/Storm  Water  Retention/Erosion/Ponding 

Issues 

Hardscape 

Site Recreation Amenities 

Site Safety and Security 

School Plant Assessment 

Educational Environment 

 

Maintenance staff members were interviewed for information 

regarding facility history and maintenance records.  Additional 

information  was  gathered  from  the  District  to  include 

completed projects for 2010‐ 2013. 

 

Projects that were not completed remain as ranked according 

to  the  FAC’s  and  District  representative  knowledge  of  the 

condition of the schools and the District’s goals.  The projects 

fall within the following categories:   

Life, Health and Safety‐Code Compliance 

Educational/Programmatic 

Adequacy 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 15 

Facility Renewal/Renovations 

New Construction at Existing Schools 

Educational Support     (ex. Technology) 

ADA Compliance 

Site Improvements & Drainage 

Demolition  

Capacity/ Utilization Studies 

  Utilizing  the Public Schools Facilities Authority recommended 

worksheets  for  capacity  and  utilization,  the  planning  team 

calculated  the  enrollment  capacity  of  each  school  based  on 

programs, enrollments, and scheduling.  

School Information 

Information about each school was gathered and  included  in 

the  overall  assessment  including:  age  of  facilities,  facility 

construction, maintenance records, neighborhood growth and 

conditions, and community goals and priorities. 

Demographics/ Enrollment 

Demographics  for  Eddy County were  gathered  for  input  and 

analysis  into  the  overall  trends  within  the  area.    Migratory 

information within the district is revealed through the growth 

rates  at  individual  schools.    Historic  enrollment  information 

was gathered from the District’s 40‐day counts for a five year 

period.    The  following  categories  of  demographic  and 

enrollment information is utilized as informational in this FMP: 

Birth rates within Eddy County as compared to NM, 

Housing starts and income information for the area, 

Historical enrollment trends within the district, 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 16 

Changing educational program needs within the district. 

Community and School District Information 

In  2013  and  2014  multiple  evening  and  day‐long  meetings 

were  conducted  to  communicate  background  and  garner 

additional  committee  guidance  on  the  proposed  plan.    The 

FAC  meetings  are  open  to  the  public  and  public 

representatives who were invited to attend, were present.   

 

Project  priorities  were  determined  through  discussion,  FAC 

knowledge of the schools, first‐hand experience during on‐site 

school  tours,  response  from  FAC  members  in  reference  to 

project  sheets  provided  by  the  planning  team,  review  of 

schools deferred from the previous bond cycle, consideration 

of the goals, and particular goals from District Administration. 

 

The  planning  team  sorted  all  potential  projects  into  several 

categories:  potential  general  obligation  bond  (GO  Bond) 

projects, SB9 funded projects, HB33 projects, and those items 

requiring only normal maintenance.   

 

3.2.3 Financial Strategies 

Local General Obligation Bonds  

Local  school districts may  issue  general obligation bonds  for 

the purpose of erecting, remodeling, making additions to and 

furnishing school buildings, or purchasing or improving school 

grounds or any combination of these purposes.  In addition, a 

school  district  may  also  use  bond  proceeds  to  purchase 

computer equipment  and  software  for  student use  in public 

school classrooms. Prior to the  issuance of bonds, the district 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 17 

is required to submit of the question to the voters by the local 

school  board.  Upon  successful  election  results,  the  local 

school  board  may,  subject  to  the  approval  of  the  Attorney 

General, proceed to issue the bonds. There are restrictions: (1) 

the  district’s  ability  to  sell  bonds  is  limited  to  6%  of  its 

assessed valuation; (2) there is a four year period in which the 

bonds may be sold from a particular approved resolution. 

 

NOTE: The tax rate associated with this type of funding is likely 

to  fluctuate  every  year  due  to  the  timing  of  principal  and 

interest payments as well as changes in assessed valuations.2 

The Public School Capital Improvements Act  

Commonly  referred  to  as  SB‐9  or  the  “two‐mill  levy,”  this 

funding  mechanism  allows  districts  to  ask  local  voters  to 

approve a property  levy of up to two mills for a maximum of 

six years. Funds generated through imposition of the two‐mill 

levy must be used for: 

Erecting,  remodeling,  making  additions  to,  providing 

equipment for, or furnishing public school buildings; 

Purchasing or improving public school grounds; 

Maintenance  of  public  school  buildings  or  public  school 

grounds,  including expenditures for technical training and 

certification  for  maintenance  and  facilities  management 

2 New Mexico Public Education Department, State Budget and Finance 

Analysis Bureau.  

http://www.ped.state.nm.us/div/fin/school.budget/dl08/How%20NM%20

schools%20are%20fundedFY0806.pdf, Aug 2006, pg 10. 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 18 

personnel, but excluding salary expenses of school district 

employees; 

Purchasing  activity  vehicles  for  transporting  students  to 

extracurricular activities; and 

Purchasing  computer  software  and hardware  for  student 

use in public school classrooms. 

