Caribbean Construction Planning v6

16
Caribbean Construction Planning Guide to building your own home Written By: Damar Hutchinson, Architectural Designer Architectural Plans Online www.ArchPlansOnline.com [email protected]

description

g

Transcript of Caribbean Construction Planning v6

  • Caribbean

    Construction

    Planning Guide to building your own home

    Written By:

    Damar Hutchinson, Architectural Designer

    Architectural Plans Online

    www.ArchPlansOnline.com

    [email protected]

  • Page | 2

    Table of Contents

    Basic Concepts of Construction Planning .............................................................. 3

    Things to Consider when Planning ..................................................................... 3

    Building Plans ...................................................................................................... 5

    Planning Permit ................................................................................................. 7

    Construction Drawings ...................................................................................... 8

    Choosing a Contractor/Builder ........................................................................... 14

  • Page | 3

    Construction Planning

    Basic Concepts of Construction Planning

    Construction planning is a fundamental and challenging activity in the management and execution of all

    construction projects. It involves the choice of technology, the definition of work tasks, estimation of the

    required resources, duration for individual tasks and the identification of any interactions among the different

    work tasks.

    A good Construction Plan is the basis for developing your budget and the

    schedule for work. This Construction plan will give you an idea of the work

    required for your project and can be used when consulting with your local

    mortgage institution.

    Things to Consider when Planning

    Budget Knowing your borrowing limit will generally help you to stay

    within budget. During construction other unforeseen events may occur

    which may affects your budget. I generally encourage persons to have at

    least 30% of the cost of the project in their personal savings before starting

    construction.

    Land - You should ensure the land you are planning to buy or already own

    is fit for a residential building whether single or multi family, according to

    local zoning codes. Mountainous lots may require cut and fill civil

    engineering work which may be costly. Consult a local Civil Engineer.

  • Page | 4

    Building Plans - Getting your proposed building layout on paper, this is the basis of your construction

    project. These drawings are generally prepared by an Architect or

    Draftsman. These drawings are very detailed and contain technical

    information required to construct your home.

    Planning Permission - This is the stage where you

    actually apply for permission to start construction. This

    process may take a few weeks base on your local

    practice. During the approval process you should start

    to interview trusted building contractors; doing this

    upon approval would put you in a better position to

    commence construction.

    Building Contractor (Costing) - This task can be done while you are

    waiting for approval from your local authority. This is the stage when

    you receive bids from various trusted contractors base on your initial

    interview and screening process.

    Please note that sometime contractors that bid with the low unrealistic

    estimate often cut corners and deliver product of low quality.

  • Page | 5

    Begin Construction - Up on approval of your building plans you should seek to sign an agreement with

    the selected contactors, we recommend getting an attorney to review the agreement before moving

    forward.

    Finish Construction At this stage you should ensure that your house was properly built and that the

    work carried out is up to the local standards, these standards are generally in placed for your safety.

    Building Plans/Drawings (explained)

    Building plans/ Drawings can be described as a graphical representation and specific guidelines illustrating

    how the building should be constructed and what the building should look like after construction.

    Before Construction After Construction

    Image Source www.constructivemedia.com.au/2013/05/before-and-after

  • Page | 6

    A full set of building plans consist of various specifications, annotations and visual illustrations if the proposed

    building. Building plans are also used when applying for construction permit from your local government

    building office.

    The creation of a set of building plans starts when an idea and then further developed into detailed

    Construction Drawings, These drawings may take up to 12months to be prepared by an Architect base on

    design complexity. The cost for building plans typically ranges from 8-15% of the total cost of the construction

    cost. Lets break it down; if you are planning to build a house and the total cost to build the house would be

    $1,200,000 in total, the Architect fee would be 8-15% of that figure which would be about $96,000 - $180,000.

    These rates are flexible and are based on the cost of construction.

    Detailed Set of Construction Drawings includes Site, Location plan, Floor Plans, Elevations, Sections, Electrical

    Plan, Plumbing/Drainage Plan, Structural Details, Foundation Plan and Other details where necessary.

    North Elevation of HD001

    archplansonline.com

  • Page | 7

    Planning Permit

    Most Islands within the Caribbean region has implemented and adopt various Building Codes which govern

    the quality, usage and location of the building you plan to build. These codes are implemented as a way to

    ensure good construction practices and safe homes.

    Under the Building Act in most countries, permission is required for any of the following:

    1. Construction/Erection of building 2. Demolition of building

    3. Additions /alterations and external repairs 4. Temporary building & Farm House

    5. Change in use of building from one use (Class to another e.g. Residential to Commercial)

    An application of such nature could take approximately four (4) weeks (for residential single family buildings),

    while all other application will take approximately 90 working days. The application waiting period solely base

    on how efficient your local government building department conduct their duties. (If you are not sure that you

    require a permit contact your Local Planning Authority).

  • Page | 8

    Await approval from your Local Planning Authority before commencing any work!!!

    You should consider visiting your local building department to seek more information.