 

An individual school district may only use SB‐9 funds for any or 

all  of  these  purposes  as  stated  in  the  school  district’s 

individual resolution.3  

The Public School Buildings Act  

This Act,  commonly  referred  to  as HB‐33,  allows  districts  to 

impose  a  tax  not  to  exceed  10 mills  for  a maximum  of  five 

years on  the net  taxable value of property upon approval of 

qualified voters. These funds are to be used for: 

Erecting,  remodeling,  making  additions  to,  providing 

equipment for or furnishing public school buildings; and 

Purchasing or improving public school grounds. 

 

There are limitations and restrictions associated with this act: 

(1)  the  authorized  tax  rate made  under  the  Public  Buildings 

Act, when added to the tax rates for servicing the debt of the 

3 New Mexico Public Education Department, State Budget and Finance 

Analysis Bureau.  

http://www.ped.state.nm.us/div/fin/school.budget/dl08/How%20NM%20

schools%20are%20fundedFY0806.pdf, Aug 2006, pg 9. 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 19 

school district and the rate authorized under the Public School 

Capital  Improvements Act,  cannot exceed 15‐mills.  If  it does 

exceed 15‐mills,  the  rate authorized under  the Public School 

Buildings Act will be adjusted downward to compensate; and 

(2)  the  revenues  generated  from  the Public  School Buildings 

Act are only to be used  for specific capital  improvements  (as 

defined  above).  This  funding  mechanism  is  most  useful  for 

districts  with  high‐assessed  valuation  and  low  bonded 

indebtedness. 

 

The primary goal of  the master plan was  to  identify projects 

for  the upcoming GO Bond Election.   However,  the planning 

team  identified projects to be completed under SB‐9 and HB‐

33 funds.  A complete list of these projects is found in Section 

4.    The  SB‐9  and  HB‐33  projects  will  be  completed  by  the 

District  as  the  funds  are  available.    The  funds  are  currently 

allocated  at  approximately  $2.5  million  a  year  for  SB‐9  and 

$2.5 million per year for HB‐33.   

 

Once  all  school  data  was  gathered  for  consideration,  the 

planning  team  met  with  the  FAC  and  utilized  an  interactive 

spreadsheet  tool  to  rank  and  prioritize  all  potential  project 

needs  for  the  next  five  years.  Each  potential  project  was 

discussed, ranked based on Tier Level priorities, and voted on 

in order of priority for inclusion in the overall master plan.   

 

3.2.4 Decision‐making and Planning Process  

Decision‐making  for  the  FMP  was  based  on  a  non‐biased, 

collaborative  process.    Rankings  were  established  based  on 

the overall goals listed in this document and by knowledge of 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 20 

the  needs  of  each  school.  Priorities  were  established  by 

priority categories including:  

Life, Health and Safety‐Code Compliance 

Educational/Programmatic 

Adequacy 

Facility Renewal/Renovations 

New Construction at Existing Schools 

Educational Support     (ex. Technology) 

ADA Compliance 

Site Improvements & Drainage 

Demolition  

 

Major  renovation  and  addition  projects  were  assigned  a 

priority based on school needs.  SB‐9 and HB‐33 projects were 

categorized  based  on  prime  category  and  sub‐category 

projects.   

 

The FAC voted on projects in the following manner: 

Schools  with  the  greatest  or  most  immediate  needs 

were identified 

Projects  identified  for  each  of  these  schools  were 

reviewed 

Discussion of each project 

Vote  to  include  the  projects  and  the  Tier  Level  to 

assign the projects 

 

A  summary  presentation  of  the  FMP  was  presented  to  the 

Board in first a working session and finally in a public meeting.  

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 21 

The Board approved the course of the Master Plan on April 22, 

2014. 

 

3.2.5 Financial Outlook 

The  history  and  proposed  financial  debt  management  was 

prepared and reviewed with the Board for consideration.  The 

information  was  gathered  and  presented  by  RBC  Capital 

Markets.3 

 

Proposed Debt Management Plan 

The Board voted to establish a strategy of  increasing bonding 

capacity following the 2011 GO Bond election which passed in 

February,  2011.  The  2011  GO  Bond  yielded  $7,000,000  for 

projects which were  identified as Tier 1 projects  in  the 2010 

FMP; these projects are largely complete.  The debt service for 

this bond will be complete by 2024. 

 

The Board approved an overall budget target of $60 million for 

the 2014 general obligation bond series which was established 

based on  the CMSD district’s assessed valuation of property. 

This  is  actually  less  than  the  maximum  bonding  capacity 

however, it was not deemed in the best interest of the District 

to  maximize  this  capacity.    In  2014  the  assessed  value  is 

$1.849  Billion  with  a  District  bonding  capacity  of 

$110,955,774.   

  

Subsequent  bonds  will  be  decreased  once  vital  upgrades  of 

aging facilities is complete.  Future bond elections will be held 

in 2018 and 2022; should these bonds pass an additional $20 

million per election will be added to the debt. 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 22 

 

Proposed Debt Management Plan  

The  approved  2014  bond  capacity  will  increase  the  debt 

service tax rate by 4 mills.  The following is a summary of the 

proposed debt plan.   The complete  financial plan  is provided 

in Table 3.1 page 3|25. 

Bond election  in 2011  for $7 million with no  tax  rate 

increase 

Bond election  in 2014 for $60 million with  increase to 

statewide average tax rate 

$30 million available in 2014 

$30 million available in 2016 

 

Total  capital  funding  generated by  the proposed plan  is $67 

million  over  a  four  year  period.   With  this  plan,  the  overall 

impact to taxpayers  is $4.00 per $1,000 of assessed property 

value.   

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 23 

Table 3‐1.  Existing and Proposed Debt, Source: RBC Capital Markets, LLC 

CU

RREN

T DE

BT

20

07 E

LECT

ION

$7,1

00,0

00

EST

TAX

$6.0

00SE

R 20

04$1

.100

SER

8/1/

04TO

TAL

DEBT

RATE

TYE

98%

10/3

1PR

IN 8

/1CO

UPON

INTE

REST

PRIN

8/1

COUP

ONIN

TERE

STPR

IN 8

/1CO

UPON

INTE

REST

PRIN

INTE

REST

TOTA

LCO

LLEC

20

1450

0,00

03.

90%

39,5

0025

0,00

04.

00%

164,

725

750,

000

204,

225

954,

225

1.33

720

1550

0,00

04.

00%

20,0

0021

0,00

04.

00%

154,

725

710,

000

174,

725

884,

725

0.47

420

1650

0,00

04.

00%

146,

325

500,

000

146,

325

646,

325

0.33

620

1785

0,00

04.

13%

126,

325

850,

000

126,

325

976,

325

0.49

320

181,

225,

000

3.70

%91

,263

1,22

5,00

091

,263

1,31

6,26

30.

645

2019

1,22

5,00

03.

75%

45,9

381,

225,

000

45,9

381,

270,

938

0.60

5Ca

llable

8/1

/12

TO

TAL

$1,0

00,0

00$5

9,50

0$0

$0$4

,260

,000

$729

,300

$5,2

60,0

00$7

88,8

00$6

,048

,800

Calla

ble 8

/1/1

611

/20/

2007

8/1/

2008

CURR

ENT

DEBT

PROP

OSED

DEB

T

201

1 EL

ECTI

ON$7

,000

,000

2012

EDU

CATI

ON T

ECH

NOTE

S20

13 E

DUCA

TION

TEC

H NO

TES

20

14 E

LECT

ION

$60,

000,

000

ES

T TA

X$7

,000

,000

SERI

ES 2

011

$600

,000

SERI

ES 2

012

$0SE

RIES

201

3$3

0,00

0,00

0SE

RIES

201

4$3

0,00

0,00

0SE

RIES

201

6TO

TAL

DEBT

RATE

TYE

98%

10/3

1PR

IN 8

/1CO

UPON

INTE

REST

PRIN

2/1

COUP

ONIN

TERE

STPR

IN 1

0/1

COUP

ONIN

TERE

STPR

IN 8

/1CO

UPON

INTE

REST

PRIN

8/1

COUP

ONIN

TERE

STPR

ININ

TERE

STTO

TAL

COLL

EC

2014

435,

000

2.00

%15

5,90

015

0,00

00.