    Barbados http://www.townplanning.gov.bb/

    Trinidad http://trinidad.co.gov/

    Jamaica http://www.ksac.gov.jm/

    St. Vincent & G http://www.housing.gov.vc

    Belize - http://www.cbabelize.org/

    (These website may varies base on your geographic location)

    Other useful websites are

    http://www.doingbusiness.org/data/exploreeconomies/grenada/dealing-with-construction-permits

    Construction Drawings

    Construction Drawings: must be drawn to a minimum scale of 1:100 (1:75 for complex drawings, where a

    building is too large to fit on a 24x 36paper). All legends & drawings are required to be visible and accurately

    labelled. (Generally Applicable in Jamaica, Trinidad & Barbados and other islands)

  • Page | 9

    Floor Plan- The entire floor layout including existing as well as proposed floor plans (use of rooms, doorways,

    windows, openings etc.)

    Foundation Plan -shows all structural members including stiffeners, column pad footings etc.

  • Page | 10

    *Location & Site Plan These drawings are produced to indicate where the building would position on the

    land and the setbacks based on values stipulated for the area you choose to build.

    Roof plan-shows all structural members (sizes, spacing, types, roof pitch, drainage etc.)

  • Page | 11

    Electrical Plan - Layout of all electrical components; electrical outlets, lighting fixtures etc.

    Sections-a minimum of 2 (1 longitudinal & 1 cross-sectional) sections through a critical part of the building

    depicting interior details and showing ground and finish floor levels

  • Page | 12

    Elevations-label all exterior finishes (Walls, roof material), highlighting ground levels both existing and final

    (All elevation details for new development, alterations or extensions).

    Structural Details - Include details of all structural components; foundations, columns, beams, footing, lintel,

    stiffeners, staircase plan (reinforce and section), roof vent detail, etc.

  • Page | 13

    *Drainage Details - must include grease trap, trap gully basin, septic tank, absorption pit, tile field, manhole

    etc.

    *Drainage Plan - The existing and proposed storm water drainage and Plumbing layout. Position of existing

    and proposed features such as sanitary drains, septic tanks, absorption pit, soak away pit, tile field,

    surface/storm water collection, containment and final disposal point etc.

  • Page | 14

    Choosing a Contractor/Builder

    CHOOSE YOUR CONTRACTOR/BUILDER CAREFULLY

    Most construction projects undertaken in the Caribbean; whether a highway or a house extension requires a

    professional. Selecting and dealing with a contractor is not always the easiest of tasks. There are numerous

    clients who are eager to share horror stories about their experiences with contractors - from financial rip-offs

    to piles of unfinished and sub-standard work.

    The main purpose of this article is to guide those persons with smaller jobs (simple house construction) in

    selecting and dealing with contractors.

    When looking for a contractor, the writer recommends one of the following:

    1. Builders Association in your country, you could seek advice and recommendation.

    2. Institution of Professional Engineers can also recommend suitable contractors.

    3. Check someone who has done a similar project to yours.

    The main drawback of committing to a contractor in the act of no-turning back, that is why the section process

    is so important.

    Using one or a combination of the above, select three (3) possible contractors for the job;

    Ask them for their credentials, and make sure they are qualified. That may sound like common sense, but

    most people take for granted that any contractor can do any job, but this is not necessarily the case.

    Each time I am told by owners of their grief with construction projects, I have always enquired of them how

    much they pay their doctor or lawyer and how they go about selecting them.

  • Page | 15

    Typical answer would be "US$500 - US$1,000" (depending on the assignment undertaken) you would not go

    hire a real estate lawyer to represent you for a criminal matter, you should get where I am going, same you

    could not go to a dermatologist doctor if you have just feeling pain in your head. This is the same approach as

    in relates to contractors, check their area of specialisation and get references from your friends. You will be

    pleased with this common sense approach, why not take the same approach for the largest investment in your

    life - YOUR HOUSE?

    So the contractors have now been selected, what next? Set up appointments and get bids on the project, try

    to meet with bidders individually, and allowing sufficient time for them to be fully appraised. Note an estimate

    is not a bid. An estimate is an approximate cost. It can cost you thousands/hundreds of dollars more when the

    project is completed. Ask the three (3) contractors for references relating to their work on a project similar to

    yours.

    Get three (3) references for each and talk to those customers. If possible, visit the locations to see the

    projects. Once you have chosen the contractors, make sure they provide signed itemised bids, including all

    taxes, permits etc. If you have to change the scope of the work to be undertaken, make sure it is agreed and

    signed-off by both parties before starting.

    After all the work is completed, hold on to the final payment, this should be explained in your contract

    documents signed by both parties. This is essential to ensure the job is 100% complete. For some jobs, for

    example roofing, it is necessary to hold back part of the payment, (called retention) five to ten percent, for up

    to six (6) months to allow for defects to show.

    The above warning comes in light of the many times that contractors receive all their money and do not return

    to finish the project or to correct defects. When this happens, both the owner and the contractors will be in

    dispute.

  • Page | 16

    The owner displaying extreme annoyance and the contractor putting up a stone wall, as there is no interest in

    satisfying the owner, since he would have already been fully paid.

    Like all other business transactions, knowing a little about the contractor's personality may also help. Like so

    many Caribbean business people, some contractors lack financial management and support.

    Like I have said to so many persons and organisations; having a hammer, a saw or even owning a

    construction company, does not make one into a good contractor.

    A good contractor is a trained professional who is able to properly plan and implement projects in a timely

    manner and at reasonable cost.

    Powered by Hutchinsons Designs

    If you have any questions regarding your residential project, contact us. We are ready and willing to help.

    www.ArchPlansOnline.com

    [email protected]

    Call us: 1 876-428-5388

    If you found this manual useful, share it with your family and friends on Facebook.