36%

3,87

01,

335,

000

363,

995

1,69

8,99

51.

337

2015

315,

000

2.00

%14

7,20

015

0,00

00.

58%

3,33

04,

675,

000

3.75

%1,

343,

750

5,85

0,00

01,

669,

005

7,51

9,00

54.

001

2016

535,

000

2.00

%14

0,90

015

0,00

00.

79%

2,46

05,

325,

000

3.75

%94

9,68

86,

510,

000

1,23

9,37

37,

749,

373

4.00

520

1742

5,00

02.

00%

130,

200

150,

000

0.85

%1,

275

1,00

0,00

03.

75%

750,

000

3,35

0,00

04.

00%

1,20

0,00

05,

775,

000

2,20

7,80

07,

982,

800

4.00

620

1830

0,00

03.

00%

121,

700

1,00

0,00

03.

75%

712,

500

3,75

0,00

04.

00%

1,06

6,00

06,

275,

000

1,99

1,46

38,

266,

463

4.02

820

1930

0,00

03.

00%

112,

700

1,77

5,00

03.

75%

675,

000

1,30

0,00

04.

00%

916,

000

4,60

0,00

01,

749,

638

6,34

9,63

82.

999

2020

500,

000

3.00

%10

3,70

02,

000,

000

3.75

%60

8,43

82,

000,

000

4.00

%86

4,00

04,

500,

000

1,57

6,13

86,

076,

138

2.78

520

2160

0,00

03.

25%

88,7

002,

000,

000

3.75

%53

3,43

82,

000,

000

4.00

%78

4,00

04,

600,

000

1,40

6,13

86,

006,

138

2.67

220

2265

0,00

03.

25%

69,2

002,

000,

000

3.75

%45

8,43

82,

000,

000

4.00

%70

4,00

04,

650,

000

1,23

1,63

85,

881,

638

2.54

020

2365

0,00

03.

25%

48,0

752,

000,

000

3.75

%38

3,43

82,

000,

000

4.00

%62

4,00

04,

650,

000

1,05

5,51

35,

705,

513

2.39

220

2477

0,00

03.

50%

26,9

502,

000,

000

3.75

%30

8,43

82,

000,

000

4.00

%54

4,00

04,

770,

000

879,

388

5,64

9,38

82.

299

2025

2,00

0,00

03.

75%

233,

438

2,00

0,00

04.

00%

464,

000

4,00

0,00

069

7,43

84,

697,

438

1.85

320

262,

000,

000

3.75

%15

8,43

82,

000,

000

4.00

%38

4,00

04,

000,

000

542,

438

4,54

2,43

81.

739

2027

2,22

5,00

03.

75%

83,4

382,

500,

000

4.00

%30

4,00

04,

725,

000

387,

438

5,11

2,43

81.

902

2028

2,50

0,00

04.

00%

204,

000

2,50

0,00

020

4,00

02,

704,

000

0.96

820

292,

600,

000

4.00

%10

4,00

02,

600,

000

104,

000

2,70

4,00

0-0

.018

TOTA

L$5

,480

,000

$1,1

45,2

25$6

00,0

00$1

0,93

5$0

$0$3

0,00

0,00

0$7

,198

,438

$30,

000,

000

$8,1

62,0

00$7

1,34

0,00

0$1

7,30

5,39

8$8

8,64

5,39

8

Calla

ble:

6/22

/201

18/

1/20

122/

8/20

122/

1/20

1310

/31/

2012

10/1

/201

35/

21/2

014

8/1/

2015

8/1/

2016

8/1/

2017

CARL

SBAD

MUN

ICIP

AL S

CHOO

L DI

STRI

CT$6

0 M

ILLI

ON B

OND

ELEC

TION

IN 2

014

AND

$20

MIL

LION

BON

D EL

ECTI

ONS

THER

EAFT

ER (T

AX R

ATE

= $4

.00

LEVE

L)

200

4 AP

RIL

ELEC

TION

- $7

,100

,000

$6,0

00,0

00$1

,100

,000

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 24 

 

Conclusion 

The proposed  increase  for GO Bond  funding provides  for  an 

aggressive  building  program  to  replace  aging  elementary 

school infrastructure; which in turn corrects health and safety 

issues,  replaces  portables,  responds  to  educational  program 

needs,  and  corrects  deficiencies  of  the  adequacy  standards.  

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 25 

3.3 Capital Implementation Plan 

As seen in Sections 3.1 and 3.2 of this FMP, 2014 GO Bond will 

be  utilized  to  replace  four  elementary  schools  with  new 

schools  to  address  aging  elementary  school  infrastructure; 

which  in  turn  corrects  health  and  safety  issues,  replaces 

portables,  responds  to  educational  program  needs,  and 

corrects deficiencies of the adequacy standards.  Most schools 

in the district are over 50 years old, with the oldest facility at 

90 years old.  The oldest school is Craft Elementary which will 

close  and  be  demolished  under  this  plan. All  projects  noted 

within  the  facilities  assessment  process  were  evaluated  for 

their suitability  for  the GO Bond, SB9 and HB33  funding. The 

SB9  and  HB33  projects  are  not  included  in  the  GO  Bond 

estimate.   District Operations was supplied with  the SB9 and 

HB33 projects and priorities. 

3.3.1 Implementation Plan 

The  following  implementation  plan  is  based  on  the  financial 

plan provided by RBC Capital Markets and shown in Table 3‐1.  

This  GO  Bond  cycle  will  have  two  series  of  bonds  for  $30 

million  each,  beginning  in  2014  and  2016.    RBC  considered 

future elections that are outside the FMP timeframe.   Future 

elections will generate an additional $40 million  in 2018 and 

2022. 

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 26 

Table 3‐2.  Implementation Plan Cost Detail 

Priority By Year Projects Total Budget

Budget Based On Share FUNDING SOURCE

#1

Pate Elementary School - Replacement for 600 Students: 73,800gsf (includes consolidation w/ Puckett Elementary and demolition) MACC $19,188,000 $14,391,000 District Share (75%)

$4,797,000 PSCOC (25%)Pate Elementary Soft Costs (A/E Fee’s, Contingency, NMGRT) $5,756,400 $4,317,300 District Share (75%)

$1,439,100 PSCOC (25%)Total Priority # 1 $24,944,400 $24,944,400

Total Project Funding $20,172,748.00 District GO Bond (inc offset)$6,236,100.00 PSCOC Share

Less Current 2013/14 District Offset from PSCOC Share ($1,464,448.00) Less OffsetTotal Priority Year 2014/15 $4,771,652.00 Total PSCOC Share

#2

Riverside Replacement Elementary School - 600 Students: 73,800gsf (includes consolidation w/ Puckett Elementary and demolition) MACC $19,188,000 $14,391,000 District Share (75%)

$4,797,000 PSCOC (25%)Offsite utilities / land acquisition costs 575,000.00$ 575,000.00$ District Share (100%)New Northside Elementary Soft Costs (A/E Fee’s, Contingency, NMGRT) $5,756,400 $4,317,300 District Share (75%)

$1,439,100 PSCOC (25%)Total Priority # 2 $25,519,400 $25,519,400

Total Project Funding $19,283,300.00 District GO Bond$6,236,100.00 PSCOC Share

#3Joe Stanley Smith Elementary - Replacement for 600 Students: 73,800gsf (includes consolidation and demolition) MACC $19,188,000 $14,391,000 District Share (75%)

$4,797,000 PSCOC (25%)Joe Stanley Smith Elementary Soft Costs (A/E Fee’s, Contingency, NMGRT) $5,756,400 $4,317,300 District Share (75%)

$1,439,100 PSCOC (25%)Total Priority #3 $24,944,400 $24,944,400

Total Project Funding $18,708,300.00 District GO Bond$6,236,100.00 PSCOC Share

#4Sunset Elementary - Replacement for 600 Students: 73,800gsf (includes consolidation and demolition) MACC $19,188,000 $14,391,000 District Share (75%)

$4,797,000 PSCOC (25%)Sunset Elementary Soft Costs (A/E Fee’s, Contingency, NMGRT) $5,756,400 $4,317,300 District Share (75%)

$1,439,100 PSCOC (25%)Total Priority #4 $24,944,400 $24,944,400

$18,708,300.00 District GO Bond$6,236,100.00 PSCOC Share

$76,872,648.00 District GO Bond$100,352,600.00 $23,479,952.00 PSCOC Share

Priority Year 2015/16

Priority Year 2014/15

Priority Year 2014/15

Priority Year 2015/16

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 27 

Table 3.3 Implementation Plan Priorities 

 

Tota

l MA

CC

Sof

t C

osts

Tota

l Pro

ject

C

osts

PS

CO

C25

%D

istr

ict

75%

Dis

tric

t10

0%To

tal P

roje

ct

Cos

tsTo

tal D

istr

ict

Pro

ject

Cos

tFu

ndin

g S

ourc

e

2014

/15

- #1

Pat

e E

lem

enta

ryR

epla

cem

ent S

choo

l$1

9,18

8,00

0$5

,756

,400

$24,

944,

400

$6,2

36,1

00$1

8,70

8,30

0$2

4,94

4,40

0$1

8,70

8,30

0P

SC

OC

/ GO

Bon

d

Pat

e E

lem

enta

ry(D

istri

ct O

ffset

App

lied)

-$1,

464,

448

$1,4

64,4

48$0

$1,4

64,4

48G

O B

ond

#2R

iver

side

Ele

men

tary

New

Sch

ool

$19,

188,

000

$5,7

56,4

00$2

4,94

4,40

0$6

,236

,100

$18,

708,

300

$24,

944,

400

$18,

708,

300

PS

CO

C/ G

O B

ond

Riv

ersi

de E

lem

enta

ryO

ff-si

te U

tiliti

es/ L

and

Acq

uisi

tion

Cos

ts$5

75,0

00$5

75,0

00$5

75,0

00$5

75,0

00$5

75,0

00G

O B

ond

$0$0

$0

$38,

951,

000

$11,

512,

800

$50,

463,

800

$11,

007,

752

$37,

416,

600

$2,0

39,4

48$5

0,46

3,80

0$3

9,45

6,04

8

2015

-16

#3Jo

e S

tanl

ey S

mith

E

lem

enta

ryR

epla

cem

ent S

choo

l$1

9,18

8,00

0$5

,756

,400

$24,

944,

400

$6,2

36,1

00$1

8,70

8,30

0$2

4,94

4,40

0$1

8,70

8,30

0P

SC

OC

/ GO

Bon

d

#4S

unse

t Ele

men

tary

Rep

lace

men

t Sch

ool

$19,

188,

000

$5,7

56,4

00$2

4,94

4,40

0$6

,236

,100

$18,

708,

300

$24,

944,

400

$18,

708,

300

PS

CO

C/ G

O B

ond

$38,

376,

000

$11,

512,

800

$49,

888,

800

$12,

472,

200

$37,

416,

600

$0$4

9,88

8,80

0$3

7,41

6,60

0

$77,

327,

000

$23,

025,

600

$100

,352

,600

$23,

479,

952

$74,

833,

200

$2,0

39,4

48$1

00,3

52,6

00$7

6,87

2,64

8

Tota

l 201

4/15

Pri

oriti

es

Tota

l 201

5/16

Pri

oriti

es

TOTA

L P

RO

JEC

T C

OS

TS

Car

lsba

d M

unic

ipal

Sch

ools

- 2

014

- 20

19

Pri

ority

By

Year

Dis

tric

t S

choo

lP

roje

ct D

escr

iptio

n

Impr

ovem

ent

Cos

tsFu

ndin

g

Facilities Master Plan 2014 ‐ 2019      Carlsbad Municipal School District 

         3.0 Capital Improvement Plan    Carlsbad, New Mexico 

Section 3 | 28 

The implementation plan identifies Carlsbad Municipal School 

District PSFA FAD ranking, school project priorities, projected 

costs,  the  funding  source,  and  expected  years  of 

implementation.  Table 3‐2 shows the Implementation Plan. 

 

3.3.2 FAD Priorities vs. Plan 

The primary variance between the FAD and this plan is placing 

Riverside Elementary before two other higher ranked schools.  

The rationale is the desire to replace Riverside Elementary and 

increase  its  capacity  as  soon  as  possible.    Riverside  is  in  a 

higher  growth  area  than  the other  two  schools  and  concern 

about not meeting this grow potential was the reason behind 

this decision.  The rankings and priorities, again are: 

Pate Elementary ranked number 32; 

Riverside Elementary ranked number 45; 

Sunset Elementary ranked number 31; and 

Joe Stanley Smith ranked number 33. 

 

3.3.3 State Funding Assistance 

CMSD anticipates  that State Funding will be part of  the next 

FMP cycle.   As shown  in the  Implementation Plan, Tables 3.2 

and 3.3, page 3|26 and 3|27, State Funding will account  for 

25% of the project costs.         An application  for State Funding 

assistance will be submitted in 2014. 

 

3.3.4 Board Acceptance 

A  summary  presentation  of  the  FMP  was  presented  to  the 

Board in first a working session and finally in a public meeting.  

The Board approved the course of the Master Plan on April 22, 

2014.